22-Jan-10 Page 0 of 26
-
22-Jan-10 Page 1 of 26
BSNL
Business Blueprint Document External Civil Projects
Business Process No .- BSNL_BBP_PS_SD_Ext Civil Project
(POC- CORP, KTK & MAH) Version:2.1
Approved By
Track Lead (BSNL)- Mr. Raj Kumar
Track Lead (HCL)- Mr. Rajesh Jain
Consultant (SAP India) Mr. Nitin Bhardwaj
-
22-Jan-10 Page 2 of 26
Version Control Date Version Author Change Description
1.0 Rajeev Sharma/Gaurav
Verma/Pawan Yadav,
Amit Gandhi, Shambhu
Sarkar
Draft
1.1 Rajesh Jain Review
2.0 Rajesh Jain, Rajeev
Sharma/Gaurav
Verma/Pawan Yadav,
Amit Gandhi, Shambhu
Sarkar
Final Submission and agreement
2.1 BSNL/HCL ERP/SAP
INDIA
Discussed and Mutually agreed
-
22-Jan-10 Page 3 of 26
Table of Contents
1. GENERAL EXPLANATION:- ............................................................................. 4
1.1 REQUIREMENTS / EXPECTATIONS:- .......................................................... 4
1.2 TO BE PROCESS DESCRIPTION:- ............................................................... 8
1.3 CROSS FUNCTIONAL CONSIDERATION:- ............................................... 13
1.4 ASSOCIATED PROCESSES:- ..................................................................... 15
1.5 BUSINESS MODEL / PROCESS FLOW- PDF FILE OF VISIO .................... 15
1.6 EXPLANATIONS OF FUNCTIONS AND EVENTS:- .................................... 18
2 SYSTEM CONSIDERATIONS .......................................................................... 19
2.1 SPECIAL ORGANISATIONAL CONSIDERATIONS:- .................................. 19
2.2 CHANGES TO EXISTING ORGANISATION:- .............................................. 19
2.3 DESCRIPTION OF FUNCTIONAL DEFICITS:- ............................................ 19
2.4 APPROACHES TO COVERING FUNCTIONAL DEFICITS:- ........................ 20
2.5 NOTES ON FURTHER IMPROVEMENTS:- ................................................. 20
2.6 SYSTEM CONFIGURATION CONSIDERATIONS:- ..................................... 20
2.7 AUTHORISATION AND USER ROLES:- ..................................................... 20
2.8 ADDITIONAL DATA REQUIREMENTS:- ..................................................... 23
2.9 INTERFACE REQUIREMENTS:-.................................................................. 23
2.10 REPORTING REQUIREMENTS:- ................................................................. 24
2.11 ENHANCEMENTS, LISTS AND FORMS:- ................................................... 24
2.12 ANNEXURE:- ............................................................................................... 24
-
22-Jan-10 Page 4 of 26
1. General Explanation:-
Bharat Sanchar Nigam Ltd. formed in October, 2000, is World's 7th largest Telecommunications Company providing comprehensive range of telecom services in India: Wire line, CDMA mobile, GSM Mobile, Internet, Broadband, Carrier service, MPLS-VPN, VSAT, VoIP services, IN Services etc. BSNL has installed Quality Telecom Network in the country and is now focusing on improving it, expanding the network, introducing new telecom services with ICT applications in villages and winning customer's confidence.
Civil Wing in BSNL is responsible for providing & maintaining vital infrastructure for providing Telecom services. Civil Wing has to support all BSNL function groups for development of their civil infrastructure.The Civil Wing cadre in all these setups is being maintained by BSNL.
The Civil Wing is responsible for:
Construction of Telephone Exchange Buildings, Residential Buildings, office accommodations, Administrative Buildings, Microwave Towers, Satellite communication Buildings etc
Developmental works viz road, water tanks, landscapes & horticulture works etc.
Construction of cable duct & cable duct chambers & other similar works related to external plant.
Environmental works for Telephone Exchange Buildings.
Construction/furnishing of customer service centres/call centres.
Supply of Tower, foundations and erection of different type of towers
Day to Day and Annual maintenance operations and addition/alteration works.
Facility Management such as Housekeeping, Security operations of buildings and IQs in some of the circles.
Rehabilitation and retrofitting of buildings.
Interior and furnishing works
Compilation of Asset (Land and Building) records and its valuation.
Execution of Commercial Exploitation - BSNL Assets Projects.
Real Estate management (REM) through harnessing the BSNL assets(L&B).
Execution of USO Towers (IP) Project
Updating the specifications of buildings, Quality Assurance and Technical Audit of BSNL assets, contract documents, vendor enlistment and policy statement/document for commercial exploitation.
Fair Rent Assessment for hiring of buildings/land (FRAC) for BSNL infrastructure.
Main features of Civil wing:
Civil wing carries out in-house planning, design and execution of buildings and infrastructure through experienced and registered contractors.
Project planning and design is facilitated through computers using various reputed software of the Civil Engineering field.
Structural Drawings are being prepared by departmental staff either manually or through computers.
All the infrastructure projects are done through systematic approach to project management techniques in a time bound manner.
All the construction works are closely monitored at various levels to ensure quality of work and its timely completion.
-
22-Jan-10 Page 5 of 26
1.1. Requirements / Expectations:-
1.1.1. External Project Requirements:-
a) Proposed IM Structure:
NB Projects
MAH Circle KTK Circle Gujarat Circle
Civil Works
IM STRUCTURE
For NB Projects
Electrical
Works
Below
Hierarchy will
be same as
describe under
KTK Circle
Below
Hierarchy will
be same as
describe under
KTK Circle
Ext WorksComm.
ExploitationsUSO (IP)
Civil WorksElectrical
Works
b) The system should have a provision to capture the Action Plan in the system as per the targets assigned by corporate/circle.
c) As is Process: - For external projects/Comm. Exploitations of existing lands & building the funds requirement is allocated from the circle or corporate as per the requirement as and when the project comes. This process in current scenario is done on adhoc basis.
To Be Process: - There shall be an IM structure created in the system (captured as above) wherein the corporate shall allocate the funds as per the action plan. This fund or budget is given to meet the cost on account of EMD or PBG and any cost for executing the External Projects/ Comm. Exploitations of existing lands & building.
1.1.2. Lead to Cash Process:-
1.1.2.1 Lead (Inquiry) requirements:-
Separate tracking for leads of Electrical & Civil projects.
Tracking the leads on the basis of validity.
-
22-Jan-10 Page 6 of 26
Approval mechanism for inquiry is required to approve the same based on approval hierarchy of BSNL.
Separate billing provision for Services & Material.
Requirement is there to capture the Service tax only (for Composite service tax billing) where-in the service tax is charged as applicable.
1.1.2.2 Contract requirements:-
Validation for the approval of Price/Cost Sheet in inquiry before Contract creation.
Tracking the Contract/Project on the basis of validity.
Separate billing provision for Services & Material in the Contract.
Complete Tax Capturing & Reporting (inclusive of special taxes).
1.1.2.3 Release Order requirements:- a) Release Order is required to be created based on project.
Separate tracking of External Deposit work/ PMC work Release Order.
Release Order should be referring to the contract based on the quantity and values both.
b) Two separate release orders pertaining to Deposit work/ PMC work may refer to one
contract.
1.1.2.4 Outbound Delivery requirements:-
a) Outbound delivery is required for following processes:-
Delivery of material from BSNL Stock
Delivery of material from vendor to Project Site
1.1.2.5 Commercial Invoice Requirement:-
a) Provisioning of invoice to capture material and services offered.
b) Commercial invoice is required for following billing processes:-
Milestone based billing(fixed milestone)
Cost + Margin billing (Turnkey Project)
Invoice for Consultancy Charges (PMC)
Delivery based billing
c) Commercial Invoice should capture the pricing and tax details
1.1.3. Project Structure:-
-
22-Jan-10 Page 7 of 26
a) Project Structure (External) shall be created as per the below hierarchy including Project Definition, WBS Elements and Different Activities:-
Note: The above is just an indicative of the PS Structure further WBS, activities and Milestone can be added at the time of realisation phase as well as at the execution phase. b) Individual Site wise Project structure shall be created by Executive Engineer - civil,
each project shall be containing the following information at the time of creation:
Field Name (all mandatory) Example of Values
Type of Work
PMC
Deposit
Turn Key
Type Of Project
Office/Admin Building
Staff quarters
technical building
training Centers
Auditoriums
Lab
Towers
Others
Guest House
Note: - Name of the customer shall be picked up from the Sales Order to the Projects.
c) Organizational elements such as Company Code, Business Area and Profit centre are mandatory field which are require to be entered at the time of creating the project.
d) Project Coding shall be as follows:-
-
22-Jan-10 Page 8 of 26
1.2. To Be Process Description:-
1.2.1 Lead Creation & Tracking :-
a) Different Inquiry document types will be created to capture External Civil Inquiry Process.
b) The inquiry will be validated for a defined period. c) There will be approval mechanism to approve the inquiry, provision for attachment
for the price sheet will be there (Word/Excel/PDF); this approval will be based on user status.
d) There will be SAP manual workflow (option to select the user id of recipient) for approval of Inquiry/quotation. Approval (validation) from the competent authority of inquiry will be required before quote/ Bid submission. An Approval mechanism for inquiry will be provided to approve the same based on approval hierarchy of BSNL.
e) Material and Services are to be captured as separate line items. Composite Service Tax will be charged on the entire value of work/service where no bifurcation is available for material and service value.
f) Sales tax will be charged on the price of material delivered whereas Service tax will be charged on services offered.
g) Quotation will be created with the reference to inquiry.
1.2.2 Contract Creation:-
a) Successful quotation/Bid will only be converted into contract. The contract document structure will be uniform for all contract type irrespective of Deposit work or PMC work.
b) Contract will be having a validity period. c) Following data will be copied from quotation to contract document,
Sold to Party (Customer placing the order)
Ship to Party (Project Site)
Material Code & quantity(for material to be delivered)
Material Code (for services to be offered and quantity if required)
-
22-Jan-10 Page 9 of 26
d) Pricing:
Material value will be captured based on approved material prices.
In case of material, Sales Taxes e.g. CST and VAT to be captured.
For Installation of material, Service tax will be applicable.
Any special tax applicable will be captured as manual condition type.
A separate line item to be created for the total contract Value where bifurcation is not available for material value and Installation value (For Composite service tax)
BSNL to provide the details of various existing & required pricing structures to be configured in the system.
e) Project will be executable at multiple sites referring to same contract. This means that consignee details captured in the system shall be such that the state specific sales taxes can be captured in case the sites are in different states.
1.2.3 Creation of Release Order:-
a) Release Order will be created with reference to Contract. There will be two type of civil release order. Deposit Work Order
PMC Work Order
Note: - Different order type will be use to identify the type of work for sales analysis purpose.
b) Following data will be copied from Contract to Release Order Document
Sold to Party (Customer placing the order)
Ship to Party (Project Site)
Material Code & quantity(for material to be delivered)
Material Code (for services to be offered)
Prices & Taxes (as applicable)
Note: - The Contract reference (value or quantity) will be mandatory for creating any work order.
c) Required Project (WBS) will be assigned in the work Order for capturing of Planned
Revenue.
d) Defined Milestone (created in project based on the agreed terms and condition) will be copied from Project to Releases Order.
e) Following billing scenarios will be provisioned,
Milestone based billing(fixed milestone)
Cost + Margin billing
Invoice for Consultancy charges. (Charges for validating vendor invoice)
Delivery based billing
1.2.4 Creation of Outbound Delivery:-
Note:- The below mentioned scenarios do not exist in the As-IS process , but the provision is
kept in the system to take care of the invoicing.
Two scenarios will be addressed,
-
22-Jan-10 Page 10 of 26
a) Delivery from BSNL stock
In this case the delivery will happen from BSNL stock by referring the work Order. Following Accounting entries are passed,
COGS (Cost of Goods sold) account Dr Inventory account. Cr.
b) Delivery from Vendor to Project Site
Most of cases BSNL directly procure from vendor and consume the material at project site. In this case no delivery will happen from BSNL stock Therefore no delivery document will be created.
1.2.5 Invoicing:-
a) Following billing scenarios will be addressed,
1. Milestone billing:-
In this scenario, the total project value is based on contract value. Based on milestone completion, percentage of total project value will be billed as captured against the milestone.
Required project milestone will be created in Project (WBS) which will be copied in work Order.
Each milestone will be assigned Billing block automatically. This Billing block will be removed for billing by confirming actual date in Project milestone (WBS).
2. Cost + Margin billing :-
In this billing scenario, total cost consumed in project will be billed with certain margin to customer.
In this billing process any authorized billing user will see the cost accumulated in project by running a report CJI3. By adding defined margin (as agreed in the contract) in project cost. Accordingly release order will be created and billing shall be generated referring to the Work order.
3. Invoice for Consultancy Charges(PMC Scenario):-
Some cases BSNL provide consultancy to end customer for validating vendor works. In this scenario vendor send invoice to BSNL for validation. Based on work completion, BSNL verify and validate the vendor invoice and send to customer with his consultancy charges in separate invoice.
4. Delivery based billing:-
Note: - The below mentioned scenarios do not exist in the As-IS process , but the provision is
kept in the system to take care of the invoicing.
In this billing scenario, total delivered material value shall be billed (Directly issued material from BSNL stock).
b) Accounting entries for the Commercial Invoice from BSNL stock
Customer A/c Dr.
-
22-Jan-10 Page 11 of 26
Revenue A/c Cr.
Sales taxes A/c Cr.
1.2.6 Creation of Corporate Funds Plan: -
In order to meet the funds requirement for the External projects the corporate shall be giving the circle wise funds under the Civil head (as per the IM structure). This shall be in line with the proposed targets. For the details of the same please refer to
the FI BBP document no. BSNL_BBP_FICO_CAPEX_IM_PROCESSES_V1.0
1.2.7 Project Creation and Costing:-
Scenario 1(Civil Project) a) After the work order is created in the system by the Executive Engineer or the
competent authority on the basis of the Purchase order received from the customer, the Project shall be created using the templates as captured in the Project Structure Section as well as based on contractual details.
b) At this stage Person Responsible for the top level WBS element shall be entered as per the competency.
Scenario 2 (Civil Part as a part of Electrical Project) a) The CE or the competent authority gets the intimation to create the project/detail
the Civil WBS work from the respective Electrical Wing along with the Civil WBS code and approved drawing detail from the Architect Department (or from customer) via SAP workflow mail.
1.2.8 WBS Costing and budgeting by Civil Wing: -
a) In case of external projects a Preliminary estimate (if required) otherwise a detailed estimate shall be created at the initial level only. To assist in preparation of cost estimate information shall also be available from SAP on the updated purchase price of the services on a real time basis for the same or different circles as well as the DSR item codes.
c) After creation of Cost estimate the user status (User status is a functionality in SAP system to update the progress of project by an authorized person) is changed to Cost Estimate Created by authorized civil wing person.
d) Next step will be the roll up of the cost to IM position in the system to be done by Civil Finance wing which will ensure that the cost estimate is visible in line with the budget at the respective IM Position.
e) Budgeting:- Budgeting (to be read in conjunction with the funds allotment )shall be done as per the cost estimate (either more or less) to the work package or the WBS element. The expense in such case shall not be possible to be exceeded beyond 10% of the budgeted values. This is in line with the BSNL policy of expense control.
f) In case the value of estimate is beyond 10% of the approved value (while execution) then additional /supplementary funds shall be asked for by the Executive Engineer (or the defined authorized personnel of Civil wing)from the concerned as per the competence.
g) Civil Finance wing (as per the competence) on receiving the request for additional fund shall provide the necessary funds from the IM structure and intimation shall be given to the Executive Engineer (or the requesting authority) on the same.
Note:-
The funds approval related to each WBS element shall be as per the financial powers of the concerned official in line with the BSNL policies.
-
22-Jan-10 Page 12 of 26
The information flow shall be by means of manual workflow (SAP Mail) where-in based on the cost estimate the sender selects the username /User ID of the recipient and automatically sends the cost estimate via the SAP Mail.
1.2.9 Project Execution:- a) The execution process starts with the information of project concurred and
approved being available to the CE/SE/Executive Engineer (or the defined authorized personnel of Civil wing) through the SAP workflow mail.
b) After getting the FI concurrence the project is released by the competent authority. Release of the project shall mean that now only the logistical processes can be initiated from the project
c) If required the Detailed Drawings, Detailed estimate shall be prepared internally else the PR no. shall be generated on the Civil WBS element and the tendering process shall follow. The subsequent process is as captured in the MM BBP Document No.
BSNL_P1_ALL_BBP_MM_PUR
d) Recording Project Progress:-System shall be configured to capture the following key information for Civil WBS element by either a user status, Milestone or through normal logistical transactions so that the project progress is available.
Sr No Key Information PS Object
1 Survey of the site Activities
2 Layout/Preliminary Drawings User Status
3 Approval from Municipal Authorities User Status
4 Details arch drawings User Status
5 structural drawings User Status
6 soil investigation Milestone
7 Horticulture work/land scaping Milestone
8 Foundation Milestone
9 Slab Completion Milestone
10 Building Use Permission Milestone
11 Structure Completion Milestone
12 Internal work completion Milestone
13 External Development Milestone
Disclaimer: - Above list can be further modified as per the project monitoring at the time of project execution.
e) Services Entry against the Service Order/work order (MB):- The services shall
also be recorded in the system by the JTO/SDE as per the MM process captured in
BBP Document no. BSNL_P1_ALL_BBP_MM_PUR to record the project progress.
f) Inspection Process:- After doing Pre Inspection by Executing Authority, the concerned person of the WBS element shall update the user status as Pre Inspection Done and Information communicated to Customer (Offering Memo). On getting the information of Inspection completed the user shall update the status that Inspection is completed in the SAP system. A scanned copy of the Clearance report shall be attached to the WBS element (wherever applicable) after customer inspection is over.
-
22-Jan-10 Page 13 of 26
g) Milestone confirmation: - As per the contract details the milestones shall be created in the system on the respective WBS element for raising the invoice to the customer. These predefined Milestones shall also be having a scheduled date and once the work related to the milestone is completed, the same shall be confirmed by the civil wing and an actual date shall be input on the milestone. This will remove the billing block in the work order and an invoice shall be raised to the customer as explained in the SD Billing section.
n) Journal posting by Finance:- Any other cost which is not attributable to Procurement(of material and services) and Direction and execution , e.g. fees to be given for permission to govt. Bodies etc. can be directly booked via FI postings in system using the respective WBS element(Miscellaneous etc.)
Note: - The actual cost and the revenue values shall be regularly updated to the system after the transactions automatically and the same is available in the standard reports of Projects systems.
1.2.10 Project Closure:-
a) On getting the inspection done the individual WBS element is set a status as TECO. Or Technical Complete, this status shall signify that the work is technically complete. The concerned site-in-charge or Executive Engineer shall change the user status to Hand over done.
b) Finance team settles all the expenses and Revenues related to Project. c) Civil Wing team monitors the Defect Liability period information and confirms the
milestone related to the same. d) Project is closed by changing the status to Closed (CLSD).
1.3 Cross Functional Consideration: - Integration Requirement in detail
1.3.1 FI Integration:-
a) In Some Contract, customer retains some amount as retention. This amount is settled at the end of the project as per agreement with customer. There should be provision to book the revenue with or without retention amount. (Need to discuss with FI- Integration Point)
b) Most of cases BSNL charges Composite Service tax where no bifurcation is available for material and service value. No utilization is there in such scenarios against the Cenvat etc.
c) In some of the contracts BSNL takes the advance from the customer, this advance amount is adjusted against each invoice as per milestone achieve.
d) To book the expenses on A/C of miscellaneous charges when project is not released.
e) Civil Wing shall be using the FI organizational structure values (say e.g. Controlling area, Company code, Business area and Divisions) as per the details captured in FI
BBP document no BSNL_BBP_FICO_Org Structure_V0.2 related to the BSNL organization structure.
-
22-Jan-10 Page 14 of 26
f) IM (Investment Management) structure shall be as captured in the requirements
section and as per the FI BBP document No. BSNL_BBP_FICO_CAPEX_IM_
MASTER DATA_V1.0.
g) Option to have an excel working related to Action Plan as well as a field to enter the quantity related to the funds requirement should be there in system in the IM structure.
h) The manpower charges for External Projects :-
Plan Manpower Cost: - Manpower Cost Planning is done as per Viability Report-Details.
i) For details on settlement of AUC/Profitability segment the system shall be configured
as per the details captured in FI BBP document no. BSNL_BBP_FICO_ASSETS
ACCOUNTING_V1.0.doc j) Process for acceptance of PBG/EMD amount will be captured in FI BBP Document
No. BSNL_BBP_FICO_AP NON PO IV_V1.0
k) Service tax process shall be captured in FI BBP Document number BSNL_BBP_
FICO_Taxation_V1.0 l) Payments to contractor as per MB (Invoice Verification Process) shall be captured in
details in the FI BBP Document No. BSNL_BBP_FICO_AP PO IV_V1.0.doc
1.3.2 Integration with MM:-
a) MM organizational structure: - Civil PS process shall be using the logistics organizational elements like Plant, Purchase organization, purchasing group etc. For
the details on the same please refer to the MM blue print document no BSNL_P1_
ALL_ BBP_MM_LO b) The Civil department shall create the detailed estimate using the Items code
mentioned in DPAR/DSR and also using Market Rate Items. For details of master
creation please refer to the MM Master BBP Document no. BSNL_P1_ALL_
BBP_MM_MD
c) Tendering in detail is captured in the SRM BBP document no.BSNL_P1_ALL_
BBP_SRM_Tendering
d) Procurement process related to Civil shall be as per following details:-
There is no centralized procurement (non Site specific) of materials for Civil Wing in the As-Is Process.
Purchase Requisition shall be given from project (PS Module) for procurement of services to the MM department for specific procurement.
For further details on above points please refer to the MM BBP Document No.
BSNL_P1_ALL_BBP_MM_PUR
e) Services Entry against the Service Order/work order
Four levels of approvals are required in the system before the payment is made to
vendor:-
1st level (creation) :- By JTO/SDE
2nd Level (Checking) :- By SDE
-
22-Jan-10 Page 15 of 26
3rd Level (FI Checking and Concurrence):- AO
4th Level (Passed for Payment):- By Ex. En.
Only abstract shall be captured in the service entry sheet. For details of Service Entry/R.A Bill process please refer to the MM Blue print No
BSNL_P1_ALL_BBP_MM_PUR. and FI BBP No. BSNL_BBP_FICO_AP PO
IV_V1.0.doc
Disclaimer: This BBP document covers the integration aspects of SAP MM and FI-CO module related to SAP project system module. This document does not cover the entire process of SAP
MM and FICO related to Civil business process.
Note: This BBP document covers the integration aspects of SAP MM and FI-CO module related to SAP project system module. This document does not cover the entire process of SAP MM and
FICO related to Electrical business process.
1.3.3 SD Integration:-
The logical linkage to Sales and Distribution module shall be by means of the following:- a) Capturing the WBS code in Work order. b) Capturing the Customer Code in Project Systems. c) Capturing Milestone Billing plan in Work Order.
The actual revenue shall be updated to the projects Module automatically as and when the invoicing is done to the customer. Actual cost to the project shall be on account of the Material issue/service entry sheet or direct FI postings.
1.4 Associated Processes:-
Following is the list of associated processes which form an integral part of External Projects Civil process.
a) Inquiry to Cash Process:- AS explained in the section above in the above section no. 1.1.2 .
b) Project Estimate Process:- Outside SAP (only the summary values of component heads are captured in SAP IM )
c) Approval of Project Estimate:- AS per SAP Mail d) Tendering and Procurement: - Details as per the BBP document no. BSNL_P1_
ALL_BBP_SRM_Tendering of MM.
e) Material/Service Acceptance: - Details as per the BBP document no.BSNL_P1_ ALL_BBP_MM_PUR of MM.
f) Settlement: - Details as per the BBP document no.BSNL_BBP_FICO_ PROFIT CENTRE ACTG_V1.0.doc of FI-CO.
1.5 Business Model / Process Flow- PDF File of Visio
1.5.1 Project Requirement:-
-
22-Jan-10 Page 16 of 26
1.5.2 Project Lead to Order:-
1.5.3 Project Planning:-
-
22-Jan-10 Page 17 of 26
Finance Team of Respective W
ing
Circle Civil Wing
Name
Signature
1.5.4 Project Execution:-
1.5.5 Project Closure:-
-
22-Jan-10 Page 18 of 26
Testing and project closure : Infra Civil
External Project Civil
Circle Finance Team
Final Inspection
Civil Div/Civil Circle (EE/SE)
Circle Civil Wing
Subject Matter Expert (SME)
Name
Signature
Notes
YES
Periodic inspection will
be carried out by CE/EE/
SE update user status.
START
NO
After completion of
complete work MB is filled
(Service entry is accepted)
and SDE submit the bill to EE by updating status.
SAP
After completion of
site work final inspection will be
carried out by EE/
SESAP
All work
completed?
Project Status shall be changed to TECO once
final inspection is
completed and attach
Clearance and
Commissioning Report as
PS text
SAP
A
Inform Circle Civil
team for
completion of work.
SAP
A
Collect amount
from customer
Finance team settle
the cost and
revenues on to
project.
SAP
End
Finance team carry
out profitability
analysis for Project.
SAP
SAP
SAP
EE civil wing technically
close the project and Raise
final invoice on customer
(After Defect liability period
if any) SAP
Inform Customer about
closure of the Project by
EE/SE
Take Building Use
Permission from local
authorities
Dispute management
1.6 Explanations of Functions and Events:-Trigger to a Different
process, Yes/No of approvals and typically work flows.
1.6.1 Inquiry to Cash process:- There will be approval mechanism to approve the inquiry, provision for
attachment for the price sheet will be there (Word/Excel/PDF); this approval will be based on user status.
1.6.2 Project Creation process:- The trigger to create the external project shall be from the Civil Department (in
case of Civil Project). Similarly information shall flow to civil department in case if the project has a Civil work involved in it by Electrical Wing. Both ways it will be by SAP manual workflow mail.
1.6.3 Project Execution:- Information on the reservation is created from the projects team and the reports
shall be available in the system for the stores in charge for the project wise material or equipment requirement.
The materials/service shall be issued to the project WBS element as per the stipulations and information for the same shall be given to the site-in charge by SAP mail.
After the service entry sheet is created a work flow mail shall be given to the concerned authority of the civil wing as per the MM blue print (no. Mentioned
earlier BSNL_P1_ALL_BBP_MM_PUR)
1.6.4 Project Closure:-
-
22-Jan-10 Page 19 of 26
Information to FI on inspection/A/T done shall be passed on with a manual workflow by Civil Wing.
2 System considerations
2.1 Special Organisational Considerations:-
For civil wing the purchasing authority as well as the execution team in-charge is the same authority hence both the functions are performed by same entity.
In the To Be Scenarios the Role of Architecture in SAP system shall be to attach the drawing to the respective WBS element and update the respective user statuses only.
2.2 Changes to Existing Organisation:-
Change in steps, Change Management, Point form
Work by the Civil Wing on the project shall start only on the receipt of the information from different business lines/SSAs or user departments along with the WBS code.
The assignment to WBS element with a position in IM shall initiate the budgeting or funds allotment. The change from As-Is is that the funds allotment shall be done by concerned IFA of Circle/SSA from the IM position rather than following the current process of allocation of the funds from circle or corporate on an adhoc basis.
In the new system there shall not be any approval on the hard copy of the estimate. All the approvals shall be system based. System shall keep an automatic record of the changes to the user-status and the person ID who has made these changes for future reference purpose.
All the projects or the detailing of WBS related to Civil works shall be created in the system by competent authority of civil wing.
All the internal Information related to projects work (which require instruction or approval) shall be initiated via SAP workflow mails.
All the confirmation on the important events (captured as Milestones) need to be updated with the Actual Dates to get the real time progress update by the respective authorities (Circle/SSA/Civil/Business Line)
The Civil Wing shall receive the work request of the business line via SAP mail and it is only after the civil wing gives the Preliminary estimate, the final Project Estimate shall be created by the respective Business Lines.
Approved quotation/ bid will only be converted into contract. In case of Cost + Margin Billing, the Billing value will be referred from the work
Order.
2.3 Description of Functional Deficits:-
The details of functional deficits are as follows:-
S.No. Functional Deficits
-
22-Jan-10 Page 20 of 26
1
Creation of Extra Fields for External Civil
projects
2
Note sheet with comments of the respective
approver along with the Cost estimate
2.4 Approaches to covering Functional Deficits:-
S.No. Functional Deficits Approach
1
Creation of Extra Fields for External Civil
projects Development
2
Note sheet with comments of the respective
approver along with the Cost estimate Development
2.5 Notes on Further Improvements:-
End to End process visibility of the system
Clarity and transparency of the system in terms of capturing the User-ID, Date and time of the person who is making the changes.
Real time availability of Financial and progress reports related to project.
System based tracking of funds w.r.t the budget allocated for the project. Clear visibility of the person responsible for the overall project as well as at the
component level of the project.
2.6 System Configuration Considerations:-
N/A
2.7 Authorisation and User Roles:-
sr
no Steps Where Role/Designation
Create Change
Display
(only)
1
Annual budget is
arrived for the Ext
Civil Project (IM top
position is created)
Corporate
2
Budget is bifurcated
to Circle wise (level
two position is
created in IM)
Corporate
-
22-Jan-10 Page 21 of 26
3 Create Inquiry for
customer along with
Partner Function
Corporate Civil
Wing/Circle Civil
Wing (CE)/Civil
Div/Civil Circle
(EE/SE)/Architect
wing
CE till JTO CE till JTO CE till
JTO
4 Attach Quotation as
a document to a
Inquiry
Corporate Civil
Wing EE/SDE/JTO CE till EE
CE till
EE
5 PGM/ED approve
pricing details
Corporate Civil
Wing As per User Status
6
Obtain approvals for
pricing from
competent
authority(
CE/PGM/ED)
Circle Civil Wing
(CE) As per User Status
7 Create Contract
along with contract
details
Circle Civil Wing
(CE) CE/SE/EE CE/SE/EE
CE till
JTO
8 Create Project
structure
Circle Civil Wing
(CE) CE/SE/EE CE/SE/EE
CE till
JTO
9 Update Contract
(assign Billing WBS
and Billing Plan)
Circle Civil Wing
(CE) CE/SE/EE CE/SE/EE
CE till
JTO
10 Assign activities to
Project (Task need
to be carried out)
Circle Civil Wing
(CE) CE till JTO CE/SE/EE
CE till
JTO
11
Planning team
prepares the Project
Estimate for
Individual Project.
(PE)
Circle Civil Wing
(CE) CE till JTO CE/SE/EE
CE till
JTO
12 Assign billing and
Progress Milestone
for Project
Circle Civil Wing
(CE) CE/SE/EE CE/SE/EE
CE till
JTO
13
Planning team
update Project
status on creation
of plan cost
information shall
pass on to concern
finance team.
Circle Civil Wing
(CE) CE till JTO CE/SE/EE
CE till
JTO
14 Reviews the over all
project costing and
estimation done
Finance Team of
Respective Wing
IFA of
approving
authority
IFA of
approving
authority
CE till
JTO/JAO
-
22-Jan-10 Page 22 of 26
15 Assign Project to the
IM Position to
Respective circle
Finance Team of
Respective Wing
IFA of
approving
authority
IFA of
approving
authority
CE till
JTO/JAO
16
Finance concurs the
Project based on
Financial powers of
the CE/SE/EE via
user status
Finance Team of
Respective Wing
IFA of
approving
authority
IFA of
approving
authority
CE till
JTO/JAO
17
Information shall
pass on to concern
CE/SE/EE for
approval.
Finance Team of
Respective Wing
IFA of
approving
authority
IFA of
approving
authority
CE till
JTO/JAO
18
After concurrence
from Finance (CE)
head approves the
project (Release
Project)
Circle Civil Wing
(CE) As per User Status
19
Create Down
payment
Request/milestone
payment
Finance Team of
Respective Wing
IFA of
approving
authority
IFA of
approving
authority
CE till
JTO/JAO
20 Update account
receivable
Finance Team of
Respective Wing
IFA of
approving
authority
IFA of
approving
authority
CE till
JTO/JAO
21
Service order issued
to selected Architect
by SDE/EE according
to the financial
powers
Civil Div/Civil
Circle (EE/SE) EE/SDE EE/SDE
CE till
JTO
22
Architect prepares
Layout &
Preliminary drawing
and assign as PS
Text
Civil Div/Civil
Circle (EE/SE) EE/SDE EE/SDE
CE Till
JTO
23
Architect prepares
Detail drawing and
DE shall be created
by civil wing
Civil Div/Civil
Circle (EE/SE) CE/SE/EE/SDE CE/SE/EE/SDE
CE Till
JTO
24
Drawing is reviewed
technically by
project executer
CE/SE/EE and
update user status
after review.
Civil Div/Civil
Circle (EE/SE) As per User Status
-
22-Jan-10 Page 23 of 26
25
JTO/SDE fill MB
(service entry sheet)
and update/confirm
project
activities/Milestones
Civil Div/Civil
Circle (EE/SE) SDE/JTO EE/SDE/JTO
CE Till
JTO
26
Periodic inspection
will be carried out
by CE/EE/SE update
user status.
Civil Div/Civil
Circle (EE/SE) As per User Status
27
After completion of
complete work MB
is filled (Service
entry is accepted)
and SDE submit the
bill to EE by
updating status.
Civil Div/Civil
Circle (EE/SE) SDE/JTO EE/SDE/JTO
CE Till
JTO
28
Project Status shall
be changed to TECO
once final inspection
is completed and
attach Clearance
and Commissioning
Report as PS text
Civil Div/Civil
Circle (EE/SE) CE/SE/EE CE/SE/EE
CE Till
JTO
29
EE civil wing Raise
final invoice on
customer (After
Defect liability
period if any)
Civil Div/Civil
Circle (EE/SE) EE EE
CE Till
JTO
30 Finance team carry
out profitability
analysis for Project.
Circle Finance
Team EE/AO EE/AO
CE till
JTO
31
Finance team settle
the cost and
revenues on to
project.
Circle Finance
Team EE/AO EE/AO
CE till
JTO
Note:- The role of Architect wing of BSNL (if applicable) shall be same as per the details
captured in the BBP document for Civil Internal Projects.
2.8 Additional Data Requirements:-
N/A
2.9 Interface Requirements:-
N/A
-
22-Jan-10 Page 24 of 26
2.10 Reporting Requirements:-
PS_Dev_CW_05 M_1 Expenditure Reports
PS_Dev_CW_06 M_2PR 50L-20Cr Reports
PS_Dev_CW_07 M_3 Tower Reports
PS_Dev_CW_08 Q_1Action Plan Reports
PS_Dev_CW_09 Y_2 RE-BE Reports
Standard
Plan vs Actual cost & Revenue Reports w.r.t Division,
Projects Reports
Standard Customer Specific Projects w.r.t no of Project & Values Reports
2.11 Enhancements, Lists and Forms:-
PS_Dev_CW_01 Customer Field Enhancement Enhancements
PS_Dev_CW_02 Note Sheet editable/un editable Enhancements
SD_Dev_CW_01 Invoice Layout Form
2.12 Annexure:-
2.12.1 Process Flow
Visio-Ext Civil Projects.pdf
2.12.2 MOM External projects BBP Workshop
MOM Civil 18th Jan to 20th jan.pdf
2.12.3 Integration Document SAP PS-MM & SAP PS-FI
FI-PS Integration for Ext Civil.pdf
MM-PS Integration for Ext Civil.pdf
SD-PS Integration for Ext Civil .pdf
2.12.4 Reporting Requirements:
Civil Reports.zip
2.12.5 GAP List Next Action Item
-
22-Jan-10 Page 25 of 26
Civil GAP List.zip