Unit 20: Business for Engineering LO2: Understand strategies and techniques used to improve engineering businesses Using project monitoring tools – GANTT Charts Learner activity sheet Activity 1 The ability to plan and monitor activity is essential in business. This activity asks you to consider an engineering project and apply the principles of project planning to the task. Version 1

Transcript of Cambridge Technicals in Engineering Unit 20: … · Web viewUsing project monitoring tools –...

Page 1: Cambridge Technicals in Engineering Unit 20: … · Web viewUsing project monitoring tools – GANTT Charts Learner activity sheet Activity 1 The ability to plan and monitor activity

Unit 20: Business for Engineering

LO2: Understand strategies and techniques used to improve engineering businesses

Using project monitoring tools – GANTT Charts

Learner activity sheet

Activity 1The ability to plan and monitor activity is essential in business. This activity asks you to consider an

engineering project and apply the principles of project planning to the task.

Version 1

Page 2: Cambridge Technicals in Engineering Unit 20: … · Web viewUsing project monitoring tools – GANTT Charts Learner activity sheet Activity 1 The ability to plan and monitor activity

OCR Tooling is a manufacturer of a range of tools and equipment working Monday to Friday.

Research has identified that there is a market for a specialist screw wrench. To manufacture the screw

wrench, OCR Tooling will need to source and install new equipment in the factory and will require three

extra staff to operate the equipment.

Your task is to plan out the different stages of the project and use a GANTT chart to produce a project

plan. Approval to proceed will be required at various points.

You have been provided with the list of 18 activities and how long each activity should take. You can

assume that the timings are accurate for the purpose of the task.

Task LengthDevelop proposal 1 weekPresent proposal for approval 1 daySelection of staff to operate 1 weekTraining of staff 2 weeksTrial production run 2 weeksDevelop marketing materials 1 weekSign off marketing materials 1 dayMarketing campaign 3 weeksAnalysis of trial production 1 dayProject Approval MilestoneSelection of equipment 1 weekInstallation and commissioning of equipment 2 weeksApproval to proceed to limited production MilestoneLimited production for sales 1 weekCollection of initial customer feedback 2 weeksEvaluation of initial customer feedback 1 dayScale up production 1 weekApproval of scale up based on initial customer feedback Milestone

Order the activities and transfer them to the following table and complete the last column.

Once the table is complete, use the information to create the GANTT chart.

Assuming the timings are correct, what is your estimate of the shortest length of time it will take before

OCR Tooling is in full production of the screw wrench?

Version 1

Page 3: Cambridge Technicals in Engineering Unit 20: … · Web viewUsing project monitoring tools – GANTT Charts Learner activity sheet Activity 1 The ability to plan and monitor activity

Task ID

Task Length Must follow Task ID

A

B

C

D

E

F

G

H

I

J

K

L

M

N

O

P

Q

Version 1

Page 4: Cambridge Technicals in Engineering Unit 20: … · Web viewUsing project monitoring tools – GANTT Charts Learner activity sheet Activity 1 The ability to plan and monitor activity

R

GANTT Chart Activity – Example