Bundle Finance & Performance Committee 19 December 2019
Transcript of Bundle Finance & Performance Committee 19 December 2019
Bundle Finance & Performance Committee 19 December 2019
1 15:30 - FP19/291 Apologies for absence2 FP19/292 Declaration of Interests3 15:30 - FP19/293 Draft minutes of the previous meeting held on 4.12.19 and summary action plan
FP19.293a Minutes FPC 4.12.19 Public v.03.docx
FP19.293b Summary Action Log v2.doc
4 15:35 - FP19/294 Finance Report Month 8Ms Sue HillRecommendation:It is asked that the report is noted, with particular reference to the forecast deficit of £35m and the specificactions in progress to achieve plan.
FP19.294 Finance report Month 8.docx
5 15:55 - FP19/296 2019/20 Annual Plan Progress Monitoring ReportMr Mark WilkinsonRecommendation:The Finance & Performance Committee is asked to note the report.
FP19.296a APPMR.docx
FP19.296b Annual Plan Progress Monitoring Report - November 2019 v0.8.pptx
6 16:05 - FP19/297 Integrated Quality and Performance report Month 8Mr Mark WilkinsonRecommendation:Finance & Performance Committee is asked to scrutinise the report and to consider whether any area needsfurther escalation to be considered by the Board.
FP19.297a IQPR cover November 2019 FINAL.docx
FP19.297b IQPR November 2019 FINAL v1.0.pdf
7 Business cases for approval prior to Board ratification7.1 16:35 - FP19/298 Bryn Beryl Integrated Dementia & Adult Mental Health Centre Capital Business Case
Mr Mark WilkinsonRecommendation:The Committee is asked to approve the capital business case for the Bryn Beryl Integrated Dementia & AdultMental Health Centre
FP19.298a Bryn Beryl business case december 2019 (2).docx
FP19.298b FINAL BB Integrated Dementia AMH Centre buisess case 18 Nov 19 (V9 UpdatedCosts).docx
FP19.298c EqIA screening form BB Dementia AMH Centre (003).doc
8 16:45 - FP19/299 Summary of Private business to be reported in publicRecommendation:
The Committee is asked to note the report
FP19.299 Private session items reported in public v1.0.docx
9 16:47 - FP19/300 Issues of significance to inform the Chair's assurance report10 16:49 - FP19/301 Date of next meeting 23.1.20 9.30- 13.00 Bangor University11 16:49 - FP19/302 Exclusion of the Press and Public
Resolution to Exclude the Press and Public“That representatives of the press and other members of the public be excluded from the remainder of thismeeting having regard to the confidential nature of the business to be transacted, publicity on which wouldbe prejudicial to the public interest in accordance with Section 1(2) Public Bodies (Admission to Meetings)Act 1960.”
3 FP19/293 Draft minutes of the previous meeting held on 4.12.19 and summary action plan
1 FP19.293a Minutes FPC 4.12.19 Public v.03.docx
Minutes F&P 4.12.19 Public session v.03 1
Finance & Performance CommitteeDraft minutes of the meeting held In-Committee on 4.12.19
in Carlton Court, St Asaph
Present:
Mr Mark PolinMr John Cunliffe Mrs Jackie Hughes
BCUHB Chairman Independent Member / Committee Vice ChairIndependent Member (co-opted for meeting)
In Attendance:Mr Phillip BurnsMr Gary DohertyMrs Sue GreenMr Michael HeartyMs Sue HillMr Trevor HubbardMr Andrew KentMr Rob NolanMrs Jill NewmanMrs Llinos RobertsMr Andrew SallowsMrs Katie SargentMs Emma WilkinsMr Mark WilkinsonMs Diane Davies
Interim Recovery Director Chief ExecutiveExecutive Director Workforce and Organisational Development (OD)Financial AdvisorActing Executive Director of FinanceDeputy Director Nursing and Midwifery (part meeting)Interim Head of Planned Care (part meeting)Finance Director ~ Commissioning and Strategy (part meeting)Performance Director Executive Business ManagerDelivery Programme Director, Welsh Government (WG) Assistant Director ~ Communications (observer)Deputy Director, Financial Delivery Unit (FDU)Executive Director Planning and Performance (part meeting)Corporate Governance Manager (Committee Secretariat)
Agenda Item Discussed Action By
FP19/267 Apologies for absence
It was noted that the meeting date had been postponed from 28.11.19 to 4.12.19 due to operational needs, subsequently apologies were received from Mr Eifion Jones, Mrs Helen Wilkinson, Mrs Gill Harris and Mrs Deborah Carter.
FP19/268 Declarations of Interest
A declaration of interest regarding the CT Scanner, Ysbyty Glan Clwyd (YGC) business case was received from Mrs Jackie Hughes, Independent Member in respect of her substantive post within radiology services.
FP19/269 Draft minutes of the previous meeting held on 24.10.19 and summary action plan
Minutes F&P 4.12.19 Public session v.03 2
The minutes were agreed as an accurate record, subject to a typographical error, and updates were provided to the summary action log.
FP19/270 Review of Corporate Risk Assurance Framework - risks assigned to Finance and Performance Committee
FP19/270.1 The risks assigned to the Committee were discussed. It was noted that the framework would be evolving into a new format with effect from March 2020 which could address concerns raised by some members in relation to the correct utilisation of the terms ‘controls’ and ‘actions’ within the documentation provided. The Chief Executive reminded that during the changeover period it remained important to ensure all risks were adequately reflected until 31.3.20.
FP19/270.2 In respect of CRR06 Financial stability, the RTT funding issue risk was highlighted by the Executive Director of Finance. The efficacy of the controls introduced / initial risk rating assignment were also questioned given that the current risk rating had increased from 12 to 16. The Chairman also questioned whether a risk needed to be raised on the overall financial sustainability of the Health Board.
FP19/270.3 In respect of CRR11a Unscheduled care, the Committee also queried the efficacy of the control, however the Chief Executive advised that whilst there had been an increased demand there had also been significant areas of improvement made.
FP19/270.4 In respect of CRR11b Planned Care, the Committee questioned whether the risk effectively addressed safety and potential areas of harm.
FP19/270.5 The Chief Executive undertook to feedback discussion to the Deputy Chief Executive regarding addressing risks of: Overall financial sustainability of the Health Board Reputational risk Overarching delivery of the overall plan
FP19/270.6 The Chief Executive also agreed to provide a briefing note to members to address: What is the ‘in year’ reporting plan? How this would fit for next year? The robustness of plan Consideration of whether planned care ‘Harm’ risks were adequately
identified within the corporate register especially in areas of Urology and Endoscopy.
It was resolved that the Committee agreed thatthe risk ratings CRR06, 11a, 11b and 12 remain as stated
GD
GD
FP19/271 Three Year Outlook and 2019/20 Annual Plan Update
FP19/271.1 The Executive Director of Planning and Performance presented this item, highlighting the 8 proposed changes and provided assurance that these
Minutes F&P 4.12.19 Public session v.03 3
had not been reset due to non-delivery but for pratical operational reasons set out in the report. In the discussion which followed the Committee stated that it was difficult to ascertain differences in comparison to the previous position reported within the format provided and questioned whether more narrative could be included to address this.
FP19/271.2 The Committee asked that health records storage at YGC be reviewed in order to ensure that they continued to be addressed in respect of capital changes. In discussion of delays with the WCCIS programme, the Executive Medical Director agreed to follow up potential domiciliary care software in use within a South Wales Health Board as a potential interim solution ahead of WCCIS implementation. The Interim Recovery Director advised a degree of caution given the Board’s experience in relation to the potential delays with software implementation (Microsoft).
It was resolved that the Committeenoted the report and approved the proposed changes to the plan as set out
The Interim Head of Planned Care joined the meeting
MW
DF
FP19/272 Integrated Quality and Performa7nce report
FP19/272.1 The Executive Director of Planning and Performance presented this item drawing attention to the content of the executive summary provided within the report. He particularly highlighted stabilisation of the 36 waiters and sustained improvement within unscheduled care at Wrexham Maelor although performance overall was challenging. The Committee observed that there was insufficient narrative to explain the declining performance in respect of RTT within the report.
FP19/272.2 The Financial Advisor questioned at what point the 70% of performance reporting at RED overall would improve, following discussion in which the Executive Director of Planning and Performance pointed out that these were not all of equal weighting, it was agreed that the January report would present a longitudinal view on the profile of targets and performance.
FP19/272.3 The Committee questioned deterioration in a number of areas including diagnostics and cancer, and whether these were significant trends or short term issues. The Interim Lead for Planned Care undertook to respond to IM Lucy Reid’s question regarding follow up waits following the meeting. Significant concern was raised regarding Eye Care services, especially in respect of the interface between primary and secondary care which were being addressed. The Executive Director of Planning and Performance undertook to consider a more effective presentational format to reflect the profile of activity regarding External Contracts performance.
FP19/272.4 In relation to the Financial Advisor’s observations regarding a discrepancy of figures between the RTT and IQPR report, the Interim Lead for Planned Care undertook to review the IQPR each month to ensure correlation with his report. He also agreed to include further process control context highlighted by WG’s Delivery Programme Director to ensure RTT reporting
MW
AK
MW
AK
AK
Minutes F&P 4.12.19 Public session v.03 4
addressed WG requirements and concerns within the report to be presented on 23.1.20. WG’s Delivery Programme Director undertook to share RTT reporting formats by other Health Boards, which could be helpful to BCUHB, with members and the Interim Lead for Planned Care. He emphasised the need to demonstrate transparency in closing gaps that he had highlighted in respect of cohort numbers and planned delivery.
FP19/272.3 Agency expenditure increase was discussed including the non-delivery of expected improvements following the increased recruitment to substantive appointments which had been taking place. The increase in workforce sickness was discussed in which the Executive Director of Workforce & OD explained various initiatives which were taking place to address the issue, noting that BCU was not an outlier in Wales.
FP19/272.4 It was noted that the Chairman had raised a number of issues with the Executive Director of Primary and Community Care services outside the meeting in relation to primary care and dental services performance.
It was resolved that the Committeenoted the report
AS
FP19/273 Update on Referral to Treatment (RTT) improvement programme and year-end forecast
FP19/273.1 The Interim Lead for Planned Care presented this item, he advised that of the 15 actions being progressed within the action plan, work was on schedule with the exception of two, due to delays within the external text messaging service and demand & capacity work. Discussion ensued on these issues including levels of confidence, the need for process robustness, and the Financial Advisor questioned how financial planning might be ensured.
FP19/273.2 The Chairman questioned when endoscopy performance trajectory would be understood. The Interim Lead for Planned Care advised that clarity on demand and capacity would be provided within 8 weeks on 4/5 key specialties noting particular issues with capacity and variance across the organisation. The Financial Advisor emphasised the difficulties involved in planning around a forecast performance in the range of 9 - 12k.
FP19/273.3 The Committee questioned why the ‘treat in turn’ initiative had not realised the improvements envisaged which the Interim Lead for Planned Care explained, including the complexity and difficulties around organisational culture across various workforce groups. It was noted that substantive capacity and adjustment to organisational process was being discussed with the Deputy Chief Executive.
FP19/273.4 A discussion ensued on the effect of HMRC changes on activity, in which WG’s Delivery Programme Director advised that other Health Boards had noted an increase, but this was much more significant at BCUHB. In response to the Chairman’s question on whether RTT funding had been spent on core activity, the Interim Lead for Planned Care explained how some funding had
Minutes F&P 4.12.19 Public session v.03 5
been utilised eg Urology West. The Interim Recovery Director advised that this was an area in which he and the Executive Director Workforce & OD needed to ensure increased understanding in order to improve financial grip in this significant area of expenditure, whilst noting work undertaken in supporting core specialty activity by the Workforce & OD Division. It was also noted that discussion was taking place in relation to financial support for endoscopy services in order to address patient risk.
FP19/273.5 It was agreed that the Interim Lead for Planned Care would ensure that Demand and Capacity was addressed in the January report including resources, waiting list additions and improved understanding re HMRC implications.
FP19/273.6 The Committee sought further clarification on the revised forecast. The challenges of meeting 11,799 were outlined, however it was noted that, should more funding be secured to address capacity, there was a possibility of attaining in the region of 9,000. The Financial Advisor was informed that figures reported within the finance report had been superseded by the updated RTT report.
FP19/273.7 Considerable debate ensued on the spending required, in which the FDU Deputy Director sought clarification on the amount being committed. The Chief Executive assured that BCU would not expend more than allocated on RTT.
FP19/273.8 It was agreed that the Interim Planned Care Lead, Acting Executive Director of Finance, WG’s Delivery Programme Director and the FDU Deputy Director would arrange to discuss Clarification on definitive RTT number Investment – per key decision slide Diary / Timeline confirmation re financial planning before the 5.12.19 Board
workshop meeting Clinical risk and cost issues (Risk v Finance / Performance v Deficit) Provide clarity on what will be delivered (activity forecast) based on £13.8m
as committed by WG.
It was resolved that the Committeenoted the report and revised forecast position
The Interim Head of Planned Care left the meeting.
AK
AK/ SH/ AS/ EW
FP19/274 Unscheduled Care and Building Better Care update
FP19/274.1 The Deputy Director Nursing and Midwifery joined the meeting to present this item which provided an update against both the unscheduled care performance of each acute site and the fourth 90 day cycle of the unscheduled care Building Better Care programme for the period of October 2019. The improvements within Wrexham Maelor ED were highlighted, albeit with the aid of additional senior resource and it was noted that targeted work was also being undertaken at Ysbyty Glan Clwyd (YGC) and Ysbyty Gwynedd (YG).
Minutes F&P 4.12.19 Public session v.03 6
Performance within West, Central and East Health Economies were provided within the report.
FP19/274.2 Debate ensued on the improvements introduced. WG’s Delivery Programme Director commended the improvement made, especially at Wrexham Maelor however, he questioned sustainability and cultural change. The Chief Executive supported the permanent transformation work being undertaken, citing examples of good practice and positive staff experience as well as highlighting the positive effect on the ‘front door’ of YGC and YG.
FP19/274.3 The Chairman questioned ambulance handover performance and actions necessary to address long waiters within ED which had been highlighted to him on a recent visit. Discussion ensued in which DTOC, bed day improvement, ED pathway, YGC establishment and new modelling was raised as well as whether cost pressures were being factored into planning for the following year. The Interim Recovery Director highlighted ‘noise in the system’ in respect of a perception of inequality between sites which were under performing in managing funding.
It was resolved that the Committeenoted the unscheduled care performance for October across BCUHB and for each health economynoted the update from the Building Better Care programme and ongoing work within phase 4
FP19/275 Item deferred
FP19/276 Capital Programme report Month 7
It was resolved that the Committee
noted the report and revised programme
FP19/277 Finance Report Month 7
FP19/277.1 The Acting Executive Director of Finance presented the report. The Chairman questioned why expenditure was not perceived to be under control, especially in respect of continued overspending at the YGC site, and whether this was repeat pattern behaviour of the previous year.
FP19/277.2 The Interim Recovery Director advised that YGC was a specific area of concern given that there was reporting instability. He advised that a £2.9m cost pressure was being absorbed by other areas of the organisation and reported on work being undertaken with Improvement Groups.
FP19/277.3 In response to the Chairman’s question regarding the level of confidence in attaining the year end forecast, the Chief Executive affirmed that he expected BCU would achieve this. The Financial Advisor raised his concern regarding the year to date overspend and inability to manage cost pressures. He was cautious regarding the rate of savings generation required to deliver by year
Minutes F&P 4.12.19 Public session v.03 7
end, which included 50% of ‘red’ schemes . He also questioned when prioritisation would be addressed in respect of the allocative approach being taken. FP19/277.4 The Chairman emphasised the need to understand the drivers of the deficit. In the discussion which followed regarding the cost pressures faced and achievement of planned savings, the Acting Executive Director of Finance advised that decisions were being made with some urgency. The Interim Recovery Director advised confidence in delivery of £40m savings by year end in order to achieve the £25m target. He also stated that discussion had commenced with the Health Economies and questioned whether funding for the interim Managing Directors had been factored into next year’s planning.
FP19/277.5 The Chief Executive stated that BCU would need to meet the £35m deficit forecast, excluding the Welsh Risk Pool cost pressure highlighted and explore scope for other savings. He assured that BCU’s ambition had always been to deliver on the control target.
It was resolved that the Committeenoted the report with particular reference to the forecast deficit of £35m and the specific actions in progress to achieve plan.
FP19/278 Financial Recovery Group report 7
FP19/278.1 The Interim Recovery Director reported positively on the forecast position and delivery of the cost improvement programme at month 8. He advised that the programme contained £46m savings with scope for more.
FP19/278.2 The Interim Recovery Director informed that prospective savings plans for the next financial year were being identified, highlighting the tightened grip and control processes introduced and transformation required which would be discussed further at the Board Workshop scheduled to be held on 5.12.19 including challenges within Estates, Facilities and Digital. The Chairman requested that these would need to be presented no later than January 2020.
FP19/278.3 The Interim Recovery Director advised that PWC actions had been completed with the exception of 12 which were expected to be delivered by the end of December and going forward the actions would be managed within executive portfolios. In response to the Committee’s question regarding whether there was sufficient capacity to deliver in respect of Continuing Health Care, he advised that ongoing oversight was required along with addressing the CHC structure and longer term budgeting.
It was resolved that the Committeenoted the report
FP19/279 Presentation: Financial Planning
FP19/279.1 The Finance Director ~ Commissioning and Strategy joined the meeting to provide the presentation which set out BCU’s ambition to exit Special Measures, improve Key Metrics, achieve service Redesign / Transformation and
Minutes F&P 4.12.19 Public session v.03 8
establish a Digitally Enabled Clinical Strategy. The paper also referenced the outline timetable, the resource allocation and BCUHB’s planning assumptions.
The Financial Gap Assessment also addressed Health Board’s statutory duties, cost pressure assessment and savings opportunities. Key decisions to be discussed are:
• What is the ask for 20/21?• How will the underlying deficit assessment will be considered as part of
budget setting?• What growth / cost containment will be supported / presented?• How the savings target will be set • Profile of savings• Prioritisation of funding• Source of funding for any developments to be identified as part of IMTP
FP19/279.2 In response to the Committee the Finance Director – Commissioning & Strategy clarified that transformation funding was non-recurrent, not required to be reimbursed and had not been factored into the figures provided. Discussion ensued on potential reputational risk should BCU withdraw from activities provided via transformation funding which was understood to be the subject of evaluation and investment decisions. The Interim Recovery Director agreed to include investment sums required within key decisions to be discussed at the Board workshop. The Committee discussed the difficulty in moving forward the planning process before WG’s allocation letter was received which would necessitate consideration based on assumptions. It was resolved that the Committeereceived the presentation
PB
FP19/280 Value Based Healthcare
FP19/280.1 The Acting Executive Director of Finance provided the presentation which was seen to be driving huge benefits for patients as well as cost across the healthcare sector, particularly the NHS in Wales. It was noted that the approach was successful within other Health Boards and a necessary part of the transformation agenda to move forward.
It was resolved that the Committee• approved the Executive Leadership of the programme through the Executive Medical Director and Acting Executive Finance Director• approved the structure for progressing this programme and the central role of the Clinical Effectiveness Group • endorsed the request for the Clinical Effectiveness Group to develop the VBHC programme• approved the Heart Failure Service as the development programme for VBHC in the Health Board• note that programme documentation for Heart Failure Services would be provided to a future meeting along with an assessment of capacity required to deliver the programme
Minutes F&P 4.12.19 Public session v.03 9
FP19/281 External Contracts Update
FP19/281.1 The Acting Executive Director of Finance presented this report. She highlighted that there had been some quality issues raised in relation to the Countess of Chester contract. The Committee discussed how BCU might be more innovative in the utilisation of care homes, noting that the Executive Director of Primary and Community Services was exploring developments within Hywel Dda Health Board.
It was resolved that the Committee noted the financial position on the main external contracts at September
2019 and anticipated pressures noted the work underway in respect of stabilising wider health / patient care
contracts and key risks / related activity noted the work underway in relation to RTT
FP19/282 Workforce Quarter 2 2019/20 Performance Report
FP19/282.1 The Chairman questioned whether there was any area of concern in respect of objectives reporting red status. It was noted that in respect of Mental Health and Learning Disability vacancy levels that an establishment review would address this area which was currently being supported by the W&OD Division.
It was resolved that the Committeenoted the report
FP19/283 Estates / Capital Business Cases for approval prior to Board ratification
The Executive Director of Planning and Performance advised that the following business cases had been progressed via the newly introduced process agreed at a recent F&P Committee meeting.
FP19/283.1 Replacement of a CT scanner at Ysbyty Glan Clwyd business case
It was resolved that the Committeesupported the business case for the replacement of a CT scanner at Ysbyty Glan Clwyd.
FP19/283.2 Critical Care Business Case
The Committee were assured that the business case was supported via discretionary funding. In respect of a question raised by the Committee the Executive Director of Planning and Performance agreed to review the accuracy of a salary quoted within the business case.
It was resolved that the Committeesupported the business case
MW
Minutes F&P 4.12.19 Public session v.03 10
FP19/284 2019/20 Monthly monitoring report
It was resolved that the Committeenoted the report made to Welsh Government about the Health Board’s financial position for the seventh month of 2019-20
FP19/285 NHS Wales Shared Service Partnership Committee Summary Performance Report
It was resolved that the Committeenoted the report
FP19/286 Summary of inCommittee business to be reported in public
It was resolved that the Committeenoted the report
FP19/287 Issues of significance to inform the Chair's assurance report
To be agreed outside the meeting
FP19/288 Date of next meeting
19.12.19 3.30pm Optic Centre
(Post meeting amendment to time and venue)
Exclusion of the Press and PublicResolution to Exclude the Press and Public“That representatives of the press and other members of the public be excluded from the remainder of this meeting having regard to the confidential nature of the business to be transacted, publicity on which would be prejudicial to the public interest in accordance with Section 1(2) Public Bodies (Admission to Meetings) Act 1960.”
1 FP19.293b Summary Action Log v2.doc
1
BCUHB FINANCE & PERFORMANCE COMMITTEESummary Action Log – arising from meetings held in publicOfficer Minute Reference and Action
AgreedOriginal Timescale
Latest Update Position Revised Timescale
Actions from 22.8.19 meeting:Phillip Burns / Sue Hill
FP19/191 Financial Recovery Group (FRG) report Month 4 2019/20FP19/191.2 In relation to the exit transition from PWC and remaining capability within the organisation…re availability of senior programme managers… work being undertaken to address this issue within PMO and DMO. An update would be provided at the next meeting.
20.9.19 A BCU wide review of programme management capacity has been completed that suggests we may have a group of staff currently not aligned to the recovery programme. This group are now being assessed to establish what capacity could be released and re-aligned to the recovery programme, this process should be completed in the next two weeks. The size and structure of the PMO and Improvement Team is now better understood but there remains a high number of current vacancies and roles that are being supported by PWC. The vacancies are approved and awaiting final approval to advertise, if approved it will take approx 3-4 months before any additional capacity arrives.30.9.19 Agreed to keep action open.
16.10.19 A project plan is being drafted that will be submitted to the next FRG meeting on 29.10.19.
24.10.19 Circulate updated plan to members as discussed at FRG
27.11.19 The PMO has now transferred from an external PWC team to an experienced interim capability and the next stage will be substantive recruitment. Committed costs were presented to the FRG meetings in October and November and the capability and capacity required is under review and a proposal will be presented to FRG on 11th December and circulated to F & P members.
4.12.19 Discussion ensued on the third phase of the programme and recruitment to substantive posts. It was noted that the transition from Recovery resource to transformation was also subject to Executive discussion. It was agreed to provide a
21.11.19Outstanding
December Outstanding
11.12.19
2
programme cost update to F&P Committee 19.12.19
11.12.19 The Recovery Programme cost paper is on the in-committee agenda for December F&P and a paper on the proposed PMO and SI team structure will be reviewed by the Executive team in January and will be brought to the F&P Committee in February.
Feb 2020
Actions from 30.9.19 meeting:Adrian Thomas
FP19/215.3 Annual Plan Monitoring ReportProvide an update on the associated milestones for endoscopy and diagnostics sustainability to the next meeting, and assuring the Committee around the planning capability to deliver what is required
16.10.19
20.11.19
Endoscopy update is included on RTT paper on agenda
A diagnostics sustainability paper will be brought to F&P in November
24.10.19 The Chairman emphasised there was to be no slippage in presentation to the November meeting
19.11.19 AT updates:Radiology Milestone 2 (March 2020) in the Annual Plan Monitoring Report is - Develop capacity plan for future demand (equipment and staff). Kendall Bluck have been reviewing Radiology Services and their report is to be used to inform the proposal for sustainable radiology services in time for the Milestone date.Insourcing for CT, MR and Non Obstetric Ultrasound was been agreed for the Radiology Service until the end of December 2019 and is being provided by RMS. Insourcing will be required until March 2020 and additional funding for Radiology has been requested from Welsh Government.
26.11.19 North Wales Managed Clinical Services had their accountability meeting last week and confirmed that they have received feedback from Kendall Bluck and are awaiting the final report. It was agreed at the meeting that they will develop a sustainability plan for February.
3
4.12.19 The Chairman requested an update on Diagnostic services
Mags Barnaby>Mark Wilkinson
FP19/217.3.3 Referral to TreatmentEnsure eyecare business case is submitted to November F&P
20.11.19
Jan or Feb please advise
20.11.19 Business has been deferred from November agenda
20.11.19 Work to develop ophthalmology services continues with the £400k procurement of 11 field analysers to test peripheral vision. The Board is performing well in our work to risk stratify patients. Our next challenge – flagged with health economies at the recent accountability reviews – is to ensure that we now book on this basis. Some thought is being given as to whether a full and and complete business case is required or whether this may be more of a piece of service improvement work. There is currently no timescale therefore for a business case.
4.12.19 Agreed to provide presentation on Eye Care Services to future meeting
11.12.19 Performance team confirmed are working towards preparation of paper for January F&P meeting
15.1.20 or 19.2.20
Jan 2020
Mark Wilkinson
FP19/217.3.3 Referral to TreatmentEnsure urology and orthopaedics business cases are submitted to November Board
30.10.19 The Urology business case is dependent upon the national procurement of the urology robot and so the business case will not be ready for presentation at November Board. The Orthopaedics business case will go through the revised business case process and we will continue to keep the Board and WG informed on the recruitment of the 6 Orthopaedic consultants and the development of the programme business case.
25.11.19UROLOGY - Recent discussions with clinical teams have indicated there is no clear consensus on the preferred service model, and without this, it will not be possible to complete a business case although drafting work continues.
25.11.19 ORTHOPAEDICS - 5 out of the 6 new (Welsh
4
Government Part Year Effect funded ) consultants have been appointed. Demand and capacity plan is being revised in light of forecast end of year performance. Intention is to complete PBC for submission to December F&P and January HB (subject to Exec Team, F&P and HB meetings taking place as per current timetable)
11.12.19 Orthopaedics business case scheduled to be on December F&P agenda.
12.12.19 Revised planning paper for urology approved by the Committee on 4.12.19 set a new timescale for this business case to come to the March Finance & Performance Committee meeting. This will be built into the CoB.
Item to be closed
Item to be closed
Actions from 24.10.19 meeting:Sue Hill FP19/236 Finance Academy
Forecasting Best Practice GuideA plan to implement the guidance would be provided In December
December meeting (11.12.19)January meeting
Moved to January agenda due to short December meeting Jan 2020
Sue Hill FP19/238 Resource AllocationProvide to members when formula finalised
11.12.19 20.11.19 Update - The resource allocation has not been finalised 11.12.19 This should have been issued in time to be brought to F&P in January
Jan 2020
Sally Baxter > Mark Wilkinson
FP19/239 Annual plan progress monitoringProvide clarity on whether milestones are interim or final steps and include specific narrative when they are due
11.12.19 25.11.19 – narrative has always been included on red rated plan actions; feedback on completeness and levels of assurance on the narrative is always welcomed. Specific additional narrative on amber rated actions will be included starting with the November report to be presented to the December committee.12.12.19 Incorporated within APPMR
Item to be closed
Sally Baxter > Mark Wilkinson
FP19/239.3 Annual Plan progress monitoring:Provide more detailed narrative on all amber and red positions in order that the Committee could be
11.12.19 25.11.19 – narrative has always been included on red rated plan actions; feedback on completeness and levels of assurance on the narrative is always welcomed. Specific additional narrative on amber rated actions will be included starting with the November report to be presented to the December committee.
Item to be closed
5
appraised of how the actions were being brought back into alignment and included a sense of achievability. Estates, Digital and Care Closer to Home needed to be focussed on. The Committee also sought greater grip on priorities and the relationship on interdependencies.
12.12.19 Incorporated within APPMR
Sue Green FP19/240.1 IQPRProvide briefing on potential impact on sickness in respect of changes to unsocial hours payments
15.1.20 Briefing to be included within the F&P report for January 2020 and Q3 report. Working with colleagues nationally to work through calculation of impact
Deborah Carter
FP19/242.4 USC Share Delivery Unit report with
members
21.11.19 21.11.19 update The DU issued the draft report on 21 November, which is
currently in the process of being reviewed before the finalised version is published.
13.12.19 updateFeedback has been provided to the DU, a finalised version is
awaited.Actions from 4.12.19 meeting:Gary Doherty
FP19/270.5 Chief Executive undertook to feedback discussion to Deputy Chief Exec regarding addressing risks of: Overall financial sustainability of
the Health Board Reputational risk Overarching delivery of the
overall plan
December 12.12.19 The Chief Executive fed back the discussion to the Deputy Chief Exec as agreed.
Item to be closed
Gary Doherty
FP19/270.6 provide a briefing note to members to address:
12.12.19 Following discussion with the Deputy CEO in terms of how best to address the key issues raised it was felt that a conversation between the Deputy CEO and key committee
January
6
What is the ‘in year’ reporting plan
How this would fit for next year The robustness of plan Consideration of whether
planned care ‘Harm’ risks were adequately identified within the corporate register especially in areas of Urology and Endoscopy.
members was needed prior to sending round a proposed way forward. This will be actioned, and a note sent round prior to the January meeting.
Mark Wilkinson
FP19/271.2 3 yr outlook and annual plan updateReview if health records storage is addressed in respect of capital changes
12.12.19 Based on the assumption this action relates to the need for a health records storage solution to be developed in parallel although separate to the Ablett business case. The question arose as the timescale for the Ablett business case has changed. The health records business case is being developed in the parallel to the same timescale.
Item to be closed
David Fearnley
FP19/272.2 3 yr outlook and annual plan updateFollow up potential domiciliary care software in use within S Wales Health Board as interim solution ahead of WCCIS implementation.
12.12.19 The CIO is focussing the software opportunities with his colleagues from across Wales on 12 December and will report back to DIGC next time as part of the discussion around digital solutions for integrating community services. Executive Team are looking at the Canterbury model in more depth as part of clinical strategy work in January.
Item to be closed
Mark Wilkinson
FP19/272.2 IQPR - monthly performance trendsPresent longitudinal view (previous few months) on profile of targets and performance within report to be presented in January
15.1.20
Andrew Kent
FP19/272.3 IQPR -Respond to questions raised by HB Vice Chair
RTT paper provided for December meeting. If further specific questions, AK to advise.
Item to be closed
Mark Wilkinson
FP19/272.3 IQPR - External Contracts – Consider more
12.12.19 - A plan for the external activity based on outturn 2018/19 (prorata for the month reported) so as to show activity v plan has
Item to be closed
7
effective presentational format to demonstrate activity
been added. Further feedback on any aspect of this report is always welcome.
Andrew Kent
FP19/272.4 IQPR – RTT Activity v PlanEnsure access to IQPR data going forward to ensure correlation in preparation of RTT paper
Access to IQPR data going forward will be incorporated Item to be closed
Andrew Kent
FP19/272.4 IQPR – Process ControlInclude further context highlighted by Andrew Sallows to ensure reporting addresses WG requirements and concerns within report to be presented at January meeting.
15.1.20
Andrew Sallows
FP19/272.4 IQPR – RTTShare effective RTT reports by other Health Boards with members and AK before January meeting
15.1.20
Andrew Kent
FP19/273.5 RTTEnsure report to January meeting addresses:Demand and Capacity – resources, waiting list additions and improved understanding re HMRC implications
15.1.20
Andrew Kent / Andrew Sallows/ Sue Hill/Emma Wilkins
FP19/273.8 RTTArrange discussion on Clarification on definitive RTT
number Investment – per key decision
slide Diary / Timeline confirmation re
5.12.19
8
financial planning before the 5.12.19 Board workshop meeting
Clinical risk and cost issues(Risk v Finance Performance v Deficit)
Provide clarity on what will be delivered (activity forecast) based on £13.8m as committed by WG.
Philip Burns
FP19/279.2 FRGEnsure investment requirement is included within key decisions
5.12.19 The Interim Recovery Director requested to be included in all projects and programmes to ensure the right support and/or resource is allocated or considered to ensure delivery of any outcomes and outputs.
Any financials will be net of any investment.
Item to be closed
Mark Wilkinson
FP19/283.2 PACU Business CaseCheck salary for Band 8c Psychologist quoted within business case
19.12.19 12.12.19 Finance colleagues confirm that the table within the paper should read 0.60 WTE Clinical Psychologist rather than 1.0 WTE. The figure of £55,939 is correct.
Item to be closed
17.12.19
4 FP19/294 Finance Report Month 8
1 FP19.294 Finance report Month 8.docx
1
Cyfarfod a dyddiad: Meeting and date:
Finance and Performance Committee19.12.19
Cyhoeddus neu Breifat:Public or Private:
Public
Teitl yr Adroddiad Report Title:
Finance Report Month 8 2019/20
Cyfarwyddwr Cyfrifol:Responsible Director:
Sue Hill, Acting Executive Director of Finance
Awdur yr AdroddiadReport Author:
Sue Hill, Acting Executive Director of Finance
Craffu blaenorol:Prior Scrutiny:
Acting Executive Director of Finance
Atodiadau Appendices:
Appendix 1: Summary of Financial Performance Appendix 2: ForecastAppendix 3: SavingsAppendix 4: ExpenditureAppendix 5: Balance SheetAppendix 6: Financial Risks and OpportunitiesAppendix 7: Response to Month 7 Questions
Argymhelliad / Recommendation:It is asked that the report is noted, with particular reference to the forecast deficit of £35m and the specific actions in progress to achieve plan.Please tick one as appropriate (note the Chair of the meeting will review and may determine the document should be viewed under a different category)Ar gyferpenderfyniad /cymeradwyaethFor Decision/Approval
Ar gyfer TrafodaethFor Discussion
Ar gyfer sicrwyddFor Assurance
Er gwybodaethFor Information
Sefyllfa / Situation:The purpose of this report is to provide a briefing on the financial performance of the Health Board as at November 2019, and on actions being taken to manage the financial challenge and mitigate risk.Cefndir / Background:The Health Board developed a draft 2019/20 annual deficit plan of £35m. The Financial Recovery programme is supporting delivery of a significant improvement, in line with the £25m control total, and requiring delivery of a further £10m of savings. Welsh Government reporting continues to reflect the initial plan deficit of £35m, in line with their requirements.
Asesiad / Assessment:1.0 Strategy ImplicationsThis paper aligns to the strategic goal of attaining financial balance and is linked to the well-being objective of targeting our resources to those with the greatest need.
2
2.0 Financial Implications2.1 Summary
Original Plan
£2.9m Deficit Original Plan
£23.3m Deficit
Original Plan
£35.0m Deficit
Control Total
£1.6m Deficit Control Total
£18.3m Deficit
Control Total
£25.0m Deficit
Actual £3.2m Deficit Actual £27.1m Deficit
Forecast £35.0m Deficit
Plan Variance
£0.3m Adverse
Plan Variance
£3.8m Adverse
Plan Variance
Nil
Control Variance
£1.6m Adverse
Control Variance
£8.8m Adverse
Control Variance
£10.0m Deficit
Achievement Against Key Targets
Revenue Resource Limit Public Sector Payment Policy (PSPP)
Savings & Recovery Plans Revenue Cash Balance Capital Resource Limit Medium Term Plan
2.2 Overview
In month: The Health Board delivered a £3.2m deficit, £0.3m over the original plan. Following three months of consecutive improvement in performance, there has been a deterioration this month. The in-month position is £1.6m in excess of the control total plan.
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
£m
Financial Performance and Forecast 2019/20
Plan - £35m Stretch Plan - £25m Actual Forecast
Current Month Year to Date Full Year Forecast
3
Month 7 saw a considerable under spend against the WHSCC contract, which has not been replicated this month. In addition, costs for Prescribing continue to increase and savings have not delivered to plan. In total, the position has deteriorated from the Month 7 position by £0.5m.
Year to date: The Health Board is overspent by £27.1m, £8.8m higher than control total plan and £3.8m over the original plan. The key over spending division is Secondary Care, where the non-delivery of savings, agency premium pay costs and other cost pressures are the main causes of the over spend. Further details are included in Appendix 1.
Forecast: The Health Board’s forecast deficit of £35m is in line with the initial plan but behind the £25m control total plan. The actual position for Month 8 was £0.7m worse than the Month 7 forecast position for November. Despite the downturn in performance in Month 8, the savings pipeline continues to hold a number of schemes that are forecast to deliver in the final quarter of the year. On the basis of the conversion and delivery of these schemes, the £35m forecast deficit is considered achievable. Further details are included in Appendix 2.
Savings: Savings achieved to date are £13.6m against a year to date plan of £20.6m giving a shortfall of £7m. Additional cost avoidance and efficiency savings of £6.1m have been delivered to date, which offset some cost pressures arising in-year. The original planned deficit is only achievable if the Health Board can convert and deliver 51% of the red schemes, continue to deliver green and amber schemes to planned values, and contain or offset emerging cost pressures. In addition, mitigating savings totalling £1.8m need to be identified to offset the impact of the Health Board’s share of the Welsh Risk Pool risk share contribution. Further details are included in Appendix 3.
2.3 Income and Expenditure
Income: Most of the Health Board’s funding is Welsh Government allocation through the Revenue Resource Limit (RRL). Confirmed allocations to date total £1,520m, with further anticipated allocations in year of £54m, a total forecast of £1,574m for the year.
Pay expenditure: Pay costs were inflated in Month 7 for the Medical and Dental pay award and have now returned to just below the average for the year at £62.1m. Expenditure on agency staff for Month 8 is £3.1m a fall of £0.5m on October. There have also been decreases in locum costs of £0.2m and other non-core costs (e.g. cover colleague) of £0.2m. Health Board pay costs are £1.5m under spent for the year to date, reflecting the significant number of vacancies being held.
Non- pay expenditure: Costs are above the average for the year at £78.8m in the month, with a year to date over spend of £13.7m. Of this, £5m relates to the stretch target. The key area of pressure is Prescribing; analysis of the impact of National Prices is estimated at £2.2m, with a forecast pressure of £3.5m for the full year. In addition, forecasting methodologies indicate that there is a potential risk of up to £3m over the remaining months of 2019/20. In addition to this, Secondary Care drugs continue to over spend, whilst there remains a number of savings targets that have not been allocated to cost areas by the divisions.
4
RTT: The Health Board has received RTT funding of £13.5m for the full year, of which £9.0m has been spent to date. Welsh Government have confirmed that there is no additional RTT funding available for 2019/20 although discussions do still continue. The Health Board has fully committed the remaining £4.5m of funding and is currently assessing the impact and risk on the achievement of treatment targets.
Further details on expenditure are included in Appendix 4.
2.4 Balance Sheet
Cash: The Health Board has formally requested £31m Strategic Cash Support from Welsh Government to ensure that essential payments can continue through to March 2020. This is lower than the forecast deficit for the year as the Health Board is currently forecasting that £4m of cash pressures will be managed internally by undertaking a range of cash management actions.
Capital: The Capital Resource Limit (CRL) at Month 8 is £20.0m. Year to date expenditure is £7.5m against a plan of £8.5m. The year to date slippage will be recovered throughout the remainder of the year. Further details are included in the Capital Programme report
A summary of the balance sheet is included in Appendix 5.
3.0 Risk Analysis
There are six risks to the financial position totalling £8.8m. These are detailed in Appendix 6. Offsetting these, there are is one opportunity totalling £10m relating to delivery of stretch target savings.
4.0 Legal And ComplianceNot applicable.
5.0 Impact AssessmentNot applicable.
Appendix 1 – Summary of Financial Performance
5
An overall month by month summary of the financial position is shown below, followed by a table showing the split by division.
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL BUDGET ACTUAL VARIANCE
£m £m £m £m £m £m £m £m £m £mRevenue Resource Limit (124.9) (123.2) (124.1) (129.3) (124.7) (125.5) (130.5) (126.7) (1,008.9) (1,008.9) 0.0Miscellaneous Income (10.6) (11.9) (11.1) (11.1) (12.1) (11.3) (11.5) (11.0) (87.2) (90.6) (3.4)Health Board Pay Expenditure 64.6 61.9 62.0 62.3 62.2 62.1 64.7 62.1 503.4 501.9 (1.5)Non-Pay Expenditure 74.8 76.9 76.6 81.8 78.2 77.6 80.0 78.8 611.0 624.7 13.7
Total Against Stretch Plan 3.9 3.7 3.4 3.7 3.6 2.9 2.7 3.2 18.3 27.1 8.8Stretch Target Offset 5.0 0.0 (5.0)
Total Against Original Plan 23.3 27.1 3.8
CUMULATIVE
Appendix 1 – Summary of Financial Performance
6
Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 CUMULATIVE ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL ACTUAL BUDGET ACTUAL VARIANCE
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000WG RESOURCE ALLOCATION (124,954) (123,186) (124,111) (129,295) (124,695) (125,453) (130,519) (126,714) (1,008,926) (1,008,926) 0AREA TEAMS West Area 13,278 12,998 13,066 14,339 13,470 13,505 14,215 13,777 108,510 108,735 225 Central Area 17,294 17,075 17,051 18,030 17,448 17,475 18,178 18,092 140,166 140,738 572 East Area 19,050 18,928 18,905 20,129 19,420 19,251 20,216 20,062 155,312 156,222 911 Other North Wales 834 1,072 1,206 864 1,224 997 693 758 6,423 6,246 (177) Commissioner Contracts 16,206 16,191 16,647 18,154 19,319 16,881 16,530 17,217 138,735 137,144 (1,591) Provider Income (1,601) (1,768) (1,859) (2,268) (2,154) (2,170) (1,528) (1,626) (13,853) (14,974) (1,121)Total Area Teams 65,062 64,496 65,017 69,248 68,727 65,938 68,304 68,280 535,293 534,111 (1,182)SECONDARY CARE Ysbyty Gwynedd 8,712 8,444 8,392 8,371 8,158 8,031 8,643 8,185 65,868 66,936 1,068 Ysbyty Glan Clwyd 10,392 10,281 10,259 10,469 10,285 10,258 10,971 10,284 78,918 83,199 4,281 Ysbyty Maelor Wrexham 8,908 8,700 8,530 8,773 8,650 8,702 9,080 8,676 68,694 70,020 1,326 North Wales Hospital Services 8,994 8,647 8,584 9,429 6,647 8,517 8,510 8,573 67,154 67,901 747 Womens 3,370 3,282 3,066 3,258 3,294 3,365 3,342 3,278 26,004 26,255 251Total Secondary Care 40,375 39,354 38,831 40,301 37,034 38,873 40,546 38,997 306,638 314,311 7,673Total Mental Health & LDS 10,682 10,156 10,145 10,088 10,268 10,969 10,892 10,283 83,714 84,439 724CORPORATEChief Executive 162 211 175 172 179 165 183 193 1,444 1,445 0Estates & Facilities 4,445 4,216 4,119 4,161 3,967 4,029 4,203 4,140 33,074 33,280 205Utilities & Rates 1,337 1,376 1,337 1,347 1,338 1,388 1,344 1,450 10,378 10,917 539Executive Director of Finance 845 825 806 853 633 571 1,427 (956) 4,959 5,005 46Executive Director of Nursing & Midwifery 835 1,021 935 1,029 944 946 891 922 7,127 7,520 393Executive Medical Director 1,463 1,433 1,461 1,582 1,599 1,619 1,654 1,622 12,597 12,434 (163)Executive Director of Workforce & OD 963 962 951 947 955 896 1,091 891 7,385 7,656 272Director of Planning & Performance 178 157 169 170 160 128 201 251 1,602 1,415 (187)Executive Director of Public Health 80 110 82 129 98 98 110 102 665 809 144Director of Corporate Services 0 0 0 0 0 0 0 0 (212) 0 212Office to the Board 202 195 127 179 185 152 190 188 1,398 1,417 19Director of Therapies 34 31 31 31 29 28 26 25 289 235 (54)Executive Director of Primary Care & Comm Services 75 75 92 68 55 64 64 77 681 570 (110)Director of Turnaround 90 135 112 148 224 87 255 990 2,164 2,041 (123)Total Corporate 10,709 10,747 10,397 10,816 10,366 10,171 11,639 9,895 83,551 84,744 1,193Total Other Budgets incl. Reserves 1,951 2,149 3,135 2,523 1,866 2,459 1,878 2,483 18,062 18,445 382TOTAL - STRETCH PLAN (£25.0m) 3,825 3,716 3,414 3,681 3,566 2,957 2,740 3,224 18,333 27,123 8,790
Stretch Target Offset 5,000 0 (5,000)TOTAL - ORIGINAL PLAN (£35.0m) 23,333 27,123 3,790
MAIN COST PRESSURESPrimary Care drugs 2,760Secondary Care drugs 2,126Unallocated savings - original target plus brought forward 3,852Unallocated savings - stretch target 5,000
Appendix 2 – Forecast
7
Scenarios
The Health Board’s current Monitoring Return forecast is shown below, alongside two forecast scenarios which are based on performance to date. This confirms the scale of the challenge.
Delivery of forward trajectories and full-year plan is critically dependent on an immediate step change in pace of savings delivery over the remainder of the year. The £35m deficit position will only be realised if savings delivery is at the level currently forecast by the PMO.
Divisional
Forecasts for the year submitted by the divisions are shown below. The majority of divisions continue to forecast over-spends for the year, outside the budgetary limits set by the Board and therefore beyond their authority.
Description Month 9 Month 10 Month 11 Month 12
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'00023,976 2,515 26,491 2,294 2,085 2,081 2,049 35,000
23,899 3,224 27,123 3,390 3,390 3,390 3,390 40,68323,899 3,224 27,123 3,224 3,224 3,224 3,224 40,01923,899 3,224 27,123 2,213 1,973 1,907 1,784 35,000
Forecast 2019/20
Updated for M8Year to date extrapolationMonth 8 in-month extrapolationCurrent forecast
M7 Forecast
Month 7 Year to
Date
Forecast/ Actual
Month 7
Month 7 Year to
Date
Forecast
Appendix 2 – Forecast
8
Full Year Full Year Change InMonth 7 Forecast Month 8 Forecast Forecast
Annual Year to Date Variance Year to Date Variance Variance StretchBudget Variance Over Budget Variance Over Budget From Month 7 Target
at Month 7 at Month 8 to Month 8£000 £000 £000 £000 £000 £000 £000
WG RESOURCE ALLOCATION (1,573,137) 0 0 0 0 0 0AREA TEAMS West Area 163,101 201 1,300 225 1,300 0 (731) Central Area 209,422 390 1,199 572 1,221 22 (1,221) East Area 233,890 749 2,100 910 2,100 0 (849) Other North Wales 9,712 (83) (190) (177) (191) (1) 129 Commissioner Contracts 206,913 (1,324) (843) (1,591) (1,934) (1,091) (7) Provider Income (19,180) (993) (1,093) (1,121) (1,250) (157) 0 Area Wide 0Total Area Teams 803,858 (1,060) 2,473 (1,182) 1,246 (1,227) (2,679)SECONDARY CARE Ysbyty Gwynedd 96,223 1,027 1,304 1,068 1,261 (43) (505) Ysbyty Glan Clwyd 116,740 3,664 6,114 4,281 6,108 (6) (606) Ysbyty Maelor Wrexham 101,777 1,137 2,000 1,326 2,000 0 (517) North Wales Hospital Services 99,238 601 1,547 747 1,547 0 (1,403) Womens 38,879 183 395 251 395 0 (220)Total Secondary Care 452,857 6,612 11,360 7,673 11,311 (49) (3,251)Total Mental Health & LDS 126,239 847 1,527 724 1,430 (97) (2,627)Total Corporate 124,851 732 2,457 1,193 4,261 1,804 (1,443)Other Budgets (Reserves) 90,332 102 494 382 1,049 555 0Welsh Risk Pool risk share contribution 0 0 0 0 1,817 1,817 0
Mitigating actions to reduce forecasts (West & YGC) (1,854) (1,194) 660Pan BCU Green and Amber schemes (3,748) (3,748)Welsh Risk Pool mitigation (1,817) (1,817)Red Risk Schemes (6,457) (4,355) 2,102
TOTAL - STRETCH PLAN (£25.0m) 25,000 7,233 10,000 8,790 10,000 0 (10,000)Stretch Target Offset 10,000 (3,750) (10,000) (5,000) (10,000) 10,000
TOTAL - ORIGINAL PLAN (£35.0m) 35,000 3,483 0 3,790 0 0 0
Appendix 2 – Forecast
9
Two divisions (West Area and YGC) have an action still outstanding to reduce forecasts back in line with the Month 6 forecast (£0.88m and £5.34m respectively). The total reduction required across the two divisions is £1.194m.
One division (Corporate) has incurred additional costs in Month 8, which they have highlighted as cost pressures and requested to increase their forecast deficit for a second month. The Corporate forecast will be reviewed and a reduction in run-rate required through delivery of red schemes and escalated daily recovery actions.
The Welsh Risk Pool pressure, relating to the Health Board’s share of NWSSP’s forecast over spend, requires mitigating actions to cover the cost. The Welsh Risk Pool cost is included in the forecast outturn, but there are no costs in the Month 8 position. This is a very high risk for the Health Board as inability to identify mitigations could impact on the forecast.
Pan BCU green and amber schemes are those savings schemes that are being driven by Improvement Groups and are not yet identified in divisions. Full delivery of all schemes up to their planned value is required to meet the £35m forecast outturn.
In addition, £4.4m of red risk schemes are required, equating to 51% of red schemes in the pipeline. To achieve this, there will need to be an escalation of immediate actions to reduce the run rate.
Divisions that have maintained their Month 7 forecast have done so by covering cost pressures with one-off benefits.
The divisional forecasts above have been mapped against the estimated impact of red savings schemes to give an indicative monthly forecast. This is shown below. It is noted that:
The phasing of divisional forecasts will be further challenged and updated over the next month The red risk schemes forecast is based on 51% delivery of all schemes in the pipeline. Full delivery of all planned green and amber
schemes is also required. Many savings schemes are multi-divisional or pan-Health Board (e.g. Workforce Optimisation and Procurement). The allocation of
schemes across divisions and expenditure categories will be finalised as the schemes are specified and move to delivery.
Appendix 2 – Forecast
10
Month 8
Year Forecast Indicative Forecast Indicative Forecast Indicative Forecast Indicative Forecast Indicative
to Date Actual Additional Actual Actual Additional Actual Actual Additional Actual Actual Additional Actual Actual Additional Actual
Actual Forecast Savings Forecast Forecast Savings Forecast Forecast Savings Forecast Forecast Savings Forecast Forecast Savings Forecast
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000 £000
WG RESOURCE ALLOCATION (1,008,927) (129,246) 0 (129,246) (130,918) 0 (130,918) (128,706) 0 (128,706) (176,876) 0 (176,876) (1,574,673) 0 (1,574,673)
AREA TEAMS
West Area 108,735 13,878 (23) 13,855 14,266 (132) 14,134 13,916 (132) 13,784 13,878 (132) 13,746 164,673 (420) 164,253
Central Area 140,737 17,698 0 17,698 18,098 0 18,098 17,397 0 17,397 17,322 0 17,322 211,252 0 211,252
East Area 156,223 19,599 0 19,599 20,471 0 20,471 19,981 0 19,981 20,191 0 20,191 236,465 0 236,465
Other North Wales 6,245 754 0 754 753 0 753 753 0 753 754 0 754 9,259 0 9,259
Commissioner Contracts 137,143 17,102 0 17,102 17,099 0 17,099 17,001 0 17,001 16,955 0 16,955 205,300 0 205,300
Provider Income (14,974) (1,506) 0 (1,506) (1,304) 0 (1,304) (1,304) 0 (1,304) (1,342) 0 (1,342) (20,430) 0 (20,430)
Total Area Teams 534,109 67,525 (23) 67,502 69,383 (132) 69,251 67,744 (132) 67,612 67,758 (132) 67,626 806,519 (420) 806,099
SECONDARY CARE
Ysbyty Gwynedd 66,935 7,673 0 7,673 7,711 0 7,711 7,671 0 7,671 7,981 0 7,981 97,971 0 97,971
Ysbyty Glan Clwyd 83,199 9,922 (43) 9,879 9,941 (244) 9,697 9,932 (244) 9,688 10,049 (244) 9,805 123,043 (774) 122,269
Ysbyty Maelor Wrexham 70,019 8,513 0 8,513 8,564 0 8,564 8,422 0 8,422 8,466 0 8,466 103,984 0 103,984
North Wales Hospital Services 67,901 8,131 0 8,131 8,426 0 8,426 8,239 0 8,239 8,520 0 8,520 101,217 0 101,217
Womens 26,256 3,274 0 3,274 3,258 0 3,258 3,247 0 3,247 3,239 0 3,239 39,274 0 39,274
Total Secondary Care 314,310 37,513 (43) 37,470 37,900 (244) 37,656 37,511 (244) 37,267 38,255 (244) 38,011 465,489 (774) 464,715
Total Mental Health & LDS 84,438 10,664 0 10,664 11,241 0 11,241 10,542 0 10,542 10,784 0 10,784 127,669 0 127,669
Total Corporate 84,744 10,864 0 10,864 10,880 0 10,880 10,881 0 10,881 10,901 0 10,901 128,270 0 128,270
Other Budgets (incl. Capital Charges) 18,448 5,407 0 5,407 6,415 0 6,415 6,863 0 6,863 53,890 0 53,890 91,023 0 91,023
Welsh Risk Pool risk share contribution 0 0 0 0 0 0 0 0 0 0 1,817 (1,817) 0 1,817 (1,817) 0
Multi Divisional Schemes 0 0 (448) (448) 0 (2,552) (2,552) 0 (2,552) (2,552) 0 (2,552) (2,552) 0 (8,103) (8,103)
TOTAL 27,122 2,727 (514) 2,213 4,901 (2,928) 1,973 4,835 (2,928) 1,907 6,529 (4,745) 1,784 46,114 (11,114) 35,000
Variance over £35m 11,114 0
Variance over £25m 21,114 10,000
CUMULATIVEMONTH 9 MONTH 10 MONTH 11 MONTH 12
Appendix 3 – Savings
11
Savings Plan and Forecast
The savings programme is based on the planned delivery of schemes. The value of green and amber schemes has risen by £2.9m from £33.7m in Month 7 to £36.6m in Month 8. The overall value of the programme has however reduced by £1.7m in month, reflecting reductions as a result of a re-assessment by the Financial Recovery Group of the likely delivery of pipeline schemes for Continuing Healthcare and outpatients, offset by the introduction of additional Procurement savings and Divisional recovery schemes.
The original planned deficit is achievable if the Health Board can convert and deliver 51% of the red schemes, plus deliver green and amber schemes at their planned values, and contain or offset emerging cost pressures. In addition, mitigating savings totalling £1.8m need to be identified to offset the impact of the Health Board’s share of the Welsh Risk Pool risk share contribution.
It should be noted that there is a gap between the planned savings as recorded above and the forecast delivery of savings. Where forecast of schemes has slipped from the plan, work needs to be done to increase delivery or identify additional schemes to make up the shortfall.
Month 8 PositionRed Amber Green Total£m £m £m £m
Cash Releasing 1.693 0.434 21.269 23.396
Cost Avoidance 6.584 0.136 14.055 20.775
Efficiency 0.250 0.005 0.712 0.967
Total 8.527 0.575 36.036 45.138
Amber Green Total£m £m £m
Planned savings 0.575 36.036 36.611
Actual/forecast savings 0.401 32.439 32.840
Forecast under delivery against plan 0.174 3.597 3.771
Appendix 3 – Savings
12
Savings Actions
The Recovery Programme continues to drive the identification and delivery of savings, alongside reduction in expenditure run rates. Key areas of focus are: In Month 7 the first tranche of Improvement Group schemes progressed from red to amber (including procurement savings £1.53m
and workforce savings £1.03m). Effective delivery of schemes developed by Improvement Groups needs to be demonstrated from Month 9. It is vital that
Improvement Groups, with the support of the PMO, take the Divisions with them through the necessary rapid pace of change to secure delivery of these savings.
Individual divisions have also continued to progress local schemes in response to the focus on these issues within the Divisional Recovery Meetings.
The main areas of slippage on savings schemes at Month 8 are Medical rostering / agency and divisional savings.
Focus is on the conversion of red schemes into green and amber and driving delivery in the rest of the programme. The main areas targeted for converting further savings opportunities from pipeline are: Workforce, Continuing Healthcare, Medicines Management, and Procurement.
Underlying Position
A key risk to the Health Board is its underlying deficit. The deficit brought forward from 2018/19 was £55.1m. The underlying position carried forward into 2020/21 is showing a significant reduction but is dependent on sufficient recurring savings opportunities being generated to positively impact on next year’s position.
Appendix 4 – Expenditure
13
Pay Expenditure
£50M
£52M
£54M
£56M
£58M
£60M
£62M
£64M
£66M
£68M
£70M
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
£M
Total Pay
Substantive Agency BankLocum Other Non Core OvertimeAdditional Hours WLI's Average Total Pay
Appendix 4 – Expenditure
14
11.1% (£7.1m) of total in-month pay (11.8% / £60.9m year to date) related to variable pay; agency, bank, overtime, locum, WLI, other non-core and additional hours, £0.8m less than in October. This decrease is due to falls in agency costs (£0.5m), locums (£0.2m) and other non-core costs (£0.2m). Total expenditure on locum staff for Month 8 is £0.6m.
Expenditure on agency staff for Month 8 is £3.1m, representing 4.8% of total pay, and £0.4m lower than last month. Medical agency costs have decreased by £0.3m to an in-month spend of £1.3m. The decrease is across all areas except for Wrexham Maelor where additional agency usage has been required for ED and Anaesthetics. Nurse agency costs totalled £1.1m for the month, a decrease of £0.1m from last month. The reduction is costs is due to a decrease in the number of escalation beds at Wrexham. Vacancies and increasing sickness absence rates remain the root cause of the majority of agency spend.
YTD RTT
Month 1 2019/120
Month 2 2019/120
Month 3 2019/120
Month 4 2019/120
Month 5 2019/120
Month 6 2019/120
Month 7 2019/120
Month 8 2019/120
YTD Budget
YTD Actual
YTD Variance
Costs Included
in Actuals£m £m £m £m £m £m £m £m £m £m £m £m
Administrative & Clerical 8.4 8.1 8.1 8.0 8.1 8.1 8.2 8.2 69.7 65.2 (4.5) 0.1Medical & Dental 14.3 14.0 14.3 14.7 14.7 14.4 16.9 14.5 112.7 117.8 5.1 1.9Nursing & Midwifery Registered 21.3 20.1 20.1 20.2 19.7 20.0 19.9 19.9 168.9 161.2 (7.7) 0.4Additional Clinical Services 10.0 9.2 9.3 9.3 9.0 9.2 9.0 8.9 68.3 73.9 5.6 0.1Add Prof Scientific & Technical 2.5 2.6 2.3 2.4 2.8 2.6 2.7 2.8 21.8 20.7 (1.1) 0.0Allied Health Professionals 3.7 3.7 3.7 3.7 3.7 3.7 3.8 3.7 29.7 29.7 0.0 0.4Healthcare Scientists 1.2 1.2 1.1 1.1 1.1 1.1 1.2 1.1 8.9 9.1 0.2 0.0Estates & Ancillary 3.2 3.0 3.1 2.9 3.1 3.0 3.0 3.0 25.0 24.3 (0.7) 0.1Savings to be allocated (1.6) 1.6Health Board Total 64.6 61.9 62.0 62.3 62.2 62.1 64.7 62.1 503.4 501.9 (1.5) 3.0
Primary care 1.9 1.8 2.0 1.9 2.0 1.8 1.9 1.9 13.3 15.2 1.9 0.0
Total Pay 66.5 63.7 64.0 64.2 64.2 63.9 66.6 64.0 516.7 517.1 0.4 3.0
CumulativeActuals
Appendix 4 – Expenditure
15
15800
16000
16200
16400
16600
16800
17000
17200
17400
17600
£50M
£52M
£54M
£56M
£58M
£60M
£62M
£64M
£66M
£68M
£M
Futher Pay Analysis
Core Pay Agency Bank Locum Other Medical Pay WLIs
Overtime Additional Basic Pay Pay Budget Budgeted WTE Actual WTE
WTE
Appendix 4 – Expenditure
16
£.0 M
£.5 M
£1.0 M
£1.5 M
£2.0 M
£2.5 M
£3.0 M
£3.5 M
£4.0 M
Agency Spend
Ysbyty Glan Clwyd Ysbyty Maelor Wrexham Other Mental Health & LDS
Ysbyty Gwynedd East Area Central Area West Area
Medical Agency Agency Nursing Other Agency
Appendix 4 – Expenditure
17
The Workforce Optimisation Portfolio is the overarching mechanism to ensure successful delivery of the Health Board’s workforce initiatives. Recent actions:
Medical rostering / job planning / recruitment - external expert’s recommendations have begun to be enacted. External recruitment consultants are sourcing substantive Medical staff. Medical Staff bank is predicted to save over £270,000 this financial year.
Establishment Control process including Vacancy Authorisation Panel (VAP) / Workforce Authorisation Panel (WAP) continues to give scrutiny of any increased substantive wage spend. For non-core spend the focus remains on filling substantive vacancies, reducing sickness absence and increasing pools of internal temporary staff, particularly in nursing, medical and dental and admin.
The Health Board’s overall sickness absence rate has reduced to 5.22% (5.29% in Month 7). Percentage of Long Term sickness continues to fall. Focus on priority areas and changes to enhanced pay will reduce short term frequent sickness absence and medium sickness rates in a similar way to the continued reduction in long term absence.
Successful recruitment of newly qualified staff and experienced staff from other providers has seen nursing vacancy rates fall for three consecutive month. Medical vacancies have increased to 11.1% from 9.4%. A Medical Recruitment Panel has been introduced to give focus on quickly filling vacancies, reducing the vacancy rate and associated agency spend.
There has been a focus on increasing the capacity of internal temporary staffing: Nursing - actions include auto enrolment of new substantive staff and revised pay rates. These rates are promoted to both
encourage existing bank staff to do more shifts and to attract agency staff to bank. Medical - further efforts to move temporary staffing spend from agency to cheaper alternatives via the Medical Staff Bank
went live on 11th November. Admin – The A&C staff bank continues grow and is on target to have all temporary staffing via bank by March.
Appendix 4 – Expenditure
18
Non-Pay Expenditure
66
71
76
81
86
91
96
Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
£m
Non-Pay Expenditure
Actual £m Average Non-Pay
Month 1 2019/120
Month 2 2019/120
Month 3 2019/120
Month 4 2019/120
Month 5 2019/120
Month 6 2019/120
Month 7 2019/120
Month 8 2019/120
YTD Budget
YTD Actual
YTD Variance
£m £m £m £m £m £m £m £m £m £m £mPrimary Care 16.7 17.0 17.3 16.9 17.4 17.3 18.6 18.1 140.9 139.3 (1.6)Primary Care Drugs 8.2 8.2 8.2 8.2 8.6 8.7 8.8 8.3 64.4 67.2 2.8Secondary Care Drugs 5.9 6.0 5.6 6.3 5.8 5.9 6.0 6.1 45.5 47.6 2.1Clinical Supplies 5.3 5.6 5.5 5.9 5.6 5.6 5.7 5.6 44.6 44.8 0.2General Supplies 1.8 2.3 1.3 5.3 2.6 3.3 2.8 2.5 21.1 21.9 0.8Healthcare Services Provided by Other NHS Bodies 21.1 21.0 21.5 23.1 22.2 21.5 20.6 21.8 175.2 172.8 (2.4)Continuing Care and Funded Nursing Care 8.3 8.3 8.1 8.0 8.2 8.0 7.9 8.0 64.2 64.8 0.6Other 5.1 5.9 5.6 5.2 5.0 4.5 7.1 5.6 32.8 44.0 11.2Capital 2.4 2.6 3.5 2.9 2.8 2.8 2.5 2.8 22.3 22.3 0.0
Total 74.8 76.9 76.6 81.8 78.2 77.6 80.0 78.8 611.0 624.7 13.7
CumulativeActuals
Appendix 4 – Expenditure
19
Primary Care: The Health Board continues to see cost pressures within Managed Practices particularly in relation to locum GP costs and more recently an increase in the dispensing cost of drugs. Month 7 actual costs were inflated by £1.0m due to the GDS and GMS uplifts, which were fully funded. However cost pressures in GMS have meant that expenditure remains higher than the average.
Primary Care drugs: This remains one of the Health Board’s key risks. The latest data available (September 2019) shows an increase in Prescribing costs for the Health Board of £2.4m (4.5%) in the rolling 12 month period. Whilst there is a 1.5% increase in the number of items prescribed (1.6% nationally), this only equates to an increased cost of £0.8m. The remaining £1.6m is due to price changes (typically Category M drugs or No Cheaper Stock Obtainable (NCSO)). The impact of National Prices for the Health Board up to Month 8 is therefore estimated at £2.2m, with a forecast of at least £3.5m for the year. For 2019/20 the forecasting methodologies are now indicating a range of outturns for the Health Board from £113m to £115.2m. With the continued price increases in NCSO and Category M, the outturn could increase to £116m. Should the October data indicate a further increase in the Forecasting Methodologies, then then Health Board will need to increase the current £113m forecast and therefore consider and identify mitigating actions in order to avoid increasing the overall Health Board Forecast.
Secondary Care drugs: Costs have risen by £0.1m from October and are just above the run rate for the year. This primarily relates to an increase in Cancer drugs. However, spend across most Divisions continues to outstrip budgets,
Healthcare Services provided by Other NHS Bodies: The WHSCC contract performed well in Month 7 as slippage on development funds was been released. Costs in Month 8 have returned to the average for the year.
Other non-pay expenditure: Unallocated and non-delivering savings schemes are contributing £8.9m to the over spend. These savings targets have all been
apportioned to divisions, but the divisions have not allocated them to specific cost areas. This total includes savings from the 2019/20 original £25m target and savings targets brought forward from prior years that did not have recurrent schemes attached to them (total of £3.9m) plus the year to date share of the £10m additional savings for which schemes have not yet been confirmed (£5m).
In addition the ‘Other’ category includes year to date over spends on IT costs (£0.9m) and travel (£0.8m), predominantly Non-Emergency Patient Transport Service (NEPTS).
Actual costs have fallen in month as Month 7 included the £1.0m cost for the support provided by PwC to the PMO, which has not been replicated in Month 8.
Appendix 4 – Expenditure
20
RTT
YG YGC YWM OtherSupport Services Outsource Total
£000 £000 £000 £000 £000 £000 £000Pay Costs 1,210 1,022 199 132 497 - 3,061Theatre Non Pay 221 184 108 513Other Non Pay 559 643 60 57 1,266 2,585Outsourced Activity 1,154 1,154Insourcing 999 379 300 1,678Total Expenditure 2,990 2,228 667 189 1,763 1,154 8,991Cardiology - 14 14Gastro / Endoscopy 1,497 648 337 2,482Ophthalmology 71 - 71Radiology - 1,763 1,763Urology 40 40Sub Total 1,568 648 391 - 1,763 - 4,370Anaesthetics 7 1 18 26ENT 36 169 - 205General Surgery 167 182 2 4 354Gen Med 2 2Max Fax 96 - 2 98Oral 52 52Ophthalmology 221 276 69 21 587Orthopaedics 827 636 178 114 796 2,551Other - 57 57Urology 112 178 26 331 647WPAS Validators 43 - 43Sub Total 1,422 1,580 276 189 - 1,154 4,621Total Expenditure 2,990 2,228 667 189 1,763 1,154 8,991
Dia
gnos
tics
Inpa
tient
s D
ayca
ses
Out
patie
nts
Expenditure Category
Appendix 5 – Balance Sheet
21
Opening balance
£000M8 2019/20
£000Movement
£000Non Current Assets:Fixed Assets 627,406 613,520 (13,886) Other Non Current Assets 69,363 68,998 (365) Current Assets: 0Inventories 16,077 17,082 1,005Trade and other receivables 66,441 38,182 (28,259) Cash - Revenue 307 (1,306) (1,613) Cash - Capital 3,665 2,245 (1,420) Total Assets 783,259 738,721 (44,538) Liabilities:Trade and other payables 142,428 114,640 (27,788) Provisions 110,432 109,805 (627) Total Liabilities 252,860 224,445 (28,415)
530,399 514,276 (16,123) Financed by:General Fund 402,323 386,200 (16,123) Revaluation Reserve 128,076 128,076 0Total Funding 530,399 514,276 (16,123)
Balance sheet as at Month 8 2019/20
Appendix 6 – Risks and Opportunities
22
Issue Description £m
Key Decision Point &Summary Mitigation Risk Owner
1Risk: Welsh Risk Pool Pressure
Potential risk in relation to the Welsh Risk Pool. NWSSP are forecasting that annual expenditure will exceed the 2019/20 budget by £9.851m. Welsh NHS organisations will need to take a share of this pressure. The Health Board’s share of this cost is £1.817m and is included in the forecast. However there is a risk that the increased savings required to meet this pressure will not be delivered.
(1.8) Discussions continue around potential mitigations.Tony Uttley, Interim Finance Director – Operational Finance
2 Risk: Prescribing
Lowest forecast methodology is used, giving rise to a possible financial risk. Actual costs to date in 2019/20 are showing a rising run-rate.
Emerging issue is Category M price increases, which have been reflected in the risk.
Does not include any potential growth in the number of drug items added to the No Cheaper Stock Obtainable (NCSO) price list.
(3.0) The risk is reviewed and updated monthly. There are a wide range of Prescribing Savings Schemes
in place to manage spend and growth.
Berwyn Owen, Chief Pharmacist & Nigel McCann, CFO Prescribing Finance Lead
3
Risk: Continuing Healthcare (CHC)
- The financial plan approved by the Board explicitly excluded providing growth funding for CHC. The risk on CHC is primarily in relation to Older People’s Mental Health.
(1.0) Divisions are developing cost avoidance schemes to mitigate against this impact.
Rob Nolan, Finance Director –Commissioning & Strategy
4Risk: Under-performance of savings plans
Green and amber cash releasing savings identified totalled £23.4m, a shortfall of £1.6m against the initial plan target of £25m. Of these, £0.8m relates to efficiencies, meaning the total risk is £2.4m.
(2.4) The Health Board is continuing to identify new schemes
and move existing red schemes into amber and green in order to close the gap to the initial £25.0m plan target.
Sue Hill, Executive Director of Finance
5 Risk: SICAT
The Health Board’s Single Integrated Clinical Assessment and Triage (SICAT) service was set up at the end of 2018/19 and fully funded by the 111 Programme. The service has incurred costs of circa £0.38m in the first 8 months of the year with a forecast cost for 2019/20 of £0.6m. It has been assumed to date that SICAT would be fully funded by the 111 Programme, but this is no longer the case.
(0.6) An alternative funding source for SICAT is being sought.
Eric Gardiner, Finance Director – Provider Services
6 Risk: Junior Doctor monitoring
There was a significant test legal case focusing on how NHS organisations should address monitoring for junior doctors.
Further investigations are being undertaken to quantify any potential impact. The Health Board is working to mitigate this risk through a number of measures. To date there have been no concerns raised within the Health Board. A review is in place dating back 6 years assessing the substitution and the impact it has on natural breaks. This should help provide further information.
Sue Green, Executive Director of Workforce & Organisational Development
7Opportunity: Stretch Target
Control total of £25m set by the Welsh Government requires a further £10m of savings to be made. If schemes can be identified they have the potential to reduce the year end position below the £35m currently forecast.
10.0 Work has been initiated through improvement groups,
looking at benchmarking and opportunities, to identify savings plans to meet these targets.
Sue Hill, Executive Director of Finance
Total 1.2
Appendix 7 – Response to Month 7 Questions
23
MONTH 7 FINANCES
Executive Summary – Page 1
The improvement was largely due to a £0.9m benefit on the WHSCC contract, offset by increasing pressures in Prescribing.
With everyone focused on stopping spending and delivering savings, then the £35m remains achievable. This will require commitment and concerted effort by all Executives and across all divisions for the remainder of the year.
Forecast full-year out-turn will be kept under continuous review, with increasingly critical re-assessments from December.
Year to Date and Forecast Overview – Page 2 & 3
The Grip and Control actions arising from the PwC recommendations have been enacted and there continues to be a focus on the remaining actions. The actions undertaken have supported improved practices and governance, as well as controls around expenditure.
The assessment of cost pressures is based on best information from across the organisation at that point. It does change over time, both as a result of factors under Health Board control and influence and as a result of environmental factors which are less so. It is subject to ongoing review and assessment, which in turn builds an evidence base of track record from which to more reliably estimate the potential impact going forward. This is being used to inform the planning and budget-setting process for 2020/21
It is generally expected that Health Boards will manage pressures, and mitigate identified risks. This expectation falls differently on Health Boards depending on their local circumstances and the flexibilities they have within their positions - the less flexibility the harder it is to absorb such pressures. In the case of the Risk Pool, the arrangement was useful for Health Boards as it is more effective to deal with such costs on a pooled basis. However, the pooling has ceased to be effective this year, and Health Boards have now had to revert to account for the pool’s shortfall in their individual positions.
At M7 we reported the potential Risk Pool risk of £2.8m, as advised at the time. At M8 we have not recognised our share of the Risk Pool shortfall in the year to date position, but have included the new estimate of our share in the full year forecast as a realising pressure. We have also recognised the need to find mitigating actions to cover this. The potential exposure advised to us has swung between £0.6m to £2.8m over a 3 month period, and has reduced to £1.8m at Month 8.
Appendix 7 – Response to Month 7 Questions
24
Annual Plan The planning process includes a review of the cost pressures brought forward from 2019/20 and an assessment of new inflation and growth pressures for 2020/21. This exercise is undertaken in conjunction with Divisions and provides an opportunity for a realistic assessment of pressures with appropriate challenge. It is not expected that the Health Board will be able or willing to fully fund individual divisional submissions because it is recognised that budget holders have a responsibility to manage within their budget and make every effort to live within their means. To assist in closing any gap which is identified, each Division will be subject to a deep dive into their draft budgets to clearly identify opportunities to manage budgets more effectively, to identify areas that consistently underspend and to explore how using this financial scope can help to address outstanding pressures. This will be undertaken prior to the start of the new financial year in January.
These show the forecast expenditure run rates before and after forecasted savings are taken into account. There is little difference between the two as savings equate to only 2% of total expenditure; they were an action from Month 6’s Finance and Performance Committee meeting but did not work in practice. The equivalent Month graphs have been removed from the Month 8 Finance Report.
Financial Governance and ControlThere have been a number of additional controls put in place at YGC by the hospital management team in the last few months. This includes approval in advance of cover colleague shifts and a non-pay panel that meets weekly to look for opportunities.
The site has historical issues of rotas in place above budgeted establishment. A lot of work has been undertaken within ED to reduce the run rate by employing temporary staff into these posts instead of premium cost staff. Whilst the run rate has reduced, the rotas in place are not budgeted and remain a cost pressure.
A number of services have been centralised into YGC and there has been an impact on the costs of other services.
The site has only identified a low value of cash releasing savings against its target (circa. 25%) which is one of the most significant factors causing the failure to reduce overspend to date. The site is significantly behind the other acute hospitals in this respect and needs to catch up. A number of schemes are identified such as transferring orthopaedics off the Abergele site, but it will take some time for this to be implemented.
A desktop review of the actual expenditure and WTEs over the last three years is underway and will be completed, with findings and recommendations before the year end.
Appendix 7 – Response to Month 7 Questions
25
Budget Scrutiny Meetings
Aside from the Financial Recovery programme scheduled meetings, all the divisions have set up additional scrutiny meetings in order to respond to the challenge around financial management, including savings delivery and opportunities to offset cost pressures. The main challenge to the divisions remains the handover of accountability for pan-BCUHB schemes.
There remain eight actions from the PwC Grip and Control recommendations to conclude. Significant work has progressed in all of these areas and this will continue, to ensure sustainable change is achieved.
Forecast Cost Pressures
East Area and Wrexham Maelor have maintained their year-end forecasted position as they have covered any cost pressures with additional savings or one-off benefits. We are clear that our forecasting consistency and capability across the Health Board needs to be improved and this is the subject of a Finance working group.
Budgetary Control – Page 4
Budget Holders have signed their Accountability Agreements which includes their agreed budget for the year. Where a budget holder feels they are not in a position to operate within their budget they have the option to include a narrative within their Accountability Agreement. Budget Accountability Agreements are signed in April as part of the Opening Budget, but taking this financial year as the example, the Divisions were given a collective share of an additional £10m savings target. The Budget Accountability Agreements were not then changed to reflect this, although some divisions have nevertheless demonstrated progress towards achieving these stretch targets.
Accountability meetings are held quarterly between Executives and Divisions which include a review of the individual Division’s financial position. It is suggested / recommended that any material in-year changes to the overall bottom line Divisional Budget (or spending plans) are also reflected in a New / Updated Accountability Agreement, which formally records the reason for the change and the implications of such a change, the source of additional funding for any increase in core spend, etc.
However, it is clear that individual budgets have been set which didn’t reflect the FYE of cost pressures and that the impact of the non-recurrent delivery of savings over several years has been a significant contribution to the Health Board’s current financial position.
Appendix 7 – Response to Month 7 Questions
26
Forecasting
Robust expenditure plans refer to the spending plans that underpin additional funding received from Welsh Government. Additional funding is initially held in a central reserve, and is distributed to the relevant divisions as soon as possible but only once the appropriate use of this funding is established. There should be no bottom line impact overall as the spending plan should underpin the funding provided, although the impact of accounting for the funding and the related expenditure does affect expenditure trends in the relevant costs.
In Month 7 we had significant new funding. This is still being held centrally pending confirmation of appropriate plans.
Potential inconsistencies refer to differences between planned savings included in defined pan-BCU schemes developed through Improvement Groups, and the savings projected within the individual divisions that benefit from these schemes as they contribute to the achievement of their divisional savings targets.
The IGs are now beginning to develop and convert significant pan-BCU wide schemes. A number of these schemes were implemented at speed in Month 7. The datasets that support these schemes and enable their effective tracking and reporting across all the costs and divisions benefiting from them are being developed but lagged behind the schemes’ implementation. In this context, divisional forecast did not fully recognise the full potential benefit of these schemes. The impact of these differences, which have been corrected centrally at corporate level, is shown within the Month 8 Finance Report.
The overall forecasts accordingly recognise the benefit of these pan-BCU wide schemes. It is acknowledged that the datasets referred to above and the related communication between IGs and divisions impacted by these significant schemes needs to be developed further to enhance collective understanding.
Savings – Page 5
The anticipated conversion and delivery of red risk savings is based on information provided by the PMO. It is clear that the £35m deficit position will only be realised if conversion of red schemes and delivery of all savings is at the level currently forecast. WG, through the Monitoring Return, are sighted on this position and are keen that all savings are quickly moved into delivery.
Further escalatory actions are currently in rapid development in order to create further impetus and surety around the delivery of the £35m deficit forecast.
There is also an urgent requirement for the PMO to validate the monthly profile of the red schemes, in order to identify any opportunities to bring
Appendix 7 – Response to Month 7 Questions
27
delivery forward and provide greater assurance around the forecast out-turn position.
The anticipated conversion and delivery of red risk savings is based on information provided by the PMO. This takes into account the work of the IGs and their forecast for the savings that they will deliver. IGs are responsible for meeting their savings plans.
As noted above additional escalatory measures are also being adopted to supplement additional IG schemes development.
The Month 8 in month deficit has necessitated the consideration of more radical cost reduction options in order to deliver the average sub £2m deficit each month in the last 4 months of the year required to deliver the forecast.
Underlying Deficit
This will be going to January F&P Committee, in order to reflect a coordinated assessment in conjunction with the FDU.
We await details of the funding allocations for next year.
Our emerging IGs are critical in identifying and addressing efficiency gains on an ongoing basis.
The Health Board also has a number of sub-optimal structural costs, eg our Estate and asset-related costs amount to over £100m per annum.
The savings programme is supported by information on our areas of inefficiencies which is drawn from both the FDU’s Efficiency Framework and our own Benchmarking analysis. This has been distributed to Improvement Groups and was referenced in the planning workshop as a key source of intelligence regarding opportunities for savings. Savings identified against opportunities highlighted by the FDU will be tracked in year to demonstrate progress in addressing inefficiencies.Clearly progress by our IGs will both reveal and also address identified efficiency and other gains as they develop further and expand their ongoing impact.
Welsh Government will be issuing the details of a new national allocation formula within the 2020/21 Allocation Letter, and we have been told that the allocation of growth will be based on our Outcomes. Within the rollout of the new formula is a commitment to develop the formula down to Cluster level for 2021/22. As a Finance function we have expressed our wish to be involved in the piloting of this work in 2020/21.
Appendix 7 – Response to Month 7 Questions
28
Risks and Opportunities – Page 7
Opportunities
Divisions are still actively trying to identify savings to meet their stretch targets. The opportunity level is reviewed each month and we have increased our risk rating to red in Month 8. This will be reviewed continuously, as will our forecast, as we move closer to the end of the financial year.
Revenue Resource Limit – Page 8
Income and Expenditure
Project leads have been asked to liaise with Welsh Government policy leads to determine the likelihood that funding which is not fully committed will be subject to clawback. If this is the case, there is no detrimental impact as the funding is not currently in the year to date position, nor considered for the forecast. If slippage on funding can be retained then this may have a positive impact on the position. A specific and significant risk relates to committed RTT funding, in light of the current performance trajectory.
Pay Expenditure – Page 9
Pay Award
The pay award has only impacted on actual pay costs and not the variance. Reserves were held to cover the cost of the pay award and have been released to match actual costs, so there was no impact on the position.
Agency and Locum Costs – Page 10
Establishment
Medical agency costs increased in July and remained at that high level, although we have seen a decrease in November. A combination of using more agency staff to deliver RTT related activity and the implementation of the pension taper relief rules has led to an increase in medical agency staff usage over recent months. This should start to reduce again with the implementation on the Medical Staff Bank.
Substantial work is underway through multiple workstreams with the WIG’s oversight. Onboarding the additional staff costs that will support the identified savings are subject to strong establishment controls. Steps are being taken to carefully manage further third party costs that support savings realisation, which tend to be front-end loaded (eg permanent candidate finders fees) relative to prospective savings, to ensure their incidence close to year end does not compromise in-year savings.
Appendix 7 – Response to Month 7 Questions
29
The Kendal Bluck work has taken longer than originally planned but the final reports are now being fed back to the Health Board and discussed with the management teams. Some of the findings in the reports will challenge the Health Board to operate different models but have large savings attached to them. There is Executive support for this scheme to be delivered this year.
Some of the increased cost will be funded from the Winter Plan in the short term while the staffing structures are reviewed for the longer term.
The nursing workforce is also being reviewed in parallel with the medical staffing as they need to operate as a single integrated team to be successful.
The delivery of the WIG schemes in the current financial year is critical as they should deliver significant reductions in pay budgets for 20/12.
Non-Pay Expenditure – Page 12
Primary Care
These uplifts have only impacted on actual costs and not the variance. Funding was received in Month 7 to cover the cost of the uplifts and has been brought into the position to match actual costs, so there is no impact on the position.
Other Non-Pay
These savings have been allocated to the divisions and it is the responsibility of the divisions to identify savings schemes to meet these targets. When recurrent schemes have not been identified, divisions will hold those savings targets on a savings subjective within one or more of their cost centres. As recurrent schemes are identified, these targets will be moved to the relevant subjectives. Stretch targets that have not been covered by converted savings schemes are also held centrally within divisions.
The coding of savings within divisions is being reviewed for 2020/21.
RTT – Page 13
The £7.740m spent to date on RTT is included in the figures in the rest of the Finance Report. An additional £6.1m has been committed, to bring total commitment to £13.8m. This committed expenditure has not yet been spent, so is not reflected in the year to date financial position, but is included in expenditure forecasts.
Appendix 7 – Response to Month 7 Questions
30
Performance data is included in the IPQR report. We will consider improved ways of presenting plan and actual financial and non-financial performance going forward.
Balance Sheet – Page 14
Reserves
In previous years the reserves have been managed and held centrally but this year, where it was practical, we have allocated reserves to divisions. The strategy is to only hold reserves centrally where there is a clear advantage in doing so. The establishment of contingency reserves is addressed in annual planning and budget-setting.
The utilisation of reserves is managed by the Directors of Finance, who have pan-BCU responsibilities and ensure that the reserves are responsibly reviewed and released when appropriate.
See also comments above in relation to “…robust expenditure plans…”.
The opening contingency reserve was set at £2.4m. Of this £0.7m has been released to fund specific unexpected cost pressures such as increases in Losses and Compensation Claims. In addition to this, a further £1.3m has been phased in to support the financial position.
31
5 FP19/296 2019/20 Annual Plan Progress Monitoring Report
1 FP19.296a APPMR.docx
1
Cyfarfod a dyddiad: Meeting and date:
Finance & Performance Committee19.12.19
Cyhoeddus neu Breifat:Public or Private:
Public
Teitl yr Adroddiad Report Title:
Annual Plan Progress Monitoring Report (APPMR)
Cyfarwyddwr Cyfrifol:Responsible Director:
Mr Mark Wilkinson Executive Director of Planning & Performance
Awdur yr AdroddiadReport Author:
Dr Jill Newman, Director of Performance
Craffu blaenorol:Prior Scrutiny:
This paper has been scrutinised and approved by the Executive Team and the Executive Director of Planning and Performance.
Atodiadau Appendices:
1. APPMR
Argymhelliad / Recommendation:The Finance & Performance Committee is asked to note the report.
Ar gyferpenderfyniad /cymeradwyaethFor Decision/Approval *
Ar gyfer TrafodaethFor Discussion*
Ar gyfer sicrwyddFor Assurance*
Er gwybodaethFor Information*
Sefyllfa / Situation:This report provides a self-assessment by the executive leads of the progress being made in delivering the key actions contained in the 2019/20 Operational plan.
Cefndir / Background:The operational plan has a number of key actions required to be delivered during 2019/20. The Executive lead reviews on a monthly basis progress against their areas for action and RAG-rates progress. Where an action is complete this is RAG rated purple, where on course to deliver the year end position the rating is green. Amber and red ratings are used for actions where there are risks to manage to secure delivery or where delivery is no longer likely to be achieved. For Amber and Red rated actions a short narrative is provided. The plan was reviewed at the finance and performance committee in November and a number of the original actions revised. These revisions have been included in this report.
2
Asesiad / AssessmentStrategy ImplicationsDelivery of the operational plan actions is key to implementation of the Boards strategy
Financial ImplicationsDelivery of the operational plan within the budget set by the Health Board is part of ensuring resources are well-managed and care effectively provided within the allocated resources.
Risk AnalysisThe RAG-rating reflects the risk to delivery of key actions
Impact Assessment The operational plan has been Equality Impact Assessed.
1 FP19.296b Annual Plan Progress Monitoring Report - November 2019 v0.8.pptx
Cover Page
Three Year Outlook and 2019/20 Annual Plan: Monitoring of Progress against Actions
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
1
Table of Contents..
Table of Contents
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
2
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Cover 1 Workforce Matrix 12
Content 2 Workforce Exception Report 13
About this Report 3 Estates Matrix 14
Health Improvement & Health Inequalities Matrix 4 Estates Exception Report 15
Health Improvement & Health Inequalities Exception Report
5 Digital Health Matrix 16
Care Closer to Home Matrix 6 Digital Health Exception Report 17
Care Closer to Home Exception 7 Digital Health Exception Report 18
Planned Care Matrix 8 Finance Matrix 19
Planned Care Exception Report 9 Finance Exception 20
Unscheduled Care Matrix 10 Further Information 21Unscheduled Care Exception Report 11
About this Report..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
3
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
This report presents performance as at the end of October 2019 against the 2019/20 Annual Plan actions, and is presented in the same order as the plan i.e. health improvement and health inequalities, care closer to home, planned care, unscheduled care, workforce, digital, estates and finance.
The ratings have been self assessed by the relevant lead executive director. All the ratings have been reviewed and approved by the lead executive.
Where a red or amber rating is applied in any month, a short narrative is provided to explain the reasons for this and actions being taken to address.
To interpret this report, it is necessary to note the basis of the rating which provides a succinct forecast of delivery, combined with an assessment of relative risk. Future milestone markers are included as M in the matrix to indicate when elements of actions contained in the report were due for completion. Many of the actions have multiple milestones to support delivery of the year end position. Only when all milestones are complete can the action be achieved.
Feedback is welcomed on this report and how it can be strengthened. Please email [email protected].
Programme.
Programme: Health Improvement & Health Inequalities
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
4Health Improvement & Health Inequalities Matrix
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
5
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Health Improvement & Health Inequalities Exception
AP008 - Partnership plan for children progressed with a strong focus on adverse childhood experiencesImproved partnership working is taking place across children’s services. All services are gradually focusing their work with an ‘ACE aware and trauma informed’ approach. This particularly takes place within our services for Children who are Looked After (LAC) where there is significant multiagency team work to enable earlier intervention. This is as a result of the Children’s Transformation Bid investment. Partnership working is also evident for the implementation of the Additional Learning Needs (ALN) Act, with work taking place to develop the role of the DECLO. More recently a multi- disciplinary arrangement has been agreed between the health board and third sector partners in the development of an On-call rota for the provision of care to children at the End of their Life, as expected within the palliative care standards. While progress is being made there are risks to delivery which mean that the overall action remains amber at present.
Programme.
Programme: Care Closer to Home
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
6Care Closer to Home Matrix
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
7
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Care Closer to Home Exception
AP014 Model for health and well-being centres created with partners, based around the “home first” ethos Work on this action is progressing, but presently on is based on three footprints, and the approach is not yet sufficiently collated into a single model for this action to be considered as green, although good progress towards achieving the action continues.
AP016 Plan and Deliver Digitally Enabled Transformation of Community Care - Procurement delays related to IT, alongside the multi-partner approach and requirement for system upgrades in a number of areas have resulted in there being some slippage on the delivery of this action. This is therefore rated amber.
Programme.
Programme: Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
8Planned Care Matrix
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
9
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Planned Care ExceptionAP021: Implement preferred service model for acute urology servicesTask group have been meeting re the assisted robotic service in urology, the model for Urology continues to be worked on and the operational difficulties are being worked throughAP022: Business case, implementation plan and commencement of enabling works for OrthopaedicsThe orthopaedic 1st wave of consultants have been recruited and commence in new year. The orthopaedic business case is being reviewed at this current time and early work around theatre capacity has commencedAP023: Transform Eye Care PathwayThe eye care improvement work is progressing on time with the cataract pathway now embedded on all three sites, the glaucoma pathway re-design commencing during December and with tender evaluation scheduled for early January to develop the primary care shared care model and the wet AMD facility on schedule to deliver at the end of December 2019. However the progress is amber rated as there are risks which are needing to be managed both locally within BCU and with slippage on the national programme of work. For example the national digital eye care procurement is awaiting award of contract, which was originally planned for October 2019 and the e-referral project is subject to further decision as to the preferred option. Locally the training requirements for non-medical staff combined with the need to ensure image transfer from optometry to hospital eye services can be achieved will mean that the 2019/20 benefits from the shared care arrangements will originate from referral refinement with benefits from patient monitoring and management arising in 2020/21 once staff have completed higher level training and have signed off competencies. A full briefing paper on progress will be provided to the Finance & Performance committee in January 2020.AP024: Rheumatology Service ReviewGood recent progress, with board paper imminent, but as this was due in July 2019, the action can only remain Amber.AP025: Systematic Review and Plans developed to address sustainability for all planned care specialties: Work is continuing on the 2019/20 delivery plan. Demand and Capacity analysis for 2020/21 across all specialties is progressing to contribute to the operational plan. The full systematic review of all services will not be completed in accordance with the plan, priority is being given to those specialities with the greatest challenge to delivery.AP025: Endoscopy AmberThere is a plan in place to deliver the end of year position of 700 over 8 weeks. This is now operational following the commencement of additional insourcing at YGC and Wrexham. However it is dependent upon the allocation of additional resource as highlighted in the RTT paper discussed at F&P on 4th December 2019.AP025: Systematic Review and Plans developed to address sustainability for all planned care specialties: Work is continuing on the 2019/20 delivery plan. Demand and Capacity analysis for 2020/21 across all specialties is progressing to contribute to the operational plan. The full systematic review of all services will not be completed in accordance with the plan, priority is being given to those specialities with the greatest challenge to delivery.
Programme .
Programme: Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
10Unscheduled Care Matrix
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
11
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Unscheduled Care ExceptionAP031 Demand: Workforce shift to support Care Closer to Home – Community Resource Teams (CRTs) and Admission and Discharge Team ( ADT ) in ED across all three EDs. Work continues through financial recovery works to improve the impact of these services to provide more care closer to homeAP039 Stroke Services This action remains red rated as it has not been possible to find a route to resource the business case in 2019/20. However, progress has been made in implementing aspects of year 1 of the business case. As such the thrombectomy service ( clot retrieval) has been expanded to provide a seven day per week service from November 2019. The health board has been successful in its bid for rehabilitation assistants and is moving forward to recruit 2wte assistants for each acute site so as to increase the acute therapeutic time patients receive and support patient optimal recovery and early discharge. The consultants home-based technology has been improved to support prompt decision making in relation to opportunities for thrombolysis. Work is continuing to include the implementation of the early supportive discharge and rehabilitation model within health economy plans for 2020-2021.AP030 Demand: Enhanced Care Closer to Home Pathways – Improvements are being made in Emergency Departments (ED) to provide timely care although slower than planned. New ED escalation triggers and action cards implemented across all sites. Targeted gold level command and control work has commenced across all three EDs to improve patients access to timely ED care. AP033-Improved crisis intervention services for Children – Out of hours provision for young people in distress is being reviewed across Wales by the DU. We are working in partnership with Local Authorities to address the missing middle of services for young people with both health and social care needsAP034 –Flow- Milestone delivered at Ysbyty Glan Clwyd (YGC) and Ysbyty Wrecsam Maelor (YWM). Ysbyty Gwynedd (YG) has opened the new ED unit but models of care are still being finalised to fully operationalise the space. Plans for these to be implemented in December 2019. Work to reduce outliers in Wrexham has been successful through achievement of new acute floor. Part of the gold level command and control has been focused on ensuring the patient is in the right bed, first time and supporting teams through making bed allocation decisions. Strategic plans in place to look at how we can use the Christmas period to re-balance patients in the Hospital as we are likely to be the lowest occupied on Christmas Eve. Engaged with National ‘Every Day Counts’ work although delay to National agreement on discharge pathways and engaging with social care.AP038 –Discharge Ongoing work with local authorities, recognition there is a shortage in provision of package of care. Regional Partnership Board winter funding to support. Home First principles being embedded through financial recovery work, delays impacted by resource. Long length of stay reviews in Acute and Community Hospitals is multi-agency and is identifying areas where community beds are inappropriately used and work is underway to ensure Home First approach is maximised as part of financial recovery work. This commenced in West late November. What matters conversations are happening but not consistently within 24 hours and further work is needed on discharge planning.
Programme .
Programme: Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
12Workforce Matrix
Three Year Outlook and 2019./20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
Workforce Exception
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
13
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Workforce ExceptionAP043 - Deliver Year One Workforce Optimisation Objectives - reducing waste and avoidable variable/premium rate pay expenditure. Demonstrating value for money and responsible use of public funds - Progress has been achieved in areas such as Retention Improvement Plan in place and actions progressing, N&M bank capacity increased through revised rates and auto-enrolment, Establishment Control (EC) system via electronic portal enabling effective vacancy control, Workforce Optimisation Programmes and associated PIDs are in place and overseen by the Workforce Improvement Group (WIG). However this objective remains Amber as whilst work programmes are all being vigorously pursued and some schemes are green there are still programmes in early stages of development. Next Steps: Continued oversight and delivery of all Workforce Optimisation programmes including: Medical Productivity & Efficiency, Nursing; Midwifery and AHP Productivity & Efficiency, Non Clinical Productivity & Efficiency and Overarching / T&Cs Application.
AP044 - Deliver year one Health & Safety Improvement programme, focussing on high risk / high impact priorities whilst creating the environment for a safety cultureThe gap analysis of legislative compliance has been completed in Q2. This objective remains amber as the review of 31 pieces of legislation indicated there was a lack of compliance in 15 pieces of legislation, partial compliance with 13 and fully compliant with only 3. Next Steps: comprehensive set of action plans has been developed to address the shortfalls in key areas of risks described above. The most significant risks are on the risk register and will be monitored by the Strategic Occupational Health & Safety Group. Plans to develop an accredited Occupational Health Service are underway through the Safe Effective Occupational Health Standards (SEQOSH), this will be implemented in June 2020. A comprehensive set of policies will form the basis of the next 12 months work that are realistic and clear on roles and responsibilities.
AP049 - Provide ‘one stop shop’ enabling services for reconfiguration or workforce re-design linked to key priorities under Care Closer to Home; excellent hospital servicesSome aspects of this objective have been achieved (e.g. further developing guidance to assist managers to take ownership of actions, increasing organisational capacity in regards to Equality Impact Assessment knowledge and understanding). However this objective remains amber as whilst teams across W&OD have deployed a multi team intervention model in support reconfiguration/ workforce redesign in areas such as sickness management and in support of various workforce PIDS this model has not been formalised and publicised. Next Steps: W&OD will continued multi team support to Workforce Optimisation programmes and will document this approach in order to develop this into an ‘offer’ which can be publicised to areas planning significant change.
Programme.
Programme: Estates Strategy
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
14Estates Strategy Matrix
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
15
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Estates Strategy ExceptionVale of Clwyd removed from programme for this year as reported last month and Ablett and Central Medical Records programmes reset, as reported last month
AP071 – Hospital Redevelopment
This plan action comprised three elements: • Review Abergele Hospital – this is actively underway.• Progress redevelopment plans for the Wrexham Maelor – a new timescale has been approved for a programme business case to fully reflect the
digitally enabled clinical strategy ie first quarter 2020/21.• Progress development plans for Llandudno Hospital – this is actively underway.
AP073 - Residences
On 17th December a meeting is taking place with selected North Wales housing providers to explore a potentially ground breaking collaboration between health and housing. We are seeking to address the principal risk to the delivery of a business case to improve the quality of the Board’s ageing residential accommodation i.e. capacity and (to some extent) capability to develop a supportable proposal. The Quarter 4 timescale for production of a business case is at risk and the next few weeks will determine whether it can be achieved.
Programme.
Programme: Digital Health
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
16Digital Health Matrix
Three Year Outlook and 2019./20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
17
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Digital Health ExceptionAP052 WCCIS The WCCIS (Welsh Community Care Information Solution) implementation has been delayed since March 2017 pending resolution of significant functional issues. The WCCIS Programme Committee agreed to pursue implementation despite gaps in functionality, once key prerequisites were met, and providing an interim reduction in costs could be negotiated. An initial pilot implementation was planned to explore product capabilities and inform the potential for a wider rollout. Commercial negotiations were hindered by the supplier’s requirement for BCU to scale up to the full contract value within a 12 month period, without any reciprocal commitment to deliver on product functionality. The Commercial Group ultimately advised BCU in August 2019 to cease negotiations pending agreement on a Functional Development Roadmap (FDR). In the interim, agreement has been reached to progress the pilot a prototype implementation, using Local Authority licenses. Planning and preparatory work is underway, and implementation is expected to begin around April 2020. The prototype will focus in establishing the requirements of the CRTs and will inform wider planning of the Welsh Community Care Information System.
This Action has now been removed from the 2019/20 Plan and been incorporated into the 2020/21 Annual Plan.
Programme..
About This Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
18
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Digital Health ExceptionAP056: Good Record Keeping/ManagementDeputy Head of Health Records post (8b) has been recruited to internally with formal start date of 1st October. The B7 Project Manager requirement has been confirmed in principle and funding is being secured through the HASCAS & Ockenden Board. As soon as able to start the work, Mental Health Services will be the priority area - aim to complete this section by March 2020.
AP058: Deliver Capital Programme for 2019 2020 as defined within plansThe discretionary programme is progressing as planned with progress being made in all expected areas. The programme was subject to change control at the end of QTR2 via the Capital Programme Management Team to reflect the removal of the paging systems replacement project and emerging priorities for spend which include Health Records racking and Telephone Switches.
AP059: Provision of infrastructure and access to support Care Closer to HomeThe group lead by BCU to facilitate standard access to "home networks" for community resource teams have identified 6 Work streams for the provision of ICT infrastructure; • Formalising IT Service Desk call logging procedures and service agreements • Federating Active Directory across 6 Local Authorities and implementing trust relations with BCUHB Nadex • Implementation of Wide Area Networks, Local Area Networks and Govroam wireless networks into required sites • Implementation of telephony solutions for each of the identified sites e.g. Interactive Voice Response call routing & Contact Centres as required • Implementation of shared managed print solutions for all partner organisations at sites • Deployment of Office 365 and MS Teams to enable collaborative working for the various partner organisations. A capital business case is under development to enable work, data from CRT teams is required to complete. This is taking longer to gain than anticipated.
AP060: Support Eye Care TransformationAssistant Business Analyst (Band 5) appointed in Qtr. 2. Commenced 4th November. Induction underway. Further discussions on "requirement" gaps / resource may be required. Meetings scheduled.
Programme.
Programme: Finance
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
19Finance Matrix
Three Year Outlook and 2019./20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Programme..
Finance Exception Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
20
Three Year Outlook and 2019/20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
Finance ExceptionAP075 GovernanceWork is continuing on developing the Governance framework of the Health Board, the revised draft Clinical Risk Strategy is on target for implementation in April 2020 .The work to date has highlighted a number of issues to be addressed and posed 6 emergent risk management themes which need to be considered in order to compliment the work on the overall governance framework.
AP076 - Grip and controlProgress is being made against the Financial Recovery Action Plan.We will successfully single out remaining critical areas of attention if we are to accurately focus energy on the correct key action for the remainder of the year, and to build financial governance capability for the future. AO077 - PlanningPerformance against in-year financial plan (including savings programme) is being tracked. Accurate trajectories and forecasts to recover YTD position will be critical in focusing and driving cost/savings actions by divisions over the remainder of the year.Planning cycle for future years is underway.We are learning lessons from current year planning, in-year performance to date, and from Financial Recovery programme to better inform future planning. AP078 - ProcurementEfficiency framework and other opportunities are being scoped and accessed. Conformance with procurement requirements is being monitored and any deviations reported.Lessons from this year show that utilising national frameworks and All-Wales approaches via NWSSP is not sufficient to guarantee meeting the Health Board’s financial targets. Engagement with NWSSP on All-Wales approaches has begun with DOF and new Director of Procurement, to identify any potential new approach and scale.
Appendix A: Further Information.
Appendix A: Further Information
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
http://www.wales.nhs.uk/sitesplus/documents/861/Agenda%20bundle%20Health%20Board%2028.3.19%20%20V2.0%20updated%2022.3.19-min.pdf
21
Three Year Outlook and 2019./20 Annual PlanMonitoring of progress against Actions for Year One (2019/20)
The Annual Plan is included on page 423 of the March 2019 Health Board papers.
The link to these papers is shown below:
6 FP19/297 Integrated Quality and Performance report Month 8
1 FP19.297a IQPR cover November 2019 FINAL.docx
Cyfarfod a dyddiad: Meeting and date:
Finance & Performance Committee
19.12.19 Cyhoeddus neu Breifat:Public or Private:
Public
Teitl yr Adroddiad Report Title:
Integrated Quality & Performance Report (IQPR)
Cyfarwyddwr Cyfrifol:Responsible Director:
Mark Wilkinson Executive Director of Planning & Performance
Awdur yr AdroddiadReport Author:
Dr. Jill Newman, Director of Performance
Craffu blaenorol:Prior Scrutiny:
This paper has been scrutinised and approved by the Executive Director of Planning and Performance.
Atodiadau Appendices:
None
Argymhelliad / Recommendation:The Finance & Performance Committee is asked to scrutinise the report and to consider whether any area needs further escalation to be considered by the Board.Ar gyferpenderfyniad /cymeradwyaethFor Decision/Approval *
Ar gyfer TrafodaethFor Discussion*
Ar gyfer sicrwyddFor Assurance*
Er gwybodaethFor Information*
Sefyllfa / Situation:Please refer to Executive Summary contained within the IQPRCefndir / Background:Our report outlines the key performance and quality issues that are delegated to the Finance & Performance Committee. The summary of the report is now included within the Executive Summary pages of the IQPR and demonstrates the areas that are challenged in relation to delivery of the expected standards of performance, together with the actions being taken to address the performance.
The Financial Balance is discussed in detail in the Finance Report.
Asesiad / Assessment
Strategy ImplicationsThe performance measures within the IQPR are aligned with the Annual Plan and identified as the key performance indicators in monitoring and managing the Health Board’s strategy.
Financial ImplicationsThe delivery of the performance indicators contained within our annual plan will have direct and indirect impact on the financial recovery plan of the Board. Our operational plan is aligned to our resource allocation for delivery
Risk AnalysisThe RAG-rating reflects the performance against the Plan. Where there aren’t Plan Profiles, the performance is measured against the national target.
Impact Assessment The operational plan has been Equality Impact Assessed. The Finance & Performance Committee is asked to scrutinise the report and to consider whether any area needs further escalation to be considered by the Board.
1 FP19.297b IQPR November 2019 FINAL v1.0.pdf
Integrated Quality and Performance Report – Finance & Performance Committee
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
1
November 2019
Table of Contents..
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
2
Cover Page 1 Stroke Care Graphs 26
Table of Contents 2 Stroke Care Report page 1 27
About this Report: Section 1: Report Structure 3 Stroke Care Report page 2 28
About this Report: Section 2: Report Content 4 Emergency Department inc Minor Injuries Units 4 Hour Waits: Graphs 29
Overall Summary Dashboard 5 Emergency Department inc Minor Injuries Units 4 Hour Waits: Report 30
Performance Summary – Page 1 6 Emergency Department: Number of 12 hour breaches: Graphs 31
Performance Summary – Page 2 7 Emergency Department: Number of 12 hour breaches: Report 32
Performance Summary – Page 3 8 Ambulance Handover: Number of Breaches over 1 hour: Graphs 33
Chapter 1 – Summary Planned Care 9 Ambulance Handover: Number of Breaches over 1 hour: Report 34
Referral to Treatment (RTT) Graphs 10 Delayed Transfers of Care Graphs 35
Referral to Treatment (RTT) Report 11 Delayed Transfers of Care Report 36
Referral to Treatment (RTT) Waiting List 12 Chapter 3 – Summary Finance & Resources 37
Referral to Treatment (RTT) Projection 13 Agency and Locum Spend Graphs 38
Cancer: Graphs 14 Agency and Locum Spend Report 39
Cancer: Report 15 Financial Balance Graph 40
Diagnostic Waits: Graphs 16 Financial Balance Report 41
Diagnostic Waits: Report 17 Sickness Absence Graphs 42
Follow up Backlog Graph 18 Sickness Absence Report 43
Follow up Backlog Report 19 PADR Graphs 44
Eye Care Measure Report 20 PADR Report 45
Activity v Plan Report Page 1 21 Mandatory Training Graphs 46
Activity v Plan Report Page 2 22 Mandatory Training Report 47
Activity v Plan Report Page 3 23 Chapter 4 – Summary Primary Care 48
Activity v Plan Report Page 4 24 Dental Care Report 49
Chapter 2 – Summary Unscheduled Care 25 Proposed new Measures for Primary Care 50
Appendix A: Further Information 51
Finance & Performance Committee Version
Integrated Quality and Performance Report November 2019
This Integrated Quality & Performance Report (IQPR) provides a clear view of current performance against a selected number of Key Performance Indicators (KPI) that
have been grouped together to triangulate information. This report should be used to inform decisions such as escalation and de-escalation of measures and areas of focus.
Actions for escalation should be captured in the Chair’s report for the Board and minutes of the committee.
The measure code relates to the code applied within the NHS Wales Annual Delivery Framework, which Welsh Government hold the Board accountable for delivering. A key
difference in the structure of the IQPR for 2019/20, in comparison to 2018/19 is that it is that the report reflects the organisational priorities as set out in the Annual Plan
approved by the Board. The report maps each of the measures included against the corresponding work programme within the Annual Plan for 2019/20. This is done via a
reference number in the 4th column of the Measure Component Bar.
The actual performance reported is compared to the BCU plan in the first instance, with the background colour used to depict whether the performance is better or worse
than planned. The national target is shown so that performance can be compared against expected national standards and locally agreed plans. Performance from April
2019 to date is also shown in the Measure Component Bar together with the position reported for the same reporting period in the previous year. The Wales Benchmark
position is acquired from the Chief Executive Officer Papers published by Welsh Government and is usually at least one month in arrears.
About this Report..
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
3
Status Key:
Finance & Performance Committee Version
Integrated Quality and Performance Report
Section 1: Report Structure
November 2019
Performance has improved since last reported
Performance as got worse since last reported
Performance remains the same as last reported
Profiles
For each key performance indicator the accountable Executive Director has confirmed the profile of performance expected to be delivered during the year based on the
actions and resourcing set out in the annual plan. The report tracks performance against this profile and as such the Red Amber Green (RAG) rating applied are for
performance against the Plan. Where a local plan profile is not available the RAG rating will relate to the National target ,which is presented alongside each indicator on the
chapter Summary pages. The frequency of reporting of indicators is set out in the NHS Annual Delivery issued by Welsh Government and this frequency is reflected in the
reporting with some indicators annual, others bi-annual, quarterly, bi-monthly or monthly.
Escalated Exception Reports
When performance on a measure is worse than expected, the Lead for that measure is asked to provide an exception report to assure the relevant Committee that a)the
reason for the under-performance is understood , b) that a plan and set of actions in place to improve performance, c) that there are measurable outcomes aligned to those
actions and d) that they have a defined timeline/ deadline for when performance will be 'back on track’. Although the exception reports are scrutinised by Finance &
Performance Committees, there may be instances where they need to be ‘escalated’ to the Board via the Committee Chair.
Longitudinal view of performance
Where possible the committee is provided with a longitudinal view of performance against each indicator . Run charts and Statistical Process Control (SPC) charts are used
to assist with the visualisation of performance overtime and to provide an understanding of normal variation within the month to month performance. This will assist with
tracking performance over time, identifying unwarranted trends and outliers and fostering objective discussions rather than reacting to ‘point-in-time’ data.
Cycle of business
This report attempts to set out the actions in the operational plan and the associated measures which come under the terms of reference for this committee to scrutinise
during 2019/20. Key performance indicators have been reviewed again in during October 2019 and the amendments ratified by the November Board. These profiles replace
the previous key performance indicators and will be used to track and RAG rate performance against from November 2019. Where monthly measures are reportable to this
committee the November data is included in this report. For other measures the data provided relates to the latest validated and submitted reporting period. Where data is
not currently available the measure is greyed out in the report.
About this Report..
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
4
Finance & Performance Committee Version
Integrated Quality and Performance Report
Section 2: Report Content
November 2019
Performance Executive Summary.. Page 1
November 2019Finance & Performance Committee Version
Integrated Quality and Performance Report
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
The committee are asked to note that mandatory training has been compliant with the national delivery requirement and our BCU plan for the last 3 months and therefore
should be stood down from exception reporting in accordance with the Board’s performance management strategy.
The executive team would draw the attention of the committee to three main performance themes contained in the report: timely access to planned care, unscheduled care
and the use of our resources.
Planned Care.
For Planned Care this report shows both the level of performance against the national targets for 36weeks and 95% of patients waiting less than 26 weeks. The
performance on RTT has continued to deteriorate during November with 757 more patients waiting in excess of 36 weeks. Given the additional expenditure on RTT already
taken place during 2019/20 the resource remaining for additional internal or outsourced activity over the next 4 months is limited and therefore the Executives are reviewing
the affordability of further opportunities for improvement. The current forecast position for year end remains at 11,799 whilst this review takes place.
The underlying size of the overall waiting list is shown overtime, demonstrating a consistency in the pattern of the waiting list volume month on month but a higher volume of
patients waiting this year compared to last year and that the difference in size of waiting list has grown at an increasing rate each month this year. This is reflected in the
growth in the over 36 week cohort of patients requiring treatment before year end, which is also included in the report.
A more detailed RTT report focussing on the balance of harm reduction, RTT target delivery and resource requirements is included in the papers for the Committee this
month and should be referred to for additional information.
Performance Executive Summary..
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
6
Finance & Performance Committee Version
Integrated Quality and Performance Report
Page 2
November 2019
BCU HB Target Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
Plan 5,714 6,838 7,465 7,961 8,846 8,021 7,227 7,683 AP
Actual 6,932 7,144 8,034 7,826 6,004 6,870 7,499 7,998 8,900 10,167 10,052 10,768 11,525
Diagnostics 8wks Actual 0 1,275 1,486 2,116 2,123 2,277 2,548 2,857 2,827 2,793 2,957 2,816 2,443 2,233
Plan 73,000 73,000 72,000 71,000 70,000 87,712 86,835 85,967 81,890 79,924
Actual 80,712 84,769 83,473 82,483 87,712 88,210 88,079 88,511 88,648 91,288 90,569 89,909 89,235
Plan 89.00% 90.00% 90.00% 91.00% 92.00% 82.00% 83.00% 84.00% 84.00% 84.00% 85.00% 85.00% 85.00%
Actual 80.90% 87.20% 84.40% 808.00% 87.60% 82.20% 81.50% 80.40% 84.90% 86.00% 82.60% 82.90%
Plan 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00% 98.00%
Actual 99.50% 98.10% 97.40% 98.90% 97.20% 100% 98.30% 98.30% 99.50% 98.10% 96.40% 99.50%
Single Cancer Pathway 78.00% 80.00% 76.00% 77.00% 75.00%
Amber is used where performance is within 3% of Plan There is no set target for Single Cancer Pathway Cancer is reported 1 month in arrears
Cancer 31 Day 98%
Followup Overdue 0
RTT over 36 wks 0
Planned Care Performance against Plan - Rolling 12 months to 30th November 2019
Cancer 62 Day 95%
The diagnostic 8 week waits have improved slightly in November, with the greatest improvement being seen in endoscopy. Two of the three sites expect to eliminate the
backlog of surveillance patients and so support it being given to enable patients at the Wrexham site to have investigations carried out in Ysbyty Glan Clwyd (YGC). The
insource capacity is being focussed on the long waits and surveillance patients on the Wrexham site, with planned additional capacity for 27 lists per week to take place
between the middle of December and year end.
Cancer 31 day performance recovered this month to deliver the national target. The 62 day target remains below both the national target and our local planned profile. The
backlog of patients over 62 days remains stable at 88 patients. The challenges to reduction of this backlog relate to : sustainable urological surgery capacity, and delivery of
endoscopy and gastro-enterology services.
Performance Executive Summary..
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
7
Finance & Performance Committee Version
Integrated Quality and Performance Report
Page 3
November 2019
BCU HB Target Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
Plan 88.0% 90.0% 85.0% 85.0% 85.0% >= 74% >= 75% >= 76% 74.0% 75.0% 76.0% 77.0% 72.0%
Actual 71.68% 67.64% 66.94% 72.50% 71.11% 69.48% 71.21% 71.49% 73.72% 73.04% 71.68% 71.15% 72.12%
Plan 850 800 1,000 1,000 900 1,500 1,395 1,290 1,209 1,085 990 961 1,320
Actual 1,404 1,553 1,989 1,430 1,635 1,743 1,660 1,444 2,044 1,786 1,977 1,757 1,786
Plan 1,055 1,100 1,080 1,092 900 540 341 270 248 186 120 404 446
Actual 404 446 691 358 438 700 616 447 811 694 896 809 792
Plan 77.0% 74.0% 71.0% 73.0% 75.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0% 65.0%
Actual 68.5% 74.7% 72.2% 75.0% 70.4% 70.0% 70.2% 69.0% 68.0% 69.6% 69.0% 68.9% 62.9%
Note: Amber has been applied where performance is within 3% of Plan.
Cat A 8 Minutes 65%
Unscheduled Care Performance against Plan - Rolling 12 months to 30th November 2019
1 Hour Ambulance
Handover 0
4 Hour 95%
12 Hour 0
Unscheduled care
The end of November 4 hour combined ED and MIU performance delivered in accordance with our planned profile. The other key performance indicators for unscheduled
care did not deliver the revised planned position. The Cat A 8 minute response time dipped below the national 65% target for the first time this financial year.
Work continues to deliver the USC as outlined in Building Better Care and supported by the National ED Quality and Delivery Framework.
The bed reconfiguration for the Wrexham site have been completed and these together with the Gold Command did demonstrate initial improvement in performance on the
site. This included a reduction in the number of outliers, the level of escalation and the ED congestion. This hasn’t been fully sustained and further work is progressing to
ensure grip and control is in place. Gold command has been implemented in YGC and this is also showing early improvements with flow of patients being re-established. Work is being supported with a workforce review being undertaken through Kenall Bluck.,
Overall Summary .
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
8
Finance & Performance Committee Version
Integrated Quality and Performance ReportAP = Awaiting Profile November 2019
Annual Plan National
Profile Target
DFM072 Emergency Department 4 Hour Waits (inc MIU) 72.13% >= 72% >= 95%
DFM025 Delayed Transfers of Care (DToC): MH 16 <= 12 Reduce
DFM054 Diagnostic Waits: > 8 Weeks 2,233 AP 0
DFM063 Cancer: 31 Days (non USC Route) 99.5% >= 98% >= 98%
DFM055 Follow-up Waiting List Backlog 89,235 <= 81,890<= 74,555
Annual Plan National
Profile Target
DFM053 Referral to Treatment (RTT): > 36 Weeks 11,525 AP 0
DFM053 Referral to Treatment (RTT): < 26 Weeks 78.08% AP >= 95%
DFM070 Ambulance Response within 8 minutes 62.90% >= 65% >= 65%
DFM026 Delayed Transfers of Care (DToC): non-MH 105 <= 28 Reduce
LM002F Finance: Position against Financial Balance £27.1m <= £23.3m <= £25m
Improved
Of Most Concern
Measure Status
Measure StatusCode
Code
24
0
120
AllChapters
7
040
Unscheduled Care
70
2
0
Planned Care
6
04
0
Finance & Resources
40
2
0
Primary Care
0
5
10
15
20
25
30
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
All Measures RAG Timeline 2019/20 November 2019
Red Amber Green No Data
Chapter 1 – Summary .
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Planned Care 9
Finance & Performance Committee Version
Integrated Quality and Performance ReportAP = Awaiting Profile November 2019
7
02 0
Planned Care
4
0
10
RTT
10
1
0
Cancer 2 000
Other
0
2
4
6
8
10
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
Chapter 1 - Planned Care RAG Timeline 2019/20 November 2019
Red Amber Green No Data
Annual Plan National
Profile Target
DFM052 Referral to Treatment (RTT): < 26 Weeks 78.08% AP >= 95%
DFM053 Referral to Treatment (RTT): > 36 Weeks 11,525 AP 0
LM053a Referral to Treatment (RTT): > 52 Weeks 3,177 AP 0
DFM054 Diagnostic Waits: > 8 Weeks 2,233 AP 0
DFM055 Therapy Waits: <= 14 Weeks 0 0 0
DFM056 Follow-up Waiting List Backlog 89,235 <= 81,890<= 74,555
DFM057 Ophthalmolgy R1 64.01% AP >= 95%
DFM063 Cancer: 31 Days (non USC Route) 99.50% >= 98% >= 98%
DFM064 Cancer: 62 Days (USC Route) 82.90% >= 95% >= 95%
DFM065Cancer: 62 Day Single Pathway (inc
Suspensions)75.00% AP Improve
Measure StatusCode
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Referral to Treatment: Graphs 10
Finance & Performance Committee Version
Integrated Quality and Performance Report
Why we are where we are: The Board has observed significant reduction in additionality delivered internally through Waiting List Initiatives (WLI), it is mainly due to
changes in Her Majesty’s Revenue & Customs (HMRC) rules on personal pensions. This level of reduction in activity when compared like for like when compared against
2018/19 has caused an increase over 36 weeks backlog.
November 2019
-
-
-
Same
Period
Last Year
Apr-19 May-19 Jun-19
--AP024
7,886
DFM05
2
The percentage of patients waiting less
than 26 weeks for treatmentNov-19 78.08% 7th 84.05% 83.21% 82.22% 83.00%
DFM05
3
The number of patients waiting more than
36 weeks for treatmentNov-19
LM053aThe number of patients waiting more than
52 weeks for treatmentNov-19 3,177
11,5260
0
AP024
Code Measure Description
N/A
8,900 10,167 10,052
2,496 2,621 2,7302,540 2,5062,356
7th
Plan
Ref
National
TargetJul-19 Aug-19 Sep-19
82.00% 80.24% 79.94%
AP
AP 2,369
6,768 7,396
AP024
AP
Current
PeriodActual Status
Wales
Benchmark
>= 95%
6,932
Qtr 1
19/20
2,880 3,177 0 0 0
78.65% 78.08% 0.00%
10,768 11,526 0
Qtr 3
19/20
Qtr 4
19/20
0
Plan
TargetOct-19 Nov-19
Qtr 2
19/20
-
-
-
-
--
-
Jan-20 Feb-20 Mar-20
0.00% 0.00% 0.00%
Dec-19
0 0
0
70%
75%
80%
85%
90%
95%
100%
Nov-1
7
Dec-1
7
Ja
n-1
8
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-1
8
Ju
n-1
8
Ju
l-18
Au
g-1
8
Se
p-1
8
Oct-
18
Nov-1
8
Dec-1
8
Ja
n-1
9
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-1
9
Ju
n-1
9
Ju
l-19
Au
g-1
9
Se
p-1
9
Oct-
19
Nov-1
9
BCU Level - RTT Waits % <= 26 Weeks: November 2019
RTT 26W % Target Control Line Upper Control Limit Lower Control Limit
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Nov-1
7
Dec-1
7
Ja
n-1
8
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-1
8
Ju
n-1
8
Ju
l-1
8
Au
g-1
8
Se
p-1
8
Oct-
18
Nov-1
8
Dec-1
8
Ja
n-1
9
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-1
9
Ju
n-1
9
Ju
l-1
9
Au
g-1
9
Se
p-1
9
Oct-
19
Nov-1
9
BCU Level - RTT Waits Number > 36 Weeks: November 2019
RTT Over 36W Target Control Line Upper Control Limit Lower Control Limit
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Referral to Treatment: Narrative 11
Finance & Performance Committee Version
Integrated Quality and Performance Report
Actions Outcomes Timeline
1. Referral to Treatment (RTT) cross site validation of Stage 1 patients.Improved data quality. Reduction in Waiting List (WL)
by 5%31st December 2019
2. Development of weekly planned care dashboard
Operational tool in place to manage RTT performance
in real time. This is being used to drive weekly
management meetings.
30th January 2019
3. Outsourcing 750 Orthopaedics. All 750 transferred and progressing to
treatment. Reduce 750 backlog cohort in Orthopaedics 31st March 2020
4. Use of insource and outsource capacity Further 152 capacity in Orthopaedics, 890 in
Ophthalmology and 50 in Dental 31st January 2019
5. Improve scheduling based on clinical urgency and waiting time
chronology Reduction in RTT backlog 28th February 2020
6. Training: assessment of organisational knowledge and Mainstream RTT
training programme Training programme in place to support RTT rules 31st December 2019
7. Implementation of schemes to free up follow up capacity for services, e.g.
Supported Discharge, virtual results review clinics
• Virtual PROMs in Orthopaedics in place
• SoS (access as and when required by the patient)
in Rheumatology in the West
• FU backlog reduction by 15%
31st March 20120
8. External resource to validate Follow Up (FU) backlog FU backlog reduction by 15% 28th February 2020
November 2019
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Referral to Treatment: Narrative 12
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
The RTT total waiting list size is 4,274 greater in November 2019 than it was in November 2018. The rate of increase each month is rising from 0.8% increase between
April 2018 to April 2019 to the 4.35% increase seen comparing November to November positions
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Referral to Treatment: Projection 13
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,00029/0
4/2
019
06/0
5/2
019
13/0
5/2
019
20/0
5/2
019
27/0
5/2
019
03/0
6/2
019
10/0
6/2
019
17/0
6/2
019
24/0
6/2
019
01/0
7/2
019
08/0
7/2
019
15/0
7/2
019
22/0
7/2
019
29/0
7/2
019
05/0
8/2
019
12/0
8/2
019
19/0
8/2
019
26/0
8/2
019
02/0
9/2
019
09/0
9/2
019
16/0
9/2
019
23/0
9/2
019
30/0
9/2
019
07/1
0/2
019
14/1
0/2
019
21/1
0/2
019
28/1
0/2
019
04/1
1/2
019
11/1
1/2
019
18/1
1/2
019
25/1
1/2
019
02/1
2/2
019
09/1
2/2
019
16/1
2/2
019
23/1
2/2
019
30/1
2/2
019
31/1
2/2
019
Betsi Cadwaladr 36 Week Cohort Reduction ProjectionCohort Date: 31/12/2019 - Comparison to Same Quarter Last Year
All Specialties (All Stages)
Previous Year Cohort Volume Projection Actual Cohort Volume EoY Commitment
The overall growth in the waiting list is a function of the mismatch between demand and activity delivered month on month. This then contributes to the increase the volume
of the over 36 week cohort that needs to be treated.
The average number of over 36 week pathways closed in 2019/20 has increased to 1,950 per month (2018/19 average 1,763). This shows that on average 187 more long
waiting patients commence treatment each month, this shows evidence of treatment in turn.
Therefore a straight line forward projection to year end would suggest if activity in 2019/20 replicated that of 2018/19 the cohort could be reduced by c8,100. However given
constraints on activity experienced in 2019/20 it is unlikely that this level of activity can be replicated this year and so this level of cohort reduction is unlikely to be achieved
End of Year Commitment
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Cancer: Graphs 14
Finance & Performance Committee Version
Integrated Quality and Performance Report
80.00%
82.00%
84.00%
86.00%
88.00%
90.00%
92.00%
94.00%
96.00%
98.00%
100.00%
Oct
-17
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
BCU Level - Cancer Waiting Times - 31 Day - October 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
75.00%
80.00%
85.00%
90.00%
95.00%
100.00%
Oct
-17
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
BCU Level - Cancer Waiting Times - 62 Day from Receipt of Referral - October 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
Why we are where we are: In October the Health Board improved its performance and met the 31 day target; performance improved very slightly against the 62 target
with the main delays being due to delays to first appointment, in particular for breast and urology patients. In addition there were delays to major urology surgery cases.
November 2019
0.00% 0.00%
99.50% 0% 0% 0% 0% 0%
0.00%
75.00% 0.00% 0.00%
0.00% 0.00%3rd 85.80%
100%
83.23%
>= 98%
The percentage of patients newly
diagnosed with cancer, via the urgent
suspected cancer route, that started
definitive treatment within (up to &
including) 62 days of receipt of referral
Oct-19 82.90%
DFM06
399.50%
DFM06
4>= 95%
>= 98% Oct-19
>= 85%
Improve AP
5th
The percentage of patients newly
diagnosed with cancer, not via the urgent
route, that started definitive treatment within
(up to & including) 31 days of diagnosis
(regardless of referral route)
2nd75.00%
0.00% 0.00%
0.00%
98.33%
77.10%
98.40%
New 19/20
98.44%
81.55%
79.00%
81.05%
77.00% 76.00% 77.00%78.00%
82.90%
96.40%
84.88% 86.62% 82.60%
Oct-19DFM06
5
Percentage of patients starting first
definitive cancer treatment within 62 days
from point of suspicion
99.49% 98.15%
AP026
AP026
AP026 -
-
-
-
--
--
-
---
Jan-20 Feb-20 Mar-20Dec-19Qtr 3
19/20
Qtr 4
19/20
Plan
TargetOct-19 Nov-19
Qtr 2
19/20
Plan
Ref
National
TargetJul-19 Aug-19 Sep-19
Current
PeriodActual Status
Wales
Benchmark
Qtr 1
19/20Code Measure Description Apr-19 May-19 Jun-19
Same
Period
Last Year
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Cancer: Narrative 15
Finance & Performance Committee Version
Integrated Quality and Performance Report
Actions Outcomes Timeline
1. Prioritise endoscopy capacity for Urgent Suspected Cancer (USC) and other
clinically urgent patients; provide additional capacity via insourcing (contracts
agreed and to provide additional sessions from end November)
All USCs to be booked within 2 weeks 31st December 2019
2. Hold additional breast rapid access clinics; ensure patients offered transfer
to alternative site if shorter wait to ensure equalised waiting times; continue
recruitment process for consultant breast radiologists and consider insourcing
option
All USCs to be seen within 3 weeks 31st December 2019
3. Agree urology surgery capacity plan for major surgery and to recover urology
haematuria clinic waiting times position
All surgery within 31 days of decision to treat
All USCs to be seen within 3 weeks31st January 2020
4. Track all patients on a USC pathway in order to ensure all delays are
escalated and remedial action taken as appropriate
Continuation of backlog reduction to under 75
Improve 62 day performance to 90%31st December 2019
5. Appoint tracking staff to ensure all patients tracked from point of suspicion Improved single cancer pathway performance 31st January 2020
November 2019
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Diagnostic Waits: Graphs 16
Finance & Performance Committee Version
Integrated Quality and Performance Report
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
4,500
Nov-1
7
Dec-1
7
Ja
n-1
8
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-1
8
Ju
n-1
8
Ju
l-1
8
Au
g-1
8
Se
p-1
8
Oct-
18
Nov-1
8
Dec-1
8
Ja
n-1
9
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-1
9
Ju
n-1
9
Ju
l-1
9
Au
g-1
9
Se
p-1
9
Oct-
19
Nov-1
9
BCU Level - Diagnostic Waits Number of Breaches: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
Why we are where we are:
Endoscopy: Lack of sufficient capacity mainly in WMH continued to be challenging in managing increase in demand. There has also been severe delays in implementation
of solutions; such as Vanguard due to issue with water testing. Further increase in capacity has been arranged through numbers of insourcing options, this capacity has
come on line during December and should create 27 additional lists per week.
Radiology: Insufficient capacity for CT, MRI and US to meet underlying demand growth pressures. Insourcing capacity is secured to address majority of capacity gap, but
some constraints remain around cardiac and breast sub speciality capacity. Locum and substantive recruitment attempts have not been successful to date.
November 2019
Same
Period
Last Year
Apr-19 May-19 Jun-19Qtr 2
19/20
Qtr 1
19/20Code Measure Description
Qtr 4
19/20
Plan
Target
Plan
Ref
National
TargetJul-19 Aug-19 Sep-19
Current
PeriodActual Status
Wales
BenchmarkOct-19 Nov-19 Dec-19
Qtr 3
19/20Jan-20 Feb-20 Mar-20
- --AP024 DFM05
4
The number of patients waiting more than
8 weeks for a specified diagnosticNov-19 7th2,233 2,548 2,793 2,9572,857 2,8271,275 2,443 2,233AP0 -0 02,816 00
0
500
1,000
1,500
2,000
2,500
3,000
3,500
Oct-
17
Nov-1
7
Dec-1
7
Ja
n-1
8
Fe
b-1
8
Ma
r-1
8
Ap
r-1
8
Ma
y-18
Ju
n-1
8
Ju
l-1
8
Au
g-1
8
Se
p-1
8
Oct-
18
Nov-1
8
Dec-1
8
Ja
n-1
9
Fe
b-1
9
Ma
r-1
9
Ap
r-1
9
Ma
y-19
Ju
n-1
9
Ju
l-1
9
Au
g-1
9
Se
p-1
9
Oct-
19
BCU DIagnostics - Number of Breaches over 8 WeeksOctober 2017 to October 2019 by Service
Cardiology Total Diagnostic Endoscopy Total Imaging Total
Physiological Measurement Total Radiology - Consultant referral Total Radiology - GP referral Total
Neurophysiology Total Grand Total
Chapter 1 – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Diagnostic Waits: Narrative 17
Finance & Performance Committee Version
Integrated Quality and Performance Report
Actions Outcomes Timeline
Endoscopy
1. Improve scheduling based on clinical urgency and waiting
time chronology Reduction in routine >8 weeks and Surveillance backlog 31st December
2. Insourcing solutions for all three sitesAdditional capacity to reduce routine >8 weeks and Surveillance backlog.
This is now in place from 02/12/201931st December
3. Recruitment of Gastroenterology locum consultant in West.
This is now in place and started demonstrating an improved
position.
127 additional capacity a month 31st October
4. Complete specialty level Demand &Capacity (D&C) to
identify sustainable gap as well as gap for backlog clearance
Site level D&C by modality in place. The first draft has been completed by
information. Awaiting sign off 31st December 2019
5. Pooling of Surveillance patients from East to West and
Centre
Reduction in Surveillance Backlog in East. This is in place. The Vanguard
Capacity in Ysbyty Glan Clwyd (YGC) is being used for Wrexham Maelor
Hospital WMH) patients.
31st December
Radiology
1. Continue with insourcing through framework contract within
available resources
Maintain capacity for Computerised Tomography (CT), Magnetic Resonance
Imaging (MRI) and US scanning31st December
2. Secure contract and resource for consultant mammographer
Ultra Sound (US) sessions in YGCAdditional breast US capacity
31st December- continuing to
31st March 2020
3. Completion of Kendall-Bluck Review of radiology services Inform the basis for proposal for sustainable radiology services 16th December
4. Completion of proposals for sustainable radiology service Develop sustainable staffing/activity model 28th February 2020
November 2019
Chapter 3a – Planned Care.
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Follow Up Waiting List Graphs 18
Finance & Performance Committee Version
Integrated Quality and Performance Report
Why we are where we are: Data quality issue related to WPAS (Wales Patient Administration System) implementation and ongoing shortfall in capacity to manage patient
pathways in Referral to Treatment (RTT), Urgent Suspected Cancer (USC) and Follow Up (FU). There was also delay in implementing Patient Reported Outcome Measures
(PROMs) FU in orthopaedics as well as external support for FU validation. This has now been in place and mobilisation plan is being worked through.
010,00020,00030,00040,00050,00060,00070,00080,00090,000
100,000110,000
Oct-
17
Nov-1
7
Dec-1
7
Ja
n-1
8
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-1
8
Ju
n-1
8
Ju
l-1
8
Au
g-1
8
Se
p-1
8
Oct-
18
Nov-1
8
Dec-1
8
Ja
n-1
9
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-1
9
Ju
n-1
9
Ju
l-1
9
Au
g-1
9
Se
p-1
9
Oct-
19
BCU Level - Number of Follow Up Backlog: October 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
November 2019
Same
Period
Last Year
Apr-19 May-19 Jun-19Qtr 2
19/20
Qtr 1
19/20Code Measure Description
Qtr 4
19/20
Plan
Target
Plan
Ref
National
TargetJul-19 Aug-19 Sep-19
Current
PeriodActual Status
Wales
BenchmarkOct-19 Nov-19 Dec-19
Qtr 3
19/20Jan-20 Feb-20 Mar-20
- ---AP024 80,712<= 81,890
The number of patients waiting for an
outpatient follow-up (booked and not
booked) who are delayed past their agreed
target date for planned care specialities
Nov-19 89,235 DFM05
6<= 74,555 88,2107th 88,079 88,511 88,648 92,067 90,569 89,909 89,235 0 0 0 0
Chapter 3a – Planned Care.
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Follow Up Waiting List - Narrative 19
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline
1. Stable Glaucoma Monitoring via Virtual Clinics and Cataract Direct to Listing
Pathway redesign
15% reduction on Follow Up (FU) 100% overdue
backlog ( note 18.6% reduction has been achieved
by end of November and therefore on course to
deliver year end target)
28th February 2020
2. Cross site validation of all stage 1 patients – validation team commenced
during December
Improved data quality. Reduction in Waiting List
(WL) by 5%30th December 2019
3. Training: assessment of organisational knowledge and Mainstream Referral
to Treatment (RTT) training programme Training programme in place to support RTT rules 31st December 2019
4. Implementation of schemes to free up follow up capacity for services, e.g.
Supported Discharge, virtual results review clinics
• Virtual Patient Reported Outcome Measures
(PROMs) in Orthopaedics in place
• SoS (Service access as required by patient) in
Rheumatology in the West
• FU backlog reduction by 15%
31st March 2020
5. External resource to validate FU backlog – Validation provider commenced in
November 2019FU backlog reduction by 15% 28th February 2020
Chapter 3a – Planned Care.
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Eye Care Measure 20
Finance & Performance Committee Version
Integrated Quality and Performance Report
Actions Outcomes Timeline
1. Appointment of Assistant
Business AnalystAssistant Business Analyst recruited by informatics who will support the Eye Care Measures Programme 2-3 days per week. January 2020
2. Light Touch Tender for
Community Optometry Ophthalmic
Diagnostic & Treatment Centres
(ODTCs)
Overarching Specification agreed for Community Optometry ODTCs, also detailed specification for referral refinement service and
management of stable glaucoma supported by clinical governance case reviews with Consultant Ophthalmologists. Tender published
3rd December. Selection 2nd January and clarification interviews 9/10 January 2020. ODTCs appointed by 10th January 2020.
Dependent upon funding being secured.
January 2020
3. Glaucoma working parties
established in East and West HES
sites; and in Central by end
December.
Glaucoma working parties include community optometrist and will undertake clinical validation of the Glaucoma outpatient waiting list
backlog. Reviewing patients who may be suitable for community Optometrist support or self management. All sites are arranging
additional clinics to review and reduce the backlog waiting list commencing with the longest waiting R1 patients. Clinics will run
December 2019 – March 2020
December 2019
– March 2020
4. Eye image data sharing
between Community ODTCs and
HES
Dicom pilot (system for capturing and transferring High Definition images) successful and Ophthalmologists happy with the quality of
images transmitted. Feedback to Welsh Government Digitalisation Programme Manager. Next steps being explored. If feasible this will
make a step change in shared care working and virtual patient review by HES
March 2020
5. Presentation to Cross Party
Group on Vision
Director of Performance presented to the Cross Party Group on Vison on the transformation plan for N Wales Eye Care and the
spending plans for the non recurrent revenue funding for reducing the backlog outpatient waiting list; the eye care measures
transformation fund and the sustainable business case for Integrated Medium Term Plan (IMTP) support.
12th November
2019
6. Cataract Pathway The cataract pathway has now been embedded as a direct referral service from optometrists thus reducing outpatient attendances.30th November
2019
November 2019
Same
Period
Last Year
Apr-19 May-19 Jun-19Qtr 2
19/20
Qtr 1
19/20Code Measure Description
Qtr 4
19/20
Plan
Target
Plan
Ref
National
TargetJul-19 Aug-19 Sep-19
Current
PeriodActual Status
Wales
BenchmarkOct-19 Nov-19 Dec-19
Qtr 3
19/20Jan-20 Feb-20 Mar-20
- - ----AP022 63.07%New 19/20AP Nov-19 64.01%
95% of opthalmology R1 patients who are
waiting within their clinical target date or
within 25% in excess of their clinical target
date for care or treatments
DFM05
7>= 95% -7th 63.40% 65.00% 64.01% 0.00% 0.00% 0.00% 0.00%64.30%
Chapter 3a –Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Internal BCU Activity v Plan 21
Finance & Performance Committee Version
Integrated Quality and Performance Report
This table shows all internal delivered activity in the categories and so includes activity delivered by non-medical staff in clinic setting. This activity includes activity that is
undertaken without being on an elective waiting list and so does not match to the high level RTT monitoring report. For instance within outpatients new attendances include
patients for whom an appointment is arranged on the day by the GP ( known as walk-in patients). This activity is included in the above data but is not waiting list activity
and is not included in the planned capacity to deliver RTT new outpatient requirements.
November 2019
Plan Actual Diff % Diff Plan Actual Diff % Diff Plan Actual Diff % Diff Plan Actual Diff % Diff
Emergency Inpatients 17,805 18,272 467 3% 21,758 23,296 1,538 7% 24,800 24,830 30 0% 64,363 66,398 2,035 3%
Elective Daycases 7,469 7,789 320 4% 8,472 9,698 1,226 14% 5,630 4,552 -1,078 -19% 21,570 22,039 469 2%
Elective Inpatients 3,866 3,737 -129 -3% 2,763 3,605 842 30% 2,847 3,060 213 7% 9,477 10,402 925 10%
Endoscopies 4,302 7,482 3,180 74% 2,397 2,452 55 2% 3,894 3,618 -276 -7% 10,593 13,552 2,959 28%
MOPS (Cleansed DC) 790 840 50 6% 650 311 -339 -52% 217 230 13 6% 1,657 1,381 -276 -17%
Regular Day Attenders 6,952 7,065 113 2% 10,988 10,735 -253 -2% 14,564 12,880 -1,684 -12% 32,504 30,680 -1,824 -6%
Well Baby 1,238 1,143 -95 -8% 1,064 992 -72 -7% 1,298 1,307 9 1% 3,600 3,442 -158 -4%
New Outpatients 48,009 50,093 2,084 4% 69,008 68,028 -980 -1% 61,917 64,784 2,867 5% 178,934 182,905 3,971 2%
Review Outpatients 96,991 97,127 136 0% 117,352 119,799 2,447 2% 143,038 147,889 4,851 3% 357,381 364,815 7,434 2%
Pre-Op Assessment 6,523 6,327 -196 -3% 6,862 6,581 -281 -4% 9,387 8,952 -435 -5% 22,772 21,860 -912 -4%
New ED Attendances 50,799 53,718 2,919 6% 62,407 63,164 757 1% 45,233 45,055 -178 0% 158,439 161,937 3,498 2%
Review ED Attendances 665 697 32 5% 923 929 6 1% 2,925 2,788 -137 -5% 4,513 4,414 -99 -2%
Grand Total 245,409 254,290 8,881 4% 304,644 309,590 4,946 2% 315,750 319,945 4,195 1% 865,803 883,825 18,022 2%
Please note : East's, Nephrology, Regular Day Attenders figures are obtained from a manual source and are one month in arrears - November 2019 activity is missing from the above figures.
BCU Activity versus Plan 2019/20 Year to Date - 30th November 2019
West Central East BCU Total
Chapter 3a – Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
External Contracted Activity
Key Providers 22
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
*All data relates to the period April to October 2019 for outpatient activity.
Plan Actual Plan Actual Plan Actual Plan Actual
Countess of Chester NHS Foundation Trust Oct 4,286 3,812 4,253 4,010 11,778 10,243 26,232 25,047
Robert Jones & Agnes Hunt NHS Foundation Trust Oct 1,518 1,421 22 26 3,907 3,998 10,525 10,113
Hywel Dda LHB Oct 586 685 617 602 707 745 1,403 1,522
Royal Liverpool and Broadgreen University Hospitals NHS Trust Sep 586 528 94 89 838 798 3,297 3,255
Wirral University Teaching Hospital NHS Trust Oct 535 387 111 103 272 264 891 905
Shrewsbury & Telford Hospitals NHS Trust Oct 109 95 84 82 1,032 912 1,244 1,081
Aintree University Hospital NHS Foundation TrustIP - Sep
OP - Oct220 231 57 43 406 358 1,188 1,126
The Clatterbridge Cancer Centre NHS Foundation TrustIP - Sep
OP - Oct114 180 25 18 202 195 4,489 4,663
University Hospital of North Midlands NHS Trust Oct 40 41 137 171 215 286 302 328
University Hospital of South Manchester NHS Trust
Liverpool Women's NHS Foundation Trust Oct 24 21 63 60 278 337 740 820
Shropshire Community Health NHS Trust Oct 7 0 23 11 13 7
Activity up to
and including:*
New Outpatient
Emergency
Inpatient (inc.
Maternity)
Elective Inpatient &
Daycase (inc.
Endoscopy)
Follow Up
Outpatient Provider
Chapter 3a –Planned Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
RTT Core Activity v Plan 23
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Summary: Internal Delivery of core activity aligned to the declared internal capacity is shown above.
The three site access meetings have been strengthened with the site directors expected to chair these
weekly meetings of activity delivered and scheduled in accordance with the plan. Additional support has
been requested from the DU to aid the development of this approach on the Wrexham site. The fortnightly
Access meetings will be chaired by the Interim Assistant Director for planned care and the Director of
Performance to increase the level of confirm and challenge and ensure that Pan BCU capacity utilisation can
be improved.
Work is underway to develop the provider site activity plans for 2020/21 with commissioner based challenge
expected to take place within the next month. These are aimed to test the operational thinking and support
development of sustainable service plans aligned to clinical pathway re-design.
*Ophthalmology data is
excluded while work
concludes on reconciling data
from YG.
RTT Core Activity V Plan - 1st April 2019 to 8th December 2019
General Surgery 12,428 13,223 795
Urology 5,240 4,437 -803
Trauma & Orthopaedics 8,823 7,117 -1,706
ENT 9,651 9,607 -44
Maxillo-Facial Surgery 4,057 3,890 -167
Restorative Dentistry 228 145 -83
Orthodontics 818 560 -258
Pain Management 1,338 967 -371
General Medicine 882 1,435 553
Gastroenterology 3,004 3,595 591
Endocrinology 1,543 1,577 34
Cardiology 5,118 5,685 567
Dermatology 7,107 7,962 855
Respiratory Medicine 2,087 2,374 287
Nephrology 815 717 -98
Rheumatology 2,066 1,263 -803
Paediatrics 5,788 6,133 345
Geriatric Medicine 2,355 1,614 -741
Gynaecology 6,333 6,083 -250
Child & Adolescent Psychiatry 4,909 4,909 0
Total 79,680 78,384 -1,296
Stage 1 (New Outpatient) Core Activity Against Plan
Difference
from Plan
Actual
YTD
Plan
YTDSpecialty
General Surgery 3,937 3,913
Urology 2,171 2,122
Trauma & Orthopaedics 3,734 3,944
ENT 2,160 2,258
Maxillo-Facial Surgery 1,011 911
Pain Management 475 597
Gynaecology 1,648 1,642
Total 15,136 15,387
Stage 4 (inpatient / Daycase) Core Activity Against Plan
Specialty
RTT
Admissions
Achieved
Plan
YTD
Chapter 3a – Planned Care.
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
RTT additional activity
and cost Summary totals24
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Summary: The total resource claimed against RTT funding in 2019/20 amounts to £8.99m at the end
of month 8. This resource has delivered 5,029 outpatients, 6,365 diagnostic and follow up
appointments and 2,222 in-patient or day case treatments.
It is noted that not all additional outpatient or diagnostics appointments will have resulted in
commencement of treatment. Patients treatment can commence in outpatients or via a procedure
being undertaken and so it is normal for patients to convert from one stage on their pathway prior to
treatment commencing.
General Surgery
Urology
Orthopaedics
ENT
Ophthalmology
Max Fax / Oral Surgery
Cardiology
Dermatololgy
Gastro
Endoscopy
Pain
Total Activity
General Surgery
Urology
Orthopaedics
ENT
Ophthalmology
Max Fax / Oral Surgery
Cardiology
Dermatology
Gastro
Endoscopy
Pain
Total Spend
0 0
Cost
Activity
RTT Additional Activty and Cost per Stage - April to November 2019
£565,555 £2,343,419 £4,060,789
Specialty
£0 £2,279,273 £0
£0 £0 £6,782
£0 £0 £113
£221,690 £0 £0
£29,532 £0 £120,189
£0 £13,993 £0
£38,000 £0 £166,980
£188,950 £0 £457,525
£57,461 £42,176 £596,485
£1,034 £0 £2,394,103
5029 6,365 2,222
£318,613£7,977£28,889
32 5,829 0
0 0 20
0
1459 0 0
347 0 114
0 144 0
Stage 4Stages 2&3Stage 1
24042274
IP & DCInvestigations etc.New OPD
620 350 232
11 0 655
419 0 200
1867 0 760
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 FYTD
Validation (YGC) £7,249 £7,249 £7,249 £7,249 £7,249 £7,249 £43,494
Gastro Vanguard £0 £7,227 £0 £0 £0 £0 £7,227
Other Diagnostics (Pathology / Radiology) £180,200 £227,599 £177,522 £233,019 £228,718 £238,516 £235,419 £242,125 £1,763,118
Physio £132,806 £132,806
Optometry £16,493 £40,174 £56,667
Dietetics £3,781 -£3,781 £0
Transport £3,846 £1,942 £4,471 £2,000 £6,000 £18,259
Total £187,449 £258,568 £361,532 £240,333 £237,909 £250,236 £237,419 £248,125 £2,021,571
M01 M02 M03 M04 M05 M06 M07 M08
£'000 £'000 £'000 £'000 £'000 £'000 £'000 £'000
YG 416 466 425 342 333 238 376 395 2,990
YGC 220 265 340 234 461 254 272 183 2,228
YMW 133 122 37 76 21 72 95 110 666
North Wales 180 228 178 233 229 239 235 241 1,763
Area - 17 176 -4 189
Outsource 141 118 165 68 101 72 169 321 1,155
Total 1,090 1,216 1,321 949 1,144 874 1,147 1,250 8,990
Hospital /
SiteTOTAL
Chapter 2 – Summary .
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Unscheduled Care 25
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
00
1
0
Other
7
04
0
Unscheduled Care
2
00
DToC
2
02
0
Stroke Care
30
1
0
ED & Ambulance
Annual Plan National
Profile Target
DFM066 Stroke Care: Admission within 4 Hours 50.00% >= 50% >= 55.5%
DFM067 Stroke Care: Review by consultant 24 Hours 82.60% >= 85% >= 84%
DFM068 Stroke Care: Access to Speech Therapy 54% AP Improve
DFM069 Stroke Care: 6 Month Follow up Assessment 22.30% N/A AP Improve
DFM070 Ambulance Response within 8 minutes 62.90% >= 65% >= 65%
DFM071 Ambulance Handovers within 1 Hour 792 <= 404 0
DFM072 Emergency Department 4 Hour Waits (inc MIU) 72.13% >= 72% >= 95%
DFM073 Emergency Department 12 Hour Waits 1,786 <= 1,320 0
DFM074 Hip Fracture Survival 30 days 84.80% AP Improve
DFM025 Delayed Transfers of Care (DToC): MH 16 <= 12 Reduce
DFM026 Delayed Transfers of Care (DToC): non-MH 105 <= 28 Reduce
StatusMeasureCode
0
2
4
6
8
10
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
Chapter 2 - Unscheduled Care RAG Timeline 2019/20 November 2019
Red Amber Green No Data
Please note: Timeline graphs based on when Out of Hours was under
Unscheduled Care Chapter. Will be reviewed for next month.
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Stroke Care: Graphs 26
Finance & Performance Committee Version
Integrated Quality and Performance Report
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
BCU Level - Stroke Care - Admissions within 4 Hours: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
BCU Level - Stroke Care - Consultant Assessd within 24 Hours: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
November 2019
-
-
-
-
0.00%
75.90% 85.70%
22.30%
-
-
-
0.00%
-
-
-
0.00%
-
-
-
Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20
Qtr 4
19/20
AP038
AP038
AP038
AP038 53.20% 0.00%
Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20Apr-19
79.80%
Plan
Ref
Plan
Target
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
1st 41.70%
-
0.00%
65.00% 70.00% 69.00%
-
May-19
70.00%
0.00%
- - -
55.00% 69.00% 56.00%
Feb-20 Mar-20
0.00% 0.00%
-
82.83%
- -
Jun-19
-
80.40% 81.00% 88.00%
25.70%
N/A
Improve
Qtr 1
19/20
5th
N/A
Code Measure DescriptionNational
Target
2nd
82.60%
Nov-19
Improve
Percentage of stroke patients receiving the
required minutes for speech and language
therapy
DFM06
7
Percentage of patients who are assessed
by a stroke specialist consultant physician
within 24 hours of the patient's clock start
time
>= 84%
>= 55.5%
>= 85%
>= 50%
Nov-19
DFM06
853.90%
22.30%DFM06
9
Percentage of stroke patients who receive
a 6 month follow up assessment
DFM06
6
Percentage of patients who are diagnosed
with a stroke who have a direct admission
to an acute stroke unit within 4 hours of the
patient's clock start time
Nov-19 50.00%
62.30% 59.00% 56.70% 53.90% 0.00% 0.00%
82.60% 0.00% 0.00%
50.00% 0.00% 0.00%
82.10%
- - -
0.00%
59.30% 61.40% 51.20%
AP
AP
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Stroke Care - Narrative 27
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Why we are where we are and outcomes of the recent National Stroke Audit
DFM066 Admission to Stroke Unit within 4 Hours: Performance to the Acute Stroke Unit (ASUs) has seen a dip in month in Wrexham and significantly in Ysbyty Glan
Clwyd (YGC) with Ysbyty Gwynedd (YG) showing slight improvement. The deterioration in Wrexham is aligned to the sickness in the Stroke Coordinator Team, with just
one available in November. Additionally Unscheduled Care pressures have resulted in the ring fenced beds being used for non stroke patients more frequently, resulting in
Breaches on the clinical standard. In YGC, it is the Unscheduled Care pressures, with the impact on the ring fenced beds as in Wrexham.
DFM067 Assessment by a Stroke Specialist Consultant in 24 hours has seen a minor deterioration overall in BCU with YG having an 8% deterioration, YGC static and
Wrexham 3% improvement. As always, this relates to weekend assessments and depends on whether the Stroke Consultants are On Call for General Medicine at their
Site over a weekend and will then do the assessment. If they are not On Call then the standard is breached for anyone who is admitted from a Friday evening to late on
Sunday
DFM068 The % of patients receiving the required Minutes for Speech and Language Therapy data for November is not available. For October, BCU position was 2%
worse than September 2019. There was an improvement in East, but deterioration in West and Centre. Both of these were due to staffing issues in month
DFM069 The % of patient who receive six month reviews: current data is not available
The Organisational Audit was conducted on the 3rd June 2019. The recently received results are currently being analysed by Sites and show the following levels of
performance out of 10 : YG -6, YGC -4, Wrexham -3. YG has achieved the highest audit score across Wales. The quarterly Sentinel Stroke National Audit Programme
(SSNAP) scores for July-September 2019 show that YG and YGC have retained their levels as C and B respectively whereas Wrexham has improved to achieve a B
score.
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Stroke Care - Narrative 28
Finance & Performance Committee Version
Integrated Quality and Performance Report
Actions Outcomes Timeline
1. Continue to highlight need to retain 2 ring fenced beds at Safety Huddles/bed meetings and
with Site Management Teams. All wards to agree list of patients at daily Board rounds appropriate
to out-lie if required to create Stroke beds and Ward Sisters/Matron/Stroke Coordinators/Ops
Teams to focus on ensuring beds available. Awareness sessions in Emergency Department (ED)
to continue to highlight need for early referral to Stroke Team
Improved compliance against the 4 hour
Standard and the Sentinel Stroke National
Audit Programme (SSNAP) Scores
Immediate with daily Safely
Huddles and bed meetings.
ED awareness ongoing
month on month.
2. Options paper for implementation of virtual weekend ward rounds has been submitted to
Secondary Care and Area Teams for discussion but this is not achievable without an increase in
the number of Consultants on the Stroke Out of Hours (OOH) rota and an adjustment to their
commitment to the General Internal Medicine (GIM) On Call rotas. Adjustment has been made in
East but not agreed in West and Centre. Remote access for reviewing of patients and images
from home is now being funded by Area Teams
Greater compliance with the Standard if
adjustments made to GIM rotas and remote
access in place. Without agreement, rota is
not sustainable. Short Term agreement for
October rota but there will be no or
significantly reduced OOH Service from
November unless solution is reached
Options paper submitted,
discussions continue in
September.
3. Deep dive of Speech & Language Therapy (SALT) performance for East in September and
October 2019 has been done. Comparison of staffing and processes across BCU September and
investigating possibility of independent review of processes in North Wales. Meeting in December
2019 to ensure parity in application of Eligibility. Delivery Unit (DU) undertaking mapping review of
Therapy Standards, date awaited.
Understanding of reasons for low
performance in East and options for
improvement. Parity of Eligibility.
December 2019
4. Additional clinics that were due to be run from September in East to support clearance of
backlog which was due to vacancies have not happened due to sickness. Stroke Association have
undertaken additional weekly clinic to support from September for 3 months and then review if
need to extend. Stroke Association are now working to same model in West and Centre
supporting the reviews as in East
Reduction in backlog and greater compliance
with standard
Additional clinics from
September. In East
Process review for West
and Centre in September
November 2019
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
ED & MIU 4Hour Waits: Graphs 29
Finance & Performance Committee Version
Integrated Quality and Performance Report
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
West - Emergency Department (inc MIU) 4 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Nov-1
7
Dec-1
7
Ja
n-1
8
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-1
8
Ju
n-1
8
Ju
l-1
8
Au
g-1
8
Se
p-1
8
Oct-
18
Nov-1
8
Dec-1
8
Ja
n-1
9
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-1
9
Ju
n-1
9
Ju
l-1
9
Au
g-1
9
Se
p-1
9
Oct-
19
Nov-1
9
Central - Emergency Department (inc MIU) 4 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
East - Emergency Department (inc MIU) 4 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
November 2019
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
BCU Level - Emergency Department (inc MIU) 4 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
Code Measure DescriptionNational
TargetJun-19 Feb-20 Mar-20May-19
Plan
Ref
Plan
Target
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20Qtr 4
19/20
Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20
- - -AP033 69.44% 0.00% 0.00%71.53%>= 72% 5thDFM07
2
The percentage of patients who spend
less than 4 hours in all major and minor
emergency care (i.e. A&E) facilities from
arrival until admission, transfer or
discharge BCU
Nov-19 72.13% -71.21% 71.38% 73.72% 73.04% 71.63% 71.15% 72.13% 0.00% 0.00%>= 95%
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
ED & MIU 4Hour Waits: Narrative 30
November 2019
Actions Outcomes TimelineYSBYTY GWYNEDD
• Increased senior clinical presence in Emergency department during the out of hours period
continues as staffing allows• Reduce Emergency department 4 hour breaches attributed to doctor waits to a maximum
of 20 per day
31st March
2020
• 2 hour Safety huddle in Emergency department embedded with increase to hourly during peak
demand.
• Information support to validate left without being seen as impacting on over reporting of 4 hour
breach numbers
• Reduce non-admitted breaches to a maximum of 15 per day to increase non-admitted
performance to 90%
• Information Technology (IT) issues now resolved regarding data capture of Left
Emergency Department Without Being Seen (LEDWBS) onto PiMS/IRIS. Retrospective
cleansing of the data from September currently underway. Assurance from the Informatics
team that the data for December will be accurate at time of reporting.
31st
December
2019
• Emergency department observation unit staffed 7 days per week from 18.11.19, with increased bed
numbers and ability to flex in times of demand.
• Interim HoN EC post appointed to with ability for immediate start, this coupled with the start of the
newly appointed Clinical Director will support the Directorate to make rapid improvements
• ICAN/Red Cross and fit to sit, and a dedicated area for the 9th CRT will be incorporated into the front
door footprint and operational by 16th December 2019.
• Reduce admitted breaches to a maximum of 18 per day (compared to current 20 per day)
• Implement and embed an admission avoidance culture within the new front door facility
31st
December
2019
YSBYTY GLAN CLWYD
The review of the ward administrator role has been undertaken with changes agreed to hours of work,
and redistribution of some tasks. This will enable an increased focus upon:
• Ensuring treatment plans are completed within the first 2 hours
• Ensuring that any decision to admit or discharge are made within the first 3 hours.
• Non-admitted performance
Increased grip and control leading to improvements in non-admitted performance up to 80%.
Paediatric breaches reducing to 1 or 2 per day, working towards an ultimate goal of being a
never event.
31st
December
2019The design phase of the protected minors work is close to completion with agreement on the model
and cohorting of patients. This will include
• Identified teams for minors, majors, resus and START.
• Allocated resource to paediatrics in out of hours period
WREXHAM MAELOR
• Streamline the paediatric pathway in ED including directing to ward for PAU care • Reduce paediatric breaches to 3 maximum per day (allowing for clinical exceptions)
31st
December
2019
• Embed ED escalation process including the 2 hourly safety huddle with clear actions for the day
working within the 4 hour standard
• Reduced non-admitted breaches by 50% (maximum 15 a day) to increase non-admitted
performance to 85%
31st
January
2020
• Use Clinical Decisions Unit for ED patients only
• Reduced non-admitted breaches by 50% (maximum 15 a day) to increase non-admitted
performance to 85%
• Improved patient experience and outcome
31st
December
2019
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
ED 12 Hour Breaches: Graphs 31
Finance & Performance Committee Version
Integrated Quality and Performance Report
0250500750
1,0001,2501,5001,7502,0002,2502,5002,7503,000
Nov
-17
Dec
-17
Jan-
18
Feb-
18
Mar
-18
Apr
-18
May
-18
Jun-
18
Jul-1
8
Aug
-18
Sep
-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Feb-
19
Mar
-19
Apr
-19
May
-19
Jun-
19
Jul-1
9
Aug
-19
Sep
-19
Oct
-19
Nov
-19
BCU Level - Emergency Department 12 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
100
200
300
400
500
600
700
Nov
-17
Dec
-17
Jan-
18
Feb-
18
Mar
-18
Apr
-18
May
-18
Jun-
18
Jul-1
8
Aug
-18
Sep
-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Feb-
19
Mar
-19
Apr
-19
May
-19
Jun-
19
Jul-1
9
Aug
-19
Sep
-19
Oct
-19
Nov
-19
West - Emergency Department 12 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
100
200
300
400
500
600
700
800
900
1,000
1,100
Nov
-17
Dec
-17
Jan-
18
Feb-
18
Mar
-18
Apr
-18
May
-18
Jun-
18
Jul-1
8
Aug
-18
Sep
-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Feb-
19
Mar
-19
Apr
-19
May
-19
Jun-
19
Jul-1
9
Aug
-19
Sep
-19
Oct
-19
Nov
-19
Central - Emergency Department 12 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
100
200
300
400
500
600
700
800
900
1,000
1,100
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
East - Emergency Department 12 Hour Waits: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
November 2019
Code Measure DescriptionNational
TargetJun-19 Feb-20 Mar-20May-19
Plan
Ref
Plan
Target
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20Qtr 4
19/20
Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20
- 1,708 1,977 - -DFM07
3
The number of patients who spend 12
hours or more in all hospital major and
minor care facilities from arrival until
admission, transfer or discharge BCU
1,743 0- 01,5941,405<= 1,320 7thAP037 Nov-19 1,786 1,445 2,044 1,757 1,786 0 00
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
ED 12 Hour Breaches: Narrative 32
Actions Outcomes TimelineYSBYTY GWYNEDD
• Introduction of outlier clinical management team for cohort ward to support timely senior decision
making .
• Support deliver of maximum 6 > 12 hour breaches per day
• Increased number of morning discharges from wards improving flow from
Emergency department and Acute medical admissions unit
31st December 2019
• Full implementation of community length of stay reduction model (Tuag Adref) • Reduce number of Medically fit for discharge in Ysbyty Gwynedd by 50%31st December 2019
• Increased Emergency department nurse in charge attendance at site mini-huddles throughout the
day
• Joint secondary care and area review of unscheduled care escalation procedures 6.12.19
• Increase capacity of the Tuag Adref team to include staffing linked to the 9th CRT
• Reduction in > 12 hour Emergency department breaches through improved
escalation process
• Increase the number of patients discharged from the front door
31st December 2019
YSBYTY GLAN CLWYD
The site wide escalation framework is operational. This includes:
• Escalation triggers and actions for ED
• Escalation actions for medicine in support of ED and flow
• Escalation actions for surgical directorate in support of ED and flow
Clearer processes for escalation and de-escalation, with ED being the final point
of escalation as opposed to the first.9th December 2019
Work on ‘queueing out’ of EQ via an area in Recovery 1 is progressing. Current challenges being
worked upon include
• Design work and build of the toilet facility
• Staffing model required
Decompression of ED, with 9 moves out of EQ by 9am each morning31st December 2019
There is a refreshed focus upon Board Rounds with members of the HMT attending to offer support
and constructive feedback on how they can all be delivered to the same standard.
Increased compliance with PDD with 90% of patients expected to have one set
within 24hrs of admission. Earlier discharge in line with SAFER principles
leading to 30% of discharges happening before midday.
31st January 2020
WREXHAM MAELOR
• Embed the Acute Floor care model principles • Reduced 12 hour breaches31st December 2019
• Improve the site function and management through Head of Site leadership • Improved patient flows reducing outlying, escalation and 12 hour waits31st December 2019
• Improve ward discharge management including golden patients identified the day before• Improved flow by 08:30 with minimum of 8 beds freed and 45% discharged by
10:30 and 55% by 12:30
31st January 2020
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Ambulance Handovers: Graphs 33
Finance & Performance Committee Version
Integrated Quality and Performance Report
0
250
500
750
1,000
1,250
1,500
1,750
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
BCU Level - Ambulance Handovers over 1 Hour: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
100
200
300
400
500
600
700
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
West - Ambulance Handovers over 1 Hour: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
100
200
300
400
500
600
700
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
Central - Ambulance Handovers over 1 Hour: November2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
100
200
300
400
500
600
700
800
900
1,000
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
East - Ambulance Handovers over 1 Hour: November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
November 2019
Code Measure DescriptionNational
TargetJun-19 Feb-20 Mar-20May-19
Plan
Ref
Plan
Target
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20Qtr 4
19/20
Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20
- - -AP029 4th 696 00404<= 404DFM07
1
Number of ambulance handovers over one
hour BCUNov-19 792 - 792 0 0809614 447 811 694 8960
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Ambulance Handovers: Narrative 34
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline
YSBYTY GWYNEDD
• Emergency department escalation to include ambulance handover standard
operating procedure (in line with East)• > 60 minute ambulance handover a never event 31st December 2019
• Additional handover screens in Acute Medical Assessment Unit (AMAU),
Emergency Department (ED) Majors and Minors.• Eliminate delays for dual pin entry. 1st December 2019
YSBYTY GLAN CLWYD
The process and location has been agreed with Welsh Ambulance Service NHS
Trust (WAST) for them to look after patients in ED. The Work Initiation Document
has been updated accordingly.Improved availability of ambulance resources to respond to emergency calls
within the 8 minute target.
An initial 20% reduction in 1hr delays leading towards a zero tolerance approach.
31st December 2019
Specific actions for delayed ambulance handovers have been included in the
new site escalation framework.
WREXHAM MAELOR
• Sustain the current ambulance handover times and strengthen performance • Nil 60 minute delays 31st January 2020
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Delayed Transfers of Care Graphs 35
Finance & Performance Committee Version
Integrated Quality and Performance Report
0102030405060708090
100110120130140150
Nov
-17
Dec
-17
Jan-
18
Feb-
18
Mar
-18
Apr
-18
May
-18
Jun-
18
Jul-1
8
Aug
-18
Sep
-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Feb-
19
Mar
-19
Apr
-19
May
-19
Jun-
19
Jul-1
9
Aug
-19
Sep
-19
Oct
-19
Nov
-19
BCU Level - Delayed Transfers Of Care (Non-MH): Number of Patients - November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
500
1,000
1,500
2,000
2,500
3,000
3,500
4,000
Nov
-17
Dec
-17
Jan-
18
Feb-
18
Mar
-18
Apr
-18
May
-18
Jun-
18
Jul-1
8
Aug
-18
Sep
-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Feb-
19
Mar
-19
Apr
-19
May
-19
Jun-
19
Jul-1
9
Aug
-19
Sep
-19
Oct
-19
Nov
-19
BCU Level - Delayed Transfers Of Care (Non-MH): Number of Beddays - November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
300
600
900
1,200
1,500
1,800
2,100
2,400
2,700
3,000
Nov
-17
Dec
-17
Jan-
18
Feb-
18
Mar
-18
Apr
-18
May
-18
Jun-
18
Jul-1
8
Aug
-18
Sep
-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Feb-
19
Mar
-19
Apr
-19
May
-19
Jun-
19
Jul-1
9
Aug
-19
Sep
-19
Oct
-19
Nov
-19
BCU Level - Delayed Transfers Of Care (MH): Number of Beddays - November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
0
5
10
15
20
25
30
35
40
Nov
-17
Dec
-17
Jan-
18
Fe
b-1
8
Ma
r-18
Ap
r-18
Ma
y-18
Jun-
18
Jul-1
8
Au
g-1
8
Se
p-1
8
Oct
-18
Nov
-18
Dec
-18
Jan-
19
Fe
b-1
9
Ma
r-19
Ap
r-19
Ma
y-19
Jun-
19
Jul-1
9
Au
g-1
9
Se
p-1
9
Oct
-19
Nov
-19
BCU Level - Delayed Transfers Of Care (MH): Number of Patients - November 2019
Actual Target Control Line Upper Control Limit Lower Control Limit
November 2019
Why we are where we are: Lack of availability within the Community of general residential and nursing home beds and Elderly Mentally Infirm (EMI) residential and
Nursing home beds.
Code Measure DescriptionNational
TargetJun-19 Feb-20 Mar-20May-19
Plan
Ref
Plan
Target
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20Qtr 4
19/20
Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20
12
68 68
9 17
-
-
-
- -
-
6thDFM02
5
Nov-19 105 81
16
77
5 -
-
7th
Nov-19 16
DFM02
6
Number of health board non mental health
delayed transfer of care
Number of health board mental health
delayed transfer of care 0 0
0 07274 87 105 0 0
24 24 18 16 0 0<= 12
<= 28Reduce
Reduce
AP037
AP031
Chapter 2 – Unscheduled Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Delayed Transfers of Care - Narrative 36
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline
1. Implement Delayed Transfer of Care (DTOC) Action Plan,
reviewing weekly with Senior Leadership Team
Improved communication and discharge planning
Reduction in days delayed /bed days lost once Medically Fit for
Discharge (MFD)
Improved joint working with local authorities
weekly
2. Weekly Multi Disciplinary Team (MDT) DTOC meetings - improve
communication and remove blockages
Process to agree required actions to reduce the numbers of
patients medically fit but who are waiting in a hospital bed. Process undertaken on a weekly basis
3. Review of all patients who have been away from home 14
days+ in acute/community; escalation & review by HMT to identify
any trends.
Identify reasons for delay and escalate to Senior Leaders Process undertaken on a weekly basis
4. Acute & Community teams to identify alternative pathways to
support/improve patient journeys. Increased capacity to ensure timely discharge weekly
5. Support wards to reinforce Home First and What Matters Ensure a focus on early, safe discharge weekly
6. Daily safety brief attended by all departments to identify
problems relating to patient flow.
Integrated working between Area and Acute services in the co-
ordination of discharges Daily
Chapter 3 – Summary .
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Finance & Workforce 37
Finance & Performance Committee Version
Integrated Quality and Performance ReportAP = Awaiting Profile N/A A = Not Applicable - Annual November 2019
7
030
Finance & Resources
1
000
Finance
40
3
0
Workforce
2000
Other
0
2
4
6
8
10
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
Chapter 3 - Finance & Resources RAG Timeline 2019/20 November 2019
Red Amber Green No Data
Annual Plan National
Profile Target
DFM084 Quantity of Biosimilar medicines prescribed 73.30% ND Improve
DFM085 Critical Care Bed days Lost to DToC 18.20% N/A N/A Improve
DFM087 PADR Rate (%) 75.2% >= 78% >= 85%
DFM088 Staff agreed PADR helps improve 54.0% N/A N/A Improve
DFM089 Staff engagement Score 3.76 N/A N/A Improve
DFM090 Mandatory Training (Level 1) Rate (%) 84.58% >= 85% >= 85%
DFM091 Sickness absence rates (% Rolling 12 months) 5.22% <= 4.46% <= 4.31%
DFM092 Staff happy for BCU to treat Friends/Relatives 67.00% N/A Improve
LM001F Finance: Agency & Locum Spend £3.66m AP TBA
LM002F Finance: Position against Financial Balance £27.1m <= £23.3m <= £25m
StatusMeasureCode
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Agency and Locum Spend Graphs 38
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Qtr 4
19/20Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 May-19Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20Code Measure Description
National
Target
Plan
Ref
Plan
Target
- -LM001FCost of Agency & Locum spend within
MonthNov-19 £3.66m £3m £3.7m £4.1mNIP £0£2.6m £0N/A £2.7m -£0 £0-£4.2m £3.96m £4.34m £3.66mAPTBA
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Agency and Locum Spend - Narrative 39
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomeses Timeline
1. Focus remains on filling substantive vacancies, reducing sickness
absence and increasing pools of internal temporary staff , particularly
in nursing, medical and dental, A&C.
The Workforce Optimisation Portfolio is the overarching mechanism to
ensure delivery of BCU wide workforce initiatives. This is managed by
the Workforce Improvement Group (WIG) and consists of :
Medical Productivity, Nursing, Midwifery & AHP Productivity, Non-
Clinical Productivity and Terms & Conditions Application Productivity.
Agency as a percentage of total pay bill has significantly reduced
this month (currently 4.8% Nov 19, Previously 5.3% Oct 19). Agency
spend for Nov 19 was £3,056,788, much improved from £3,525,720
in Oct 19. Locum spend for Nov 19 at £606,529, much lower than
£811,642 in Oct19 and now at a historic low level.
The BCU overall sickness absence rate has reduced (currently
5.22% Nov 19, Previously 5.29% Oct 19).
The BCU overall vacancy rate has increased (currently 8.8% Nov
19, Previously 8.5% Oct 19). Successful recruitment of newly qualified
staff and experienced staff from other providers has seen N&M
vacancy rates fall for three consecutive month (now 10.5%, last month
11.3%) , unfortunately M&D have increased to 11.1% from 9.4%. Loss
of 18.53 FTEs along with increase in budget FTE of 7.51 resulted in
this increase (half the loss and majority of the increase was at YMW)
Detailed timelines are contained in the
Workforce optimisation portfolio and
accompanying PIDs. Impacts are expected
to build from December onwards.
Revised attendance improvement plan has
detailed actions / timelines around themes of
Data Analysis, Sickness Administration,
Active Absence Support and Preventative
Action.
Medical Recruitment Panel has been
introduced (Dec 19) to give focus on quickly
filling M&D vacancies, reducing the M&D
vacancy rate and associated Agency spend.
2. Work is on-going to increase the capacity of BCU internal temporary
staffing as an alternative to Agency.
N&M - auto enrolment to the bank and revised pay rates.
A&C - bank has been set up and is being expanded to include all
directly employed BCU A&C temporary staff by February 2020 (currently
on zero hours contracts in divisions).
M&D - In further efforts to move temporary staffing spend from Agency
to cheaper alternatives a Medical Staff Bank went live on 11 Nov 2019.
Increased N&M Bank Usage - The 13,037 N&M hours delivered in
Nov 2019 was 758 more than same period last year mitigating agency
costs and improving safety.
The introduction of the Medical Staff Bank will reduce M&D agency,
the MSB went live part way through November the impact on Agency
spend will be seen in December 2019 and will build as the MSB
expands and as outlier areas in terms of rates are addressed.
Auto enrolment of new N&M starters,
continued promotion of revised pay. A&C
staff bank programme to conclude Feb 2020.
Implementation (Nov 19) and expansion of
the Medical Staff Bank.
3. External consultancy services are analysing Medical spend and
advising areas of potential improvement including: review of medical
rotas, review of job planning process, introduction of medical and dental
bank, external specialist M&D recruitment.
Anticipated reduction of M&D vacancies in key specialisms via
implementation of Kendal- Bluck recommendations, use of external
recruitment to source substantive M&D staff. Medical Recruitment
Panel introduced (Dec 19). Recommendations of M&D rota reviews
are being validated and implemented.
M&D programmes plan to deliver savings.
Including external agencies sourcing M&D
staff. Continued expansion of Medical Staff
Bank. Impacts on run rates defined in PIDs
to deliver from December 19 onwards.
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Financial Balance 40
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Qtr 4
19/20Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 May-19Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20Code Measure Description
National
Target
Plan
Ref
Plan
Target
- -£18.20m -£0 N/A £14.64m £21.16m £23.9m £27.1mLM002F% Cumulative Deficit Position against the
planned Financial Balance Nov-19 £27.1m £3.83m £0 £0£7.54m £10.96m -£0NIP <= £23.3m<= £25m
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
£m
Financial Performance and Forecast 2019/20
Plan - £35m Stretch Plan - £25m Actual Forecast
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Financial Balance: Narrative 41
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline
1.Identify the full savings programme to meet the planned
savings requirement.
The savings programme continues to remain a key focus area. In month the value
of green and amber schemes increased by £2.9m. The overall value of the
programme however reduced by £1.7m in month following a reassessment of two
schemes by the Financial Recovery Group. The original planned deficit is
considered achievable if the Health Board can convert and deliver 51% of the
remaining red schemes, and deliver the green and amber schemes at their
planned values alongside containing emerging cost pressures.
31st January 2020
2. Ensure the Health Board implements the full suite of Grip
and Control actions to ensure all expenditure is necessary and
is effectively supporting clinical services.
A comprehensive financial recovery action plan (FRAP) programme has been in
place since July and is monitored through the Financial Recovery Group to
ensure timely progression of any incomplete actions and scrutiny of the complete
actions.
28th February 2020
3.Ensure the recovery programme progresses at pace.
Progress against plan is being monitored at both divisional and board level. The
Committee and Board reports have been updated to provide additional clarity on
progress and areas requiring priority attention. The format and content of the
reports will continue to be reviewed to ensure clear and relevant messages are
highlighted, to support the necessary decision making process.
31st December 2019
4. Identify emerging expenditure pressures to ensure informed
decisions are taken.
Both internal and external factors are being reviewed to support both the current
year recovery and 20/21 integrated planning process. An additional cost pressure
relating to the Welsh Risk Pool, which was previously recognised as a risk, has
now been confirmed and mitigating actions need to be identified to offset the cost
pressure, which is now a high risk to delivery of the forecast deficit.
28th February 2020
5. Identify and deliver further savings schemes to support
delivery of the £25m control target.
The Financial Recovery programme continues to work with Divisions and
Improvement Groups to deliver the additional £10 of savings schemes.31st January 2020
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Sickness Absence Graphs 42
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Qtr 4
19/20Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 May-19Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20Code Measure Description
National
Target
Plan
Ref
Plan
Target
- -5.22% 3rdDFM09
10.00% 0.00%AP043 4.92%4.95%
Percentage of sickness absence rate of
staffNov-19 5.05% 5.10% 5.13% -5.16% 5.22% 5.29% 5.22% 0.00% 0.00%-<= 4.46%<= 4.31%
Why we are where we are: Overall absence has seen a decrease of 0.7%. Days lost to Long Term (LT) continues to fall - There has been particular focus on LT sickness,
this has resulted in days lost and percentage off LT falling (Percentage - 3.22% (Nov 19) from 3.87% (Oct 19)). Focus on priority areas and changes to enhanced pay will
reduce short term frequent sickness absence and medium sickness rates in a similar way to the continued reduction in long term absence.
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Sickness Absence - Narrative 43
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline
1. Revised attendance improvement plan being enacted with
detailed actions / timelines around themes of Data Analysis,
Sickness Administration, Active Absence Support and
Preventative Action.
The BCU overall sickness absence rate has reduced (currently 5.22% Nov 19,
Previously 5.29% Oct 19).
All divisions reported reduced sickness reducing with the one exception of Women’s
which increased.
Support and trajectories remain in
place to deliver 4.2% by the end of
March 2020, however reaching this
remains in doubt..
2. Priorities of Long Term / Stress / MSK – remain in place, as
does the support for hotspots and support for all absences over
12 weeks.
Percentage off Long Term (LT) continues to fall - There has been particular focus
on LT sickness, this has resulted in percentage off LT falling to 3.22% (Nov 19) from
3.87% (Oct 19). Focus on priority areas and changes to enhanced pay will reduce
short term frequent sickness absence and medium sickness rates in a similar way to
the continued reduction in long term absence. This is likely to result in a 0.2% drop
from the baseline at October 2019 to February figures.
Progress against trajectories is
actively monitored. Further impact
of interventions should be seen in
Jan 2020.
3. Staff members who have had have reached and exceeded the
agreed sickness absence prompts have been identified with
active support being given to managers and staff to reduce
absence levels and prevent reoccurrences of absence.
Short term frequent sickness absence rates will reduce giving a 0.2% drop from the
baseline at October 2019 to February figures.
The impact of these interventions
should be seen in Jan 2020.
4. Changes to Enhanced pay during sickness absence from 1st
October 2019 with payments for sickness absence paid as basic
pay for absences of less than three months in length. National
agreement which reverts back to the position prior to June 2018.
Sickness levels across the health board prior to the enhancements being reinstated
were at 4.3%, since June 2018 when enhancements were brought back in we have
seen a steady increase in sickness levels despite intensive support and interventions.
Although only a temporary measure for now putting enhancements “on hold” has
preceded a reduction in absence levels expected to continue as staff groups most
impacted by this feel the effect.
Dec 2019 for initial reduction of
0.2% for “on hold” position.
5. Occupational health have introduced rapid access referral
pathways for staff in the following disciplines: Mental Health,
Counselling, Physiotherapy, CMATS – orthopaedics / pain clinic /
rheumatology, Radiology (scans), Drug & Alcohol, Podiatry and
Dermatology
Rapid access to services will enable staff to either remain in work for return to work
sooner.
Occupational Health ‘fast track’
number referred available from Q3
and turnaround times available from
Q4.
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
PADR (Appraisals) Graphs 44
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Qtr 4
19/20Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 May-19Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20Code Measure Description
National
Target
Plan
Ref
Plan
Target
- -AP046 59.39% -68.80% 70.00%3rdDFM08
7
Percentage of headcount by organisation
who have had a Personal Appraisal and
Development Review (PADR)/medical
appraisal in the previous 12 months
(excluding doctors and dentists in training)
Nov-19 75.20% 66.90% 0.00%72.00% 0.00%73.00% 74.10% 73.50% 75.20% 0.00% 0.00%->= 78%>= 85%
Why we are where we are: Compliance has improved this month by 1.7% to 75.2%. 10 divisions continue to see increases with only 3 seeing slight decreases. Estates &
Facilities continue to make good progress with an increase again this month from 61.9% to 69.9%.
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
PADR (Appraisals) - Narrative 45
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline1. Provided each Division with a full report of PADR status including
detail on staff in date, within 4 month expiry, out of date 12-24
months, out of date 24 months+ and never had a PADR and also
highlighting priority areas to focus on.
Attended 2 matron and ward manager meetings to raise awareness
of new PADR paperwork and resources and be available to answer
any queries staff may have.
Developed PADR self-learning guide for appraisers which includes
information on PADR principles, paperwork and best practice
The BCU overall PADR compliance rate has
increased, 75% Nov 19 (74% Oct 19) this is
significantly improved from last year (59% Nov 18).
Providing the detailed breakdown to all divisions has
led to 16 out of 23 divisions seeing an increase in
compliance over the month. Some large divisions such
as Estates & Facilities have seen a significant
increase of 8%.
Positive responses to attending matron and ward
managers meetings confirming the new PADR
paperwork and process to be more user friendly and
less repetitive.
All actions completed during
November. PADR self-learning
guide to be communicated widely
during December
2. Tailored session to be held with teams that have been identified as
being low in compliance from data analysis including Theatres YGC,
and teams within Estates & Facilities. Sessions to look at identifying
root cause of low compliance and solutions to improvement in moving
forward and Group PADR facilitation
Working with teams who have low compliance to
identify root cause of low compliance and solutions will
ensure good practice is adopted for sustainable PADR
compliance in moving forward
Sessions to be held during
December
3. Facilitated workshops held with managers attending Institute of
Leadership & Management (ILM) Qualifications
Workshops with managers contributes towards
ensuring they feel confident with the new resources to
conduct more meaningful PADR’s with their teams and
are given the opportunity to ask any questions they
may have around PADR
Sessions to be held during
December
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Mandatory Training Graphs 46
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Qtr 4
19/20Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20
Current
PeriodActual Status
Wales
Benchmark
Same
Period
Last Year
Apr-19 May-19Qtr 3
19/20
Qtr 2
19/20
Qtr 1
19/20Code Measure Description
National
Target
Plan
Ref
Plan
Target
- - -AP046 84.00% 85.00%DFM09
084.10% 0.00% 0.00%83.00%
Percentage compliance for all completed
Level 1 competencies within the Core
Skills and Training Framework by
organisation
Nov-19 85.00%84.58% 1st -85.00% 85.00% 84.00% 84.58% 0.00% 0.00%>= 85%>= 85%
Why we are where we are: Targeted support has ensured compliance for November is only marginally short of the national compliance target of 85% at 84.58%.
Chapter 3 – Finance & Workforce
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Mandatory Training - Narrative 47
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
Actions Outcomes Timeline
1.
Compliance for November has reached the national compliance target
again of 85% . As projected timeline figures identify a possible drop
again to 84% over the next quarter, work is taking identifying specific
areas and staff groups where compliance will drop and delivering
training as required
Compliance for November nearly achieving
the national compliance target of 85%
(84.58% Nov 2019).. By identifying specific
clinical areas and staff groups where
compliance will fall will prevent the target
dropping below the 85% national target rate.
This will inform all SME’s of the training
schedules required to meet projected demand.
We anticipate remaining at / or
near 85% target
2.
Completion of an audit of Section 6, WP30, Statutory and Mandatory
training policy has commenced beginning of December 2019, The
random Audit will concentrate for December 2019 on Ysbyty
Gwynedd. With 8 other Audits to follow to include Ysbyty Glan Clwyd,
Wrexham Maelor hospital, Estates & Facilities, Mental Health, Areas
West, Central & East.
By Identifying to specific managers their staff
who are non-compliant with section 6 of the
policy along with offering relevant advice and
support will maintain and increase the current
compliance rate.
Audit commenced December
2019 with other areas
receiving audit over the
following 7 months.
3.Implement a more robust action plan for addressing no significant rise
in training compliance within the following areas:
1. Medical & Dental
2. Estates & Facilities
By developing a more robust plan with follow
up reports will address the concern of no
significant increase in compliance within these
particular areas.
We anticipate maintaining the
85% target over the winter
months.
Chapter 4 – Summary .
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Primary Care 48
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
4
020
Primary Care
2
000
Dentist
2
00
0
GP
002
0
Out of Hours
Plan this National
Period Target
DFM049 OOH Assessment within 1 Hour 91.10% AP >= 90%
DFM050 OOH Very Urgent Seen within 1 Hour 100% AP >= 90%
DFM047 Convenient GP Appointment 37.50% N/A N/A Reduce
DFM048 GP Practice Open 5pm to 6.30pm 0.00% AP Improve
DFM051 Accessed NHS Dentist 49.25% AP Improve
DFM086 Dentist Follow Up 36% AP Reduce
LM101Number of CHC & Joint funded Packages
of Care1,788 0 0
LM102Cumulative cost of CHC & Joint funded
Packages of Care£59.46m 0 0
LM103 Total number of Emergency Admissions 7,380 0 0
LM104Total Number of Emergency Admissions
with an Average Length of Stay of 02,411 0 0
LM105Average Length of Stay for Emergency
Admissions: Acute Sites5 0 0
LM106 Average Length of Stay: Community 27 0 0
StatusMeasureCode
0
2
4
6
8
10
Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19
Chapter 4 - Primary Care RAG Timeline 2019/20 November 2019
Red Amber Green No Data
Please note: Timeline graphs based on when Out of Hours was under
Unscheduled Care Chapter. Will be reviewed for next month.
Chapter 4 – Primary Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Dental Care Report 49
Finance & Performance Committee Version
Integrated Quality and Performance Report
Actions Outcomes Timeline
1. Funding has now been secured for the procurement of dental
activity for the central Bangor/Menai Bridge locality
Commissioning approval will now be sought from Finance &
Performance CommitteeFebruary 2020
2. Additional funding unscheduled daytime access sessions will be
commission from 1st January 2020 to 31st March 2020 for 8
practices aligned to Emergency Dental Service (EDS) provision
£50K to be assigned immediately January 2020
3. Welsh Government Contract Reform Innovation funding will be
assigned to qualifying practices to commission 8 scheduled access
sessions liaising with Private Contractors (PC) & EDS colleagues
£157K programme funding for 5 years developed through
an Service Line Agreement (SLA) agreement with the
Health Board
January 2020
November 2019
National
Target
Plan
Ref
Plan
TargetNov-19 Dec-19 Jan-20Sep-19 Oct-19
Qtr 2
19/20
Qtr 1
19/20Jul-19 Aug-19
Qtr 3
19/20
Same
Period
Last Year
Apr-19 May-19 Jun-19 Mar-20Qtr 4
19/20Code Measure Description
Current
PeriodActual Status
Wales
BenchmarkFeb-20
#
-
0.00%
- -
0.00%36.30%0.00%
- 49.30% 49.30% 49.23% 49.25% 0.00% 0.00%
- - - - - -
AP007DFM05
1
Percentage of the health board population
regularly accessing NHS primary dental
care
Nov-19 49.25% 6th 49.30% 49.30% 0.00% 0.00%
36.30% 7th New 19/20DFM08
6
Percentage of adult dental patients in the
health board population re-attending NHS
primary dental care between 6 and 9
months
AP
APReduce
Improve
Qtr 2
19/20- - - -- -
49.30% 49.30% 49.30%
AP007
Chapter 4 – Primary Care
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Proposed New Measures 50
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
National
Target
Plan
Ref
Plan
TargetNov-19 Dec-19 Jan-20Sep-19 Oct-19
Qtr 2
19/20
Qtr 1
19/20Jul-19 Aug-19
Qtr 3
19/20
Same
Period
Last Year
Apr-19 May-19 Jun-19 Mar-20Qtr 4
19/20Code Measure Description
Current
PeriodActual Status
Wales
BenchmarkFeb-20
LM101Number of CHC & Joint funded Packages
of CareNov-19 1,788 N/A 1,915 1,830 1,841 1,849 1,839 1,844 1,825 1,811 1,785 #REF! #REF! #REF! #REF!
LM102Cumulative cost of CHC & Joint funded
Packages of CareNov-19 £59.46m N/A £61.71m £7.54m £15.08m £22.62m £30.29m £34.72m £45.00m £52.50m £59.46m
LM103 Total number of Emergency Admissions Nov-19 7,380 N/A 7,917 7,857 7,947 7,880 7,934 7,515 7,377 7,885 7,380
LM104Total Number of Emergency Admissions
with an Average Length of Stay of 0Nov-19 2,411 N/A 2,238 2,166 2,169 2,014 2,148 1,857 1,938 2,242 2,411
LM105Average Length of Stay for Emergency
Admissions: Acute SitesNov-19 5.3 N/A 5.2 5.6 5.4 5.3 5.4 5.4 5.5 5.6 5.3
LM106 Average Length of Stay: Community Nov-19 27.0 N/A 29.0 27.0 28.5 29.1 30.0 26.9 30.3 27.8 29.0
* = Rated against same period previous year
The Health Board is a provider of integrated care across primary, community, mental health and secondary care parts of patients pathways. Much of the data within the organisation
relates to hospital care. However, our strategic direction it to provide care closer to home for our population. National indicators for access to primary care are in development and will be
included in IQPR reports from April 2020. However the above local indicators are included to reflect some of the work being undertaken through the care closer to home and unscheduled
care improvement groups. The Continuing Health Care indicator is included to monitor the level and cost of provision for our population.
The level of emergency admissions reflects the whole system approach to unscheduled care, ability of primary and community services to manage patients close to home and
effectiveness of admission avoidance schemes. The zero day length of stay acts as an indicator on the effectiveness of ambulatory care services and the ability of primary and community
care to support patients return to their normal place of residence. The average length of stay data is useful in assessing the ability to support patient flow through the whole system and
facilitate patients to return to their residence at the earliest opportunity. As this is an introductory report the data presented is for information in this report , with the expectation that future
reports will include information on actions, expected outcome and timescales from the improvement groups in future reports.
Appendix A: Further Information.
Put patients first Work together Value and respect each other Learn and innovate Communicate openly and honestly
Further information is available from the office of the Director of Performance which includes:
• performance reference tables
• tolerances for red, amber and green
• the Welsh benchmark information which we have presented
Further information on our performance can be found online at:
• Our website www.pbc.cymru.nhs.uk
www.bcu.wales.nhs.uk
• Stats Wales www.statswales.wales.gov.uk
We also post regular updates on what we are doing to improve healthcare services for patients on social media:
follow @bcuhb
http://www.facebook.com/bcuhealthboard
51
Finance & Performance Committee Version
Integrated Quality and Performance ReportNovember 2019
7.1 FP19/298 Bryn Beryl Integrated Dementia & Adult Mental Health Centre Capital Business Case
1 FP19.298a Bryn Beryl business case december 2019 (2).docx
1
Cyfarfod a dyddiad: Meeting and date:
Finance and Performance Committee 19.12.19
Cyhoeddus neu Breifat:Public or Private:
Public
Teitl yr Adroddiad Report Title:
Bryn Beryl Integrated Dementia & Adult Mental Health CentreCapital Business Case
Cyfarwyddwr Cyfrifol:Responsible Director:
Mr Mark Wilkinson, Executive Director of Planning and Performance
Awdur yr AdroddiadReport Author:
Mr Neil Bradshaw, Assistant Director of Planning and Performance - Capital
Craffu blaenorol:Prior Scrutiny:
This business case has been recommended for approval by the Estates Improvement Group and the Executive Team
Atodiadau Appendices:
Appendix 1 – The capital business caseAppendix 2 – Equality Impact assessment
Argymhelliad / Recommendation:The Committee is asked to approve the capital business case for the Bryn Beryl Integrated Dementia & Adult Mental Health CentrePlease tick one as appropriate (note the Chair of the meeting will review and may determine the document should be viewed under a different category)Ar gyferpenderfyniad /cymeradwyaethFor Decision/Approval
√Ar gyfer TrafodaethFor Discussion
Ar gyfer sicrwyddFor Assurance
Er gwybodaethFor Information
Sefyllfa / Situation:In summary, this business case sets out the rationale for the development of an integrated Dementia and Adult Mental Health Centre on the Bryn Beryl site.
Cefndir / Background:Until the recent move to a temporary leased site (Hafod Lon) owned by Gwynedd Council, Dementia / Older Persons Mental Health (OPMH) services for the Llyn area were fragmented across several sites (Ala Road, Hafan in Bryn Beryl and Cilan) within extremely poor accommodation. The Dementia day service in Ala Road was the last remaining service on the Ala Road Health Centre site in Pwllheli, however a site risk assessment carried out in June 2018 assessed the health and safety risks to be too high for service users and staff to remain on the site. This decision meant that urgent temporary accommodation needed to be found. At the same time, accommodation was also needed for the Hafan Unit Dementia service in Bryn Beryl (to allow for ward extension and refurbishment work to start in August 2018).
The Hafod Lon site - former special needs school (now named Hafod Hedd by the OPMH Service) was identified and is being leased (at nil rent paying service costs only) from Gwynedd Council on a short term basis.
Adult mental health (AMH) services are currently located in Cilan Mental Health Resource Centre a Health Board owned premises in the centre of Pwllheli, which also has significant health and safety
2
risks in terms of its condition, compliance with statutory regulations (e.g. DDA) and overall suitability for the delivery of modern health care. The need to create permanent location for the OPMH team affords the opportunity to rationalise all OPMH / AMH accommodation in this area into one centre on a single site and ensure that any proposed development integrates both local different stage dementia services as well as adult mental services. This proposal (as well as enabling the disposal of Ala Road) would ultimately enable the disposal of the Cilan site generating running cost efficiencies.
The overall aim of this development is therefore to bring together two different stage dementia services together with the Cilan adult mental health service, into one location and one centre.
Asesiad / Assessment & AnalysisStrategy Implications
The North Wales Mental Health Strategy aims to ensure there is promotion of health and well-being for everyone; prevention of mental ill-health and early intervention when needed and the delivery of joined-up and recovery-focused care. The Strategy focuses on integrating as much as possible – across disciplines, across agencies and across services, in both planning and delivering services, with a view to reducing fragmentation.
A key strand of the Health Board’s ‘Living Healthier, Staying Well Strategy’ (LHSW) is the delivery of Care Closer to Home. An integrated centre for OPMH and AMH services will enable service users to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care. People can 'step up and step down' within the services depending on their need at the time, a flexible approach within both the adult mental health service and the dementia service. Separate locations and buildings for OPMH and AMH services are currently fragmenting services for service users and their families. An integrated centre for dementia and adult mental health services will provide easier access for local people to ensure.
Financial Implications
The Capital Cost of the preferred option to develop a new extension to house an integrated dementia and adult mental health centre at the back of the Bryn Beryl site is £1,309,989. Welsh Government have confirmed a capital grant of £812,928 from the Integrated Capital Fund (ICF) in support of the proposal. There is a remaining shortfall in capital of £497,061 which would require support from the Health Board discretionary capital allocation.
The estimated revenue / running costs relating to the new build extension (360m²) are £24,440. Annual savings of £45,766 have already been realised through the relocation from Ala Road (subject to final disposal of the site). The anticipated savings arising from the closure of Cilan Mental Health Resource Centre as well as the rental costs of the Hafod Hedd site (Gwynedd Council) are £30,421 which when offset against the estimated running costs of the new Centre still mean the generation of savings of just under £6,000 per annum.
Capital receipts will be generated from the sale of the two Health Board sites and there value are currently subject to valuation by the District Valuer.
Risk AnalysisIf the Health Board does nothing, then local provision of dementia and adult mental health services in the Llyn area faces the following risks and issues;
3
Dementia and AMH services will continue to be delivered within unsuitable, unfit for purpose accommodation, with poor accessibility and failing statutory compliance (Cilan)
Less than optimum integration of Dementia and AMH services for the Dwyfor population resulting in services continuing to be delivered from three separate sites / locations, which ultimately results in poor continuity of care
No capacity to expand and develop services – OPMH would like to run an additional post diagnostic group, extra clinics for OPMH and AMH, new carers’ drop-in groups
Perpetuation of the status quo with dementia services being accommodated in temporary / leased accommodation (not a viable long term option), as Gwynedd Council wish to sell the site ultimately. In addition, the leasing / purchase of an additional site by BCU is not in line with its LHSW and Estates Strategies.
Ongoing inefficient use of resources – running sites which are unnecessary, poor quality and non-compliant with statutory regulations
Missed opportunity to utilise ICF capital from Welsh Government to improve services for vulnerable client groups
Impact Assessment
A formal equality impact assessment has been undertaken as the attached Appendix 2.
Board and Committee Report Template V1.0 December 2019.docx
1 FP19.298b FINAL BB Integrated Dementia AMH Centre buisess case 18 Nov 19 (V9 Updated Costs).docx
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
1 | P a g e
Bryn Beryl Integrated Dementia & Adult Mental Health Centre
Capital Business Case
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
2 | P a g e
Business Case Template
Division West AreaDevelopment or Scheme
Bryn Beryl Integrated Dementia & Adult Mental Health Centre
Author/s Christine Rudgley / West Area Team / OPMH & AMH Services
Version 9Date 18th November 2019
1. Executive Summary1.1 Headline information
What do we want to do ?
We need to provide permanent accommodation for Older People’s Mental Health (OPMH) and Adult Mental Health (AMH) service users and staff in the Dwyfor / Llyn peninsula area - OPMH / dementia services from Ala Road Health Centre and Hafan Unit on the Bryn Beryl site transferred to a temporary council owned site just outside Pwllheli in Summer 2018. The services transferred following the closure of Ala Road Health Centre (due to significant Health & Safety risks) and the need to vacate Hafan Unit to enable the recent Ysbyty Bryn Beryl ward reconfiguration and refurbishment to take place.
We want to use ICF capital to develop new, purpose-built facilities (an extension) on the Bryn Beryl site to accommodate local OPMH and AMH services users and staff.
We want to deliver more day assessment services for people in all stages of dementia, including people experiencing significant behaviour and psychological symptoms of dementia, as well as more group and individual therapy for adult mental health service users. We also want to provide integrated office accommodation for Health and Local Authority OPMH and AMH community staff.
Why do we want to do it ?
Modern, fit for purpose accommodation – we want to provide purpose built facilities and a suitable therapeutic environment to meet the needs of our vulnerable OPMH and AMH client groups
Improved integration - Integrating dementia and AMH services in one building enables people to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care – ultimately increasing the number of patients cared for within their own communities with reduced need for hospital admission. Integration also significantly improves communication between community teams and agencies.
Reduced service fragmentation - OPMH and AMH services in Dwyfor are currently fragmented across previously three (and now two) sites. One centre will provide a single point of access.
Increased clinical capacity through expanded accommodation to see more dementia and AMH service users locally in line with the Mental Health Measure, the Health Board’s Care Closer to Home strategic objective and projected future demand.
Strategic alignment – Building a new integrated centre on the Bryn Beryl site is in line with BCUHB strategic direction (Living Healthier, Staying Well) in terms of Care Closer to
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
3 | P a g e
Home - caring for people with dementia / AMH conditions for longer in their own communities, as well as the North Wales Mental Health Strategy (promoting integration and less fragmentation) and the Health Board’s Estates Strategy – investing in Bryn Beryl as a level 1 Health & Wellbeing hospital / centre.
Rationalise estate and generate efficiencies - We would like to get rid of existing, poor community estate and replace with modern, fit for purpose, efficient facilities in line with the Health Board’s Estate Rationalisation Strategy
How much will it cost ?
Capital Cost - The preferred option to develop a new extension to house an integrated dementia and adult mental health centre at the back of the Bryn Beryl site is £1,309,989.
Funding - An ICF capital allocation of £812,928 has already been formally approved by WG for this project to be spent in 2019/20 and 2020/21.
Capital shortfall - There is a remaining shortfall in capital required of £497,061. potentially to come from Health Board discretionary capital which would be required in 2020/21.
Revenue costs - The estimated revenue / running costs relating to the new build extension (360m²) are £24,440.
Savings - The annual savings generated from the closure of Ala Road are £45,766 and have already been realised in 18/19. The anticipated savings arising from the closure of Cilan Mental Health Resource Centre (MHRC) as well as the rental costs of the Hafod Hedd site (Gwynedd Council) are £30,421 which when offset against the estimated running costs of the new Centre still mean the generation of savings of just under £6K per annum.
Capital receipts - The capital receipts generated from the sale of the two BCU sites are subject to a DV valuation.
What are the benefits ?
Modern, expanded, fit for purpose accommodation to meet OPMH (Dementia) & AMH service user and staff needs
More integrated and improved patient care for OPMH Dementia and Adult Mental Health service users as a result of co-location - leading to improved continuity of care for service users, less duplication and better communication between services
Increased capacity by up to 10-15% to deliver both group and individual therapy as required under the Mental Health Measure and in line with increasing demographic demand
Care closer to home - supporting more accessibility in the community as set out in the national Dementia Strategy, the Mental Health Measure, the Health Board’s Living Healthier, Staying Well (LHSW) Strategy and the Estates Strategy through investment in the Ysbyty Bryn Beryl site as a Level 1 community hospital / health & wellbeing facility, providing integrated dementia and AMH services as locally as possible
Estate efficiency and rationalisation - improving the quality and efficiency of the estate through the rationalisation of poor community sites, reduced backlog maintenance, reduced running costs and achievement of statutory and regulatory compliance
How are we going to measure success?
More integrated care – we will measure the anticipated improvement in continuity of care and communication between teams through patient and staff questionnaires
Improved capacity - to deliver group and individual therapy to Dementia and AMH service users will be measured in terms of increased clinical contacts / assessments over time
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
4 | P a g e
Fit for purpose accommodation and a therapeutic environment will be measured on completion of the new centre (achieving statutory compliance and service standards) and adjacent dementia garden and through service user questionnaires
Care closer to home - we will measure the increased numbers of OPMH / AMH service users who are supported to remain self-caring avoiding admission to hospital
Delivery of savings – we will demonstrate efficiencies from the closure and ultimate disposal of two poor, inefficient community sites and from securing the sale of these sites.
Recommendation:
It is recommended that this business case to develop an integrated Dementia and Adult Mental Health centre on the Ysbyty Bryn Beryl site is approved, as it delivers a full range of benefits in terms of the improvement of patient care as outlined above, is strategically aligned to both national and organisational strategies, is less expensive than the do nothing option and secures financial efficiencies related to estate rationalisation.
It is proposed that the development be funded from a combination of Welsh Government ICF capital and Health Board discretionary capital, as set out above. Whilst there will be estates related revenue implications resulting from the capital development, these costs would have been offset against the closure of Ala Road Health Centre in 2018/19 and the savings have already been realised. Therefore the revenue impact of the development will not occur until 2021/22 and will be offset against the savings related to the closure and sale of Cilan. The net effect is expected to be just under £6,000 savings per annum.
1.2 Approval Process
This business case will be processed in accordance with the Procedure Manual for Managing Capital Projects. It will require local approval in the first instance from the West Capital Group and the West Area Leadership Team. Subsequently, the case will require approvals from the Health Board’s F&P Committee and Board.The proposal has already received formal approval from Welsh Government in terms of the capital allocation of £812,928 (from ICF capital monies). The intention is that the balance in funding will come from the Health Board’s discretionary capital allocation in 2020/21, subject to Estates Improvement Group, Executives, F&P Committee and Board approval.
2. The Strategic Case2.1 Overview of the Business Case
In summary, this business case sets out the rationale for the development of an integrated Dementia and Adult Mental Health Centre on the Bryn Beryl site. It has been developed by the West Area Operational Improvement Lead in conjunction with the Assistant Project Support Manager, Estates Senior Project Manager, Area Chief Finance Officer and service leads for OPMH and AMH services.
Background / Context
Until the recent move to a temporary leased site (Hafod Lon) owned by Gwynedd Council, Dementia / OPMH services for the Llyn area were fragmented across several sites (Ala Road, Hafan in Bryn Beryl and Cilan) within extremely poor accommodation. The Dementia day service in Ala Road was the last remaining service on the Ala Road Health Centre site in Pwllheli, however a site risk assessment carried out in June 2018 assessed the health and safety risks to be too high for service users and staff to remain on the site. This decision meant that urgent temporary accommodation needed to be found. At the same time,
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
5 | P a g e
accommodation was also needed for the Hafan Unit Dementia service in Bryn Beryl (to allow for ward extension and refurbishment work to start in August 2018).
The Hafod Lon site - former special needs school (now named Hafod Hedd by the OPMH Service) was identified and is being leased (at nil rent paying service costs only) from Gwynedd Council on a short term basis. Already the two different stage dementia services are enjoying the benefits of integration, as well as the improved environment and larger space for the service users and staff. However if Hafod Lon were to become the permanent location for Dementia services, the Health Board would need to purchase the site from Gwynedd Council and it would require more extensive refurbishment (estimated at £800K minimum including the site purchase).
Cilan MHRC is a Health Board owned premises in the centre of Pwllheli, which also has significant health and safety risks in terms of its condition, compliance with statutory regulations (e.g. DDA) and overall suitability for the delivery of modern health care. Some OPMH Team office accommodation, as well as clinical and office space for Adult Mental Health Services / Team are housed in Cilan. It would seem sensible to take this opportunity to rationalise all OPMH / AMH accommodation in this area into one centre on a single site and ensure that any proposed development (this business case) integrates both local different stage dementia services as well as adult mental services. This proposal (as well as enabling the disposal of Ala Road) would ultimately enable the disposal of the Cilan site generating running cost efficiencies.Originally the Hafan service was planned to relocate temporarily to Ala Road, however this was no longer possible. The site is now decommissioned and the running cost savings are being incurred by Operational Estates
There is therefore a requirement to find a permanent integrated accommodation solution for both Dementia and AMH services. The overall aim of this development is therefore to bring together two different stage dementia services together with the Cilan adult mental health service, into one location and one centre. The new Centre will provide modern, purpose built accommodation and an improved environment for local Older People’s Mental Health (OPMH) and Adult Mental Health (AMH) service users and staff, previously located in very poor conditions in three separate buildings on three separate sites. The co-location of OPMH and AMH services and staff in one centre, as well as with several members of local authority staff will significantly improve the integration of and communication between services, which should positively impact on the delivery of patient care.
Strategic context
The national Dementia Strategy focuses on the need to provide high quality, person-centred care to people living with dementia and those affected by it, to support the creation of dementia-friendly communities and to listen and respond to people with dementia. The provision of facilities and a therapeutic environment that are purpose built to meet the needs of people with dementia is paramount. The model focuses on the need to ‘support people to remain self-caring avoiding admission to hospital’ - whether general or psychiatric - whenever possible and facilitate timely discharge from hospital (with the right care or support at home), as an admission to hospital can be devastating for a person with dementia.
Welsh Government’s Mental Health Measure requires health boards to provide timely assessments and interventions to significant numbers of individuals in the locality. Current estate provision is limited in terms of capacity. This provision will provide much increased capacity to deliver group therapy and individual care close to home.
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
6 | P a g e
The North Wales Mental Health Strategy aims to ensure there is promotion of health and well-being for everyone; prevention of mental ill-health and early intervention when needed and the delivery of joined-up and recovery-focused care. The Strategy focuses on integrating as much as possible – across disciplines, across agencies and across services, in both planning and delivering services, with a view to reducing fragmentation.
A key strand of the Health Board’s ‘Living Healthier, Staying Well Strategy’ is the delivery of Care Closer to Home. An integrated centre for OPMH and AMH services will enable service users to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care. People can 'step up and step down' within the services depending on their need at the time, a flexible approach within both the adult mental health service and the dementia service. Separate locations and buildings for OPMH and AMH services are currently fragmenting services for service users and their families. An integrated centre for dementia and adult mental health services will provide easier access for local people to ensure.
2.2 The Current Service
Older People’s Mental Health Services
Population, Geography & DemographicsDwyfor has a population of around 25,000. The area has an older population than the North Wales average, with 27% aged 65 years and over and just over 4% aged 85 years and over.
A higher proportion of the population of Dwyfor (registered primary care cluster population) live in a rural area than the Arfon and Meironnydd Primary Care Cluster areas and the average across North Wales.
South Gwynedd OPMH services currently use two bases in the Dwyfor area. The ‘Cilan’ building in Pwllheli provides office space for the three community psychiatric nurses, psychologist and support worker. ‘Hafod Hedd’ in Y Ffor is the temporary location of the day assessment services, which provides a tiered model of care depending on the service user’s level of need, housed within the same building. The consultant psychiatrists’ clinic is also held there once a week.
Day assessment services are open Monday to Friday from 9am to 5pm. They offer ongoing assessment and treatment in the form of cognitive stimulation for people with dementia. There are three main ‘groups’ of people who attend on different days or different areas of the building, depending on their need. Service users usually attend 2 or 3 times a week, however this can be increased in times of crisis in a ‘step-up, step-down’ manner. As such, day assessment is considered an alternative to hospital admission, and our number of admissions to the psychiatric inpatient unit in Llangefni has greatly reduced since the establishment of this service. We also acknowledge that although respite for carers is not the main focus of this service, it is by nature offering short term respite for carers.
Clinic/patient numbers per weekIn terms of day assessment, there is capacity for 24 service users to attend three times per week and 12 service users attending twice a week. This equates to 96 patient contacts / attendances per week for dementia day assessment services.The separate OPMH outpatient clinic is held weekly with usually between 5 and 8 service users attending.
Current staffing levels
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
7 | P a g e
Our staffing establishment is as follows:1 x band 6 RMN2 x band 5 RMN3 x band 3 HCSWSocial services provide two support workers three times a week.
Location, current buildings, condition of the properties
OPMH services for the Llyn population are currently provided from the leased Gwynedd Council owned Hafod Hedd site in Y Ffor (just outside Pwllheli). The leasing of this site is a temporary arrangement arising from the need to find emergency accommodation for the Ala Road Joint day assessment service in May / June 2018, as a result of the outcome of the health & safety risk assessment of the Ala Road site (which advised the need to close the site as soon as possible). At the same time, there was also a need to relocate the early stage dementia service from the Hafan Unit in Ysbyty Bryn Beryl to allow the ward refurbishment works to start in September 2018. Both service transfers have been achieved without any loss or reduction in services for patients.
Hafod Hedd is a single storey site offering large spaces for services and is in semi reasonable condition for a temporary service, however it is not suitable in its current state as permanent accommodation. Some very minor upgrading (painting / suspended ceilings etc) was undertaken in 2018 before occupation. Cilan MHRC is a Health Board owned three storey terraced townhouse type premises in the centre of Pwllheli, with no lift and some adjacent car parking at the back. The site has recently been assessed as having significant health and safety risks in terms of its condition, compliance with statutory regulations (e.g. DDA) and overall suitability for the delivery of modern health care.
Dementia model of care
The Population Needs Assessment identifies that there needs to be a clear pathway from assessment and diagnosis of dementia through to ongoing support and end of life care. The OPMH service is also required to support the community hospitals and care homes caring for people with dementia.
The model focuses on Supporting people to remain self-caring avoiding admission to hospital - whether general or psychiatric - whenever possible and facilitating timely discharge from hospital (with the right care or support at home) is vital, as an admission to hospital can be devastating for a person with dementia.
The right care and support does not just focus on levels of ‘functioning’ or daily living tasks but also 'what matters' to people – such support (getting out and about, retaining social contact) often falls to friends, family and neighbours, which is why supporting carers is an important aspect of this project.
Social isolation is known to have a negative effect on both physical and emotional health, the creation of this specialist mental health facility will be an opportunity to encourage people with mild mental health problems to engage with voluntary agencies to potentially prevent problems escalating into serious mental illness.
Fragmented services in different locations do not enable the delivery of the right model of dementia care. Co-locating services together under one roof will enable the person to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care - people can 'step up and step down' within the services depending on their need at the time, a flexible approach within both the adult mental health service and the dementia service.
Integrating services in one building also provides an opportunity to undertake a further assessment and thus contribute towards maintaining the individual who is living with
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
8 | P a g e
dementia in the community for a longer period of time, increasing the number of patients cared for within their own homes with reduced need for hospital admission.
Gaps in existing service provision
Need for additional post diagnostic therapy group for people recently diagnosed with dementia – this will be able to be established in the new centre, as there will be suitable, available space (12 new clinic spaces per week)
Space for carers to ‘drop in’ if they need support and advice - there will be a designated space in the new centre for a new Carers’ drop in group
VC facilities – new video-conferencing facilities will be included within the Project’s equipment
Limited usable outside space - a new dementia garden is planned outside the new Centre for use by service users and staff
Space for third agency organisations to offer services – there will be an increase in clinic and interview rooms for use by OPMH & AMH services, as well as relevant third sector organisations.
Inadequate meeting/training space – a large meeting / training room has been included within the new centre plans
Evenings and weekends – Future service plans include looking at the implementation of an out of hours service to meet service user needs (the business case is not dependent on securing these funds)
Admin cover – additional administration cover is also a future requirement but again is not business case dependent.
Adult Mental Health Service (Cilan)
Population, geography & demographicsAs mentioned above, Dwyfor has a population of around 25,000. It is estimated that one in four people experience common mental health problems or suffer from anxiety and depression at some point in their lives, and this has a significant impact on the adult working population. One in three GP consultations is also estimated to be mental health related.
Location and current buildingsThe South Gwynedd Adult Community Mental Health Team (CMHT) is based at Ysbyty Alltwen, Tremadog. There is also a satellite base at Plas Brith in Dolgellau, and staff work from various GP surgeries and third sector buildings across the area. The CMHT does have access to Cilan Mental Health Resource Centre (MHRC) in Pwllheli on a peripatetic basis, but the CMHT services currently provided at Cilan are limited as the building is no longer fit for purpose. In Cilan the office space is being used by the CMHT on a daily basis, however the interview rooms are shared with the other services who operate from Cilan. Room availability is therefore limited. This means that new to service clients cannot presently be seen in Cilan or clients who are known to potentially present as a risk. The lack of space in Cilan has meant that local people are having to travel to access AMH services. Both the Consultant Psychiatrist and Clinical Psychologist have moved their clinics to Ysbyty Alltwen. There are no inpatient adult mental health beds in South Gwynedd. Clients requiring inpatient care are admitted to the Hergest Unit in Ysbyty Gwynedd.
Clinic Capacity & Current Staffing The Psychiatrist has one Dwyfor clinic (for Cilan clients) in Alltwen per week (7 slots).
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
9 | P a g e
The Psychologist undertakes three clinics per week for Dwyfor (Cilan) clients (5 slots per day).
The Primary Care Mental Health Team currently conduct assessments across GP surgeries / third sector (Felin Fach). This is problematic as the staff are dependent on third party room availability and need to fit in with what is available. This in turn result is appointments being delayed due to lack of rooms.
The Primary Care Mental Health Team has two practitioners working in Dwyfor. They see 20 clients each per week. The sessions include assessments and intervention.
There are six secondary care CMHT workers based in Dwyfor. Client numbers are less due to travel as most appointments are conducted at the home address. Secondary Care workers also attend the ward round in Bangor and other meetings. They see approximately 16 clients each per week.
The service would like to establish a depot clinic / physical health monitoring clinic one morning per week in Dwyfor. Depots are currently undertaken at CILAN or clients homes. The physical health monitoring would entail Blood Pressure/ weight monitoring/ health promotion, smoking cessation. ECGs.
Adult Mental Health Issues / Gaps in existing service provision
Lack of clinic capacity with Dwyfor clients having to travel further to Psychiatrist and Psychologist clinics in Alltwen resulting in higher DNA rates – Capacity will be increased within the new Centre with these clinics being able to transfer back so that clients can be seen locally.
Unfit for purpose building (Cilan) in terms of layout and general condition – the new Centre will provide modern, purpose built facilities which have statutory compliance
Challenges arising from housing OPMH / AMH services with Children’s services in close proximity in the same building (Cilan) – It is proposed to relocate Children’s office / admin services to the Bryn Beryl site (when Cilan closes) and to secure interview space in central Pwllheli in Ffordd y Cob.
Limited access to suitable appointment/ interview rooms in Cilan - resulting in ineffective appointment system and poor short notice access for urgent and crisis appointments. This will be addressed in the new Centre.
2.3 The Case for Change
2.3.1 Business Needs – the gap between where we want to be and where we are now
As indicated previously, national, organisational, Mental Health and local West Area plans prioritise the need to deliver care as close to home as possible in community settings and to integrate services wherever possible with those provided by other agencies. Currently both OPMH and AMH services are fragmented in the Dwyfor area which affects access for vulnerable client groups. The aim is to deliver a single point of access to integrated services to ensure easier, more timely assessments and interactions for the local population. Co-locating and working closely with local authority and third sector colleagues will also facilitate the move towards a seven day service.
In terms of estate, neither the current Health Board estate (in Bryn Beryl and Cilan) nor the leased Hafod Lon premises are able to optimally support the delivery of modern, integrated services to fully meet current and future service needs. The leased facilities require a significant upgrade to effectively support the delivery of modern dementia and adult mental health services.
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
10 | P a g e
Whilst this is feasible, the site would need to be purchased first and the existing footprint would limit the design potential to some extent.In addition, there is no capability to extend the existing Cilan premises to increase capacity and the building itself is unsuitable for modern health care delivery and is in very poor condition. This means that the building is more costly to run and is incompatible with our aspiration to provide services of the highest quality. In terms of dementia and adult mental health services, the current provision of accommodation does not meet the needs of service users and staff.
The key issues affecting the optimum delivery of OPMH / Dementia and AMH services which would be overcome through the development of a new integrated Dementia and Adult Mental Health Centre on the Bryn Beryl site serving the local wider Pwllheli / Llyn peninsula community are as follows:
Poor quality (not purpose built) accommodation in terms of accessibility, suitability and fabric of premises Hafod Lon (currently housing the two different stage dementia services) is a single storey building that was originally a special needs school. Whilst the current dementia service accommodation in Hafod Lon has undergone a very minor upgrade (some painting and some new suspended ceilings) and represents a definite improvement on the very poor Ala Road accommodation, it is not purpose built and would need fairly significant refurbishment to meet existing and future dementia service needs.
Specific issues include:
The building is leased so would need to be purchased by BCUHB before significant investment in refurbishment could be undertaken.
The acquisition of another site is not in line with the Health Board’s estate rationalisation strategy
The internal fabric of the building requires significant upgrading to make it fit for modern health service delivery and more dementia friendly.
Alterations would need to be made to accommodate clinic rooms and office space for AMH services
The current site access is single lane and not ideal.
Fragmentation of services and poor integration
The location of dementia and adult mental health services in several sites across the area presents problems. By co-locating on the Hafod Lon site the two different stage dementia services including two local authority colleagues (from Ala Road and Hafan Unit), integration has improved already for both service users and staff. However, this could be much improved as some OPMH staff remain in Cilan along with AMH Teams and AMH clinic accommodation. The issues are as follows:
Fragmentation of services leading to difficult / confusing access for service users and carers and less than optimum continuity of care. This makes it more difficult to offer service users the preferred model of care – the ‘wraparound’ approach. If services are under one roof, this enables the person to access the most appropriate element of the service easily and more seamlessly;
Lack of integration between OPMH and AMH clinical teams, leading to extended communication chains, greater duplication and poorer patient outcomes.
There is a need to integrate more with third sector organisations to improve seven day access / crisis support
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
11 | P a g e
Lack of space / capacity: overcrowding & an inability to expand services
In the leased Hafod Lon building, dementia services have more space to expand although the space requires refurbishment. However Cilan, which currently houses OPMH and AMH Team offices and AMH clinical rooms and some Children’s services (offices, record storage and clinic rooms), is cramped and has no room to expand. Some AMH services (Pyschiatrist and Psychologist clinics) have had to re-locate to Alltwen temporarily, as there is no suitable clinic space in Cilan. It is a three storey town house with accessibility issues (no lift). It has recently been risk assessed as requiring substantial investment to bring up to standard.Specific issues as a result of this lack of space include the following:
The lack of space restricts the ability of OPMH and AMH services to expand in terms of clinic space and office space e.g. new post diagnostic dementia group, additional clinics, new Carers’ drop in groups;
Some services have had to move to Alltwen (which is not easily accessible for the Llyn population) including Consultant Psychiatrist & Psychologist clinics and this has impacted negatively on DNA rates
Whilst Dementia services can expand in Hafod Lon, this requires investment and is currently a leased building.
It is not ideal to house OPMH, AMH and Children’s services in close proximity in the same building (Cilan). It would be preferable to house Children’s services separately.
The lack of a dedicated meeting or training room in Cilan limits the ability to carry out Continuing Professional Development for existing staff and inductions for new staff, as well as restricting team meetings, BCUHB liaison groups and patient group meetings.
Lack of parking at current premises
Whilst there is some parking capacity on the Hafod Lon site, there are issues with the single road access from the main road.Cilan MHRC is a town centre site in Pwllheli and has few car parking spaces for service users and carers.
2.3.2 The Risks of continuing Business as Usual
If the Health Board does nothing, then local provision of dementia and adult mental health services in the Llyn area faces the following risks and issues;
Dementia and AMH services will continue to be delivered within unsuitable, unfit for purpose accommodation, with poor accessibility and failing statutory compliance (Cilan)
Less than optimum integration of Dementia and AMH services for the Dwyfor population resulting in services continuing to be delivered from three separate sites / locations, which ultimately results in poor continuity of care
No capacity to expand and develop services – OPMH would like to run an additional post diagnostic group, extra clinics for OPMH and AMH, new carers’ drop-in groups
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
12 | P a g e
Perpetuation of the status quo with dementia services being accommodated in temporary / leased accommodation (not a viable long term option), as Gwynedd Council wish to sell the site ultimately. In addition, the leasing / purchase of an additional site by BCUHB is not in line with its LHSW and Estates Strategies.
Ongoing inefficient use of resources – running sites which are unnecessary, poor quality and non-compliant with statutory regulations
Missed opportunity to utilise ICF capital from Welsh Government to improve services for vulnerable client groups
2.3.3 Potential Business Scope and Key Service Requirements
This business case seeks to address the bringing together of OPMH and AMH services located in the Dwyfor / Llyn peninsula area into one fit for purpose building / new centre on the Ysbyty Bryn Beryl site. The overall aim is to integrate OPMH and AMH services and community teams including local authority and third sector colleagues into one building to improve continuity of care and communication for service users and staff. The new Centre will also provide increased clinical capacity ensuring future service sustainability.This development will also enable the Health Board to rationalise poor quality, community estate, and generate site running cost efficiencies
2.3.4 Investment Objectives, Benefits & Risks
The investment objectives for this project are as follows:
1. To deliver modern, expanded, fit for purpose accommodation in a suitable environment to meet OPMH (Dementia) & AMH service user and staff needs
2. To deliver improved integration of different stage OPMH Dementia services and Adult Mental Health services through co-location which leads to improved continuity of care for service users and better communication between services
3. To ensure strategy alignment with the national Dementia Strategy and Mental Health Measure, the North Wales Mental Health Strategy, the Health Board’s Living Healthier, Staying Well Strategy and the Estates Strategy by investing in the Ysbyty Bryn Beryl site as a Level 1 community hospital / health & wellbeing facility, providing integrated dementia services as locally as possible
4. To improve the quality and efficiency of the estate through the rationalisation of poor sites, reduced backlog maintenance, reduced running costs and achievement of statutory and regulatory compliance
Main benefits Criteria
This section describes the main outcomes and benefits associated with the implementation of the potential scope in relation to business needs. The four categories of benefit are as follows:
The following table summarises the benefits arising from each of the investment objectives which were identified above:
Investment Objectives Stakeholder Group
Benefit
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
13 | P a g e
Patients
Patients will benefit from the improved physical environment in terms of:
Functional suitability;
Dementia friendly space / design;
Increased space for assessment, clinics and activities;
Health Board Staff: clinical / administration
It will improve staff morale and operational management of service; meets national and local policy objectives to transfer services as close to people’s homes as possible.
Investment Objective 1:
To deliver modern, expanded, fit for purpose accommodation in a suitable environment to meet OPMH & AMH service user and staff needs;
Health Community / Others
It supports the delivery of BCUHB’s Living Healthier, Staying Well Strategy & associated Estates Strategy.
Investment Objectives Stakeholder Group
Benefit Category of Benefit
Patients
Patients will benefit from more service integration through improved continuity of care, better communication between services and teams which ultimately leads to improved outcomes for patients.
Investment Objective 2:
To deliver improved integration of different stage OPMH Dementia services and Adult Mental Health services through co-location on a single site;
Health Board Staff: clinical / administration
It meets national and local policy objectives to improve integration through co-location of services.
OPMH & AMH Teams will be co-located with LA OPMH colleagues which will improve integration and communication. Opportunity for staff and services to share facilities – offices, meeting rooms, kitchen, toilets etc
Qualitative benefit
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
14 | P a g e
Health Community / Others
It supports the delivery of WG’s Dementia Strategy and Mental Health Measure, as well as the North Wales Mental Health Strategy in terms of integration and improved accessibility and the Health Board’s LHSW Strategy in terms of Care Closer to Home, Estates Strategy and West Area Operational Plan (CCTH).
Quantifiable benefit
Investment Objectives Stakeholder Group
Benefit Category of Benefit
Patients
Patients will benefit from a local service that is more integrated and less fragmented – easier to access, housed in fit for purpose, quality facilities. This is likely to lead to improved outcomes.
Health Board Staff: clinical / administration
It meets national and local policy objectives to integrate services.
Investment Objective 3:
To support the health service model configuration as set out in the Health Board’s LHSW Strategy and Estates Strategy by investing in the Ysbyty Bryn Beryl site as a Level 1 facility, to provide integrated dementia services as locally as possible
Health Community / Others
It supports the delivery of national strategies for dementia and mental health and BCU’s Mental Health Strategy, the LHSW Strategy, Estates Strategy & West Area Operational Plan 2019/20
Qualitative benefit
Investment Objectives Stakeholder Group
Benefit Category of Benefit
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
15 | P a g e
Patients
Patients will benefit from the improved physical environment in terms of:
Functional suitability;
Fire safety compliance;
Accessibility;
Ease of use for those suffering from Dementia;
Reduced risk of infections.
Health Board Staff: clinical / administration
Staff will benefit from working in an improved physical environment as above. The Health Board will comply with the objectives of the estates condition and performance survey in regard to national performance indicators.
The building will meet key HTM and HBN requirements.
The Estate will be rationalised (Ala Road already closed, future closure of Cilan) and therefore generate running cost efficiencies through the disposal of Ala Road Health Centre and Cilan MHRC
Investment Objective 4:
To improve the quality and efficiency of the Estate through estate rationalisation, by reducing backlog maintenance, reducing running costs and achieving statutory and regulatory compliance;
Health Community / Others
The Llyn / wider Pwllheli community will benefit from a modern purpose-built building.
Quantifiable benefit
Cash releasing benefit
Non-cash releasing benefit
Qualitative benefit
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
16 | P a g e
Potential Main risks
The potential main risks associated with the proposed development are shown below, together with their counter measures.
Main Risk Counter Measure
Strategic
Failure to gain BCUHB approval of Business Case
Planning Dept and Capital Planning Team are aware that business case is being developed.
ICF capital funding has been formally approved by WG for this Project.
Tenders are returned with higher than expected costs (higher than ICF capital sum approved in principle) with potential outcome being the option for a smaller (less integrated) scheme is taken forward
Explore potential with Planning Team for other sources of potential funding (discretionary capital) to bridge any cost differential between tendered cost and ICF approved capital allocation
Maintain close dialogue with WG ICF Capital Lead to clarify whether any additional ICF capital might be available (20/21)
Explore potential for value engineering without significantly affecting project benefits
Explore potential for pursuing alternative option within ICF capital allocation - the purchase and refurbishment of Hafod Lon / Hedd site
Revenue costs are higher than anticipated savings
Consider importance of scheme in terms of service improvement for vulnerable patient groups, estate rationalisation opportunities and the development within overall DCP of the Bryn Beryl site and the need to move forward
Model of Care
Inability to include AMH services within project to further improve integration and estate rationalisation, as well as include some expansion for future flexibility for integrated model of care to develop
Building design to identify shared OPMH / AMH facilities / rooms where appropriate and include expansion space at the outset
Bryn Beryl to have an agreed site development control plan.
Commissioning
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
17 | P a g e
Disruption to services during construction works and during transfer to new Centre
Dementia services to remain on leased Hafod Lon site and AMH services to remain in Cilan MHRC until completion of capital works (extension of Hafod Lon lease period already agreed in principle with Gwynedd Council)
Actual relocation of services to new Centre to take place over a weekend period
BCUHB to continue to monitor targets/normal provision of care.
2.4 Proposed Service Development
The proposal is to develop a new build / extension at the back of the Ysbyty Bryn Beryl site to integrate local OPMH and AMH services into a single centre. This development will address the current service issues outlined above in the Case for Change, as well as the investment objectives already identified. The proposed centre will be located at the rear of the Bryn Beryl site adjacent to the former Llyn Ward building and will provide expanded, purpose built accommodation and a therapeutic environment for dementia and adult mental health service users and staff.The development will allow the co-location of two different stage dementia services (joint with the local authority) together with the Adult Mental Health service to create a new, integrated centre on the Bryn Beryl site. This model will facilitate the delivery of more streamlined care, improved communication between teams and operational efficiencies.
The Older People’s Mental Health and Adult mental Health services to be delivered from the new Centre will be provided by the existing OPMH and AMH Teams. No additional staffing / posts are anticipated to deliver the full range of services from the new Centre.
The bringing together of OPMH and AMH services onto the current leased site Hafod Hedd has already facilitated the closure of the Ala Road Health centre site in Pwllheli. In addition, the new Centre will also facilitate the closure of the Cilan MHRC site in Pwllheli, as well as cease the need to lease the Hafod Lon / Hedd site.
The proposal to develop a new, integrated Dementia and AMH Centre in Bryn Beryl is also fully in line with national strategies for dementia and adult mental health and the North Wales Mental Health Strategy to deliver integrated, more accessible care, as well as the Health Board’s LHSW Strategy in terms of delivering care closer to home and caring for people longer in the community, as well as reflecting the principles within the Estates Strategy with regard to the need to invest in the Bryn Beryl site as a level 1 community hospital / health and social care facility.
This development project will make full use of the approved ICF capital allocation (£812,928) and will generate efficiency savings in terms of running costs and cost avoidance associated with backlog maintenance.
There are five options for consideration and the detail is set out in Section 5 in the Options Appraisal section.
2.5 Areas affected by the Proposal, Inter-dependencies
Is project part of a larger programme ?
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
18 | P a g e
The need to invest in the infrastructure and overall refurbishment of the Ysbyty Bryn Beryl site (as a Level 1 health & wellbeing facility / community hospital) has been identified within the Estates Strategy to support ‘Living Healthier, Staying Well’. Phase 1 of this overall refurbishment commenced in August 2018 using BCUHB discretionary capital monies, to bring the two existing wards together into one newly refurbished ward. This work is almost complete and together with Safe Clean Care monies awarded to pay for piped medical gases on the new ward, and the Hospital League of Friends’ funding for an extension to the x-ray corridor, an extensive refurbishment of the inpatient accommodation has now been achieved.
The development of a new build integrated Dementia Centre in a peaceful, self contained setting at the back of the Bryn Beryl site is the next site redevelopment priority. Such a development will allow the service to provide fully integrated services in fit for purpose premises, to transfer off the leased local authority owned Hafod Lon site and to facilitate the closure and disposal of Cilan. It has already facilitated the vacating of the Ala Road site ready for disposal.
Relevant related initiatives
The proposed new integrated Dementia Centre is planned to be constructed as a new build adjacent to the former Llyn Ward at the back of the Hospital site and fits with the proposed development control plan for the Ysbyty Bryn Beryl site.Once Llyn ward transfers to the new ward at the front of the Hospital, the old accommodation will be used to temporarily accommodate Outpatients and Therapies until the final phase of the Bryn Beryl site redevelopment is completed. Part of the old Llyn Ward accommodation (palliative care single rooms) will need to be demolished to make way for the new Dementia Centre.In addition, consideration is being given to accommodating a new Community Dental Unit adjacent to the proposed Dementia Centre – sharing the peaceful location at the back of the site for vulnerable client groups with dedicated parking. The final phase of the Bryn Beryl site redevelopment will potentially include a redeveloped central core to house a large Outpatient Department, larger Minor Injuries Unit and new Therapies and other clinical support service accommodation.
Inter-dependencies
The project is subject to the following dependencies: Business Case approval from BCUHB and formal approval of ICF capital funding from
the Welsh Government (received 13th November 2019).
ConstraintsThe project is subject to the following constraints: To deliver the project within the allocated capital budget. In terms of ICF capital, this
means ensuring spend of the ICF Year 1 (18/19) carried over allocation and the Year 2 allocation by the end of March 2020 and the Year 3 allocation by end of March 2021.
To deliver the project in compliance with current legislation and guidance.
2.6 Milestones and Quantified Benefits
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
19 | P a g e
Benefits Milestones
1. Patient Care
1.1 Optimum environment in purpose built accommodation for Dementia & AMH service users delivering improved patient care experience
The new facilities will deliver an improved patient care experience from the outset
1.2 Integrated facility will deliver improved continuity of care and better communication between teams leading to improved patient outcomes
Patient outcomes should improve gradually as teams will be able to liaise and interact quickly and more easily (within the same building)
1.3 An integrated centre with co-located services will provide easier access / use for those suffering from dementia and mental health issues
Easier access for service users will be realised on opening of the Centre
2. Quality & Safety
2.1 Quality of care (patient outcomes) should improve as a result of increased integration – through co-location of teams and improved continuity of care
Patient outcomes should improve gradually from the outset as the benefits of co-location become established
2.2 The new facilities will enable a safer environment, as a result of much improved physical accommodation which is purpose built, dementia friendly and fully DDA and fire safety compliant
A safer environment will be provided from the outset
3. Operational
3.1 Clinic / consultation capacity will increase as there will be more clinic rooms available
Clinic attendances for Dementia and AMH will increase as more clinics are established.
3.2 AMH DNA rates should decrease as clinics are provided closer to home
As soon as Psychiatrist Clinic is transferred from Alltwen to the new Centre, DNA rates will start to improve due to decrease in travelling distance
4. Acceptability to patients, staff, public etc
4.1 Patients will benefit from a local service which is more integrated, less fragmented and easier to access
This will be realised from the outset
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
20 | P a g e
4.2 Staff will experience an increase in morale working in an improved physical environment and co-located with other MH teams and colleagues
This will be realised from the outset
4.3 The public will benefit from having a single point of access and focus in Dwyfor for Dementia and AMH services
This will be realised from the outset
5. Accessibility
5.1 One single integrated centre for Dementia and AMH services in Dwyfor will improve ease of access
This will be realised from the outset
5.2 The new accommodation will be fully accessible to all services users and carers and DDA compliant
This will be realised from the outset
5.3 Transferring back services temporarily located in Alltwen due to lack of clinic space will ensure more care is provided closer to home
Benefit realised when services transfer from Alltwen – ideally as soon as Centre opens
5.4 Car parking will be increased and improved
Some limited car parking for the new Centre will be available on completion of the scheme. Additional parking will be available when the final phase of site redevelopment is completed.
6. Effectiveness 1. Patient Care
6.1 The new Centre will provide improved quality of patient care and staff morale
Patient care and staff morale will improve from the outset
6.2 The expanded accommodation for Dementia and AMH will increase patient numbers and ensure future service sustainability
Additional capacity will be available immediately for local services to transfer back from Alltwen and enable services to grow as needed in line with future demand
6.3 The project will deliver efficiency savings through site rationalisation (Ala Road and Cilan), capital receipts through site dispoal and cost avoidance through reduced backlog maintenance
Running cost savings and cost avoidance will be realised immediately on closure of each site
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
21 | P a g e
6.4 The development is fully aligned with the Health Board’s Estates Strategy associated with LHSW – to rationalise poor estate where possible and develop and invest in the Ysbyty Bryn Beryl site as a Level 1 facility
Strategy alignment will be realised from project outset and will continue with the ongoing redevelopment of the Bryn Beryl site
7. Deliverability 2. Quality & Safety
7.1 The detailed design /plans have been signed off and the scheme has been tendered.
Tenders / actual costs ready
7.2 ICF capital allocation of £812K has already been formally approved by WG. Additional capital will be required to cover the shortfall to deliver the preferred option.
Approval of ICF capital allocation received from WG on 13 Nov 2019. Additional capital (to cover shortfall) to be considered as part of this business case submission in Nov / Dec 2019
7.3 Scheme will need to start on site in January 2020 if it is to achieve full spend of ICF carried-over Year 1 (18/19) allocation by end of March 20.
WG have agreed not to allocate Year 2 ICF allocation until Year 3. Proposed start on site January 2020 and completion by March 2021
7.4 Site location adjacent to former Llyn Ward at the back of the Bryn Beryl site is available for new build construction
Site available now
3. Formulation and Short-listing of Options
3.1 Overview of Options
There are 5 options to consider:
(1) Do nothing / status quo optionTo continue to lease the Gwynedd Council owned Hafod Hedd site for Dementia services and to remain on the BCUHB owned Cilan MHRC site (for some OPMH staff & AMH services)
(2) Do Minimum optionTo transfer the dementia services based in Hafod Hedd to the vacated Llyn Ward at the back of the Bryn Beryl site (which was the original proposal as part of the current Phase 1 ward refurbishment plans for Bryn Beryl).
(3) Purchase the Gwynedd Council owned Hafod Hedd site & refurbish to accommodate the two dementia services plus Adult Mental Health from Cilan MHRCTo acquire the Hafod Hedd site from the Council (DV valuation £220K) and refurbish the facilities to meet existing and future OPMH and AMH service provision needs. This
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
22 | P a g e
option allows for some service expansion and the sharing of some facilities between OPMH and AMH. This option includes the rationalisation of the Cilan MHRC site.
(4) Development of integrated Dementia Centre on the Bryn Beryl siteOption 4 involves the building of a new centre on the Bryn Beryl site to co-locate the two dementia services currently housed in Hafod Hedd. This option does not include AMH services and therefore would not incorporate the rationalisation of the Cilan MHRC site.
(5) Development of integrated Dementia & Adult Mental Health Centre on the Bryn Beryl siteOption 5 involves the building of a new centre on the Bryn Beryl site to co-locate the two dementia services together with the Adult Mental Health service (Cilan MHRC). This option allows for ervice expansion and the sharing of some facilities between OPMH and AMH and would incorporate the rationalisation of the Cilan MHRC site.
3.2 Benefits of the Options
The benefits of the options have been grouped under the headings of Patient Care, Quality & Safety, Operational, Acceptability to Patients/Staff/Public, Accessibility, Effectiveness & Deliverability and set out in the tables below:
Options Benefits
1. Patient Care
1.1 Do Nothing / Status Quo Minimal / no disruption / change to current dementia patient care & AMH care – both in less than satisfactory accommodation
The two different stage dementia services have already achieved some integration, however AMH services remain separately located – fragmented for service users
1.2 Do Minimum Slightly improved patient care environment for dementia, but AMH environment remains unsatisfactory for patients
The two different stage dementia services will achieve a degree of integration however AMH services remain separately located – fragmented for service users
1.3 Intermediate – purchase Hafod Hedd & refurbish
Possible Patient accommodation for Dementia &
AMH services will be made more fit for purpose benefiting all service users and staff
Dementia & AMH services will become more integrated leading to better communication between teams and improved patient outcomes
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
23 | P a g e
Site setting in Y Ffor is peaceful and therapeutic
1.4 Intermediate – New Build Dementia only Centre
Possible Accommodation will be purpose built to
meet dementia service users’ needs – better patient experience
New centre will include expansion affording an improved patient care environment
Dementia services will become more integrated leading to better communication between teams and improved patient outcomes
1.5 Maximum – New Build Integrated Dementia / AMH Centre
Preferred Accommodation will be purpose built to
meet dementia & AMH service users’ needs – better patient experience
New centre will include expansion affording an improved patient care environment
Dementia & AMH services will become more integrated leading to better communication between teams and improved patient outcomes
2. Quality & Safety
2.1 Do Nothing / Status Quo Leased building meets statutory requirements but is in need of more extensive upgrade to ensure quality patient environment
2.2 Do Minimum Meets Q&S minimally
Slight upgrade to accommodation for the two dementia services only – will minimally meet statutory requirements
2.3 Intermediate – purchase Hafod Hedd & refurbish
Meets Q&S requirements
Significant refurbishment will ensure that accommodation for dementia and AMH services is fit for purpose – meets all statutory requirements
Re-design / refurb limited to original building footprint
2.4 Intermediate – New Build Dementia only Centre
Meets Q&S requirements
Centre will be purpose built, dementia friendly and fully compliant with statutory regulations
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
24 | P a g e
Patient environment will be able to be designed to meet the needs of dementia service users
2.5 Maximum – New Build Integrated Dementia / AMH Centre
Meets Q&S Requirements
Centre will be purpose built, dementia and AMH friendly and fully compliant with statutory regulations
Patient environment will be able to be designed to meet the needs of dementia & AMH service users
3. Operational
3.1 Do Nothing / Status Quo Services would not be able to remain long term in a leased Hafod Hedd building – a permanent solution would need to be found.
3.2 Do Minimum Dementia services would be able to run fully from former Llyn Ward area but no expansion space available for future. AMH services would continue to run out of Cilan, which does not meet statutory regulations. Opportunity is missed to bring services back from Alltwen.
3.3 Intermediate – purchase Hafod Hedd & refurbish
Possible
Both Dementia and AMH services would be able to further integrate and fully run from the Hafod Hedd refurbished site.
3.4 Intermediate – New Build Dementia only Centre
Possible
Dementia services would fully operate and integrate from the new purpose built facilities with expansion space for future.
AMH services would continue to run out of Cilan, which does not meet statutory regulations.
Opportunity is missed to bring services back from Alltwen.
3.5 Maximum – New Build Integrated Dementia / AMH Centre
Preferred
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
25 | P a g e
Both Dementia and AMH services would be able to fully operate and integrate from the new purpose built facilities.
Expansion space would be incorporated and clinics temporarily located in Alltwen (due to lack of space in Cilan) would be transferred back
4. Acceptability to patients, staff, public etc
4.1 Do Nothing / Status Quo Not acceptable long term
Whilst the current set-up in Hafod Hedd is an improvement on Ala Road, the accommodation requires significant refurbishment to bring it up to modern health care standards for patients and staff.
4.2 Do Minimum Minimally acceptable
The two dementia services would be brought together with a limited refurbishment of the old ward accommodation.
There would be less space overall for patients and staff than in staying on the Hafod Hedd site.
4.3 Intermediate – purchase Hafod Hedd & refurbish
Acceptable
Patients and staff would benefit from a much improved integrated environment for Dementia and AMH services with more space and light.
4.4 Intermediate – New Build Dementia only Centre
Acceptable
Dementia patients and staff would benefit from a purpose built, integrated environment for Dementia services with more space and light and the potential for a dementia sensory garden outside the Centre.
4.5 Maximum – New Build Integrated Dementia / AMH Centre
Acceptable
Dementia and AMH patients and staff would benefit from a purpose built, integrated environment for Dementia & AMH services with more space and light and the potential
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
26 | P a g e
for a dementia sensory garden outside the Centre.
5. Accessibility
5.1 Do Nothing / Status Quo Accessible for Dementia, poor access for AMH
Present accommodation requires refurbishment but meets statutory accessibility regulations. Single lane entry road to Hafod Hedd site not ideal.
5.2 Do Minimum Accessible for Dementia, poor access for AMH
Limited refurb of part of former Llyn Ward will ensure fully accessible for Dementia patients and staff. AMH services in Cilan will continue to breach regulations in terms of accessibility (with no lift and three floors). Access to back of site not straightforward with limited close parking for service users / carers.
5.3 Intermediate – purchase Hafod Hedd & refurbish
Accessible
Significant refurb of Hafod Hedd will ensure full accessibility for Dementia and AMH service users and staff and will be compliant with statutory regulations regarding access.
5.4 Intermediate – New Build Dementia only Centre
Accessible for Dementia, poor access for AMH
A purpose built centre for Dementia will ensure the accommodation is fully accessible for Dementia service users and staff and fully compliant with statutory regulation relating to access.
Some additional car parking close to the new Centre will be provided and further spaces will be delivered on completion of the overall site redevelopment
However, AMH service users and staff will remain in Cilan where accessibility is not satisfactory. There is no lift (3 storey building) and no car parking.
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
27 | P a g e
5.5 Maximum – New Build Integrated Dementia / AMH Centre
Accessible
A purpose built centre for Dementia will ensure the accommodation is fully accessible for Dementia & AMH service users and staff and fully compliant with statutory regulation relating to access.
Some additional car parking close to the new Centre will be provided and further spaces will be delivered on completion of the overall site redevelopment.
6. Effectiveness
6.1 Do Nothing / Status Quo Not effective
This will not be an effective long term option for service users and staff, as it is a leased site and in need of refurbishment.
6.2 Do Minimum Not effective
This option does not include sufficient future proofing in terms of space and does not include AMH services therefore there is no site rationalisation.
6.3 Intermediate – purchase Hafod Hedd & refurbish
Partly effective
This is a partly effective option in that it fully integrates both dementia and AMH services in a significantly refurbished building.
However it is not in line with BCUHB estates strategy, as it involves site acquisition as well as site rationalisation.
6.4 Intermediate – New Build Dementia only Centre
Partly effective
This is a partly effective option in that it fully integrates dementia services in a purpose built new Centre on the existing Bryn Beryl site – in line with Health Board strategy.
It does not address AMH accommodation issues in Cilan and therefore does not deliver site rationalisation.
This is not an effective option in terms of value for money. There are minimal capital
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
28 | P a g e
cost (build) savings by not accommodating AMH services within the Dementia Centre.
6.5 Maximum – New Build Integrated Dementia / AMH Centre
Effective
This is the most effective option in that it fully integrates both dementia and AMH services in a purpose built new centre on the existing Bryn Beryl site,
It is in line with LHSW and Estates Strategies, delivering services closer to home from a single site and from an existing level 1 community hospital / health and wellbeing site Bryn Beryl
It achieves the rationalisation of the Cilan site.
7. Deliverability
7.1 Do Nothing / Status Quo Not deliverable
This option is not viable. Gwynedd Council ultimately wish to sell the Hafod Hedd site, so a long term lease is not an option.
This option is also not preferable for BCUHB as it would incur ongoing revenue (lease & service) costs.
7.2 Do Minimum Not deliverable
The ‘window’ of opportunity for this option has probably now passed. Other services have now transferred to the former Llyn Ward building and one half of the accommodation is now being explored to permanently house a new Community Dental Unit.
7.3 Intermediate – purchase Hafod Hedd & refurbish
Deliverable
The site purchase and refurbishment of Hafod Hedd could be completed within the ICF capital allocation.
Refurbishment could be undertaken in phases allowing dementia services to continue on site whilst works in progress, moving across AMH services from Cilan on completion
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
29 | P a g e
By closing Cilan, the Health Board will address the site risks regarding health & safety and the significant backlog maintenance requirements, as well as achieving site rationalisation
7.4 Intermediate – New Build Dementia only Centre
Deliverable
The site is available (back of Bryn Beryl) however the capital works would not be able to be completed within the ICF capital allocation – potential £300K shortfall (PTE £1,258,811) subject to approved tender cost. Additional capital would be required from discretionary capital in 2020/21.
All works could be completed in single phase with dementia services transferring from Hafod Hedd on completion
As this option does not include AMH services, Cilan would be remain operational – an inefficient unfit for purpose site.
7.5 Maximum – New Build Integrated Dementia / AMH Centre
Deliverable
The site is available (back of Bryn Beryl) however the capital works would not be able to be completed within the ICF capital allocation – potential £497K shortfall (Tendered cost) £1,309,989). The additional capital would be required from discretionary capital in 2020/21.
All works could be completed in single phase with dementia & AMH services transferring from Hafod Hedd and Cilan on completion
By closing Cilan, the Health Board will address the site risks regarding health & safety and the significant backlog maintenance requirements, as well as achieving site rationalisation
Based on the above information, two options have been discounted as impracticable in terms of Deliverability and Effectiveness – Option 1 – cannot lease the Hafod Hedd site long term and Option 2 – Llyn Ward not now available to accommodate OPMH services) and have therefore been excluded at this stage. The following short list of options has emerged:
Option 3: Intermediate – Purchase Hafod Hedd & refurbishOption 4: Intermediate – New Build Integrated Dementia Centre
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
30 | P a g e
Option 5: Maximum – New Build Integrated Dementia & AMH Centre
3.3 Cost & Resource information for the Options
The table below summarises the resource requirements and costs associated with the three options:-
Resources requirements & Costs
Option 3 – Purchase Hafod Hedd & Refurbish
Option 4 – New Build Integrated Dementia Centre
Option 5 – New Build Integrated Dementia & AMH Centre
Works Cost £356,000 £800,000 £890,157.26
Non-works cost £254,000 (Inc. Building Purchase)
£20,700 £45,750
External Fees £32,192 £58,100 £59,100
Internal Project costs £3,560 £7,800 £7,800
Information Technology costs
£25,000 £25,000 £25,000
Equipment costs £50,000 £50,000 £50,000
Contingency £17,800 £50,000 £50,000
VAT together with assessment of recoverable VAT
£76,560 £174,150 £182,181.45
Total Costs £815,112 £1,185,800 £1,309,989.09
Based on the above cost and resource information, it should be noted that whilst Option 3 is achievable within the ICF capital allocation approved by WG (£812,928), options 4 and 5 both require an additional capital allocation to cover the shortfall. However Option 4 delivers poor value for money in that the overall capital cost is only slightly reduced and it does not include Adult Mental Health services so does not deliver full integration or include the rationalisation of the Cilan site.
3.4 Key Assumptions and dependencies of the Options
Option 3 (Purchase & refurbishment of Hafod Hedd site) assumes the Gwynedd local authority owned site is still available for purchase. It also assumes there are no significant issues with planning and statutory approvals.Options 4 & 5 (new build at back of Bryn Beryl site) also assume no significant issues with planning permission and statutory approvals, as well as connections to existing site infrastructure.
3.5 Options Appraisal
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
31 | P a g e
The preferred and possible options detailed in the Benefits tables in Section 3.2 have been carried forward onto the short list for further appraisal and evaluation. All the options that were discounted as impracticable have been excluded.
3.5.1 Criteria for Assessing the Options
The table and narrative below summarises the assessment of each option against the investment objectives:
Reference to: Option 3 Option 4 Option 5
Description Purchase Hafod Hedd & Refurbish
New Build Integrated Dementia Centre
New Build Integrated Dementia & AMH Centre
Investment Objectives
1. Expanded, fit for purpose estate
2. Improved integration
3. Alignment with Health Board Strategy
4. Improve quality & efficiency of estate
3.5.2 Selection of Preferred Option
All 3 options for consideration provide improved, expanded, fit for purpose accommodation, although Options 4 & 5 (as new builds) will be purpose built rather than refurbishment within an existing footprint (Option 3).All 3 options deliver improved integration, however Options 3 and 5 deliver full integration between Dementia and AMH services.Options 4 and 5 are in line with BCU’s LHSW Strategy delivering integrated care closer to home, however in terms of estate rationalisation, only Option 5 delivers fully in terms of providing a new Centre for both Dementia and AMH services on an existing Health Board level 1 community hospital / health & wellbeing centre site, thereby releasing the Cilan MHRC site. Option 3 also releases the Cilan site but involves the acquisition of a new site.All 3 options improve the quality of estate to varying degrees, however Option 5 remains the preferred option in terms of efficiency, as it achieves the rationalisation of poor community estate.
Overall, taking into account the option benefits in Section 3.2, the cost and resource information in Section 3.3 and an assessment against the investment objectives above, Option 5 – a new build Integrated Dementia and Adult Mental Health Services Centre on the Bryn Beryl site represents the preferred option in terms of improved patient care, integration, effectiveness, alignment with national and Health Board strategy and efficient use of resources (value for money).
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
32 | P a g e
4 The Financial Case 4.3Capital Cost of the preferred option
£Works Cost £890,157.26Fees
- External fees- Internal project costs
£59,100£7,800
Non Works Costs £45,750Equipment
- Equipment- Informatics
£50,000£25,000
Contingency £50,000VAT £182,181.45
Sub Total £ 1,309,989.09Less Recoverable VAT
Total £
4.4Revenue consequences
The assumption is that the revenue costs relating to this business case are all estate and facilities related. All other service staffing (OPMH and AMH) existing costs will move to the new Centre and the intention is to continue to look for efficiencies on an ongoing basis e.g. in terms of admin/reception and joint working opportunities, however this would in reality contain capacity/growth.
The annual details with regard to estates are as follows:
Site / building Annual running costs
Note
Hafod Hedd (temporary site) running costs £19,597.81 BCU is not being charged full costs by Gwynedd LA at the moment but these are are the indicative annual costs.
Cilan MHRC running costs £10,823.24
Savings from closure of Ala Road site £45,766.15 Most of these savings have already been realised in 18/19 however the site has not been sold yet
Do Nothing / Status Quo option revenue costs
£30,421.05 (Hafod Hedd + Cilan)
Preferred Option estimated revenue costsNew Integrated Dementia & AMH Centre extension (360m²)
£24,440.00
Projected overall Project savings £5,981.05 Transition costs will be linked to the ultimate
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
33 | P a g e
On delivery of new Centre and closure / disposal of Cilan (2021/22)
closure and sale of Ala Road & Cilan sites
4.5Expenditure Profile
Total Year 18/19
Year 19/20
Year 20/21
Year 21/22
Works Cost 890,157 0 100,000 765,157 25,000Non-works Cost 45,750 2,500 11,000 30,750 2,500External Fees 59,100 32,000 20,000 12,900 2,000
Internal Project Costs 7,800 0 2,600 2,600 2,600Information Technology
Costs 25,000 0 0 25,000
Equipment Costs 50,000 0 0 50,000 Contingency 50,000 0 0 50,000
VAT (Inc payable Vat) 182,181.45 0 20,000 159,181 3,000 Total 1,309,989 34,500 151,00 1,092,988 32,500
5 Project Management
5.3Governance
The project management arrangements for capital projects are outlined in the Procedure Manual for Managing Capital Projects, which was adopted by the Health Board in May 2015.
5.4 Project Plan – Implementation Timeline
The key dates and milestones associated with the project are detailed in the table below:
Milestones Target DateWG approval of ICF capital allocation Sep 2019BCUHB approval of Business Case Oct / Nov 2019Commence on site January 2020Handover / Commissioning December 2020Project Closure December 2020
6 Critical Assumptions, Risk and Issues
The Health Board is required to undertake a comprehensive assessment of the risks associated with the Preferred Option.
The risk management strategy is based upon the following principles:
Identifying the possible risk in advance, putting in place mechanisms to minimise the likelihood of risks occurring and their associated adverse effects
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
34 | P a g e
Having processes in place to ensure up to date, reliable information about risks is available, and establishing an ability to effectively monitor risks
Establishing the right balance of control is in place to mitigate the adverse consequences of risks, should they materialise
Setting up decision-making processes, supported by a framework of risk analysis and evaluation
The Project Board has identified and quantified the key risks associated with the preferred option. All identified risks have been apportioned to either the Health Board or SCP and mitigating strategies identified in the risk register. This will be monitored on a monthly basis by the Project Board for the life of the project. It is the project manager’s responsibility to manage the risk register.
7 Conclusions and Recommendations
It is concluded that the preferred option to develop a new build Integrated Dementia & Adult Mental Health Centre on the Ysbyty Bryn Beryl site is approved, as it delivers a full range of benefits in terms of the improvement of patient care as outlined within this case, is strategically aligned to both national and organisational strategies, and secures financial efficiencies related to estate rationalisation.
It is proposed that the development is funded from a combination of Welsh Government ICF capital and Health Board discretionary capital, as set out within the case. It is envisaged that the savings generated by closing two community sites (Ala Road savings already realised) and the Cilan savings will be offset against the running costs of the new Centre. In terms of revenue costs, Option 5 is less expensive than the Do Nothing / Status Quo option and will ultimately deliver overall annual savings of approximately £6K .
8 Project Evaluation8.1 Monitoring of Project Progress
The project will follow the monitoring guidelines set out in the Capital Manual. A monthly project board meeting will be held and chaired by the Project Director. Cost and Highlight Reports will be prepared by the Project Manager for consideration and monitoring at the Project Board meetings. A Service User Group will be held on an ad hoc basis to include representation from key statutory services (Fire, Health & Safety, Operational Estates, Facilities etc) as well as OPMH / AMH service users to assist in agreeing the design detail and operational management of the new building.
Whilst building work / construction is in progress, there will be monthly contract progress meetings with the Contractor, Project Manager and Design Team to review progress to date and to address any issues causing concern or requiring action. Design Team meetings will be held with representatives as and when required. Any decisions required from the meetings referred to above will be escalated to the Project Board to agree the way forward.
The Project Board will report on progress and cost to the West Area Leadership Team and to the Capital Management Team meeting. The Project Manager will provide monthly cost and highlight reports for the Project to the Project Director and Assistant Director of Strategy – Capital And Planning.
Betsi Cadwaladr University Health BoardCapital Business Case Guidance and Template
35 | P a g e
8.2 Post Project Evaluation
The Health Board is fully committed to ensuring that a thorough and robust post-project evaluation is undertaken at key stages in the process to ensure that positive lessons can be learnt from the project. The lessons learnt will be of benefit to:
The Health Board – in using this knowledge for future projects including capital schemes Other key local stakeholders – to inform their approaches to future major projects The NHS more widely – to test whether the policies and procedures which have been
used in this procurement effective
NHS guidance on PPE has been published and the key stages which are applicable for this project are:
Evaluation of the project procurement stage Evaluation of the various processes put in place during implementation Evaluation of the project in use shortly after the new unit is opened Evaluation of the project once the new unit is well established
1 FP19.298c EqIA screening form BB Dementia AMH Centre (003).doc
1
EQUALITY IMPACT ASSESSMENT FORMSPARTS A and B: SCREENING AND OUTCOME REPORT
Introduction:These forms have been designed to enable you to record, and provide evidence of how you have considered the needs of all people (including service users, their carers and our staff) who may be affected by what you are writing or proposing, whether this is:
a policy, protocol, guideline or other written control document; a strategy or other planning document e.g. your annual operating plan; any change to the way we deliver services e.g. a service review; a decision that is related to any of the above e.g. commissioning a new service or decommissioning an existing service.
This is not optional: Equality Impact Assessment is a specific legal requirement on public sector organisations under equalities legislation and failure to comply could result in a legal challenge to a decision or strategy. More importantly, equality impact assessment helps to inform better decision-making and policy development leading to improved services for patients. This form should not be completed by an individual alone, but should form part of a working group approach.
The Forms:You must complete:
Part A – this is the Initial Screening that is always undertaken and consists of Forms 1 to 3; these forms are designed to enable you to make an initial assessment of the potential impact of what you are doing, and decide whether or not you will need to proceed to a Full Impact Assessment (Part C);
AND Part B – this is the Outcome Report and Action Plan (Form 4) you will need to complete whether or not you proceed to a Full Impact
Assessment;
Together, these forms will help to provide evidence of your Impact Assessment and how you have shown “due regard” to the duties.
You may also need to complete Part C (see separate Form) – if parts A and B indicate you need to undertake a Full Impact Assessment. This enables you to fully consider all the evidence that is available (including engagement with the people affected by your document or proposals) to tell you whether your document or proposal will affect people differently. It also gives you the opportunity to consider what changes you may need to make to eliminate or mitigate any adverse or negative impact you have identified.
2
Remember that these forms may be subject to external scrutiny e.g. under a Freedom of Information request.
Once completed, the EqIA Forms should accompany your document or proposal when it is submitted to the appropriate body for approval.
Part A Form 1: Preparation
1.What are you assessing i.e. what is the title of the document you are writing or the service review you are undertaking?
The capital business case for the development of a new integrated Dementia and Adult Mental Health Centre on the Ysbyty Bryn Beryl site. The case presents an exciting opportunity to develop a fit for purpose combined facility that will operate as an integrated, co-located and joint (with local authority) model of different stage dementia services with adult mental health services to meet the specific needs of the local population.
2.Provide a brief description, including the aims and objectives of what you are assessing.
The proposal is to provide a modern, fit-for-purpose, fully compliant and accessible building to deliver an improved therapeutic environment for local Older People’s Mental Health (OPMH) and Adult Mental Health (AMH) service users and staff on the Bryn Beryl site (previously located in very poor conditions in 3 separate buildings). The co-location of OPMH and AMH services and staff in one centre, as well as with local authority OPMH colleagues will significantly improve the integration of and communication between services, which will positively impact on the delivery of patient care.
It is proposed to use a combination of ICF capital monies and Health Board discretionary capital to fund the new integrated Dementia Centre. The total capital cost is £1,309,989.
Key Objectives
Modern, fit for purpose accommodation – we want to provide purpose built facilities and a suitable therapeutic environment to meet the needs of our vulnerable OPMH and AMH client groups
Improved integration - Integrating dementia and AMH services in one building enables people to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care – ultimately
3
increasing the number of patients cared for within their own communities with reduced need for hospital admission. Integration also significantly improves communication between community teams and agencies.
Reduced service fragmentation - OPMH and AMH services in Dwyfor are currently fragmented across previously three (and now two) sites. One centre will provide a single point of access.
Increased clinical capacity through expanded accommodation to see more dementia and AMH service users locally in line with the Mental Health Measure, the Health Board’s Care Closer to Home strategic objective and projected future demand.
Strategic alignment – Building a new integrated centre on the Bryn Beryl site is in line with BCUHB strategic direction (Living Healthier, Staying Well) in terms of Care Closer to Home - caring for people with dementia / AMH conditions for longer in their own communities, as well as the North Wales Mental Health Strategy (promoting integration and less fragmentation) and the Health Board’s Estates Strategy – investing in Bryn Beryl as a level 1 Health & Wellbeing hospital / centre.
Rationalise estate and generate efficiencies - We would like to get rid of existing, poor community estate and replace with modern, fit for purpose, efficient facilities in line with the Health Board’s Estate Rationalisation Strategy
Project Outcomes:
The project outcomes can be quantified as follows:
Modern, expanded, fit for purpose accommodation to meet OPMH (Dementia) & AMH service user and staff needs
More integrated and improved patient care for OPMH Dementia and Adult Mental Health service users as a result of co-location - leading to improved continuity of care for service users, less duplication and better communication between services
Increased capacity by up to 10-15% to deliver both group and individual therapy as required under the Mental Health Measure and in line with increasing demographic demand
Care closer to home - supporting more accessibility in the community as set out in the national Dementia Strategy, the Mental Health Measure, the Health Board’s Living Healthier, Staying Well (LHSW) Strategy and the Estates Strategy through investment in the Ysbyty Bryn Beryl site as a Level 1 community hospital / health & wellbeing facility,
4
providing integrated dementia and AMH services as locally as possible Estate efficiency and rationalisation - improving the quality and efficiency of the estate
through the rationalisation of poor community sites, reduced backlog maintenance, reduced running costs and achievement of statutory and regulatory compliance.
3.Who is responsible for the document/work you are assessing – i.e. who has the authority to agree/approve any changes you identify are necessary?
A Dementia Centre Project Board has been established to oversee the development of the scheme since May 2019 and this Board reports to the WALT (West Area Local Team). The business case will be seeking approval from the Health Board’s Estates Improvement Group, the F&P Committee and the Board. In terms of design changes, these will be discussed and agreed at Project Board level (ensuring within overall budget).
4.Is the Policy related to, or influenced by, other Policies/areas of work?
The business case links into multiple national and organisational strategies and legislation: The national Dementia Strategy focuses on the need to provide high quality, person-centred care to people living with dementia and those affected by it, to support the creation of dementia-friendly communities and to listen and respond to people with dementia. The provision of facilities and a therapeutic environment that are purpose built to meet the needs of people with dementia is paramount. The model focuses on the need to ‘support people to remain self-caring avoiding admission to hospital’ - whether general or psychiatric - whenever possible and facilitate timely discharge from hospital (with the right care or support at home), as an admission to hospital can be devastating for a person with dementia.
Welsh Government’s Mental Health Measure requires health boards to provide timely assessments and interventions to significant numbers of individuals in the locality. Current estate provision is limited in terms of capacity. This provision will provide much increased capacity to deliver group therapy and individual care close to home.
The North Wales Mental Health Strategy aims to ensure there is promotion of health and well-being for everyone; prevention of mental ill-health and early intervention when needed and the delivery of joined-up and recovery-focused care. The Strategy focuses on integrating as much as possible – across disciplines, across agencies and across services, in both planning and delivering services, with a view to reducing fragmentation.
A key strand of the Health Board’s ‘Living Healthier, Staying Well Strategy’ is the delivery of Care Closer to Home. An integrated centre for OPMH and AMH services will enable service users to access the most appropriate element of the service easily and seamlessly, providing
5
continuity of care, and a 'wraparound' approach to care. People can 'step up and step down' within the services depending on their need at the time, a flexible approach within both the adult mental health service and the dementia service. Separate locations and buildings for OPMH and AMH services are currently fragmenting services for service users and their families. An integrated centre for dementia and adult mental health services will provide easier access for local people to ensure.
New Programme for Government and the NHS Plan The Welsh Government’s new Programme for Government Taking Wales Forward 2016-21 and NHS Plan set out a programme for health and wellbeing in Wales focussing on improving our healthcare services; our healthcare staff; being healthy and active; our mental health and wellbeing; the best possible start for children and care for older people.
Well-being of Future Generations (Wales) Act 2015 The Welsh Government published the Well-being of Future Generations (Wales) Act in April 2015 to improve the social, economic, environmental and cultural well-being of Wales. It aims to make public bodies think more about the long-term, work better with people and communities and each other and look to prevent problems and take a more joined-up approach. The Act sets out seven well-being goals, and five ways of working in order to support the implementation of these goals: a prosperous Wales a resilient Wales a healthier Wales a more equal Wales a Wales of cohesive communities a Wales of vibrant culture and thriving Welsh Language a globally responsible Wales
Social Services and Well-being (Wales) Act 2014 A number of actions in this delivery plan have been developed to further embed the requirements of the Social Services and Well-being (Wales) Act 2014, which came into force on the 6 April 2016. The Act places a duty on health boards and local authorities to jointly undertake an assessment of the local population’s care and support needs, including the support needs of carers. The population assessment is intended to ensure that health boards and local authorities produce a clear and specific evidence base to inform various planning
6
and operational decisions, including Integrated Medium Term Plans.
Population Needs Assessment Population needs assessments are critical to the development of good long-term strategies. The Well-being of Future Generations Act makes it clear that this needs to be done in conjunction with other public service bodies, such as local authorities, education and housing. Population needs assessment underpin the local well-being plan, developed by public service boards. Health and Social Care Inequalities Delivering the actions set out in the plan will make a positive contribution to the Welsh Government’s equality agenda objectives through a commitment to identify and meet the needs of all groups in relation to stroke, including those from disadvantaged backgrounds who are statistically more likely to be living in poverty and be at greater risk of heart disease.
Welsh Language The objectives of ‘More than just words’ the Welsh Government’s strategic framework for Welsh language services in health, social services and social care have also been embedded into the plan through actions that make it clear all organisations associated with service delivery must ensure that such services are available to those who wish to communicate in Welsh.
5.Who are the key Stakeholders i.e. who will be affected by your document or proposals?
The key stakeholders are:- The general public, including patients & carers needing to access Dementia and AMH
services. BCUHB Clinicians, Managers and Staff Gwynedd Local Authority, Social services and elected members Third Sector and voluntary organisations Community Health Council Public Health Wales Welsh Government Ysbyty Bryn Beryl League of Friends Independent Contractors including GPs and Pharmacists Welsh Ambulance Services Trust Community Transport Local Town and Community Councillors
7
Assembly Members and Members of Parliament Trade union representative
6.
What might help/hinder the success of whatever you are doing, for example communication, training etc?
If the Health Board decides not to fund the business case capital shortfall from discretionary capital, this will prevent the scheme progressing. It will then be necessary to review with the Director of Estates the available options and the preferred way forward.
Communication on a local and regional level will be crucial to raise awareness of the new Integrated Dementia and AMH Centre. If the business case is approved, a communication campaign will be undertaken by the Health Board’s Communication Officer for the West e.g. joint press releases, promoting on various social media platforms and internal staff communications.
8
Form 2: Considering the potential impact of your document, proposals etc in relation to equality and human rights
Potential Impact by Group. Is it:-
Characteristic or other factor
to be considered
Positive (+) Negative (-)Neutral (N)No Impact/Not applicable (N/a)
HighMedium or Low
Please detail here, for each characteristic listed on the left:- (1) any Reports, Statistics, Websites, links etc. that are relevant to your document/proposal and
have been used to inform your assessment; and/or (2) any information gained during engagement with service users or staff; and/or any other
information that has informed your assessment of Potential Impact.
Age Positive HighIt is anticipated that the impact for adults / older people will be positive and high. The new integrated Centre will provide purpose built, expanded facilities for Dementia and AMH service users. It will provide a much-improved therapeutic environment and will ensure services for these vulnerable clients are delivered closer to home.
Dementia and AMH services are available for all people over the age of 18 years. At the age of 17.5 years, there is a handover between CAMHS and AMH to ensure a smooth transition for young people.
Evidence includes:
9
Population projections, persons aged 18 years and over, by age group, Gwynedd, 2015 to 2035
Disability Positive HighThe new Centre will positively impact those with disabilities, as it will meet all statutory and DDA regulations ensuring full accessibility. The improved therapeutic environment and signage within the new centre will also adhere to all dementia friendly requirements. Car parking for service users, carers and community transport will be an improvement on existing arrangements and will further improve with the future redevelopment of the Bryn Beryl site. Patients with a disability have the same access to Dementia and AMH services as everyone else.
2015 2020 2025 2030 203518 to 24 15,070 14,370 14,070 14,430 13,82025 to 34 13,480 16,500 18,110 17,110 17,21035 to 44 12,820 11,870 12,960 15,940 17,55045 to 54 16,100 14,820 12,680 11,750 12,84055 to 64 14,980 15,930 16,220 15,020 12,98065 to 69 8,180 6,870 7,280 7,830 7,63070 to 74 6,520 7,450 6,280 6,690 7,24075 to 79 4,880 5,700 6,580 5,580 6,00080 to 84 3,860 3,980 4,760 5,550 4,76085 and over 3,870 4,420 5,030 6,150 7,560Total population aged 18 and over 99,780 101,910 103,960 106,050 107,570Source: Welsh Government Statistical Unit (Daffodil)Figures may not sum due to rounding. Crown copyright 2014
10
Evidence includes:
Number of people registered as having a learning disability, by age group, Gwynedd, 2018-19
Under 16 years: 8116-64 years: 51465+: 71Total: 666
11
Number & percentage of people of working age who report having a disability, Wales & Betsi Cadwaladr UHB unitary authorities, 2013
Persons with learning disabilities*, by accommodation type, Betsi Cadwaladr UHB unitary authorities, 2015/16
Gender Reassignment
Neutral No Impact No anticipated differential impact
Evidence includes:Following section taken from North Wales Local Authority Summary Equality Profile Isle of Anglesey:-
Data on gender reassignment is not routinely collected. The section below is taken from a 2009
Number PercentageWales 409,900 22.5Isle of Anglesey 8,000 20.4Gwynedd 12,300 17.5Conwy 12,600 20.3Denbighshire 13,000 24.7Flintshire 15,700 17.3Wrexham 14,300 17.6Source: Office for National Statistics
Total community placements
Health service accommodatio
n (inc. hospitals/host
els etc.)
Local authority residential
accommodation (staffed or unstaffed)
Private or voluntary residential
accommodation (staffed or unstaffed)
Other accommodation
Total placements
Isle of Anglesey 274 3 6 29 0 312Gwynedd 614 3 21 41 20 699Conwy 540 18 2 69 27 656Denbighshire 469 10 2 64 3 548Flintshire 685 0 0 52 0 737Wrexham 455 12 1 55 14 537Source: StatsWales (WG)* The register of people with learning disabilities is a voluntary register, and therefore may be an underestimate the total number of people with learning disabilities
12
report from the Office of National Statistics, entitled ‘Trans Data Position Paper’, which defines transgender as an ‘umbrella term referring to individuals whose gender identity or gender expression falls outside of the stereotypical gender norms’.
Currently, there are huge inconsistencies in population estimates of both transsexual people and the less clearly defined trans community. The Home Office ’Report of the interdepartmental working group on transsexual people‘ based on research from the Netherlands and Scotland, estimates that there are between 1,300 and 2,000 male to female and between 250 and 400 female to male transsexual people in the UK. However, Press for Change estimate the figures at around 5,000 post-operative transsexual people. Further, GIRES claims there are 6,200 people who have transitioned to a new gender role via medical intervention and approximately 2,335 full Gender Recognition Certificates have been issued to February 2009.
The figures are more diverse when looking at the trans community in the UK, where estimates range from 65,000 to 300,000. To put this in context, the former figure is close to the population of Inverness, while the latter is similar to the population of Cardiff (51,000 and 305,000 respectively). The variation above demonstrates that it is important to find accurate measures of the trans population at local and national levels. The absence of official estimates makes it difficult to ascertain the level of discrimination, inequality or social exclusion faced by the trans community.
Marriage & Civil Partnership
Neutral No Impact No anticipated differential impact.
Evidence includes:
Census 2011 - Marital and civil partnership status, unitary authorities in North Wales – All usual residents aged 16 years and over
All categories: Marital and
civil partnership
status
Single (never
married or never
registered a same-sex
civil partnership)
Married
In a registered same-sex
civil partnership
Separated (but still legally
married or still legally in a same-sex civil
partnership)
Divorced or formerly in a same-sex
civil partnership
which is now legally dissolved
Widowed or surviving partner from a
same-sex civil
partnership
Isle of Anglesey 57,890 17,245 28,385 90 1,210 5,694 5,266
13
Gwynedd 100,923 36,781 44,330 140 1,906 9,049 8,717Conwy 96,102 27,729 46,379 197 2,229 10,215 9,353Denbighshire 76,781 23,413 36,950 138 1,790 8,043 6,447Flintshire 123,862 37,581 62,308 167 2,770 11,962 9,074Wrexham 109,026 35,546 52,154 151 2,179 10,877 8,119
Pregnancy & Maternity
Positive HighIt is anticipated that there will be a high positive impact for this group because there will be improved access for service users and carers, in terms of both the physical building and increased numbers of clinics. Accommodation will be available if required for those wishing to breast feed.
Race / Ethnicity
Neutral No Impact
No anticipated differential impact.
Evidence includes:
Number of live births
Number of live births
2005 1,263 56 (53 to 59) 32,590 56 (55 to 57)
2006 1,332 59 (56 to 62) 33,623 57 (57 to 58)
2007 1,254 56 (53 to 59) 34,392 59 (58 to 59)
2008 1,276 57 (54 to 60) 35,644 61 (60 to 61)
2009 1,338 60 (56 to 63) 34,938 60 (59 to 60)
2010 1,272 57 (54 to 60) 35,945 62 (61 to 62)
2011 1,319 60 (56 to 63) 35,604 61 (61 to 62)
2012 1,327 60 (57 to 63) 35,238 61 (61 to 62)
2013 1,229 56 (53 to 60) 33,742 59 (58 to 60)
2014 1,175 54 (51 to 58) 33,541 59 (58 to 60)
CI=Confidence Interval
Produced by Public Health Wales Observatory, using PHB & MYE (ONS)
General fertility rate (GFR)*, Gwynedd and Wales, 2005-2014
Gwynedd Wales
GFR* (95% CI) GFR* (95% CI)
*GFR is the number of live births per 1,000 females aged 15-44
14
Religion or Belief
Neutral No Impact
No anticipated differential impact. Patients and carers across the religious denominations will have the same access to spiritual support as required.
Evidence includes:
Figure 17: Religious denominations, Betsi Cadwaladr UHB unitary authorities, 2011
All categories:
ReligionChristian Buddhist Hindu Jewish Muslim Sikh Other
religionNo
religion
Religion not
stated
Isle of Anglesey 69,751 45,400 165 45 40 250 43 257 17,797 5,754Gwynedd 121,874 72,503 426 238 55 1,378 39 637 36,163 10,435Conwy 115,228 74,506 347 206 62 583 17 478 30,017 9,012Denbighshire 93,734 60,129 266 167 32 469 8 345 25,132 7,186Flintshire 152,506 101,298 344 158 70 482 29 362 38,726 11,037Wrexham 134,844 85,576 351 504 58 860 87 310 36,927 10,171
Source: Census 2011 (ONS) Sex Neutral No
Impact No anticipated differential impact.
Evidence includes:
People who say they are from a
white background
People who say they are from a
non-white background
Percentage of population from a
non-white background
Isle of Anglesey 68,700 800 1.1Gwynedd 115,400 5,700 4.7Conwy 112,300 2,000 1.8Denbighshire 91,900 2,200 2.3Flintshire 150,000 3,900 2.6Wrexham 131,800 4,100 3.0Source: StatsWales (WG)
15
Sexual Orientation
Neutral No Impact
No anticipated differential impact.
Evidence includes:
Sexual identity by status, UK, Wales and North Wales unitary authorities, 2014
Welsh Language
Positive HighIt is anticipated that the impact on the Welsh Language will be positive and high. Most Centre staff will be bilingual speakers and patients will be receiving care in their own community closer to home. The Dementia and AMH staff will be adhering to the ‘active offer’ delivering services through the medium of Welsh in the Dwyfor locality. All signage in the new Centre will be bilingual in line with BCUHB Policy.
Evidence includes:
Heterosexual/Straight
Gay/Lesbian/Bisexual
Don't know/Refusal No response Other
United Kingdom 92.8 1.6 3.9 1.4 0.3Wales 93.9 1.5 3.0 1.1 0.4Isle of Anglesey 96.6 * 1.7 0.6 *Gwynedd 96.4 * 1.4 1.3 *Conwy and Denbighshire 90.1 1.3 7.2 1.1 *Flintshire and Wrexham 87.4 1.0 9.7 1.5 *Source: StatsWales (WG)
16
Human Rights Positive High It is anticipated that the impact on Human Rights will be positive and high. The Centre will provide a much improved, purpose built, therapeutic environment for Dementia and AMH service users – meeting all DDA regulations and dementia friendly requirements. It will also facilitate improved patient confidentiality through better clinic room soundproofing.The Centre will also provide a single point of access to Dementia and AMH services locally (instead of fragmented across several sites at present). Integrating these services in one building will enable people to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care – ultimately increasing the number of patients cared for within their own communities with reduced need for hospital admission.
Use your judgement to indicate the scale of any impact identified. The factors used to determine an overall assessment for each characteristic should include consideration of scale and proportionality as well as potential impact.
Guidance on completing Form 2: For each of the characteristics listed, and considering the aims and objectives you detailed in Q2 on Form 1, you need to consider whether your document or proposal likely to affect people differently, and if so, will this be in a positive or negative way? For example, you need to decide:
Will it affect men and women differently? Will it affect disabled and non-disabled people differently? Will it affect people in different age groups differently? - and so on covering all the protected characteristics.
Persons aged 16 years and over who speak Welsh, 2018-19Number %
Wales 463,670 18Betsi Cadwaladr UHB 187,960 33Isle of Anglesey 30,690 53Gwynedd 68,200 66Conwy 36,320 37Denbighshire 23,420 30Flintshire 13,950 11Wrexham 15,380 14Source: StatsWales (WG) using National Survey for Wales
17
Form 3: Assessing Impact against the General Equality Duty
As a public sector organisation, we are bound by the three elements of the “General Duty”. This means that we need to consider whether (if relevant) the policy or proposal will affect our ability to:-
Eliminate unlawful discrimination, harassment and victimisation; Advance equality of opportunity; and Foster good relations between different groups
1. Describe here (if relevant) how you are ensuring
your policy or proposal does not unlawfully
discriminate, harass or victimise
The new Centre will significantly improve access to Dementia and AMH services in the Dwyfor locality. It is not anticipated that the proposed development will create any negative impacts upon protected characteristic groups or the wider community. It has anticipated a range of significant positive impacts on a number of groups (outline these) as well as high impact on the Welsh Language and Human Rights.
2. Describe here how your policy or proposal could better advance equality of opportunity (if relevant)
The integrated Centre will address the current issue of service fragmentation and will enable those AMH (Consultant Psychiatry etc.) services currently being delivered in Ysbyty Alltwen (as there is no capacity in the Pwllheli area) to transfer across to the new Centre ensuring more care closer to home.The staffing skill mix of the new Centre will also offer a bilingual workforce so that patients can receive care from staff speaking their first language.
3. Describe here how your policy or proposal might
be used to foster good relations between different
groups (if relevant)
By co-locating Dementia and AMH health and social care professionals together, this will foster better working relationships and more streamlined transfer of patients through the different stages of care. The familiarity of the surroundings in one integrated Centre will benefit these vulnerable service users and carers.
18
Part B:Form 4 (i): Outcome ReportOrganisation: BETSI CADWALADR UNIVERSITY HEALTH BOARD
1. What is being assessed? (Copy from Form 1) Copy form 1
2. Brief Aims and Objectives:
(Copy from Form 1)
Copy form 1
The project has the following main aims and objectives:
Modern, fit for purpose accommodation – we want to provide purpose built facilities and a suitable therapeutic environment to meet the needs of our vulnerable OPMH and AMH client groups
Improved integration - Integrating dementia and AMH services in one building enables people to access the most appropriate element of the service easily and seamlessly, providing continuity of care, and a 'wraparound' approach to care – ultimately increasing the number of patients cared for within their own communities with reduced need for hospital admission. Integration also significantly improves communication between community teams and agencies.
Reduced service fragmentation - OPMH and AMH services in Dwyfor are currently fragmented across previously three (and now two) sites. One centre will provide a single point of access.
Increased clinical capacity through expanded accommodation to see more dementia and AMH service users locally in line with the Mental Health Measure, the Health Board’s Care Closer to Home strategic objective and projected future demand.
Strategic alignment – Building a new integrated centre on the Bryn Beryl site is in line with BCUHB strategic direction (Living Healthier, Staying Well) in terms of Care Closer to Home - caring for people with dementia / AMH conditions for longer in their own communities, as well as the North Wales Mental Health Strategy (promoting integration and less fragmentation) and the Health Board’s Estates Strategy – investing in Bryn Beryl as a level 1 Health & Wellbeing hospital / centre.
Rationalise estate and generate efficiencies - We would like to get rid of existing, poor community estate and replace with modern, fit for purpose, efficient facilities in line with the Health Board’s Estate Rationalisation Strategy
19
The project outcomes can be quantified as follows:
Modern, expanded, fit for purpose accommodation to meet OPMH (Dementia) & AMH service user and staff needs
More integrated and improved patient care for OPMH Dementia and Adult Mental Health service users as a result of co-location - leading to improved continuity of care for service users, less duplication and better communication between services
Increased capacity by up to 10-15% to deliver both group and individual therapy as required under the Mental Health Measure and in line with increasing demographic demand
Care closer to home - supporting more accessibility in the community as set out in the national Dementia Strategy, the Mental Health Measure, the Health Board’s Living Healthier, Staying Well (LHSW) Strategy and the Estates Strategy through investment in the Ysbyty Bryn Beryl site as a Level 1 community hospital / health & wellbeing facility, providing integrated dementia and AMH services as locally as possible
Estate efficiency and rationalisation - improving the quality and efficiency of the estate through the rationalisation of poor community sites, reduced backlog maintenance, reduced running costs and achievement of statutory and regulatory compliance
3a. Could the impact of your decision/policy be discriminatory
under equality legislation?
Yes No
3b. Could any of the protected groups be negatively affected? Yes No
3c. Is your decision or policy of high significance? Yes No
Yes No 4. Did the decision scoring on Form 3, coupled with your answers to the 3 questions above indicate that you need to proceed to a Full Impact Assessment?
The assessment is that the development will have a range of high positive impacts on a number of protected characteristic group and a neutral / no differential impact on the remaining groups. Overall, the new integrated Dementia and Adult Mental Health Centre will have a significant positive impact on the delivery of these services locally. It will replace fragmented, extremely poor existing accommodation in the Pwllheli area with fit for purpose facilities to meet the needs of Dementia and AMH service users and staff. Ultimately, the expanded accommodation will ensure that more people can be cared for in their local communities for longer avoiding the need for admission wherever possible.
x
x
x
x
20
Yes 5. If you answered ‘no’ above, are there any issues to be addressed e.g. mitigating any identified minor negative impact?
Record Details: There may be a small group of AMH / Dementia patients who live in the Pwllheli area who may experience an issue with accessing the proposed Centre on the Bryn Beryl site. This will be mitigated by providing clarity on the public and community transport options available (e.g. bus routes, hospital transport and O Drws i Drws etc). All patients / carers will be asked at the point of referral to the new Centre whether they have any transport concerns and every effort will be made to address the individual’s circumstances and identify a transport solution. Currently the means of transport available to access the service is predominantly hospital transport; this is arranged in advance either at the point of referral or within 48 hours’ notice, and is the most popular mode of transport (about 80 - 90% currently avail of this option). Around 5% -10% arrive with a carer or family member (in the car) and about 5% avail of the local O Drws i Drws service. Only one day in the last 6 years has a person looking to utilise the dementia service, used the public bus service.
Patients and carers have been travelling to the former Hafan Dementia Day Assessment Unit (on the Bryn Beryl site) for several years and are currently travelling to Hafod Hedd in Y Ffor which is further from Pwllheli than Bryn Beryl. As mentioned, the Consultant Psychiatric clinic will be transferred from Ysbyty Alltwen to the new Centre, which will improve local access and DNA rates.
Currently anyone looking to access Ysbyty Bryn Beryl can do so via the following 2 buses; (www.traveline-cymru)
The # 12 bus (Direction: Trefor) has 18 stops departing from Bus Station, Pwllheli and ending in Maes Y Neuadd, Trefor. The 12-bus normally starts operating at 18:25 and ends at 22:40. Normal operating days weekdays.
The # 14 bus (Direction: Pwllheli) has 32 stops departing from Smithy, Clynnog and ending in Bus Station, Pwllheli (C). The 14-bus normally starts operating at 08:55 and ends at 08:55. Normal operating days: weekdays.
X
21
Yes No
How is it being monitored? The project will follow the monitoring guidelines set out in the Capital Manual. A monthly project board meeting will be held and chaired by the Project Director. Cost and Highlight Reports will be prepared by the Project Manager for consideration and monitoring at the Project Board meetings. A Service User Group will be held on an ad hoc basis to include representation from key statutory services (Fire, Health & Safety, Operational Estates, Facilities etc.) as well as OPMH / AMH service users to assist in agreeing the design detail and operational management of the new building.
24 months after opening, a post project evaluation exercise will be undertaken by the Project Board to assess whether the Project’s objectives and outcomes have been met.
Who is responsible? The Project Board with regular reporting to Planning and WALT.
What information is being
used?
The Dementia and AMH services will collect their own data, whilst Estates will record building related information in accordance with the Capital Manual.
6. Are monitoring arrangements in place so that you can measure what actually happens after you implement your document or proposal?
When will the EqIA be
reviewed? (Usually the same
24 months after opening
x
22
date the policy is reviewed)
7. Where will your decision or policy be forwarded for approval? Project Board / WALT / Capital Improvement Group / Execs / F&P/ Board
8. Describe here what engagement you have
undertaken with stakeholders including staff and
service users to help inform the assessment
Dementia and AMH staff have been involved in the planning and design of the new Centre from the project outset. A combined AEDET (achieving Excellence Design Evaluation Toolkit) meeting will be undertaken in due course including service users and carers to help inform the detailed design.
Name Title/Role
Christine Rudgley West Area Lead Operational Improvement (Chairperson), BCUHB
Gary Prendiville Assistant Project Manager, BCUHB
Daniel Eyre Estates Senior Project Manager, Planning, BCUHB
Glenys Williams Team Manager, Mental Health & Learning Disabilities, BCUHB
9. Names of all parties involved in undertaking this Equality Impact Assessment:
Jane Hartshorne Day Services Lead, Older Persons Mental Health, BCUHB
Mark Couchman? Mental Health Services Manager Adult & Older Persons (community), Mental Health & Learning Disabilities, BCUHB
Iolo Jones Deputy County Manager, Adult Mental Health & Social Care, BCUHB
Please Note: The Action Plan below forms an integral part of this Outcome Report
23
Form 4 (ii): Action PlanThis template details any actions that are planned following the completion of EqIA including those aimed at reducing or eliminating the effects of potential or actual negative impact identified.
Proposed Actions Who is responsible for this
action?
When will this
be done by?
1. If the assessment indicates significant potential negative impact such that you cannot proceed, please give reasons and any alternative action(s) agreed:
None
2. What changes are you proposing to make to your document or proposal as a result of the EqIA?
None
3a. Where negative impacts on certain groups have been identified, what actions are you taking or are proposed to mitigate these impacts? Are these already in place?
With regard to public and community transport to and from the new Centre, the various options available will be clarified including the bus routes and timetables and this information will then be collated for service users / carers by Reception staff to ensure that there are no issues with access for patients to the new Centre.
Gary Prendiville / Joyce Jones By January 2020
3b. Where negative impacts on certain groups have been identified, and you are proceeding without mitigating them, describe here why you believe this is justified.
None
4. Provide details of any actions taken or planned to advance equality of opportunity as a result of this assessment.
None
24
8 FP19/299 Summary of Private business to be reported in public
1 FP19.299 Private session items reported in public v1.0.docx
Cyfarfod a dyddiad: Meeting and date:
Finance and Performance Committee 19.12.19
Cyhoeddus neu Breifat:Public or Private:
Public
Teitl yr Adroddiad Report Title:
Summary of business considered in private session to be reported in public
Cyfarwyddwr Cyfrifol:Responsible Director:
Sue Hill, Acting Executive Director Finance
Awdur yr AdroddiadReport Author:
Diane Davies, Corporate Governance Manager
Craffu blaenorol:Prior Scrutiny:
None
Atodiadau Appendices:
None
Argymhelliad / Recommendation:
The Committee is asked to note the report
Please tick one as appropriate (note the Chair of the meeting will review and may determine the document should be viewed under a different category)Ar gyferpenderfyniad /cymeradwyaethFor Decision/Approval
Ar gyfer TrafodaethFor Discussion
Ar gyfer sicrwyddFor Assurance
Er gwybodaethFor Information
Sefyllfa / Situation:To report in public session on matters previously considered in private session
Cefndir / Background:Standing Order 6.5.3 requires the Board to formally report any decisions taken in private session to the next meeting of the Board in public session. This principle is also applied to Committee meetings.
Asesiad / Assessment
The Finance and Performance Committee considered the following matters in private session on 4.12.19
Proposed Interim Arrangements for Continuing Health Care (CHC) and Free Nursing Care Fee Changes for 2019/20
Medical and Dental Agency Locum monthly report Approved the tender for the project to develop the SMS accommodation at
Rowley’s Drive, Shotton.