INTRODUCTION

THE BUILDING PROJECT SUBCOMMITTEE ON BEHALF OF

THE MANAGEMENT COMMITTEE OF THE SWIMMING

SECTION WELCOMES YOU TO THE PRESENTATION OF ITS

REPORT WITH RESPECT TO THE PROPOSED CHANGING

ROOMS, TOILET & TERRACE BAR PROJECT.

Page 3: Building commitee presentation 1

PROJECT JUSTIFICATION

• APPROVED IN THE 5-YEAR SECTION MASTER PLAN•DETERIORATING FACILITIES•GROWING MEMBERSHIP BASE

•GENDER SENSITIVITY•PROJECTING A MORDERN OUTLOOK

•IMPROVED CLUB IMAGE

Page 4: Building commitee presentation 1

PROJECT DELIVERY

• CONSTITUTION OF BUILDING SUB-COMMITTEE• ARCHITECTURAL DESIGN & SERVICES•TRANSPARENT TENDER PROCESS

•AWARD OF CONTRACT•FUND RAISING

•PROJECT DELIVERY

Page 5: Building commitee presentation 1

OLD BUILDING FRONT VIEW

Page 6: Building commitee presentation 1

AERIAL VIEW

Page 7: Building commitee presentation 1

FRONT VIEW

Page 8: Building commitee presentation 1

SIDE VIEW

Page 9: Building commitee presentation 1

GROUND FLOOR PLAN VIEW

Page 10: Building commitee presentation 1

FACILITIES PROVIDED

The Ground Floor accommodates:

•Reception•Mother’s Den•Swimming Store•Toilets (Male & Female)•Changing Room/Showers (Male & Female;10 each)

•Lockers (54 each for both Male & Female)

Page 11: Building commitee presentation 1

FIRST FLOOR PLAN VIEW

Page 12: Building commitee presentation 1

FACILITIES PROVIDED

The First Floor accommodates:

•Chairman’s office•Committee room•Toilets (Male & Female)•Bar•Relaxation/Events’ area

Page 13: Building commitee presentation 1

PROJECT COSTFOLLOWING A TRANSPARENT BIDDING PROCESS CONDUCTED BY THE LAGOS COUNTRY

CLUB TENDERS COMMITTEE THE FOLLOWING COST FOR THE COMPLETION OF THE PROJECT WAS ARRIVED AT.

S/NO. PHASES COST NAIRA

1. PHASE 1 13,100,793:50

2. PHASE 2 2,435,062:50

3. PHASE 3 5,568,962:50

4. TOTAL 21,104,818:50

5. ADD M&E 4,000,000:00

6. ESTIMATED COST 25,104,818:50

Page 14: Building commitee presentation 1

APPEAL FOR FUNDING

IN ORDER TO REALISE THIS NOBLE OBJECTIVE TRANSFORMING THE SECTION THE MANAGEMENT COMMITTEE WISH TO SOLICIT THE SUPPORT OF ALL MEMBERS FOR A ONE OFF LEVY OF N10,000 PER MEMBER . THIS IS EXPECTED TO COMPLEMENT THE FUNDING CURRENTLY AVAILABLE TO THE SECTION.

Page 15: Building commitee presentation 1

THANK YOU