Chapter 1 Executive Summary

Transcript of CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003,...

Page 1: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

Chapter 1 Executive Summary

Page 2: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐1 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

CCHHAAPPTTEERR  11  

EEXXEECCUUTTIIVVEE  SSUUMMMMAARRYY   1.1  BACKGROUND 

1.1.1  Introduction 

In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated vision for the long-term future development at Columbia Metropolitan Airport (CAE), which this Master Plan Update builds upon. The Master Plan Update is intended to address the steps over the next twenty years (the “planning period” required by FAA). The primary focus will be on the short and intermediate-term actions to improve air transport access, passenger terminal efficiency and security, air safety, and to maximize development and economic impact to generate resources to support CAE. 1.1.2  Goals and Key Issues 

The Master Plan Update is the Commission’s strategy for the development of the Columbia Metropolitan Airport to satisfy demand in a cost effective manner, while minimizing environmental and socioeconomic impacts. The planning process is tailored to the unique conditions at CAE. In particular, the CAE Master Plan Update will address the impacts of the following issues and changing trends upon airport facilities:

Post 9/11 Security Impacts Airline Mergers, Acquisitions, Bankruptcies Broad Global Economic Downturn Fuel Costs / Changes in Airline Fleet Mixes / Operational Efficiencies “Green” Design Momentum Maturing Technologies (i.e. Internet Check-In, Common Use Equipment)

1.1.3  Factors Influencing the Master Plan 

Focus Group Meeting Summary 

The Columbia Metropolitan Airport is perceived as a beautiful, attractive showcase of the Midlands.

Page 3: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐2 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

The airport has not yet reached its greatest use potential because of the high costs of airfare and parking, the limited availability of flight options, and the limited number of direct flights.

The airport should be more involved in marketing its products and services to the local community and marketing the local community to prospective passengers and major employers in an effort to increase volume at the airport.

The airport should assume more of a leadership role in economic development. The Community should engage in ongoing communications and dialogue with the airport

staff and RLAD Commission to continue toward a more competitive model going forward.

 

1.2  EXISTING FACILITIES 

A review of information related to the Columbia Metropolitan Airport and the surrounding communities provided the basis for future analyses. Historic data was obtained from a variety of sources (i.e. FAA approved documentation, site visits, data provided by users, staff and tenants, etc.). 1.2.1  Airfield Area 

The airport is owned and operated by the RLAD, and is equipped with two primary runways, Runway 11-29 and Runway 5-23, which each provide 95 percent wind coverage. The two runways are supported by taxiways providing access to commercial, cargo, fixed based operator and general aviation facilities. Existing airfield facilities are illustrated below.

Page 4: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

Columbia 

Executive 

 1.2.2  T

REpev

Tnlo

Tyex

Metropolitan

Summary 

erminal Are

Road access Expressway

lanning periventually I-2

The terminal ow includesocated in sep

The terminal ards is currxcellent con

n Airport Mas

ea 

to the airpoand dedicatiod with dire20 to the norarea parking

s 3,305 spacparate areas capron consi

rently usabldition, havin

ster Plan Upd

EXISTING A

ort is very gted overpassect connectirth. g was improces. Employconsisting ofsts of 153,47e for aircrang been repla

date 

AIRFIELD FAC

good with ths to the airion to I-26 t

oved with coyee parking f another 2575 square yaaft parking naced in 2004

CILITIES 

he 2005 comrport. This to the south

ompletion of and rental 8 and 326 sp

ards of concrnear the ter4 and 2006.

mpletion of may be im(John Hard

f a public pacar ready/r

paces respecrete pavemerminal. The

the John Hmproved ovedee Phase II

arking garagreturn spacectively. nt. 65,686 sq

e pavement

 

1‐3 

ardee er the ) and

e and es are

quare is in

Page 5: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

Columbia 

Executive 

TTcoarse

1.3  H

Overall, might be 1.3.1  A

Columbigeneral adata for Citinerant civil (LOdetailed aanalysis carrier (I  

IT A

 

ANNUAL OPER

ATIONS

Metropolitan

Summary 

The current tThe concoursompleted in rea is approeparate build

HISTORIC D

the purposeused to aug

Aircraft Oper

a Metropoliaviation, corpCAE (1990 air taxi (IT

OC CIV), andand is usefuof the TAF T AC) and i

AC – Itinerant Air

0

10,000

20,000

30,000

40,000

50,000

60,000

n Airport Mas

erminal builse area was1997, resul

oximately 23ding for adm

DEMAND 

e of the histgment the for

rations 

itan Airportporate, and m– 2009) is sAT), itinera

d local militaul in demonsdata revealen the itinera

HISTORIC

Sources: FAA 20r Carrier, IT AT –

 

ster Plan Upd

lding was or replaced anlting in the t31,000 squa

ministrative u

torical activrecasts of av

t accommodmilitary aircorted into thant general ary (LOC Mtrating the v

ed that cargoant air taxi (I

CAL AIRCRAF

009 TAF and The– Itinerant Air Tax

Y

date 

riginally connd a major terminal mu

are feet withuse.

ity analysis viation deman

dates a mixcraft. Historhe followingaviation (IT

MIL). Althouvarious typeso operationalT AT) totals

FT OPERATIO

e LPA Group Incoxi, IT GA – Itiner

 

EAR

nstructed in renovation

uch as it exih an additio

is to identind.

x of operatirical FAA Teg categories: T GA), itinerugh this meths of activityl activity was.

ONS (1990‐2

orporated, Februrant General Avi

1965 and exto the land

ists today. Tonal 10,345

ify specific

ions by comerminal Areitinerant air

rant militaryhodology of

y that occur aas included in

2009) 

uary 2010. iation, LOC CIV –

xpanded in dside portionThe total bui

square feet

local trends

mmercial, ca Forecast (Tr carrier (IT y (IT MIL), f categorizatiat CAE, a fun the itinera

– Local GA/Civil

IT A

IT A

IT G

LOC

 

1‐4 

1976. n was ilding t in a

s that

cargo, TAF) AC), local

ion is urther ant air

 

AC

AT

GA

C CIV

Page 6: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐5 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

1.3.2  Passenger Enplanements 

Since 1990, annual growth or decline in CAE’s enplanement levels may be linked to the following events: U.S. economic recessions, low-cost-carrier service by Air South, Independence Air, Allegiant, and Spirit Airlines, terminal renovations, hurricane impacts in the Carolinas and the Gulf Coast, and the terrorist actions on September 11, 2001. Because of these various events, some of which were unpredictable, CAE’s enplanement growth has generally been experienced in short-term spurts of no more than three years.

1.4  AVIATION DEMAND FORECASTS 

1.4.1  Long‐Term Demand Forecast Development 

Within 10 years activity passenger enplanements at CAE will recover to 2005-2006 previous peaks, then increase another 27% by 2028 (about 2% per year).

AIR CARRIER/REGIONAL ENPLANEMENT SPLIT FORECAST 

YEAR PREFERRED 

ENPLANEMENTS AIR CARRIER  REGIONAL 

2008  569,561  66,549  503,012 

2009  538,741  54,444  484,297 

2013  591,076  54,444  536,632 

2018  664,524  54,444  610,080 

2023  748,035  54,444  693,591 

2028  842,980  54,444  788,536 

AAGR 2008‐2028  1.98%  ‐1.00%  2.27% 

GROWTH 2008‐2028  48.01%  ‐18.19%  56.76% 

INCREASE 2008‐2028  273,419  ‐12,105  285,524 

Source: The LPA Group Incorporated, February 2010. 

Page 7: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

Columbia 

Executive 

Althoughnumber igeneral aplanning traffic atFAA’s fo

1.5  A

Based upaviation requiremnecessary  

2

3

3

4

4

5

OPER

ATIONS

Metropolitan

Summary 

h the total ois skewed byaviation activ

period. Ast CAE, annuorecast numb

AIRPORT CA

pon the visiodemand, op

ments. This y to meet sho

05,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

45,000

0,000

n Airport Mas

operations foy the significvity are exps might be eual airline ober of passen

SUM

Sourc

APACITY &

on for the Coperational re

informationort and long

 

ster Plan Upd

orecast onlycant decline iected to oncxpected with

operations arnger enplane

MMARY OF O

ce: The LPA Grou

& FACILITY

olumbia Metequirements n provides t-term needs

date 

y shows an in 2009 genece-again growh the currenre expected ements.

OPERATIONS

up Incorporated,

Y REQUIREM

tropolitan Aiand capacit

the basis foover the twe

YEAR

additional 1eral aviationw beginning

nt nature of rto grow th

S FORECAST

, February 2010.

MENTS 

irport, an evty were ide

or the typesenty-year pl

120 operation activity. Ag in 2011 anregional or

he most to a

valuation of aentified to ds and quantanning perio

ons by 2028Airline, cargond throughoucommuter a

accommodat

aviation anddetermine fatities of faciod.

M

CA

GA

AI

 

1‐6 

, this o, and ut the airline te the

 

d non-acility ilities

ILITARY

ARGO

A

RLINE

Page 8: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐7 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

1.5.1  Airfield Requirements 

The airfield facility requirements analysis compares the existing airfield and landside components of CAE to Federal Aviation Administration (FAA) planning guidelines and to the FAA-approved 20-year forecast of aviation demand. The goal is to establish the framework for resolving the issues identified at the beginning of this Master Plan Update, including the identification of long-term requirements for runway length, aircraft hangar storage, support facilities, and vehicular ground access. A summary of long-term facility requirements is identified below.

Summary of Facility Requirements

Runway 

Runway 11‐29  Extend runway to 11,000’ 

Runway 5‐23  Extend runway to 8,800’ 

Runway Width  No recommendations 

Pavement Strength  No recommendations 

Runway Safety Areas 

Runway Safety Areas (RSA) Adjust declared distances to provide additional RSA at runway ends 23, and 11.  Re‐grade RSA near end of Runway 5 to achieve additional RSA 

Runway Object Free Areas (ROFA)  Apply for modification of design standards for nonstandard ROFA areas 

Taxiways / Connectors 

Taxiway A  Recommend addition of paved shoulders to meet ADG‐V criteria 

Taxiway F  Recommend addition of paved shoulders to meet ADG‐V criteria 

Taxiway U  Widen existing taxiway to 75’ to meet ADG‐IV standards 

Taxiway Y  Recommend addition of paved shoulders to meet ADG‐V criteria 

Connectors Recommend addition of paved shoulders to meet ADG‐V criteria.  Recommend widening of connectors GG and S in conjunction with widening of Taxiway U. 

Approach Facilities 

Non‐Precision Approach Install approach lighting system, ODALS etc. and clear 30:1 GQS to achieve lower approach minimums to Runway 23 

Visual Landing Aids  Upgrade existing VASI at Runway 23 to PAPI 

Airfield Lighting  No recommendations 

Airfield Signage  No recommendations 

Pavement Markings  No recommendations 

Weather Instrumentation  No recommendations 

Fuel Storage  Install or relocate existing 100LL tanks to midfield general aviation area   

Landside Facilities 

T‐Hangar Facilities  12 T‐hangar Bays 

Corporate Hangar Facilities  23 Corporate Hangars with a minimum of 5,000 s.f. each 

Page 9: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐8 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

Summary of Facility Requirements

Aircraft Parking Apron 

Transient Aircraft Apron No additional Apron required – replicate existing apron areas to new midfield development area. 

Based Aircraft Apron (Tie‐downs) No additional Apron required – replicate existing apron areas to new midfield development area. 

Auto Parking 

Parking Lot New midfield development area should provide ample parking for proposed facilities 

ARFF Facility  Identify site for future relocation of ARFF facility 

ATCT Facility  Relocate ATCT to a new location within the midfield area 

Fuel Storage Requirements Relocate or purchase additional 100LL fuel tanks to support midfield development area. 

Air Cargo Requirements  Identify and reserve area for 40,000 SY apron expansion 

Property Acquisition 

Property Acquire additional 10.2 acres of property via easement or acquisition within existing and ultimate RPZ areas. 

Source: The LPA Group Incorporated, 2010. 

 

1.5.2  Terminal Requirements 

Columbia Metropolitan Airport (CAE) is a small hub airport and expected to remain in that category until 2028. Use has consistently been over 1.1 million total passengers with a high point of 1.45 million in 2005. As terminal use rebuilds from the current (CY 2010) level of approximately 1.0 million total passengers to a projected 1.65 million in 2028, expect further changes to be required. These will be generated by ongoing changes in the airline industry and in the security process such as:

Passenger check-in processes and airline offices (more off-site and automated transactions, smaller staffs, continued airline merger / consolidations).

Baggage screening for security and more technology to do it (replacing the manual systems currently located in the lobby).

Passenger screening process and more technology to do it (as well as increased space needs to accommodate it, with adequate space to queue, direct, and observe the passengers to maintain or improve processing time).

Continued efforts to increase airport revenues from non-airline uses and concessions. Larger aircraft (70-100 seats) to replace the current predominant use of 50 seat regional

jets. Improvements over time in the relationship of parked aircraft to the terminal, including

the use of more passenger loading bridges to maximize passenger comfort, as well as apron security.

Page 10: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

Columbia 

Executive 

To determserving aclaim, acomponea whole.2028 as i

Metropolitan

Summary 

mine the reqa specific fu

and passengents, which a At CAE, thindicated in t

n Airport Mas

quirements, unction. Somger holding.are analyzedhere are mothe followin

ster Plan Upd

the terminalme of the m Each ca

d in more detodest needs ng summary

date 

l building camain groups an then be tail, then reafor added teof terminal r

an be divideof activity further sub

assembled foerminal spacrequirement

ed into manyareas includ

bdivided inor a picture ce in plannits.

y sub-areas,de ticketing

nto specific of the demaing period o

 

1‐9 

each g, bag

sub-and as out to

Page 11: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐10 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

1.6  RECOMMENDED DEVELOPMENT 

The recommended plan is the primary output of the master plan process providing a strategic vision to address future demand, infrastructure requirements and the long-term goals of the airport as a whole. The recommended development plan further identifies resources to address potential opportunities related to commercial passenger service and industrial/commercial growth through the 20-year planning period. CAE’s current location near major transportation corridors, available land, and associated infrastructure combined with recommended development allows the airport to capitalize on several opportunities including its effort to be an impetus for future business and urban development. The illustrated recommended development plan consists of airfield, ground transportation, terminal, and various aviation support and land acquisition projects. 1.6.1  Airfield Improvements 

Several airport and terminal development options were presented to the public, stakeholders and the RLAD during several meetings and workshops. Airfield development alternatives evaluated included recommendations outlined in previous reports especially the FAA approved 2003 Master Plan Update and the FAA approved 2005 FAR Part 150 Study. The preferred development includes a comprehensive plan that balances future development with existing usable infrastructure, the surrounding environment, long-term vision of the RLAD Commission and the airport’s continuing role as a commercial service airport. Recommended airfield development projects shown in the figure below include the extensions of Runways 11 and 5, various pavement rehabilitation, taxiway and apron expansion projects, hangar and facility development, ARFF station relocation, installation of additional NAVAIDS, etc. In conjunction with proposed development of Runway 5-23, some parcels of property were also identified for future avigation easement or land acquisition allowing for continued expansion/development while limiting potential impacts to surrounding communities. Based upon preliminary environmental impacts and rough design requirements, preliminary order of magnitude cost estimates were developed. In addition, cost estimates, phasing, and funding options for the projects shown on the preferred alternative are included as part of an Implementation Plan.  

   

Page 12: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

Columbia 

Executive 

 

1.6.2  T

Tpcase

Metropolitan

Summary 

erminal Imp

The terminal lanning periapital improecurity stand

n Airport Mas

PRE

provements 

loop road hod. Road imovements pld-off are sug

ster Plan Upd

EFERRED AIR

as been rebumprovementslan. Improv

ggested as a l

date 

RFIELD DEVE 

uilt and offers elsewhere ovement to thlong term im

ELOPMENT

rs adequate on the airporthe curbfronmprovement.

capacity thrrt campus ar

nt area for .

rough the 20re included ibetter flow

 

1‐11 

0-year in the

w and

Page 13: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐12 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

Adequate automobile parking for the planning period exists, though uses may need to shift to better balance use of existing facilities.

The terminal apron capacity can be easily expanded when future demand requires it by “squaring off” the existing apron, which will also improve the useable parking areas, compared to the aircraft circulation areas.

Initial changes to the gates and holdroom area are limited to expansion of the lower level

holding area and addition of a weather concourse at apron level to improve the level of service and capacity for ground loading.

Page 14: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐13 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

In the long term as additional gate capacity is needed, the concourse is expanded at the lower level parallel with the existing concourse. The floor level will be ramped up to approximately 4 feet above grade, allowing for loading bridges. The central atrium of the existing concourse will be reoriented for direct access to the lower level.

1.6.3  Terminal Building Interior 

The current terminal building size is nearly adequate for the 20-year planning period, however changes are needed to add space where uses increase (for instance baggage claim) or to repurpose existing areas for better utilization. The more immediate needs for the terminal address maintaining and improving the existing building to address changes in security and technology and to improve energy use and sustainability as it ages and systems need replacement.

Improvements to checked baggage inspection screening include construction of a remote building for explosive detection systems. Over time, this will include consolidation of airline operations to the west side of the terminal. Minimizing bag travel distances and centralizing equipment are key components of a functional and lowest cost system. The east side ticket lobby will be repurposed for other airport uses.

Page 15: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐14 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

The passenger security screening checkpoint (SSCP) area initial needs include addition of Advanced Image Technology equipment and more and better queing areas. At the outer years of the planning period, a fourth screening lane will be required to keep wait times within acceptable limits (10 minutes or less, 95% of the time) .

With changes to the SSCP, changes to the atrium area are needed. The ambiance of the

area will be enhanced and retained, while improving facilities for passenger queuing, meeter-greeter waiting area, food and beverage concessions, and relocating the information desk.

Page 16: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐15 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

In the later years of the planning period, replacements of the baggage claim devices and

expansion to add a fourth carousel are envisioned. Space should be reserved at the east end of the building to allow for this expansion.

 

 

The majority of terminal systems date back to the major renovation in the 1995-97 time period. As systems near the end of their useful life, they need to be replaced. In addition, there are more efficient lighting types, lighting controls, mechanical systems and controls that should be implemented. Recommendations for these system replacements and improvements are included as a part of the capital improvement program. This will also have the effect of lowering operating costs for the building.

 

Page 17: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐16 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

1.7  IMPLEMENTATION PLAN 

The CAE Master Plan Update sets forth a strategic financial plan (Implementation Plan) which provides for the financial implementation of the recommended improvements identified over a 20-year planning period. 1.7.1  Capital Improvement Program and Phasing 

The Airport Capital Improvement Program (ACIP) includes cost estimates and development phasing for the various projects identified within the Airport Layout Plan (ALP) drawing. The cost projections presented should be used for planning purposes only and do not imply that funding will necessarily be available. Each year indicates the initiation of design and/or environmental efforts and it is assumed that construction would be undertaken either in that same year or the following year. The following provides an overview of the capital improvements proposed for Columbia Metropolitan Airport (Proposed Projects) over a 20-year planning period (Development Period). 1.7.2  Funding Sources 

A detailed funding plan for the Proposed Projects was prepared with an emphasis on the Short-Term Development Period (0 to 5 years). Recommended projects were evaluated to determine eligibility for funding by the Federal Aviation Administration (FAA) Airport Improvement Program, Passenger Facility Charge Program, other funding sources, and Third Party/Tenant Financing. The local funding requirement and potential opportunities for satisfying the local share requirement were identified, including airport debt funding, cash flows, and airport reserves. Cost estimates were developed to determine the District’s ability to fund and implement the recommended development plan. An analysis assessing the financial implications of the District undertaking the Proposed Projects and the District’s ability to generate future revenues sufficient to exceed projected operating and capital expenses during the Short-Term Development Period were examined. Based upon forecast revenue and expenses and anticipated project costs, the airport has the financial capacity to undertake and complete the recommended development during the Short-Term Development Period. The proposed development, including public and private development, over the 20-year planning period is shown in the tables below.

Page 18: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐17 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

   

SHORT‐TERM FUNDING PLAN 

YEAR  PROJECT DESCRIPTION PROJECT COST 

FAA ENTITLEMENT 

FAA DISCRETIONARY 

STATE/ OTHER 

LOCAL TOTAL 

CASH  LOAN 

2011  Airport Pavement Management System  $250,000  $237,500  $0    $12,500    $250,000 

2011 Pitts Lake Stormwater Detention Pond Dam Reconstruction 

$557,948  $530,051  $0    $27,897    $557,948 

2011 Terminal Improvements ‐ Restroom / Elevators Renovation 

$1,163,500  $1,105,325  $0    $58,175    $1,163,500 

2011 Public Use Circulation Roads Rehabilitation – Design (Phase 1 of 2) 

$174,738  $166,001  $0    $8,737    $174,738 

2011 Airfield Signage and SMGCS Implementation – Design (Phase 1 of 2) 

$147,237  $139,875  $0    $7,362    $147,237 

2011 Runway 5 Safety Area Improvement – Design (Phase 1 of 2) 

$200,000  $190,000  $0    $10,000    $200,000 

2011  Runway 11‐29 AIP #38 Funds Transfer  $733,867  $697,174  $0    $36,693    $733,867 

Total 2011  $3,227,290  $3,065,926  $0  $0  $161,365  $0  $3,227,290 

2012 East Air Freight Apron Joint Sealing and Rehabilitation ‐ Design & Construction 

$510,340  $484,823  $0    $25,517    $510,340 

2012  Taxiway Rehabilitation ‐ Design & Construction  $1,700,000  $1,615,000  $0    $85,000    $1,700,000 

2012  Terminal Improvements Roof Rehabilitation  $500,000  $475,000  $0    $25,000    $500,000 

2012  Airport Perimeter Fence Upgrade  $575,000  $546,250  $0    $28,750    $575,000 

2012  1500 Gallon ARFF Truck Replacement  $600,000  $570,000  $0    $30,000    $600,000 

2012 Runway 5 Safety Area Improvement ‐ Construction 

$500,000  $475,000  $0    $25,000    $500,000 

2012 Airfield Signage and SMGCS Implementation ‐ Construction (Phase 2 of 2) 

$1,337,250  $570,388  $   

700,000   $66,863    $1,337,250 

Total 2012  $5,722,590  $4,736,461  $700,000  $0  $286,130  $0  $5,722,590 

Page 19: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐18 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

   

SHORT‐TERM FUNDING PLAN 

YEAR  PROJECT DESCRIPTION  PROJECT COST FAA 

ENTITLEMENT FAA 

DISCRETIONARY STATE/ OTHER 

LOCAL TOTAL 

CASH  LOAN 

2013 Public Use Circulation Roads Rehabilitation ‐ Construction (Phase 2 of 2) 

$1,800,000  $1,710,000   $0    $90,000    $1,800,000  

2013 Terminal Building‐ EDS (design reimbursement from work begun 2012) 

$300,000  $285,000   $0    $15,000    $300,000  

2013 Mechanical (items B,D,N Table 8‐4) and Security  (items 5,6 Table 8‐3) Renovations 

$1,062,000  $1,008,900   $0    $53,100    $1,062,000  

2013  ARFF Station ‐ Design  $350,000  $332,500   $0    $17,500    $350,000  

Total 2013  $3,512,000  $3,336,400   $0  $0  $175,600  $0  $3,512,000  

2014  Terminal Building Upgrades Mech / Electrical)  $550,000  $522,500   $0    $27,500    $550,000  

2014  Remote EDS ‐ Phase 1 (AIP / PFC) Construction  $2,650,000  $2,517,500   $0    $132,500    $2,650,000  

2014  Remote EDS‐ Phase 1 (TSA funded) Construction  $3,300,000    $0  $3,135,000  $165,000    $3,300,000  

2014 Taxiway U Widening and Lighting ‐ Design & Construction 

$3,100,000  $2,945,000   $0    $155,000    $3,100,000  

2014  ARFF Station ‐ Construction  $4,000,000    $3,800,000    $200,000    $4,000,000  

Total 2014  $13,600,000  $5,985,000   $3,800,000  $3,135,000  $680,000  $0  $13,600,000  

2015 West Cargo and Terminal Apron Joint Sealing/Rehabilitation 

$750,000  $712,500   $0    $37,500    $750,000  

2015  Taxiway "S" Rehabilitation ‐ Design  $750,000  $712,500   $0    $37,500    $750,000  

2015 Airfield Drainage Rehabilitation ‐ Design & Construction 

$1,075,000  $1,021,250   $0    $53,750    $1,075,000  

2015 Runway 5‐23 Centerline Lighting Project 

 $   1,000,000 

$950,000   $0    $50,000    $1,000,000  

Total 2015  $3,575,000  $3,396,250   $0  $0  $178,750  $0  $3,575,000  

               

Total Short‐Term Projects  $29,636,880  $20,520,036   $4,500,000  $3,135,000  $1,481,844  $0  $29,636,880  

Percent of Total    69.2%  15.2%  10.6%  5.0%     

*TSA eligible portion of project includes Baggage handling and upfit of the screening room and support facility 

Source: ADCI and THE LPA GROUP INCORPORATED, 2011. Note: These are order‐of‐magnitude cost estimates for planning purposes only.   

Page 20: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐19 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

   

INTERMEDIATE‐TERM PROJECTS FUNDING PLAN 

YEAR  PROJECT DESCRIPTION PROJECT COST 

FAA ENTITLEMENT 

FAA DISCRETIONARY 

STATE/ OTHER 

LOCAL TOTAL 

CASH  LOAN 

Intermediate‐Term Development 

I‐1  T/W Shoulders Construction Project  $3,500,000  $1,662,500   $1,662,500    $175,000    $3,500,000 

I‐2  Loop Road Rehabilitation Project  $100,000  $95,000       $5,000    $100,000 

I‐3 Mechanical (Items P,R Table 8‐4) and Security  (Items 4 Table 8‐3) Renovations 

$430,000  $408,500   Non‐eligible    $21,500    $430,000 

I‐4  SSCP and Atrium Concessions Renovations  $1,530,000  $1,147,500   Non‐eligible    $382,500    $1,530,000 

I‐5  Mechanical (Items I and L, Table 1‐4)  $900,000  $855,000   Non‐eligible    $45,000    $900,000 

I‐6  Airfield Pavement Rehabilitation Projects  $5,000,000  $497,250   $4,252,750    $250,000    $5,000,000 

I‐7  Special Systems Renovations (Items 1,2,3,7‐Table 8‐3)  $1,875,000  $1,781,250   Non‐eligible    $93,750    $1,875,000 

I‐8 Apron Expansions and Taxiway Shoulder Improvements 

$3,000,000  $1,425,000   $1,425,000    $150,000    $1,575,000 

I‐9  Mechanical Renovations (Items L,M‐ Table 8‐4)  $2,195,000  $2,085,250   Non‐eligible    $109,750    $2,195,000 

I‐10 Mechanical & Electrical Renovations  (Items A,C,E,F,G,H,J,K,Q, and S Table 8‐4) 

$1,785,000  $1,695,750   Non‐eligible    $89,250    $1,785,000 

I‐11  Electrical Renovations (Item O‐ Table 8‐4)  $1,610,000  $1,529,500   Non‐eligible    $80,500    $1,610,000 

I‐12  Lower Level Holdroom Expansion  $4,350,000  $4,132,500   Non‐eligible    $217,500    $4,350,000 

I‐13  Roof Replacement and Skylight Renovations  $2,000,000  $1,900,000       $100,000    $2,000,000 

I‐14  EA for Runway 11 Extension  $300,000  $285,000       $15,000    $300,000 

Total Intermediate‐Term Development  $28,575,000  $19,500,000   $7,340,250  $0  $1,719,750  $0  $28,575,000 

Source: ADCI and THE LPA GROUP INCORPORATED, 2011. Note: These are order‐of‐magnitude cost estimates for planning purposes only.   

Page 21: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐20 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

 

LONG‐TERM PROJECTS FUNDING PLAN 

YEAR  PROJECT DESCRIPTION PROJECT COST 

FAA ENTITLEMENT 

FAA DISCRETIONARY 

STATE/ OTHER 

LOCAL TOTAL 

CASH  LOAN 

Long‐Term Development 

L‐1  Baggage Claim ‐ Replace Existing Claim Conveyors  $1,230,000  $1,168,500   Non‐eligible    $61,500    $1,230,000 

L‐2  Runway 11 Extension (with Tunnel)  $77,500,000    $   

73,625,000   $3,875,000    $77,500,000 

L‐3  Remote EDS, Phase 2 and Curbfront Renovations  $4,650,000  $4,417,500   Non‐eligible    $232,500    $4,650,000 

L‐4  CUPPS / CUSS Implementation  $1,100,000  $1,045,000   Non‐eligible    $55,000    $1,100,000 

L‐5  Runway 5 Extension  $18,500,000    $   

17,575,000   $925,000    $18,500,000 

L‐6  Taxiway U Extension and Compass Calibration Pad  $7,100,000    $   

6,745,000   $355,000    $7,100,000 

L‐7  General Aviation Development  $43,400,000      $43.4M      $43,400,000 

L‐8  Taxiway U Construction and Cargo Apron Expansion  $36,600,000    $   

34,770,000   $1,830,000    $36,600,000 

L‐9 Long Term Holding Expansion ‐ Gates and Apron ‐ Alternate 3 

$20,070,000  $19,066,500   Non‐eligible    $1,003,500    $20,070,000 

L‐10  Baggage Claim expansion ‐ Alternate 1  $4,800,000  $4,560,000   Non‐eligible    $240,000    $4,800,000 

L‐11  Taxiway L Construction  $24,300,000  $3,000,000   $   

20,085,000   $1,215,000    $24,300,000 

L‐12  Taxiway L Extension  $14,600,000  $8,742,500   $   

5,127,500   $730,000    $14,600,000 

Total Long‐Term Development  $253,850,000  $42,000,000   $157,927,500  $43.4M  $10,522,500  $0  $253,850,000 

Total Intermediate and Long‐Term Development  $282,425,000  $61,500,000   $165,267,750  $43.4M  $12,242,250  $0  $282,425,000 

Percent of Total    21.8%  58.5%  15.4%  4.3%     

Source: ADCI and THE LPA GROUP INCORPORATED, 2011. Note: These are order‐of‐magnitude cost estimates for planning purposes only.   

Page 22: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐21 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

1.8  SUMMARY 

The FAA recognizes the long term potential of CAE to be a major asset in the national aviation transportation system. This Master Plan Update balances needed airport improvements with the goals of the RLAD and the community thus providing a consensus on how to best meet future demand and build upon the potential that has been revealed over the years. The planning process using extensive coordination, technical evaluations and community participation creates a framework for responsible, exciting and effective development of Columbia Metropolitan Airport as a regional and national asset.  

Page 23: CAE Chapter 1 - XSUM - FINALCHAPTER 1 EXECUTIVE SUMMARY 1.1 BACKGROUND 1.1.1 Introduction In 2003, the Richland Lexington Airport District (RLAD) Commission completed an initial well-articulated

 

1‐22 Columbia Metropolitan Airport Master Plan Update 

Executive Summary 

THIS PAGE IS INTENTIONALLY LEFT BLANK.