Bridgewater State College Energy and Water Conservation ...

20
Bridgewater State College Bridgewater State College Energy and Water Energy and Water Conservation Project Conservation Project

Transcript of Bridgewater State College Energy and Water Conservation ...

Page 1: Bridgewater State College Energy and Water Conservation ...

Bridgewater State CollegeBridgewater State College

Energy and WaterEnergy and Water

Conservation ProjectConservation Project

Page 2: Bridgewater State College Energy and Water Conservation ...

EXECUTIVE SUMMARYThe Massachusetts Division of Capital Asset Management (DCAM) and

Bridgewater StateCollege (BSC) selected Ameresco Select Inc. (ASI) to provide comprehensive

energy and waterconservation upgrades at Bridgewater State College, a state institution of higher

Educationlocated in Bridgewater, Massachusetts. The goal of this project is to reduce

energy and watercosts and provide capital improvements to the campus infrastructure.

Following is a timeline of milestones achieved:

RFP Issued April 2004 Contractor Selection March 2005 DEA Start March 2005 DEA Submittal January 2006 ESA Execution March 31, 2006 Contract Completion Date June 30, 2007 Actual Completion Date June 15, 2007 Final Project Notification August 28, 2007

Page 3: Bridgewater State College Energy and Water Conservation ...

EXECUTIVE SUMMARY (cont’d)Of the five options presented, DCAM and BSC selected ASI based on Option 2A:

20‑YearCentral Utilities. This option includes a comprehensive package of measures that

woulddeliver significant energy and water cost savings; provide valuable infrastructureimprovements; improve reliability and occupant comfort; provide electric

generation; andreduce the maintenance burden.

The scope of work completed, comprises a project of $10.7 million to implementthe

24 measures which deliver energy and water cost savings of $956,249. After debtservice,

the net annual savings to the College is $ 33,249. Table ES-1 summarizes theeconomics of

the program recommended by ASI.Table ES-1:Table ES-1:

Project Economic SummaryProject Economic Summary

Total Project Cost $ 10,442,355

Total Annual Savings $ 956,249

Annual Lease Payments $ 923,000

Net Annual Savings to theCommonwealth $ 33,249

Page 4: Bridgewater State College Energy and Water Conservation ...

SAVINGS

Baseline Consumption and SavingsBaseline Consumption and Savings

Baseline GuaranteedSavings

#6 Oil (gals) 1,064,595 344,294

Natural Gas (ccf) 422,216 33,253

Electricity (kWh) 15,965,432 4,769,995

Water/Sewer (cf) 5,096,554 1,244,874

Page 5: Bridgewater State College Energy and Water Conservation ...

SAVINGS (cont’d)

ECM DescriptionContract

GuaranteedSavings

ECM-1 High-Efficiency Lighting $ 144,122ECM-2 Lighting Controls $ 13,565ECM-2A New Lighting Control Panels in Maxwell $ 2,053ECM-3 High Efficiency Motors $ 2,227ECM-4A Energy Management System Platinum

Option: Full DDC Control, EliminatePneumatics

$ 156,801

ECM-4D Campus Wide Electric and SteamMetering

-ECM-5 Domestic Water Conservation $ 102,623ECM-6B Replace All Steam Traps $ 167,545ECM-7A Variable Frequency Drives on AHU’s $ 124,121ECM-7B Variable Frequency Drives on Pumps $ 8,025ECM-9 Vending Machine Controllers $ 5,608ECM-10C

Hunt Hall Window Replacement $ 2,090ECM-11B

Distributed Cogeneration $ 7,875ECM-12 New Boiler Controls at Central Plant $ 83,020

Summary of Guaranteed Savings by ECMSummary of Guaranteed Savings by ECM

Page 6: Bridgewater State College Energy and Water Conservation ...

SAVINGS (cont’d)

ECM DescriptionContract

GuaranteedSavings

ECM-14 Underground Steam & Condensate PipingReplacements

$ 14,404

ECM-15B

Replace Kelly Gym Locker Room H&V Unit $ 18,171ECM-15C

Replace Kelly Gym Unit Ventilators -ECM-15D

Miscellaneous Work -ECM-16 Repair Radiator Controls in Dormitories $ 38,360ECM-17A

Piping Insulation $ 25,727ECM-19 Kitchen Hood Controls $ 42,690ECM-21 Field House Laundering Improvements $ 718ECM-23A

New Air Conditioning Systems inRondileau

$ (3,745)ECM-25 Steam Operated Condensate Pumps $ (1,565)ECM-28A

New Boiler in Hunt Hall $ 1,816

TOTAL CONTRACT GUARANTEED SAVINGS $ 956,249

Summary of Guaranteed Savings by ECMSummary of Guaranteed Savings by ECM

Page 7: Bridgewater State College Energy and Water Conservation ...

ECM-7AVariable Frequency Drives on AHU’s

Old Motor StartersOld Motor Starters New Variable Frequency DrivesNew Variable Frequency Drives

Page 8: Bridgewater State College Energy and Water Conservation ...

ECM-12New Boiler Controls at Central Plant

Old Bailey PanelOld Bailey Panel

New Control PanelNew Control Panel

Page 9: Bridgewater State College Energy and Water Conservation ...

ECM-28ANew Boiler in Hunt Hall

Old BoilerOld Boiler New BoilerNew Boiler

Page 10: Bridgewater State College Energy and Water Conservation ...

ECM-11B75 KW Cogen at Tinsley

Page 11: Bridgewater State College Energy and Water Conservation ...

ECM-4AEnergy Management System Platinum Option: Full

DDC Control, Eliminate Pneumatics

HVAC Control Room, Operations CenterHVAC Control Room, Operations Center

Page 12: Bridgewater State College Energy and Water Conservation ...

Bridgewater State CollegeBridgewater State College

Marshall Conant MathMarshall Conant Mathand Science Projectand Science Project

Page 13: Bridgewater State College Energy and Water Conservation ...

INTEGRATED PROJECT DESIGN

TEAM

Division of Capital Asset Management, Owner

Payette & Associate, Designer

Barr & Barr, Construction Manager (CM)

Bridgewater State College, Agency

Page 14: Bridgewater State College Energy and Water Conservation ...

COMMITTEE STRUCTURE: USER GROUP

MIKEGOMES

PAIDCAM

USER GROUP

HOWARDLONDON

BARR & BARR

MATH

EARTHSCIENCE

PHYSICS

CHEMISTRY

BIOLOGY

GEOGRAPHY

COMP

SCI

TECHNOLOGY.

PAT CRONIN

Page 15: Bridgewater State College Energy and Water Conservation ...

COMMITTEE STRUCTURE: BUILDING COMMITTEE

MIKEGOMES

KARENJASON

PAI

DCAM

BUILDING COMMITTEEBARR &

BARR

Page 16: Bridgewater State College Energy and Water Conservation ...

COMMITTEE STRUCTURE: EXECUTIVE

PAI BARR & BARR

HOWARDLONDON

MIKEGOMES

EXECUTIVE COMMITEE

DANAMOHLER-FARIA

DCAM

Page 17: Bridgewater State College Energy and Water Conservation ...

DESIGN SCHEDULE:

3 mo SCHEMATIC DESIGN

1 mo Estimate/Reconciliation/Approval to Proceed

3 mo DESIGN DEVELOPMENT PHASE

1 mo Estimate/Reconciliation/Approval to Proceed

4 mo CONTRACT DOCUMENT PHASE_____________________________________________________________

1 YEAR DESIGN PHASE DURATION

Page 18: Bridgewater State College Energy and Water Conservation ...

PHASING STRATEGY: PLANNING / PHASING &SECTIONAL SOLUTION

PHASE 1PHASE 2

DEMO 1

DEMO 2

PHASE 1

PHASE 1

Page 19: Bridgewater State College Energy and Water Conservation ...

BUILDING DESIGN:

Page 20: Bridgewater State College Energy and Water Conservation ...

- High-Efficiency Lighting & Lighting Control

- Reducing # Fume Hoods (Green Chemistry/ Green Science)

- Use Atrium for Daylighting and Solar Chimney

- Rain Garden

- Green Roof + Greenhouse

- Low-flow Fume Hoods, Enthalpy Wheels, Chilled Beams

- Mechanical Zoning / Lower, appropriate levels of ventilation

- Geothermal / Groundwater, Rainwater, AHU Condensate, RODIReject water to be used for cooling tower make up

- Photovoltaics

GREEN STRATEGIES: MCSB – LEED SILVER (min.)