BUMCT Expansion Project weekly update, Dec. 14, 2015
Transcript of BUMCT Expansion Project weekly update, Dec. 14, 2015
PARKING GARAGE B LEVEL 1 WORK
DEC 28TH THROUGH DEC 31ST 2015
BUMCT EXPANSION PROJECT
WEEKLY NOTICE
Garage B
Elm St.
Rin
g R
d.
Ca
mp
be
ll A
ve.
N
East entrance will be
closed.
Use North entrance
only.
Parking available on
levels 2-4 and in
Parking Garage C.
Issued: 12/14/2015
LOT F CLOSURE AND NEW WALKING PATH
STARTING JAN 4TH 2016
BUMCT EXPANSION PROJECT
WEEKLY NOTICE
N
Issued: 12/14/2015
Employee parking.Lot F will be closed
permanently for new
Hospital Tower.
Garage
CGarage
B Rin
g R
d.
Elm St.
Wa
rre
n A
ve.
ED drop-off only. No
employee access.
EVENTSDate & Event Identification
ACTIVITIESWhat’s Happening with This Event?
IMPACTSWhat Will Be Experienced w/ the Event?
• 12/28/15 – 12/31/15
Parking Garage B Level 1
closed for work.
• All traffic will be routed to levels 2-4. • Dust may occur while cleaning.
• Employees moved to Parking Garage C.
• 1/4/16
Permanently close parking
Lot F for new Hospital
Tower.
• North 30’ of parking lot to remain open to
pedestrians for 2 weeks.
• After 1/18/16 pedestrians will take new Walk
Path on Ring Road.
• Noise from backup alarms, equipment, and
demolition hammers.
• Employees will follow new Walk Path on Ring
Road.
• 1/4/16 – 3/2/16
ED interior renovations.
• Existing entrance will remain open until
construction is complete.
• Noise from demolition and construction. The
approved ICRA and ILSM will be followed.
• 1/4/16 – 3/8/16
Close ED Parking Lot.
• All ADA spaces now on Level one (1) of Parking
Lot B.
• Noise from backup alarms and equipment.
• Pedestrians will walk around fenced site on new
path.
Issued: 12/14/2015
PROJECT STATUS
Construction begins on
1/4/2016!!!
Banner:
M. Ostrand | [email protected] | (520) 694-4076
Sundt | DPR:
Brittany Burbes | [email protected] | (602) 478-4323
Emergency:
Banner Security | (520) 694-6533
PROJECT FACTS CONTACT INFO
2016 20192016 2017 2018 2019
Construction Begins
1/4/2016
Foundations
4/20/2016
Structural Steel
7/5/2016
Framing
1/17/2017
Roof
2/15/2017
Power Turned On
5/23/2017
Elevators
6/1/2018
Banner Moves Into Building
12/19/2018
Roads and Parking
3/29/2019
Final Completion
4/2/2019
The foundation includes
of 154 drilled caissons.
Issued: 12/14/2015
CONSTRUCTION MILESTONES