BTP Stage 2 Final

download BTP Stage 2 Final

of 37

Transcript of BTP Stage 2 Final

  • 8/13/2019 BTP Stage 2 Final

    1/37

    Indian Institute of Technology Indore

    2012-13

    B-Tech Projecton

    Prognosis And Maintenance Planning

    For Mechanical Components

    Submitted by: Guided by:Janam Shah Dr. Bhupesh K. Lad

    0900305

    Astha Jain

    0900313

  • 8/13/2019 BTP Stage 2 Final

    2/37

    Objective

    Predicting remaining useful life of a component by using ANN.

    Developing optimal maintenance strategies in the framework

    of RCM

    Developing optimal maintenance strategies for multi-component system based on RUL

    Developing optimal maintenance strategies for multi-

    component system based on age of the components

  • 8/13/2019 BTP Stage 2 Final

    3/37

    Predicting Remaining Useful Life

    Neural Network Training And Validation

    Conversion Of Data Into Signature

    Identification Of Failure Signature

    Identification Of Failure Parameter

    Data Collection

  • 8/13/2019 BTP Stage 2 Final

    4/37

    Data Collection:

  • 8/13/2019 BTP Stage 2 Final

    5/37

    Failure Parameter:

    Vibration Signals

    Failure Signature:

    RMS and Kurtosis

    )2....23

    22

    21

    (n1 YNYYY

    Yrms

    4

    1

    4

    )1(

    )(

    sN

    yyY

    N

    i i

    kurtosis

  • 8/13/2019 BTP Stage 2 Final

    6/37

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    0.6

    0.7

    0.8

    0 200 400 600 800 1000 1200

    RMSofBear

    ingA

    Data points

    RMS Vs Time(Data Points)

    Conversion Into Data Signature:

  • 8/13/2019 BTP Stage 2 Final

    7/37

    0

    2

    4

    6

    8

    10

    12

    14

    16

    18

    0 200 400 600 800 1000 1200

    KurtosisOfBearingA

    Data points

    Kurtosis Vs Time(Data Points)

  • 8/13/2019 BTP Stage 2 Final

    8/37

    Neural Network Training & Validation:

    Network Data Manager

  • 8/13/2019 BTP Stage 2 Final

    9/37

    Training Window

  • 8/13/2019 BTP Stage 2 Final

    10/37

    Result:

    So, from the above graph, we can see that our training error is comingin the range of 10-11, whereas our validation error is coming to be

    equal to 10-4.

  • 8/13/2019 BTP Stage 2 Final

    11/37

    Reliability Centered Maintenance

    RCM is defined as an approach to maintenance that combinescorrective, preventive, predictive, and design out

    maintenance practices and strategies so that the equipment

    functions in the required manner.

    RCM incurs minimum maintenance cost.

    It is a philosophy that decides on which component which

    technique is to be applied.

  • 8/13/2019 BTP Stage 2 Final

    12/37

    RUL Based Group Maintenance

    Problem Statement:

    To minimize the cost of group maintenance of a machine having 5components on basis of RUL with constant MTTR.

    Assumptions:

    1. Remaining Useful Life (RUL) of components follow a normal

    distribution.2. Components are in series, even if one fails the machine will bedown, hence downtime cost is taken constant.

    3. Assembling-dissembling time of the machine is constant, if it isopened once all components can be replaced/repaired as

    components are assumed to be structurally independent.4. The components which are not included in preventive groupmaintenance are correctively maintained.

  • 8/13/2019 BTP Stage 2 Final

    13/37

    Given:

    1.Mean () and standard deviations () for all the components

    2.Cost of the components (C1-C5) (Rs)3.Mean Time To Replace (MTTR1) of the components (hrs)

    4.Mean Time To Assemble-Dissemble for machine (MTTR2)

    (hrs)

    5.Mean Time To Assemble-Dissemble for individualcomponents for corrective maintenance (MTTR3) (hrs)

    6.Labour Rate (CL) (Rs/hr)

    7.Downtime cost (CDC)(Rs/hr)

  • 8/13/2019 BTP Stage 2 Final

    14/37

    Cost calculation:

    1. Preventive maintenance

    2. Corrective Maintenance

    3. Total Cost

    CT= CPM+ CCM

    )()( 2#

    1

    #

    DCLPM CCMTTRMTTRCC

    )()( 31 DCLiCM CCMTTRMTTRCC i

  • 8/13/2019 BTP Stage 2 Final

    15/37

    Model Window:

  • 8/13/2019 BTP Stage 2 Final

    16/37

    Result

    On simulating, we get minimum cost by preventively maintaining

    components 1, 3 and 5.

    Probab

    ilityofoccurrence

    Total Cost

  • 8/13/2019 BTP Stage 2 Final

    17/37

    RUL based group maintenance with

    varying parameters

    It is similar to the previous model only the Mean Time To

    Repairs (MTTR1, MTTR2and MTTR3) are varying, i.e. they are

    taken with log-normal distribution.

    d l d

  • 8/13/2019 BTP Stage 2 Final

    18/37

    Model Window

  • 8/13/2019 BTP Stage 2 Final

    19/37

    Result:

    Minimum cost= 1,03,351

    Mean cost= 1,46,682

    Optimum solution occurs by doing preventive maintenance of 1, 3 and 5

    M

    in.Cost

    No. of trials

  • 8/13/2019 BTP Stage 2 Final

    20/37

    Age based group maintenance

    Objective:To find optimum grouping of components (having initial age)for preventive maintenance on the basis of:

    minimum cost

    maximum availability

  • 8/13/2019 BTP Stage 2 Final

    21/37

    Given:

    Cost of components (C1-C5) (Rs 5000)

    Current age of components (V1-V5)

    Shape parameter of all the components (1- 5)

    Scale parameter of all the components (1- 5hrs)

    Corrective task duration (normal distribution- and )

    Preventive task duration = 8 hrs

    Labour Rate (CL) (Rs/hr)

    Downtime cost (CDC)(Rs/hr)

    Simulation time = 1yr = 8760 hrs

    Component (hrs) (hrs) (hrs)

    1 2000 2 8 2

    2 3000 3 12 2

    3 2500 3 16 4

    4 3500 2 14 3

    5 1800 3 20 6

  • 8/13/2019 BTP Stage 2 Final

    22/37

    Assumptions:

    Components are in series, even if one fails the machine will bedown, hence downtime cost is taken constant

    Components follow weibull failure distribution

    Scheduled time is varying for preventive maintenance, which

    is from 1,2,3.....,11 months The components which are not included in preventive group

    maintenance are correctively maintained

  • 8/13/2019 BTP Stage 2 Final

    23/37

    Model:

    The Cost values, weibull parameters and maintenance parameters

    are fed in the block properties of all the components in the BlockSim

    software. The model window is:

  • 8/13/2019 BTP Stage 2 Final

    24/37

    Block properties

  • 8/13/2019 BTP Stage 2 Final

    25/37

    Scheduled task properties are given for one of the block and for adding

    other blocks to the group, a maintenance group is created and the other

    blocks are assigned the same group.

  • 8/13/2019 BTP Stage 2 Final

    26/37

    For adding components to the group:

  • 8/13/2019 BTP Stage 2 Final

    27/37

    Simulation Window:

  • 8/13/2019 BTP Stage 2 Final

    28/37

    General summary result window:

  • 8/13/2019 BTP Stage 2 Final

    29/37

    After the simulations, cost of maintenances (both correctiveand preventive) and the total cost is calculated in MS-Excel.

    The cost formulas used are: Cost of preventive group maintenance:

    Cost of Corrective maintenance of a component:

    Total Cost of group maintenance:

    )(DCLPMiPMPM

    CCMTTRCnC

    )]()[(DCLCMCMCM

    CCMTTRCnC

    CMPMT CCC

  • 8/13/2019 BTP Stage 2 Final

    30/37

    Excel Cost File:

  • 8/13/2019 BTP Stage 2 Final

    31/37

    Now, taking maximum availability and minimum cost of every

    possible grouping in account, here 0 means we are doing corrective

    maintenance for that component and 1 represents we are

    performing scheduled maintenance for that component. The finaltable will be:

  • 8/13/2019 BTP Stage 2 Final

    32/37

    Combination Maximum Availability Minimum Cost

    0 0 0 0 0 0.971157 253285.6

    1 0 0 0 0 0.970634 259143

    0 1 0 0 0 0.970947 256845

    0 0 1 0 0 0.971174 255618.5

    0 0 0 1 0 0.970884 257779.9

    0 0 0 0 1 0.971465 254694.9

    1 1 0 0 0 0.97128 253124.3

    1 0 1 0 0 0.971921 252201

    1 0 0 1 0 0.971191 254273.2

    1 0 0 0 1 0.973196 249203.3

    0 1 1 0 0 0.973067 248755.9

    0 1 0 1 0 0.971664 252057.7

    0 1 0 0 1 0.974385 241248.9

    0 0 1 1 0 0.972471 250401.7

    0 0 1 0 1 0.975743 232523.60 0 0 1 1 0.973782 247590

    1 1 1 0 0 0.974647 231140.2

    1 1 0 1 0 0.971794 245508.5

    1 1 0 0 1 0.976008 223069

    1 0 1 1 0 0.974141 237251.3

    1 0 1 0 1 0.978142 213981.4

    1 0 0 1 1 0.975541 229783.8

    0 1 1 1 0 0.975298 229607.7

    0 1 1 0 1 0.978911 205676.1

    0 1 0 1 1 0.97663 221441

    0 0 1 1 1 0.9784 212602

    1 1 1 1 0 0.97694 210976.2

    1 1 1 0 1 0.981598 186883.6

    1 1 0 1 1 0.979017 203149.5

    1 0 1 1 1 0.9811 194006

    0 1 1 1 1 0.981951 185903.8

    1 1 1 1 1 0.984601 162981.9

  • 8/13/2019 BTP Stage 2 Final

    33/37

    Results and discussion:

    After simulating, it was observed that number of preventivemaintenance decreases with increasing schedule time whereas the

    number of corrective maintenance increases with it. Similar trend is

    observed in the downtime costs of preventive and corrective

    maintenances respectively.

    Minimum Cost is achieved when all the components are collectively

    prevented also the system has maximum availability at that time.

    The scheduled maintenance task should be performed every month

    to get the optimum result.

    Min cost incurred= Rs. 1,62,981.9

    Max. System availability= 98.46%

  • 8/13/2019 BTP Stage 2 Final

    34/37

    Conclusion & Future Scope

    ANN is an accurate tool to predict remaining useful life withan error of 10-4.

    RCM approach is useful for optimizing the cost during thegroup maintenance of multi-component system.

    For future work, we can take some more failure parameterslike noise to predict RUL accurately.

    RUL based and age based maintenance models can becombined to make it more realistic, which will help inwarranty estimation.

    We can also take imperfect maintenance or crew effect oravailability of repaired equipment.

  • 8/13/2019 BTP Stage 2 Final

    35/37

    References

    Refngah F. N. Ahmad, Abdullah S, Jalar A, Chua L.B, Life Assessment of a

    Parabolic Spring Under Cyclic Strain Loading, European Journal ofScientific Research, Vol.28 No.3 , pp.351-363, 2009.

    KainulainenPerttu, Analysis of Parabolic Leaf Spring Failure, Bachelordissertation Savonia University of Applied Sciences, 2011.

    Gebraeel Nagi, Lawley Mark, Liu R, Parmeshwaran Vijay, Residual lifepredictions from vibration based degradation signals: A Neural Network

    Approach, IEEE Transaction of Industrial Electronics, Vol. 51, No. 3 2004. Mahamad A K, Saon S, Hiyama T, Predicting remaining useful life of

    rotating machinery based artificial neural network, Computers andMathematics with Applications, Vol.60, pp 1078-1087, 2010.

    https://www.ti.arc.nasa.gov

    Rommert Dekker, Wildeman Ralphe, A Review of Multi-Component

    Maintenance Models with Economic Dependence, MathematicalMethods of Operations Research45:411-435, 1997.

    http://www.ti.arc.nasa.gov/http://www.ti.arc.nasa.gov/
  • 8/13/2019 BTP Stage 2 Final

    36/37

    Moghaddam Kamran S & Usher John S., A new multi-objectiveoptimization model for preventive maintenance and replacementscheduling of multi-component systems, Department of IndustrialEngineering, University of Louisville, 2010.

    Zhigang Tian, Youmin Zhang, and Jialin Cheng, Condition BasedMaintenance Optimization for Multi-component Systems,ConcordiaUniversity, Montreal, Quebec, H3G2W1, Canada

    https://www.palisade.com

    https://www.reliasoft.com

    Yuo-Tern Tsai, Kuo-Shong Wang, Lin-Chang Tsai (2004) A study ofavailability-centered preventive maintenance for multi-componentsystems,Reliability Engineering and System Safety, 84, 261270.

    Zhigang Tian, Tongdan Jin, Bairong Wu, Fangfang Ding (2011), Conditionbased maintenance optimization for wind power generation systemsunder continuous monitoring,Renewable Energy, 36, 5, 1502-1509.

    B. Castanier, A. Grall, and C. Berenguer, (2005), A condition-basedmaintenance policy with non-periodic inspections for a two-unit seriessystem, Reliability Engineering & System Safety, 87, (1), 109-12

    http://www.palisade.com/http://www.reliasoft.com/http://www.reliasoft.com/http://www.palisade.com/
  • 8/13/2019 BTP Stage 2 Final

    37/37

    Thank You