Building for the Future of Education: Propositions S & N

29
SAN DIEGO COMMUNITY COLLEGE DISTRICT Building for the Future of Education: Propositions S and N Presented to the Elite Service Disabled Veteranowned Business Network San Diego Chapter November 6, 2012

description

​The San Diego Community College District’s (SDCCD) construction bond program, funded by voter-approved Proposition S, a $685 million bond passed in 2002, and Proposition N, an $870 million bond passed in 2006, is providing for new, state-of-the-art instructional and career training facilities, major renovations, public safety and accessibility enhancements, parking, and campuswide infrastructure projects at City, Mesa and Miramar Colleges, and six Continuing Education campuses.

Transcript of Building for the Future of Education: Propositions S & N

Page 1: Building for the Future of Education: Propositions S & N

SAN DIEGO COMMUNITY COLLEGE DISTRICT

Building for the  Future of Education:Propositions S and N

Presented to theElite Service Disabled Veteran‐owned Business Network

San Diego Chapter

November 6, 2012

Page 2: Building for the Future of Education: Propositions S & N

• City College• Mesa College• Miramar College• Continuing Education

Centre City Campus Cesar Chavez Campus Educational Cultural 

Complex Linda Vista Campus Mid‐City Campus West City Campus

San Diego Community College District About the District

Page 3: Building for the Future of Education: Propositions S & N

San Diego Community College District Propositions S and N Overview

$1.555 billion construction bond program provides for 80+projects at City, Mesa and Miramar Colleges, and six Continuing Education campuses:• State of the art teaching and learning facilities• Major renovations and modernizations• Campus‐wide infrastructure projects

3

Page 4: Building for the Future of Education: Propositions S & N

Six new teaching andlearning facilities

Eight major renovations

Campus expansion will provide facilities and programs to accommodateeventual enrollment of25,000 students

Eight projects completed to date; two more under construction

San Diego Community College District City College Overview

Page 5: Building for the Future of Education: Propositions S & N

San Diego Community College District City College – Completed Projects

Academic Success Center

“P” Building RenovationLearning Resource Center

Career Technology Center  (CTC)

Central Plant

Mathematics & Social Science

Page 6: Building for the Future of Education: Propositions S & N

C Building RenovationBuilder:  Sundt ConstructionBid and Award Timeframe:  Oct 2013 – Nov 2013Construction Timeframe:  Nov 2013 – Sept 2015

M Building RenovationBuilder:  CW DriverBid and Award Timeframe:  Sept 2013 – Dec 2013Construction Timeframe:  Dec 2013 – March 2015

D Building RoofDesign/Build RFP:  Due Nov 16, 2012Bid and Award Timeframe:  Dec 2014 – March 2015Construction Timeframe:  April 2015 – March 2018

San Diego Community College District City College – Future Projects

A Building RenovationDesign/Build RFP:  Due Nov 16, 2012Bid and Award Timeframe:  Dec 2014 – March 2015Construction Timeframe:  April 2015 – March 2018

Engineering Technology (T Bldg.)Design/Build RFP:  Due Nov 16, 2012Bid and Award Timeframe:  Dec 2014 – March 2015Construction Timeframe:  April 2015 – March 2018

Child Development Center (CDC)Builder:  TBDBid and Award Timeframe:  Dec 2015 – March 2016Construction Timeframe:  March 2018 – March 2019

Page 7: Building for the Future of Education: Propositions S & N

San Diego Community College District Mesa College Overview

Seven new teaching and learning facilities

Four major renovations

Nine infrastructureprojects

Expansion will providefacilities to accommodate eventual enrollment of 25,000 students

Eleven projects completed to date; one more underconstruction

Page 8: Building for the Future of Education: Propositions S & N

San Diego Community College District Mesa College Completed Projects

Allied Health Education & Training Facility

College Police StationMesa College Design Center Parking Structure

Student Services Center

Page 9: Building for the Future of Education: Propositions S & N

Project Budget:  $40.5 millionTargeted DSA Approval:  Dec 2012Targeted Bid Period:  Jan 2013 – Feb 2013Targeted Construction Start:  April 2013Targeted Completion: March 2014

The Social and Behavioral Sciences building will consist of approximately 66,000 GSF of new labs and classrooms for Behavioral Sciences and Social Sciences programs.  The building  will include Psychology Labs, Speech Labs and ‘smart’ classrooms.

Design/Build Team:Builder: Swinerton BuildersArchitect:  Joseph Wong Design Associates

Mesa College Projects in DesignSocial & Behavioral Sciences Building

Page 10: Building for the Future of Education: Propositions S & N

Project Budget: $45.7 millionTargeted DSA Approval:   Nov 2013Targeted Bid Period:  Nov 2013 – Dec 2013Targeted Construction Start:  Feb 2014Targeted Completion: May 2015

The 65,000 SF building will house the Food Services, bookstore and stockroom components for the Campus.

Design/Build Team:Builder: Legacy Building ServicesArchitect:  Mosher Drew Watson Ferguson and Miller Hull Architects

Mesa College Projects in DesignCafeteria/Bookstore/Stockroom

Page 11: Building for the Future of Education: Propositions S & N

Project Budget: $10.4 millionTargeted DSA Approval:  Feb 2014Targeted Bid Period:  March ‐ Apr 2014Targeted Construction Start:  June 2014Targeted Completion:  June 2015

The Fitness Center will be approximately 25,000 gross square feet facility to house Mesa College's Health Service program and Physical Conditioning program.

Design/Build Team:Builder: Balfour Beatty  ConstructionArchitect:  gkkworks

Mesa College Projects in DesignFitness Center

Page 12: Building for the Future of Education: Propositions S & N

San Diego Community College District Mesa College Future Projects

LRC Language CenterBuilder:  TBDBid & Award Timeframe:  April – May 2013Construction Timeframe: May – Dec 2013

Instructional Technology BuildingDesign/Build RFP Timeframe:  April ‐May 2013Bid & Award Timeframe:  April ‐May 2015Demolition Timeframe:  June – July 2015Construction Timeframe:  Aug 2015 – Oct 2016

Facilities Support Area (L‐200 Remodel)Builder:  TBDBid & Award Timeframe:  June ‐ August 2015Construction Timeframe:  Aug 2015 – June 2016

I‐300  Building DemolitionBuilder:  TBDBid & Award Timeframe:  Feb – May 2014Demolition Timeframe:  May – August 2014

Fine Arts and Dramatic Arts Design/Build RFP Timeframe:  June ‐ July 2014Bid & Award Timeframe:  Sept – Dec 2016Construction Timeframe: Jan – April 2017

Mesa Quad ProjectBuilder:  TBDBid & Award Timeframe:  August – Nov 2015Demolition Timeline:  Jan – Feb 2017Construction Timeframe:  Feb – Aug 2017

Page 13: Building for the Future of Education: Propositions S & N

15 new facilities

Seven major renovations

Three infrastructure projects

Expansion will providefacilities to accommodate eventual enrollment of 25,000 students

19 projects completed todate; two more underconstruction

San Diego Community College District Miramar College Overview

Page 14: Building for the Future of Education: Propositions S & N

Mathematics & Business Hourglass Park Field House

Humanities & Arts Police Station & Parking Structure

San Diego Community College District Miramar College Completed Projects

Page 15: Building for the Future of Education: Propositions S & N

Library/Learning Resource Center (LLRC)

College Services Center Aviation Technology Center

San Diego Community College District Miramar College Completed Projects

Page 16: Building for the Future of Education: Propositions S & N

Miramar College Projects in DesignStudent Services

Project Budget: $7.3 millionTargeted DSA Approval:  Nov 2012Targeted Bid Period:  Jan – Feb 2013Estimated Construction Start:  April 2013Targeted Completion:  April  2014

The Student Services project will repair, renovate and convert the interim library space to support Assessment Services, Health Services, and Outreach.

Design/Bid/Build Team:Builder: To be determinedArchitect:  Mosher Drew Watson Ferguson

Page 17: Building for the Future of Education: Propositions S & N

Miramar College Projects in DesignFire Science/EMT Training Facility

Budget: $16.5 millionTargeted DSA Approval:  Nov 2012Targeted Bid Period:  Dec 2012 – Jan 2013Estimated Construction Start:  March 2013Targeted Completion:  July 2014

The Fire and EMT Training Facility will consist of approximately 22,900 SF to serve as a classroom and active training center for the Fire Science and Emergency Medical Training (EMT) programs. The facility will have labs, support space, equipment staging, classrooms, offices and an outdoor training area.

Design/Build Team:Builder:  Swinerton BuildersArchitect:  gkkworks

Page 18: Building for the Future of Education: Propositions S & N

Miramar College Projects in DesignScience Building Expansion

Budget: $34.9 millionTargeted DSA Approval:  March 2013Targeted Bid Period: March 2013 – June 2013Estimated Construction Start: June 2013Targeted Completion:  August 2014

The project will be a new 50,000 SF structure with classrooms, and labs for chemistry, astronomy, geology, anatomy, marine biology, microbiology, physics and biology. The roof level includes a greenhouse and observatory.

Design/Build Team:Builder:  DPR ConstructionArchitect:  Marlene Imirzian and Associates

Page 19: Building for the Future of Education: Propositions S & N

Miramar College Projects in DesignAdministration Building

Budget: $10.4 millionTargeted DSA Approval:  Nov 2012Targeted Bid Period:  Jan – Feb 2013Estimated Construction Start:  Feb 2013Targeted Completion:  Oct 2013

The Administration Building project will provide for 17,000 SF of new constructionat the north end of campus, and allow forthe existing administration wing to be converted to a classroom facility for Continuing Education programs offered at Miramar. 

Design/Build Team:Builder:  Charles Pankow BuildersArchitect:  IBI

Page 20: Building for the Future of Education: Propositions S & N

Miramar College Projects in DesignA‐100 Building Remodel

Budget: $6.6 millionTargeted DSA Approval:  March 2013Targeted Bid Period:  March – May 2013Estimated Construction Start: October 2013Targeted Completion:  June 2014

This project will provide for the renovation of the existing A‐100 building to house the Continuing Education programs at Miramar. The project will include classrooms, assessment, counseling and parent education spaces in the existing 16,000 gross square feet facility. An outdoor play area for the parent education program will enhance the indoor learning spaces. This project is slated to achieve a Leadership in Energy and Environmental Design (LEED) Silver certification.

Design/Build Team:Builder:  Charles Pankow BuildersArchitect:  IBI

Page 21: Building for the Future of Education: Propositions S & N

Remodel Existing Police AcademyTargeted Construction Timeframe:  Nov 2013 – June 2014

Maintenance Facilities ExpansionTargeted Construction Timeframe:  Sept 2014 – Oct 2015

San Diego Community College District Miramar College Future Projects

Page 22: Building for the Future of Education: Propositions S & N

Seven projects completed

Two projects under construction

Two projects in design

Total of 11 projects to expand and modernize the six Continuing Education sites

San Diego Community College District Continuing Education Overview

Page 23: Building for the Future of Education: Propositions S & N

San Diego Community College District Continuing Education Completed Projects

West City Campus Mid City Campus

Skills Center North City Campus Parking Structure Cont. Ed. Mesa College Campus

Page 24: Building for the Future of Education: Propositions S & N

Continuing Education Future ProjectsCesar Chavez Campus

Project Budget: $48.5 millionDSA Approval:  June 2012Targeted Bid Period:  Feb – March 2013Targeted Construction Start:  April 2013Targeted Completion:  Nov 2014

This project consists of land acquisition and construction of a new 70,000 GSFbuilding to consolidate the current programs at the Cesar Chavez and Centre Citycampuses. It will also include underground parking with 154 spaces and an adjacent parking structure.

CM Multiple PrimeBuilder:  Rudolph & SlettenArchitect:  Martinez + Cutri

Page 25: Building for the Future of Education: Propositions S & N

Continuing Education Future ProjectsCesar Chavez Center Parking Structure

Project Budget: $6.5 millionDSA Approval:  August 2013Targeted Bid Period:  August – September 2013Targeted Construction Start:  September 2013Targeted Completion:  September 2014

As part of the Cesar Chavez Campusproject, a multi‐level parking structurewith 300+ parking spaces will be built.

Design/Build Team:Builder:  PCL ConstructionArchitect:  RJC Architects

Page 26: Building for the Future of Education: Propositions S & N

San Diego Community College District Getting Involved

Fill out and submit the SDCCD’s Certification Verification FormUpon submittal and verification, you will be added to the District’s database ofsmall and historically underutilized firms.  The database is shared with Design/Buildproposal teams looking for firms to include in Design/Build Subcontracting Participation Plans, and with GCs and Campus Project Managers for task order work.

Pursue all the small business certifications for which you are eligibleBy obtaining formal certifications from approved agencies, you are added to state and federal databases made available to the public and which make you ‘findable.”

Track SDCCD’s construction opportunitiesTrack SDCCD on Facebook and Twitter for updates, and check the Bid & Plan Roomon the Propositions S & N website: http://public.sdccdprops‐n.com/Pages/Home.aspx

Page 27: Building for the Future of Education: Propositions S & N

San Diego Community College District Resources

SDCCD Certification Verification Formhttp://public.sdccdprops‐n.com/CR/Forms/SDCCDCertificationForm.pdf

SDCCD Database of Small/Underutilized Businesseshttp://public.sdccdprops‐n.com/CR/Forms/PFDSHUF.pdf

SDCCD Approved Certifying Agency Directivehttp://public.sdccdprops‐n.com/CR/Forms/ACAP_Directive.pdf

SDCCD Prequalified Contractorshttp://public.sdccdprops‐n.com/CR/Pages/Prequal.aspx

Propositions S & N on Facebook: http://www.facebook.com/PropsSN

Propositions S & N on Twitter: https://twitter.com/SDCCDPropsSN

Page 28: Building for the Future of Education: Propositions S & N

San Diego Community College District Design/Build Contacts

Balfour Beatty C.W. Driver Clark Construction Group 

davisReed Construction, Inc.

DPR Construction Harper Construction Co.

Hensel Phelps Construction Co.

Legacy Building Services

McCarthy Building Companies

Pankow Builders PCL Construction Services, Inc.

Rudolph & Sletten, Inc.

Sundt Construction Swinerton Builders TB Penick & Sons Turner Construction

Page 29: Building for the Future of Education: Propositions S & N

29

Questions?

SAN DIEGO COMMUNITY COLLEGE DISTRICT

Richard BurkhartConstruction [email protected]

(619) 388‐6456

Ursula KroemerOutreach [email protected]

(619) 819‐5484