Business Management of IT

download Business Management of IT

of 52

Transcript of Business Management of IT

  • 7/30/2019 Business Management of IT

    1/52

    Business Management oInormation TechnologyA practical guide or senior nance executives and business managers

    INFORMATION TECHNOLOGY & MANAGEMENT

  • 7/30/2019 Business Management of IT

    2/52

    CPA Australia Ltd (CPA Australia) is the sixth largest proessional accounting body in the world with more than 117,000

    members o the nancial, accounting and business proession in 98 countries, including Australia.For inormation about CPA Australia, visit our website: cpaaustralia.com.au

    First published 2008

    CPA Australia Ltd

    ABN 64 008 392 452

    385 Bourke Street

    Melbourne Vic 3000

    Australia

    ISBN 9281 876874 28 5

    Legal notice

    Copyright CPA Australia Ltd (ABN 64 008 392 452) (CPA Australia), 2008. All rights reserved.

    Save and except or third party content, all content in these materials is owned by or licensed to CPA Australia. All trademarks, service marks and trade names are proprietory to CPA Australia. For permission to reproduce any material, a request in

    writing is to be made to the Legal Business Unit, CPA Australia Ltd, 385 Bourke Street, Melbourne, Victoria 3000.

    CPA Australia has used reasonable care and skill in compiling the content o this material. However, CPA Australia and

    the editors make no warranty as to the accuracy or completeness o any inormation in these materials. No par t o these

    materials are intended to be advice, whether legal or proessional. Further, as laws change requently, you are advised to

    undertake your own research or to seek proessional advice to keep abreast o any reorms and developments in the law.

    To the extent permitted by applicable law, CPA Australia, its employees, agents and consultants exclude all liability or

    any loss or damage claims and expenses including but not limited to legal costs, indirect special or consequential loss or

    damage (including but not limited to, negligence) arising out o the inormation in the materials. Where any law prohibits

    the exclusion o such liability, CPA Australia limits its liability to the re-supply o the inormation.

  • 7/30/2019 Business Management of IT

    3/52

    i

    Chris Gillies is an independent non-executive director serving on a number o boards, associations and charities

    and advises boards on establishing IT governance leadership in the boardroom. Boards include Oakton, CorporateExpress, Asgard Wealth Solutions, Emergency Telecommunications Statutory Authority Victoria, UCMS,

    Commsecure and the MS Society o Australia. She has established and chairs three board IT committees, as well

    as advising a number o others. Prior to her board career, Chris was Group Executive, Group Services at St George

    Bank (where her role included managing the integration with Advance), Chie Inormation Oicer or the Bank o

    Melbourne, and Victorian Director o the DMR Group, an international IT consulting company, where she

    specialised in mergers and acquisitions and in designing and implementing major IT change programs. Chris has

    over 10 years experience as a company director and more than 35 years experience in business management and

    inormation technology.

    Advisory committee

    JanBarned - Policy adviser, inormation technology and management, CPA Australia.

    Jan has held a number o directorships and has over twenty years experience working or both listed and unlisted

    domestic and international companies. Her current role at CPA Australia includes identiying current and

    emerging issues on inormation technology and management and advocacy to government, industry membershipand the wider public.

    Mark Toomey - Managing Director, Inonomics Pty Ltd.

    Mark Toomey has more than thirty years experience in planning and delivering inormation communication technology

    solutions that enable business perormance. Since 2000, he has specialised in providing governance, management and

    strategic advice to business and IT executives, and company directors. Mark is a Fellow o the Australian Institute o

    Company Directors and is the Institutes representative on Standards Australias committee controlling the Australian

    Standards or Corporate Governance o Inormation and Communications Technology.

    Vicky Kelly

    Vicky Kelly has over 35 years experience in the IT industry and has worked or Bendigo Bank or the last 13 years. Vicky

    is a member o the Banks Executive, has assisted in the establishment o the Board o IT Governance Committee and is

    an attendee o that committee.

    Diana HolmbergA seasoned IT proessional, Diana Holmberg has more than 16 years experience in the industry as a CIO, business IT

    integration consultant, business IT strategist, program director, project manager and technology practitioner. She has

    extensive experience in identiying and implementing organisational and procedural change to ensure the alignment o

    IT delivery to business strategy and to improve IT delivery capabilities. Diana is also a non-executive director on the

    Board o Australian Home Care, ocusing on the implementation o eective IT governance.

    Peter Harrison, Principal, Fujitsu Consulting, Australia and New Zealand

    Peter is a FCPA and currently leads Fujitsu Consultings Australian and New Zealand Enterprise Value Management

    consulting practice that includes value governance, portolio management and benets realisation. He was a

    contributor to Fujitsu Consultings best-selling book authored by John Thorp, The Inormation Paradox Realising the

    Business Benets o Inormation Technology. Peter is a member o the ISACAs IT Governance Institutes Val IT Steering

    Committee that launched the Val IT Enterprise Value Governance Framework.

    JudyMcKay - Associate Proessor, Swinburne University o Technology

    Judy McKay is currently academic leader o the inormation systems group in the aculty o inormation andcommunication technologies at Swinburne University o Technology. She joined the sta at Swinburne in 2004 ater

    academic appointments in inormation systems at Monash University, Edith Cowan University and Curtin University o

    Technology. She has a Bachelor o Arts (majoring in linguistics) and postgraduate qualications in education, business

    and inormation systems.

    Gavan Ord, Business Policy Adviser, Policy and Research CPA Australia

    Gavan Ord is CPA Australias business policy adviser. Gavan has responsibility or the development o policy and

    research on issues related to small medium enterprises (SMEs), business management and climate change. During the

    course o his career, Gavan has established himsel as a technical expert particularly in the area o taxation. Beore

    joining CPA Australia, he held a senior role in technical policy and international development and was a member o

    various Australian government consultation committees, including the National Small Business Forum, the ATOs National

    Taxation Liaison Group, ATO Tax Practitioner Forum and Treasury Tax Design. Gavan holds a Master o Taxation Law.

    About the author

  • 7/30/2019 Business Management of IT

    4/52

    ii

    Special thanks to:

    Kate Behan: Managing Director Kerandan Pty LtdNeil Wilson: CEO Oakton Limited

    John Wadeson: CIO Centrelink

    Brett Armstrong: Financial Controller Symex Holdings Ltd

    Mike Tamblyn: CFO Westco Jeans Pty Ltd

    Alastair Stott: CEO Schmick Solutions

    Andrew Watts: CIO Bendigo Bank

    Marianne Rose: ERS Service Line Finance Controller Deloitte Touche Tohmatsu

    John Etherington: Principal Non Executive Management Pty Ltd

  • 7/30/2019 Business Management of IT

    5/52

    iii

    Most business managers would agree that Inormation Technology (IT) is now an integral part o commercial business.

    When used eciently and eectively, it can provide organisations with competitive advantage, prot growth andultimately optimal return to stakeholders. However, business managers oten are unsure i they are getting optimal

    value rom their IT-enabled assets. Are these assets aordable? Do they come with an acceptable level o risk?

    In many organisations, IT is perceived to have ailed when:

    projects are late

    business needs are not met

    IT is over budget

    benets are not delivered

    Business managers can eel powerless over the technology upon which they are dependent. This isnt a problem

    common to the other asset classes in a business such as property, plant, equipment, people, and product development.

    Why dont we manage our technology assets as we manage any other asset class?

    Organisations that clearly communicate governance and management processes or planning, delivering and assessing

    the value o IT across their business, increase the value o their investment in IT.

    This guide introduces proven practices that have evolved within these organisations. It ocuses on the business side o

    managing IT and is written or senior nance exectives and business managers who have signicant dependence on IT

    and who want to know what action they can take to have:

    IT processes that provide cost-eective support / services to the business

    projects delivered on time and on budget

    IT service levels that t the budget and risk prole o the company

    a good understanding o IT costs and cost drivers

    evidence o the business benets delivered by IT-enabled initiatives

    You will also nd a ramework or the Business Management o IT (BMIT) that looks at ways you can modiy your

    business planning and management cycle to incorporate ve key processes to ensure the business has a clear

    understanding o the role it must play in:

    IT alignment with business strategy and objectives

    estimation and prioritisation o business programs

    setting the IT budget and balancing the supply / demand equation

    program and project delivery

    benets realisation

    planning and delivery o IT services to agreed business requirements

    This guide builds on the CPA publication IT Governance:A Practical Guide or Company Directors and Business

    Executives which helps directors:

    understand what IT governance is and why it is important

    assess the level o attention directors should be paying to IT-related issues in the board room

    understand the business issues in planning, building, running, and managing IT

    ensure good IT governance is implemented across the enterprise

    Executive summary

  • 7/30/2019 Business Management of IT

    6/52

    iv

  • 7/30/2019 Business Management of IT

    7/52

    1

    1 What is BMIT and why is it so important?

    1.1 What is BMIT? 3

    1.2 Why is BMIT so important? 4

    1.3 Assessing the level o BMIT in your organisation 5

    2 The BMIT ramework and processes 8

    3 Foundations o successul BMIT 12

    3.1 Implement clear decision-making and accountability rameworks 12

    3.2 Promote common language between business and IT 13

    3.3 Build business IT relationships 14

    3.4 Improve transparency o IT costs 15

    3.5 Introduce business measurement o IT value 16

    3.6 Recognise that business programs, not IT projects, deliver business value 17

    4 Long term strategic planning 19

    4.1 Strategic IT demand management and long term strategic alignment 20

    4.2 The business o IT strategic plan 22

    5 Annual planning and budgeting 25

    5.1 Annual project and service level demand management and budget alignment 26

    5.2 Business program prioritisation and budget alignment 28

    5.3 Business prioritisation orum 28

    5.4 Service level planning and budget alignment 29

    6 Ongoing management 31

    6.1 Ongoing IT work prioritisation 31

    6.2 Business program or project gating 34

    6.3 Benets realisation and monitoring and asset decommissioning 36

    6.4 Asset lie monitoring, evaluation and decommissioning 41

    Appendix: useul reerence material 44

    Table of contents

  • 7/30/2019 Business Management of IT

    8/52

    2

    Annual plan and budget Sets out the nancial year objectives and the action plans and budgets designed

    to achieve these objectives.

    Architecture Architecture is the continuous planning and management regime used to

    organise and control the structure o business systems and IT inrastructure or

    sustained eective, ecient and acceptable support o enterprise business.

    BMIT Business Management o Inormation Technology (BMIT) is a ramework o

    business accountabilities and processes designed to enable business managers to

    better articulate their technology requirements and proactively plan, prioritise

    and monitor short and long term technology programs, ongoing service levels

    and benets realisation.

    Business case Documentation o the rationale or making a business investment. The business case

    is used to support the decision on whether or not to proceed with the investment.

    Business program A structured group o interdependent projects that are managed together todeliver a business outcome. IT is just one o these projects. Others may include

    business process redesign, customer communications and property t out.

    Governance Governance ensures that management has the accountabilities, processes, and

    auditable and measurable controls in place to ensure a company is on track to

    achieve its objectives. Governance is the responsibility o the board o directors

    and the executive management.

    IT Inormation Technology (IT) is the term applied to the combination o technology,

    processes and people that allow organisations to cost-eectively capture, store,

    process, communicate and analyse data and inormation fows internally or

    management and sta and externally or stakeholders including suppliers,

    customers, shareholders, and regulatory groups.

    IT demand pipeline Comprehensive list o the business requests requiring IT eort including large

    projects and small change requests covering all aspect o IT delivery (e.g. desktop

    change, new applications and changes to existing systems).

    Management Management is the process o controlling the activities required to achieve the

    strategic objectives set by the organisations governing body. Management is

    subject to the policy guidance and monitoring set through corporate governance.

    Pipeline / portolio management Tracking program selection, prioritisation and delivery against the required

    portolio and monitoring progress.

    Portolio The collection o planned business programs across all asset classes designed to

    deliver the business strategy and objectives.

    Project An organised eort to complete a specic dened deliverable or set odeliverables usually satisying one business case. A project has a specic start and end

    date, specic objectives, specic resources assigned to perorm the work and a

    specic budget.

    Strategy An organisations overall plan o development describing the eective use o

    resources in support o the organisation in its uture activities. It involves setting

    objectives and proposing initiatives or action.

    Glossary

  • 7/30/2019 Business Management of IT

    9/52

  • 7/30/2019 Business Management of IT

    10/52

    4

    1.2 Why is BMIT so important?

    Despite the alling unit cost o technology, business statistics generally show that the proportion o expenditure on

    inormation technology continues to rise. In many organisations, the IT capital spend is well over 50 per cent o the

    average annual total capital investment. As IT becomes more important and pervasive, business managers are

    increasingly challenged to get more value out o their IT investment. Unortunately, ailure o IT-enabled change is

    still a common problem and increasingly associated with lost revenue, lost opportunity, lost customers and, in some

    cases, lost companies.

    There are three key root causes that continually arise when assessing why IT-enabled business programs ail or why IT is

    not delivering to business service levels:

    lack o business planning or IT

    lack o accountability and clarity as to who makes decisions about what

    ocus is on IT projects rather than business change programs

    Lack o business planning or IT means that any planning around the development and use o the companys

    technology assets is done by IT and relies entirely on the planning capability and experience o the IT management and

    its view o what the business requires. Small companies with limited resources may rely on technologists with little

    business planning experience or capability. Or they may rely on business proessionals such as accountants who are

    being expected to take responsibility with little expertise or knowledge o how to make sound plans and decisions with

    respect to IT.

    Additional implications o a lack o business planning:

    Long term plans are not connected to business strategies and objectives and the dollar investment over time

    is not understood.

    What IT does is being determined by the annual budget process and the dollars the business is prepared to

    spend, rather than being the result o dened business plans and requirements.

    IT ends up setting priorities across competing business divisions.

    The ocus is on the technology solution and estimates ail to include the associated business costs such as

    process change.

    IT goes into react mode leading to complex and dicult-to-support IT environments delivering inconsistent service.

    IT plans must be a subset o business plans and ormed collaboratively as a result o business strategy and plans.

    Lack o accountability and clarity as to who makes decisions about what has three ar reaching consequences:

    Large investments result in ailure because business users are not clear about what they want.

    Systems ail because business managers dont make the decision on the level o risk it is prepared to carry.

    Business programs go over time and over budget due to continual change o scope as no one business

    person has accountability or the nal decision on scope.

    Benets are not delivered because accountability or realisation is not clear.

    When accountabilities and decision-making responsibilities are clear, there are important outcomes:

    the right people make decisions

    decisions get made because the need or the decisions is clear

    more oten than not, the right decisions are made

    Successul delivery o IT-enabled change, value delivery and sustainable service can only be achieved through a well-

    dened relationship between business and IT, both understanding who makes decisions about what and the

    interdependencies involved in the decision-making process.

    What is BMIT and why is it so important?

  • 7/30/2019 Business Management of IT

    11/52

    5

    Focus on IT projects rather than business programs can result in:

    IT delivering an IT solution that business is not prepared or or IT delivering a solution that ails to address

    the business objectives

    Business management not being involved in developing the solution and underestimating (or not

    recognising) the resources relating to people, process and organisational change.

    The good news is that the solutions required to deal with these undamental causes o ailed IT-enabled business

    programs lie with business management taking accountability or the decisions that must be made by business (not IT)

    to aect successul planning, building / acquiring and management o IT assets.

    With very little eort, business management can take an active and inormed role in managing the IT assets o their

    company. Introducing BMIT processes into the standard business planning and management cycle helps to demystiy IT,

    highlights the risks the business may be acing without knowledge, and gives business managers a basis or inormed

    decisions. Adopting these processes inorms business managers and enables them to be active participants rather than

    powerless onlookers.

    1.3 Assessing the level o BMIT in your organisation

    Most business managers agree that they are keenly aware o ITs importance to the business. However, most eel they

    have very little say in what is delivered by IT and have little idea o the business benets delivered. As a quick test, ll in

    these questionnaires to assess the importance o IT in your organisation and your current BMIT capability.

    1.3.1 Do you have a clear understanding o the business use o IT?

    The ollowing table can help you reocus your expectations o IT in your organisation. Are you sure that your use o IT

    is aligned with business expectation? For example, you may expect IT to increase revenue but in act all IT investment is

    aimed at lowering cost.

    Why are we using IT? Now Future

    To increase revenues

    To lower costs

    To increase productivity

    To open up new lines o business and new markets, and extend geographic reach

    To keep up with the competition

    To add value to existing products and services

    To get ahead o the competition

    For nance and administration systems

    For innovative purposes e.g. research and development

    Table 1.3.1.1 Business use o IT

    What is BMIT and why is it so important?

  • 7/30/2019 Business Management of IT

    12/52

    6

    1.3.2 Do you know how much you spend?

    Make sure that the IT spend rom all business unit cost centres is included, not just the IT department. You may besurprised at how much you are spending. Use the ollowing table as a guide.

    This yearPrevious

    year 1

    Previous

    year 2

    A Total company revenue

    B Total company expenditure

    C Total IT spend (expensed)

    D Total IT spend (capitalised)

    Total IT spend (C+D) as a % o revenue (A)

    Total IT spend (C+D) as a % o expenditure (B)

    E IT spend on keeping current systems running (KIR)

    F IT spend on projects (including capitalised $)

    G Total IT spend (C+D)

    IT KIR spend (E) as a % o total company revenue (A)

    IT KIR spend (E) as a % o total company expenditure (B)

    IT KIR spend (C+D) as a % o total IT spend (G)

    % o IT spend sourced internally

    % o IT spend sourced rom external suppliers

    Total IT spend within the IT department budget

    Total IT spend across all other cost centres

    Table 1.3.2.1 Total IT spend

    1.3.3 How dependent are you on IT?

    How long would you be able to do business when aced with severe disruption to your business? Enter your estimate

    in the boxes below and make your own assessment.

    Hours Days Weeks Months

    Finance, MIS, HR, Email

    Product Service

    Customer Facing

    Supplier Facing

    Table 1.3.3.1 Dependence on IT

    What is BMIT and why is it so important?

  • 7/30/2019 Business Management of IT

    13/52

    7

    1.3.4 How well do you plan and manage the use o technology?

    How well do you plan and manage the use o IT in your business? Complete the table below. I you answer no to

    more than our o these questions, then your attention to IT is inadequate and it is highly likely IT will not be delivering

    to your requirements.

    Assessment No Yes

    Does business management make the IT investment decisions?

    Does business management consider the business use o IT when preparing business strategy?

    Does the board and executive team determine the level o IT risk the company is prepared to take (e.g.

    disaster recovery capability)?

    Does business management know where the company will be investing in IT in the next 12 months?

    Are long term IT capital spend requirements known and understood?

    Are the implications o under-investment in IT known and understood?

    Is the IT budget based on long term business plans and short term business demand?

    Is there a business orum or prioritising the IT department projects and work?

    Is a clear, compelling business case always developed beore an IT investment decision is made?

    Are business IT program risks ully understood beore program commencement?

    Are IT projects managed as part o the business programs comprising all aspects o the change?

    Are there control points in your business programs where you reconrm that the programs are still

    viable?

    Is business management held accountable or the delivery o business benets rom IT investments?

    Does business management decide whether to buy a package or build rom scratch?

    Are IT running costs clearly related to business services level requirements, recognising the cost, risk,

    perormance trade-os?

    Does business management have measures on unit cost o IT ongoing operations?

    Does business management understand what is driving ongoing IT running costs?

    Does business management have measures to assess IT success?

    Does business management have measures to assess IT risk?

    Is there a process in place to help business management make decisions on IT application asset

    replacement?

    Table 1.3.4.1 Assessment o IT

    Good BMIT creates a collaborative relationship between the business and IT where both have processes, controls

    and accountabilities. It ensures that:

    the business knows what to ask or, how to ask or it and how to monitor and assess success

    IT knows how to build / acquire solutions, advise and deliver to business expectations

    What is BMIT and why is it so important?

  • 7/30/2019 Business Management of IT

    14/52

    8

    2. The BMIT ramework and processes

    Figure 2.0 BMIT ramework

    BUSINESSPLANNING

    ANDMANAGEMENTCYC

    LE

    BUSINESS MANAGEMENT OF IT IT MANAGEMENT OF IT

    BusinessProcess

    BusinessDecisions

    ITDecisions

    BusinessFramework

    Long term

    strategic planning

    Strategic IT demand

    management and

    long term strategicalignment process

    sstrategic use of IT

    s levels of investmentvalue expected

    sPRiority

    sRisk

    What we aim toachieve

    s3Olutions

    sArchitectures

    sCosts and risks

    s Technology

    opportunities

    Annual planning

    and budgeting

    Annual project and

    service level

    demand

    management and

    IT budget

    alignment process

    sProjectssservicesPERFORMANcesMEAsuressFUNDssPRiority

    How we willachieve

    sCost estimates

    s Performancecapability

    s2isks

    Business IT strategic plan

    Pipeline / portfolio of strategic initiatives

    Business and IT business plans and budgets

    Prioritised pipelines / portfolio of business programs and projects

    Agreed business service level agreements

    Ongoing

    management

    Ongoing IT workprioritisation process

    Business program orproject gatingprocess

    Benefits realisationand monitoringand asset

    decommissioningprocess

    Building oracquiring new

    capability

    s Deliver toestimates

    sAdvise on risk

    Completed business programs

    Expected benefits and measures

    s Deliver theservice

    sAdvise on risk

    Delivering theresults

    sUse the servicesrealise the value

    sMEAsure the result

    sProcess

    schange

    svalue

    sBENEFits

    The BMIT ramework (Figure 2.0) is built into the standard business planning and management cycle, incorporating long

    term strategic planning through to ongoing operations. The ramework clearly dierentiates between theaccountabilities associated with Business Management o IT and the IT management o IT. It illustrates the interaction

    that needs to take place between business and technology to deliver the companys objectives.

  • 7/30/2019 Business Management of IT

    15/52

    9

    The ve BMIT processes (Figure 2.1) in the ramework support business management in making the right decisions or

    eective use o IT. They help business managers understand and measure the delivery o value rom IT assets and canbe tailored to suit company requirements.

    The processes must be supported by oundation behaviours and practices that oster collaboration and constructive

    interaction between business managers and IT managers.

    In section 3, the oundations that will enable this change are examined, with a ocus on why the ollowing are so

    important:

    implementing clear accountability and decision making rameworks

    promoting common language between business and IT

    building business IT relationships

    ensuring transparency o IT costs

    introducing business measurement o IT value

    recognising that business programs deliver business value not IT projects.

    In section 4, the criticality o including IT in longer term business strategic planning is discussed. The decision making

    accountabilities and interactions between business and IT are set out under the longer term planning ramework and

    the BMIT Process 1 Strategic IT demand management and long term strategic alignment.

    The BMIT process or annual planning and budgeting is reviewed in section 5. BMIT Process 2 Annual project and

    service level demand management and IT budget alignment - shows how the longer term strategic portolio o

    business programs is translated into annual plans and the decision making accountabilities and interactions, which

    must occur between business and IT when developing annual business and IT plans and budgets.

    Section 6 looks at the last three BMIT processes. Topics discussed are: the ongoing operations ramework; the common

    issues around building and/or acquiring new systems; delivering results and service level monitoring; and asset lie

    monitoring, evaluation and decommissioning. Each is captured under the BMIT Process 3 Ongoing IT workprioritization, BMIT Process 4 Business program or project gating and BMIT Process 5 Benets monitoring and

    realisation.

    The BMIT framework and processes

  • 7/30/2019 Business Management of IT

    16/52

    10

    The BMIT framework and processes

    Business Framework The Business Question Five BMIT Processes Business management will know:

    Long term

    strategic planning

    How is the businessgoing to use IT inattaining its goals?

    1. Strategic IT demandmanagement andlong term strategicalignment process

    the long term capital spendrequired to deliver the companysstrategythat IT action is aligned withbusiness strategythe connection between achievinglong term strategic objectives andIT eortthe long term priorities anddependenciesthe risk associated with reducingcapital spend

    Annual planning

    and budgeting

    What is the businessgoing to spend on ITthis year to keep itrunning and todeliver or theuture?

    2. Annual projectand service leveldemandmanagement andIT budgetalignment process

    that the IT build / acquire budgetis aligned with business demandwhich projects are unded thisnancial year along withguesstimates o the operationaland capital spendthat the Keep IT Running (KIR)budget is aligned with businessservice expectationthe risks associated with cuttingthe KIR budgetthe annual priorities anddependencies

    Ongoing

    management

    Are we working onthe right things orthe right reasons andproducing theintended results?

    Are we on track tomeet ourperormance goals?

    3. Ongoing IT workprioritisationprocess

    4. Building /acquiringcapability andbusiness programor project gating

    process

    5. Benets realisationand monitoring andassetdecommissioningprocess

    that IT eort is ocused on whatthe business requires

    that conficting business demands are resolved in line with thecompanys overall intereststhat immediate businessimperatives are delivered with theleast impact on long term plans

    that projects which are no longerviable or appropriate areterminated promptlyi dollars and eort spent anddollars to complete are in line withbudgethow scope change decisions havebeen made and what impacts thiswill have on costs and time

    the delivery and implementationrisk prole

    the service level delivery metricsand ongoing service risk prolewhen to make application andinrastructure asset replacementdecisionsi the planned benets are beingdelivered in line with the businesscasethe IT investment spent onreducing IT operating costs versusnew capability

    Figure 2.1 The ve BMIT processes

  • 7/30/2019 Business Management of IT

    17/52

    11

    Figure 2.2 The BMIT process fow

    Managing IT costs and investment through the IT budget alone can drive the wrong behaviours

    SELLCO recognised that technology could prove to be a key enabler in setting them apart rom competitors.

    Business management was very clear about strategy and how it would use technology. The problem was that the

    IT department didnt have the time nor the resources to do what the business asked or. Business managements

    rustration increased until the situation came to a head when the company lost a large contract to the

    competition because it couldnt deliver on a promised e-retailing capability. The IT managers job was on the line.

    The IT manager had no idea what to do. His job depended on him keeping to the set budget. He and his team

    had worked day and night to try and deliver the project at the same time as keeping the current systems

    running. Business kept changing requirements but didnt expect the cost to change so getting the right skills

    on the project was a real issue. In addition, day-to-day running kept him awake at night because part o the

    inrastructure was obsolete and unsupported and only one person knew how to x it when it ell over. He hadattempted to explain the issues to his boss, the CFO, and ailed. I only his business colleagues understood the

    problems he aced. They didnt and he lost his job.

    A newly appointed IT manager was told o his predecessors ailure and the warning bells went o. He suggested

    that beore settling into the job he assess just how the place had gotten into such a mess. At the end o his

    ourth week he presented his ndings to the business management team, the key ones being:

    Although the business had a clear view o how it wanted to use technology, it had no ormal plans and

    hadnt communicated to IT management.

    The IT budget was set by the CEO without any regard or the cost o building and delivering to business

    demand.

    The previous IT manager had assumed that it was his job to just do what he could within the set budget.

    He never raised his hand to advise the business o the risk it was carrying with obsolete equipment and noeective disaster recovery capability.

    He recommended that the ollowing practices be adopted immediately:

    Even though the role reported to the CFO, IT management must be at the business planning table and part

    o the business planning process.

    The IT budget should be developed as part o the annual planning process, refecting the true cost o

    business demand or IT-enabled change, levels o service and risk.

    Business management should conduct a process to better articulate, prioritise, und and approve

    requirements beore coming to IT.

    The BMIT framework and processes

    1 2

    34

    5

    Strategic IT demand

    management and long termIT alignment process

    Business Managementof IT Processes

    Ongoing IT work planningand prioritisation process

    Business program orproject gating process

    Benefits monitoring andrealisation and assetdecommissioning process

    Annual projectand service

    level demandmanagement and

    IT budget alignmentprocess

  • 7/30/2019 Business Management of IT

    18/52

    12

    A successul BMIT ramework is built on strong collaboration between IT and business. There are a number o

    oundation activities that you can adopt to help change the behaviour, practice and language that promote we rather

    than them and us.

    Foundation activities include:

    implementing clear decision-making and accountability rameworks

    promoting common language between business and IT

    building business IT relationships

    ensuring transparency o IT costs

    introducing business measurement o IT value

    recognising business programs, not IT projects, deliver business value

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Figure 3.1 The ve BMIT processes

    3.1 Implement clear decision-making and accountability rameworks

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    IT management oten makes decisions by deault because it is not clear who in the business should be making the

    decisions. Without this clarity, neither the business nor IT are likely to achieve their objectives.

    Good BMIT ensures that:

    business managers understand their responsibility or

    planning the use o IT as part o setting business objectives

    and perormance parameters, as well as their responsibility

    or delivering the intended business outcomes o theirinvestments.

    ITs responsibilities are within their capability to achieve

    and that IT is not responsible or things it cannot control

    or deliver.

    I you are held accountable, youwill be held accountable - so put

    in place the tools necessary tohelp meet that accountability.

    James CrownCEO Knowledge Group

    A simple tool to help establish who is accountable or what throughout the business planning and management cycle

    is the decision-making matrix (Figure 3.1.1). It can be tailored to your organisation and should cause a great deal o

    healthy debate when lling it in. This will lead to better understanding o the IT issues acing your organisation.

    3. Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    19/52

    13

    Board Business management CFO Head o IT

    Business strategy, objectives and plans A I I I

    Business IT strategy I A I I

    IT dollar investment over time A I I I

    Business benets case (ROI) I A I C

    Delivering business benets (ROI) I A I C

    Measuring delivered benets (ROI) C I A C

    Setting business program priorities I A I I

    Program delivery on time and budget C A C I

    Dening service level requirements C A I C

    Delivering service level requirements C I C A

    Risk prole or appetite or risk A I I I

    A - Makes the nal decision I - Must have input to the decision C - Must be told o the decision

    Figure 3.1.1 Decision-making matrix

    Once you have agreed who makes the decisions and who is accountable or implementing them, build the results into

    recognition and reward structures. Think about designing accountabilities and reward structures in a way that will drive

    collaborative behaviour between IT and the business rather than creating a divide.

    3.2 Promote common language between business and IT

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Cleardecisionmakingframeworks

    Mistakes oten occur simply because the business does not understand what IT is talking about and vice versa. IT

    speaks its own acronyms and jargon orgetting that the business doesnt necessarily understand and the business

    speaks a language that is oreign to the average technologist. In some cases, the problem is exacerbated when

    business people use IT jargon incorrectly, or when IT people attempt business speak without ully understanding.

    The solution to this issue primarily lies in recognising that the languages are dierent and translation mechanisms

    are required. Simple admission that one does not understand and clarication is required is a good start. In addition:

    Channeling communications through translators such as business analysts and relationship managers is

    another way o ensuring eective communication.

    The introduction o a shared pipeline list o business requirements which outlines business priorities, IT

    estimates and resource availability along with agreed business / IT measures will orm the basis o a common

    language that will enable business and IT management to have actual debate around how best to balance

    the supply / demand equation.

    As in the building industry, architectural drawings and plans serve as the translation between the client,

    architect and builder. They orm the basis o a common language. In IT, architectural models help to

    translate the expectations and requirements o IT into terms the business can understand. There is a

    Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    20/52

    14

    tendency to think that you must be big and sophisticated to have architectures. This is not the case. IT

    should be able to show business management conceptual diagrams o the current and uture ITenvironment and be able to describe the solutions and the logic behind the design in terms business

    management can understand.

    3.3 Build business IT relationships

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Transparencyof IT costs

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Complex chargeback and buyer supplier arrangements between IT and the business can lead to poor relationships and

    lack o trust in IT estimates.

    There are a number o ways to enhance the business IT relationship:

    Filter work requests through a business prioritisation and approval

    process beore asking IT to estimate.

    Understand that IT cant estimate accurately what the business

    cant dene precisely. Its not possible to do xed price estimates

    until all requirements have been specied and detailed design is

    complete. First cut guesstimates can be out by 100%. The

    introduction o phased estimating can clear up a lot o

    misunderstandings between business and IT. The ollowing

    diagram sets out the estimating tolerances relating to each phaseo the program liecycle.

    IT cant estimateaccurately whatbusiness cannotdeine precisely.

    Invest in business analysts to work with business managers and IT architects to identiy the solution

    approach. This role can sit in either the business or IT. Unortunately, the relationship role can be seen as an

    overhead and it goes rst with budget cuts. This is alse economy, as without this capability, IT can end up

    working on the wrong thing or has to do rework which ends up costing more.

    When doing business plans, include IT in the same way that you would your other business colleagues. Ask

    questions like:

    Are our current IT systems adequate or our ongoing business?o

    Are there technologies out in the market that we should be employing?o

    What can we do to reduce our ongoing running costs?o

    Have you any ideas on how we can bring down the cost o business process?o

    BusinessStrategyandObjectives

    Estimation Tolerance

    Build & ImplementDetailed DesignHigh Level DesignProgram FeasibilityProgram Concept

    +100%

    -100%

    0%

    Worst Case

    Best Case

    Most Likely

    Figure 3.3.1 Phased estimating: target o estimating is to provide most likelyprediction

    Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    21/52

    15

    3.4 Improve transparency o IT costs

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Collaborativebusiness ITrelationships

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    One o the core issues is that companies oten ail to ully understand the true cost o IT and what drives these costs.

    In many companies the IT budget does not refect the total IT spend. For various reasons, oten to make them look

    more palatable, IT costs get spread, in various guises, throughout business divisions.

    While companies see IT as a cost rather than an

    investment, they will continue to ocus on short termcost reduction without understanding the impact on the

    long term viability o IT systems and the business risk

    and impact o ailure.

    In order to make proper investment decisions in line with the risk

    prole o the company, business needs to understand the link

    between the IT-enabled business process and volumes and the

    cost o the IT services and resources it consumes to deliver these

    processes. Business needs to know what it is getting or

    its money and what levers it can pull to change what it is

    spending now and in the uture.

    IT costs are very otenunderstated. Anywhere up to 30%in additional costs can be oundwhen IT costs rom business costscentres are analysed. This can be areal issue when benchmarkingagainst other organisations orwhen understated igures are usedin the metrics to assess thebusiness value o IT.

    In many organisations, chart o account design and project accounting methods do not easily enable IT costs and

    measurements to be clearly linked to business outcomes, or example, cost o ongoing operations directly related tothe level o service delivered. (See Figure 6.4.1 Cost o Service Agreements.)

    The rst step in improving the transparency o IT costs is to separate them into two baskets:

    Keep IT Running (KIR) and1.

    Discretionary spend (capital and operational)2.

    KIR is dened as the cost o supporting, maintaining and growing the current business. It includes the cost o

    maintenance and regulatory and compliance changes but does not include the cost o business change. This is

    committed spend to keep the current business running and is determined by:

    business volumes

    service level agreements with the business

    level o risk the business is prepared to live with e.g. disaster recovery capability

    additional ongoing maintenance costs o new applications or inrastructure implementations and upgrades

    asset replacement schedule

    KIR spend should be determined interactively between the business and IT. The process to arrive at this spend is set out

    in section 5.1. To vary KIR costs, the business can use the ollowing cost levers:

    agree to a longer time or recovery in case o a disaster which would decrease the outlay on disaster

    recovery inrastructure

    accept a higher level o risk by running on obsolete assets which would deer the cost o replacement

    accept slower response times which would deer the cost o communication line upgrades

    reduce the length o time history les are kept which will result in a lower cost o storage

    Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    22/52

    16

    Discretionary spend is dened as the cost o the IT investment in IT-enabled business programs to introduce new

    business or to enable the existing business to be conducted in a better way.Long term investment programs (3-5 years) are scoped and costed at a conceptual level as set out in section 4.2. The

    process or determining annual discretionary spend is set out in section 5.1.

    Justication or discretionary spend is usually associated with a business benets case outlining the nancial and non-

    nancial benets that will be delivered when the program is implemented. Oten the problem with benets delivery

    stems rom the quality o the up-ront planning and scoping work resulting in costs being understated and benets

    being overstated to get the program across the line. Finance must play a key role in ensuring that:

    all costs, business and IT, have been taken into account

    phased estimating is a reality and that contingency calculations are in line with the level denition available

    or estimating

    the stated benets are reasonable and achievable

    there is a clear dierentiation between nancial and non-nancial benets

    the metrics that will be used to measure benets delivery are determined up ront in the business case

    costs are monitored throughout the program and the benets case is reassessed i costs blow out

    The introduction o the program gating process (Section 6.2) will assist in getting this right.

    3.5 Introduce business measurement o IT value

    Collaborativebusiness IT

    relationships

    Transparencyof IT costs

    Commonlanguage

    betweenbusiness and IT

    Cleardecision

    makingframeworks

    Businessmeasurement

    of IT value

    Businessprograms,

    not IT projects

    Businessprograms,

    not IT projects

    Collaborativebusiness IT

    relationships

    Transparencyof IT costs

    Commonlanguage

    betweenbusiness and IT

    Cleardecision

    makingframeworks

    I you cant measure it, you cant manage it. Credible business measures o IT eectiveness are essential to all levels o

    business planning and prioritising the use o IT. However, in many companies, much o the measurement o IT success

    is carried out and communicated by IT in IT terms that are not understood by business managers and are o little use in

    the assessment o IT eectiveness to the business.

    The ollowing table sets out examples o measures typically used by IT along with measures business management can

    introduce to assess IT eectiveness rom a business perspective.

    Business measures IT measures

    Business time lost Up time percentage

    Unit cost per transactionNetwork costs, hardware costs, total MIPS

    used

    Customer complaints Number o severity 1 problems

    Cost o business process Mean time to x problems

    Cost per delivery channel Application maintenance costs

    Business risk IT personnel turnover

    ROI Within budget

    Table 3.5.1 Measures to assess IT eectiveness

    Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    23/52

    17

    Fundamental to successul BMIT is management ully understanding and articulating why it is using IT in the rst place

    and what value means or their area o the business and the company. (See Table 1.3.1.1 Business use o IT.)

    Business management oten has diculty establishing measures due to a lack o understanding o the behaviour o

    their costs and the associated cost and revenue drivers. Finance is a critical player in supporting business managers in

    gaining this understanding and in establishing business metrics or measuring both the eectiveness o the current

    operations and the value delivered by additional investment in IT-enabled business programs.

    Metrics or the eectiveness o the current operations are ideally derived rom the business measures set out in the

    service levels agreed between business and IT management. (See section 6.3.1)

    Metrics or value delivery rom IT-enabled change programs are ideally based in the companys strategic decisions, or

    example:

    increase revenue e.g. improved sales capability, new products and services

    decrease costs e.g. urther automation o business process

    increase productivity, improving existing process improvement

    improve customer satisaction

    3.6 Recognise that business programs, not IT projects, deliver business value

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Businessprograms,not IT projects

    Collaborativebusiness ITrelationships

    Transparencyof IT costs

    Commonlanguagebetweenbusiness and IT

    Cleardecisionmakingframeworks

    Businessmeasurementof IT value

    Many companies have issues in running combined business / IT programs where both business and IT resources report

    into a single program manager. This problem seems to be a legacy issue stemming rom the times when anything to do

    with IT was let to the IT department and they were accountable or the lot, including benets. Times have changed.

    Today we need to recognise that there is really no such thing as an IT project. Most programs o change comprise

    change to several asset classes in concert including IT, business process, people and organisation. IT cannot be justied

    in isolation rom the business program it supports. (See Figure 3.6.1.)

    BusinessStrategy

    BusinessPrograms

    PROPERTY

    PEOPLE

    TECHNOLOGY

    PLANT & EQUIPMENT

    FINANCIAL

    INFORMATION

    Enterprise assets

    Interdependen

    cies

    Building or acquiring IT assets is

    rarely stand alone. The best

    results occur when the entire

    business program o change is

    planned, costed and managedas one program and the

    benets case is based on the

    delivery o the ull program.

    Trying to manage change in any

    one o these areas in isolation is

    destined to ail.

    Figure 3.6.1 Business programs composition

    Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    24/52

    18

    Divided we ailREPLACECO IT costs had increased over time due to increased maintenance costs on ageing and ragmented

    sotware. The decision was made to replace existing applications with a highly congurable industry standard

    package chosen by the business. The business had been convinced by the supplier that the package would be

    easily congured and implemented to meet REPLACECOs business needs. IT was not involved in the decision.

    The package was purchased. Business handed over responsibility or implementation to IT.

    An IT project manager and project team were appointed to work with the supplier to implement the package.

    The list o variations rom the out o the box conguration continued to grow. A heavily modied package was

    nally implemented 18 months late and 50% over budget.

    A post-implementation review by an external party ound a trail o poor decision-making and unclear

    accountabilities. Root causes o the problems were:

    no-one owned the business solution

    the solution approach was not tested or estimated beore buying

    the business benets case was not revisited

    business management expected IT to implement with little involvement rom themselves

    IT was not involved in the decision to purchase the package

    appropriate IT due diligence o the claims o the supplier and the appropriateness o the package were

    not carried out by IT

    The REPLACECO Board learned o the project ailure. When the ull picture emerged, they had little condence in

    either the business or IT. REPLACECO had more large IT projects coming up on the product ront. The board was

    skeptical that the company had the capability to deliver and asked to be convinced by business and IT

    management that it was up to delivering uture demand. The changes presented to the board included:

    an IT / business decision matrix be implemented to ensure clarity around who makes decisions about

    what

    rom now on all IT developments would be part o business programs under business ownership

    all programs o change must go through a rigorous process upront to thoroughly test the solution

    approach and benets beore investing signicant dollars

    a program gating process be implemented with clear GO / NO GO check points to identiy problems,

    revalidate benets and costs to complete

    Foundations of a successful BMIT

  • 7/30/2019 Business Management of IT

    25/52

    19

    4. Long term strategic planning

    Most companies depend on IT or day-to-day activities. What many ail to realise is that strategic growth also depends

    heavily on IT. They also depend on the IT o their business partners and customers. Moreover, many businesses mustalso take into account how IT is or will be used in their markets by competitors, regulators and so on. For these

    reasons, it has become imperative that organisations give specic attention to IT as they prepare their long term plans.

    The danger in leaving IT out o the long term strategic planning process,

    or with short term direction only, means that IT cannot ormulate long

    term uture architectures and may end up building IT applications and

    inrastructure piecemeal. Lack o eective uture planning has led to

    problems in many companies in that unnecessary complexity has been

    built into the business and consequently, into IT. This complexity can act

    like reinorced concrete - its a barrier to change.

    Plan to grow into your ITassets not out o them.

    Neil Wilson - CEO Oakton

    I you dont know where youare going, any road will takeyou there.

    Building the IT environment piecemeal leads to duplication, complexity,

    infexibility and higher running costs. It also delays business innovation

    and competitive advantage, and it may mean that business is overrun by

    competitors that are more eective in planning their IT use.

    IT long term planning is an integral part o the business strategic

    planning processes. As with a manuacturing plant or property, many IT

    assets have long asset liecycles and oten take years to implement,

    making IT dependent on eective long term business planning.

    Long term strategic planning ramework (Figure 4.0) highlights the business and IT decision areas along with the

    interactions and outcomes o long term business planning. This process occurs annually reviewing the relevance o the

    long term business strategic directions and the alignment o IT and other asset class plans with these directions. This is

    a two way process that cannot be done by either party in isolation. The process can be led by either IT or business but

    should be owned by business management.

    BusinessProcess BusinessDecisions BusinessIT Interaction ITDecisions

    Long term businesssstrategies and targets

    Business use of ITs

    Competitive positionings

    Business benefitss

    Prioritiess

    Fundings

    IT architectures andsarchitectural principlesCurrent and target ITsarchitecturesIT migration plans andsinitiativesTechnology infrastructuress

    Business strategies, priorities,funding, strategic businessbenefits

    IT trends and opportunities,future architectures, costs

    estimates, risks

    3-5 year Business IT Strategic Plan:

    Target IT architecturess

    Key IT initiatives to achieve targetss

    Estimates of IT capital investments

    Estimated ongoing operational costsdependencies

    Business IT strategic plan

    Pipeline / portfolio of strategic initiatives

    Alignment

    3-5 year business strategic plan:

    Business targetssKey initiatives to achieve targetss

    across all asset classes

    Estimates of capital investments

    Prioritiess

    Benefitss

    Strategic ITdemandmanagementand long termstrategicalignmentprocess

    Figure 4.0 Long term strategic planning ramework

    Long termstrategic planning

    Annual planningand budgeting

    Ongoingmanagement

  • 7/30/2019 Business Management of IT

    26/52

    20

    Implementation o the strategic IT demand management and long term strategic alignment process (Figure 4.1.1) will

    ensure that when business management has completed its long term strategic plan it will have:an updated business IT strategic plan that will ensure uture IT architectures are still valid and aligned with

    the business strategies and priorities, and dependencies are understood (see Figure 4.3)

    a qualied portolio o the strategic initiatives or business programs that the organisation will be

    undertaking over the next 3-5 years(Figure 4.2.2)

    The strategic initiatives or business programs identied by the plan become the basis or Business Management IT

    decision making and the setting o IT priorities.

    4.1 BMIT process 1: strategic IT demand management and long termalignment process

    This process outlines the business and IT actions and accountabilities which will:

    align IT architectures and plans with long term business strategy

    create and maintain the two way link between IT-enabled business initiatives and IT spend

    validate long term priorities

    align interdependencies between all long term strategic initiatives such as people, property and IT

    orm the ramework or ongoing business program prioritisation and portolio management

    consider the long term demand supply equation and the overall capability to absorb change

    The business IT strategic plan (Figure 4.1.1) should be owned by the business and developed jointly by the business

    and IT. This is not a technical plan although IT may do a lot o technical work behind the scenes. It is a plan that

    outlines the IT implications o business strategic intent and translates these implications into the key IT initiatives that

    will be required to deliver the strategy.

    Long term strategic planning

  • 7/30/2019 Business Management of IT

    27/52

    21

    Action Who Description

    Business strategy review Board, business

    managers and IT

    manager

    Review o the companys strategic direction and objectives to

    determine i the company is on track to achieve the

    objectives and to make changes in strategy as required. IT

    brings to the planning table advances / opportunities which

    may be considered by business to better enable strategy

    achievement.

    Strategy to business action Business managers Workshops o business management aimed at translating

    business strategy into business action. What is the business

    going to do to deliver the strategy?

    IT implications o business

    action

    IT manager, IT

    architects andbusiness analysts

    Analyse the business and IT impact o the proposed business

    actions and group impacts around application amilies, i.e.customer, nance, workfow, and warehouse.

    Gap analysis IT manager, IT

    architects and

    business analysts

    Analyse how well the existing IT architecture can deliver on

    the proposed business action and what will have to be done

    rom an IT perspective to bridge the gap.

    Develop transition plan IT manager, IT

    architects, business

    analysts and business

    managers

    High level design o the business programs that will need to

    take place to transition rom the present to the uture

    including dependencies and guesstimated timerames.

    Initiatives, costs and times

    to bridge the gap

    IT manager, IT

    architects, business

    analysts and business

    managers

    Cost estimates, benets and risks (important that the total

    cost, not just IT cost is understood)

    Feasibility assessment Business managers

    and board

    Analysis o the proposed transition plan, costs and change

    impacts. Can the company aord it? Can it absorb the

    change?

    Prioritisation and culling o

    business action

    Business managers

    and board

    I in the easibility assessment, the long term spend is

    determined to be too high, the board and business go back

    to square one and look at what actions they will not do or

    deer, then resubmit to the IT architects to reassess costs.

    Business IT strategic plan3-5 year pipeline / portolio o strategic initiatives

    business measures

    Figure 4.1.1 strategic IT demand management and long term alignment process

    Long term strategic planning

  • 7/30/2019 Business Management of IT

    28/52

    22

    4.2 The business IT strategic plan

    The business IT strategic plan sets out:

    the current baseline and evolution plan or uture ramework architectures

    the technology gap between now and the uture

    the principles and policies to guide IT decisions and architectures in building the uture

    the prioritised sequence and cost estimates o the initiatives required to migrate the organisation towards its

    target along with estimated impact on ongoing running costs

    capital expenditure and depreciation schedules

    a high level implementation plan, highlighting implementation dependencies with other asset classes

    The business IT strategic plan isthe vehicle that:

    clearly interlinks business strategy with IT architectures

    balances long term demand against long term IT spend and long term benets

    establishes a clear link between business strategy and IT initiatives so that the impact o change in business

    strategy on IT plans is understood and appropriate action is taken

    sets a two-way link between business strategy and IT spend i.e. i IT spend is cut, the impact on strategy is

    clearly understood by business management and strategy can be adjusted accordingly

    manages long term strategic demand including long term capital requirements, change impacts and inorms

    business management o the levers it can pull to vary the dollars over time

    orms the basis or business programs that deliver capability and value, rather than IT projects that just

    deliver the potential

    Long term strategic planning

  • 7/30/2019 Business Management of IT

    29/52

    23

    Figure 4.2.1 sets out a simple example o how the IT implications o high level statements o strategic direction can be

    translated into IT initiatives and costs. There is a signicant amount o architectural work required behind the scenes toachieve this level o connection but it is worth the one o investment to ully understand the investment required over

    time to deliver business strategy.

    Businessstrategy

    Business actionrequired todeliver thestrategy

    IT implication othe businessaction

    Can thecurrentenvironmentdeliver thecapability?

    Gap betweenthe currentand uture

    Impact onotherassetclasses

    Cost oinitiativesto fll thegap

    Doubling

    business

    in 5 years

    Acquire

    complimentary

    business

    Extend into ACT

    and Qld

    Increase the

    capacity o the core

    product system to

    deal with additional

    volumes

    No Core product

    system upgrade

    to latest version

    o the package

    Property

    acquisition

    in ACT and

    QLD

    $1.5m

    Extend warehousecapacity

    Extend network andinrastructure to

    include ACT and

    QLD

    No Link betweencustomer

    inormation

    systems

    ACT andQLD Oce

    set up

    $.5m

    Introduce internet

    catalogue sales

    Catalogue sales and

    payment capability

    on the website

    No Financial

    systems link to

    BPAY

    HR $3.5m

    Cross sell acquired

    product business

    to existing

    customer and

    vice versa

    Upgrade

    website

    Marketing

    and product

    design

    $.7

    Figure 4.2.1 Alignment - establishing a two way link between business strategy and action with IT costs

    The long term strategic planning process will deliver an integrated picture o the initiatives and costs required to ll the

    gap and take the organisation rom the present to the uture. This big picture serves as the base or business and IT

    annual planning and or the ongoing prioritisation o work.

    Major Initiatives Year 1 Year 2 Year 3 Year 4 Year 5

    IT-enabled business program 1

    IT-enabled business program 2

    Property initiative

    New product initiative

    Interstate expansion

    IT inrastructure program

    IT-enabled business program 2

    Total Asset Capital Spend $ XXX $ XXX $ XXX $ XXX $ XXX

    Total IT Asset Capital Spend $ XXX $ XXX $ XXX $ XXX $ XXX

    Total IT Operational Spend $ XXX $ XXX $ XXX $ XXX $ XXX

    IT Asset Replacement $ XXX $ XXX $ XXX $ XXX $ XXX

    Figure 4.2.2 The big picture

    Long term strategic planning

  • 7/30/2019 Business Management of IT

    30/52

    24

    Complete the ollowing table. I you score no to more than three questions, it is highly likely that the strategic use o

    technology is not being considered or planned appropriately in your company.

    How eective is your BMIT in the long term strategic planning process? Yes No

    Does the business management have a clear understanding as to why it is using technology and what

    it expects rom technology?

    Does business management understand what the competition is doing with technology?

    Has business management established a consistent way o determining long term IT investment and benets?

    Is IT management considered to be an essential participant in, and contributor to, the long term

    business strategic planning process?

    Does IT management keep business up-to-date on an ongoing basis with technology advances and the

    latest application packages in the market?

    Does IT management bring new technologies to the planning table as potential enablers o new or

    existing business strategies?

    Does the strategic planning process take into account the short, medium and long term viability o its current IT?

    Does the business management consider the risk implications o under investing in the longer term

    Do investment decisions take into account long term statutory and regulatory requirements?

    Are ongoing operational costs, service levels and asset replacement schedules considered in the long

    term strategic planning process and in assessing long term investment dollars?

    Does the business have a process to prioritise longer term spend against business strategy and objectives?

    Does the business have a roadmap o the business programs and IT initiatives and costs required to

    deliver business strategy and plans (the cost and eort o getting rom the present to the uture)?

    Table 4.2.3 Eectiveness o BMIT

    IT long term planning is an integral part of the business strategic planning processes.

    SALESCOs expansion plans were well on the way and business appeared to be going really well. Revenues were

    increasing at 20% per annum however bottom line perormance was being impacted as margins were being eroded

    by lower cost competition. A company-wide program was put in place to cut costs right across the board, including

    IT. Margins improved and everyone was happy, except the IT manager. He had tried to get the business executive to

    understand the implications o urther IT cuts but he couldnt get the message across.

    SALESCO systems had been purchased 10 years ago and were designed or companies running around hal o

    SALESCOs volumes. The system just couldnt keep up, errors increased, response times died and the diminished

    business and IT workorce became quite demoralised. Sta turnover increased with some key IT skill sets walkingout the door.

    Margins had improved but SALESCO started to lose key customers as a result o poor service and increasing IT

    errors. Revenues started to all. The company had started on a downwards spiral.

    SALESCO executive had taken IT or granted and ailed to really quantiy the contribution IT systems were making to

    business process eciency and eectiveness. They hadnt really thought about why they were using IT and that lack

    o investment meant that IT systems could not longer support the very processes it was designed to automate.

    SALESCO executive learned its lesson and started to invest heavily in IT. Unortunately it was too late. The

    replacement program took three years. It took SALESCO ve years to recover.

    The investment should have commenced ve years earlier when SALESCO started the planned expansion. The

    investment costs and benets should have been built into the long term business plans, not ater the expansion had

    taken place.

    Long term strategic planning

  • 7/30/2019 Business Management of IT

    31/52

    25

    Once the businesss long term strategic direction, objectives and priorities have been conrmed, nancial targets are set or

    the coming nancial year and business management then develops divisional plans and budgets to deliver these targets.There are two common scenarios which severely impact IT in this process:

    IT is not involved with the business in developing its annual plans and as a result the IT resource and1.

    budget impacts o the plans are not catered or.

    The budget process oten overtakes the planning process and the IT budget is developed in isolation o2.

    the business plans and budgets.

    Both scenarios end with the same result - the IT budget and plans (supply) are not ormulated on planned business

    requirements (demand) potentially leading to inerior service and lack o resources to deliver business programs,

    projects and services.

    The cost o IT is a direct result o the business demand (long and short term) or the delivery o service levels and the IT

    component o business programs (IT projects). For business management to understand its IT costs and the levers it can

    pull to vary these costs, IT budgets are best ormulated interactively with the business over the ollowing three key

    areas using the annual planning and budgeting ramework (Figure 5.0):

    KIR largely the commodity inrastructure determined by service level required by the business

    enhancing current capability - cost o resources to make the changes or enhancements that arise during the

    year as a result o short term business imperatives

    building / acquiring new capability mostly treated as a capital cost that should have been identied the

    long term strategic plan

    Adhering to the ramework will ensure that:

    the IT budget is not developed in isolation rom the business budget and the costs o proposed IT initiatives

    is allocated in the business or IT budgets

    the business cost o IT initiatives (e.g. training, process re-engineering) is included in either the IT or business

    budget

    the gap between the business demand on the IT budgeted supply is addressed in the business planning

    process and realistic expectations are set o IT delivery capability

    5. Annual planning and budgeting

    Long termstrategic planning

    Annual planningand budgeting

    Ongoingmanagement

  • 7/30/2019 Business Management of IT

    32/52

    26

    Business and IT business plans and budgets

    Prioritised pipeline / portfolio of business programs and projects

    Agreed business service level agreements

    Business IT strategic plan

    Pipeline / portfolio of strategic initiatives

    BusinessProcess

    BusinessDecisions

    BusinessIT Interaction

    ITDecisions

    Annual projectand servicelevel demand

    managementand IT budgetalignmentprocess

    s-ARKETSCUSTOMERS

    s2EVENUESCOSTS

    s6OLUMESGEOGRAPHIESresponse times

    s0ROPOSEDENHANCEMENTto existing systems

    s0ROPOSEDSTRATEGIC

    projects and benefits

    s0RIORITIES

    6OLUMESTRANSACTIONSUSERSCUSTOMERSETCRESPONSETIMESGROWTHESTIMATESGEOGRAPHERS

    s#APABILITYCAPACITY

    s3KILLS

    s3OLUTIONOPTIONSANDARCHITETURALIMPACTS

    s3OURCINGARRANGEMENTS

    s3ERVICEDELIVERYALTERNATIVES

    +EEP)4RUNNING+)2budget

    0ROJECTANDENHANCEMENTbudget

    3ERVICELEVELCOSTSRISKSAND

    PERFORMANCE0ROJECTESTIMATESand resource capacity

    s!NNUALBUSINESSPLANS

    s/BJECTIVES

    s-EASURES

    s"ENEFITS

    s"USINESSBUDGETS

    s/PERATIONALSPEND

    s#APITALBUDGETS

    Figure 5.0 Annual planning and budgeting ramework

    5.1 BMIT process 2: Annual project and service level demandmanagement and IT budget alignment

    A number o issues arise in the ongoing delivery o service that could be avoided i the time is taken in the annual

    planning and budget process by business and IT management to agree on the levels o service required and the costs

    and risks involved. BMIT process 2 annual project and service level demand management and budget alignment

    process will:

    link business plans and budgeted benets to the IT project resource (discretionary) budget

    ensure that IT supply is unded and capable o delivering to annual business plans

    align annual IT program o work with long term business strategy

    link IT KIR budget with business service expectations

    balance the annual demand supply equation

    deliver the rst cut annual work plan, dependencies and priorities

    On completion o the annual planning and budgeting, business and IT management should know:

    the IT contribution to strategic business programs (capital spend and resourcing) and the annual list o

    prioritised IT work required to deliver the annual business results

    the overview o the non strategic projects and enhancements (discretionary operational spend)

    the service levels IT will be required to deliver to the business and a clear understanding o the cost, risk and

    perormance issues relating to the agreed budget (KIR spend)

    Annual planning and budgeting

  • 7/30/2019 Business Management of IT

    33/52

    27

    BMIT process 2: annual project and service level demand management and IT budget

    alignment processAction Who Description

    Set annual

    objectives

    Board and

    business

    executive

    Annual objectives (nancial and other) are set or the company in line with the

    long term strategy and a decision is made on strategic program investment

    (capital spend).

    Business divisions translate these objectives in specic divisional objectives and plans.

    Actions to

    achieve

    objectives

    Business

    managers

    Develop operational plans to deliver the objectives e.g.

    change initiatives (new unction, products, processes)

    increase in volumes, geographies etc

    productivity improvements

    Business

    budgetdevelopment

    CFO, business

    managers andIT manager

    IT works with business management to identiy the IT implications o the

    proposed operational plans. This encompasses:a) KIR and service level implications

    b) strategic programs or changes to existing systems to be initiated this nancial

    year (subset o the long term strategic plan and roadmap)

    IT project cost

    and benets o

    guesstimates

    IT manager, IT

    architects,

    business

    analysts and

    business

    managers

    Interactive process between business managers and IT analysts and estimators

    to establish order o magnitude costs that will enable business to validate the

    IT costs and benet assumptions in their operational plans and budgets.

    Business managers agree preliminary cost and eort estimates and set priorities

    or each requirement to assist in the elimination process when the IT budget is

    being nalised.

    IT service level

    costs

    IT manager, IT

    operations

    and business

    managers

    Interactive process between business and IT managers to work out the ongoing

    cost implications o increased volumes, changed geography etc. IT estimates

    and advises on costs, perormance and risk and business managers decide how

    much they can aord, the risk they are prepared to carry and the perormance

    they can live with.

    IT budget

    development

    IT manager Develops IT budget based on the business division requirements or projects and

    service levels.

    Assessing total

    IT demand

    IT manager

    and business

    executives

    IT will have analysed and guesstimated the requirements rom all business areas

    and come up with the total budget or KIR, a budget or operational projects

    and a capital budget or strategic projects. The CEO and executive will decide i

    the company can spend this amount on IT. The answer is usually no.

    Prioritisation

    and IT budget

    alignment

    Business

    managers and

    the CEO

    Business divisions get together and decide what will be cut rom the business

    requirements list using the priorities set by each o the business units. The

    business and IT executives work together to balance the supply / demand

    equation.

    Finalise

    budgets

    CFO, business

    managers and

    IT manager

    Business unit operational plans and budgets are consolidated into group

    operational plans and budgets.

    Business and IT business plans and budgetsPrioritised pipeline/portoio o business programs and projects

    Agreed business service level agreementsBusiness measures o IT

    Figure 5.1.1 BMIT process 2: Annual project and service level demand management and IT budget alignment process

    Annual planning and budgeting

  • 7/30/2019 Business Management of IT

    34/52

    28

    5.2 Business program prioritisation and budget alignment

    There can be many reasons why business priorities change, or example, the competition doesnt always do as

    expected. When priorities change, it is essential that the change is quickly refected in plans so that wasted eort is

    avoided in all asset classes.

    Prioritising long term investment requirements and short term business imperatives is an ongoing process, not an

    event. The long term strategic plan sets out the overall priorities or the company, however it is critical that these

    priorities are revisited in the annual planning process and during ongoing management to ensure that resources, skills

    and unding are in place and budgeted, in all asset classes including IT. Priorities need to be reassessed through all phases o

    the planning liecycle to ensure that IT is best positioned to respond to changes in business demand (Figure 5.2.1).

    Long term

    strategic planning

    Annual planning and

    budgeting

    Ongoing

    management

    Sets strategic priorities

    the 3 5 year prioritised roadmap to achieve thecompanys objectives

    Sets Financial Year priorities

    prioritised plan o work and budgets which willdeliver this years objectives and keep the companyon course to deliver long term objectives

    Sets the IT work plan

    re-prioritisation o the annual program o work todeal with unplanned events as they arise

    Pip

    elineofplannedwork

    Figure 5.2.1 Business prioritisation o business demand

    5.3 Business prioritisation orum

    Eective prioritisation relies on well-conducted long term and annual planning processes and a well organised business

    team assigned with the authority to make prioritisation decisions on behal o business management.

    Establishing a business orum to support the ongoing IT work prioritisation process and charged with the ollowing

    tasks will ensure that IT resources are put to best use and are not losing time on non essential work:

    prioritising long term strategic demand along with short term business imperatives against IT supply

    limitations

    ensuring that work on existing applications has benet and that IT eort is ocused on adding value through

    new projects and programs (see Figure 5.3.1)

    dealing with the strategic alignment and risk issues that may arise rom having to juggle competing

    demands or a limited budget

    continually assessing the impact o work rescheduling on proposed business case outcomes

    supporting the annual planning and budgeting process and advising business management on IT investment

    priorities taking into account the companys long term and annual business objectives and making

    recommendations on which programs should go ahead and which could be deerred or cancelled

    advising business management on investment ratios (dollar spend on KIR versus new capability and

    innovation) and the risks associated with under or over investing in particular areas

    Annual planning and budgeting

  • 7/30/2019 Business Management of IT

    35/52

    29

    Evaluate Assess individual applications

    Rationalise Streamline spending

    Govern Use IT governance to control diversity

    20/80 ratio 40/60 ratio

    Newprojects

    ExistingApplications

    Newprojects

    ExistingApplications+ =

    Figure 5.3.1 Eective prioritisation o IT eort

    In some companies, the prioritisation orum charter extends beyond IT and covers the prioritisation o all business changeacross the company.

    A word o warning: when establishing a business orum, ensure that this is not a representational group with each

    member ghting or their own divisional interests. The group needs executive leadership, the skills and experience to

    set priorities and delegated authority to make decisions on behal o the company. IT management is a critical member

    to articulate supply constraints which will eect prioritisation. In smaller companies the orum may be a subset o the

    management team chaired by the CFO.

    To support the ongoing work prioritisation process (Section 6.1), the business orum requires a comprehensive pipeline

    list o the total demand and work in progress, including:

    strategic initiatives (rom the strategic planning process)

    additional business requirements (rom the annual planning process)

    adhoc requests or change resulting rom day-to-day business imperatives

    The pipeline list provides the vehicle with which the orum can prioritise business demand and IT management, and

    develop and resource the work plan o programs, projects and minor work requests.

    The level o sophistication o the pipeline list will vary depending on company size, dollars and complexity o demand.

    An excel spreadsheet can work quite well. There are also a number o packages on the market that support the

    recording, categorising and analysis o business demand and produce inormation that enables business to prioritise its

    discretionary spend in line with the business strategy, plans and objectives (portolio management).

    A number o organisations have established a program oce to manage and oversee discretionary spend or all assets

    classes including IT. This oce is oten located in nance and supports all programs o work across the organisation,

    not just IT.

    5.4 Service level planning and budget alignment

    Many organisations cannot operate i their IT systems are not unction