Caissons Cofferdams Report

download Caissons Cofferdams Report

of 24

Transcript of Caissons Cofferdams Report

  • 8/17/2019 Caissons Cofferdams Report

    1/24

    1

    B.TECH SEMINAR ON

    CAISSONS AND COFFERDAMS

    FOR THE SUBJECT OF

    ADVANCED FOUNDATION ENGINEERING

    BY

    RAJAT JAIN (11BCL020)

    KARTIK GUPTA (11BCL047)

    SUBMITTED TO

    Dr. TRUDEEP N. DAVE

    DEPARTMENT OF CIVIL ENGINEERING

    SCHOOL OF TECHNOLOGYPANDIT DEENDAYAL PETROLEUM UNIVERSITY

    GANDHINAGAR, GUJARAT

  • 8/17/2019 Caissons Cofferdams Report

    2/24

  • 8/17/2019 Caissons Cofferdams Report

    3/24

    3

    1. I ntroduction

    1.0 GENERAL

    During the construction of bridges, dams or any other structure where the foundation part

    of the structure is most likely to lie underwater, we have to opt for underwater

    construction. Construction in water poses many difficulties especially in the places where

    there the depth is considerable. During underwater construction our main objective is to

    create dry and water free environment for working in such manner that the structural

    stability of the structure is not compromised.

    Fig- 1 Flowchart showing techniques of underwater construction

    Underwater Construction

    Caissons

    Cofferdams

  • 8/17/2019 Caissons Cofferdams Report

    4/24

    4

    2. C aissons

    2.0 GENERAL

    The name „caisson‟ is French and is to be translated as a „large chest‟, which refers to thegeneral shape of the caissons. In geotechnical engineering, a caisson is a watertight

    retaining structure used, for example, to work on the foundations of a bridge pier, for the

    construction of a concrete dam, or for the repair of ships. These are constructed such that

    the water can be pumped out, keeping the environment dry.

    2.1 TYPES

    Caissons are divided into three major types:

    i. Open Caissons

    ii. Box Caisson (or closed caissons)

    iii. Pneumatic Caissons

    Open caissons (Fig-2) are concrete shafts that remain open at the top and bottom during

    construction. The bottom of the caisson has the cutting edge. The caisson is sunk into

    place, and soil from the inside of the shaft is removed by grab buckets until the bearing

    stratum is reached. The shafts may be circular, square, rectangular or oval. Once the bearing stratum is reached, concrete is poured into the shaft (underwater) to form a seal at

    its bottom. When the concrete seal hardens, the water inside the caisson shaft is pumped

    out. Concrete is then poured into the shaft to fill it. Open caissons can be extended to

    great depths, and the cost of construction is relatively low. However, one of their major

    disadvantages is the lack of quality control over the concrete poured into the shaft for the

    seal. Also, the bottom of the caisson cannot be thoroughly cleaned out. An alternative

    method of open-caisson construction is to drive some sheet piles to form an enclosed

    area, which is filled with sand and is generally referred to as a sand island. The caisson is

    then sunk through the sand to the desired bearing stratum.

  • 8/17/2019 Caissons Cofferdams Report

    5/24

    5

    Fig-2 Open Caisson

    Box caissons (Fig-3) are caissons with closed bottoms. They are constructed on land and

    then transported to the construction site. They are gradually sunk at the site by filling the

    inside with sand, ballast, water or concrete. The cost for this type of construction is low.

    The bearing surface must be level, and if it is not, it must be leveled by excavation.

  • 8/17/2019 Caissons Cofferdams Report

    6/24

    6

    Fig-3 Box Caisson

    Pneumatic caissons (Fig-4) are generally used for depths of about 50-130 ft (15-40 m).

    This type of caisson is required when an excavation cannot be kept open because the soil

    flows into the excavated area faster than it can be removed. A pneumatic caisson has a

    work chamber at the bottom that is at least 10 ft (≈ 3 m) high. In this chamber, the

    workers excavate the soil and place the concrete. The air pressure in the chamber is kept

    high enough to prevent water and soil from entering. Workers usually do not counter

  • 8/17/2019 Caissons Cofferdams Report

    7/24

    7

    severe discomfort when the chamber pressure is raised to about 15 lb/in 2 (≈ 100 KN/m 2)

    above atmospheric pressure. Beyond this pressure, decompression periods are required

    when the workers leave the chamber. Workers enter and leave the chamber through a

    steel shaft by means of a ladder. This shaft is also used for the removal of excavated soil

    and the placement of concrete. For large caisson construction, more than one shaft may

    be necessary, an airlock is provided of each one. Pneumatic caissons gradually sink as

    excavation proceeds. When the bearing stratum is reached, the work chamber is filled

    with concrete.

    Fig-4 Pneumatic Caisson

  • 8/17/2019 Caissons Cofferdams Report

    8/24

    8

    2.2 FUNCTIONS

    The main functions of caissons generally are soil or water retention and transfer of

    vertical and horizontal loads into the subsoil. Less frequent functions are provision of

    space for equipment or machinery, and locking through of ships, if the caisson is part of alock or barrier.

    With respect to application:

    i. Closure of breaches in dikes and dams (closed and flow-through caissons)

    ii. Breakwater

    iii. Quay wall

    iv. Storage

    v. Tunnel element

    vi. Foundation for bridge pier, lighthouse, wind mill etc.

    vii. Specials – casing for hydro-electric plant; Gate for a dry dock

    2.3 THICKNESS OF CONCRETE SEAL IN OPEN CAISSONS

    The concrete seal should be thick enough to withstand an upward hydrostatic force from

    its bottom after dewatering is complete and before concrete fills the shaft. Based on the

    theory of elasticity the thickness „t ‟, according to Teng (1962) is

    Fig-5 Calculation of the thickness of the seal for an open caisson

  • 8/17/2019 Caissons Cofferdams Report

    9/24

    9

    t = 1.18 R i √(q/f c )………………………………………(Circular Caisson)

    and

    t = 0.866 B i √q/f c [1+1.61(L i /Bi )…………………… (Rectangular Caisson)

    where;

    Ri = inside radius of a circular caisson

    q = unit bearing pressure at the base of the caisson

    f c = allowable concrete flexural stress

    Bi , L i = inside width and length, respectively, of rectangular caisson

    The value of q can be approximated as

    q ≈ Hγw - tγc

    where,

    γc = unit weight of concrete

    The thickness of seal calculated by equations will be sufficient to protect it from cracking

    immediately after dewatering. However, two other conditions should also be checked for

    safety.

    1) Check for Perimeter Shear on Contact Face of Seal and Shaft

    According to Fig-5, the net upward hydrostatic force from the bottom of the seal

    is − (where = 2 for circular caissons and A = for

    rectangular caissons). So the perimeter shear developed is

    v ≈ ( – )/

    Where,

    p i = inside perimeter of the caisson

    Note that

    p i = 2 ……………………………………..(For circular caissons)

  • 8/17/2019 Caissons Cofferdams Report

    10/24

    10

    And

    p i = 2 (L i + B i)…………………………….. (For circular caissons)

    The perimeter shear given by equation should be less than the permissible

    shear stress, v u , or

    v (MN/m 2) ≤ v u (MN/m 2) = 0.17 √f’ c (MN/m 2)Where

    = 0.85

    2 Check for Buoyancy

    If the shaft is completely dewatered, the buoyant upward force, F u , is

    F u = ( R 0 2 ) H ……………………………(For circular caissons)

    And

    F u = (B 0 L 0 ) H ……………………………(For rectangular caissons)

    The downward force, F d , is caused by the weight of the caisson and the seal

    and by the skin friction at the caisson-soil interface, or

    F d = W c + W s + Q s

    Where

    W c = weight of caisson

    W s = weight of seal

    Q s = skin frictionIf F d > F u , the caisson is safe from buoyancy. However, if F d < F u , dewatering

    the shaft completely will be unsafe. For that reason, the thickness of the seal

    should be increased by Δt or

    Δt = ( F u – F d )/A i

  • 8/17/2019 Caissons Cofferdams Report

    11/24

    11

    Example:-

    An open caisson (circular) is shown in Fig. Determine the thickness of the seal that

    will enable complete dewatering.

    Solution:-

    t = 1.18 R i √(q/f c )For Ri = 7.5 ft,

    q ≈ (45)(62.4) -

    with = 150lb/ft 3, q = 2808 – 150t and

    f c = 0.1 f’ c = 0.1 x 3 x 10 3 lb/in 2 = 0.3 x 10 3 lb/in 2

    So

    t = (1.18)(7.5) √(2808 – 150)/(300 x 144)or

    t 2 + 0.07 t – 5.09 = 0

    t = 2.2 ft

    Use t = 2.5 ft

    Check for Perimeter Shear

    v = ( 2 – 2 )/ 2 2

    = ( )(7.5) 2[(45)(62.4)-(2.5)(150)]/(2)( )(7.5)(2.5) ≈ 3650 lb/ft 2

    = 25.35 lb/in 2

  • 8/17/2019 Caissons Cofferdams Report

    12/24

    12

    The allowable shear stress is

    vu = 2 √f c = (2)(0.85) √300= 29.4 lb/in 2 v = 25.35 lb/in 2 < v u = 29.4 lb/in 2 --- OK

    Check against Buoyancy

    The buoyant upward force is

    F u = ( R 0 2 ) H

    For R 0 = 10ft

    F u = ( ) (10) 2(45) (62.4)/1000 =882.2 kip

    The downward force, F d = W c + W s + Q s and

    Wc = (R 02 – Ri2) ( )(55) = ( 10 2 – 7.5 2) (150) (55) = 1,133,919 lb ≈ 1134 kip

    Ws = ( Ri2)t = ( ) (7.5) 2 (1) (150) = 26,507 lb =26.5 kip

    Assume that Q s ≈ 0, So

    F d = 1134 + 26.5 = 1160.5 kip

    Because F u < F d , it is safe. For design, assume that = 2.5 ft.

    2.4 CAISSONS THROUGH THE AGES

    2.4.1 ANCI ENT TI M ES

    Caissons in civil and military engineering have been used since the era of the Roman

    Empire for various purposes. The first application of caissons found in the research, is in

    about 250 BC, in Alexandria, Egypt, where watertight caissons have been used to

    construct quay walls (Fig-6). (De Gijt, 2010)

    Fig-6 Floating caisson used to transport a mortar block, Alexandria 250BC

  • 8/17/2019 Caissons Cofferdams Report

    13/24

    13

    Later on in history, 13 years BC, king “Herod the Great” ordered the construction of the

    port of Caesarea, Judea, which became the largest on the eastern Mediterranean coast.

    The mole (havenhoofd) was built on floating units; timber casing that were prefabricated,

    transported over water (floating) and on the right location immersed by ballasting with

    stone (Fig-7). The dimensions of these caissons were 15 x 5.5 x 2.7 m, the water

    displacement was 220 tons. (Bernshtein 1994)

    Fig-7 Timber caisson for the mole of the port of Caesarea, Judea, about 13 BC

    Some centuries later, Robert Weldon, a British Engineer, invented a ship elevator, which

    he called a “Hydrostatic Caisson Lock”. This caisson lock is a type of canal lock, and was

    intended to raise and lower ships in the Shropshire Canal. The vertical transport of ship

    took place in an immersed, sealed caisson box that moved up and down in a big water

    container, a cistern (Fig-8)

  • 8/17/2019 Caissons Cofferdams Report

    14/24

    14

    Fig-8 Robert Weldon`s Caisson lock at Oakengates

    Engineers found out that in the same way they could construct foundations for bridge

    piers, which they first did in Vichy (France), later also in England (e.g. for the piers of

    the Royal Albert Bridge in Cornwall, 1859 and the Firth of Forth railroad bridge in

    Scotland, 1890) and the United Sates of America (e.g. the Brooklyn Bridge in New Yorkand the Mississippi Bridge in St. Louis), followed by other countries. (Nebel, 2007)

    2.4.2 TWENTI ETH CENTURY

    Another important field of application of caissons nowadays are ports and harbors. The

    variations in dimensions through the years is shown in Fig-9

    Fig-9 Various Caisson Dimensions in the Netherlands, 20 th Century

  • 8/17/2019 Caissons Cofferdams Report

    15/24

    15

    2.4.3 NOWA DA YS USE OF CA I SSONS

    Caissons nowadays are used for a wide variety of applications. Pneumatic caissons, for

    example, are still used for the construction of metro tunnels, like for the Amsterdam

    Noord – Zuidlijn underpass of the Damrak.

    Fig-10 Caisson for the metro of Amsterdam

    Fig-11 Caisson pier foundation with watertight partition during construction of the HSL bridge over the

    Hollandsch Diep

  • 8/17/2019 Caissons Cofferdams Report

    16/24

    16

    2.5 CONSTRUCTION

    Standard caissons are generally prefabricated „in the dry‟ in a construction dock. When

    ready, the dock is inundated and the caisson can be transported over water to the actual

    site using its own buoyancy. There it is immersed to the river, sea or estuary bed and ballasted heavily enough to remain at its place and fulfill its function. The life cycle of

    caissons consists of the following stages:

    i. Idea/ Initiative

    ii. Planning and design, laboratory tests

    iii. Prefabrication

    iv. Transport

    v. In – situ constructionvi. Operation, Maintenance

    vii. Upgrading, removal & reuse or demolition

  • 8/17/2019 Caissons Cofferdams Report

    17/24

    17

    3. C offerdams

    3.1 GENERAL

    A cofferdam is a temporary structure designed to keep water and/or soil out of the excavationin which a bridge pier or other structure is built. When construction must take below the

    water level, a cofferdam is built to give workers a dry work environment. Sheet pile is driven

    around the work site, seal concrete is placed into the bottom to prevent water from seeping in

    from underneath the sheet piling, and the water is pumped out. The word “cofferdam” comes

    from “coffer” meaning box, in other words a dam in the shape of a box. There are different

    types of cofferdam, some are used to support excavation operation and some are enclosed

    type box placed in water.

    3.2 TYPES OF COFFERDAMS

    1. Braced: - It is formed from a single wall of sheet piling which is driven into the

    ground t o form a „„box‟‟ around the excavation site. The box is then braced on the

    inside and the interior is dewatered. It is primarily used for bridge piers in shallow

    water (30-35 ft depth)

    2. Earth – Type: - It is the simplest type of cofferdam. It consists of an earth bank with

    a clay core or vertical sheet piling enclosing the excavation. It is used for low levelwaters with low velocity and easily scoured by water rising over the top.

    3. Timber – Crib: - Constructed on land and floated into place. Lower portion of each

    cell is matched with contour of river bed. It uses rock ballast and soil to decrease

    seepage and sink into place, also known as “Gravity Dam”. It usually consists of 12`

    x 12` cells and is used in rapid currents or on rocky river beds. It must be properly

    designed to resist lateral forces such as tipping / overturning and sliding.

    4. Double – Walled Sheet Pile: - They are double walled cofferdams comprising two

    parallel rows of sheet piles driven into the ground and connected together by a system

    of tie rods at one or more levels. The space between the walls is generally filled with

    granular material such as sand, gravel or broken rock.

  • 8/17/2019 Caissons Cofferdams Report

    18/24

    18

    5. Cellular: - Cellular cofferdams are used only in those circumstances where the

    excavation size precludes the use of cross excavation bracing. In this case, the

    cofferdam must be stable by virtue of its own resistance to lateral forces.

    3.3 ADVANTAGES OF COFFERDAM

    Performing work over water has always been more difficult and costly than performing the

    same work on land. And when the work is performed below water, the difficulties and cost

    difference can increase geometrically with the depth at which the work is performed. Below

    some of the advantages of cofferdam are listed:

    a. Allow excavation and construction of structures in otherwise poor environment

    b. Provides safe environment to work

    c. Contractors typically have design responsibilityd. Steel sheet piles are easily installed and removed

    e. Materials can typically be reused on other projects

    3.4 TYPES OF IMPOSED LOADS

    A typical cofferdam will experience several loading conditions as it is being build and during

    the various construction stages. The significant forces are hydrostatic pressure, forces due to

    soil loads, water current forces, wave forces, ice forces, seismic loads and accidental loads.

    In order to overcome the displaced water buoyancy, the tremie seal thickness is about equal

    to the dewatered depth.

    Fig – 12 Cofferdam schematic

  • 8/17/2019 Caissons Cofferdams Report

    19/24

    19

    3.4.1 H YDROSTAT I C PRESSURE

    The maximum probable height outside the cofferdam during construction and the water

    height inside the cofferdam during various stages of construction need to be considered.

    These result in the net design pressure shown in Fig-13 below:

    Fig-13 Hydrostatic forces on partially dewatered cofferdam

    3.4.2 F ORCES DUE TO SOI L L OADS

    The soil imposes forces, both locally on the wall of the cofferdam and globally upon the

    structure as a whole. These forces are additive to the hydrostatic forces. Local forces are a

    major component of the lateral force on sheet-pile walls, causing bending in the sheets,

    bending in the wales, and axial compression in the struts.

    Fig – 14 Soil force in typical weak mud or clays

  • 8/17/2019 Caissons Cofferdams Report

    20/24

    20

    3.4.3 CURRENT F ORCES ON STRUCTURE

    With a typical cofferdam, the current force consists not only the force acting on the normal

    projection of the cofferdam but also on the drag force acting along the sides. With flat sheet

    piles, the latter may be relatively small, whereas with z-piles it may be substantial, since thecurrent will be forming eddies behind each indentation of profile, as shown in Fig – 15

    Fig-15 Current flow along sheet piles

    3.5 SCOUR

    Scour of the river bottom or seafloor along the cofferdam may take place owing to river

    currents, tidal currents, or wave-induced currents. Some of the most serious and disastrous

    cases have occurred when these currents have acted concurrently.

    A very practical method of preventing scour is to deposit a blanket or crushed rock or heavy

    gravel around the cofferdam, either before or immediately after the cofferdam sheet piles are

    set. A more sophisticated method is to lay a mattress of filter fabric, covering it with rock to

    hold it in place.

    3.6 SHEET PILE SHAPES

    Larsen/”U” Type Flat/Straight Type Fig-16 Sheet Pile Shapes

    Arch shaped and Lightweight

  • 8/17/2019 Caissons Cofferdams Report

    21/24

    21

    3.7 TYPES OF INTERLOCKS

    Ball & Socket (BS)

    Single Jaw (SJ)

    Double Jaw (DJ)

    Hook and Grip (HG)

    Thumb and Finger one point contact (TFX)

    Double Hook (DH)

    Thumb and Finger three point contact (TF)

    Fig-17 Types of Interlocks

  • 8/17/2019 Caissons Cofferdams Report

    22/24

    22

    3.8 EXAMPLES OF COFFERDAM

    Cofferdam for the Sidney Lanier Bridge, Oregon

    Installation of wale & strut system – Braced Cofferdam

    Installation of strut system and driving the sheet piles

    Fig-18 Cofferdam examples

  • 8/17/2019 Caissons Cofferdams Report

    23/24

    23

    REFERENCES

    Bernshtein, L.B. (chief edt.) Tidal Power Plants Korea Ocean Research and Development

    Institute. 1996.

    Gijt, J.G. de A History of Quay Walls Doctoral dissertation Delft, 2010

    Nebel, B. Die Caissongründung

    http://www.berndnebel.de/bruecken/6_technik/caisson/caisson.html. 2007

    FIGURES

    Fig – 1: Flowchart showing techniques of underwater construction

    Fig – 2: Drilled Shaft and Caisson Foundation, NPTEL

    Fig – 3: Drilled Shaft and Caisson Foundation, NPTEL

    Fig – 4: Drilled Shaft and Caisson Foundation, NPTEL

    Fig – 5: Drilled Shaft and Caisson Foundation, NPTEL

    Fig – 6: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures

    Fig – 7: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures

    Fig – 8: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures

    Fig – 9: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures

    Fig – 10: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures

    Fig – 11: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures

    Fig – 12: Professor Kamran M. Nemati, Tokyo Institute of Technology

    Fig – 13: Professor Kamran M. Nemati, Tokyo Institute of Technology

    Fig – 14: Professor Kamran M. Nemati, Tokyo Institute of Technology

    Fig – 15: Professor Kamran M. Nemati, Tokyo Institute of Technology

    http://www.berndnebel.de/bruecken/6_technik/caisson/caisson.html.%202007http://www.berndnebel.de/bruecken/6_technik/caisson/caisson.html.%202007http://www.berndnebel.de/bruecken/6_technik/caisson/caisson.html.%202007

  • 8/17/2019 Caissons Cofferdams Report

    24/24

    Fig – 16: Professor Kamran M. Nemati, Tokyo Institute of Technology

    Fig – 17: Professor Kamran M. Nemati, Tokyo Institute of Technology

    Fig – 18: Professor Kamran M. Nemati, Tokyo Institute of Technology