    Introduction

    -Practice objective-

    1.

    Enrich students' knowledge in technology and organization work

    and generally in the composition and execution of buildings.

    2.Acquisition by students of the method of expression in writing

    and graphically by schemes and technological sheets, both overall

    design and details that makes the practical implementation of

    various technological processes, in appropriate terms of quality,

    work safety and economic efficiency.

    3. Initiate students in the daily activities of the leader of a work

    point, achieve an objective of building activity that characterizez

    the immediate following college graduation period.

  • 7/29/2019 caiet de practica tehnologica

    2/15

    Raport activitate saptamanal

    Practica tehnologic i de organizare

    la

    ECHIPA ...1....

    Luni 18.06.2012 durata 1h

    Activitati: Prezentarea generala a metodologiei si cerintele practicii tehnologice si de

    organizare.In cadrul acestei sedinte ni s-au prezentat obiectivele practicii si ceea va trebui

    sa contina caietul de practica de la sfarsitul stagiului.

    Marti si Miercuri (19-20.06.2012)

    Activitati: Insusirea programei analitice si recapitularea cunostiintelor din timpul anului in

    vederea desfasurarii intr-un mod coerent si comprhensibil a perioadei de practica.

    Joi (21.06.2012) durata 09:00-14:00

    Activitati: Impartirea pe echipe si pe companii in sala R 02 dupa care efectuarea cursurilor

    de Siguranta si Sanatate a Muncii(SSM) , Situatiilor de orgenta (SU) si Protectia mediului,

    finalizate fiecare in parte cu cate un test de evaluare.Aceste cursuri au fost realizate la

    sediul firmei in vederea informarii asupra riscurilor de pe santier.Totodata ne-au fost

    prezentate atat obligatiile cat si drepturile practicantului.

    In cadrul aceleeasi zile la sediul firmei Sc Cris Crisco SRL ni s-au prezentat planurile

    necesare deschiderii unui santier precum si fisele tehnice si metodele evaluarii riscurilor

    existente pe un santier.

    Vineri (22.06.2012) durata 08:00-10:30

    Activitati: Vizitarea santierului denumit Parcare subterana apartinand Hotelului Unirea .

    In cadrul acestei vizite ni s-a prezentat organizarea santierului (fiind unul de dimensiuni

    reduse organizarea acestuia a fost realizata intr-un mod simplu avand o singura cale de

    acces direct din str.V Alecsandri), dupa care domnul director executiv Robert ne-a descris

    succint etapele realizarii constructiei, plecand de la sapaturi, sprijiniri, drenaje, necesar de

    materiale, tip de materiale, tipuri de cofraje, etapele cofrarii precum si perioadele aferenteacestor operatiuni.

    Asadar constructia avand dimensiunile 24x67 m are drept sistem de fundare radier general

    avand grosimea de 0.8m, armat cu STPB 10 si 8. Sistemul structural fiind constituit din

    stalpi + plansee armate pe doua directii. Stalpii au fost armati cu 16 iar planseul cu STPB

    10 si 8 ambele elemente fiind realizate cu beton clasa C28/32.5.

  • 7/29/2019 caiet de practica tehnologica

    3/15

    Luni (25.06.2012) durata 08:00-10:15

    Activitati: Vizitarea santierului denumit Hotel Imperial.

    Discutii in cadrul grupului pe tema santierului vizitat. S-a putut observa planurile planurile

    arhitecturale ale santierului, detalii de constructie(structura pe cadre) si finisaj astructurii(fatada placata cu placi decorative melaminate)

    Marti (26.06.2012) durata 08:00-11:30

    Activitati: Discutii cu domnul inginer Cristi Cioanca pe baza ultimului santier vizitat:

    Parcare subterana apartinand Hotelului Unirea. Am aprofundat si reluat etapele realizarii

    constructiei: sapaturi, sprijiniri, drenaje, obiectivul final.

    Vizitarea santierului denumit Hotelului Imperial, avand ca obiectiv realizarea unui

    tip de imobil hotel, cu un regim de inaltime P+6E avand o suprafata utila de 600mp,

    parterul fiind predestinat pentru activitati comerciale.

    In aceasta vizita ni sa prezentat succint etapele realizarii constructiei, plecand de la

    pregatirea terenului, sapaturi pana la finisaje.

    Constructia fiind intr-o etapa avansata am putut observa atat lucrari de finisaj cat si lucrari

    gata finalizate(fatada, camerele de la ultimale 2 etaje, acoprerisul terasa).

    Vizitarea unui santier din zona Copou avand ca obiectiv o casa unifamiliala.

    Ni s-au prezentat etapele realizarii constructiei: pregatirea terenului, sprijinirea

    pamantului cu ajutorul unui perete de sprijin , aducerea la o cota uniforma convenabila,

    realizarea fundatiei si suprastructurii. La acest santier sa putut observa structura pe pereti

    portanti a structurii, zidul de sprijin, finisaje(termoizolatie, izolatie fonica).

    Vizitarea unui santier din zona Breazu avand ca obiectiv o casa unifamiliala + garaj+

    beci+ magazie.

    La acest santier sa putut observa etapele realizarii constructiei: sapaturi, sisteme de

    cofrare, tipuri de cofraje, sisteme pe cadre a structurii.

    Miercuri (27.06.2012) durata 08:00-10:30

    Activitati: Discutii cu domnul inginer Cristi Cioanca pe tema tuturor santierelor vizitate:

    -santierul de la parcarea subterana a Hotelului Unirea

    - santierul de la Hotelul Imperial

    - santierul din zona Copou avand ca obiectiv o casa unifamiliala-santier din zona Breazu avand ca obiectiv o casa unifamiliala + garaj+ beci+ magazie.

    Lucru la caietul de practica si prezentarea ppt.

  • 7/29/2019 caiet de practica tehnologica

    4/15

    Joi (28.06.2012) durata 08:00-08:30

    Activitati: Intalnirea cu indrumatorul de pratica in vederea rezolvarii eventualelor

    probleme si neintelegeri.

    durata 12:00-15:30

    Activitati: Instruirea si Protectia Muncii la firma Cris-Crisco.SRL in vederea angajarii.

    Semnarea contractelor de munca.

    Vineri (29.06.2012) durata 10:00-11:30

    Activitati: Discutii in cadrul grupului pe tema caietului de practica.

    Lucru la caietul de practica si a prezentarii ppt.

  • 7/29/2019 caiet de practica tehnologica

    5/15

    2.Health and Safety in ConstructionMinimum safety and health requirements for construction sites

    1. Stability and solidity

    1.1. Materials, equipment and, in general, anything that, to shift something, may affect safety and

    health, should be fixed in an appropriate and safe way.1.2. Access to any surface material that has not adequate strength is not permitted unless equipment is

    used or suitable means so that work is done safely.

    2. Power distribution equipment

    2.1. Installations must be designed, made and used so as not to present a fire or explosion, and workers

    are properly protected against the risk of electrocution by direct or indirect affect.

    2.2. The design, construction and choice of material and protection devices must take into account the

    type and power of the energy distributed, external conditions influence and competence of persons

    with access to parts of the plant.

    3. Routes and emergency exits

    3.1. Emergency routes and exits must be permanently free and lead in the most direct way possible in asecure area.

    3.2. In an emergency, all construction sites must be able to evacuate quickly and safely as possible for

    workers.

    3.3. Number, location and dimensions of emergency routes and exits is determined according to use of

    equipment and site dimensions and the rooms and the number of persons that may be present.

    3.4. Emergency routes and exits must be marked in accordance with the provisions of national

    legislation transposing Directive 92/58/CEE.

    Signaling panels must be made of a sufficiently durable material and be placed in appropriate places.

    3.5. To be used at any time, without difficulty, routes and emergency exits and passages and doors that

    have access to them must not be blocked by objects.3.6. Emergency routes and exits requiring illumination must be provided with safety lighting, adequate

    intensity in case of power failure.

    4. Detection of fire and fire fighting

    4.1. Depending on site characteristics and the size and destination rooms, equipment present, the

    physical and chemical properties of substances or materials present, and the number of persons that

    may be present, it is necessary to provide a sufficient number of devices appropriate fire-fighting and, if

    necessary, a sufficient number of fire detectors and alarm systems.

    4.2. Extinguishing devices, fire detectors and alarm systems must be maintained and checked

    periodically.

    At regular intervals should be made appropriate tests and exercises.

    4.3. Non-automatic extinguisher must be accessible and easy to handle.

    4.4. They must be marked according to the national legislation transposing Directive 92/58/CEE.

    Signaling panels must be sufficiently resistant and placed in appropriate places.

    5. Ventilation taking into account the working methods used and the physical demands placed on

    workers, have taken steps to ensure workers enough fresh air. If using an installation of ventilation, it

  • 7/29/2019 caiet de practica tehnologica

    6/15

    must be maintained in working order and must not expose workers to drafts which could affect health.

    When necessary for health workers, a control system must signal any accidental shutdown of the plant.

    6. Exposure to particular risks

    6.1. Workers should not be exposed to hazardous noise levels or harmful external influences such as

    gases, vapors or dust.

    6.2. When workers must enter into an area whose atmosp