C51 RESERVOIR PROJECT UPDATEDesign, Permitting and CoordinationNOVEMBER 10, 2014
![Page 2: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/2.jpg)
C51 RESERVOIR
LOCATION
![Page 3: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/3.jpg)
C-51 Reservoir Benefits► Existing rock mine with unique
geological features
► Location is ideally suited for a multitude of water resource benefits
► Utilizes existing infrastructure for conveyance with some improvements
![Page 4: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/4.jpg)
Augmenting existing water suppliesImproving flood control in western Palm
Beach CountyEnhancing water quality protection for
the EvergladesReducing harmful discharges to Lake
Worth LagoonMitigating saltwater intrusionProtecting against droughtMitigating climate change impacts
C-51 Reservoir Benefits
![Page 5: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/5.jpg)
The project could be eligible for a long-term permit (S. 373.236(5), F.S. and as a Preferred Water Source (S. 373.2234 F.S.)
As a multi-jurisdictional project, it is expected that the C-51 Project would rank highly for alternative water supply funding under the "Water Protection and Sustainability Program" (S. 403.890, F.S.)
Potential for permit modifications vs. a new permit
C-51 Reservoir Benefits
![Page 6: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/6.jpg)
C-51 Reservoir
Operations
3
Cell 9, 10
Cell 11Cell 12
Cell 13Cell 14
Cell 16
Cell 18
C51 Phase 2 Area
C51 Phase 1 Area
L8 FEB
Cell5
Cell1+2
Cell4
Cell3
Cell7
Cell6
L8 Pump Station
L8 Inflow Gate Structure
L8 Canal
Southern Blvd
L8/C51 Connection
L8 C
anal
FPL Electrical Generation Plant
L8 Flow Direction
C51 Reservoir
L8 FEB
![Page 7: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/7.jpg)
Consistency with CERP/ Regional Availability/ Restoration Strategies
SFWMD
![Page 8: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/8.jpg)
C-51 Reservoir Sources
L8 excess/M1 Basin
Consistency with CERP/Regional Availability/Restoration Strategies
![Page 9: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/9.jpg)
1965
C51 RESERVOIR
![Page 10: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/10.jpg)
C51 RESERVOIR
![Page 11: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/11.jpg)
C51 RESERVOIR
![Page 12: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/12.jpg)
C51 RESERVOIR
![Page 13: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/13.jpg)
CONVEYANCE
C-51 Reservoir
![Page 14: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/14.jpg)
C51 RESERVOIR
![Page 15: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/15.jpg)
C51 RESERVOIR
![Page 16: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/16.jpg)
C51 Reservoir Status Design
Reservoir – Complete L8 Reservoir Connection and
Control Structure – Complete Pump Station – Preliminary
design criteria being established
Broward County Pump Station – Locations being researched
Stormwater Retention Area – Design 99%. 100% pending SFWMD Permit review.
![Page 17: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/17.jpg)
C51 Reservoir Status
PermittingERP – ReceivedCUP – Submitted and RAI receivedResponse is being prepared
RAI requested identification of end users
Stormwater Retention Area – Application submitted, RAI received, response pending
![Page 18: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/18.jpg)
C51 Reservoir Status Construction
Pending Allocation Agreements and commitments from end users
Pending all permits Construction duration expected to take 24 months
after start
Target start date May 2015
![Page 19: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/19.jpg)
C-51 Reservoir CostsMWH Construction Cost June 2014 $106,782,7
93 Project Management/Fees
1,067,828 Engineering, design, permitting and CM
17,085,247 Interest during construction at 6%
7,785,249 Value at 12% of construction cost
12,813,935 LWDD projected initiation cost
350,000 LWDD canal user fee
380,160 Total $146,265,2
12
PBA Aggregates Estimate January 2013 - $150,500,000
![Page 20: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/20.jpg)
C-51 Reservoir Costs – Additional Items Since Estimates Coffer Dam
East Rip Rap placed in the wet Rip Rap volume and product change Guard Rail Boat Ramp C51 Top Off Pump Station Broward County Canal Pump Station Cost Escalation since May 2014
![Page 21: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/21.jpg)
C51 Reservoir Next Steps
Utility Letters of Intent MWH Estimate of Additional Items Conclude Reservoir Permitting Utility Demand Projections (updated &
extended) Utility Permitting Capacity Allocation Agreements Set Construction Start Date
![Page 22: C51 RESERVOIR PROJECT UPDATE Design, Permitting and Coordination NOVEMBER 10, 2014.](https://reader038.fdocuments.net/reader038/viewer/2022110206/56649cf75503460f949c7958/html5/thumbnails/22.jpg)
Questions