BRM Aug 2013 Section A - Compulsory Question
1
Date
From :
JL Building Consultancy Ltd
8, Marina Square
#08-08
Singapore
To:
Esq Client
Ace Property Development Inc
Suggested Solutions
2
Ace Property Development Inc
88 Central Lowlands
NN 32 RZ, Edinburgh
Scotland
Attn: Mr Walter Scott
Managing Director
RE: ADVISORY ON THE REFURBISHMENT TO TOWER CITY CENTRE
We thank you for the opportunity to provide advisory service to your company on
the recommendations and challenges in the refurbishment to Tower City Centre.
Part a)
Client’s brief / objective
The client’s objective is to update an existing old office
building built in the 50’s such that its building performance
is acceptable by modern standard and its functional use is
improved.
Background & Implications
3
Currently the office building is well maintained and serviced
but experienced major vacancy at the upper floors where the
office use is. Such situation suggests that the building is
facing redundancy and possibly obsolescence. In another
words the building especially is no longer fetching market
rental value. Another hint that points towards building
obsolescence is that the building is located at city centre
and yet there seems to be less demand for the building. It is
probably also not competitive as compared to its
neighboring building.
Problem / Current Situation
The building is made of structural steel frame and its façade
is constructed using masonry panels and steel frame single
glazing.
Given that the building is now more than 60 years old we
expect the fire protection coating if there is any at all for the
4
expect the fire protection coating if there is any at all for the
structural steel frame to be worn out. Its façade performance
against weather protection, water penetration should have
failed after 30 years. In another words the energy
consumption of the building in terms of heating and cooling
is likely to be very high. Its internal thermal comfort level is
likely to be unacceptable.
The building has flat roof and mastic asphalt
waterproofing. After 60 years such design would have
faced ponding issue at the roof and the warranty of
the waterproofing which usually only last for 20 years
at most has expired.
5
Assuming that the owner has not replaced the roof
waterproofing, the building faces major waterproofing
issue and also water penetration at the upper most
floors. This likely impact the structural steel frame
material and causes oxidization and deterioration.
The building has a large internal floor plate. Its floor
design is open concept. In another words the building
columns are concentrated mostly at the building
perimeter and has large span beams and floor. Such
floor construction could either be metal deck flooring or
post tensioned concrete or one way reinforced concrete
slab or long span precast beam slab.
Given that the building is built more than 50 years,
6
Given that the building is built more than 50 years,
modern construction technology is not available at that
time. Hence it is likely constructed using one way
reinforced concrete. Most probably there could be
spalling concrete on the ceiling arising from water
penetration from the façade or roof.
Lastly only three retail shops at operating at the building
and there is a large reception. All of these are that the
ground floor.
Options / Evaluation / Recommendation / Change of Use
I would propose the following modernization options:-
Structural steel frame – carry out repair and ensure that
new intumescent paint coat covers the structural steel
7
new intumescent paint coat covers the structural steel
beam.
I recommend encasing the structural steel column with
concrete to strengthen the loading capacity of the
building and also to provide a more durable fire proofing
solution.
Façade – I recommend carrying out a re-cladding rather than
over-cladding. As the building is currently vacant at its upper
floors and only a few retail outlet at the ground floor it makes
practical sense to either terminate the retail lease or
temporarily relocate to another building if the owner has
some other building. With the relocation of the retail shops,
the building could be shut down to facilitate a faster and less
disruptive refurbishment. Given this context it is more
appropriate to carry out re-cladding rather than over-
8
appropriate to carry out re-cladding rather than over-
cladding. It provides a more permanent solution in view that
the existing cladding is 60 years old already. Given that the
existing façade is masonry panel it is also not difficult to
dismantle. The new façade recommended is curtain wall with
full length double glazing that would meet the current modern
code for EETV thermal transmission. Full length glazing also
provides natural lighting which is more appealing and saves
on energy used for artificial lighting. Please see below a
sketch of re-cladding. (sketch and annotate)
Flat roof – As the building is recommended to be shut
down as justified above, we could consider re-roofing or
over-roofing of the building to provide a permanent
solution to expired waterproofing at the existing flat
rooftop and also possible water penetration issue. Re-
roofing is not recommended as the existing roof deck is
likely to have deteriorated after 60 years and may not
provide suitable gradient and water discharge. Over-
9
provide suitable gradient and water discharge. Over-
roofing is more cost effective. Please see below a sketch
of over-roofing. (sketch a 3D view of over-roofing and
annotate. Indicate also the possible issues – loading on
existing column, aesthetic of roof design,
accommodating building services etc)
(You could recommend other solution eg skylight, green
roof if you have the technical knowledge)
Existing floor – The existing floor should be repaired if
there are any spalling concrete. It is also a good
opportunity to re-level the floor level if there is any
unevenness of the floor especially the circulation area or
connection area. Depending on the new use of the
building, floor penetration ie partial demolition of the floor
could be considered. This is to create a air well or atrium
10
could be considered. This is to create a air well or atrium
for activity generating purpose. If an atrium is created
then skylight may need to be installed at the roof. It is an
excellent time to consider re-configuration of the internal
floor and also fit out with new wall , floor and ceiling
finishes. Internal retrofit of the building services to
upgrade the electrical capacity or air conditioning chiller
to a more energy efficient type would saves utilities cost
in future.
Change of use – As the building is a very old building,
its technical performance is unlikely to meet modern
office standards in terms of generous ceiling height,
floor loading capacity, provision for raised floor, high
electrical capacity etc.
In addition as the building is situated at city centre it
would be more viable to convert the building to a
11
would be more viable to convert the building to a
hotel. More retail outlets could be considered at Level
2 as well to increase the commercial viability of the
building. With the building’s large floor plate, internal
dry partitioning could be used to create the hotel
rooms. However sanitary provisions and design
would have to be re-considered.
Construction and Access Challenges
Access – there is possible access issue as the building
is situated at city centre it is likely to be congested with
very tight site constraint with main or secondary roads
at the front and rear of the building. It is also likely that
the building is side by side with adjacent building on its
12
left and right. In addition the building could be either
mid-rise or high-rise, access to the roof top to carry out
over-roofing is also another challenge.
Construction challenges – Besides access issue, as the
building is very old there are several technical risk in
carrying out work on old buildings :-
a) It is likely that there is insufficient information on the
existing building as such records could have been lost
or removed over time. Critical information are – existing
floor loading, foundation design , dimensioning of
existing structural members, presence of asbestos ,
building services performance etc.
b)The structural integrity of the building must be
maintained at all times. Hence extra temporary support
13
maintained at all times. Hence extra temporary support
is required to hold the building while it undergoes
refurbishment.
c)The existing structure and design may not be able to
cater to current code compliance eg fire code,
accessibility code, energy efficiency which would
require a large plant room, carpark requirements, fire
engine access etc.
Other challenges include some issues mentioned
earlier:-
a) Strengthening of existing building loading capacity
which may require underpinning of building.
b) Relocation of existing retail tenants and
compensation if any
14
compensation if any
c) Demolition and removal of debris. Storage issue
for material and equipment
d) Installation of numerous sanitary provision for
hotel guestrooms arising from the proposed change
of use from office use to hotel and retail.
e) Noise , dust and disturbance to neighbouring
buildings.