Canoe Creek Penstock and the Use of Pipe Couplers

John EbellProject Manager

Barkley Project Group

Page 2: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.
Page 3: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.
Page 4: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.
Page 5: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

1850 m of 36” coupled penstock

Page 6: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Off-site preparation

Page 7: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Rolled grove couplers 0 – 300 psi

(103 used)

Welded ring couplers 0 – 600 psi

(51 Used)

Page 8: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Used Gas Pipeline

Page 9: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.
Page 10: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Completion of 3 – 5 joints per day

Page 11: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Pipe installation within the narrow road / pipe allowance

Page 12: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Minimize construction footprint

Page 13: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Backfilled with crushed 3” minus

Page 14: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Finished Access Road

Page 15: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Assembly time 10 – 20 minutes

Page 16: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Increased opportunity for local work force

Minimizes specialized trades

Page 17: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.
Page 18: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Rapid pipe assembly on adverse sites

Page 19: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Avoids confined-space entry

Page 20: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

Alignment tabs

Page 21: Canoe Creek Penstock and the Use of Pipe Couplers John Ebell Project Manager Barkley Project Group.

John Ebell

Barkley Project Group

250 390 2627

Scott McDonald

Victaulic Canada