Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic...

10
Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia ACOUSTICS 2016 Page 1 of 10 Building Acoustic Design of the Queensland University of Technology Creative Industries Precinct Phase 2 (CIP2) Cameron Hough Arup, Brisbane, Australia ABSTRACT The QUT Creative Industries Precinct Phase 2 (CIP2) co-locates the music, dance, performance and visual arts portfolios of the Creative Industries Faculty in a mixture of new-build and adaptive re-use of heritage structures. The acoustic design of CIP2 was of primary importance to the overall building performance and posed significant design challenges. Building acoustic design included high sound-insulation separation requirements between music studios, particularly the two professional-quality recording studios and small/medium rehearsal rooms, as well as the design of open-plan office spaces connected by a full-height atrium and secondary voids in order to provide sufficient acoustic privacy between floors and reduce disturbance to office areas from student common areas on floors below. As part of the briefing study, auralisation was used to negotiate project-specific design criteria for the studio spaces based on the requirements of the end-users, resulting in significant cost savings to the building façade for dance and drama studios which did not require high levels of external noise control. A key design challenge was the low-noise mechanical services system for the recording studios, which used a non-traditional system including flexible ductwork which provided significant challenges in achieving the required services noise levels and in controlling crosstalk and duct-breakout between adjacent studios. 1. INTRODUCTION Queensland University of Technology (QUT) has recently moved into the new Creative Industries Precinct Phase 2 (CIP2) building at the Kelvin Grove campus. CIP2 is a new-build facility co-locating the music, dance, performance and visual arts portfolios of the Creative Industries Faculty into a single site, replacing several buildings split across QUT’s Kelvin Grove and Gardens Point campuses as well as an external recording studio facility in Newstead. The CIP2 building is split into a “western bar” of three double-height floors, containing multiple studio spaces plus an “eastern bar” of six single-height floors. The western bar contains studios including a large ensemble rehearsal/performance room, small rehearsal/practice rooms, two recording studio complexes (“Studio A” and “Studio B”, each consisting of multiple control, live and isolation rooms), three large interdisciplinary “black box” studios, three dance studios with sprung dance floors and four drama rehearsal spaces. The eastern bar contains office accommodation, meeting and seminar rooms and student common areas. Visual arts studios and gallery spaces are accommodated in an adjacent mixture of new-build and reused heritage structures which were formerly part of the Kelvin Grove barracks. The acoustic performance of CIP2 was key to the success of the entire project and required careful acoustic design to achieve the desired performance outcomes. This paper focusses on the building acoustic design of the CIP2 facility, with special emphasis on the high acoustic separation requirements between studios and unusual low-noise system design for recording studio spaces. 2. ACOUSTIC PERFORMANCE REQUIREMENTS Acoustic design targets for CIP2 were developed in consultation with the end users via an auralisation workshop, which established the degree of acoustic performance required for each space. In several instances, the design targets adopted differed from the AS2107 (Standards Australia 2000) guidance – e.g. for music studios the end users required more-stringent control of background/external noise than AS2107, whereas for Dance/Performance studios less-stringent noise control was required. A credit interpretation request was negotiated with the Green Building Council of Australia in order to use the project-specific criteria from the end- user workshop in place of the AS2107 criteria.

Transcript of Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic...

Page 1: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia

ACOUSTICS 2016 Page 1 of 10

Building Acoustic Design of the Queensland University of Technology Creative Industries Precinct Phase 2 (CIP2)

Cameron Hough

Arup, Brisbane, Australia

ABSTRACT

The QUT Creative Industries Precinct Phase 2 (CIP2) co-locates the music, dance, performance and visual arts portfolios of

the Creative Industries Faculty in a mixture of new-build and adaptive re-use of heritage structures. The acoustic design of

CIP2 was of primary importance to the overall building performance and posed significant design challenges. Building

acoustic design included high sound-insulation separation requirements between music studios, particularly the two

professional-quality recording studios and small/medium rehearsal rooms, as well as the design of open-plan office

spaces connected by a full-height atrium and secondary voids in order to provide sufficient acoustic privacy between

floors and reduce disturbance to office areas from student common areas on floors below. As part of the briefing study,

auralisation was used to negotiate project-specific design criteria for the studio spaces based on the requirements of the

end-users, resulting in significant cost savings to the building façade for dance and drama studios which did not require

high levels of external noise control. A key design challenge was the low-noise mechanical services system for the

recording studios, which used a non-traditional system including flexible ductwork which provided significant challenges

in achieving the required services noise levels and in controlling crosstalk and duct-breakout between adjacent studios.

1. INTRODUCTION

Queensland University of Technology (QUT) has recently moved into the new Creative Industries Precinct

Phase 2 (CIP2) building at the Kelvin Grove campus. CIP2 is a new-build facility co-locating the music, dance,

performance and visual arts portfolios of the Creative Industries Faculty into a single site, replacing several buildings

split across QUT’s Kelvin Grove and Gardens Point campuses as well as an external recording studio facility in

Newstead.

The CIP2 building is split into a “western bar” of three double-height floors, containing multiple studio spaces

plus an “eastern bar” of six single-height floors. The western bar contains studios including a large ensemble

rehearsal/performance room, small rehearsal/practice rooms, two recording studio complexes (“Studio A” and

“Studio B”, each consisting of multiple control, live and isolation rooms), three large interdisciplinary “black box”

studios, three dance studios with sprung dance floors and four drama rehearsal spaces. The eastern bar contains

office accommodation, meeting and seminar rooms and student common areas. Visual arts studios and gallery

spaces are accommodated in an adjacent mixture of new-build and reused heritage structures which were formerly

part of the Kelvin Grove barracks.

The acoustic performance of CIP2 was key to the success of the entire project and required careful acoustic

design to achieve the desired performance outcomes.

This paper focusses on the building acoustic design of the CIP2 facility, with special emphasis on the high

acoustic separation requirements between studios and unusual low-noise system design for recording studio

spaces.

2. ACOUSTIC PERFORMANCE REQUIREMENTS

Acoustic design targets for CIP2 were developed in consultation with the end users via an auralisation

workshop, which established the degree of acoustic performance required for each space. In several instances, the

design targets adopted differed from the AS2107 (Standards Australia 2000) guidance – e.g. for music studios the

end users required more-stringent control of background/external noise than AS2107, whereas for

Dance/Performance studios less-stringent noise control was required. A credit interpretation request was

negotiated with the Green Building Council of Australia in order to use the project-specific criteria from the end-

user workshop in place of the AS2107 criteria.

Page 2: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

9-11 November 2016, Brisbane, Australia Proceedings of ACOUSTICS 2016

Page 2 of 10 ACOUSTICS 2016

3. BUILDING ACOUSTIC DESIGN

3.1 Façade Sound Insulation

The CIP2 site is located adjacent to Kelvin Grove Road, a major arterial road north of the Brisbane CBD.

External noise level control was particularly important for the music spaces. End-user consultation with the Dance

and Performance portfolio staff concluded that external noise control was less-important for dedicated Dance or

Performance spaces with the adopted targets of 45 dB(A) LAeq during peak hour being less-stringent than AS2107;

however for music spaces the requirement for external noise control was significantly more-stringent than AS2107,

with noise intrusion targets of 30 dB(A) LAeq (large rehearsal room) and 15 dB(A) LAeq (recording studios) during peak

hour.

Figure 1 View from Rehearsal/Performance Room along Kelvin Grove Road

This constrained the space planning of music studios, in particular meaning that studio live rooms could not

practically be located on the façade; however it was considered practical to have façade-located control rooms,

because control rooms are slightly less-sensitive to external noise intrusion than live rooms.

The base building façade of the CIP2 studios was 10mm float glass | 12 mm airgap | 10.76 mm acoustic

laminate glazing (Rw 37), however for the Level 5 spaces structurally-isolated secondary glazing (supported from the

isolated slabs of the music spaces) was required: 12.38 mm laminated glazing for the large rehearsal/performance

room at the northern end of CIP2, and 18.38 mm laminated glazing for the recording studio control rooms at the

southern end. To provide access to clean the secondary glazing, the airgap between the façade and the secondary

glazing was wide enough to be trafficable (~900 mm), which also improved the acoustic separation.

Noise breakin levels in peak hour within the music spaces met the design targets, with a measured noise level

(background-corrected, i.e. the measured break-in level during peak hour with the measured background noise

outside of peak hour logarithmically subtracted) of 9 dB(A) in the Studio A control rooms, and 26 dB(A) in the large

rehearsal/performance room.

3.2 Internal Sound Insulation

The multidisciplinary nature of CIP2 means the internal sound insulation of the building needed to avoid

disturbance between adjacent spaces, which could potentially be used simultaneously for noise-generating and

Page 3: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia

ACOUSTICS 2016 Page 3 of 10

noise-sensitive activities. A relatively-high sound separation target of Dw 60 between adjacent studios was set in

order to allow for independent use of spaces.

The sound insulation strategy was defined separately for the music floor (Level 5) and other floors of the

building. On other floors, the sound insulation between adjacent studios was generally achieved by space planning

by incorporating buffer zone spaces such as storerooms between adjacent studios where possible; the main

exception was the performance studios, which are paired within the structural building “box” and have an

increased-performance wall construction.

For the music floor, all spaces except the large rehearsal room are fully-structurally isolated via a jack-up slab

and a “box-in-box” construction, with a trafficable timber “lid” above the box that provides an accessible zone for

services reticulation. The large rehearsal room has a floating floor for isolation from the dance studio below, but

does not have fully-isolated internal walls as it (plus its associated control room and store room) occupies an entire

structural “box” and hence has no directly-adjacent spaces on the same floor.

Partitions around live rooms within the studios and some rehearsal rooms were constructed of masonry

blockwork, while other partitions were lightweight.

All measured studio spaces achieved the Dw 60 performance requirement, with the best-performing

separation between studios a measured performance of Dw 73 for masonry partitions and Dw 69 for lightweight

partitions.

3.3 Acoustic Separation of Floors Via Atrium and Voids

Levels 2-6 of the eastern bar of CIP2 are linked by a central atrium and stair, while each pair of floors (1-2, 3-4

and 5-6) are further linked by double-height “voids” between floors. On studio floors (Level 3 and Level 5) the office

accommodation in the eastern bar of CIP2 is separated from the voids by glazed partitions, however the

intermediate floors (Level 2, Level 4 and Level 6) have glazed balustrades and open onto the voids.

Figure 2: Typical Void Connecting Office Floors

Locations of acoustic absorption were added onto the soffit of the voids and the soffit adjacent to the slab

edge to control noise transfer between office floors via the voids/atriums and to reduce noise break-in to office

areas from student activities in the foyers outside the studios (particularly the Level 5 foyer outside the music

studios which is likely to have instruments warming up etc). An Odeon model of the atrium and voids was used to

design the absorption layout and predict the extent of noise transfer between floors.

Page 4: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

9-11 November 2016, Brisbane, Australia Proceedings of ACOUSTICS 2016

Page 4 of 10 ACOUSTICS 2016

3.4 Services Noise Control

Somewhat unusually for a building with low-noise systems, the project procurement model for CIP2 had

responsibility for services noise control with the mechanical engineer (Aurecon) with the acoustic consultant

providing guidance and high level reviews of the mechanical design, but not conducting detailed calculations.

The system design for the low-noise (NR20 and NR25 systems) for the recording studios and music studios

was undertaken using a Variable Air Volume (VAV)-based system with distribution via flexible ductwork – an

unusual approach for a low noise system, but dictated by the reduced space which ruled out a more-traditional low-

noise system. This was considered to be a high-risk approach since aerodynamic noise is typically the dominant

noise source for low-noise systems and the aerodynamic noise generation of flexible ductwork is highly dependent

on the installation conditions (ASHRAE 2015).

This required particular attention to detail during the construction phase as several instances of “convoluted”

flexible duct routing were identified, either by visual inspection, or from audible aerodynamic noise once the air

handling units (AHUs) were operational. This required some adjustment to the duct layouts (rerouting some flexible

duct and strapping/slinging of flexible duct to ensure straight routing of the duct. An example is the ductwork layout

shown in Figure 3.

Figure 3: Poorly-aligned flexible ductwork caused high aerodynamic noise levels and required modification

In order to keep the ductwork in place, the flexible ductwork runs required multiple support points to keep

the ductwork as straight as possible and avoid uneven flow conditions (which could in turn result in aerodynamic

noise). Figure 4 shows a typical flexible duct installation after adjustment.

Page 5: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia

ACOUSTICS 2016 Page 5 of 10

Figure 4 Flexible ductwork required additional support from straps to keep the required duct routing

3.4.1 Measured Noise Levels

During the acoustic commissioning of CIP2, the initial tested range of noise levels in the recording studios was

from approximately the N1 background noise curve (Essert 2013) – i.e. approximately the human threshold of

hearing – through to NR36, a variation of 22 dB between systems with the same nominal noise criterion of NR20!

The quietest spaces were the studio control rooms, with noise levels measured at just over N1, as shown in Figure

5:

Page 6: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

9-11 November 2016, Brisbane, Australia Proceedings of ACOUSTICS 2016

Page 6 of 10 ACOUSTICS 2016

Figure 5: Background Noise Measurements (L90) in Studio A Control Rooms

(data from 1kHz upwards is at noise floor of meter and is shown dotted)

After subsequent adjustment of the flexible duct and adjustment to system balance, all spaces complied with

the NR20 noise limit with the exception of one live room, where the AHU fan setting was set too high and the noise

limit was marginally exceeded at NR22. It is expected that this room will meet criteria once the AHU fan speed is

adjusted down to the design speed, although retesting of this space had not occurred at the time of writing of this

paper. Figure 6 shows the results of background noise testing in this room with the contribution from each noise

source (supply air, return air and house lights).

NR15

NR20

NR25

NR30

NR35

N1 Background Noise Curve

0

10

20

30

40

50

60

63 125 250 500 1k 2k 4k 8k

Sou

nd

Lev

el d

B

Octave Band Centre Frequency (Hz)

Studio A Control Room 1 Final Measurement Studio A Control Room 2 Final Measurement

Page 7: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia

ACOUSTICS 2016 Page 7 of 10

Figure 6 Studio A Live Room 1 Measured Background Noise (L90), showing effect of adjusting flexible ductwork

The experience at CIP2 suggests that low noise levels can be achieved even with a system design that would

normally be considered “unsuitable” using duct elements such as VAV boxes and flexible ductwork. However, the

experience at CIP2 also shows that such as an approach is inherently “risky” and that significant adjustment to the

ductwork is likely to be required to meet the noise limits. Nevertheless, in cases where the spatial requirements rule

out the use of a traditional low-noise system, it may be possible to meet low-noise targets even with an

“unfavourable” design if extreme care is taken in the system design and in site supervision.

In particular, the following factors are expected to have contributed to the success of the system at CIP2:

• The ability to access the technical loft above the studios to make adjustments to the routing of flexible

ductwork during construction and commissioning

• The presence of a length of lined sheet metal ductwork and a lined mitred bend as the final connection to the

room for each isolated “box”. This was originally introduced to control crosstalk between rooms via the

common technical loft (refer Section 3.4.2), but would also have an additional benefit in providing some

“guaranteed” attenuation downstream of the flexible ductwork to address aerodynamic noise generated by the

flexible ductwork.

3.4.2 Control of Duct Crosstalk

A major concern with the adopted mechanical services design was the risk of duct crosstalk between

adjacent spaces. Although multiple AHUs were used so that adjacent spaces would not be served off the same AHU

(with the large live room of each space being served by a dedicated AHU), there was still a risk of duct breakout

from the flexible ductwork in the technical loft above the studios, since flexible duct has very low breakout/breakin

TL.

To control crosstalk, the final 1.5m of ductwork was required to be internally-lined solid sheet metal

ductwork incorporating at least one lined mitred bend. The ductwork was sized to be as small as practicable without

exceeding the maximum velocity requirements for controlling aerodynamic noise in order to maximise the

attenuation provided by the duct lining. This provided sufficient down-duct attenuation to control the crosstalk path

NR15

NR20

NR25

NR30

NR35

N1 Background Noise Curve

0

10

20

30

40

50

60

63 125 250 500 1k 2k 4k 8k

So

un

d L

evel

dB

Octave Band Centre Frequency (Hz)

STA-LIV1 (initial) STA-LIV1 (Final) - All Services Off

STA-LIV1 (Final) - Mech Off, Lights On STA-LIV1 (Final) - Supply Air Only

STA-LIV1 (Final) - Return Air Only STA-LIV1 (Final) - All Services On

Page 8: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

9-11 November 2016, Brisbane, Australia Proceedings of ACOUSTICS 2016

Page 8 of 10 ACOUSTICS 2016

via the shared void. Measured acoustic separation between two non-adjacent rooms (i.e. transfer via the shared

technical loft above) was in the range Dw 73-78 for three pairs of rooms tested.

3.4.3 Structural Isolation of Services

All services connections to the isolated “boxes” were made using flexible connections (flexible ductwork,

flexible pipe connections, and by cutting cable tray and providing slack in cable connections) to avoid bridging the

structural isolation. Figure 7 shows the design concept for the structural isolation, where a flexible connection was

included wherever services crossed a structural isolation joint. Figure 9 shows an example isolation joint. This

allowed connections to the studio “box” itself to be made rigidly while avoiding bridging between adjacent studios

by services.

Figure 7: Structural and services isolation concept for recording studios

Coordination with the contractor and a series of “acoustic briefings” was critical in getting the contractor and

subcontractors to understand the concepts of structural isolation and the importance of maintaining the integrity of

the structural isolation breaks. Figure 8 shows a sketch developed with the architect and contractors which was

displayed in the site office for the duration of the construction program to remind contractor and subcontractor

staff of the requirements for preserving the acoustic isolation.

Page 9: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

Proceedings of ACOUSTICS 2016 9-11 November 2016, Brisbane, Australia

ACOUSTICS 2016 Page 9 of 10

Figure 8: Site sketch used to convey structural isolation concepts to subcontractors.

During the construction stage, ongoing site inspections were required to preserve the integrity of the

structural isolation, requiring some on-site modifications where solid ductwork had been incorrectly installed across

an isolation joint.

Page 10: Building Acoustic Design of the Queensland University of ... · PDF fileBuilding Acoustic Design of the Queensland University of Technology Creative ... Queensland University of Technology

9-11 November 2016, Brisbane, Australia Proceedings of ACOUSTICS 2016

Page 10 of 10 ACOUSTICS 2016

Figure 9: Example of Services Isolation at joint between isolated “box” constructions

CONCLUSIONS

The Queensland University of Technology Creative Industries Precinct Phase 2 project has provided end users

with a highly-flexible creative arts building, with initial feedback from end users being positive.

The co-location of multiple functional spaces in close proximity required careful acoustic design to achieve

the high sound insulation requirements. Control of duct crosstalk and flanking paths allowed acoustic separation of

Dw 60 or higher to be achieved even with spaces sharing a common technical void above.

A particular highlight of the CIP2 project is the use of a non-traditional mechanical services system design for

a low-noise application (especially the use of flexible duct), with the implemented system being closer to a typical

office approach than a traditional low-noise system. The experience of CIP2 has shown that low noise levels (as low

as N1) can be achieved even with a non-traditional system, but at the cost of a high degree of construction-stage

supervision and additional tuning and commissioning of the system. While the approach of CIP2 would not be

recommended as a “normal” approach to low-noise system design, it does demonstrate that in space-constrained

environments low-noise levels can be achieved even with an “unfavourable” system design.

REFERENCES

American Society of Heating, Refrigeration and Air-conditioning Engineers, 2015 “ASHRAE Applications Handbook –

Chapter 48 Noise and Vibration Control”

Essert, R, 2003 “Why Silence?” Proc. International Symposium of Room Acoustics, Toronto, Canada, June 2013