Business Case - Welcome to GOV.UK Case for the Health and Care Modernisation Transition Programme 4...

70
July 2013 Business Case for the Health and Care Modernisation Transition Programme

Transcript of Business Case - Welcome to GOV.UK Case for the Health and Care Modernisation Transition Programme 4...

July 2013

Business Case for the Health and Care Modernisation

Transition Programme

2

You may re-use the text of this document (not including logos) free of charge in any format or medium, under the terms of the Open Government Licence. To view this licence, visit www.nationalarchives.gov.uk/doc/open-government-licence/

© Crown copyright

Published to gov.uk, in PDF format only.

www.gov.uk/dh

3

Business Case for the Health and Care Modernisation

Transition Programme

Business Case for the Health and Care Modernisation Transition Programme

4

Contents

Introduction ................................................................................................................................ 5

Executive Summary ................................................................................................................... 6

The Case for Change ............................................................................................................... 10

Key Changes ........................................................................................................................... 15

Financial Case ......................................................................................................................... 31

Economic Case ........................................................................................................................ 41

Commercial Case .................................................................................................................... 46

Management Case ................................................................................................................... 49

Appendix A - Changes Adopted Following the NHS Future Forum's Report ........................... 63

Appendix B - Accountabilities in the New Structures ............................................................... 65

Appendix C - Other Arm's length Bodies .................................................................................. 67

Business Case for the Health and Care Modernisation Transition Programme

5

Introduction

The health and care transition programme was established by the Department of Health (DH) in September 2010 to co-ordinate the implementation of the Health and Care reforms outlined in the White paper, “Equity and Excellence: Liberating the NHS”. The programme provided a governance framework to co-ordinate a number of distinct programmes of work across the health and care system to deliver the Government's vision to reshape healthcare so that it is more patient-centred, led by health professionals and focused on delivering world-class health outcomes. The reforms affected around 45,000 staff and more than 400 organisations across the NHS, local government, public health, DH and its arm’s length bodies (ALBs). The health and care reforms came into operation on 1 April. They reshaped the NHS so that it is more patient-centred, led by health professionals and focused on delivering world-class health outcomes. The abolition of SHAs and PCTs, and the establishment of CCGs, puts commissioning in the hands of GPs and local clinicians. New, more autonomous Arm’s Length Bodies are empowered to deliver services according to national priorities. Local government has an important new role in addressing local community health needs. Local authorities are also working with the NHS to deliver integrated health and care services. The new system provides a stronger voice for people and communities, empowering patients and local communities by ensuring services are responsive to their needs. This business case reflects the original proposals as captured in the Health and Social Care Bill 2011, updated to include the changes introduced in response to the report of the NHS Future Forum. The costs and benefits outlined in the business case reflect those included in the revised Impact Assessment for the Bill published in September 2011. In May 2012, the Department published a Transition Scheme for Publication. In this it made a commitment to publish the business case once the transition programme closed in April 2013. As the transition programme has now closed, this business case is being published to fulfil that commitment. What follows, therefore, is the case for change and the costs and benefits of reform as they were assessed in 2011. Parliament has also been given an up-to-date assessment of the costs and benefits of the reforms, alongside the Department’s annual report and accounts for 2012-13.

Business Case for the Health and Care Modernisation Transition Programme

6

Executive Summary

1. The reforms of the NHS and wider health and care system, as set out in the NHS White Paper Equity and Excellence: Liberating the NHS and the Social Care Bill 2011 are fundamental and wide ranging. Aspects of the policy intent will take years to fully implement. The first and most significant stage of the delivery of reforms is setting up the new organisational infrastructure for managing the NHS and Public Health.

2. The transition programme was established in September 2010 to manage the

implementation of the organisational and structural changes, which will largely be implemented by 1 April 2013. This Business case for the Transition Programme is essentially focused on the delivery of the organisational changes rather than all the longer term transformation and full policy intent behind the reforms.

3. The business case is not the document which was used to justify and approve the

reforms, or the Transition Programme or its funding. However, it sets out a summary of the case for change, a description of the main changes, and the costs and benefits of the programme. We are using the business case to provide the baseline of costs and benefits, so we can track their delivery through the life of the programme.

The Case for Reform

4. The current NHS architecture of the health and care system has evolved in a piecemeal way, which is now unwieldy and involves duplication. Costs are increasing at a rate which is unaffordable in the current financial climate, due to an ageing population, increased expectations, and the costs of treatment and technology. Its centralised management structure run out of the Department of Health tends to result in centrally driven changes and process targets which impact on the NHS ability to focus on local service delivery and outcomes.

5. The reforms aim to create a more responsive patient-centred NHS which delivers

outcomes that are amongst the best in the world. In order to deliver the full policy reforms, a new management infrastructure is required which:

puts commissioning in the hands of GPs and local clinicians

puts management of commissioning at arm’s length from the Department and focuses on delivery of outcomes

puts Local Government at the heart of ensuring local community needs are addressed. The Key Changes

6. The main structural changes to organisational infrastructure across the Health and Care system will be implemented by 1 April 2013. By then:

A full system of Clinical Commissioning Groups will have been established and ready to commission services for their patients;

Business Case for the Health and Care Modernisation Transition Programme

7

the NHS Commissioning Board will be running to manage commissioning to deliver NHS outcomes through CCGs;

Health Education England will have taken over SHAs’ (and part of the Department’s) responsibilities for education and training;

Public Health England (PHE) will have been established as the lead body accountable for delivery of Public Health outcomes, and will take on functions from the National Treatment Agency (NTA) and the Health Protection Agency (HPA), which will be abolished;

Health and Wellbeing Boards will be established in every upper tier local authority in England as the local system leaders for health and wellbeing;

Healthwatch England and Local Healthwatch will have been established, and

Local Authorities will have taken on local public health responsibilities from PCTs;

Primary Care Trusts (PCTs) and Strategic Health Authorities (SHAs) will have been abolished.

7. Altogether about 50,000 staff, currently in SHAs, PCTs, DH and other ALBs, will be

affected, either by moving with their functions into another part of the system or through leaving the system. All the current NHS estate and the majority of the other resources, processes and systems which are managed, owned or controlled by SHAs and PCTs will transfer into some part of the new system.

Financial Case

8. The key purpose of the reforms is to deliver the best possible patient services and the Government has committed to a one third reduction in administrative spending to release resources of £4.5 billion (in 2010-11 prices, or £4.9 billion in nominal terms) to the front line by the end of 2014-15. The annual savings from 2014-15 onwards will be £1.5 billion (in 2010-11 prices).

Business Case for the Health and Care Modernisation Transition Programme

8

9. The savings and transition costs in nominal terms are shown in summary below:

£ millions

Year 2010/11 2011/12 2012/13 2013/14 2014/15 Total

Original trajectory - costs of existing system

4,500 4,631 4,746 4,874 5,006 23,757

New trajectory - costs of new system

4,260 3,969 3,811 3,486 3,337 18,863

Trajectory of net savings

240 662 936 1,389 1,669 4,895

Estimated Redundancy Costs

195 219 141 218 83 856

Estimated Other Transition Costs

5 121 272 146 85* 629*

Est. Transition Total Costs

200 340 413 364 168* 1,485*

* includes £31 million incurred after 2014/15

10. The financial costs of the changes are being monitored on a quarterly basis.

Economic Case

11. The Impact Assessment for the Health and Social Care Bill estimated the total economic costs of the programme (excluding transfer costs) to be in the range £1.2 billion - £1.3 billion. The long term annual savings on administration costs are expected to be £1.5 billion per year from 2014-15 onwards (both in 2010-11 prices).

12. In addition to the savings that can be redirected to frontline services, there are a number

of non-quantifiable benefits. For example, Clinical Commissioning Groups will give health professionals the freedom to design services around patients, the NHS Commissioning Board will ensure quality improvements through nationally agreed clinical standards and streamlined and integrated public health services will lead to better responsiveness and democratic involvement.

13. Overall, the economic case is such that the Department will be able to live within the

allocations set by the Spending Review and be able to deliver the required reductions in administrative costs.

Commercial Case

14. The Department is mostly managing the transition through internal resources together with utilising the knowledge and support from the NHS. Commercial arrangements will deliver some aspects of the work, including the set-up of commissioning support

Business Case for the Health and Care Modernisation Transition Programme

9

organisations, establishing a publicly owned company to manage and disposal of the surplus primary care estate, and developing shared service arrangements to achieve service efficiencies and financial savings. In addition, reviews have been commissioned to assess commercial efficiencies at the NHS Business Services Authority, the NHS Litigation Authority and the NHS Blood and Transplant.

Management of the Change

15. This programme is the largest and most radical ever undertaken in the NHS, as it fundamentally changes the way the NHS is managed and run. It is being managed through an integrated programme run out of the Department. The programme SRO and Transition Director are professional and experienced change programme managers, who ensure the programme is subject to best practice assurance by the Cabinet Office Major Projects Authority. The programme is organised into 24 separate programmes, each with an SRO, Programme Board and team, responsible for managing the delivery of a major change.

16. The Permanent Secretary and NHS Chief Executive each chair the two main oversight

Transition Boards, and hold individual programme SROs to account for delivery of their programmes.

Business Case for the Health and Care Modernisation Transition Programme

10

The Case for Change Summary The current NHS architecture of the Health and Care system has evolved in a piecemeal way, which is now unwieldy and involves duplication. Costs are increasing at a rate which is unaffordable in the current financial climate, due to an ageing population, increased expectations, and the costs of treatment and technology. Its centralised management structure run out of the Department of Health tends to result in centrally driven changes and process targets which impact on the NHS ability to focus on local service delivery and outcomes. The reforms aim to create a more responsive patient centred NHS which delivers outcomes that are amongst the best in the world. In order to deliver the full policy reforms, a new management infrastructure is required which:

puts commissioning in the hands of GPs and local clinicians

puts management of commissioning at arm’s length from the Department and focuses on delivery of outcomes

puts local government at the heart of ensuring local community needs are addressed.

Vision

17. The Government plans to create a more responsive, patient-centred NHS, which achieves outcomes that are among the best in the world.

18. Their plans have been formulated in a series of White Papers and

Consultations leading up to the publication of the Health and Social Care Bill 2011, which sets out a series of structural reforms to the way the health and care system in order to:

Improve outcomes. Secretary of State’s over-arching ambition is to create a healthcare system that achieves results amongst the best in the world. The current system focuses too narrowly on process targets.

Give patients more power, so that the health and social care services better respond to patients’ and service users’ own needs and wishes.

Focus more on prevention, to tackle the rising incidence of ‘lifestyle disease’ including obesity and alcohol dependency.

Increase the local democratic legitimacy of local commissioning to foster integrated local service planning and commissioning across the NHS, social care and public health, and local government and address the wider determinants of health and wellbeing.

Business Case for the Health and Care Modernisation Transition Programme

11

Improve NHS commissioning so that there is less variability of commissioning arrangements.

Liberate the provider sector to create locally accountable and efficient NHS providers.

Drive quality and productivity improvements so that the NHS can meet the challenging financial position over the coming period as a result of rising demand, rising healthcare inflation, and pressure on social care funding.

Develop a workforce which is more flexible and responsive to changing service needs.

The Structural Problems of the Health and Social Care System

19. The current architecture of the health and social care system has developed piecemeal, involves duplication, and is unwieldy. The Health and Social Care Bill aims to put more power in the hands of patients and clinicians, and remove layers of management, while building on key aspects of the existing arrangements.

20. The main structural problems being addressed are as follows:

Improving public health and tackling health inequalities by setting up a dedicated new public health service - Public Health England (PHE).

Increasing the democratic involvement in commissioning and planning across health and social care through establishing Health and Wellbeing Boards to ensure services develop more around the needs of patients and communities.

Improving commissioning so that it is more patient focused by establishing Clinical Commissioning Groups that will comprise consortia of GP practices, patients, carers and the public as well as other health and care professionals, to work in partnership with local communities and local authorities to commission the great majority of NHS services for their patients.

Ensuring there is national leadership in commissioning and improved quality across the country by creating a statutory NHS Commissioning Board.

Strengthening the accountability of local commissioners and the responsiveness of local services by bringing elected representatives, local health, public health and social care commissioners and a representative of Local Healthwatch, together in local health and wellbeing boards.

Improving the economic regulation of Foundation Trusts in the new system by developing an economic regulator for all providers by

Business Case for the Health and Care Modernisation Transition Programme

12

changing the functions of Monitor, the current regulator for Foundation Trusts.

Streamlining the system to work more effectively and to reduce overheads so that maximum resources can be diverted to front line services by reducing the number of Arms Length Bodies (ALBs) and abolishing Strategic Health Authorities (SHAs) and Primary Care Trusts (PCTs), transferring functions as appropriate to the new bodies.

Strengthening and embedding the voice of patients and the public at both the local and national level through the establishment of Healthwatch England (as a committee of the regulator CQC) and Local Healthwatch (sharing local intelligence with Healthwatch England to inform the national picture).

21. The Key Changes section sets out a high level model for the future health

and care system and the functions of the new bodies in more detail. Financial Context

22. The Autumn 2010 Spending Review protected healthcare funding in real terms over the Spending Review period. However, even with this increase the NHS will need to achieve significant efficiency gains to meet the future costs of an ageing population, increased expectations and changes in technology.

23. The three core commitments to meet this challenge are to:

radically de-layer and simplify the number of NHS bodies, and the Department’s own NHS functions;

make up to £20 billion of NHS annual efficiency savings by March 2015 through the Quality, Innovation, Productivity and Prevention (QIPP) programme; and

reduce the costs of the Department and its arms length bodies (ALBs) by at least 33% in real terms by March 2014.

24. Up to £20 billion of annual efficiency savings over the next four years will

be reinvested to meet rising levels of demand, to meet rising costs in some areas, and to support improvements in quality and outcomes. QIPP delivery is outside the Transition Programme, however higher quality care is often better value in the long term, compared to unsafe or ineffective care that can cost money to put right, or require more care and treatment than is necessary.

25. The scale of the efficiency challenge is such that it can only be met by

system-wide reform. Improving quality and productivity is inextricably linked with implementing the transition programme’s structural reform, for

Business Case for the Health and Care Modernisation Transition Programme

13

example through bringing together responsibility for clinical decisions with the financial consequence of those decisions.

26. The Government has committed to reducing administrative spending by

one-third in order to free up resources for frontline services. The NHS and the Department of Health will therefore realign the entire system to make functions more efficient, or could remove some non-essential functions entirely.

Transition Programme Scope and Objectives

Scope

27. The modernisation and reform of the health and social care system

encompasses a range of policy developments that go beyond the structural changes. In particular, the Health and Social Care Bill includes cross-cutting themes on developing a patient led-NHS, improving quality of care, developing choice and competition and tackling health inequalities.

28. The Transition Programme will oversee the structural design of the new

system and the associated policy development, so that by 2013 the main components of the new Health and Care system will have been properly defined and understood, and the new organisations established to take them forward. In addition, there are a range of policy areas that will also be developed and implemented by 2014 and while the Department is taking these forward they fall outside the specific scope set for the Transition Programme. Examples from the White Papers include personal health budgets, NHS Outcomes Framework, payment by results reform, wider Information Strategy, Social Care funding reform and the changes to Foundation Trusts.

29. The new bodies will continue with the implementation and delivery of

benefits after April 2013 to complete the delivery of the Government’s vision, as set out in the Health and Social Care Bill, and secondary legislation.

Objectives

30. The objectives of the Transition Programme are to:

reform the health and care system such that it will deliver the Secretary of State’s vision;

Business Case for the Health and Care Modernisation Transition Programme

14

deliver the structural changes on time and within the programme’s budget;

ensure the transition of activities from the old system to the new system occur smoothly, including the closure of entities and transfer of appropriate accountabilities;

ensure the future system runs within the cost envelopes set by the 2010 Spending Review; and

ensure the Health and Care system maintains operational and clinical performance, and emergency preparedness throughout the transition.

Business Case for the Health and Care Modernisation Transition Programme

15

Key Changes Summary This section describes the new health and social care system and the changes from the current structure, how these will be implemented, and the timescales. The main structural changes to organisational infrastructure across the Health and Care system will be implemented by 1 April 2013. By then:

A full system of Clinical Commissioning Groups will have been established and ready to commission services for their patients;

the NHS Commissioning Board will be running to manage commissioning to deliver NHS outcomes through CCGs;

Health Education England will have taken over SHAs’ (and part of the Department’s) responsibilities for education and training;

Public Health England (PHE) will have been established as the lead body accountable for delivery of Public Health outcomes, and will take on functions from the National Treatment Agency (NTA) and the Health Protection Agency (HPA), which will be abolished;

Health and Wellbeing Boards will be established in every upper tier local authority in England as the local system leaders for health and wellbeing;

Healthwatch England and Local Healthwatch will have been established; and

Local Authorities will have taken on local public health responsibilities from PCTs;

Primary Care Trusts (PCTs) and Strategic Health Authorities (SHAs) will have been abolished.

Altogether about 50,000 staff, currently in SHAs, PCTs, DH and other ALBs will be affected, either by moving with their functions into another part of the system or through leaving the system. All the current NHS estate and the majority of the other resources, processes and systems which are managed, owned or controlled by SHAs and PCTs will transfer into some part of the new system. Overview of the new Health and Social Care System

31. The Secretary of State for Health remains responsible for promoting a comprehensive health service, and retains ultimate accountability for securing the provision of services. However, instead of directly managing providers or commissioners Ministers will transparently set objectives for the NHS through a mandate to the NHS Commissioning Board. Ministers will hold to account all of the national bodies, with powers to intervene in the event of significant failure, or in an emergency.

Business Case for the Health and Care Modernisation Transition Programme

16

32. The Department of Health will provide system leadership, setting strategic

outcomes and the regulatory, policy and legal framework. It will assure delivery through the stewardship of the system, securing the resources required and allocating those resources across the health and social care system.

33. The NHS Commissioning Board will allocate the funding received from the

Department to clinical commissioning groups, who will commission services from GPs and other clinicians. The Board will also commission some national and regional specialist services, including family health dentistry and community pharmacy.

34. Clinicians will lead commissioning for their local population, with clinical

senates and networks providing additional expertise to improve the design and delivery of patient care.

35. Local authorities will also have a much stronger role in shaping services

and will take over responsibility for local population health improvements. The new health and wellbeing boards will bring together local commissioners of health and social care, elective representatives and Healthwatch to come to a joint view of the health and wellbeing needs of local people and a joint strategy for addressing those needs, which will drive local commissioning across the NHS, social care and public health. At a national level, Public Health England will bring together a range of organisations, integrate the functions and bring public health to centre stage.

36. NHS providers will no longer be performance managed by Strategic

Health Authorities. There will be a consistent system of regulation for all providers: the Care Quality Commission will ensure services meet safety and quality requirements while Monitor will promote efficiency, with powers to set prices, and support service continuity. Patients will be able to choose the best service for themselves, from any qualified provider, with competition on quality not price and with Monitor overseeing compliance with regulations and tackling specific abuses and restrictions that act against patients’ interests. Monitor will temporarily also retain oversight of Foundation Trusts while the NHS Trust Development Authority will help the remaining NHS trusts achieve foundation status.

37. Health Education England will provide oversight and leadership for

professional education and training. It will ensure that the health workforce has the right skills, behaviours and training and is available in the right numbers to support the delivery of excellent healthcare and healthcare improvement.

Business Case for the Health and Care Modernisation Transition Programme

17

38. The National Institute for Health and Care Excellence will continue to

provide independent advice and guidance to the NHS and will extend its role to social care. The Information Centre will continue to act as an authoritative source of health and social care information.

39. The diagram below shows the health and social care system in 2013,

including the relationship between the national and local structures.

The key accountabilities in the new structures are set out in the Accountabilities Statement for the Department of Health. An overview summary is in Appendix B.

Organisation structure changes

40. The main structural changes for each of the organisations are set out below, which include the changes since the Bill was originally introduced in January 2011 from both the Commons Committee and Government’s response to the NHS Future Forum report (Appendix A sets out changes from the report).

Business Case for the Health and Care Modernisation Transition Programme

18

NHS Commissioning Board

What the organisation is for:

The NHSCB’s overarching role is to ensure that the NHS delivers better outcomes for patients within its available resources. The NHSCB can fulfill this role through its leadership on delivering the NHS Outcomes Framework, supported by its accountability framework for clinical commissioning groups, its framework for choice and competition, and its framework for emergency planning and resilience.

Key changes:

The Board will be an independent non-departmental public body (NDPB); it will have its own powers and it will be accountable to Secretary of State. It will commission national and regional specialised services, the family health services of dentistry, community pharmacy and primary ophthalmic services, and allocate and account for NHS resources. It will also take over the current CQC responsibility of assessing NHS commissioners and will hold GP consortia to account for their performance and quality.

How these will be implemented:

The NHSCB will be organised to ensure that each member of staff is working to improve health outcomes as well as taking on a particular functional responsibility. It will be organised nationally around the five outcome domains of the NHS Outcomes Framework (reducing mortality, long-term conditions, acute episodes, patient safety and patient experience) and there will be national professional leads for each of these areas, reporting to a national medical director or nursing director.

Timeline / Key stages:

It will operate in shadow form as a Special Health Authority from October 2011. Subject to the passage of the Health and Social Care Bill, in May 2012, the NHSCB will be established as an independent statutory body and take on some formal statutory accountabilities, including the authorisation of Clinical Commissioning Groups and the planning for 2013–14. The NHSCB will be fully operational by April 2013.

Business Case for the Health and Care Modernisation Transition Programme

19

Clinical Commissioning Groups

What the organisation is for:

Establishing groups of GPs, other health and social care professionals and patients and the public to commission the great majority of NHS services. They will not be directly responsible for commissioning services that GPs themselves provide but they will become increasingly influential in driving up the quality of general practice. This role will be transferred from Primary Care Trusts (PCTs) which will close by 31 March 2013. Clinical Commissioning Groups will be responsible for the functions that directly support commissioning healthcare services, including:

population health needs assessment;

strategy development;

patient and public engagement;

procurement and contracting; and

validation and reimbursement.

Key changes:

By April 2013, there will be a comprehensive system of Clinical Commissioning Groups, supported by and accountable to the new independent NHS Commissioning Board. The legislative framework will be designed to make sure that these groups are able to focus on improving quality of care within the resources available to them.

How these will be implemented:

Pathfinders are currently testing the new commissioning arrangements to ensure they are working well before shadow arrangements come into place. The pathfinders will also be involved in the design and testing of the authorisation processes, accountability, and support and intervention in readiness for authorisation to start from October 2012.

Timeline / Key stages:

The NHS Commissioning Board will be able to authorise Clinical Commissioning Groups from October 2012, and SHAs and PCTs will be abolished by April 2013. However the Board will only authorise CCGs when it is satisfied that they are ready to take on the commissioning functions.

Business Case for the Health and Care Modernisation Transition Programme

20

Health Education England and Local Education and Training Boards

What are the organisations for:

Health Education England (HEE) will be established to provide oversight and national leadership for education and training. HEE will bring together the interests of healthcare providers, the professions, patients and staff and take over the advisory role of Medical Education England and the professional advisory boards for education and training of nurses and allied health professionals.

Key changes:

The healthcare providers, with their local clinical leadership, will take a lead role in planning and developing their workforce, with responsibility for many of the workforce functions currently led by the Strategic Health Authorities (SHAs). Funding arrangements would be reformed to provide a fairer and more transparent approach. Oversight and national leadership for education and training will be provided by Health Education England (HEE).

How these will be implemented:

HEE will promote and ensure high quality workforce planning, education and training that is responsive to the changing needs of patients and local communities, providing national leadership on planning and developing the health workforce. It will allocate and account for most NHS Education & Training resources, support the development of provider-led networks and hold the local networks to account for the use of Education & Training resources.

Timeline / Key stages:

The Health Education England will be established as a Special Health Authority in shadow form in 2012 and will take over most SHA responsibilities for education and training in April 2013, when the Boards come into full operation.

Monitor

What the organisation is for:

Monitor will carry out the following functions as regulator for providers of health services:

setting, in conjunction with the NHS Commissioning Board, and regulating prices for NHS-funded services, and preventing anti-competitive behaviour that acts against patients’ interests;

supporting the continuity of vital services in the event of the financial failure; and

Business Case for the Health and Care Modernisation Transition Programme

21

licensing providers.

It will have a vital role in making sure that the system works together to give patients choices about their health and care. It will tackle specific abuses and restrictions that act against patients’ interests to ensure a level playing field between providers. Monitor will also have a duty to support commissioners to provide care in an integrated way where this best meets the needs of patients.

Key changes:

The Bill turns Monitor into a regulator for providers of NHS-funded health services, from it’s current role of determining whether NHS trusts are ready to become foundation trusts, ensuring foundation trusts comply with the conditions of their authorisations, and supporting their development.

How these will be implemented:

Monitor’s core duty will be to protect and promote patients’ interests. It will do this by promoting the provision of care that is economic efficient and effective and ensure that quality is maintained and where possible increased.

Timeline / Key stages:

It is anticipated that, subject to Parliamentary approval, foundation trusts will be subject to Monitor’s licensing regime from April 2013. From April 2013 Monitor will also issue guidance for commissioners on good procurement practice; protecting patient choice and preventing conflict of interest and anticompetitive behaviour.

NHS Trust Development Authority

What the organisation is for:

The NHS Trust Development Authority will provide governance and accountability for NHS Trusts in England. It will be responsible for overseeing the performance management of NHS Trusts including clinical quality, and driving their progress towards Foundation Trust status. It will be accountable nationally for performance and maintaining financial balance of NHS Trusts, the management of the foundation trust pipeline, monitoring clinical quality, governance and risk in NHS Trusts, and public appointments to NHS Trusts and NHS Charities. It will also be responsible for public appointments to NHS Trusts and some NHS charities.

Business Case for the Health and Care Modernisation Transition Programme

22

Key changes:

The NTDA will take on performance management role previously undertaken by the Strategic Health Authorities. It will also take over the work of the Appointments Commission in relation to appointments for NHS Trusts. The NTDA will exist until all NHS trusts are a Foundation Trust in their own right, part of an existing Foundation Trust or in another organisational form.

How these will be implemented:

NTDA will be a time-limited Special Health Authority of the Department of Health.

Timeline / Key stages:

NTDA will be established in shadow form in October 2012 and will take over SHAs’ responsibilities for the foundation trust pipeline and for the overall governance of NHS trusts from April 2013.

Health and Wellbeing Boards

What the organisation is for:

Health and wellbeing boards will be a forum for local commissioners across the NHS, public health and social care, as well as elected representatives and representatives of Local Healthwatch, to develop robust joint strategies, based on local need, which will drive integrated local commissioning, and securing better outcomes for local people.

Key changes:

Local authorities and clinical commissioning groups will perform Joint Strategic Needs Assessments through health and wellbeing boards, and develop joint health and wellbeing strategies which will drive local commissioning. From April 2013, local authorities will receive their public health ring-fenced budgets for the first time, and the health and wellbeing boards will assume their statutory powers to improve commissioning.

How these will be implemented:

Clinical commissioning groups and local authorities will assume joint responsibility for performing Joint Strategic Needs Assessments (currently undertaken by local authorities and PCTs) through health and wellbeing boards. There will be a new duty on boards to develop a joint health and wellbeing strategy, based on local need and setting out priorities for collective action, which will drive joint local commissioning and integrated service provision across the NHS, public health and social care.

Business Case for the Health and Care Modernisation Transition Programme

23

Timeline / Key stages:

Subject to the passage of the Health and Social Care Bill, health and well being boards will be established in every upper tier authority from April 2013. It is intended that they will run in shadow form from 2012.

Healthwatch England and Local Healthwatch

What the organisation is for:

Local Healthwatch and Healthwatch England will strengthen the voice of patients and the public locally, and will enable the collective views of users of health and social care services to influence national policy.

Key changes:

Local Healthwatch will carry forward the current functions of Local Involvement Networks (LINks) such as entering and viewing services, and will take on further functions, supporting individuals by providing information to promote choices, and potentially providing or signposting to NHS complaints advocacy. It will give local people the opportunity to make their views on their experiences known to commissioners and providers of services, and will provide feedback to Healthwatch England. Healthwatch England will provide leadership to Local Healthwatch organisations and will provide advice and information to the Secretary of State, the NHS Commissioning Board, Monitor, local authorities and the Care Quality Commission on the views and experiences of patients and the public. Local authorities and clinical commissioning groups will perform Joint Strategic Needs Assessments through health and wellbeing boards, where Local Healthwatch will be represented, and develop joint health and wellbeing strategies which will drive local commissioning. Boards are intended to operate in shadow form in 2012-13, and will be established on a statutory basis from April 2013.

How these will be implemented:

Healthwatch England will be established as a statutory committee of the Care Quality Commission. Local Healthwatch organisations will be funded via local authorities, and will have a seat on health and wellbeing boards. The Health and Social Care Bill creates various duties on the Secretary of State, Monitor, the Care Quality Commission, the NHS Commissioning Board and local authorities to respond in writing to the advice of Healthwatch England; and for commissioners and providers to respond in writing to the advice of Local Healthwatch.

Business Case for the Health and Care Modernisation Transition Programme

24

Timeline / Key stages:

Subject to the passage of the Health and Social Care Bill, Healthwatch England will be established in October 2012 and Local Healthwatch will be established in April 2013.

Public Health England

What the organisation is for:

Public Health England (PHE) will be a new integrated public health organisation – bringing together a number of existing bodies – that will strengthen the national response on emergency preparedness and health protection. It will support delivery across the three domains of public health – health improvement, health protection, and population health services – through information, evidence, surveillance and professional leadership. The Secretary of State is ultimately accountable to Parliament and the public for the delivery of the functions for which Public Health England is responsible PHE will drive improved outcomes in health and wellbeing, and protect the population against existing and future threats to health.

Key changes:

Setting up a dedicated new public health service - PHE - in the Department and taking on the functions of the Health Protection Agency (HPA); the National Treatment Agency for Substance Misuse (NTA); public health and intelligence functions; and national commissioning of health promotion and improvement campaign activity. PCT responsibilities for local health improvement will transfer to local authorities, who will employ the Director of Public Health jointly appointed with PHE.

How these will be implemented:

PHE will be an executive agency of the Department of Health. Its chief executive will be accountable to the Permanent Secretary for how the agency delivers against its business plan. PHE will also be accountable to the Department for the public funding it receives.

Timeline / Key stages:

Public Health England will be established on 1 April 2013, alongside the establishment of the NHS Commissioning Board and local authorities taking on their new statutory responsibilities for both public health and the Directors of Public Health.

Business Case for the Health and Care Modernisation Transition Programme

25

This timing ensures that the transition is separated from the Olympic and Paralympic Games, where responsibilities for health protection through this crucial period will remain with the existing statutory bodies.

Department of Health

What the organisation is for:

The role of the Department of Health is to maximise the health and wellbeing gain for the population through its stewardship of the adult social care, public health and NHS systems, and its work with other government departments.

It will do this by:

setting strategic outcomes for the health and adult social care system and assuring delivery through its stewardship of the systems;

securing resources for the health and social care system;

setting the regulatory, policy and legal framework for the health and social care system; and

providing system leadership for the whole system.

Key changes:

Commissioning policy and the allocation and accounting for NHS resources will move the NHS Commissioning Board, and tariff work will move to Monitor.

How these will be implemented:

A detailed mapping of functions is in progress, together with design of jobs within the future DH. Staff moves into confirmed posts will be completed in accordance with the HR framework.

Timeline / Key stages:

The top level structure for the Department was announced in July 2011. Function and people moves will be aligned with receiving organisations and will be completed by April 2013.

Other Arm’s Length Bodies

Overall aim:

In future the arm’s length bodies’ sector will mirror the reformed NHS and social care landscape, creating institutions that have clear duties, are transparent in their accountabilities and their responsibilities to patients, users and the public, and are more streamlined, with no overlap of functions between organisations.

Business Case for the Health and Care Modernisation Transition Programme

26

Key changes:

The following changes are being implemented following the review of the Department’s ALBs published in July 2010. Eight of the ALBs will leave the sector either becoming self-funding or being abolished and having their services transferred/delivered elsewhere:

Alcohol and Education Research Council (AERC)

Appointments Commission (AC)

Council for Healthcare Regulatory Excellence (CHRE)

Human Fertilisation and Embryology Authority (HFEA)

Human Tissue Authority (HTA)

General Social Care Council (GSCC)

National Patient Safety Agency (NPSA)

NHS Institute for Innovation and Improvement) (NHSIII).

Three ALBs are undergoing commercial reviews with likely consequences to each organisation's business from 2012-13 onwards:

NHS Business Services Authority (NHS BSA)

NHS Blood and Transplant (NHS BT)

NHS Litigation Authority (NHS LA).

Four other ALBs will continue, but each has some element of transition to manage:

Medicines and Healthcare products Regulatory Agency (MHRA)

Care Quality Commission (CQC)

National Institute for Health and Clinical Excellence (NICE)

The Health and Social Care Information Centre (HSCIC).

NICE and HSCIC will change status from Special Health Authorities to be non-departmental public bodies, which will give them greater autonomy. The remaining three ALBs included in the ALB review are:

Health Protection Agency (HPA)

National Treatment Agency (NTA)

Monitor (see separate section). The Health Protection Agency (HPA) and the National Treatment Agency (NTA) will be abolished with functions will be transferred to become part of Public Health England (PHE). In addition Health Research Authority (HRA) is a newly formed NHS organisation from December 2011 to protect and promote the interests of patients and the public in health research. It brings together the functions previously provided by the National Patient Safety Agency and the Research Ethics Committee.

Business Case for the Health and Care Modernisation Transition Programme

27

How these will be implemented:

Some organisations will be abolished or move to self-funding status, and some functions will cease or transfer. Savings and efficiencies will be made by streamlining the number of bodies and changing the way that they deliver their functions. Business support services across ALBs will be aggregated, helping to reduce duplication and bureaucracy through shared services initiatives for back office functions such as HR, finance and procurement. The continuing and new arm’s length bodies will formally set out their roles and responsibilities through framework agreements, including how the Department will seek assurance on the delivery of their objectives within their available resources.

Timeline / Key stages:

The ALB transition timetable continues until transition is complete. The majority of those ALBs leaving the sector will be closed during 2012-13. The exceptions being the transfer of functions from and closure of HFEA and HTA, which are subject to passage of the Public Bodies Bill and future primary health legislation, where closure is planned for 2015. Further details on the future roles, timings and function transfers are included in Appendix C.

Business Case for the Health and Care Modernisation Transition Programme

28

High Level Timeline

41. The sequence of key transition events is outlined below on the current plans:

Design and Policy Phase: To April 2011

White Paper ‘Equity and Excellence: Liberating the NHS’ published in July 2010.

Public Health White Paper published November 2010.

Command Paper (response to White Paper consultation) published December 2010.

House of Commons Bill Committee Stage.

Publication of HR framework for transition to the new system.

Publication of the NHS Operating Framework and PCT allocations for 2011-12.

Identification of the first wave of “pathfinder” Clinical Commissioning Groups.

DH confirms the design framework, subject to Parliamentary approval.

DH gives permission to pathfinders and early implementers to model some elements of the new arrangements and explore key issues for wider roll-out.

Listening Exercise: April 2011 – June 2011

Pause to undertake more engagement with stakeholders and consider improvements.

Government response to the NHS Future Forum report.

Preparation and Early Implementation: July 2011 – March 2013

SHA cluster arrangements in place by October 2011.

NHS Commissioning Board established in shadow from as a Special Health Authority from November 2011.

PCT provider-arm divestments largely completed; Community FTs come on stream.

Health Research Authority created as a Special Health Authority in 2011.

Health Education England and the NHS Trust Development Authority are established in shadow form as Special Health Authorities during 2012.

Business Case for the Health and Care Modernisation Transition Programme

29

Public Health England set up in shadow form for preparatory work before establishment in April 2013. Shadow allocations to local authorities for public health.

NHSCB is established as an independent statutory body by October 2012, carrying out limited functions, in particular, establishing and authorising clinical commissioning groups

Monitor starts to take on economic regulation powers and functions in October 2012.

Healthwatch England and local Healthwatch are established in October 2012.

Health and wellbeing boards operate in shadow form during 2012-13

Implementation – first full year of new system: April 2013 – March 2014

PCTs and SHAs abolished by April 2013.

NHS Commissioning Board takes on its full functions.

A full system of clinical commissioning groups is established. But the NHS Commissioning Board will not authorise clinical commissioning groups to take on their responsibilities until ready.

Health Education England takes over SHAs’ responsibilities for education and training.

Establishment of Public Health England and abolition of NTA and HPA.

Local Authorities take on local public health responsibilities and functions.

Most changes to ALBs implemented.

The NHS Trust Development Authority takes over SHAs’ responsibilities for the foundation trust pipeline and for the overall governance of NHS trusts.

Health and wellbeing boards established on a statutory basis.

Monitor will regulate all providers of NHS care.

The timeline is shown in chart form below:

Business Case for the Health and Care Modernisation Transition Programme

30

Transition High Level timeline from November 2010 to April 2013

Business Case for the Health and Care Modernisation Transition Programme

31

Financial Case Summary The key purpose of the reforms is to deliver the best possible patient services, and the Government has committed to a one third reduction in administrative spending, to release £4.5 billion resources to the front line by the end of 2014/15. The annual savings from 2014-15 onwards is £1.5 billion. The savings and transition costs in nominal terms are shown in summary below:

£ millions,

Year 2010/11 2011/12 2012/13 2013/14 2014/15 Total

Original trajectory

- costs of existing

system

4,500 4,631 4,746 4,874 5,006 23,757

New trajectory -

costs of new

system

4,260 3,969 3,811 3,486 3,337 18,863

Trajectory of net

savings 240 662 936 1,389 1,669 4,895

Estimated

Redundancy

Costs

195 219 141 218 83 856

Estimated Other

Transition Costs 5 121 272 146 85* 629*

Est. Transition

Total Costs 200 340 413 364 168* 1,485*

Financial costs are being monitored on a quarterly basis. * includes £31 million incurred after 2014/15. Reduction in Administrative Spending

42. The Government has committed to a reduction of one third in administrative spending across Whitehall. In the health sector, this covers all functions within the Department of Health, SHAs, PCTs and ALBs that do not constitute the direct delivery of a frontline service. The changes introduced by the Health and Social Care Bill will deliver these planned reductions in administrative expenditure.

43. The one third real terms reduction in administrative spending has been

measured against a 2010-11 baseline and is to be fully achieved by 2014-15. The Department estimated a baseline for administrative expenditure in January 2011 at £5.1 billion and subsequently adjusted it in September

Business Case for the Health and Care Modernisation Transition Programme

32

2011 to £4.5 billion. The main reason for the revision is that further data has become available on differentiating the local components of front line and administration spending, in particular better information on the costs of staff working in the commissioning arms of PCTs. Further details are set out in the Impact Assessment co-ordinating document published in September 2011.

44. The majority of savings will be achieved through the rationalisation and

streamlining of functions. Transition will also help to deliver QIPP by reducing bureaucracy. The abolition of SHAs and PCTs, and the reshaping of commissioning led by local commissioning groups, will reduce costs and the number of staff required. The reduction in NHS management costs alone is expected to be £850 million per annum from 2013-14 onwards.

45. Public health services are being streamlined and the Department is

reducing its day to day operational management. Along with the staff reductions a shared service approach is being actively pursued both across the Department and its Arm’s Length Bodies and in the NHS. This is targeting savings in back office functions such as finance, procurement and transaction processing. .

46. The revised profile for the cost-savings is shown in Table 1 below.

Table 1: Cost saving from the reduction in administrative spending, 2010/11

– 2014/15 (in nominal terms)

£millions

Year 2010/11 2011/12 2012/13 2013/14 2014/15

Administrative running costs at

2010/11 level 4,500 4,631 4,746 4,874 5,006

Real administrative running costs 4,260 3,969 3,811 3,486 3,337

Saving per annum 240 662 936 1,389 1,669 *

Proportion of the final savings

achieved by each year (i.e. speed

of trajectory)

14% 40% 56% 83% 100%

* £1.5 billion in 2010-11 prices

47. The table includes the actual administrative spending in 2010-11 of £4,260 million. This is below the baseline because the outturn figures from PCTs showed that they began to reduce staff numbers in 2010-11 in preparation for the proposed changes, which was earlier than originally anticipated.

Business Case for the Health and Care Modernisation Transition Programme

33

Redundancy costs

48. The Health and Social Care Bill proposals involve a major de-layering in the NHS, and recognise that some staff who are currently employed by PCTs, SHAs, ALBs, NHS Leadership and DH will be made redundant.

49. Table 2 below shows the estimated redundancy numbers and costs from

April 2011 onwards, and how this is broken down across those organisational groups. These numbers assume that the new organisations recruit all of their staff from existing organisations. Further reductions in staff numbers will be achieved through natural wastage. The differences in the predicted future staff reductions across different organisations are based on high-level modelling of the skills that the new organisations might require. The percentage reduction includes both the staff numbers from redundancy and those occurring from natural wastage.

Table 2: Lower estimate redundancy costs and numbers from April 2011

onwards

Future expected

redundancy

numbers

Predicted

wastage

numbers

Future expected

redundancy cost

(£m)

Total future

reduction in

staff (%)

SHAs 600 400 51 27%

PCTs 7,900 3,500 343 33%

ALBs 200 600 11 15%

NHS

Leadership

plus DH

400 500 32 21%

Total 9,100 5,000 437 29%

50. The costs and figures in Table 2 are based on the following assumptions:

The extent of redundancies will be different across organisational groups;

Redundancies are phased over the transition period. So, in comparison to the initial Impact Assessment figures in January 2011, more of the reduction in the workforce is achieved through natural wastage rather than redundancy. This is, however, offset by higher unit costs of redundancy as a result of increased pay pressures in the system;

A one third real reduction in running costs is achieved over 4 years for the whole non-provider administrative spend;

The redundancy multipliers (the number of times their salary an individual can expect to receive if they are made redundant) are 1.5 for DH, SHAs and ALBs, and 1.2 for PCTs. These are based on the

Business Case for the Health and Care Modernisation Transition Programme

34

information available at this stage, including from the Electronic Staff Records database;

Redundancies are spread evenly throughout the wage structure, across all levels of employment; and

Natural wastage (the proportion of staff that leave of their own accord, for example through finding new jobs or through retirement) is 3% per annum (see also paragraph 54 below).

51. The strongest drivers of cost in this table are the redundancy cost

multiplier and the wastage assumption. The redundancy cost multiplier is applied at the higher point of the salary scale, making this a high-end estimated cost; this has been adopted because redundancy packages are usually more attractive to higher paid, longer serving staff and because some staff have pension protection included in the redundancy package. Reducing the multiplier for DH, SHAs and ALBs to 1, and the PCT multiplier to 0.8, would reduce the redundancy costs by £154 million.

52. The wastage assumption figure is derived from current levels of natural

wastage (around 6%) being reduced by the anticipation of the prospect of redundancy packages being made available. The current turnover of managers within the NHS is estimated to be around 12.5%; the working assumption is that this level would halve during an economic downturn, as managers have transferable skills but fewer opportunities. This is then halved again as fewer staff will choose to leave when there is the prospect of redundancy packages, giving the assumption of 3% used here. For example, wastage fell by a half in 2006-7 when PCTs were being reorganised and redundancy was made available; increasing the wastage to 6% would reduce costs by £243 million.

53. Some redundancies occurred in 2010-11 and the payments recorded in

the 2010-11 accounts are shown in the table below (excluding provisions for future years), along with the remaining staff numbers as at April 2011.

Table 3: Current staff numbers and redundancy costs incurred so far

Remaining staff

(April 2011)

Redundancy costs

incurred 2010/11 (£m)

SHAs 3,800 3

PCTs 34,500 142

ALBs 5,800 29

NHS Leadership plus DH 4,200 21

Total 48,300 195

54. With the £195m redundancy costs already incurred in 2010-11, this makes a total projected redundancy cost of £632m. This is a theoretical minimum total cost as there are likely to be extra redundancy costs because of:

Business Case for the Health and Care Modernisation Transition Programme

35

Friction – skill and geography mismatches between the staff available and those required in the new organisations; and

Flexibility – future organisations may decide to employ staff that are not employed in the current system.

55. The uncertainty is most relevant for the staff numbers relating to SHAs

and PCTs. The table below sets out how the overall redundancy costs change depending on the proportion of existing SHA and PCT staff that transfer to the new organisations. The minimum proportions are taken from Table 2, and the total redundancy cost figures include the £195m already incurred in 2010-11. Table 4: range of costs depending on the proportion of PCT and SHA staff that transfer to the new organisations

Proportions of staff transferring

to new organisations

Redundancy numbers Redundancy costs

(£m)

PCTs SHAs Extra Total Extra Total

67% 73% 0 9,100 0 632

62% 68% 1,900 11,000 89 721

57% 63% 3,800 12,900 179 810

52% 58% 5,800 14,900 268 900

47% 53% 7,700 16,800 357 989

56. The figures for redundancies and redundancy costs in the table above are from the April 2011 baseline. The extra redundancy numbers are those additional to the minimum set out in Table 2 (9,100) and the total redundancy numbers adds these together. The wastage numbers (5,000, shown in Table 2) are not assumed to increase, and so are not included. The proportions of staff from ALBs and NHS Leadership plus DH are not assumed to change.

57. The projected range for the redundancy costs, including those already

incurred in 2010-11, is £632m to £989m. Using a best estimate of 57% of existing PCT and 63% of existing SHA staff transferring to the new organisations, the estimated redundancies are 12,900 and the estimated redundancy cost is £810m. Using figures of 57% and 63%, which are considered to be at the midpoint of the realistic ranges, allows for the new organisations to have flexibility in who they employ and how they perform their functions. Table 5 gives a breakdown of this across different sectors, along with the assumed ranges per sector. This includes the 2010-11 redundancy costs figures.

Business Case for the Health and Care Modernisation Transition Programme

36

Table 5: Predicted range of total redundancy costs

All figures are in £millions in 2010/11 prices

Minimum redundancy

cost

Most likely

redundancy cost

Maximum redundancy

cost

SHAs 54 84 114

PCTs 485 634 782

ALBs 40 40 40

NHS Leadership

plus DH 53 53 53

Total 632 810 989

58. Table 6 shows an initial profile of the redundancy costs and the conversion from 2010-11 prices to cash figures. The modelling is to be further developed to reflect emerging data on the transfer of functions and people between ‘sender’ and ‘receiver’ organisations, revised timings and the end state budgets.

Table 6: Redundancy Expenditure Profile in nominal and 2010-11 prices

Year £m 2010/11 2011/12 2012/13 2013/14 2014/15 Total

Estimated

Redundancy Costs –

2010-11 prices

195 194 156 213 52 810

Redundancy Costs –

nominal prices 195 219 141 218 83 856

Non-Redundancy costs

59. Table 7 sets out the non-redundancy costs and each of the components is explained in more detail in the sections below.

Business Case for the Health and Care Modernisation Transition Programme

37

Table 7: Non-redundancy costs

Year £m 2010/11 2011/12 2012/13 2013/14 2014/15 Total

Estates Costs 5 20 85 85 195*

IT Costs 13 114 40 167

Internal Costs 5 38 43 86

Other External

Costs 65 95 21 181

Total Other

Transition Costs 5 121 272 146 85 629*

* includes £31 million estates costs estimated to be incurred after 2014-15

Estates Costs

60. The Department’s and ALB’s administration estates baseline has been

taken as £90m, based on the running costs in 2009-10 (excluding specialist estates operated by the Health Protection Agency and NHS Blood and Transplant).

61. The SHA and PCT admin estate comprises over 500 separate buildings

with an annual running cost in excess of £150m. The budget for these properties, and the staff currently required to manage them, are held by SHAs and PCTs. In October 2011 the current 10 SHAs and 152 PCTs were consolidated administratively into 4 SHA clusters and 50 PCT clusters. For some time into the future staff are likely to continue in most of the locations, although they will require less space than the current offices provide.

62. The main estates transition cost relates to the legacy costs of surplus

office space, and is dependent on how much of the estate will be reused for the new CCGs and other sub-national structures. NHS estate cost data is available for the SHA estate (£16m excluding hosted functions), but for PCTs it has been estimated on the basis of 63% of their estate total being used for commissioning activity, with the remaining 37% being used for provider activity. Excluding provider activity, the total NHS administrative office cost was circa £106 million per annum in 2009-10. This estimate will be revised once further data collected by the Property Services (Propco) programme in the summer of 2011 is analysed.

Business Case for the Health and Care Modernisation Transition Programme

38

63. In line with the proposed governance regime, it is anticipated that the large majority of CCGs and Commissioning Support Groups (CSGs) will continue to use existing estate. However, these costs will rise substantially, both in terms of capital investment and additional legacy costs, if there is significant acquisition of new property rather than utilisation of existing property, resulting in a larger surplus. The timing of these costs (and therefore the profile of the net saving) is still uncertain given the dependency on the details of the individual buildings to be retained or made surplus. This is not yet known but could stretch over a period of years as leased property is managed out.

64. The scale of the costs (and therefore how quickly the savings are accrued)

depend critically on how much of the existing SHA and PCT estate can be recycled and how much needs to be replaced.

65. By analysing the current lease profiles, and assuming that between a half

and one-third of the current PCT estate is retained, the transition cost for estates is estimated to be between £80 million to £200 million. This includes between £10 million to £20 million for the DH and ALB estate changes, including preparing buildings for new organisations. The range reflects the uncertainty about where, in terms of buildings, new organisations are likely to be based and how the existing estate will be used.

66. The £195 million in Table 7 represents a high end estimate together with

the related costs for ICT (information, communication and telephony) such as cabling and core computer equipment and networks for the new organisations.

Information Technology

67. The organisational changes to the NHS will impact on the operation of the

informatics systems across the Department, its Arms Length Bodies and the NHS.

68. Costs are likely to arise in the following areas:

changes to existing national systems owned by Connecting for Health;

changes to DH and ALB systems;

changes to / transfer of existing systems operated by SHAs, PCTs and the wider NHS; and

new requirements may emerge from the operational design of the economic regulator, NHS Commissioning Board and other organisations.

Business Case for the Health and Care Modernisation Transition Programme

39

69. The main cost is expected to be incurred on PCT systems and their transfer to successor organisations. In the Impact Assessment it was assumed that the cost would be equivalent of 6 months of the average IT spend per year for setting up new IT and transferring from the old one. This gave a figure of £950,000 per PCT (in 2010-11 prices) or £151 million in total as an estimate (£167 million in nominal terms).

Internal Costs

70. The Department of Health will incur costs to fund the teams that develop the way that the new bodies will operate and in designing the new systems and organisations, as well as managing the implementation. For most of these teams, specific budgets have been established to contain the costs. However, for a few areas where costs are being incurred within recurrent directorate allocations, an apportionment basis has been used to identify transition costs.

71. These internal costs cover all the significant work programmes, although

they do not cover some support areas (e.g. finance) where there is no clear distinction between transition work and business as usual.

72. Table 7 shows the internal costs incurred in 2010-11, expected to be

incurred in 2011-12, and an initial estimate for 2012-13. It is anticipated that costs for 2012-13 will be broadly consistent with 2011-12.

Other External Costs

73. In addition to estates and IT costs, other set-up costs for the new

organisations will include those for design and recruitment, and for establishing internal systems. Costs are also expected to be incurred on establishing the new organisations’ identities and brands, and harmonising pay and conditions for staff transferring from other organisations.

74. Such costs falling outside the Department are currently estimated to be £181 million, of which about £100 million has been identified for the setup of Clinical Commissioning Groups. The cost profile for Other External Costs is shown in Table 7.

Funding for Transition Costs

75. Most of the financial resources to support transition are held at local level.

SHAs and PCTs are expected to fund their redundancy and other

Business Case for the Health and Care Modernisation Transition Programme

40

transition costs within the 2% headroom for non-recurrent spending they have been required to create. This 2% headroom is worth approximately £1.6 billion per annum and is recognised in current NHS plans. However non-recurrent spending within this amount is not restricted to transition costs.

76. Funds are also held centrally for transition costs. The initial estimate for centrally-held programme revenue and capital resources is shown in Table 8.

Table 8: Original Central Programme Resources for transition (£m)

2011/12 2012/13 Notes

Capital 107

Redundancy - Central 80 102 For DH and ALBs,

SHAs are assumed self-

financing.

Non Redundancy -

Central

50 100

Total 237 202

77. In 2011 the Department established new arrangements to govern the allocation of non-recurrent administration funds to those DH directorates and newly-established arm’s length bodies which were incurring costs on developing or setting up the new arrangements. A Special Allocations Group (SAG), comprising three DH finance directors and a representative from the Integrated Programme Office of the Transition Programme, considered cases for non-recurrent funding against criteria of affordability, value for money and alignment to Transition Programme priorities. For 2012-13 the Transition Costs Group has been established to carry out an analogous role.

Business Case for the Health and Care Modernisation Transition Programme

41

Economic Case

Summary

The total economic costs of transition in 2010-11 prices are estimated to be in the range £1.2bn - £1.3bn (excluding transfer costs), and the long term annual savings are expected to be £1.5bn per year from 2014-15 onwards. In addition to the savings that can be redirected to frontline services, there are a number of non-quantifiable benefits. For example, Clinical Commissioning Groups will give health professionals the freedom to design services around patients, the NHS Commissioning Board will ensure quality improvements through nationally agreed clinical standards, and streamlines and integrated public health services will lead to better responsiveness and democratic involvement. Overall, the economic case is such that the Department will be able to live within the Spending Review allocations, and be able to deliver the management cost reductions.

Summary of the Impact Assessments

78. The Impact Assessments (IA) for the Health and Social Care Bill 2011

assessed the benefits, costs and risks of implementing the policies that require primary legislation. It was originally published in January 2011 and revised in September 2011 for when the Bill entered the House of Lords.

79. Table 9 below shows the total costs set out in the Impact Assessment that

were assumed to be attributable to the changes in the system architecture. The full range is £1,001 million to £1,478 million, from the estimated best case to the estimated worst case. These costs are assumed to be incurred predominantly in 2011-12 and 2012-13, when SHAs and PCTs are abolished, and the NHS Commissioning Board and clinical commissioning groups are set up.

Business Case for the Health and Care Modernisation Transition Programme

42

Table 9: Impact Assessment Figures (in 2010-11 prices)

Savings and Costs £million Notes

Savings 11,989 £4.5bn in first 5 years and £1.5bn in

each of next 5 years. Para 48.

Redundancy 632 - 989 Breakdown in table 5. £195m

incurred in 2010-11.

Estates 80 - 200 Outlined in Paras 65-71.

Other Non-redundancy 289 Costs from Para 64 et seq. but

excludes items commented on

below

Total Costs 1001 - 1478

80. The best estimate of transition costs, based on the most likely level of redundancy costs is £1,179 million to £1,299 million. This includes the £195 million already spent. This is compared to a total predicted saving over the 10-year period of £11,989 million. These figures are financial costs rather than opportunity costs, are in 2010-11 prices, and are not discounted.

81. The overall savings arise from the reduction in administrative costs set out in Table 2. The benefits figures do not include the health benefits associated with the proposed changes. The Impact Assessment overall shows that the anticipated monetarised benefits are significantly larger than the associated costs.

Business Case for the Health and Care Modernisation Transition Programme

43

Table 10 Summary of the Impact assessment (2010-11 prices)

September 2011

Figures

Total costs of transition (best estimates) £1.2bn - £1.3bn

Long-term annual savings (from 2014/15 onwards) £1.5bn per year

Long-term annual admin spending (2014/15 onwards) £3.0bn

Gross savings over the transition (2010/11 – 2014/15) £4.5bn

Net savings over the transition (2010/11 – 2014/15) £3.2bn - £3.3bn

82. The Financial Case includes some costs beyond those covered by the Impact Assessment, including the costs of change to arms length bodies not covered by the primary legislation, workforce and Health Education England proposals and national NHS IT systems through DH Informatics Directorate. Further, by convention, the impact assessments did not include the internal Government costs of implementing particular policies. The costs outside the scope of the Impact Assessment but inside the scope of the business case total around £100 million and represent a 3% reduction on the net savings in the table above.

Unquantified Benefits

83. The Impact Assessments describes a range of benefits, building on the rationale set out in the White Paper for the new healthcare structure and system. The main non-quantified benefits are set out below, which arise at least in part from the structural changes set out in this business case:

Clinical commissioning gives GPs the freedom to design services around patients. This is expected to deliver benefits in terms of improved services that deliver better outcomes, improved patient experience, and more efficient management of NHS resources.

Clinical commissioning of patient services, in place of managers in PCTs, improves the alignment of clinical and financial incentives, and should led to improved care of patients with long term conditions, reductions in growth/level of urgent and emergency admissions, and improved prescribing.

Business Case for the Health and Care Modernisation Transition Programme

44

NHS Commissioning Board will ensure quality improvements through nationally agreed clinical standards, with a new legal duty for quality improvements. The Board will also be able to make additional payments in the form of a quality reward to reflect the performance of commissioning groups in relation to the quality of services, reductions in inequalities and outcomes achieved.

NHS Commissioning Board will streamline decision-making, planning and commissioning of all specialist services, providing greater consistency and reducing inequitable access to specialised services across the country. This will enable a consistent approach to service specifications to contain costs and get best value for money (e.g. agreeing single tariffs across providers).

The economic regulator will develop a more independent, transparent and stable regulatory framework for providers, increase certainty on the structure and level of prices, and strongly police anti-competitive practices to restrain the market power of large incumbent providers, which is expected to support efficiency gains in the NHS, encourage providers to be more flexibly to patient needs and support innovation.

A streamlined and integrated public health service will lead to better responsiveness, for example removing the potential for delays in responding to public health threats and emergencies and enhance the use of evidence.

Less central control and reduced bureaucracy means there is less need for intermediate tiers to communicate instructions down through the system and manage delivery.

Greater local democratic involvement in commissioning through health and wellbeing boards should ensure stronger joint working and more responsive local services. The strengthened voice of patients and the public in decisions at both the national and local level through Local Healthwatch and Healthwatch England will further ensure that services better address local needs, ultimately leading to higher levels of patient satisfaction, improved quality of services and more cost effective commissioning.

HEE will provide an opportunity to embed a single, multi-professional approach to provide professional leadership and focus on quality of education and training being commissioned, improving on the current fragmented approach. Health Education England (HEE) will also reinforce national co-ordination of education and training activity, and provide better leadership across the whole system, bringing together the interests of the professions and providers of NHS services.

Employers will have clearer ownership and involvement in the education, training and planning of their workforce through the creation of local education and training boards. They will be able to better link service planning and workforce planning, focusing on the whole workforce, while

Business Case for the Health and Care Modernisation Transition Programme

45

recognising the levels of contact with patients and service users and the varying local needs.

The Education Outcomes Framework (EOF) being developed will set out the high level principles and outcomes for achieving a world class health care education system, so for the first time the investment in education and training will be directly linked to improvements in patient care.

84. Most of these benefits will be delivered in the longer term following the transitional structural changes. The benefit realisation will be achieved through the framework agreements and NHSCB mandate and the system levers embedded into the new operating arrangements.

Business Case for the Health and Care Modernisation Transition Programme

46

Commercial Case

Summary

The Department is mostly managing the transition through internal resources together with utilising the knowledge and support from the NHS. Commercial arrangements will deliver some aspects of the work, including the set up of commissioning support organisations, establish a publicly owned company to manage and disposal of the surplus primary care estate, and developing shared service arrangements to achieve service efficiencies and financial savings. In addition, reviews have been commissioned to assess commercial efficiencies at the NHS Business Services Authority, NHS Litigation Authority and NHS Blood and Transplant, which are due to report later in 2011.

Introduction / Approach

85. The Department is mostly managing the transition through internal

resources together with utilising the knowledge and support from the NHS. This section sets out the aspects of the transition programme that require commercial procurements or the transfer of personnel and assets, with reference to their core documents.

Commercial Arrangements across the Transition Workstreams

Commissioning Support Arrangements

86. It is anticipated that Clinical Commissioning Groups will buy in, or share with other organisations, support to assist them to carry out their commissioning functions. Potential areas include business support such as finance, accounting and administration; transactional support such as planning, performance modelling and contract management; and commissioning support such as pathway redesign, service specification and establishing best practice around cost effectiveness and clinical quality.

87. Support could be bought in from commissioning support organisations,

local authorities, private and third sector bodies or joint ventures. The Department is developing a national framework and a range of support tools, and is also actively working with the PCT clusters to reshape commissioning and develop their commissioning support offerings.

Business Case for the Health and Care Modernisation Transition Programme

47

Commercial Reviews

88. A key finding of the 2010 Arm’s Length Bodies review identified that the bodies had under-exploited potential commercial opportunities. Commercial reviews were subsequently commissioned for the NHS Business Services Authority, NHS Blood and Transplant and NHS Litigation Authority. Within each of these organisations there are activities which are either similar to those already delivered by the private sector, or which could be traded in a market type environment. The reviews aim to identify commercial opportunities which can improve value for money, drive up operational efficiency and increase income

NHS Property Vehicle

89. NHS administrative estate which is not transferred to existing healthcare providers will be transferred to an NHS property vehicle (NHS PV) established as a company wholly owned by the Secretary of State for Health. Its prime focus will be efficient property management, reducing running costs and maximising the value achieved from the sale of any surplus assets.

Shared Services

90. The management of non-core services into a shared or standardised service is a cross-government strategy to help reduce administrative costs. A Shared Service Programme has been established to maximise the savings across Department, its new public health arm Public Health England (PHE) and the remaining and newly created Arms Length Bodies (ALBs), including the NHS Commissioning Board. Savings will be made by aggregating volumes of activity, standardising service specifications and, in some areas, using external skills to improve efficiency.

91. The shared services are being initially developed in the following areas:

Financial Transactions – for payroll, accounting, invoice processing and supplier maintenance, cash and debt management, and VAT returns;

HR – starters, leavers, changes, absence management, policy development, HR support; and

Procurement – contract management, e-procurement tools, catalogue data maintenance, and government procurement card admin.

Business Case for the Health and Care Modernisation Transition Programme

48

92. Each area is expected to develop separate business cases in due course.

Information Technology

93. The Information Technology elements of the transition programme are still in development and the commercial approach for any procurements will be established in the coming months. A number of IT contracts will need to be reviewed and potentially novated to different organisations.

Business Case for the Health and Care Modernisation Transition Programme

49

Management Case

Summary

This Management Case sets out how we are managing the Transition Programme, and how the Programme fits in to the wider Health and Social Care system, and the key Governance processes that are in place.

There are also sections on the functions of key Boards, Delivery Plan, Risk Management, stakeholder engagement and Gateway Review. The key decisions are taken at a hierarchy of programme boards which include the permanent secretary and NHS chief executive and senior DH and NHS directors. Each transition workstream has an SRO, programme plan, milestones and risk management arrangements. An ongoing series of stakeholder events also ensures there is wider consultation and engagement.

The programme is the largest ever undertaken in the NHS, and is being managed through best practice in Project and Programme Management, with full scrutiny by the Cabinet Office Major Projects Authority.

Transition Programme Structure

94. The Transition Programme was established by the Department to oversee and coordinate the work to design and implement the new Health and Care system to April 2013. There are 24 separately managed programmes of work, led by A Senior Responsible Owner, Programme Director and supported by a programme team. The Transition Programme governance structure, operating from September 2011, has been revised to reflect the move from system design to programme development and delivery, and is set out below:

Business Case for the Health and Care Modernisation Transition Programme

50

95. The following paragraphs describe the different work strands in more detail:

NHS Transition

96. The NHS facing programme includes:

Commissioning Board: Establishing the new NHS Commissioning Board.

Commissioning Development: responsible for ensuring a smooth transition from the current commissioning system to a new structure of Clinical Commissioning Groups. The team will oversee the development and implementation of the new commissioning architecture and the transition in the Department of Health and NHS to the new commissioning arrangements.

SHA Transition: Transition and closure of Strategic Health Authorities (SHAs) and Primary Care Trusts (PCTs), ensuring the effective

Business Case for the Health and Care Modernisation Transition Programme

51

transfer of services to new organisations and close down of discontinuing functions.

Health Education England: provision of sector-wide leadership and oversight of workforce planning, education and training in the NHS.

NHS Trust Development Authority (NTDA) and FT Pipeline: a short-life special health authority for transition that will ensure continued governance and performance management for NHS trusts who have yet to achieve Foundation Trust (FT) status, and help to manage the approval of Trusts to achieve Foundation Trust status (FT Pipeline).

Sector Regulation: creation of a new Regulator to promote patient choice and competition, set efficient prices and support continuity of service.

NHS Development: provision of overall strategic direction for the QIPP Programme, including National Clinical Workstreams such as Long Term Conditions and Urgent Care, working with the NHS and the Department on improvement, and work on commissioning for primary care.

Future State Informatics: supporting the NHS in delivering better, safer care to patients, by bringing in new computer systems and services

DH Transition Programmes

97. These programmes include:

DH Transformation and Shared Services: creation and implementation of the new Department of Health, and the delivery of shared services arrangements for business support services across DH and the ALBs.

Public Health England: creation of Public Health England, and the new Public Health system.

Local Government: establishing the new Local Government arrangements, including the design and implementation of Health and Wellbeing Boards, the establishment of Healthwatch England and local public health services.

Health Research Authority (HRA): forming the Health Research Authority (HRA) to provide a new pathway for the regulation and governance of health research, streamline regulation, create a unified approval process, and promote proportionate standards for compliance and inspection within a consistent national system of research governance.

ALB Transition: structural reorganisation of the Arm’s Length Bodies following the ALB review.

Emergency Preparedness, Resilience and Response (EPRR): setting clear principles for emergency preparedness, resilience and response.

Business Case for the Health and Care Modernisation Transition Programme

52

Social Care Programme: making services more personalised, more preventative and more focused on delivering the best outcomes for people using services.

Workforce Transition: design and safe transfer of health and social care workforce functions in the new system.

Governance and Accountabilities: establishment of the overall chain of accountability for the proper stewardship of Parliamentary funds and the accountability structures and processes in the new system.

Cross-cutting Functional Workstreams

98. The implementation programmes are supported by cross-cutting functional

workstreams. They will work in partnership with business leads in the implementation programmes to provide specialist professional advice during the design stage, and deliver the requisite changes during the implementation phase, ensuring joined-up working across the DH, ALBs and the NHS. The workstreams are as follows:

Finance

NHS Estates and establishing a NHS Property Vehicle

Informatics Transition

IT enabled Estates for DH and ALBs

HR

Communications and Stakeholder management

Equalities.

Executive Board

99. The Executive Board’s purpose when considering Transition business is:

to oversee the overall design, strategic approach, planning and implementation of the new direction for the health and care system, ensuring the phased alignment of system-wide organisational changes, mitigation of risks to business continuity and financial control and co-ordinated engagement and communications. It ensures that at a strategic level, effective people and programme disciplines are in place across all parts of the Transition Programme with the aim of ensuring successful delivery of the new health and care system.

Business Case for the Health and Care Modernisation Transition Programme

53

100. In particular, the Executive Board:

ensures transition is coordinated between NHS, DH, ALBs and local government as part of an integrated plan;

provides a single point for joint decision making for all aspects of Transition, which require senior level decisions; and

provides the overall governance of the Transition Programme ensuring the programme delivers successfully, managing the risks and issues effectively, though most routine programme governance is delegated to the Transition Programme SRO.

Transition Board for Cross Cutting Functions

101. This Board oversees and assures the delivery of the cross cutting functional work programmes, ensuring they deliver the necessary functional change, and are fully integrated with the DH and NHS programmes they support. It meets monthly, providing reports and escalating issues to the Executive Board or other bodies as appropriate, and is chaired by the Transition SRO (DH’s Director General of Policy, Strategy and Finance). Its remit is to:

ensure functional designs, transition policies and decisions are aligned to the system needs, and agreed as necessary by the right decision makers;

ensure each workstream is making good progress to the overall integrated programme and implementation plan, and dependencies across the programme are identified, tracked and managed;

ensure risks to progress, costs and benefits are being managed effectively;

escalate risks, issues to Executive Board as necessary; and

formally report status and progress to plan to the Executive Board every month.

DH, Social Care and Public Health Transition Board

102. This Board oversees the design and delivery of each of the DH, Public

Health and Local Government component programmes. Specifically, it ensures the design and implementation of the DH, Public Health and Social Care structures and systems, and the transition to Local Government, are consistent with the needs of the new Health and Care system, and with the transition to the new NHS system.

Business Case for the Health and Care Modernisation Transition Programme

54

103. The Board covers the following workstreams in support of the transition:

DH Transformation and the delivery of shared services across the system;

delivery of Public Health England and the wider Public Health system, including the PH transition into Local Government;

transition of the wider health and care changes for Local Government, including establishment of Health and Wellbeing Boards, and new Healthwatch;

development and implementation of Social Care changes;

implementation of the new Health Research Authority;

transition of the current DH ALBs.

NHS Future Systems Executive (and NHS Transitional Executive Forum)

104. This Board oversees the design and delivery of each of the NHS

component programmes, ensuring they design and implement the new NHS organisations and structures as required to meet the policy intention, and that they work consistently as part of one new aligned NHS system.

105. This Board feeds into the NHS Transitional Executive Forum, which will

ensure the new NHS structures work together as an integrated whole, interact effectively as part of the wider Health and Care system, and that the current NHS structures transition effectively to the new system and close down effectively.

106. The NHS Future Systems Executive covers the following workstreams in

support of the Transition:

NHS Commissioning Board;

commissioning development, including commissioning architecture;

NTDA and FT pipeline;

Monitor changes and economic regulation regime;

HEE and education and training;

Future Informatics organisation;

future design of shared services for the NHS; and

development of leadership and systems across the system.

Business Case for the Health and Care Modernisation Transition Programme

55

Implementation Programme Boards

107. Each of the implementation programmes have their own governance

arrangements and associated boards (e.g. Commissioning Development Board and Public Health Programme Board).

108. The role of each Board is to govern and drive the design and delivery of

each of the Programmes according to the policy and legislative framework set by Ministers, and within the design framework and context set by the Executive Board. Each Board identifies risks and interdependencies and escalates issues to the DH Transition Programme Board, NHS Future System Executive or Transition Board for Cross Cutting Functions as appropriate, and if necessary, to the Executive Board.

Delivery Plan

109. There is a high level Transition Programme Roadmap, as well as more

detailed delivery plans for each of the individual programmes and workstreams. The following is a snapshot of the high level summary that shows the complexity of the programme and the inter-relationships between the different workstreams.

2011 2012 2013

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

QH Initial Occupation

Health & Care Transition Programme – High Level RoadmapHSC Transition Programme Plan Update Annex A

PROTECT: Management

Full System of Health & Wellbeing Boards

Fully Operational

NTDA SpHA Established

NTDA Commence Formal Role

Dev. Implementation Plan

Establish Health & Wellbeing Network Health & Wellbeing Board JSNA/JHWS Guidance Available

NTDA Fully Staffed

LA & local Healthwatch

Organisations take on

NHS Advocacy

Olympics & Para Olympics

Develop Governance Guidance

Run Programme of Continuous Learning & Support

Staff Consultation Response – TBC

NTDA Preparatory Running

Local Healthwatch Organisations Established

Healthwatch England Organisation Established

Local Healthwatch Organisations Preparatory Running

Senior Recruitment Exec Team Appointed - TBC

PHE Commence Formal Role

NTA & HPA Abolished

PHE Established in Shadow Form

Agree 2013/14 Business Plan & Budget

IT In Place

HQ Building Accommodation In Place

Exec Agency Business Case Agreed by CST & MCO

Publish draft Framework, Operating

Model, Org. Structure

PTP Agreed

CEO & Exec Team Appointed

Full Staff Consultation on

Structure

PHE Staff Appointed

System Testing & Training

Parliamentary Passage

Health and Social Care Bill Receives Royal Assent - TBC

Re-committal Lords 3rd Reading - TBCCommons 3rd Reading

Inst. Issued & Regulations Drafted

NHS CB & HRA Regs Laid

HRA SpHA Est’d – 1 Dec

NTDA & HEE Regs Laid - TBC

NTDA HEE SpHA Est’ed – TBC

Health and Social Care Act/ Secondary Legislation - TBC

Appointments Commission Abolished

Shadow Health & Wellbeing Boards In Place

HEE SpHA Established

HEE Commence Formal Role

Agreed Framework

DH Staff Consultation

Completed

Chair, NEDs and CEO Recruitment

Chair & NEDs Appointed

Agreed Operating Model

HEE Business Plan 2012/13 Agreed

Staff Consultation Response Published –

29 Aug

Transfer of Staff - Main

Transfer of Functions from NPSA & Appointing Authority Functions from SHAs

Commence Organisational Design Work

Monitor/Regulator Fully Operational

FT Provider Licenses In Place

Monitor Distress & Failure Regime Go Live for FTsTransition Dates Agreed

NHS CB Re-Established as NDPB

NHS CB able to Authorise Commissioning Groups

NHS CB Chair, NED & Directors Appointed

NHS CB Full Go Live -takes on Full Statutory

Functions & Financial

Responsibility

All SHAs & PCTs Abolished

NHS CB Staffed

Launch Discrete NHS CB Accounting System

Mandate Published – for 2013/14

Agree 2012/13 Budget baseline

Staff Consultation

Response

Published

NDPB Framework Agreement Agreed

Internally Agreed Framework

Executive Team & Board Recruitment

NHS CB Establishes & Authorises Commissioning Groups

NHS CB Preparatory Running

NHS Institute & NPSA Abolished - TBC

DH MoU Signed-off

Maple Street Refurb Completed

Staff Recruitment & TransfersFunctions Proposals Presented to Senior Team

STATUS

Build, Implement & Test EPRR Arrangements (PHE & NHS CB)New EPRR Arrangements Live

HEE Preparatory Running

Produce Detailed Operating Model

PHE Preparatory Running

Tfr Staff & Recruitment

Emergency Preparedness - Pre Olympics Testing

HRA Preparatory Running

Take On NPSA Functions - TBC

H&SC Bill

Dilnot Report Published SC WP & Draft Bill Published - TBC Parliamentary Passage - TBC

Decision on Buildings for NTDA in -London & Leeds

NHS CB SpHA Est’d – 31 Oct

NHS CB SpHA Established

Working Draft Framework

Approach to Competition Agreed

Interim DH Accountabilities Framework In Place

Network MGT Boards In Shadow

HEE & Networks Financial Roles & Responsibilities Agreed

Network’s Go Live

CEO Appointed

Exec Team AppointedExec Team Recruitment

Staff Consultation

HEE Functions Agreed

Agreed Org. Structure Design

V1.2 15-09-2011

SC&H Bill

NHS Commissioning

Board

NHS Other

Legislation &

Finance

Secondary

Finance

Monitor

DH

NTDA

HEE/Networks

Public Health England

Emergency Preparedness

DH Other

HRA

Informatics

Healthwatch

(England & Local)

Health & Wellbeing

Boards

Working Draft Framework

Chief Exec & Exec Team Appointed - TBC

Monitor Essential Services Regime Go LivePricing Roles & Responsibilities Agreed - TBC MoU In Place with NHSCB - TBC

New Operation Model in Place for CCP

Working Draft Framework

Network DevelopmentNetworks Mirror End State Operations

Agreed Costing & Tariff Management Process

First JHWS JSNA for 2014/15

Action Learning Sets – for early Imkplementor BoardsSupport for Elected Members

Develop Benchmarking Measures

Self Assessment of Local Government Readiness (SALGR)

SALGR SALGR SALGR SALGR

Acting Chief Exec & Acting Finance Director

HRA Established (Health Service Purposes)

Framework/MoU In PlaceShadow Term Arrangements Agreed

Shared Service Functions In PlaceNRES Financial Processes & Budget transferred to HRANew HO

Location

identified

NRES HO Tfrs to New Location

Current IRAS & RED contracts Tfr to HRA

Commence Shared Services Engagement

Website Development

Development Work

DG Structure SCS 1 AppointedDH Staff Moves

Redraft of Business Case Completed Majority of Bus. Case Costs Confirmed Bus. Case update – Interim Cost Outturn Bus. Case update – Interim Cost Outturn

Recruitment Process

Lords 2nd Reading 10 Oct TBC

Agreed Framework

Agreed IT Spec.

PTP Published

Chair & 1 NED Appointed CEO Appointed 5 NEDs Appointed

Commence HR Staff Process Tfr of Appointment Commission Staff

Location ready for occupancy

Working Draft Framework

Decision on Location - TBC

Monitor Additional Accommodation Available

HEE Decision on Location

Abolish GSCC Abolish CHRE

HEE Draft Operating Model

Sign-off EPRR Model

Concordat

Procurement Business Case Signed off

Directors Appointed

CEO In Post

Section 28 Staff Consultation Commences

Final DH Accountabilities Framework In Place

Informatics Key Organisational Transition .

Informatics Systems Transition (NHS)

Clarify budgets for routine and programme operation in

2012-13

Define arrangements for InformaticsDesign support arrangements for continuity of

local informatics capability

Latest date to get org design for coding into specification

Latest date to get funding approval for org design changes

IMS 3 Contract Award

Decision on national informatics functions destination/futures Closure of Informatics Directorate

and transfer of all continuing

informatics functions to new host

organisations completeClarification of main organisation design assumptions by the NHS CB

Latest dates for cross DH/NHS HR announcement on destination

organisations

HEE SRO Appointment

NHS PVFull Business Case Signed-off

High Level Commercial Strategy Completed

Senior Board Appts.

Commence HR ConsultationWaves of Staff Transfers

Narrative Narrative Narrative Narrative NarrativeNarrative

Activity Milestone Critical Activity Critical Milestone Go Live/Est Milestone Key Sequencing Completed Milestones & Activities At Risk Milestones Slipped Milestones & ActivitiesNarrative Narrative Narrative

Narrative

Business Case for the Health and Care Modernisation Transition Programme

56

110. The Listening Exercise and the subsequent Government Response to the NHS Future Forum’s report did impact quite significantly on the original timetable for change. The new timings allow for a more phased approach to transition as follows:

October 2011: NHS Commissioning Board established in shadow form as a special health authority, and SHA cluster arrangements in place.

During 2012: Health Education England and the NHS Trust Development Authority are established as Special Health Authorities, but in shadow form, without full functions.

April 2012: The next step in extending the choice of Any Qualified Provider, which will be phased in gradually.

By October 2012: NHS Commissioning Board is established as an independent statutory body, but initially only carries out limited functions – in particular, establishing and authorising Clinical Commissioning Groups.

October 2012: Monitor starts to take on its new regulatory functions, and HealthWatch England and local HealthWatch are established.

April 2013: SHAs and PCTs are abolished and the NHS Commissioning Board takes on its full functions. Health Education England takes over SHAs’ responsibilities for education and training. The NHS Trust Development Authority takes over SHA responsibilities for the FT pipeline and for the overall governance of NHS Trusts. Public Health England is established, and a full system of Clinical Commissioning Groups is established. But the NHS Commissioning Board will not authorise groups to take on their responsibilities until they are ready. Health and wellbeing boards are established in upper tier local authorities in England and Local HealthWatch established.

April 2014: Our expectation is that the remaining NHS Trusts will be authorised as Foundation Trusts by April 2014. But if any Trust is not ready, it will continue to work towards FT status under new management arrangements.

April 2016: Monitor’s transitional powers of oversight over Foundation Trusts will be reviewed (except for newly authorised FTs, where Monitor’s oversight will continue until two years after the authorisation date if that is later).

Business Case for the Health and Care Modernisation Transition Programme

57

Business Assurance Arrangements

Internal review

111. All deliverables will be reviewed and regularly approved by:

the relevant Programme/ Workstream Board; and

the Transition Board for Cross Cutting Functions, which confirms that proposals are consistent and integrated with all programmes and workstreams.

112. Some key deliverables will also require sign off by:

NHS Transitional Executive Forum, DH, Social Care and Local Government Board and / or DH Management Committee; and

(Transition) Executive Board.

113. An independent programme management expert, Ian Andrews, provides advice and Non-Executive Director scrutiny to the SROs and Transition Director.

114. Progress on transition is a standing item on the Department Board, and

the Board receives a regular status report on the Programme.

External review and assurance

115. The programme is subject to review from several sources:

Ministers review the programme on a regular basis, with Earl Howe PS(Q) appointed as lead Minister on Transition.

The programmes comprising the Transition Programme are subject to peer review through the long-established Gateway Review process, and the overall Transition Programme through the Cabinet Office Major Projects Authority and Major Projects Review Group (MPRG) processes.

Within Cabinet Office, the Major Projects Authority (MPA) oversees the Gateway Process to ensure best value for money and efficient delivery of major government projects. The Transition Programme is included within the Government Major Programmes and Project (GMPP) Portfolio, and quarterly reports are provided to the MPA by the Department of Health.

The OGC Gateway Process examines programmes and projects at key decision points in their lifecycle. It looks ahead to provide delivery confidence that they can progress to the next stage; the process is best practice in central government, including the health sector.

Business Case for the Health and Care Modernisation Transition Programme

58

Risk Management

116. Each SRO and Programme Board is responsible, supported by their

project support team, for determining, establishing and managing risks and issues within the wider programme framework and governance. They will maintain a risk and issues register covering their areas of responsibility and report these at regular intervals – alongside their Programme Status Reports which are submitted to their relevant senior Board. Risks and issues can be escalated through this process for consideration by the senior board, executives and the Transition SRO. To support the senior boards in their responsibility for coordinating risks and issues the Integrated Programme Office has established, and maintains, Transition Programme-wide risk and issues registers, incorporating key risks across the programme.

117. This register is updated on a cyclical basis, using monthly updates which

have been approved by the respective SROs and Programme Boards, discussing areas of concern with representatives from each of the programme teams or workstreams. A number of key strategic risks are included in the Departmental Risk Register, which is reviewed by the Executive Board and Transition risks are also escalated to the Departmental Board as appropriate.

Stakeholder engagement

118. As part of the staff engagement and stakeholder plans each SHA has

hosted a ‘Transition Event’. SHAs have also hosted a series of assurance events, where DH leaders held sessions with representatives of local stakeholders, including PCTs, acute NHS and FTs, community and independent sector providers, local authorities and GP consortia, to explore the key challenges in the region.

119. Regular engagement events continue with Local Government and third

sector organisations, along with a series of ministerial visits.

120. Consultations: Significant stakeholder and public engagement has taken place around the NHS White paper with the following associated consultations:

Healthy lives, healthy people: consultation on the funding and commissioning routes for public health.

Healthy lives, healthy people: transparency in outcomes, proposals for a public health outcomes framework.

Healthy lives, healthy people: our strategy for public health in England – White Paper consultation.

Liberating the NHS: developing the healthcare workforce.

Business Case for the Health and Care Modernisation Transition Programme

59

A consultation on proposals - transparency in outcomes: a framework for adult social care.

Liberating the NHS: Greater choice and control. a consultation on proposals.

Equity and excellence: liberating the NHS.

Liberating the NHS: commissioning for patients - consultation on proposals.

Liberating the NHS: increasing democratic legitimacy in health.

Liberating the NHS: regulating healthcare providers

Benefit Realisation Plan

121. The main quantifiable benefits from the planned structural reforms are

financial, primarily from the reduction in administrative costs from the closure of SHAs and PCTs, releasing some 24,500 staff. Indirect benefits will arise from the organisation changes, as they will facilitate or stimulate broader changes in clinical quality and efficiency (including the QIPP initiatives), across the NHS.

122. The intended wider benefits are:

better patient outcomes;

better alignment to patient demands and needs, and more clinical input;

improvement in response to public health threats and emergencies

improved public health outcomes and a reduction in health inequalities

reduced numbers of people living with preventable ill health and people dying prematurely whilst reducing the gap between communities

more responsive system, with stronger levers, and

more local decisions.

123. The ability to monitor and measure the benefits is the responsibility of the new organisations operations, through their Operating Frameworks and Mandates. In particular, the NHS Commissioning Board will need to monitor overall NHS performance and track the improvements, and the Bill’s duty to secure quality improvements will be incorporated into the design of Clinical Commissioning Groups, and evaluated as part of their authorisation process.

Business Case for the Health and Care Modernisation Transition Programme

60

124. The NHS Outcome Framework is a key part of the future NHS system to provide macro quality performance measures, and corresponding indicators.

125. During transition, an NHS early warning system is being developed to

monitor NHS performance on a monthly / quarterly basis.

Delivering Cost Benefits

126. Budgets are being set for the Health and Care System on the basis there

will be a reduction of one-third in administrative spending covering the functions of the Department of Health, SHAs, PCTs and ALBs that are not directly frontline services.

127. The one-third real reduction in administrative spending is equivalent to a

25.8% nominal reduction in total resources for the management of the system.

128. To achieve these reductions, PCTs and SHAs will be abolished and

Clinical Commissioning Groups and the NHS Commissioning Board will be created, together with Health and Wellbeing Boards, and new public health responsibilities in local authorities.

129. These cost benefits will be realised by the system keeping in financial

balance, and living within the reduced financial envelopes.

Realising Non-financial Benefits by key area

130. In addition to realising cost benefits as above, there are a substantial

number of non financial benefits. In many areas it is difficult to attribute these to a particular part of the system, however the following does provide an indicative benefits realisation for the key areas of activity:

Commissioning for Patients (Clinical Commissioning Groups and the National Commissioning Board)

131. While the main monetised benefit for this area are the reductions in

administration savings referred to above, the main non-monetised benefits are from improved clinical engagement, improved outcomes and more responsive and co-ordinated care. There are further additional benefits from the reduced variation in outpatient referrals and elective activity, improved care of patients with long term conditions, reductions in the level of urgent and emergency admissions, and improved prescribing.

Business Case for the Health and Care Modernisation Transition Programme

61

Provider Regulation

132. The new more stable and transparent regulatory regime will support

quality gains as providers face a clear set of incentives to improve.

Increasing local democratic legitimacy in Health (Health and Well Being Boards)

133. Greater democratic involvement, and requiring the attendance of key commissioning partners, elected representatives and local HealthWatch, will ensure stronger joint working, with services being tailored more towards local needs and priorities. This will be supported by the enhanced Joint Strategic Needs Assessment and joint health and wellbeing strategy, which should serve to identify and address needs across an area. Ultimately, this will lead to higher levels of patient satisfaction, improved quality of services and more cost effective commissioning.

Healthwatch

134. The main non financial benefits will be from improvements in the patient

experience, and health outcomes stemming from stronger public voice. Complaints advocacy will also lead to improved services and patient confidence in the Health and Social Care system. There should also be a reduced likelihood of significant ‘adverse events’ through better information flows.

Public Health:

135. Incorporating both national and local structures should provide a

streamlined and efficient service, which will make a positive impact on health and improve health outcomes.

Delivery of Non-Financial Benefits

136. The DH will publish a set of Outcomes Frameworks which will define the

outcomes for which we will hold the health and care system to account. Each year the Secretary of State will set out his objectives for the NHS Commissioning Board in the Mandate. The Department's ALBs, including the NHS Commissioning Board will be held to account to deliver the outcomes and objectives set out by the Department effectively, efficiently and economically. Transparent, outcome-focused indicators will enable the DH and the NHS and the public to understand progress. Each year

Business Case for the Health and Care Modernisation Transition Programme

62

the Secretary of State will publish an annual report on the NHS which will set out a review of the NHS's achievements, that will provide evidence of financial and non financial benefits realisation.

Business Case for the Health and Care Modernisation Transition Programme

63

Appendix A

Changes adopted following the NHS Future Forum’s report

The NHS Future Forum was set up by the Secretary of State in April 2011, comprising of a group of 45 leading professionals across health and social care. It focused on four themes:

how advice from a range of healthcare professions can improve patient care;

how to ensure public accountability and patient involvement in the new system;

the role of choice and competition in improving the quality of care; and

how new arrangements for education and training can support the modernisation process.

The Forum reported to the Government in June 2011 and the key changes set out in the Government response to the Future Forum report are below:

GP consortia will now be called “clinical commissioning groups”, and will have governing bodies with at least one nurse, one specialist doctor and lay members;

where a clinical commissioning group is ready and willing, it will take on commissioning responsibility from April 2013; if it is not ready by that date, the local arms of the NHS Commissioning Board will commission on its behalf;

commissioners will be supported by clinical networks and clinical senates, both hosted by the NHS Commissioning Board;

there will be clearer duties across the system to involve patients, the public and carers;

foundation trusts will have public board meetings;

a strengthened role for health and wellbeing boards in driving local commissioning;

strengthening the role of HealthWatch England by ensuring that other bodies at the national level need to respond in writing to its advice;

Monitor’s core duty will be to protect and promote the interests of patients – not to promote competition as if it were an end in itself;

there will be further safeguards against price competition, cherry picking and privatisation;

there will be stronger duties on commissioners to promote, and Monitor to support, care that is integrated around the needs of users; and

Business Case for the Health and Care Modernisation Transition Programme

64

Public Health England will be established as an Executive Agency rather than a core part of the Department of Health.

Business Case for the Health and Care Modernisation Transition Programme

65

Appendix B

Accountabilities in the New Structure

The key accountabilities in the new structures are set out in the Accountabilities Statement for the Department of Health. A brief overview summary is provided below. Ministers will retain ultimate accountability for the health service: as now, they will be responsible for setting strategic direction, overseeing the system and for accounting to Parliament. The Bill, however, significantly reduces their role and that of the Department, in day-to-day operational management. Department of Health’s the Permanent Secretary is accountable to Parliament for the proper stewardship of the resources assigned to the Department by the Treasury through the Spending Review and voted by Parliament. Her responsibilities are set out in the Treasury guidance Managing Public Money. The Department’s Accounting Officer appoints an Accounting Officer for each ALB, with the exception of the NHS Commissioning Board where the Health and Social Care Bill provides directly for the Chief Executive of the Board to be its Accounting Officer. Each ALB Accounting Officer will be held to account for the stewardship of public money and assets and the delivery of the ALB’s objectives and outcomes as agreed with the Department. For all ALBs, a framework agreement will set out their responsibilities and delegations, and ALBs are expected to hold open board meetings and make papers available on their websites. CCGs will be accountable to the NHSCB for the outcomes they deliver for patients and their stewardship of public resources. The NHSCB Accounting Officer will appoint an Accountable Officer for each CCG, and they will hold specific responsibilities for promoting continuous improvement in the quality of the services it commissions and providing good value for money.

Business Case for the Health and Care Modernisation Transition Programme

66

Appendix C

Other Arm’s Length Bodies – roles from April 2013

Key: ENDPB = Executive Non Departmental Public Body

SpHA = Special Health Authority

ALB Category Role

Care Quality

Commission

(CQC)

ENDPB CQC is the independent regulator of health and adult

social care providers in England. All providers of

regulated activities, including NHS and independent

providers, have to register with CQC and meet a set

of essential requirements of safety and quality. CQC

has independent enforcement powers where

providers are not meeting the requirements and

operate a joint licensing regime with Monitor. Current

responsibility of assessing NHS commissioning

moves to the NHS Commissioning Board. In the

future, it will receive functions from NIGB, and may

also receive functions from other organisations, e.g.

HTA and HFEA

It will also be the host organisation for Healthwatch

England, which will operate as a statutory committee

of CQC and act as the independent national

champion for health and social care consumers.

Business Case for the Health and Care Modernisation Transition Programme

67

Health Research

Authority (HRA)

ENDPB The role of the HRA is to protect and promote public

and patient interests in health research, streamlining

regulation to facilitate appropriate research, improving

health and helping to make it cost-effective to do

research in the UK.

It has been initially established as a Special Health

Authority from December 2011. HRA has the National

Research Ethics Service (NRES) as its core and has

taken on the functions which have been the

responsibility of the National Patient Safety Agency. In

due course, it will perform the Secretary of State’s

function of approving the processing of patient

information for medical research. Subject to

legislation, HRA will be established as a Non

Departmental Public Body (NDPB), which will enable

it to take on more functions. There will be a

consultation on the future of the Human Fertilization

and Embryology Authority to determine if its research-

related functions should pass to the HRA.

Health & Social

Care Information

Centre (HSCIC)

ENDPB The Information Centre is the national repository for

information collected from NHS and social care

organisations in England. It collects, joins up and

publishes information in an anonymised and de-

identified form so that it can be used for many

purposes (including to enable more integrated

provision of care, for public accountability and to

support research.) HSCIC will change status from a

special health authority to an ENDPB in April 2013.

Human

Fertilisation &

Embryology

Authority (HFEA)

ENDPB The Human Fertilisation & Embryology Authority

licences and monitors in vitro fertilisation (IVF), donor

insemination and human embryo research in clinics,

regulates the storage of sperm, eggs and embryos.

The ALB review recommended that HFEA should be

abolished as an ALB and its functions transferred to

other regulators by the end of the current Parliament.

DH is examining the practicalities and legal

implications of how to divide the functions between the

proposed Health Research Authority and the CQC.

Business Case for the Health and Care Modernisation Transition Programme

68

Human Tissue

Authority (HTA)

ENDPB The Human Tissue Authority is responsible for

implementing the Human Tissue Act and is a

Competent Authority for the EU Tissue and Cells

Directive. It regulates activities such as anatomical

and post-mortem examinations, transplantations and

the storage of human material for education, training

and research. The ALB review recommended that

HTA should be abolished as an ALB and its functions

transferred to other regulators by the end of the

current Parliament. DH is examining the practicalities

and legal implications of how to divide the functions

between the proposed Health Research Authority and

the CQC.

National Institute

for Health & Care

Excellence (NICE)

ENDPB NICE provides guidance, sets quality standards and

manages a national database of best practice for the

NHS in England to improve people's health, prevent

and treat ill health. Its remit is being extended to

adults and children’s social care. NICE will change

status from a special health authority to an ENDPB in

April 2013.

NHS Blood &

Transplant

(NHS BT)

SpHA NHSBT is responsible for the provision of a reliable,

efficient supply of blood to hospitals in England and

North Wales. It is also the organ donation

organisation for the UK and is responsible for

matching and allocating donated organs. NHSBT will

seek opportunities to become more commercially

effective.

NHS Business

Services Authority

(NHS BSA)

SpHA BSA is the main processing facility for payment,

reimbursement, remuneration and reconciliation for

NHS patients, employees and affiliated parties. This

includes the remuneration of Community Pharmacists,

Dentists and administration of the NHS pensions

scheme alongside a range of other transactional

functions. It has been subject to a review examining

its potential for increased commercial opportunities.

NHS Litigation

Authority (NHS LA)

SpHA NHSLA’s main role is to administer five indemnity

schemes on behalf of Secretary of State under which

NHS bodies pool some of their clinical and non-

clinical liabilities. It has been subject to a review

examining commercial efficiencies.

Business Case for the Health and Care Modernisation Transition Programme

69

Medicines &

Healthcare

Products

Regulatory Agency

(MHRA)

Executive

Agency

The MHRA protects public health through regulation

of medicines and devices, by helping users to

understand their risks and benefits, and by

encouraging and facilitating developments in products

that will benefit people. It will take on the Central

Alerting System (CAS) from NPSA; the Research

Capability Programme (RCP); and, the National

Institute for Biological Standards and Control (NIBSC)

from HPA.

Arm’s Length Bodies leaving the system

ALB Name Category Function Transfers

Alcohol Education and Research Council

AERC

ENDPB The assets of AERC have been transferred to a new independent charity, Alcohol Research UK, which was launched in September 2011, as part of the cross-government policy to reduce the harm from alcohol misuse. The residual body will be abolished by the end of July 2012.

Appointments Commission

AC

ENDPB Will close by the end of October 2012 as an ALB in view of the substantial reduction in the number of appointments required. The remaining appointment work will transfer to DH, the NHS CB and the NTDA. Secretary of State and Privy Council will, in future, retain powers of appointment

Council for Healthcare Regulatory Excellence

CHRE

ENDPB This will be made a self-funding body, by charging a levy on regulators by the end of September 2012. Its role will be extended role to set standards for and quality assure voluntary registers. It will be renamed the Professional Standards Authority (PSA)

General Social Care Council

GSCC

ENDPB The role of the regulation of social workers in England to the Health Professions Council (HPC) will be transferred to and will be renamed the Health and Care Professions Council (HCPC) to reflect its remit across health and social care. GSCC will close at the end of July 2012

Health Protection Agency

HPA

ENDPB HPA will close as a statutory organisation by April 2013 and transfer functions to the Secretary of State as part of the new Public Health England (PHE)

Business Case for the Health and Care Modernisation Transition Programme

70

National Patient Safety Agency

NPSA

SpHA NPSA will close by the end of July 2012. Some safety functions will be retained, with the responsibility for them moved to the NHS Commissioning Board. DH will transfer National Research Ethics Service (NRES) functions to a new Health Research Authority. National Clinical Assessment Service (NCAS) will become self-funding over the next two to three years (hosted by NICE during 2012/13). Confidential Enquiries will sit with the National Clinical Audit Patient Outcome Programme, managed on behalf of the Department by the Healthcare Quality Improvement Partnership (HQIP)

NHS Institute for Innovation and Improvement

NHSi

SpHA NHSi will close no earlier than July 2012 and its functions that will support the NHS Commissioning Board in leading for quality improvement will be moved to the Board. DH will review the potential for its remaining functions to be delivered through alternative commercial delivery models

National Treatment Agency for Substance Misuse

NTA

SpHA NTA will close by April 2013 and functions will transfer to the Secretary of State as part of the new Public Health England

National Information Governance Board for Health and Social Care

NIGB

ANDPB NIGB will close by the end of December 2012 and functions will transfer to the Care Quality Commission, the NHS Commissioning Board and the Health Research Agency.

(Not part of DH’s ALB review, but part of the Cabinet Office’s public bodies review.)

Joint Committee on Vaccination and Immunisations

JCVI

ANDPB JCVI will be abolished by the end of December 2012 with the intention of being re-constituted informally as an expert committee at the Department of Health to advise the Secretary of State (in relation to public health in England).

(Not part of DH’s ALB review, but part of the Cabinet Office’s public bodies review.)