Business Process Procedure for standard third party sales
By Gopal Reddy, Wyvil Systems Inc
1. Business Scenario
a. Business Process Steps
a. Create Third Party Sales Order (VA01) { Purchase requisition will be
automatically generated by the system due to the following configurations Theschedule line category for third party sales order is CS. For the schedule linecategory CS in Define schedule line category, the Order type is definedas NB which stands forpurchase requisition standard, Item category isdefined as 5 which is athird party item and Account AssignmentCategory is defined as 1 which stands forthird Party. This triggers thegeneration of purchase requisition automatically by the system.}
b. Create purchase order with reference to Purchase Requisition (ME21N)
c. Create Invoice Verification for Vendor (MIRO) w.r.t Purchase Order
d. Generate billing document to the customer (VF01) w.r.t 3 rd party sales order.
2. Inputs/Pre Requisitions
a. Organization Data
Sales organization 3000
Purchase Organization 3000
Distribution Channel01
Division 00
Plant 3000
Storage Location 0002
Ware house Number 001
b. Master Data
Material {Create a Trading Material (material type: HAWA), In Sales Organization
2 view assign Item Category Group as BANS, in MRP2 view make sure that the
procurement type is F External Procurement, there should be no warehouserelated views, assign MRP Type as ND No Planning Material Number usedin this document: 4540
Customer200193
-
7/28/2019 Business Process Procedure for 3rd Party ,
2/20
Vendor --- 400036 (need to create a Vendor if doesnt have)
Condition record for price, PR00 @100.00
c. SPRO Configurations
Define the item category { TAS Third party Item, Billing Relevance F Order
related Billing Doc- status according to invoice quantity}
Define Item Category Group{ BANSThird Party Item}
Assign item Categories { OR BANS TAS}
Define the Schedule line categories{ CS Leg, Order TYPE NB (Purchase
Requisition Standard), Item Category5 (Third Party), Account Assignment Cat1(Third- Party)}
Assign Schedule Line Category--- { TAS CS}
SPRO Configurations check for Third Party Sales
1. Configurations list for third party sales in SPRO settings
-
7/28/2019 Business Process Procedure for 3rd Party ,
3/20
2. Click on Define the item category and define TAS as Third party Item. Click on Display details
icon.
3. Check whether the Billing Relevance is defined as F {Order related Billing Doc- status according toinvoice quantity}. Click on logoff button.
4. Click on Define Item Category Group BANSThird Party Item. Click on Logoff icon
-
7/28/2019 Business Process Procedure for 3rd Party ,
4/20
5. Click on Assign item Categories and assign standard order type OR to third party item category groupBANS and item category TAS. Click on Logoff Icon
6. Click on Define the Schedule line categories and define the schedule line category as CS Leg
-
7/28/2019 Business Process Procedure for 3rd Party ,
5/20
7. Click on display details icon and define Order TYPE as NB (Purchase Requisition Standard), ItemCategory as 5 (Third Party), Account Assignment Cat as 1 (Third- Party)
8. Click on Assign Schedule Line Categories and assign item category TAS to schedule line category CS
-
7/28/2019 Business Process Procedure for 3rd Party ,
6/20
1. Create Material as trading goods and under sales organization 2 select the item category group asBANS.
2. Under MRP1 view, make sure to select MRP type is selected as ND-> no planning.
-
7/28/2019 Business Process Procedure for 3rd Party ,
7/20
3. Under MRP 2, make sure procurement type is selected as F External Procurement.
Business Process Steps
-
7/28/2019 Business Process Procedure for 3rd Party ,
8/20
1. Create 3rd party sales Order (initial screen) T-Code VA01
2. Sales order overview screen. Enter the sold to party, material, quantity and storage location and hitenter.
3. Sales Order: Purchase Order Scheduling Screen. Click on continue
-
7/28/2019 Business Process Procedure for 3rd Party ,
9/20
4. Schedule line for the third party standard sales order
4. Pricing condition maintained for the material
-
7/28/2019 Business Process Procedure for 3rd Party ,
10/20
5. Check for completion and save the document.
6. Enter TCode ME5A in the command bar and hit enter.
List of purchase requisitions screen. Enter material and plant
-
7/28/2019 Business Process Procedure for 3rd Party ,
11/20
7. Click on the purchase requisition number.
8. Purchase requisition for the standard third party sales order created. Double click on PR no to check thesource of supply and other details > Back.
9. Enter TCode ME21N in the command bar and enter.
Create purchase order w.r.t PR.
Click on the document overview screen at the top left corner of the screen.
Click on the variants icon and Select the purchase requisition and click on adopt icon under thedocument overview.
-
7/28/2019 Business Process Procedure for 3rd Party ,
12/20
10.Check the purchase Order tabs such invoice etc.. and save the document.
11.Enter MIRO in the command bar to create Invoice verification for vendor. Enter the company code and hitenter.
12.Enter the invoice date, amount, and at the item level, change the tax code to I0 (A/P sales tax exempt),and jurisdiction code to IL0000000 and click on Simulate.
13.Check the GL accounts.
-
7/28/2019 Business Process Procedure for 3rd Party ,
13/20
14. Click on Save/Post
15. Enter VF01 to create billing document for the customer and hit enter.
16. Overview of the billing items.
-
7/28/2019 Business Process Procedure for 3rd Party ,
14/20
17 Save the billing document
Document Flow of the Standard Third Party Sales Scenario
Third party sales processing does not work like that actually..
In fact, a third party sales processing is required because your company does not have the required
goods to sell to the customer, so that's why a third party vendor is required to supply (anddeliver/ship) the goods directly to your customer and then bill your company.
The standard process flow would work this way:
-
7/28/2019 Business Process Procedure for 3rd Party ,
15/20
Create Third Party Sales Order (VA01/VA03 - retrieve PR num)* --> Create Purchase Order (Display
list of PR with ME57 and convert to PO with ME58) --> Approval/Release of PO (if required - ME28)
--> Invoice Verification (MIRO)**
--> Billing (VF01/vf04)
The PR number is automatically created in this step.
**The incoming invoice from the vendor updates the billing quantity, so that the customer-billing
document can only be created after entering the invoice from the vendor.
So, in this situation, you do not carry out a MIGO in your company process.
Configuration:
1. Create your Account Assignment Category required for Purchasing.
2. Create your Item Categories for Purchasing Doc.
3. Assign to combination of the relevant Item Categories for Purchasing Doc.
4. Create your relevant 3rd Party Sales Doc Ty & Assign the Item Categories for SD.
5. Maintain the copy control for your Sales Doc (header & item).
6. Define and maintain your Transfer Requirement config - Define the Class --> Define the
Requirement --> Assign the Determination.
7. Maintain the SD Schedule Line Categories control - here u assign the Acct. Assignment Cat
similar to your Purchasing and determine the PR type you want to trigger (i.e. ZNB).
8. Assign the Schedule Line Categories to Item Categories.
9. Maintain copy control for Schedule Lines.
10. Configure your Billing Doc - it must be Order-related Billing.
11. Maintain copy control for Billing: i.e, OR --> F2 (if you did a Copy As.. function from the std SAP
docs, the copy control should already be in place).
As for the "Billing Quantity" indicator in the Billing Copy Control config - You can consider indicator
E, F and I for third party transactions, depending on the requirement of the your company.
Process Flow for 3rd Party Sales
Customize the third party sales in summary:
-
7/28/2019 Business Process Procedure for 3rd Party ,
16/20
1. Create Vendor XK01
2. Create Material Material Type as "Trading Goods". Item category group as
"BANS".
3. Assign Item Category TAS to Order type that you are going to use.
4. A sale order is created and when saved a PR is generated at the background
5. With reference to SO a PO is created (ME21N). The company raises PO to the
vendor.
6. Vendor delivers the goods and raises bill to company. MM receives the invoice
MIRO
7. Goods receipt MIGO
8. Goods issue
9. The item cat TAS or Schedule line cat CS is not relevant for delivery which is
evident from the config and, therefore, there is no delivery process attached in the
whole process of Third party sales.
10. Billing *-- Seema Dhar
SD - 3rd party sales order Create Sales Order
VA01
Order Type
Sales org, distr chnl, div
Enter
Sold to
PO #
Material
Quantity
EnterSave
SD - 3rd party sales order View the PR that is created with a third party sales
order
VA01
Order Number
-
7/28/2019 Business Process Procedure for 3rd Party ,
17/20
Goto Item Overview
Item ->Schedule Item
SD - 3rd party sales order View the PR that is created
ME52N
Key in the PR numberSave
SD - 3rd party sales order Assign the PR to the vendor and create PO
ME57
Key in the PR number
Toggle the "Assigned Purchase Requisition"
Execute
Check the box next to the material
Assign Automatically button
Click on "Assignments" buttonClick on "Process assignment"
The "Process Assignment Create PO" box , enter
Drag the PR and drop in the shopping basket
Save
SD - 3rd party sales order Receive Goods
MIGO_GR
PO Number
DN Number
Batch tab , click on classification
Serial Numbers tab
Date of Production
Flag Item OK
Check, just in case
Post
Save
SD - 3rd party sales order Create Invoice
MIRO
Invoice Date
Look for the PO , state the vendor and the Material
Check the box
Clilck on "Copy"
Purchase Order Number (bottom half of the screen)
Amount
State the baseline date
-
7/28/2019 Business Process Procedure for 3rd Party ,
18/20
Simulate & Post
Invoice Number
*Invoice blocked due to date variance
SD - 3rd party sales order Create a delivery order
VL01NIn the order screen , go to the menu Sales Document , select "Deliver"
Go to "picking" tab
State the qty and save
SD - 3rd party sales order Create a billing document
VF01
Ensure that the delivery document is correct in the
Enter
Go to edit -> Log
Save
SAP SD Tips by: Liza Rao
Fast Links:
Re: credit management configuration in Third party sales
Anand NJul 20, 2011 9:27 AM (in response to S K)
Hi...For Third Party, since there is no Delivery and PGI, the block can be at Billing.however the total outstanding value from the customer at the time of billing along withthe days as set in the credit limit shall be basis of blocking.Config Steps:u2022 Assigned the credit control area to the company code
Assign Permitted Credit Control Area to Company Code Credit Control Account
Credit management Accounts Receivable and Accounts Payable Financial
Accounting (New)u2022 Assign Sale Document and Delivery Document, The credit limit check for theselected sales document type is set to automatic control.
http://scn.sap.com/message/10463287#10463287http://scn.sap.com/people/anand.navalehttp://scn.sap.com/thread/1998540#10458707http://scn.sap.com/people/anand.navalehttp://scn.sap.com/message/10463287#10463287http://scn.sap.com/people/anand.navalehttp://scn.sap.com/thread/1998540#10458707 -
7/28/2019 Business Process Procedure for 3rd Party ,
19/20
Credit limit check for order typesAssign Sales Documents and Delivery Document
Credit Management Credit management / Risk management Basic Functions
Sales and Distribution
u2022 Assigning Risk Category to Credit Control Area
Define Risk Categories Credit Control Account Credit management Accounts
Receivable and Account Payable Financial Accounting (New)
u2022 Defining Automatic Credit Control
Define Automatic Credit Control Integration with Sales and Distribution Integration
with Accounts Receivable Accounting and Sales and Distribution Credit Management
Financial Supply Chain Managemento Report Abuse
o Like (0)
o Reply
o Re: credit management configuration in Third party sales
SAP SDJul 20, 2011 9:32 AM (in response to Anand N)
Hi Anand,Credit Management is not possible to Block in Billing Level . It is possible in Sale order ,Delivery and PGI levelRegards,
Prasanna
Report Abuse
Like (0)
Reply
Re: credit management configuration in Third party sales
S KJan 16, 2012 6:31 PM (in response to S K)
Dear All,In Third Party Sales, Purchase Requisition and Purchase Order should not create when Isave Sale Order, When I release Order then only PR, PO should create.
http://scn.sap.com/message-abuse!input.jspa?objectID=10463287&objectType=2http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/message/10463316#10463316http://scn.sap.com/people/prasanna.kumar4http://scn.sap.com/thread/1998540#10463287http://scn.sap.com/message-abuse!input.jspa?objectID=10463316&objectType=2http://scn.sap.com/message-abuse!input.jspa?objectID=10463316&objectType=2http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/message/10994554#10994554http://scn.sap.com/people/sudarshan.khttp://scn.sap.com/thread/1998540#10458707http://scn.sap.com/people/sudarshan.khttp://scn.sap.com/people/prasanna.kumar4http://scn.sap.com/message-abuse!input.jspa?objectID=10463287&objectType=2http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/message/10463316#10463316http://scn.sap.com/people/prasanna.kumar4http://scn.sap.com/thread/1998540#10463287http://scn.sap.com/message-abuse!input.jspa?objectID=10463316&objectType=2http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/message/10994554#10994554http://scn.sap.com/people/sudarshan.khttp://scn.sap.com/thread/1998540#10458707 -
7/28/2019 Business Process Procedure for 3rd Party ,
20/20
Request you where is the configuration setting to block Purchase Requisition.RegardsKS
o Report Abuse
o Like (0)
o Reply
o Correct AnswerRe: credit management configuration in Thirdparty sales
Shiva RamJan 16, 2012 6:48 PM (in response to S K)
In t.code OVB8, maintain routine 102 under RNO column and then check again. Byadding this routine, when the sales order is in credit block, the system will not allowcreation of purchase req.Regards,
http://scn.sap.com/message-abuse!input.jspa?objectID=10994554&objectType=2http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/message/10994590#10994590http://scn.sap.com/message/10994590#10994590http://scn.sap.com/people/sivakumar.ramakrishnanhttp://scn.sap.com/thread/1998540#10994554http://scn.sap.com/people/sivakumar.ramakrishnanhttp://scn.sap.com/message-abuse!input.jspa?objectID=10994554&objectType=2http://scn.sap.com/thread/1998540http://scn.sap.com/thread/1998540http://scn.sap.com/message/10994590#10994590http://scn.sap.com/message/10994590#10994590http://scn.sap.com/people/sivakumar.ramakrishnanhttp://scn.sap.com/thread/1998540#10994554