Campbell River Quarterly Public Meeting
September 18, 2014
• Laichwiltach Territory
o We Wai Kai Nation
o Wei Wai Kum First Nation
Acknowledgment of Traditional Lands
2
Approvals
• Treasury Board
• Cabinet
Project Agreement
• Commercial Close
• Financial Close
Construction Underway
• Groundbreaking
• Site Administration
• Excavation
• Concrete
• Steel
Since May 29, 2014
3
• Location: Next to existing hospital (375 - 2nd Avenue)
o 32,316 m2
o 95 beds
o $274.5 million`
o Comox Strathcona Regional Hospital District 40%
Campbell River Hospital
4
Webcam 10:15 a.m. September 18, 2014
4
• Location: 101 Lerwick Road, Courtenay
o 39,826 m2
o 153 beds
o $331.7 million
o Comox Strathcona Regional Hospital District 40%
5
Comox Valley Hospital
Webcam 11:52 a.m. September 16, 2014
5
Project Coordinator
Campbell River Site
(EA to CPO)
Monique Hebert
Chief Project Officer
Tom Sparrow
Technical Team
Lead: Kerry Beauchamp
Equipment Lead: Catherine Brooks
Clinical Team Lead: Norma Jones
IMIT Team Lead: Steve Carter
Smart Technologies
Team Lead: David Leadbetter
Financial Team Lead: Bill Boomer
Communication Team
Sr Project Coordinator
Comox Valley Hospital
Jennifer Singer
6
Island Health Project Team
7
Tandem Health Partners
7
Working Group Structure
COVER
8
9
Business
Case &
Design
Concept
Construction
Issue
RFQ
Issue RFP
Negotiate
Maintenance
3 years
5 months
to 2 years
Design
Concept
Plan
Contract Term
30 years
2 to 4
months We are here
10
Progress – Design & Construction Phase
Design
• Detail Design Review
• Clinical User Consultation
• Mockup Spaces
• Guidance
• Aboriginal Working Group
• Public Advisory Committee
Construction
• Excavation - Underway
• Foundation Work – Underway
Where we are going
11
Campbell River – Level 0
12
Campbell River – Level 1
13
Campbell River – Level 2
14
Campbell River – Level 3
15
Mockups
Sink
Paper Towel
Sharps
Soap
16
Mockup – Operating Room
17
Community Engagement & Consultation
Quarterly Public Meetings
Newsletters
Website
Webcams
Public Patient
Advisory Committee
(in recruitment)
Art Committee
(Terms of Reference in development)
Aboriginal Working Group
School Advisory
Committee
18
Public-Patient Advisory Committee
Expression of Interest – September 16
First Intake - Interviews – mid October
First Committee Meeting - end October
19
Education and Training
• Inter-agency Discussions – March 13, 2014
• North Island Employment Foundations Society, North Vancouver Island Aboriginal Training Society, Industry Training Authority, North Island College, SD72, SD71, Vancouver Island Construction Association, Island Health
Industry Training Authority
• Dialogue on Trades/Apprenticeships Opportunities – September 9, 2014
Community Benefits - Opportunities
20
Business and Industry
• Chambers of Commerce – Industry Speed Dating Sessions
• Campbell River: May 27, 2013 (Workshop: May 16)
• Comox Valley: May 28, 2013 (Workshop: May 16)
• Follow up Sessions (Planning in Progress)
Tender / Bid Opportunities
• Prequalification
• Work Packages
Community Benefits - Opportunities
21
Work Packages and Awards
22
Work Packages and Awards
23
Community Benefits - Today
24
25
Construction Fencing Parking Lot Closure Birch Street Closure Heliport Closure Implement Alternate Ambulance Access/Egress Route Access Roads Establish Site Administration Commence Bulk Excavation Commence Foundation / Concrete
Campbell River Construction – August, September
Campbell River - Excavation
26
27
Install Site Trailers – In Progress Continue Bulk Excavation Continue Foundation / Concrete Erect Cranes – end of September Commence Level 1 Suspended Slab
Campbell River Construction – October, November
Campbell River - Construction
28
Design and Construction of New Facilities
July 2014 – April 2017
Service Commencement – Project Completion April 30, 2017
Commissioning and Transition Period
Summer – Fall 2017
Move-In
Late Fall 2017
29
Project Schedule
What we have been hearing
• Traffic Safety
o Non-compliant street parking
o Big truck traffic
o Congestion
o Speed
• Construction Noise
o Project Agreement
o City of Campbell River Nuisance Bylaw
30
What we have been hearing
• Dust Control
o Preventive Measures
31 31
• Temporary Lots west of Yucalta Lodge (144 stalls)
• Parking Shuttle - Transit to/from temporary lots
o Weekday mornings
o Expansion of Service in October to early afternoon
Hospital Parking Shuttle
Parking
32
For more information and updates, visit our website:
http://nihp.viha.ca/
North Island Hospitals Project Website
33
Thank You!!