Bridgewater State College Energy and Water Conservation ...
Transcript of Bridgewater State College Energy and Water Conservation ...
Bridgewater State CollegeBridgewater State College
Energy and WaterEnergy and Water
Conservation ProjectConservation Project
EXECUTIVE SUMMARYThe Massachusetts Division of Capital Asset Management (DCAM) and
Bridgewater StateCollege (BSC) selected Ameresco Select Inc. (ASI) to provide comprehensive
energy and waterconservation upgrades at Bridgewater State College, a state institution of higher
Educationlocated in Bridgewater, Massachusetts. The goal of this project is to reduce
energy and watercosts and provide capital improvements to the campus infrastructure.
Following is a timeline of milestones achieved:
RFP Issued April 2004 Contractor Selection March 2005 DEA Start March 2005 DEA Submittal January 2006 ESA Execution March 31, 2006 Contract Completion Date June 30, 2007 Actual Completion Date June 15, 2007 Final Project Notification August 28, 2007
EXECUTIVE SUMMARY (cont’d)Of the five options presented, DCAM and BSC selected ASI based on Option 2A:
20‑YearCentral Utilities. This option includes a comprehensive package of measures that
woulddeliver significant energy and water cost savings; provide valuable infrastructureimprovements; improve reliability and occupant comfort; provide electric
generation; andreduce the maintenance burden.
The scope of work completed, comprises a project of $10.7 million to implementthe
24 measures which deliver energy and water cost savings of $956,249. After debtservice,
the net annual savings to the College is $ 33,249. Table ES-1 summarizes theeconomics of
the program recommended by ASI.Table ES-1:Table ES-1:
Project Economic SummaryProject Economic Summary
Total Project Cost $ 10,442,355
Total Annual Savings $ 956,249
Annual Lease Payments $ 923,000
Net Annual Savings to theCommonwealth $ 33,249
SAVINGS
Baseline Consumption and SavingsBaseline Consumption and Savings
Baseline GuaranteedSavings
#6 Oil (gals) 1,064,595 344,294
Natural Gas (ccf) 422,216 33,253
Electricity (kWh) 15,965,432 4,769,995
Water/Sewer (cf) 5,096,554 1,244,874
SAVINGS (cont’d)
ECM DescriptionContract
GuaranteedSavings
ECM-1 High-Efficiency Lighting $ 144,122ECM-2 Lighting Controls $ 13,565ECM-2A New Lighting Control Panels in Maxwell $ 2,053ECM-3 High Efficiency Motors $ 2,227ECM-4A Energy Management System Platinum
Option: Full DDC Control, EliminatePneumatics
$ 156,801
ECM-4D Campus Wide Electric and SteamMetering
-ECM-5 Domestic Water Conservation $ 102,623ECM-6B Replace All Steam Traps $ 167,545ECM-7A Variable Frequency Drives on AHU’s $ 124,121ECM-7B Variable Frequency Drives on Pumps $ 8,025ECM-9 Vending Machine Controllers $ 5,608ECM-10C
Hunt Hall Window Replacement $ 2,090ECM-11B
Distributed Cogeneration $ 7,875ECM-12 New Boiler Controls at Central Plant $ 83,020
Summary of Guaranteed Savings by ECMSummary of Guaranteed Savings by ECM
SAVINGS (cont’d)
ECM DescriptionContract
GuaranteedSavings
ECM-14 Underground Steam & Condensate PipingReplacements
$ 14,404
ECM-15B
Replace Kelly Gym Locker Room H&V Unit $ 18,171ECM-15C
Replace Kelly Gym Unit Ventilators -ECM-15D
Miscellaneous Work -ECM-16 Repair Radiator Controls in Dormitories $ 38,360ECM-17A
Piping Insulation $ 25,727ECM-19 Kitchen Hood Controls $ 42,690ECM-21 Field House Laundering Improvements $ 718ECM-23A
New Air Conditioning Systems inRondileau
$ (3,745)ECM-25 Steam Operated Condensate Pumps $ (1,565)ECM-28A
New Boiler in Hunt Hall $ 1,816
TOTAL CONTRACT GUARANTEED SAVINGS $ 956,249
Summary of Guaranteed Savings by ECMSummary of Guaranteed Savings by ECM
ECM-7AVariable Frequency Drives on AHU’s
Old Motor StartersOld Motor Starters New Variable Frequency DrivesNew Variable Frequency Drives
ECM-12New Boiler Controls at Central Plant
Old Bailey PanelOld Bailey Panel
New Control PanelNew Control Panel
ECM-28ANew Boiler in Hunt Hall
Old BoilerOld Boiler New BoilerNew Boiler
ECM-11B75 KW Cogen at Tinsley
ECM-4AEnergy Management System Platinum Option: Full
DDC Control, Eliminate Pneumatics
HVAC Control Room, Operations CenterHVAC Control Room, Operations Center
Bridgewater State CollegeBridgewater State College
Marshall Conant MathMarshall Conant Mathand Science Projectand Science Project
INTEGRATED PROJECT DESIGN
TEAM
Division of Capital Asset Management, Owner
Payette & Associate, Designer
Barr & Barr, Construction Manager (CM)
Bridgewater State College, Agency
COMMITTEE STRUCTURE: USER GROUP
MIKEGOMES
PAIDCAM
USER GROUP
HOWARDLONDON
BARR & BARR
MATH
EARTHSCIENCE
PHYSICS
CHEMISTRY
BIOLOGY
GEOGRAPHY
COMP
SCI
TECHNOLOGY.
PAT CRONIN
COMMITTEE STRUCTURE: BUILDING COMMITTEE
MIKEGOMES
KARENJASON
PAI
DCAM
BUILDING COMMITTEEBARR &
BARR
COMMITTEE STRUCTURE: EXECUTIVE
PAI BARR & BARR
HOWARDLONDON
MIKEGOMES
EXECUTIVE COMMITEE
DANAMOHLER-FARIA
DCAM
DESIGN SCHEDULE:
3 mo SCHEMATIC DESIGN
1 mo Estimate/Reconciliation/Approval to Proceed
3 mo DESIGN DEVELOPMENT PHASE
1 mo Estimate/Reconciliation/Approval to Proceed
4 mo CONTRACT DOCUMENT PHASE_____________________________________________________________
1 YEAR DESIGN PHASE DURATION
PHASING STRATEGY: PLANNING / PHASING &SECTIONAL SOLUTION
PHASE 1PHASE 2
DEMO 1
DEMO 2
PHASE 1
PHASE 1
BUILDING DESIGN:
- High-Efficiency Lighting & Lighting Control
- Reducing # Fume Hoods (Green Chemistry/ Green Science)
- Use Atrium for Daylighting and Solar Chimney
- Rain Garden
- Green Roof + Greenhouse
- Low-flow Fume Hoods, Enthalpy Wheels, Chilled Beams
- Mechanical Zoning / Lower, appropriate levels of ventilation
- Geothermal / Groundwater, Rainwater, AHU Condensate, RODIReject water to be used for cooling tower make up
- Photovoltaics
GREEN STRATEGIES: MCSB – LEED SILVER (min.)