BTS3900 GSM Quick Installation Guide-(V300R008&R009_02)PDF

12
1 BTS3900 GSM V300R008&R009 Quick Installation Guide 900 mm 42 mm 450 mm 600 mm 420 mm 200 mm 800 mm Cabinet dimensions (height x width x depth): 900 mm x 600 mm x 450 mm Modules in the Cabinet 220 V cabinet -48 V cabinet +24 V cabinet Fan box BBU DCDU-01 BBU +24 V power equipment DCDU-01 BBU 220 V power equipment DCDU-01 RFU RFU RFU Issue: 02 Date: 2010-01-30 Safety Information Check the electrical connection of the device before operation and ensure that the device is reliably grounded. When working at a height, be cautious about falling objects. When operating the device, comply with the local safety regulations. The safety precautions provided in the documents are supplementary. You must comply with the local safety regulations. Power off the device before performing operations on the power supply equipment. High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down. When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes. When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss. The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards. When the cabinet is unpacked, it must be powered on in seven days. The maximum duration of the power-off state of the cabinet is 48 hours during maintenance. Clearance for the Cabinet Copyright © Huawei Technologies Co., Ltd. 2010. All rights reserved. Fan box Fan box

description

BTS 3900 GSM QIG

Transcript of BTS3900 GSM Quick Installation Guide-(V300R008&R009_02)PDF

1

BTS3900 GSM V300R008&R009Quick Installation Guide

900 mm

42 mm

450 mm

600 mm420 mm

≥200 mm

≥800 mm

Cabinet dimensions (height x width x depth): 900 mm x 600 mm x 450 mm

Modules in the Cabinet220 V cabinet-48 V cabinet +24 V cabinet

Fan box

BBUDCDU-01

BBU

+24 V power equipment

DCDU-01BBU

220 V power equipment

DCDU-01

RFU RFU RFU

Issue: 02Date: 2010-01-30

Safety InformationCheck the electrical connection of the device before operation and ensure that the device is reliably grounded.

When working at a height, be cautious about falling objects.

When operating the device, comply with the local safety regulations. The safety precautions provided in the documents are supplementary. You must comply with the local safety regulations.

Power off the device before performing operations on the power supply equipment.

High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all parties to ensure that the transmitter antennas are shut down.

When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes.

When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss. The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards.

When the cabinet is unpacked, it must be powered on in seven days. The maximum duration of the power-off state of the cabinet is 48 hours during maintenance.

Clearance for the Cabinet

Copyright © Huawei Technologies Co., Ltd. 2010. All rights reserved.

Fan box Fan box

2

Installing the Base on the Concrete Floor

2. Install the base.

1. Determine the installation position of the base and install expansion bolt assemblies.

Base

Ø1690°

52 mm to 60 mm

M12x60 boltSpring washerFlat washer

Expansion tubeDo not use a hammer drill to drill holes on the concrete pad through the holes on the base.

Insulating spacer(x2)

M12x60 bolt (x4)Spring washer 12

Flat washer 12Insulating washer

3. Adjust the base level and measure the resistance between the base and the bolts.

Adjust M12x30bolts (x4) on site.

Normal display: > 5 MΩ

The resistance between the base and the four expansion bolt assemblies should be respectively measured.

Level

Anchor hole

Concrete floor

Marking template

Installing the Base

3

Installing the Base on the ESD Floor

Concrete floor

2. Temporarily fasten the ESD floor and supports.

1. Determine the installation position of the base and drill holes on the ESD floor.

Support for the ESD floor

ESD floorFor details on how to drill holes and install expansion bolt assemblies on the concrete floor as shown in the figures ② and ③, see page 2.

When tightening the height locking bolts, you should tighten the bolts in the middle before tightening the bolts on both sides.

3. Install the base on the ESD floor.

M12x60 bolt

M12x70 bolt

Spring washer 12

Flat washer 12

M12x60 bolt (x4)Spring washer 12Flat washer 12Insulating washer

Insulating spacer (x2)

4. Adjust the base level and measure the resistance between the base and the bolts.

Do not use a hammer drill to drill holes on the concrete pad through the holes on the base.

(For details, see step 3 on page 2.)

For details, see step 1 on page 2.

Anchor hole

ESD floor

Marking template

Height locking bolt (both sides)

Mounting holes for the support

Height locking bolt (middle)

4

Installing the PGND Cables and Equipotential Cables

Installing the Cabinet and PGND Cables

Installing the PGND Cablesa

External ground barExternal ground bar

1. Install the PGND cable for the -48 V or 220 V cabinet.

2. Install the PGND cable for the +24 V cabinet.

If the cabinet is installed with the power subrack before delivery, you should remove the power subrack from the cabinet and also the power cable between the power subrack and the DCDU-01 and PGND cable for the power subrack before tightening bolts. After the cabinet is installed, install the power subrack, related power cable, and related PGND cable.

The cabinet door can be removed before the cabinet is installed for easy operations.

M12x50 bolt (x2)

Power subrack

Installing the Cabinet

5

Installing the Equipotential Cables b

side-by-side mode stack mode

M6

M6

M6

M6

BBU

DCDU-01 DCDU-01

BBU

DCDU-01

DCDU-01

RFU RFU RFU

RFU

Remove the cover plate.

The EquipotentialCables need to be installed only in the stacked +24 V cabinet scenario.

The cable installations in the stacked +24 V cabinet scenario and in the stacked -48 V cabinet scenario are similar, except that the equipotential cable needs to be installed on the left of the cabinet in the stacked +24 V cabinet scenario.

Fan box

Fan boxFan boxFan box

6

Installing the Power Cable for the -48 V Cabineta

Installing the Power Cable for the +24 V Cabinetb

DCDU-01

Free

PSU

+24 V cabinet

-48 V cabinet

When arranging for the power cable on site, do not expose the metal wire.

BBUFREE

BBUDCDU-01

RFU

RFU

Plastic cover plate

RTN(+)

The method for installing the power cable for cabinets installed side-by-side or power cable for stacked cabinets is the same as that for installing the power cable for a single cabinet.

NEG(-)

Installing the Input Power Cable

Installing Cables

In this document, the cable color and equipment appearance is for reference only. The actual cables and equipment may differ from what are shown in the figures.

Attach labels before routing cables.When cutting the BTS3900 input power cable, reserve an extra length of 300 mm. Add an OT terminal to the cable on site.

+-

Fan box

Fan box

7

Installing the Input Power CableInstalling the Power Cable for the 220 V Cabinetc

Installing Transmission Cables

PSU

BBU

RFU

DCDU-01

PMU

220 V AC single-phase input

110 V AC dual-live-wire input

220 V AC three-phase input

Short-circuiting cable for live wires (brown)

Short-circuiting cable for neutral wires (blue)

220 V cabinet

BBUGTMU

UPEU

BBU

E1/T1FE0

1. Installing the E1 Cable 2. Installing the FE Cable

Based on transmission mode, only one type of E1/T1 cable needs to be installed. Alternatively, FE cable is installed if FE transmission mode is used.

Ensure that both ends of the E1 cable are disconnected. Then, weld connectors to the bare wires at one end of the E1 cable all at once.

Fan box

8

Installing RF Cables

Attach color rings by referring to the following table.

Install the cables in the sequence from top to bottom and from both sides to middle.

Diversity antenna: one white ring and one blue ring

Main antenna: one white ring and two blue rings

3

Diversity antenna: one white ring and one yellow ring

Main antenna: one white ring and two yellow rings

2

Diversity antenna: one white ring and one red ring

Main antenna: one white ring and two red rings

1System 2

Diversity antenna: one blue ring

Main antenna: two blue rings3

Diversity antenna: one yellow ring

Main antenna: two yellow rings2

Diversity antenna: one red ring

Main antenna: two red rings1System 1

Color RingSectorSystemANT_TX/RXA

BBU

DCDU-01

RFU

ANT_TX/RXB

ANT_TX/RXA

ANT_TX/RXA

BBU

DCDU-01

DCDU-01

RFU

RFU

ANT_TX/RXB

ANT_TX/RXB

A single cabinet

Stacked cabinets

If main and diversity are not distinguished, the RF signals transmitted from the left RF unit are regarded as the main signals by default, and the RF signals transmitted from the right RF unit are regarded as the diversity signals.

If an antenna system serves six sectors, the colors of the rings for sectors 4, 5, and 6 are purple, orange, and green respectively.

If the inter-RFU RF signal cables are installed before the cabinet is delivered, only the cables on the ANT_TX/RXA ports need to be installed.

The methods for routing RF jumpers in a single cabinet and in cabinets installed side-by-side are the same. The cover plate of the upper cabinet must be removed before the RF jumpers are installed in stacked cabinets.

Remove the cover plate.

Fan box

Fan box

Fan box

9

Power-On Check

This chapter describes only the power-on check of the equipment. The base station must be powered on in seven days after installation.

The normal status of the indicators on the PMU:

RUN indicator: BlinkingALM indicator: OFF

The normal status of the indicators on the PSU:

Power indicator: Steady greenProtection indicator: OFFFault indicator: OFF

The normal status of the indicators on the GTMU:

RUN indicator:BlinkingALM indicator:OFFACT indiactor:ON

The normal status of the indicators on the FAN:

STATE indicator:Blinking greenThe normal status of the indicators on the UPEU:

RUN indicator:ON

The normal voltage range of the DC output power to the DCDU-01 is from:

-38.4 V DC to -57 V DC

The normal status of the indicators on the RFU:

RUN indicator: BlinkingALM indicator: ON for 1s and

then OFFACT indicator: ONVSWR indicator: OFFCPRI indicator: Steady green

The normal status of the LEDson the Fan box is as follows:

RUN indicator:BlinkingALM indicator:OFF

Turn on the external switch of thepower supply to the BTS3900

Start

Rectify the fault

Rectify the fault

Rectify the fault

Rectify the fault

No

No

No

No

No

Yes

Yes

Yes

Yes

Yes

End

Power on the DCDU-01

Check whether the outputpower of the DCDU-01 is normal?

(Optional)Check whether the LEDs

on the PSUs and PMU arefunctional?

Set the MCB labeled FAN on theDCDU-01 to ON

Check whether the Fan boxunit is functional?

Set the MCB labeled BBU on theDCDU-01 to ON

Set the MCB labeled RFU on theDCDU-01 to ON

Check whether all theLEDs on the BBU panel are functional?

Check whether all theLEDs on the RFU panel are functional?

10

AppendixRemoving the CPRI Cables

Product 4 Product 5

Product 3 Product 2 Product 1

Waterproofing Outdoor Cables

1. Wrap three layers of waterproof tapes.

2. Wrap three layers of insulating tapes.

Push Push Push

Push Push

PullPull

Pull

Pull

Cable tie

Waterproof tape

Insulating tape

The waterproof tape should be wrapped for an extra length of 20 mm away from the connectors at both ends.

The tapes should be wrapped around the connector from the lower part to the upper part. When wrapped for another layer, the tapes may not be cut.

When wrapping the waterproof tape, ensure that the upper layer of the tape covers at least 50% of the lower layer.

The insulating tape should be wrapped for an extra length of 20 mm away from the waterproof tapes at both ends.

Extend the tape.

Pull

11

Pin Assignment

TX4

TX3

TX2

TX1

RX4

RX3

RX2

Green

Gray

White

Brown

White

Green

Blue1

Orange23

Red22Twisted

pair Blue21

White20

Twisted pair Red26

Twisted pair Red24

25

White

Orange

White

Wire Color

6

Twisted pair

7

8

Twisted pair

19

Twisted pair

5

4

3

2

X1

Twisted pair

Twisted pair

Wire Type

RX1

Label

TX4

TX3

TX2

TX1

RX4

RX3

RX2

Tip

Tip

Ring

Tip

Ring

Tip

Tip1

Tip23

Ring224

Tip21

Ring20

8Ring26

6Ring24

25

Ring

Tip

Ring

Wire Type

6

77

8

219

55

4

3

2

X1

3

1

Coaxial SN

RX1

Label

1. Pin assignments for the wires of the 75-ohm E1 coaxial cable

2. Pin assignments for the wires of the 120-ohm E1 twisted pair cable

Green/whiteBrown/whiteGray/whiteBlue/redOrange/redGreen/red

Orange/whiteBlue/white

12

HUAWEI TECHNOLOGIES CO., LTD.Huawei Industrial Base Bantian Longgang

Shenzhen 518129People’s Republic of China

www.huawei.com