Document number: VN-RP-ENG-2004-011 Title: BSC&XCDR Preventive Maintenance Service Record Revision: Release Date: V02 07-Jan-2004 BSC_PreventiveMantenance_update_Jan2012.doc Page 1 / 17 BSC Hardware Preventive Maintenance Service Record SITE NAME REGION CABINET CONFIGURATION Motorola Engineer Motorola Signature VNP Engineer VNP Signature DATE

description

BSC PreventiveMantenance

Transcript of BSC PreventiveMantenance Update Jan2012

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 1 / 17

    BSC Hardware

    Preventive Maintenance

    Service Record

    SITE NAME

    REGION

    CABINET

    CONFIGURATION

    Motorola Engineer

    Motorola Signature

    VNP Engineer

    VNP Signature

    DATE

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 2 / 17

    A. BSS System Health Check

    1. Cabinet view

    2. General Configuration Cage Connection Type: Expansion Extension

    Clock Synchronization Status: Phase locked Free run

    GPRS Service: Available Unavailable

    External Alarm System: Available Unavailable

    Non Volatile Memory (NVM) Available Unavailable

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 3 / 17

    3. Configuration and Link Diagram i. Hardware Configuration

    Items Total Items Total

    CAB GCLK

    CAGE BSP GPROC

    MSI CSFP GPROC

    GDP OMF GPROC

    XCDR LCF GPROC

    KSW Pool GPROC

    ii. Connection Configuration Connected to MSC:

    Connected to RXCDR: The number of sites:

    MMS

    Port

    Connected To

    Network Entity

    At Port Carried

    MMS 0 0 TRAU_XXXM MMS 6 0 MTL-x, OML-x, XBL-x, OPL-x,, CIC:xxx-yyy,

    MMS 0 1 BTS_N:XXX-YYY MMS 0 0 RSL-x, RTF channel

    MMS 1 0

    MMS 1 1

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 4 / 17

    4. Event and alarm summary

    5. Comments/Remarks

    Any device with active alarms? Any device with repeated alarms? BSS software code object list in NVM and BSP are identical? Any redundancy lack: BSP, Pool GPROC?

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 5 / 17

    B. Hardware Checking

    1. BSSC CABINET CHECK

    D.C Voltage Tests D.C. Power Supply Tests for cabinets (Requirement DC input 53.65 to 55.40 Volts)

    DC input to First cabinet DC input to Second cabinet DC input to Third cabinet

    Volts

    Volts Volts

    Digital Shelf IPSM Insert dummy load card into slot 18 and test each IPSM with only one IPSM powered up at a time. Record results.

    Upper shelf in the first cabinet

    Voltage IPSM 0 IPSM 1 IPSM 2 Limits

    + 12 volts +/- 600mvdc

    - 12 volts +/- 600mvdc

    + 5 volts +/- 100mvdc

    Lower shelf in the first cabinet

    Voltage IPSM 0 IPSM 1 IPSM 2 Limits

    + 12 volts +/- 600mvdc

    - 12 volts +/- 600mvdc

    + 5 volts +/- 100mvdc

    Upper shelf in the second cabinet

    Voltage IPSM 0 IPSM 1 IPSM 2 Limits

    + 12 volts +/- 600mvdc

    - 12 volts +/- 600mvdc

    + 5 volts +/- 100mvdc

    Lower shelf in the second cabinet

    Voltage IPSM 0 IPSM 1 IPSM 2 Limits

    + 12 volts +/- 600mvdc

    - 12 volts +/- 600mvdc

    + 5 volts +/- 100mvdc

    Comment and Action Done:

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 6 / 17

    2. CIRCUIT BREAKER ALARM TEST

    Circuit breaker CB 0 CB 1 CB 2 CB 3 CB 4 CB 5 CB 6 CB 7 CB 8 CB 9

    First Cabinet

    Second Cabinet

    Third Cabinet

    Switch off each circuit breaker in turn and check alarms register on laptop indicate Pass or Fail in box.

    Comment and Action Done:

    3. EAS (FIX) ALARMS TESTS Purpose: 1. External alarm was installed and connected to this BSC? 2. Verify the functionality of all external alarms, which have been defined by Motorola on site. 3. Ensure the alarms are being reported to the OMCR 4. Motorola will only check those EAS alarms installed by Motorola.

    Alarms E.A.S.

    Optocoupler 1

    Optocoupler 2

    Optocoupler 3

    Optocoupler 4

    Optocoupler 5

    Optocoupler 6

    Optocoupler 7

    Optocoupler 8

    Comment and Action Done:

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 7 / 17

    4. SITE CHECK

    Tasks Status

    Check the distribution frame (DDF) wiring description table available and attached to DDF frame?

    Check all MMS ports at DDF frame are labeled?

    Check all BIB and power connections are securely fastened.

    Perform air filter cleaning

    Perform GCLK calibration

    SLOT SERIAL

    NUMBER OF GCLK BOARD

    DATE

    DATE OF LAST

    CALIBRATION

    FREQUENCY BEFORE

    CALIBRATION

    Comment and Action Done:

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 8 / 17

    5. CABLING/WIRING/MISC CHECK

    Tasks Status

    Having any cabling within the cabinets for loose/bad connections, signs of wear or rodent damage?

    Having any ground wire connections at rack for tightness and signs of corrosion?

    Having any check of DC power connections at rack for tightness and signs of corrosion?

    Having any missing/loose screws on equipment racks?

    Current BSC/RXCDR configuration matches with database configuration?

    Having labeling for all Cabinets, DC cables, grounding cables, BIB cables, Alarm cable and Battery cables? Labeling cables at 2 ends and clearly?

    Having label for DC circuit breaker to single cabinets?

    All labels have the rule and follow with VNP or Motorola standard?

    Comment and Action Done:

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 9 / 17

    6. EXTERIOR GROUND SYSTEM CHECK 1. If applicable, clean debris from inspection holes. Report broken or missing inspection hole covers. 2. Inspect the following grounding connections and notify customer of any action required. (Not tightness or signs of corrosion)

    Comment and Action Done:

    7. AIR CONDITIONING CHECK

    Using digital thermometer to measure equipment room temperature, it should be not excessive 26 degree Celsius.

    Comment and Action Done:

    8. BATTERY SYSTEM CHECK Using Battery tester makes sure all cells of battery system having good inter-cell resistance and cell impedance as well. Note down any issue with battery system?

    Comment and Action Done:

    9. PICTURES

    1. Equipment Room 2. BSSC cabinets and cages 3. Any installation abnormal

    For the purpose of recording and filling, these pictures are printed and attached to section D

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 10 / 17

    10. UPDATE INVENTORY OF BSC/RXCDR CABINET CAGE 0

    CARDS BOARD POSITION PART NUMBER SERIAL NUMBER

    CAGE

    BTC SLOT 0

    KSW SLOT 1

    GCLK SLOT 2

    GCLK SLOT 4

    MSI/GDP SLOT 6

    MSI/GDP SLOT 7

    MSI/GDP SLOT 8

    MSI/GDP SLOT 9

    MSI/GDP SLOT 10

    MSI/GDP SLOT 11

    MSI/GDP SLOT 12

    MSI/GDP SLOT 13

    MSI/GDP SLOT 14

    MSI/GDP SLOT 15

    MSI/GDP SLOT 16

    MSI/GDP SLOT 17

    GPROC-2/GDP SLOT 18

    GPROC-2/GDP SLOT 19

    GPROC-2/GDP SLOT 20

    GPROC-2/GDP SLOT 21

    GPROC-2/GDP SLOT 22

    GPROC-2/GDP SLOT 23

    GPROC-2 SLOT 24

    GPROC-2 SLOT 25

    GPROC-2/NVRAM SLOT 26

    KSW SLOT 27

    BTC SLOT 28

    IPSM SLOT 0

    IPSM SLOT 1

    IPSM SLOT 2

    CAGE 1

    CARDS BOARD POSITION PART NUMBER SERIAL NUMBER

    CAGE

    BTC SLOT 0

    KSW SLOT 1

    GCLK SLOT 2

    GCLK SLOT 4

    MSI/GDP SLOT 6

    MSI/GDP SLOT 7

    MSI/GDP SLOT 8

    MSI/GDP SLOT 9

    MSI/GDP SLOT 10

    MSI/GDP SLOT 11

    MSI/GDP SLOT 12

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 11 / 17

    MSI/GDP SLOT 13

    MSI/GDP SLOT 14

    MSI/GDP SLOT 15

    MSI/GDP SLOT 16

    MSI/GDP SLOT 17

    GPROC-2/GDP SLOT 18

    GPROC-2/GDP SLOT 19

    GPROC-2/GDP SLOT 20

    GPROC-2/GDP SLOT 21

    GPROC-2/GDP SLOT 22

    GPROC-2/GDP SLOT 23

    GPROC-2 SLOT 24

    GPROC-2 SLOT 25

    GPROC-2/NVRAM SLOT 26

    KSW SLOT 27

    BTC SLOT 28

    IPSM SLOT 0

    IPSM SLOT 1

    IPSM SLOT 2

    CAGE 2

    CARDS BOARD POSITION PART NUMBER SERIAL NUMBER

    CAGE

    BTC SLOT 0

    KSW SLOT 1

    GCLK SLOT 2

    GCLK SLOT 4

    MSI/GDP SLOT 6

    MSI/GDP SLOT 7

    MSI/GDP SLOT 8

    MSI/GDP SLOT 9

    MSI/GDP SLOT 10

    MSI/GDP SLOT 11

    MSI/GDP SLOT 12

    MSI/GDP SLOT 13

    MSI/GDP SLOT 14

    MSI/GDP SLOT 15

    MSI/GDP SLOT 16

    MSI/GDP SLOT 17

    GPROC-2/GDP SLOT 18

    GPROC-2/GDP SLOT 19

    GPROC-2/GDP SLOT 20

    GPROC-2/GDP SLOT 21

    GPROC-2/GDP SLOT 22

    GPROC-2/GDP SLOT 23

    GPROC-2 SLOT 24

    GPROC-2 SLOT 25

    GPROC-2/NVRAM SLOT 26

    KSW SLOT 27

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 12 / 17

    BTC SLOT 28

    IPSM SLOT 0

    IPSM SLOT 1

    IPSM SLOT 2

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 13 / 17

    11. RECTIFIER MODULE TEST AND COMMISSIONING RESULTS

    The first module

    Date

    Module Type

    S/N

    No. Item Verified Values Specification Pass Fail Remarks

    1 AC Input 198 to 242V

    2 Grounding

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 14 / 17

    The fourth module

    Date

    Module Type

    S/N

    No. Item Verified Values Specification Pass Fail Remarks

    1 AC Input 198 to 242V

    2 Grounding

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 15 / 17

    12. POWER BOARD TEST AND COMMISSIONING RESULTS.

    Power Type

    S/N

    No. Item Verified Values Specification Pass Fail Remarks

    1 LED Display Checking the

    operation of LED

    2 Major Alarm

    (Mains Fails)

    LED Indicated

    Alarm activated

    3 Minor Alarm

    (Rec Fails)

    LED Indicated

    Alarm activated

    4 HV Alarm 58.40 V

    5 LV Alarm 48.25 V

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 16 / 17

    C. Findings/Outstanding Issues

  • Document number:

    VN-RP-ENG-2004-011

    Title: BSC&XCDR Preventive Maintenance Service Record Revision:

    Release Date:

    V02

    07-Jan-2004

    BSC_PreventiveMantenance_update_Jan2012.doc Page 17 / 17

    D. Equipment and Installation Pictures