Business Continuity Plan for the IBO
Transcript of Business Continuity Plan for the IBO
Date approved: 30.10.14
Business Continuity Plan August 2014 (V 1.5)
Date approved: 30.10.14
Version Control
Author Version Date Notes
Wendy Xerri Draft 1 November 2012
Draft 2 April 2013
Draft 3 July 2013
Version 1 September 2013
Document Control
Version Date Distributed Recipients
Draft 1 November 2012 TSD Senior Directorate
Draft 2 April 2013 TSD Senior Directorate
Draft 3 July 2013 TSD Senior Directorate
Draft 4 September 2013 Director of Operations &
Planning
Version 1 September 2013 Audit & Risk Management
Committee
Draft 5 August 2014 Pro-VC(Finance &
Planning)
Senior Corporate
Development Officer
Approved (signature) ....................date .................
Plan director
Approved ......................................date ..................
Date approved: 30.10.14
Contents 1. Executive Summary 1
2. Purpose, scope and responsibility 2
2.1 Purpose 2
2.2 Scope 2
2.3 Role of the PVC (Finance & Planning) 2
3. Normal Operations 3
Carmarthen Campus 3
Lampeter Campus 3
Swansea Campus 4
Techniums Swansea 4
Cardiff Campus 4
London Campus 4
Academic Faculties and Schools 5
4. Incident Management 5
4.1 Critical Incident Definition 5
4.2 Reporting an Incident 6
4.3 Incident Response 7
4.4 Notifying Emergency Services 7
4.5 Fire and Emergency Services 8
4.6 Buffer time and Standby Actions 8
4.7 Site Closure 8
4.8 Incident Management Control 9
5. Business Continuity: Activation Procedures 10
5.1 How the Business Continuity Plan is activated 11
5.2 Roles and Responsibilities: Plan Director and Plan Manager 11
5.3 Members of the Gold and Silver Team 12
5.4 Roles and Responsibilities: Gold and Silver Teams 13
6. Business Continuity: Incident Management Plan 14
6.1 Staff Notification 14
6.2 Notifying Other Offices, Students, Key suppliers and Third Parties 15
6.3 Emergency Communications 15
6.4 Media Response 16
6.5 Gold and Silver Team Actions 16
6.6 Actions Timeline 18
6.7 Team Actions 20
6.7.1 Gold Team 20
6.7.2 Silver External Relations Team 22
6.7.3 Silver Home Site 22
6.7.4 Silver Recovery Site Team 23
6.7.5 Silver Academic Team Tasks 24
6.7.6 Silver Operations Team Tasks 25
6.7.7 Silver Student/Staff Liaison Team Tasks 25
6.7.8 Departmental Responsibilities 26
7. Recovery Process 26
Date approved: 30.10.14
7.1 Alternate Work Locations 26
7.2 Recovery of Premises 27
7.3 Recovery of People 27
7.4 Recovery of Technology 27
7.5 Recovery of Information 28
7.6 Recovery of Critical External Suppliers 28
8. Standing the Plan Down 28
9. Audit, Review, Maintenance and Testing 29
Appendices
Appendix 1 – Gold and Silver Team Members 31
Appendix 2 – Salvage Team and Actions 34
Appendix 3 – Recovery Site Location and Contacts 35
Appendix 4 – Succession Planning 36
Appendix 5 – Telephone Cascade 37
Appendix 6 – Staff Contact Details 37
Appendix 7 – Staff Recovery Locations 38
Appendix 8 – Partner Institution Contact Details 41
Appendix 9 – Key Supplier Contacts 41
Appendix 10 – Bank Account Details 41
Appendix 11 – Battlebox 41
Appendix 12 – Emergency Evacuation Plan 42
Appendix 13 – Activity Log 43
Appendix 14 – Call-Out Procedure 44
Appendix 15 – Stakeholder contact Details 44
Appendix 16 – Emergency Information Sources and Local Radio 44
Appendix 17 – Insurance Company/Loss Adjuster Details 45
Appendix 18 – IT DR Plan and Voice Diversion Procedures 45
Appendix 19 – Holding Statement 45
Appendix 20 – Buffer time Action 46
Appendix 21 – Assumptions 47
Appendix 22 – Critical Dates Calendar 47
1 Date approved: 30.10.14
1. Executive Summary
The Business Continuity Plan (BCP) identifies the functions that need to be restored for
normal operations to be resumed after an incident at University of Wales Trinity Saint David.
The objective is to resume operations and supply services to internal and external clients to
an acceptable level, in an acceptable timescale. As clients are serviced globally any incident
that affects South-West Wales has a potentially major impact, not just an incident during
working hours.
This document has been written as a repository of information. It is not a policy document
it is an action plan for use in the event of a disaster.
The plan is structured to deal with a local incident impacting the Carmarthen, Lampeter, and
Swansea campuses, and incidents affecting UW Trinity Saint David’s campuses in Cardiff
and/or London.
Incident Management deals with the immediate impact of an incident and the process of
evaluation. Options for response are either ‘back-to-business’ where there is no impact on
operations, use of ‘buffer time’ where a situation is unclear or the activation of the plan
where disruption to services is obvious and immediate.
The procedures to activate the BCP are described, together with the responsibilities of the
Gold and Silver teams. The tasks and timelines of the recovery teams are defined for use
once the BCP has been invoked.
The recovery processes for premises (including alternative locations), people, technology,
information and key suppliers are described, and the conditions governing the controlled
method of standing the BCP down are identified.
Supporting all aspects of the BCP are a number of Appendices. There are Appendices relating
to the members of the Gold and Silver teams, contact information for all staff and other key
contacts, a telephone cascade, succession planning and staff recovery site information. A list
of standby actions supports preparation during buffer time. The critical functions of IT, with
the priorities and timescales for restoring services and servers are incorporated along with
the technical IT Disaster Recovery Plan.
This document contains all the information required to restore operations in the event of
acute disruption. It has also been designed to be a flexible recovery tool, and can be used in
part, in the event of less serious incidents.
2 Date approved: 30.10.14
2. Purpose, scope and responsibility
2.1 Purpose
The purpose of this Business Continuity Plan is to enable the operations of the University of
Wales: Trinity Saint David to survive a critical incident that disrupts normal operations and
working practices. The Plan has been arrived at through a business continuity management
process undertaken by the University. It is based on the information obtained and agreed in
the Risk Assessment / Business Impact Analysis.
Within this plan is the method of activation, detailed responsibilities and timelines for
recovery and a process for standing the plan down.
2.2 Scope
This plan addresses the operations that are undertaken at the Carmarthen, Lampeter, and
Swansea campuses, and at the two campuses of University of Wales: Trinity Saint David in
Cardiff and London as at June 2014.
It is possible that an incident may occur that impacts on the whole of the South Wales
region, affecting the Carmarthen, Lampeter, Swansea and Cardiff campuses. It is likely that
an event of this scope would have a significant impact on transport links, and recovery could
not progress until staff could manage to reach the recovery site.
The loss of any campus could be a serious issue during exam sessions. However, this could
be dealt with as part of normal operations as long as another campus was still functional.
However, a critical incident at any one campus that causes injury or death to University staff,
students, guests or visitors, or has the potential to damage the reputation of the University,
may cause the plan to be initiated.
2.3 Role of the PVC (Finance and Planning)
The PVC (Finance and Planning) has responsibility for Business Continuity Management
(BCM) in the University and is the Plan Director. His role is to:
- Integrate the Business Continuity Plan;
- Introduce staff to the BCM programme, and define what it means to them;
- Have a process for identifying and delivering BCM training requirements to relevant
staff and evaluating the effectiveness of its delivery;
- Develop a testing strategy with regular exercises, and involve a variety of staff in
these exercises;
- Keep critical staff up to date with reference to their BCM skills;
- Place information on the Intranet about BCM;
- Add BCM into regular staff meetings;
- Ensure that documentation is kept up to date, completed, reviewed regularly and
signed off.
3 Date approved: 30.10.14
3. Normal Operations
The University of Wales: Trinity Saint David operates on five different sites - Carmarthen,
Lampeter, Swansea, Cardiff and London.
Carmarthen Campus
The original 1848 building lies at the heart of the Carmarthen campus. Sweeping lawns and
landscaped areas form a picturesque setting for the mix of Victorian and modern buildings.
The campus boasts a range of facilities including a well-stocked library and excellent learning
and teaching spaces, a fully-equipped theatre and workshops, media and music suites as
well as IT facilities which include refurbished open access areas and rooms for students to
complete group work.
Sports facilities include the Sports Centre with a Health and Fitness Suite, swimming pool, a
multi-purpose dance studio. Students Services and Students’ Union are both located in their
own buildings on the campus enabling students to access their facilities and services easily.
Student accommodation includes catered and self-catering halls which are located on the
campus.
Art and Design are offered jointly with Coleg Sir Gâr and include studios, exhibition spaces
and workshops. A new Learning and Teaching block built during the 2012-13 provides
enhanced facilities.
Lampeter Campus
The campus was founded in 1822 as St David’s College to provide a liberal education to
members of the clergy including Classics and History amongst other disciplines. Over the
years it developed the range of subjects and, as the University of Wales Lampeter, enjoyed a
reputation for undergraduate and postgraduate provision in Archaeology, Chinese, Classics,
History, Theology, as well as others including Business and IT.
The campus facilities boast one of the best libraries and private collections of medieval
manuscripts in the country - The Roderic Bowen Library and Archives - as well as the Arts
Hall and Cliff Tucker Theatre which are modern and well-equipped venues used for lectures
as well as arts and community events.
Major refurbishment has been carried out across the campus including the creation of a
centre in the Canterbury Building for the integrated Student Services Department and other
student-facing services. The University’s sports facilities have been enhanced and include
joint provision between the University and Ceredigion County Council. In addition, student
accommodation across the campus has been renewed and upgraded.
Swansea Campus
4 Date approved: 30.10.14
Swansea is surrounded by resorts, parks, wildlife centres, caves and castles and the Gower
Peninsula was the first part of Britain to be awarded the title of ‘Area of Outstanding Natural
Beauty' by the Government in 1956. It is one of the most stunning peninsulas in the UK, with
wide, clean sands and steeply cliffed coves protected by thick woods.
The Swansea campus is spread across a number of dedicated buildings - all within walking
distance of Swansea city centre. Each subject area has its own dedicated facilities relevant to
the needs of students, from the workshops where formula student racing cars are designed
and built, to the art and design studios where students have spaces set aside to develop
their ideas. The University is currently investing in new and improved facilities and buildings
on the Swansea campus; the aim is to have industry standard facilities for students so that
when they progress to employment they are able to thrive in their future careers.
There are dedicated subject-relevant libraries across campuses and all students have access
to IT suites and remote access to library services and study materials through an online
library catalogue and virtual learning environment.
Techniums Swansea (Techniums 1 & 2) is also part of the Swansea campus. Techniums
Swansea is a unique facility in Wales, offering a 60,000Sq foot incubation facility for
companies undertaking web and computer technical design. The site houses approximately
20 organisations including Cyden, OSTC, and a number of small start-up companies.
Cardiff Campus
The Cardiff campus is the location for the Welsh International Academy of Voice, which
provides a highly specialised and unique environment for a small number of exceptional
singers at the early-professional stage, selected and recruited globally to develop and polish
their talent to the highest professional standards.
London Campus
TSD London is a new development providing an opportunity for predominantly international
students to study a range of programmes in one of the safest areas of London, along with
other professional based courses/employment training offered to students domiciled within
the UK. It is located at Winchester House, Cranmer Road, London SW9 close to both the
Oval Underground station and the Oval cricket ground.
These programmes are offered by University of Wales: Trinity Saint David’s School of
Business, and as such are of the highest academic standard, being part of the University’s
commitment to a growing number of international students.
Academic Faculties and Schools
The University consists of five faculties:
Faculty of Architecture, Computing & Engineering;
5 Date approved: 30.10.14
Faculty of Art & Design;
Faculty of Business and Management;
Faculty of Education and Communities;
Faculty of Humanities and Performing Arts.
The University of Wales: Trinity Saint David offers high quality education through a range of
undergraduate and post-graduate programmes of study and, throughout the year a range of
activities are held in areas such as professional development. Workshops and conferences
are also held regularly.
The restoration of ‘normal’ services includes:
- Protection of staff, students, visitors and clients;
- Control of the flow of information about an incident;
- The communication to all staff and students of immediate contingency arrangements;
- Collection and processing of inbound post;
- Formulation of an insurance claim with loss adjuster.
The Business Continuity Plan is structured to deal with critical incidents that affect the
following areas, either singly or in combination:
- Premises;
- People;
- Technology – Infrastructure;
- Information and Data;
- Key Suppliers.
To ensure the maximum flexibility, it is not based around the response to specific scenarios,
but looks at the effects any incident might have.
4. Incident Management
Critical Incident Definition
A critical incident may be defined as any event which threatens to severely disrupt (in whole
or in part) the functioning of a faculty, service or the University as a whole, and/or which
carries the risk of significant adverse publicity.
Whilst it is probably impossible to identify in advance all types of event which would
constitute a critical incident, it would be likely to include the following characteristics:
There are substantial threats to the safety or well-being of individuals or to the
fabric or reputation of the institution; and
The incident is likely, or has the potential, to lead to the suspension of normal
operations.
6 Date approved: 30.10.14
It follows that a critical incident might require:
The calling out of the emergency services;
Special communications mechanisms; and
The necessity to manage a high level of media interest.
Possible examples of critical incidents could include; a major fire or explosion, an occurrence
or outbreak of a contagious disease, such as meningitis.
The majority of incidents are dealt with by the normal management processes of the
business. The Business Continuity Plan will be activated if the incident is of such a critical
nature that normal operations at any or all campuses are unable to continue. In the majority
of cases it is expected that an incident will only partially close a campus, allowing the control
centre (see 4.8 below) to remain at that campus and the rest of the campus to operate as
normally as possible.
The initial response to an incident is described in this section, including the concept of buffer
time where recovery services are placed on standby or time consuming actions started.
There is a sliding scale between ‘normal operations’ and ‘total disruption’. It is important in
the response to an incident to keep definitions as simple as possible – if there is no impact
on operations, then the organisation can go ‘back to business’. There will be a level where
there is some impact, but the extent may be unclear, and here the organisation should
either implement ‘buffer time’ or initiate the plan. Finally, there will be a level where there is
an obvious impact on operations, and the plan should be initiated immediately.
Some incidents may become more severe over time through events outside the control of
the University. As long as this is understood, and any incident is monitored over time, then
the response can be scaled up at any point. It is always better to err on the side of caution
and initiate the plan which can then be stood down, than to do nothing.
4.1 Reporting an Incident
During working hours most incidents will be resolved by the normal processes and
procedures of the business, following normal reporting lines.
Normal Working Hours
If the incident affects a site, the Emergency Evacuation Plan (see 4.5 below) should be
followed. The Gold team (see 5.7.1 below) will then assemble and assess the situation,
taking advice from the emergency services if they have attended the site.
NB: Personal welfare is of paramount importance, and site evacuation (if required) and the
instructions of the emergency services take priority over all other actions.
Out of Hours - during the night, at weekends or on public holidays.
7 Date approved: 30.10.14
If an incident occurs out of hours at any campus, onsite security will contact an individual on
the Call-Out procedure list (see Error! Reference source not found.). The Call-Out list is appended to certain copies of the BCP due to the confidential nature of the information it contains.
Out of Hours Contact Numbers
Carmarthen campus – duty porter 07767 842738
Lampeter campus – duty porter 07854 458920
Townhill campus – duty porter 07837 591368/07850 321705
Mount Pleasant campus – duty porter 07850 321705
Ty Bryn Glas, Alexandra Road, Dynefor - duty porter 07850 321705
Cardiff (WIAV) – 02920 396576 (Masonic lodge (next door))
London campus – security staff 07972 660557
Emergencies not notified.
If an incident outside normal working hours is not notified through the out-of-hours process,
it will not become apparent until staff begin arriving for work. In this case, the first member
of senior management on site will be responsible for:
contacting emergency services, if staff have not already done so; and
informing the members of the Gold team (see
Appendicles
) who will decide on the appropriate response.
4.2 Incident Response
The options for responding to an incident are as follows:
if the incident is minor, and does not impact on the operations of the University, then
the process ends and return to normal working is declared;
if the incident is unresolved then it must be continuously monitored until a decision can
be made to either return to normal operations, or to activate the Business Continuity
Plan. Buffer time may be utilised (see Buffer Time and Standby Actions), placing recovery
services on standby and starting time consuming actions (see Error! Reference source
not found.);
if the incident has an immediate impact on operations, or has caused serious injury or
death to University staff, students, guests or visitors, then the plan should be activated
immediately.
4.3 Notifying Emergency Services
At any time a member of staff may contact the emergency services by dialling 999,
requesting the appropriate service and reporting the nature and location of the incident.
During working hours the incident should then be reported immediately to the Plan Director
or, if they are not immediately available, to another director or a member of the Gold team.
8 Date approved: 30.10.14
If in doubt, an individual discovering an incident should report to reception who will pass the
information to the Plan Director (Pro VC (Finance& Planning) & HR) or, if they are not
immediately available, to the most senior, relevant individual onsite at the time
When the emergency services arrive on site they will be met by the Plan Director and, if an
evacuation has taken place, the Emergency Services Liaison.
4.4 Fire and Emergency Evacuation Plans
The University fire and emergency evacuation plans will be used and are not compromised
or superseded by this document. A copy of the University fire and emergency evacuation
plans are attached as Error! Reference source not found..
Fire Wardens will check their areas and report their status to the Emergency Services
Liaison. This information will then be passed to the attending emergency services. The Fire
Incident Commander can be identified by a white tabard.
If an incident requires staff to shelter on-site, the evacuation procedures should be followed.
If a bomb threat is received, as much information as possible should be obtained from the
caller. The instructions of the emergency services must be followed, but would normally
involve keeping staff at their desks and using fire wardens to sweep their areas for anything
unusual.
4.5 Buffer Time and Standby Actions
‘Buffer Time’ is a concept to ensure that no time is lost in the response to an incident. If the
impact of an incident is uncertain (e.g. a gas leak), a period of up to 24 hours may be allowed
to gather information and make a decision. During this time, actions that are time
consuming may be started with the understanding that, if the situation is resolved, they may
be stood down.
At any time during buffer time, the plan may be initiated or ‘back-to-business’ instructed. If
the situation is not resolved after 24 hours, the plan must be initiated by default.
4.6 Site Closure
Partial Closure
The layout of each campus means that it is possible that only parts of the premises are
affected by an incident. In the majority of incidents it is expected that an incident will only
partially close a campus, allowing the control centre to remain at that campus and the rest
of the campus to operate as normally as possible. If this is the case, it may be decided by the
Gold Team to continue some presence in the offices. However, this will only be where
Health & Safety criteria can be met, specifically:
The emergency services confirm there is no further danger;
The Insurance Company agrees to this (where a claim will be made);
Safe access / egress can be maintained;
Heating, lighting, sanitation, power, and network access are available;
9 Date approved: 30.10.14
The unaffected area is secure;
There is adequate containment (fire or security doors etc.) from the damaged areas.
Full Closure
Where a critical incident has occurred, the emergency services may require the closure of
the premises. When this decision is made during office hours, line managers will be
informed to send staff home, to a recovery centre or to another appropriate venue. Where
closure is initiated out of hours, the Gold team will notify line managers of the situation via
the telephone cascade (see Error! Reference source not found.). Dependent on the
circumstances, line managers may be directed to:
Stay at home pending further instructions;
Attend the office, if closure is not the result of damage (e.g. through a gas leak);
Attend the recovery site;
Contact their staff according to the telephone cascade.
Security Arrangements
Where it is not possible to secure the building by normal means (alarms and locks) owing to the nature of the damage, the Silver Home Site team (see .
Roles and Responsibilities: Gold and Silver Teams) will liaise with the emergency services and give consideration to:
the boarding up / sealing off, of potential points of entry (windows, doors etc.);
the engagement of extra security staff to guard the premises.
Public Access
Public areas will be kept closed until it is safe and convenient for members of the public to
re-enter the building. Prominent notices will be posted at the front door. Any regular visitors
will be contacted by staff in the department to notify them of a closure / restricted service,
and of alternative arrangements. If a member of staff has made an appointment with an
external party, they must contact them to either cancel or reschedule the appointment, if
necessary.
4.7 Incident Management Control Centre If access is denied to the Carmarthen campus, the Gold Team will assemble at the
Lampeter campus which will be the Incident Management Control Centre.
If access is denied to the Lampeter campus the Gold Team will assemble at the
Carmarthen campus, which will be the Incident Management Control Centre.
If access is denied to the Mount Pleasant campus the Gold Team will assemble at the
Townhill campus which will be the Incident Management Control Centre.
If access is denied to the Townhill campus the Gold Team will assemble at the Mount
Pleasant campus which will be the Incident Management Control Centre.
10 Date approved: 30.10.14
If access is denied to Alexandra Road, Dynefor or Ty Bryn Glas, the Gold Team will
assemble at the Mount Pleasant campus which will be the Incident Management Control
Centre.
If access is denied to Technium 1 the Gold Team will assemble at Technium 2 which will
be the Incident Management Control Centre and vice versa. If both buildings are
unavailable, the Gold Team will assemble at the Mount Pleasant campus
If access Is denied to the Cardiff campus, the Gold Team will assemble at the University
of Wales, Cardiff.
If access is denied to the London campus the Gold Team will assemble at serviced
accommodation.
5. Business Continuity: Activation Procedures
In the event of a critical incident that may cause death or injury to staff, students, guests or
public, damage to or destruction of University property, the alarm must be raised
IMMEDIATELY (as per the University emergency plan – see Error! Reference source not
found.) and the emergency services contacted.
During working hours, any incident (at any campus) that could affect the operations of the
University should be bought to the attention of the Plan Director. The Plan Director must
then assess the incident – if necessary on an on-going basis – and keep the Gold Team
informed so that they may make a decision as to whether they should invoke the Plan. It is
possible that an incident may be of such magnitude that the Gold Team can make a decision
without waiting for confirmation from the Plan Director.
If an incident occurs at the Carmarthen, Lampeter or Swansea campuses out of hours, the
duty porter will contact an individual on the Call Out procedure list. The nature and scale of
the incident should be established, and this may require a visit to the site. The Gold Team
must be informed, and should assemble at the Carmarthen campus if it is accessible, or at
the Lampeter or Swansea campus to review the situation. If an incident occurs on the
Cardiff campus out of hours, staff at the Masonic Lodge will contact an individual on the Call
out Procedure list. If an incident occurs on the London campus security staff will contact an
individual on the Call Out procedure list.
11 Date approved: 30.10.14
No Majority Majority
Yes
No
5.1 How the Business Continuity Plan is activated.
Activation of the Plan is the responsibility of the Gold Team. They must take a view on how
the incident may impact on the operations of the University.
If an incident has occurred and the situation is not clear the decision may be taken to utilise
‘buffer time’. During this time, actions that are critical and have a lead time may be started.
At any point in the buffer time the plan may either be activated or stood down. Buffer time
must not exceed 24 hours from the time of incident.
The plan is activated by a simple majority of those members of the Gold Team available
at the time when the decision is taken.
If the members are evenly divided then the most senior member will have the casting
vote.
If there is no member with obvious seniority then a tied vote will be taken as a vote for
activation of the plan.
The location of the Incident Management Control Centre will be determined by the Gold
Team. If an incident results in the evacuation of any campus, the members of the Gold
Team should assemble immediately and, depending on the weather conditions, make a
decision as to what to do with staff.
5.2 Roles and Responsibilities: Plan Director and Plan Manager
The Plan Director and Plan Manager, and their deputies have the responsibility for
maintaining the Business Continuity Plan. The Plan Director is the high level champion of the
project, responsible for keeping the profile of business continuity high on the business
agenda. They also have a critical role to play in the activation of the plan. The Plan Manager
Gold Team Assemble at Incident Management Control Centre
Vote taken on plan activation
Activate
Back to Business
Buffer Time
Senior Member present?
Casting Vote
12 Date approved: 30.10.14
is responsible for the administration of the plan and drives the regular updating and testing
of the document.
Plan Director: Pro-VC (Finance & Planning) & Executive Head of IT/IS
Plan Manager: Director of Operations and Senior Campus Manager
The contents page has a clear expiry date for the validity of the plan, and it should be
updated and re-issued accordingly. Old versions should be collected by the Plan Managers
and securely destroyed. Any changes to personnel, premises or process that impact the
organisation must be reviewed in relation to Business Continuity.
5.3 Members of the Gold and Silver Teams
The members of the Gold Team are listed in the following table. This table should be used to
record any vote for invocation.
Title Vote for activation of
plan (Y / N / Buffer time)
Signature
PVC (Finance and Planning)
PVC (Academic)
PVC (Student Experience)
Executive Head of IT/IS
Director of HR
Once the decision has been taken to invoke the plan, the Silver Teams must be informed.
The following table details the responsibilities for contact:
Team Member to contact Responsibility of Assemble at
External Relations Head of Corporate
Communications &
PR
Gold Team
member – to be
decided at time of
invocation
Affected Site
Home Site Senior Campus
Manager
Affected Site
Recovery Site Director of
Operations
Recovery Site
Academic Dean of Quality and
Enhancement
Recovery Site
Operations Director of Finance Recovery Site
Staff / Student
Liaison
Director of Student
Services
HR representative
Affected Site
13 Date approved: 30.10.14
Each team head is then responsible for informing the other members of their team, as per
the cascade in Appendix 6 - Staff Contact Details.
Roles and Responsibilities: Gold and Silver Teams
The Gold Team have the responsibility for activating the plan. Once it is initiated, they have
the responsibility for strategic decisions concerning recovery. They must also make the initial
contact to the Silver Teams to inform them that the plan has been activated.
In the immediate aftermath of an event the flow of information may be chaotic and a
system is required to prioritise this information and assess its reliability. The following
system has been agreed:
Priority
Level One Information that has a direct and immediate impact on staff and/or
students, or the operations of the University.
Level Two Information that may indirectly impact on the operations of the University.
Level Three Information that will have no impact on the operations of the University.
Reliability
High Same information from two or more direct sources.
Medium Information from one direct source, television or radio.
Low Information from an indirect or uncorroborated source.
Level 1 Level 2 Level 3
High Critical Important Relevant
Medium Important Relevant Relevant
Low Relevant Relevant Relevant
All information used to take decisions must be kept for the post event review.
There are six Silver Teams. These should be additional staff to those members of the Gold
Team. Their roles and responsibilities are detailed below:
Silver External Relations team will control the flow of information to the media, other
campuses, key suppliers and students. An appointed spokesperson will have sole
responsibility for speaking on behalf of the University.
Spokesperson: Head of Corporate Communications & PR
Members: Additional, identified member of Corporate Communications & PR
14 Date approved: 30.10.14
Silver Home Site team usually has an IT member, an HR member and a member of the
Technical Services Team. Depending on the nature of the incident, a Salvage team may also
be convened (see Error! Reference source not found.).
Emergency Services Liaison: Senior Campus manager
Members: Head of Information Services and identified member of HR
Silver Recovery Site team will prepare the alternative campus (if necessary) for the teams
that are going there. This team consists of IT to recover the IT environment, HR to handle
pastoral care and organise reception staff to answer voice lines as soon as they are
transferred, if possible.
Members: Director of Operations, IT Manager and an identified member of HR
Silver Academic Team will be responsible for ensuring that the process of maintaining
academic programmes and assessment continues.
Members: Dean of Quality & Enhancement, Dean(s) of the affected Faculty(ies) or Head of
School and an identified member of Registry
Silver Operations team will restore all other functions of the University including Finance,
and Facilities.
Members: Director of Finance, Head of Facilities
Silver Staff/ Student Liaison will be responsible for communication to staff and students and
securing alternative student accommodation if required.
Members: Director of Student Services, Accommodation Officer, HR representative
In the event of an incident that requires a site to be evacuated during working hours, the fire
evacuation procedure should be followed. If, for whatever reason this is not possible, staff
and students should assemble in the following areas:
The Llwyfan car park on the Carmarthen campus;
The Hockey Pitch on the Lampeter campus;
The staff car park on the Mount Pleasant campus;
The car park behind the main teaching block on the Townhill campus;
The car park at Ty Bryn Glas;
The car park at the rear of the Dynefor building;
Alexandra Road – to be confirmed;
The car park at the rear of the WIAV building at the Cardiff campus;
The courtyard at the rear of Winchester House
Fire wardens should sweep their areas and report to the Emergency Services Liaison for the
site, who will then coordinate with the Emergency Services on their arrival.
15 Date approved: 30.10.14
6. Business Continuity: Incident Management Plan
6.1 Staff Notification
The loss of IT systems may result in the loss of the HR system or access to it, and therefore
to the staff contact details it contains. A hard copy of staff contacts is to be kept in the
Battlebox (see Error! Reference source not found.) and managers should have their team’s
details on their mobile phones.
During working hours all staff on site not immediately required will be briefed before being
sent home. In the event that they are unable to retrieve their cars, the Home Site team will
organise transport to take staff home. Once any staff absent from the site have been
identified (e.g. through sickness or holiday), their managers will be advised and these staff
will be contacted and appraised of the situation.
For an incident outside normal working hours the Gold Team will use the telephone cascade,
if the phone networks are available, to advise all staff of the situation. Contact is as
described in the Telephone Cascade and Staff Contact Details in Appendices 5.1., 5.2. and 6.
If an incident is not perceptible until staff start to arrive for work they should wait to be
advised by their manager as to what is required of them.
For all of the above the number of individuals required for recovery at different locations is
detailed in Appendix 7. Actual staff will be confirmed at the time, taking into account
injuries, holidays and sickness. The Recovery Site team should co-ordinate the lists of staff to
ensure site security. Staff not immediately required will be instructed to return home and
await further instructions.
6.2 Notifying Other Offices, Students, Key Suppliers and Third Parties
Contact will be arranged by the External Relations team. For an incident at the Carmarthen
campus, the Lampeter & Swansea campus should be informed immediately, and they will
notify the other University offices. For an incident at the Lampeter, Swansea, Cardiff or
London campuses, all SMT members currently in Carmarthen should be informed, and they
will then co-ordinate the flow of information to other University offices.
Contact details for other offices are contained in Appendix 23, for Critical Suppliers in
Appendix 9.
6.3 Emergency Communication
In the event of an incident that has caused a significant impact to the operations of the
University, or may be perceived as having done so (e.g. an incident in the surrounding area),
the following methods of communication should be utilised.
Website – the front page should be replaced with one that acknowledges an incident has
occurred and that a response is underway. If an incident affects access to South Wales, but
16 Date approved: 30.10.14
systems are still running, this can be done by a regional office. If the systems are down, this
will be done as part of the restore process.
Telephone – if the site is evacuated it would not be possible to answer inbound calls.
Email – The email system will be available on the Carmarthen, Lampeter and Swansea
campuses under normal circumstances, unless the incident itself affects the e-mail system.
University of Wales: Trinity Saint David Council – will be contacted by the Vice Chancellor.
6.4 Media Response
Examples of Holding Statements that may be released in the immediate aftermath of an
incident are attached in Error! Reference source not found.. Press releases will be
composed by the Head of Corporate Communications & PR, who is also the nominated
spokesperson for the University). No other member of staff is authorised to speak on behalf
of the University. All inbound requests for information or comment should be forwarded to
the Silver External Relations team.
6.5 Gold and Silver Team Actions.
The following timelines and flowcharts detail the actions from incident to plan stand down
for all teams. This plan has been designed as a flexible recovery tool, and these actions
should form a guideline rather than a prescriptive framework. The Carmarthen campus has
been used as an example – suggested timelines and flowchart below could be used for any
site.
17 Date approved: 30.10.14
External Relations Recovery Site Home Site Operations Academic
Assemble at or near
to the Carmarthen
campus
Assemble at
Lampeter campus
Assemble at
Carmarthen campus Assemble at
Lampeter campus
Assemble at
Lampeter campus
Issue holding
statement to the
media, deal with
external enquiries
Prepare Lampeter
campus for the
arrival
of University staff.
Monitor casualties,
assess the damage to
site, liaise with the
emergency services
Assess impact,
restore critical
activities, prioritise
recovery of backlog.
Take decision as to
whether normal
processes can
continue
Liaise with
University offices,
media and
stakeholders.
Relocate restored IT
systems to campus
or new site and
acquire to network
Contact Loss
Adjustor, establish
timescale for site
recovery
Return to normal
working operations,
catch up with any
process backlog
Return to Faculty
offices etc. and
work out timescales
for issues
Normal operations resumed - Home Site restored or replacement site sourced.
IT hardware rebuilt, network recreated, data uploaded and acquired, telecoms restored.
STAND DOWN BUSINESS CONTINUITY PLAN
Staff / student
Liaison
Assemble at
Carmarthen campus
Deal with staff /
student queries and
liaise with External
Relations
Establish whether
staff / students need
to be relocated to
another campus
Business Continuity Plan activated by Gold Team
Incident at Carmarthen campus
18 Date approved: 30.10.14
6.6 Actions Timeline
Activating the Plan should allow the operations of the University to be restored to a
minimum acceptable level within the Maximum Tolerable Period of Disruption defined by
the business and recorded in the IT Disaster Recovery Plan. The resources should be
available to achieve the following:
Incident
During working hours, the University emergency plan followed; outside working hours,
Plan Director notified and informs Gold Team if appropriate.
Gold Team review the situation:
If incident is minor and has been dealt with, no action is taken;
If impact of incident is unclear, buffer time is utilised;
If incident is obviously going to impact on the operations of the University,
Business Continuity Plan is invoked.
Gold Team to assemble at the Incident Management Control Centre to manage initial
response to incident.
BCP invoked:
Gold Team inform all Silver teams. Decision made as to whether to send staff home or to
keep them available. If sending them home, decision made about providing transport
and locksmiths as required;
Liaison with emergency services, next of kin contact (through emergency services),
casualty management, grief counselling all implemented as required;
Silver Home Site team make initial damage assessment, contact Loss Adjustor and
discuss salvage potential with Emergency Services;
Silver Recovery Site team prepare the Recovery campus The University’s telecoms
provider will be contacted to divert lines to the recovery site. As Carmarthen is a C-Pop
installation for the regional PSBA circuit, the PSBA may have to be informed of the
incident;
Silver External Relations team release holding statement and contact other University
offices with a situation report. Public website restored as part of IT recovery;
Silver Operations team on standby to attend the Recovery campus;
Silver Assessment team decide the impact to the examination schedule;
Silver Student/Staff liaison team on standby at the affected site;
Cascade of information to all staff begins.
4 – 24 hours:
Recovery campus- re-build of IT servers starts, as per IT DR plan;
19 Date approved: 30.10.14
Silver External Relations distribute prepared message to University offices, media and
stakeholders;
Telephone lines continue to operate through the central switchboard at the recovery
site;
Silver Recovery Site Team answer diverted telephone lines;
Silver Operations Site to notify insurance company and begin discussion with the
managing agent;
Decision taken by Gold Team as to whether to prioritise personal or business items for
salvage. Silver Home Site team collate department salvage lists with Heads of
Departments and liaise with emergency services.
24 – 48 hours:
IT systems are restored at the Recovery Site. Servers and PCs are built; data is restored
and acquired to the network;
The Silver Operations team begins recovery projects.
48 – 72 hours:
Staff continue to report to their recovery site locations as detailed in Appendix 7;
Remote access begins to become available to people working at home or in other
locations.
7 days:
On-going review by Gold Team of service levels to affected offices and campuses;
Board review impact on reputation;
Finance informs SMT(and / or University Council) of anticipated financial implications.
Beyond 7 days:
Assessment of length of dislocation from Home Site is made;
Decisions are made on where staff will work in the medium to long term;
New equipment is purchased and prepared for data transfer at the new or restored site;
Insurance claims are finalised;
If any staff members have been injured, decisions need to be taken by the University
whether to temporarily replace or reorganise;
All University offices are kept informed of situation.
Up to 3 months:
20 Date approved: 30.10.14
Normal operations resumed either at original site or at new location. New IT hardware
built and data restored to it. Plan stood down, debrief occurs and lessons learned are fed
back into the plan.
21 Date approved: 30.10.14
6.7 Team Actions
6.7.1 Gold Team
Description Time from incident or invocation
Comments Sign Off
0. Incident occurs at one of the five campuses: no resolution possible.
0 hours
If in normal working hours
1. Emergency Evacuation Plan followed
Immediate
2. Gold team assemble to review the situation.
Immediate
3. Decision made as to whether to invoke the plan, use buffer time or go back to business.
Immediate
4. If buffer time used, standby actions started.
Up to 24 hours
5. If incident unresolved within 24 hours, plan must be initiated.
Up to 24 hours
6. If incident resolved, standby actions stood down.
Up to 24 hours
If disaster notified when staff start to arrive on site
7. The first Plan Director or Plan Manager to arrive at the site notifies the emergency services if not already done.
Immediate
8. Plan Director / Plan Manager notifies the members of the Gold Team
Immediate
9. As per actions 2 – 6 above. As above
If out of normal working hours
10. Out of hours contact notified by duty porter/security staff.
0 hours
11. Out of hours contact attends site if necessary. If incident is likely to
0 – 1 hours
22 Date approved: 30.10.14
affect operations, Gold Team notified.
12. As per actions 2 – 6 above. As above
If Plan is invoked:
13. Plan invoked – notify Silver teams 0 – 2 hours
14. Silver Home Site monitors casualties and provide next of kin information to the emergency services as required. Any casualties notified to the Gold Team.
0 – 4 hours
15. Reception notified to expect increase in call volumes if phone network available. Message to all stakeholders prepared in conjunction with Silver External Relations.
0 – 2 hours
16. Decision made as to whether staff to be sent home. If staff vehicles inaccessible, liaise with Silver Home Site to organise transport.
0 – 4 hours
17. Gold Team instruct Silver External Relations to prepare and distribute holding statements
2 hours
18. Recovery Site campus is prepared. Silver Operations assemble and report impact on operations to Gold Team.
4 hours
19. Gold Team continue to collate and assess information about incident
Ongoing
20. Silver External Relations handle media enquiries and continue to provide updates all stakeholders.
Ongoing
21. Silver Home Site report on damage to site. Gold Team make decision about working arrangements in the medium to long term.
Ongoing
23 Date approved: 30.10.14
22. Gold Team declares return to normal working, stand down the Plan
Up to end Month 3
23. Gold Team initiates post event debrief
Post event
6.7.2 Silver External Relations Team
Description Time elapsed Comments Sign Off
0. Incident occurs. 0 hours
1. Gold Team advises Silver External Relations Team that plan has been invoked.
Immediate
2. Silver External Relations prepare and distribute holding statements, notify all other University locations.
2 hours
3. Silver External Relations update website with information
4 hours
4. Silver External Relations handle media enquiries and continue to provide updates for all stakeholders.
Ongoing
5. Debriefing and stand-down. 3 months
6.7.3 Silver Home Site
Description Time elapsed Comments Sign Off
0. Incident occurs. 0 hours
1. Gold Team advises Silver Home Site Team that plan has been initiated.
Immediate
2. Silver Home Site Team assemble at affected site).
Immediate
3. Silver Home Site monitor casualties and provide next of kin contact information to the emergency services
0 – 2 hours
24 Date approved: 30.10.14
4. Staff allocated to attend hospital with any casualties. Grief counselling put on standby if required.
0 – 24 hours
5. Silver Home Site Team assess damage to the site and contact Loss Adjustor. Potential of salvage investigated and salvage priorities established from departments and Gold Team.
On-going
6. Salvage Team assembled if emergency services are likely to permit salvage.
On-going
7. Silver Home Site provides Gold Team with report on state of home site and likely length of dislocation.
Week 1
8. Silver Home Site advises site recovery or reconstruction options to Gold Team.
On-going
9. Gold Team make decision on move to a new site / return to original site
On-going
10. Silver Home Site manage restoration of home site or move to new site in conjunction with Silver Recovery Site
On-going
11. Debriefing and stand-down. 2 months
6.7.4 Silver Recovery Site Team
Description Time elapsed Comments Sign Off
0. Incident occurs. 0 hours
1. Gold Team advises Silver Recovery Site Team that plan has been initiated.
Immediate
25 Date approved: 30.10.14
2. For local incident Silver Recovery Site assemble at the Carmarthen, Lampeter or Swansea campus. For regional incident, Silver Recovery Site to be located at the Cardiff campus. For a local incident at the Cardiff campus, Silver Recovery Site to be located at the University of Wales, Cardiff. For a London incident, Silver Recovery Site will be located at serviced accommodation
2 hours
3. Local or Regional recovery site prepared.
2 – 6 hours
4. IT rebuild commences. From 6 hours
5. IT systems restored and acquired to the network
Up to 96 hours
6. If the Carmarthen, Lampeter or Swansea campus not operational in the medium to long term, Silver Recovery Site involved in the acquisition and equipping of new site.
On-going
7. Debriefing and stand-down. 3 months
6.7.5 Silver Academic Team Tasks
Description Time from invocation
Comments Sign Off
1. Incident occurs. 0 hours
2. Gold Team advises Silver Academic Team that plan has been invoked
Immediate
3. Decision taken as to whether it is a critical time of year for assessment process.
0 – 2 hours
4. Impact to exam schedule investigated
2 – 4 hours
5. Silver Academic team standby to attend the recovery site campus.
4 – 6 hours
26 Date approved: 30.10.14
6. Silver Academic team restore operations at Recovery Site and catch up any process back log.
Ongoing
7. Debriefing and stand-down. Up to 3 months
6.7.6 Silver Operations Team Tasks
Description Time elapsed Comments Sign Off
1. Incident occurs. 0 hours
2. Gold Team advises Silver Operations Team that plan has been initiated
Immediate
3. Silver Operations standby to attend Carmarthen campus.
2 hours
4. Silver Operations assemble at the Carmarthen campus and assess impact on operations
4 hours
5. Banking institutions informed. 4 - 24 hours
6. Silver Operations catch up process back log and return to normal operations
Ongoing
7 Debriefing and stand-down. Up to 3 months
6.7.7 Silver Student/Staff Liaison Team Tasks
Description Time from invocation
Comments Sign Off
1. Incident occurs. 0 hours
2. Gold Team advises Silver Staff/Student Liaison Team that plan has been initiated
Immediate
3. Silver Student/Staff Liaison team stand by to attend the affected site campus.
2-4 hours
4. Decision taken as to whether alternative student
4 - 24hours
27 Date approved: 30.10.14
accommodation has to be sourced.
5. Prepare relevant communications for students and respond to staff queries as required.
Ongoing
6. Inform commercial clients on status of Facilities. Cancel bookings if required.
Week 1
7. Silver Student/Staff Liaison team restore operations at Recovery Site and catch up any process back log.
Ongoing
8. Debriefing and stand-down. Up to 3 months
6.7.8 Departmental Responsibilities
The Silver teams are designed to ensure that the recovery can occur in the most effective
way, and that service to staff and students can be restored. The delivery of these services
will continue in the normal operational way by the departments with delivery responsibility.
Although the teams contain members of different departments, the structure and method of
working will be changed as little as possible and departments will retain their normal
operational responsibility.
7. Recovery Processes
7.1 Alternate Work Locations
In the short term, for an incident at the Carmarthen campus, recovery will be at the
Lampeter campus and vice versa. At Swansea, Mount Pleasant campus recovery will be at
the Townhill campus and vice versa. Alexandra Road, Dynefor and Ty Bryn Glas recovery will
be at the Mount Pleasant campus. For Cardiff, campus recovery will be at the Carmarthen
campus, and for the London campus recovery will be in serviced accommodation.
Serviced Accommodation - London campus
Following an incident on the London campus the following could be implemented:
1. The hire of other rooms, halls and common areas on the Kennington Business Park at
short notice and at affordable prices;
2. There are many temporary D1 premises available in London – it would be possible to
use church halls, community halls and temporary commercial premises for recovery, in
the short term;
28 Date approved: 30.10.14
3. Between the months of June – September there are other London based University
premises available to rent. The University has already used London South Bank
University premises during the summer of 2013.
For an incident that has a regional impact, recovery will be to the University of Wales
campus, Cardiff. Medium term options will depend on the scale and duration of any
incident, but the more severe an incident the quicker these options should be put into place.
7.2 Recovery of Premises
Recovery of the affected site will be influenced by the degree of damage. It is critical to get
the rapid involvement of the insurance agent and a loss adjuster, especially if a significant
number of other businesses in the area are affected.
It may well be the case that recovery of a site may take a significant amount of time and that
an interim site will have to be sourced. Care should be taken to ensure that it meets IT
requirements. HR will also have to ensure that staff are not adversely affected by the
journey to the interim site, or by its facilities.
7.3 Recovery of People
A major incident may lead to casualties within University staff, and loss of staff with long
term injuries or medical conditions (including stress). The emergency services will contact
next of kin. University staff should not make this initial contact unless explicitly directed to
by the emergency services.
The HR department will be responsible for pastoral care, and the arrangement of grief or
trauma counselling. If the emergency services require the University to make contact with
next of kin for less seriously injured staff, this is also a HR responsibility. Under no
circumstances should untrained staff make this contact.
Succession Planning (Appendix 4) provides a short term staffing solution for critical roles. In
the longer term, prior cross training and production of job manuals can help mitigate the
absence of accumulated knowledge and in training new staff. New staff will be recruited
externally (including temporary staff where appropriate) and the HR department will be
responsible for their integration.
7.4 Recovery of Technology
Whilst technology is always replaceable, the availability of compatible hardware cannot be
predicted, and the pace of change may mean that obsolete equipment cannot be obtained.
As part of the plan, a detailed IT disaster recovery plan must be kept up to date as any
changes occur to the IT systems.
The recovery priority of IT services to the business is detailed in the IT DR plan in Appendix
18.
29 Date approved: 30.10.14
7.5 Recovery of Information
Electronic data – see IT Disaster Recovery Plan. Financial documentation is held at the Carmarthen campus – invoices that have been
destroyed without being paid will be identified, and resubmitted by the supplier.
All other paper records should be covered by the Records Management System and the
University’s document retention procedures.
7.6 Recovery of Critical External Supplies
Critical (required within 30 days) suppliers are detailed in Error! Reference source not
found.Contacts
The loss of a campus may mean that the Royal Mail will not be able to deliver post. In this
situation, without advice, they will mark all mail gone away and will return to the sender.
Details of the local Royal Mail delivery office and contacts are held in Appendix 9.
If the event renders the normal offices inaccessible for a protracted period then mail should
be redirected or held at the sorting office. The Plan Director can decide to:
Implement the Mail Collect service, a free service to collect mail from the local Delivery
Office by authorised staff with ID;
Redirection. This allows the University to continue to receive mail sent to the former
address, even if the move is only temporary. Details and ID requirements are available
on the Royal Mail website;
Business Keepsafe: To use Business Keepsafe, Royal Mail requires a week’s notice to set
up the service, the name of the organisation including any variations, plus authorising
signatures on the application form. There is a charge for this service.
8. Standing the Plan Down
The plan has an anticipated lifespan of up to three months from activation. This is
considered sufficient time for any damage to the home site to be identified and timescales
for remedial action formalised, or for alternative accommodation to be sourced and
equipped. As such, the plan is either stood down at three months or when:
- the Home Site has been restored to full operational capacity or a new site has been
sourced, equipped and is able to handle normal operations;
- operations have been restored to pre-incident levels;
- staffing issues have been resolved and all departments have sufficient personnel to
undertake their critical activities.
The decision to stand the plan down is taken by the Gold Team, and should be recorded in
the following table.
30 Date approved: 30.10.14
Title Stand plan down? Signature
PVC (Finance and Planning) Y/N
PVC (Academic)
PVC (Student Experience)
Executive Head of IT/IS
Director of H R
Once the plan is stood down, the information used during the response to the incident
should be collected and stored safely. A debrief for Gold and Silver teams should occur to
assess the success of the plan and the lessons learned. This information should then be used
to update the BCP.
9. Audit, Review, Maintenance and Testing
The responsibility for the maintenance of the plan and for the initial response lies with the
Plan Managers who will work with the teams/departments/units/individuals nominated to
maintain/review the Appendices.
Apendix Responsibility
Appendix 1 – Gold & Silver Team Members SDD/SMT- review
Appendix 2 – Salvage Team and Actions Faculties/Support Units
Appendix 3 – Recovery Site Locations &
Contacts
Corporate Services
Appendix 4 – Succession Planning SDD/SMT- review
Appendix 5 – Telephone Cascade SDD/SMT- review
Appendix 6 – Staff Contact Details HR
Appendix 7 – Staff Recovery Locations SDD/SMT- review
Appendix 8 – Partner Institution Contact
Details
Dean of Quality & Enhancement
Appendix 9 – Key Supplier Contacts Finance Unit
Appendix 10 – Bank Account Details Finance Unit
Appendix 11 – Battlebox Corporate Services
Appendix 12 – Emergency Evacuation Plans Technical & Property Services
Appendix 13 – Activity Log Senior Gold & Silver Teams to be completed at time
of incident
Appendix 14 – Call Out Procedure Corporate Services
Appendix15 – Stakeholder Contact Details Silver External Relations Team
Appendix 16 – Emergency Information
Sources and Local Radio
Corporate Communications & PR
Appendix 17 – Insurance Company/Loss
Adjustor Details
Director of Finance
31 Date approved: 30.10.14
Appendix 18 – IT DR Plan and Voice Diversion
Procedures
Information Systems
Appendix 19 – Holding Statement SDD/SMT - review
Appendix20 – Buffer Time Actions SDD/SMT -review
Appendix 21 – Assumptions SDD/SMT -review
Appendix 22 – Critical Dates Calendar Academic Services
Appendix 23 – Campus maps Technical & Property Services
32 Date approved: 30.10.14
Appendicles
The appendicles contain restricted information and are therefore not published for general consumption.