BUMCT Expansion Project weekly update, Dec. 14, 2015

4
PARKING GARAGE B LEVEL 1 WORK DEC 28 TH THROUGH DEC 31 ST 2015 BUMCT EXPANSION PROJECT WEEKLY NOTICE Garage B Elm St. Ring Rd. Campbell Ave. N East entrance will be closed. Use North entrance only. Parking available on levels 2-4 and in Parking Garage C. Issued: 12/14/2015

Transcript of BUMCT Expansion Project weekly update, Dec. 14, 2015

PARKING GARAGE B LEVEL 1 WORK

DEC 28TH THROUGH DEC 31ST 2015

BUMCT EXPANSION PROJECT

WEEKLY NOTICE

Garage B

Elm St.

Rin

g R

d.

Ca

mp

be

ll A

ve.

N

East entrance will be

closed.

Use North entrance

only.

Parking available on

levels 2-4 and in

Parking Garage C.

Issued: 12/14/2015

LOT F CLOSURE AND NEW WALKING PATH

STARTING JAN 4TH 2016

BUMCT EXPANSION PROJECT

WEEKLY NOTICE

N

Issued: 12/14/2015

Employee parking.Lot F will be closed

permanently for new

Hospital Tower.

Garage

CGarage

B Rin

g R

d.

Elm St.

Wa

rre

n A

ve.

ED drop-off only. No

employee access.

EVENTSDate & Event Identification

ACTIVITIESWhat’s Happening with This Event?

IMPACTSWhat Will Be Experienced w/ the Event?

• 12/28/15 – 12/31/15

Parking Garage B Level 1

closed for work.

• All traffic will be routed to levels 2-4. • Dust may occur while cleaning.

• Employees moved to Parking Garage C.

• 1/4/16

Permanently close parking

Lot F for new Hospital

Tower.

• North 30’ of parking lot to remain open to

pedestrians for 2 weeks.

• After 1/18/16 pedestrians will take new Walk

Path on Ring Road.

• Noise from backup alarms, equipment, and

demolition hammers.

• Employees will follow new Walk Path on Ring

Road.

• 1/4/16 – 3/2/16

ED interior renovations.

• Existing entrance will remain open until

construction is complete.

• Noise from demolition and construction. The

approved ICRA and ILSM will be followed.

• 1/4/16 – 3/8/16

Close ED Parking Lot.

• All ADA spaces now on Level one (1) of Parking

Lot B.

• Noise from backup alarms and equipment.

• Pedestrians will walk around fenced site on new

path.

Issued: 12/14/2015

PROJECT STATUS

Construction begins on

1/4/2016!!!

Banner:

M. Ostrand | [email protected] | (520) 694-4076

Sundt | DPR:

Brittany Burbes | [email protected] | (602) 478-4323

Emergency:

Banner Security | (520) 694-6533

PROJECT FACTS CONTACT INFO

2016 20192016 2017 2018 2019

Construction Begins

1/4/2016

Foundations

4/20/2016

Structural Steel

7/5/2016

Framing

1/17/2017

Roof

2/15/2017

Power Turned On

5/23/2017

Elevators

6/1/2018

Banner Moves Into Building

12/19/2018

Roads and Parking

3/29/2019

Final Completion

4/2/2019

The foundation includes

of 154 drilled caissons.

Issued: 12/14/2015

CONSTRUCTION MILESTONES