Bunker Maintenance and Bunker Renovations
Mark KingoraGolf Course Manager
Golf Course SuperintendentBethesda Country Club
![Page 2: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/2.jpg)
Early bunker maintenance begins in late winter or early spring. A simple depth check is performed to insure that the sand depth is consist at 4 inches throughout each bunker.
![Page 3: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/3.jpg)
A standard soil probe is marked at 4 inches and is used to check the sand depth. During this pre-season check, we typically discover that sand depths vary where the depths are usually less than 4 inches nearest to the green and depths are usually greater than 4 inches in the low areas or farthest away from the green, which is normal due to water flow and normal raking. Any areas of a bunker with excess sand above 4 inches is re-distributed to areas that need additional sand. When sand cannot be moved within the bunkers to maintain the consistent depth, additional new sand is purchased and added as needed.
![Page 4: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/4.jpg)
Bunker Maintenance Process
1. Begins in late winter or early spring2. A simple depth check is performed to insure that the
sand depth is consist at 4 inches throughout each bunker.3. Re-distribute sand or add new sand4. Periodic depth checks
- In heavily concentrated collection areas- After heavy rainfall
5. Maintenance raking is normally 5 times/week6. Grass bunker face mowing is weekly during the growing
season
![Page 5: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/5.jpg)
Factors affecting bunker playability
1. Weather - Rain makes the sand heavy and compacted- Golf balls don’t bury- May appear that sand is too shallow- Dry conditions make the sand fluffy- Golf balls may bury (“fried egg”)- May appear sand is too deep- Normally does not occur because of
irrigation2. Irrigation can have the same affect as rain
![Page 6: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/6.jpg)
Bunker Renovations
1. Bunker Face Re-grassing2. Bunker Sand Replacement
![Page 7: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/7.jpg)
Bunker Face Re-grassing
First, the sand is pulled away from the edge approximately 3-6 feet to give ample room to work. Soil was added to this greenside part of this bunker so that the grass face could be re-built and to reduce the 12 inch depth of sand on the perimeter to a 2 -4 inch taper to reduce the likelihood of plugged balls.
![Page 8: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/8.jpg)
Some of this sand was re-distributed throughout the bunker to maintain a consistent 4” depth.
![Page 9: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/9.jpg)
Sand Splash
Several of the last photos also represents sand buildup from 20 years of bunker shots or “sand splash.”
![Page 10: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/10.jpg)
![Page 11: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/11.jpg)
Three to six feet of the surrounding turf was removed and replaced with zoysiagrass as was specified in Arthur Hills golf course re-design from the early 1990’s. Zoysiagrass was chosen due to it’s ability to withstand drier, sandy soil conditions and shorter mowing heights. Zoysia also has a great brown/tan contrasting color to the white sand and the dark green grasses throughout the golf course in the fall through early spring.
![Page 12: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/12.jpg)
Soil was added to reconstruct the bunker face and edge.
![Page 13: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/13.jpg)
Sod or turf was removed between the bunker and the green and the soil was lowered a foot to its original elevation.
![Page 14: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/14.jpg)
All reconstructed areas are compacted with a vibratory plate tamper to stabilize the soil.
![Page 15: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/15.jpg)
![Page 16: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/16.jpg)
The sand is being redistributed for a consistent 4” depth. The mechanical rake has a plow attachment to aide in this process.
![Page 17: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/17.jpg)
Vibratory Plate Tamper
The vibratory plate tamper is also used on the sand to minimize plugged “fried egg” lies in the bunker.
![Page 18: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/18.jpg)
![Page 19: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/19.jpg)
Completed, number 8 greenside bunkers. These three bunkers were completed in 3 days.
![Page 20: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/20.jpg)
Local RulePlease follow the Local Rule for all renovated bunkers. It is a mandatory drop from all new sod marked with white paint.
It will take 4-6 weeks to establish the turf. Bunkers that are renovated include all on #7 and #8, plus the fairway bunkers on #10 and #15.
Please do not walk up the steep, greenside face of the grass bunker surrounds and keep all traffic on the new sod to a minimum.
![Page 21: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/21.jpg)
Bunker Sand Replacement
• Our most recent Bunker renovations were completed in 2006• Bunker sand usually last 5-7 years• All bunkers have been evaluted• Bunker Sand Replacement Project
– Complete replacement of the sand• Left bunker on #15 green• Left front bunker on #18 green• Possibly the right bunker on #14 green
– Partial replacement of the sand• Remove top contaminated layer• Add new sand to the 4” depth
– Add sand to the 4” depth as needed
![Page 22: Bunker Maintenance and Bunker Renovations Mark Kingora Golf Course Manager Golf Course Superintendent Bethesda Country Club.](https://reader033.fdocuments.net/reader033/viewer/2022050816/5519ca53550346443e8b480a/html5/thumbnails/22.jpg)
• Most bunkers fall into the categories of partial sand replacement or just a need for additional sand.
• Our goal is to extend the life of the bunkers from 5-7 years to 10 -12 years.
• We will evaluate the bunkers annually and may repeat this process in 3 or 4 years to even further extend the life of the bunkers and reduce the need of major bunker reconstruction.