BRICS FOUNDRY FORUM 2012 HOSTED BY CHINA FOUNDRY ASSOCIATION PRACTICAL APPLICATION OF IMPROVING ENERGY EFFICIENCY IN FOUNDRIES PRESENTED BY: John T Davies CEO – South African Institute of Foundrymen

description

Brics presentation by saif

Transcript of Brics presentation by saif

Page 1: Brics presentation by saif

BRICS FOUNDRY FORUM 2012 HOSTED BY

CHINA FOUNDRY ASSOCIATION PRACTICAL APPLICATION OF IMPROVING

ENERGY EFFICIENCY IN FOUNDRIES PRESENTED BY: John T Davies

CEO – South African Institute of Foundrymen

Page 2: Brics presentation by saif

THE SOUTH AFRICAN FOUNDRY INDUSTRY

1. NUMBER OF FOUNDRIES

* Includes 4 Investment Casting Foundries

In addition there are 13 Art Foundries and 9 Spin Casters

cf Germany = 900

USA = 2000

China = 2600

METAL TYPE 2003 2007 2011 %Change 2011/2007

Ferrous 110 110 101* 8

Non Ferrous 103 101 80 21

TOTAL 213 211 181 14

Page 3: Brics presentation by saif

DEFINITION

• “Demand Side” refers to the demand for, or consumption of, electricity.

• “Demand Side Management” refers to interventions to reduce energy consumption

• “Energy Efficiency” refers to the effective use of energy to produce a given output (in a production environment)

• technology is one that which produces the same service or output with less energy input.

• “Green Technology” means

• Technology that when properly implemented allows an organisation to meet its present needs without compromising its future needs.

Page 4: Brics presentation by saif

4 4

Per Capita Electricity Consumption for Countries with similar GDP per capita (± 20%) relative to South Africa*

The Case for Energy Efficiency South Africa vs. the Rest of the World

Gabon(1,128 kWh pa)

Russian Federation(6,425 kWh pa)

Venezuela (Bolivarian Republic of)(3,770 kWh pa)

Malaysia(3,196 kWh pa)

South Africa

(4,818 kWh pa)Mauritius

(1,775 kWh pa)

Turkey(2,122 kWh pa)

Saint Lucia(1,879 kWh pa)

Uruguay(2,408 kWh pa)

Panama(1,807 kWh pa)

Argentina(2,714 kWh pa)

Costa Rica(1,876 kWh pa) Romania

(2,548 kWh pa)Grenada

(1,963 kWh pa)

Brazil(2,340 kWh pa)

0.80

0.85

0.90

0.95

1.00

1.05

1.10

1.15

1.20

- 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60

Electricity consumption per capita x South Africa Electricity consumption per capita

GD

P p

er

cap

ita x

So

uth

Afr

ica G

DP

per

cap

ita

Source: UN (United Nations). 2007d. The 2004 Energy Statistics Yearbook. Department of Economic and Social Affairs, Statistics Division. New York.

Compared to other countries with a similar per capita GDP (15% variance),

SA is more electricity intensive by factor of 35-

65%

*Situation as in 2004, beneficiation policy and co-generation will alter the above picture

Page 5: Brics presentation by saif

Together we have the power to save 5

Page 6: Brics presentation by saif

Together we have the power to save 6

Benchmarks Programmes Offer

Lighting & HVAC Up to 5.2m/MW

Solar water heating (SWH) Up to 6.3m/MW

Heat pumps Up to 5.2m/MW

Demand Response Up to 3.5m/MW

Compressed Air Up to 4.4m/MW

Process Optimisation Up to 5.2m/MW

Shower Heads Up to 2.8m/MW

Page 7: Brics presentation by saif

Together we have the power to save 7

ESCO Implementation Model

DSM Agreement

Maintenance or Performance agreement

New Engineering Contract

ESCo • Audit

• Proposal • Installation

Eskom DSM • Evaluation • Financier

Customer • Sustainability

ESCo

Page 8: Brics presentation by saif

Heat Treatment 6%

Melting 55%

Post Casting 7%

Core Making 8%

Other 12%

Mold Making 12%

Page 9: Brics presentation by saif

ENERGY SAVING OPPORTUNITIES

1. SCRAP SELECTION AND PREPARATION

2. CHARGING

3. MELTING

4. ALLOYING / REFINING / TREATMENT / SAMPLING

5. HOLDING

6. TAPPING / LADLES

7. TRANSPORTING METAL

8. POURING

9. MAINTENANCE OF PLANT AND EQUIPMENT

Page 10: Brics presentation by saif

1. SCRAP SELECTION AND PREPARATION

• Safety

• Correct Size

• Density

• Cleanliness:

Sheared versus shredded scrap

Rusted scrap

Briquetted swarf

• Preheating of scrap?

• Induction melting Limits the range of scrap used

Page 11: Brics presentation by saif
Page 12: Brics presentation by saif
Page 13: Brics presentation by saif
Page 14: Brics presentation by saif

2. CHARGING OF SCRAP

• Prepare the Charge Sequence

• Vibrating Systems

• Continuous Charging During the Melt

• Pre Heat the Charge in the Furnace

• Focus on Reducing the Duration of Charging to Maximise the Melting Process

Page 15: Brics presentation by saif

3. MELTING THE CHARGE

• Mains versus medium Frequency / cupola

• Theoretical Power Versus “Best Practice”

• Benefits of Batch Melting

• Efficiency (No Holding) 97 Percent

• Max Power

• Power Density

• Melting Rate

• Furnace Size

• Production Planning

• Less Emmision

• Improved Control

• Improved Homogeneity

• Furnace Lids / Covers

• Slag and Dross

Page 16: Brics presentation by saif

Best Tactic Best

Theoretical Industry % Practice % Practice

Selected Processes Minimum Average Difference Minimum Difference Minimum

Iron Induction Melting 351.5 796.3 56% 538.1 35% 1,689.50

Iron Cupola Melting 351.5 1,413.60 75% 1,002.50 65% 1,124.50

Aluminum Reverberatory 288.7 1,399.80 79% 510.5 43% 523.2

Melt Furnaces

Comparison of Practical Minimum, Theoretical Minimum and Best Practice Minimums for

Selected Processes

Estimated Iron Induction Melting Energy Usage

Per Ton Melt

Gross Melt Tacit Tacit Tacit

Item KWh/Ton Loss KWh/Ton KWh/Ton 10 Btu / Ton 10 Btu / Ton 10 Btu / Ton**

Heel Melting Calculated 800 1.5% 812 2550 2.77 8.71 14.52

Heel Melting and Holding Estimated 954 1.5% 969 3041 3.31 10.39 17.31

Modern Batch Melter Caclulated 500 1.5% 508 1594 1.73 5.44 9.07

Batch Melter and Holding Estimated 530 1.5% 538% 1690 1.84 5.77 9.62

Includes Hold Power for 8 Hours per day and preheat gas at 74 kWh/ton melt for heel melter

Ship tons consider 60% yuekd

Page 17: Brics presentation by saif

Induction and Cupola Melting Energy Comparison 10' Btu / Ton

Melt Tacit Melt Tacit Ship

Item Energy Energy Energy

Induction Heel Melting 3.31 10.39 17.31

Modern Induction Batch Melting 1.84 5.77 9.62

Low Efficiency Cupola 4.92 5.76 9.6

High Efficiency Cupola 3.25 3.84 6%

Page 18: Brics presentation by saif

0%

10%

20%

30%

40%

50%

60%

70%

80%

1950 - 1960's 1960 - 1970's 1970 - 1980's 1990's

Energy Efficiency

Tacit Energy Efficiency

Iron Induction Melting Energy Efficiency

Page 19: Brics presentation by saif

0

100

200

300

400

500

600

700

800

900

1950 - 1960's 1960 - 1970's 1970 - 1980's 1990's

kWh/ton

Historical Induction Melting Furnace Energy* (Delivered)

Page 20: Brics presentation by saif

4. ALLOYING / REFINING / DE - SLAGGING / SAMPLING

• Ferro – Alloy Additions

• Sampling – Floor Controls

• Sampling – Spectrometer Analysis

• Slag Removal – Tools, Efficiency

• Slag Wall, Slag Build – Up – Use of Fluxes

• Treatment of Metal

Page 21: Brics presentation by saif

5. HOLDING

• Avoid Holding Metal in Batch Furnaces

• Melt Cold – Pour Hot

Page 22: Brics presentation by saif

6. TAPPING / LADLES

• Refractories

• Pre Heating Using Oxy – Fuel to Improve Efficiency

• Management

Page 23: Brics presentation by saif

7. TRANSFER OF MOLTEN IRON

• Preparation

• Speed and Accuracy of the Operation

• Temperature Control

• Skimming

Page 24: Brics presentation by saif

8. POURING

• High Power Thermal Plasma Heating

Efficient Heating

Fast

Offers Metallurgical Benefits

• Existing Systems = Ladles & Auto Pouring Units

Both have Disadvantages

• HPTP Offers a Cost Effective Solution

• Improved Temperature Control to +- 5 C

• Energy Efficiency Improvement of 20%

Page 25: Brics presentation by saif

9. MAINTENANCE

• Refractories:

Replacement Schedule – Push Out

Type of Refractory

Campaign Life

On Going Repairs – Chemical Erosion Leading to Failure

Measurement

• Furnace:

Regular Coil Inspection

Water System Quality

Control of Harmonics

Short Main Power Cable Supply

Page 26: Brics presentation by saif

CONCLUSION

• There is no “One Size Fits All” Solution

• There are no immediate technological innovation in the melting of Iron

(No Magic Wand)

• Retrofitting Technology is Available for many frequency Furnaces

• The Approach Recommended is Continuous Improvement in Small Increments

• Opportunities for Energy Savings EXIST

Page 27: Brics presentation by saif

ACKNOWLEDGEMENTS

• Advanced Melting Technologies “BCS Inc Nov 2005”

• Theoretical / Best Practice Energy Use in Metal Casting Operations “JF Suhfo, JT Radia – May 2004”

• Improvement in Energy Efficiency of a Melting furnace “Dr DS Padan, Tata Motors Limited”

• High Power thermal Plasma Heating in Automotive Casting Units: Tomorrow’s Technology Applied to

Today’s Casting “Luis Cobos Enal 2010”

• Casting Directory 2011 “Crawford Publications”

• How to become a practical Green Foundry Indsustry?

“G Gigante, Thyssen Krupp – Wupaca, WI USA 2010

• ESKOM – Discussion with the Foundry Industry – Stephen Koopman, Energy Manager RSA 2010