    Slide 1 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Gernot Beer,

    Professor, Graz University of Technology, Austria

    conjoint Professor, University of Newcastle, Australia

    Slide 2 of 51

    1. Why tunnels ?

    2. Large tunneling projects in LA

    3. Agua Negra tunnel project

    4. State of the art of tunneling technologies

    5. Emerging and Future technologies

    6. Summary and conclusions

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 3 of 51

    The trans European traffic network

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

  • 7/27/2019 CACBeer Tunnels

    2/17

    28.07.2012

    2

    Slide 4 of 51

    Paso Libertadores

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    4 Million tons/year !!

    Slide 5 of 51

    Paso Libertadores

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Shut down inwinter5000 !! trucksstranded

    High economic cost, CO2 emissions

    Slide 6 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    1. Los Olmos, Water tunnel, Peru, 20 km, US $ 247 M, completed2. Bioceanico Aconcagua: Railway tunnel, 54 km long base tunnel, cost US$ 4 Billion3. Agua Negra: Road tunnel, 14 km, cost US$ 800 M

  • 7/27/2019 CACBeer Tunnels

    3/17

    28.07.2012

    3

    Slide 7 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    High mountainpass,Gravel road,Open only for 3-4months/year

    Slide 8 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Planned tunnel

    Slide 9 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

  • 7/27/2019 CACBeer Tunnels

    4/17

    28.07.2012

    4

    Slide 10 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 11 of 51

    Conventional Tunneling Method

    (New Austrian Tunneling Method, NATM)

    Tunnel Boring Machine (TBM)

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 12 of 51

    Tunnel Boring Machine (TBM)

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Advantages:Fast advance rates (if all goes well)Segments can be the final liningEconomic (if all goes well)Disadvantages:High initial cost (Tailor made TBM for project)Problems with changing geological conditionsNeed a plant for production of segmentsOnly circular cross-section possible

  • 7/27/2019 CACBeer Tunnels

    5/17

    28.07.2012

    5

    Slide 13 of 51

    Conventional tunneling (NATM)

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Advantages:Flexible, can be adjusted to geological conditionsAny cross-section possibleLow initial costDisadvantages:Lower advance rates than TBM (if all goes well with TBM)Need to construct final lining

    Slide 14 of 51

    Experiences with TBM in Andean region:

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    The use of TBM in the Andes has been of mixedsuccess with world records of progress as well asnearly un-completed projects with machines beingabandonedD. Brox and G. Venturini, Rapid Tunnelling Conference , 2009

    Slide 15 of 51

    Geological conditions in Andean region:

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    The Andes are a relatively young geologicalenvironment with highly variable rock conditions,highly altered and extremely strong and abrasiveandesites. The rocks are extremely folded and faultedin some areasD. Brox and G. Venturini, Rapid Tunnelling Conference , 2009

  • 7/27/2019 CACBeer Tunnels

    6/17

    28.07.2012

    6

    Slide 16 of 51

    Weakness of TBM:

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Abrasive rocks (excessive tool wear)Faults (TBM gets stuck)

    Source: Nick Barton

    Slide 17 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    TBMs are most appropriately applied inhomogeneous rock conditions .. D. Brox and G. Venturini, Rapid Tunnelling Conference , 2009

    Slide 18 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Source: D. Brox and G. Venturini, Rapid Tunnelling Conference , 2009

  • 7/27/2019 CACBeer Tunnels

    7/17

    28.07.2012

    7

    Slide 19 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    1. Results from EC Project TUNCONSTRUCT2. New Developments of TBM technology in Brazil

    Slide 20 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    34 RTD partners + 7 clients

    Budget: 26 M Euros

    Start: 1.9.2005

    End: 30.11.2009

    Slide 21 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Use of virtual reality andinteractive tools

  • 7/27/2019 CACBeer Tunnels

    8/17

    28.07.2012

    8

    Slide 22 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    User friendly simulation

    EKATE

    Slide 23 of 51

    User friendly simulation

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    FLAC3D (500 000 Elements) BEFE++ (5 000 Elements)

    Slide 24 of 51

    User friendly simulation

    Example: Hudson river crossing Simulation, CAD Data

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

  • 7/27/2019 CACBeer Tunnels

    9/17

    28.07.2012

    9

    Slide 25 of 51

    User friendly simulation

    Example: Hudson river crossing Simulation, Mesh

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 26 of 51

    User friendly simulation

    Example: Hudson river crossing Simulation, Results

    2012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 27 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Koralm tunnel, Austria

  • 7/27/2019 CACBeer Tunnels

    10/17

    28.07.2012

    10

    Slide 28 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 29 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Monitored disk cutters

    Slide 30 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Monitored disk cutters

    Results:

    Display of actual disc cutter load

    Display of rotation speed

    Mapping of geological faceconditions

  • 7/27/2019 CACBeer Tunnels

    11/17

    28.07.2012

    11

    Slide 31 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Monitored disk cutters

    Slide 32 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Underground Construction Information System

    Slide 33 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Underground Construction Information System

  • 7/27/2019 CACBeer Tunnels

    12/17

    28.07.2012

    12

    Slide 34 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Underground Construction Information System

    Slide 35 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Underground Construction Information System

    Slide 36 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Underground Construction Information System

    DisplacementsShotcrete thickness

    Bolt forces

  • 7/27/2019 CACBeer Tunnels

    13/17

    28.07.2012

    13

    Slide 37 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Underground Construction Information System

    Slide 38 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Slide 39 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

  • 7/27/2019 CACBeer Tunnels

    14/17

    28.07.2012

    14

    Slide 40 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Innovations in use:

    Underground information system Monitored disc cutters Innovations being transferred to industry:

    Numerical simulation (Hudson river crossing, Koralm) ..Innovations still needing further development

    Virtual reality TBM technology

    Slide 41 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    www.tunconstruct.org

    Slide 42 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Disadvantages of TBM:High initial cost (Tailor made TBM for project)Problems with changing geological conditionsAbrasive rockNeed a plant for production of segmentsOnly circular cross-section possible

  • 7/27/2019 CACBeer Tunnels

    15/17

    28.07.2012

    15

    Slide 43 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Brute force !!

    Slides courtesy of Prof.Marcos NoronhaFlorianopolis, Brazil

    Slide 44 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Tailor made machinesHigh initial cost !!

    Slide 45 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    High maintenance costs !!

  • 7/27/2019 CACBeer Tunnels

    16/17

    28.07.2012

    16

    Slide 46 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Current technology

    Slide 47 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Future technology

    Slide 48 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Water jet

  • 7/27/2019 CACBeer Tunnels

    17/17

    28.07.2012

    17

    Slide 49 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Extruded lining superfast setting concrete engineered material

    Slide 50 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    Advantages:Flexible, can be adjusted to geologicalconditionsAny cross-section possibleReusable

    Can be used in abrasive rockHigh advance ratesNo need for concrete segment plant

    Slide 51 of 512012 Congreso Andino de Carreteras , Lima 20.- 22.8.2012.

    State of development:Research grant approvedLab for prototype testing nearing completionPrototype testing completed in 3 years