Camp Lemonnier Requirements
RDML Dave Boone June 2012
Unclassified
Unclassified – Pre-Decisional Information
Camp Lemonnier Requirements
• You asked: How do we control COCOM Appetite? • AFRICOM, SOCOM, TRANSCOM, CENTCOM, EUCOM
• Approach:
• Operational Requirements • NCC review of COCOM requirements
• Infrastructure • Integrated requirements • Austere infrastructure process
• Fiscal Controls • DODI and FMR host-tenant guidance
2
Unclassified
Unclassified – Pre-Decisional Information
Austere Infrastructure Process Overview
Identify Site Assumptions and Sources
Assess Austere Site Standards and Criteria
Conduct Site Infrastructure TOC Analysis
Determine Policy Changes and Impacts
3
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Unaccompanied Housing
Identify Site Assumptions and Sources
Assess Austere Site Standards
and Criteria
Conduct Site Infrastructure TOC Analysis
Determine Policy Changes
and Impacts
• Enduring
• FOS
• 25+ year duration
• Projected manning
• Land use provided
• Baseline in FY13
• Prior investment in CLU and 2 BQ(2+0)
• Energy efficient retrofit of existing CLU
• OCONUS MILCON constrained
• Semi-Permanent • 10-25 year life • Perm party <12 mo • CLU
• Permanent
• 50 year life • Perm Party ~12 mo • CMU Construction
• Other changes
• Increased density • Gang heads • Minimal finishes • Minimal HVAC
• COA/TOC Analysis (Next Slide) recommends:
• Austere CMU • 35% lower first cost • Similar ST/Energy
cost • Retrofit older
existing CLUs
• Waiver/Policy changes • UFC • AT/FP • Assignment std • Construction std • LEED
CLUs
Austere CMU
4
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Housing Alternatives/COAs
• COAs • COA 1: All Permanent AUH (Alt 1 or 2); FY12 BQ is (2+0) • COA 2: All Semi-Permanent CLU (Alt 3/4) • COA 3: Hybrid: Permanent AUH (Alt 2) for ~12 mo/ Semi-Permanent CLUs (Alt 3/4) for <12 mo
• CNO Decision Points • Permanent Const Standard: 2+0 or 4+Gang Head configuration • Assignment Policy: All Steady State personnel in Perm Bks or only 12 mo in Perm Bks
• Recommendation – COA 3 • Future BQ’s would be 4 person+Gang Head, result is mix of BQs (FY12 BQ is 2+0) • Requires Policy waiver for assignment and construction criteria • CNIC concurs with COA 3
Construction Type
Criteria First Cost
Sustainment 25 yrs
Energy 25 yrs
TOC 25 yrs
Alt 1 Permanent Austere (2+0) Concrete (175 sf/person) 125 room (250 bed) – 57,060 SF No kitchen, no closet, austere finishes, no elevator
$25.2M $4.8M $4.2M $34.2M
Alt 2 Permanent Austere 4 person/room - Concrete (72 sf/person) 62 room (~250 bed) – 43,900 SF No kitchen, no closet, gang latrine/bath, austere finishes, no elevator
$16.6M $3.9M $4.0M $24.5M
Alt 3 Semi-Permanent
New CLUs - 4 person dry CLU (80 sf/person) (Energy Efficient) . P-944 (FY12 OCO) 62 berthing CLU's - (~ 250 bed) – 3 gang latrine/baths
$4.5M $5.3M $8.0M $17.8M
Alt 4 Semi-Permanent
Existing CLUs - 4 person dry CLU (80 sf/person) (upgraded to Energy Efficient) 62 berthing CLU's - (~ 250 bed) – 3 gang latrine/baths
$800K $5.3M $8.0M $14.1M
5
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Master Plan
• Annual submittal to Congress
• Addresses COCOM requirement and desired phasing plan • Assumes: Enduring FOS with a minimum presence of 25 years • Effective way to manage/constrain CCDR demands through deliberative process • Supports most-critical missions • Eliminates redundant facilities • $1.3B in requirements over 25 years
• AFRICOM’s CLDJ Requirements Document (RD) is Master Plan source document: • 43 Steady State Aircraft, 12 Surge • Force assignments will continue to be rotational deployed (12 months or less) • Projected Steady State base loading for berthing ~2,400 PN
• Up to 2,100 all DoD GS and MIL personnel • 300 Task Force (TF)
• Projected Surge for berthing up to 1,500 PN plus 800 TF
6
Unclassified
Unclassified – Pre-Decisional Information
NOV DEC JAN FEB MAR APR MAY JUNE JULY AUGUST▀ Stakeholder Requirements Meeting: Stuttgart, 1 – 3 November 2011 ▀ CLDJ Site Visit: 28 November - 7 December 2011
▀ Visioning Workshop: Stuttgart, 14-15 December 2011 ▀ Draft Concept Brief to NAVFAC: 13 January 2012 ▀ Final Concept Brief to AFRICOM: 27 January 2012
▀ New - Table of Contents and draft BFRs ▀ Pre-Draft Master Plan: 17 February 2012
▀ Pre-Draft reviewed by installation: 23 Feb - 16 Mar 2012 ▀ Follow up site visit: 28Feb-3Mar2012
▀ Over-shoulder reviews with PW: 20/22 Mar 2012 ▀ Draft Final Master Plan: 30 March 2012
▀ NAVAF N3/N5 Brief: 29 May 2012 ▀ NAVAF DCOM Brief: 30 May 2012
▀ AFRICOM JLCB/P-DASN (E,I&E) Brief: 7 Jun 2012 ▀ Region Concurrence: 8 Jun 2012 ▀ OPNAV N46 Brief: 12 Jun 2012 ▀ CNIC Brief: Week of 18 Jun 2012
Deliver MP and Draft RTC 1 AUGDeliver RTC to ASN(EIE) 22 Aug□ CNO Brief TBD Aug 2012□ ASN Brief: TBD Aug 2012□Congress Brief: TBD Aug 2012
Final Master Plan Delivered August 2012
▀ Complete□ DueRevised 19Jun2012
2011 2012
▀ Updated plan based on new loading numbers: 19 Mar 2012 New Personnel and Aircraft Loading from AFRICOM 24Feb12
CLDJ Master Plan and Briefing Schedule
• Master Plan is on schedule for August delivery to Congressional Staffs • Delivery Schedule set by CNIC Tasker to CNREURAFSWA. Anticipates DNS Tasker 8 Aug. • Review of Report to Congress accompanying Master Plan through taskers
Today
7
Unclassified
Unclassified – Pre-Decisional Information
Master Plan Requirements and (ROM) Costs
ROM: $1.32B $265M Barracks** $219M Task Force Compound* $248M Air OPS Facilities* $142M +TBD Power Utilities/Roads/Comms $152M MWR/Galley/NEX/Chapel** $ 24M Warehousing $ 97M HQ/ADMIN $ 62M Security/Fire/Armory** $ 48M Medical $ 21M Boat/Vehicle Maintenance $ 14M Training $ 15M EOD* $ 16M Construction Battalion * Operations ** Community
Category Projects (SF) Shortfall Delta after
Project
Operations 554,263 -662,938 -108,675
Maintenance 168,964 -175,001 -6,037
Laboratory 0 -1,472 -1,472
Storage 134,359 -167,449 -33,090
Medical 43,552 -43,552 0
HQ/Admin 127,117 -138,338 -11,221
Community 573,645 -573,645 0
Totals 1,601,900 -1,762,395 -160,495
Category Retained Assets
(SF) Requirements
(SF) Balance (SF) Operations 44,082 707,020 -662,938
Maintenance 17,803 192,804 -175,001
Laboratory 0 1,472 -1,472
Storage 22,800 190,249 -167,449
Medical 2,383 45,935 -43,552
Headquarters 0 138,338 -138,338
Community 50,171 623,816 -573,645
8
• Integration process used to assess and combine requirements. • Significant reduction of AFRICOM requirements during the Master Plan review process
(COCOM self-limiting infrastructure requirements) • Reduced # of Aircraft from 65 to 43 • Decreased PN from 5475 to 4200 • Reduction of Mission and Support infrastructure from reduced requirements.
• ROM reduction of 35% ($2B$1.3B) due to integration and reduction of requirements
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Master Plan Future Land Use
9
Unaccompanied Housing
Installation Boundary
Airfield Administration
Community Service
Maintenance
Open Space
Operational
Recreational
Storage
Unaccompanied Housing
Utility
Unclassified
Unclassified – Pre-Decisional Information
Camp Lemonnier Next Steps
• Apply austere infrastructure process to all requirements
• Institute ISSAs to execute host-tenant agreements in FY13
• Develop POM14 Summer Review Strategy and POM 15 investment recommendation
• Identify MPN IA/GSA to PCS conversion trigger points and requirements
• 2013 master plan update—kickoff Oct 2012
10
Unclassified
Unclassified – Pre-Decisional Information
Backup
11
Unclassified
Unclassified – Pre-Decisional Information
• OMN transferred to baseline in POM14, but bodies did not. • Permanent manning requires approval of State Department • Three requests in the Joint Manpower Validation Process for CLDJ:
• JMD currently shows 450+. Request to make permanent 315 of which approx 95 would be Navy.
• Office of Security Cooperation and Cape Verde requests 15 billets - of which only 1 is Navy (Officer)
• Reserve - plus up J2 by 50 billets - service equities unknown
12
IA/GSA to MPN transition
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Austere Infrastructure Policy Impacts
• Housing
Potential Waivers DoD 4165.63-M Bath criteria (# of people sharing) OSD
Potential New Policy Troop Housing Assignment and construction standards SECNAV
Potential Policy Changes OPNAVINST 5009.1 Assignment and construction standards ASN
UFC 04-721-10 Construction criteria (code changes) Tri-Service Board
NAVMED P5010-2 Preventative medicine criteria (72 sf) BUMED
13
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Housing Analysis (ROM)
-- Key Consideration Points 14
Unclassified
Unclassified – Pre-Decisional Information
• NCC review of COCOM requirements • Awaiting results of NAVAF visit to AFRICOM to validate
operational requirements
15
Operational Requirements
Unclassified
Unclassified – Pre-Decisional Information
• Suggested OPNAV Interpretation of Financial Guidance: • Rely primarily on the FMR as the authoritative source.
• Single-use, Department-unique, Service-common are all analogous: These facilities should be funded by DoD Component requiring the facility.
• Joint-use Facilities : Funded by DoD Component with jurisdiction over the host.
• Common-Purpose Facilities: Funded by the executive agent.
• ISSAs to execute host-tenant agreements.
16
Fiscal Controls
Unclassified
Unclassified – Pre-Decisional Information
Austere Infrastructure Process Overview
Identify Site Assumptions and Sources
Assess Austere Site
Standards and Criteria
Conduct Site Infrastructure TOC Analysis
Determine Policy Changes
and Impacts
• Enduring or Contingency
• MOB, FOB, CSL
• Mission Duration
• Projected manning
• Land use/ availability • OCONUS climate
• Standards and criteria • Construction
• Temporary • Semi-Perm • Permanent
• Planning • Performance
• Policy
• Criteria • Waivers
• Other factors
• QOL • Previous invest • Risks (AT/FP, $)
• Mission time frame
• Previous investment
• Evaluate TOC • Const type • ST/Energy cost • Recap cost
• QOL impact
• Waivers needed • Policy changes
• Construction stds • AT/FP • Assignment std • Construction std
17
Unclassified
Unclassified – Pre-Decisional Information
Alt 1 Permanent AUH
Permanent Austere (2+0) 175 sf/person
• Concrete • Austere finishes • No kitchen • No closet • No elevator
18
Unclassified
Unclassified – Pre-Decisional Information
Alt 2 Permanent AUH
Permanent Austere, 4 Person per Room 72 sf/person
• Concrete • Austere finishes • No kitchen • No closet • Gang latrines • No elevator
19
Unclassified
Unclassified – Pre-Decisional Information
Alt 3 and 4 Semi-Permanent AUH
Semi-Permanent 4 Person Dry CLU 80 sf/person • Gang latrines • Energy efficient
20
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Master Plan Lay Down
Second ECP for Commercial Vehicles/Trucks
Permanent Barracks moved away from airfield
Triple-stacked CLUs retained for Surge
Weapons area relocates arcs
• Executable over time • Room for all steady state requirements plus surge • Flexible to future changes in mission/horizon
Room for Apron Expansion to meet aircraft parking safety standards
RPAs remain in Sprung Shelters
Task Force Compound
21
Unclassified
Unclassified – Pre-Decisional Information
• DODI and FMR host-tenant guidance • VC CJCS Memo: Global Defense Posture Infrastructure Responsibilities
• DoN assigned Lead Agent for Camp Lemonnier. • Department-unique facility: Facility used exclusively by single Military Depart;
analogous to Service-common in DODD 5100.03 • FMR Vol 2B, Chapter 6 060301 Para 8: Facilities Programming and Financing at DoD
Installations Utilized by Two or More DoD Components • Single-use Facilities : Funded by DoD Component requiring the facility • Joint-use Facilities : Funded by DoD Component with jurisdiction over the host • Common-Purpose Facilities: Funded by the executive agent.
• DoDI 4165.70 Real Property Management • 3.2. Predominant User. The DoD Component whose activities comprise the
predominant use of an installation, as measured by expenditures for operations, relative number of personnel, using the largest quantity or unit of measured space, and other mission-related metrics.
• 6.12.1. The predominant user will normally be designated as the host at joint-use installations.
22
Fiscal Controls
Unclassified
Unclassified – Pre-Decisional Information
• DODI and FMR host-tenant guidance • DoDD 5100.3 Support of the HQ of Combatant and Subordinate Unified Commands
• Commander, USSOCOM, shall program and budget for the special operations-peculiar support of …other joint special operations commands established within the Combatant Commands for which funds have been transferred from the Military Departments to Major Force Program 11.
• Service-common. Equipment, material, supplies, and services adopted by a Military Service for use by its own forces and activities. These include standard military items, base operating support, and the supplies and services provided by a Military Service to support and sustain its own forces, including those assigned to the Combatant Commands. Items and services defined as Service-common by one Military Service are not necessarily Service-common for all other Military Services. See also special operations-peculiar.
• Special operations-peculiar. Equipment, material, supplies, and services required for special operations missions for which there is no Service-common requirement. These are limited to items and services initially designed for, or used by, special operations forces until adopted for Service-common use by one or more Military Service; modifications approved by the Commander, USSOCOM, for application to standard items and services used by the Military Services; and items and services approved by the Commander, USSOCOM, as critically urgent for the immediate accomplishment of a special operations mission. See also Service-common.
23
Fiscal Controls
Unclassified
Unclassified – Pre-Decisional Information
CLDJ Master Plan Future Land Use