Business Driven PMO Setup and Management

39
Mark Price Perry September 30, 2015 Project Management Institute Minnesota Chapter Business Driven PMO Setup and Management

Transcript of Business Driven PMO Setup and Management

Page 1: Business Driven PMO Setup and Management

Mark Price Perry

September 30, 2015

Project Management Institute Minnesota Chapter

Business Dr iven PMO

Setup and Management

Page 2: Business Driven PMO Setup and Management

Introduction to the Business Driven PMO ◦ All too familiar PMO story

◦ Purpose of the PMO

◦ Purpose of project management

Roadmap for PMO Setup ◦ Three steps

◦ Two tips

◦ One golden rule

Summary

Slide 2

Page 3: Business Driven PMO Setup and Management

Slide 3

Leadership team decided to have a PMO

Page 4: Business Driven PMO Setup and Management

Slide 4

PMO manager was hired to start a new PMO

Page 5: Business Driven PMO Setup and Management

Slide 5

PMO manager hastily created a PMO Charter

People

Tools

Process

Training

PMO

Page 6: Business Driven PMO Setup and Management

Slide 6

One year later…

• Lack of support for the PMO

• Questioning of PMO value

• PMO given a second chance

• With a new PMO manager

Page 7: Business Driven PMO Setup and Management

Slide 7

New more professional (better dressed) PMO manager..!

Page 8: Business Driven PMO Setup and Management

Slide 8

Same old PMO, but with buzz and hype added to PMO activities

People

Tools

Process

Training

PMO

Sell the PMO

Show

Qu

ick W

ins

Obtain Executive Buy-in

Cele

bra

te S

uccess

Page 9: Business Driven PMO Setup and Management

Slide 9

Another year later…

• Still lack of support for the PMO

• Even more questioning of PMO value

• PMO given a third chance

• With a third PMO manager

Page 10: Business Driven PMO Setup and Management

Slide 10

Experienced business manager asked to head PMO

Page 11: Business Driven PMO Setup and Management

Slide 11

Let’s act like business people and speak the language of business

People

Tools

Process

Training

PMO

Sell the PMO

Show

Qu

ick W

ins

Obtain Executive Buy-in

Cele

bra

te S

uccess

Page 12: Business Driven PMO Setup and Management

Slide 12

Leadership team determined PMO mandate

“Nemawashi”

• Leadership team determined (ends)

• Top 3 project-related problems

• Vision for the PMO

• Mission of the PMO

• Goals / Objectives (how much by when)

• Assessed value to the business

• PMO determined (means)

• Business plan for the PMO

• Strategy components for each objective

• Key PMO capabilities

• Tactics to enable capabilities

• People, process, tools, training

• KPIs relative to the PMO objectives

Page 13: Business Driven PMO Setup and Management

Nemawashi – Individual Starting Position

Slide 13

I. Top three problems/opportunities to be solved by the PMO 1. ……………………………………………………….

2. ……………………………………………………….

3. ……………………………………………………….

II. Vision • ………………………………………………………………………………………………………

………………………………………….

III. Mission • ………………………………………………………………………………………………………

………………………………………….

IV. Goals and objectives of the PMO (fulfillment of problem/opportunity) 1. ………………………………………….

• Objectives: ………………………………………………………….

2. ……………………………………….....

• Objectives: ………………………………………………………….

3. ……………………………………….....

• Objectives: ………………………………………………………….

V. Value to the business

• …………………………….

From Individual Perspectives to Unanimous Consensus

Page 14: Business Driven PMO Setup and Management

Nemawashi – Leadership Team Ending Position

Slide 14

I. Top three problems to be solved by the PMO I. Poor forecasting and management of project-based revenue

II. Not enough capacity to perform more projects

III. Lack of visibility of all the projects of the company

II. Vision I. To be an enabling and facilitating organization that is focused on, and accountable for, the

project-based success of the company

III. Mission I. To develop and execute annual plans and strategies that solve the major project-related

problems faced by the company

IV. Goals and objectives I. The top three goals and objectives (how much by when) of the PMO

I. Goal 1: Improve project revenue management

I. Objectives: Reduce forecasting margin of error to 5 percent by year end

II. Goal 2: Increase project capacity

I. Objectives: 100% increase by year end

III. Goal 3: Provide holistic view of all projects

I. Objectives: Effective project reporting in place within 90 days

V. Value to the business ($50m / Significant)

Business Planning vs. Cookie-Cutter PMO Chartering

Page 15: Business Driven PMO Setup and Management

Slide 15

After a year of this

• Tremendous support for the PMO

• No question of PMO value

• PMO given more to do (not another chance)

• Executive initiatives

• Strategic planning

• Portfolio management

• Organizational-wide counsel

Page 16: Business Driven PMO Setup and Management

The purpose of a PMO is not… ◦ To develop standards for the management of projects…

◦ To support, report, train, coach, and mentor…

◦ To provide PMO services…

Most folks answer “what is the purpose of a

PMO” by describing what a PMO does

Slide 16

Page 17: Business Driven PMO Setup and Management

The purpose of a PMO is… ◦ To best address the project-related issues and

opportunities of the constituent leadership team for whom the PMO was created and exists to serve and for which business as usual (sans-PMO) is not a viable option…

Slide 17

Until the ends to be achieved are first established,

there can be no sensible discussion about the means

Page 18: Business Driven PMO Setup and Management

Lots of excuses for not having a leadership team determined and unanimously agreed to PMO purpose ◦ Heard them all…

If you don’t have PMO purpose… ◦ You have missed an opportunity

Servant Leadership

Business Management

Business Value

◦ You have put the PMO at risk

Strike one - All honeymoons end

Strike two – Buzz and hype only prolong the reckoning

Strike three – If there is a third strike, you might not be the batter

Slide 18

PMO management is business unit

management, not project management

Page 19: Business Driven PMO Setup and Management

Which project manager did a better job..?

Slide 19

Project Overall Status

Schedule Status

Cost Status

Estimated Duration

Planned Duration

Actual Duration

Start Finish Planned Cost

Actual Cost

Project 1 100 days 125 days 125 days 01/06/04 07/03/04 $190,000 $190,000

Phase 1 20 days 25 days 25 days 01/06/04 02/10/04 $50,000 $50,000

Phase 2 20 days 25 days 25 days 02/11/04 03/17/04 $55,000 $55,000

Phase 3 20 days 25 days 25 days 03/18/04 04/22/04 $25,000 $25,000

Phase 4 20 days 25 days 25 days 04/23/04 05/28/04 $35,000 $35,000

Phase 5 20 days 25 days 25 days 05/29/04 07/03/04 $25,000 $25,000

Project 2 100 days 75 days 85 days 01/06/04 05/09/04 $140,000 $160,000

Phase 1 20 days 15 days 17 days 01/06/04 01/29/04 $40,000 $42,000

Phase 2 20 days 15 days 18 days 01/30/04 02/25/04 $45,000 $48,000

Phase 3 20 days 15 days 15 days 02/26/04 03/19/04 $15,000 $20,000

Phase 4 20 days 15 days 19 days 03/20/04 04/16/04 $25,000 $29,000

Phase 5 20 days 15 days 16 days 04/17/04 05/09/04 $15,000 $21,000

Page 20: Business Driven PMO Setup and Management

Gaming industry consulting firm ◦ Target Market – Casinos

Specialty – On time openings, risk management

New Engagement – Casino readiness

Product of the Project Benefit – Avoidance of fines, license loss

Estimated Project Cost - $250,000

Estimated Project Duration – 100 days

Stakeholder Bias – Time (I need a completion date I can count on..!)

Casino will commit open date to public/regulators based upon project schedule

Scope is secondary

Cost is tertiary

Slide 20

Approach Project Manager #1

Technique Employed Positive Buffering – added time to phase estimates

Why To best meet the stakeholder bias for the project

Result Finished on time, avoided penalties and loss of license

Page 21: Business Driven PMO Setup and Management

A leading manufacturer of wool yarns ◦ Target Market – Knitters and Commercial Weavers

Routes to Market – Direct Sales, Channel Sales, Telemarketing

New Initiative – Selling directly to knitters via company website

Product of the Project Benefit - $20k per day, $20m first three years

Estimated Project Cost - $250,000

Estimated Project Duration – 100 days

Stakeholder Bias – Time (I want it now..!)

Scope is secondary

Cost is tertiary by a wide margin

Overrun to meet/beat schedule to realize benefits sooner welcomed

Slide 21

Approach Project Manager #2

Technique Employed Negative Buffering – subtracted time from phase estimates

Why To best meet the stakeholder bias for the project

Result Finished earlier, cost less, recognized $1m+ in benefits

Page 22: Business Driven PMO Setup and Management

The Project Management Triangle ◦ Intended to reveal stakeholder biases for the project

◦ Never intended to be a measurement system

Slide 22

The Project

Management Triangle

Time Cost

Scope

Page 23: Business Driven PMO Setup and Management

Slide 23

“If we only speak the language of

project management as in scope, time,

and cost; then project management as

a profession will fail today’s

businesses..!”

-- Mark Langley, CEO PMI

Page 24: Business Driven PMO Setup and Management

Slide 24

“To achieve and sustain PMO success,

there is a lot that must be learned and

there is even more that must be

unlearned..!”

-- Matt Light, VP of Gartner Research,

PPM Practice

Page 25: Business Driven PMO Setup and Management

Is stakeholder bias understood?

100 PMOs surveyed, random project charter picked

What percent of project charters did not show stakeholder bias for scope, time, cost and will to pay/wait..? 25% did not show stakeholder bias

50% did not show stakeholder bias

75% did not show stakeholder bias

90% did not show stakeholder bias

Slide 25

Reflect upon your own “Project Charter” perspectives regarding

the percent of project charters that did not show stakeholder

bias and will to pay/wait.

Page 26: Business Driven PMO Setup and Management

Is stakeholder bias understood?

100 PMOs surveyed, random project charter picked

What percent of project charters did not show stakeholder bias for scope, time, cost and will to pay/wait..? 25% did not show stakeholder bias

50% did not show stakeholder bias

75% did not show stakeholder bias

90% did not show stakeholder bias

Slide 26

If Stakeholder Bias is not understood (used) by the project

manager, how likely is it that stakeholders will be best

served over the course of the project..?

Page 27: Business Driven PMO Setup and Management

The purpose of project management is not… ◦ The delivery of a project on time and on budget

Most folks answer “what is the purpose of

project management” by describing a

commonly used technique

Slide 27

Page 28: Business Driven PMO Setup and Management

The purpose of project management is… ◦ The practical application of knowledge, skills, tools, and

techniques to project activities to meet the project requirements

Slide 28

Most project managers do not know the

stakeholder bias for their project and much worse,

most project managers do not know their craft..!

Page 29: Business Driven PMO Setup and Management

Post-selection, how do we talk about projects..?

Slide 29

Page 30: Business Driven PMO Setup and Management

Post-selection, how do we talk about projects..?

Slide 30

Where on our PMO dashboards do you find the stakeholder bias

for the project, the will to pay / will to wait

(drop deads) for the project, and the stakeholder

provided benefit of the project..?

Less than 5% of PMO dashboards provide

key stakeholder information..!

What kind of decisions are we facilitating..?

Appearance of good PM (achieving project measures)..?

Reality of good PM (best managing the projects)..?

Page 31: Business Driven PMO Setup and Management

Project Scope Time Cost Budget EAC Overall

Project A

$1.0m $1.3m

Consider the following project characteristics ◦ Project Duration: 6 months

◦ Project Cost: $1m

What is the overall project status..?

Slide 31

Dashboard Policy:

Green = 0-10%, Yellow = 10-25%, Red = >25%

Page 32: Business Driven PMO Setup and Management

Project Scope Time Cost Budget EAC WTP WTW BENE SH Bias Overall

Project A

$1.0m $1.3m $5.0m 12mo $60m Time

Consider the following project characteristics ◦ Stakeholder Bias: Time most important (for this project)

◦ Five Year Benefit: $60m ($1m per month after completion)

◦ Project Duration: 6 months

◦ Project Cost: $1m

◦ Stakeholder Will to Pay: $5m

◦ Stakeholder Will to Wait: 12 months

What is the overall project status..?

Slide 32

Dashboard Policy:

Green = 0-10%, Yellow = 10-25%, Red = >25%

Note: $300k budget overrun incurred, as approved by the sponsor, to avoid a potential project delay of 3

months that has a 50% risk of happening.

Page 33: Business Driven PMO Setup and Management

Three Step Process ◦ Step 1: Establish the Constituent-Determined PMO Mandate

Determine who the constituents of the PMO are

Determine technique for establishing the PMO mandate (ends)

Guidance – 6 months to complete, 3 months if you are really good

◦ Step 2: Develop the PMO Business Plan

Determine business planning approach/template (means)

Use the business planning approach that your company already has

Guidance – 1 to 3 months

◦ Step 3: Execute the PMO Business Plan

Manage the PMO like a business unit “Manage by Objective”

Phase based staffing based upon PMO business plan

Guidance – PMO review meetings are NOT the same as project review meetings and PMO success is NOT the same as project success

Slide 33

Recast annually

Page 34: Business Driven PMO Setup and Management

Tip #1 – PMO Mandate ◦ Nemawashi technique

Business Driven PMO Success Stories (Chapter 5, pages 41-48)

◦ Individual sessions

PMO constituents

Leadership team

PMO steering committee

PMO advisory board

◦ Group meeting(s)

◦ Unanimous agreement on PMO purpose and value

PMO mandate progress reviewed (quarterly)

PMO mandate validated (annually)

Slide 34

Tip #2 – Stakeholder Bias ◦ Project charters

◦ Project status reports

◦ Executive dashboards

If the PMO has a leadership

team determined mandate and

uses stakeholder bias in all

that it does, the PMO will find

success..!

Page 35: Business Driven PMO Setup and Management

One Golden Rule

Slide 35

It’s not your PMO..!

Page 36: Business Driven PMO Setup and Management

Don’t be driven by good intentions…

Slide 36

• Sell pre-determined PMO solution

o Pick a PMO model

o List PMO services

o Present generic PMO benefits

o Ask for management “Buy-in”

• PMO Charter (becomes purpose)

o People, process, tools

o PM training program

o Sell/defend the PMO

Quick wins

Buzz & hype

Popcorn & ice cream

Page 37: Business Driven PMO Setup and Management

Be driven by business needs…

Slide 37

• Leadership team determined (ends to be achieved)

o Report period PMO mandate

o Project-related issues / value

o Vision, mission, goals, objectives

• PMO determined (means to ends)

o Business plan for the PMO

o Strategy components for each objective

o Key PMO capabilities

o Tactics to enable capabilities

People, process, tools, training

o KPIs relative to the PMO objectives

Page 38: Business Driven PMO Setup and Management

Slide 38

Business Driven PMO Setup and Management ◦ Driven by business need, not a PMO model

◦ Managed like a business unit, not an overhead staff org

Practical application ◦ Application of the PMO in response to business needs

◦ Application of PM in response to stakeholder biases

Tangible value ◦ PMO value – fulfillment of PMO mandate, ends to be achieved

◦ PMO manager value – plans/executes the means to the ends

◦ Project manager value – performs to the business context

Always keep in mind ◦ Most do not know the purpose of the PMO

◦ Most do not know the purpose of project management

Page 39: Business Driven PMO Setup and Management

Slide 39

Thank you..!