Transcript of Bricks lecutre
10/29/2015 1:51 PM 1
BRICKS
Civil Engineering Materials
Fall Semester 2014
Department of Civil Engineering
Iqra National University Peshawar
Civil Engineering Materials
10/29/2015 1:51 PM 2 Civil Engineering Materials 2
Building Materials
• Building stones
• Bricks and clay products
• Cement concrete
• Timber and wood products
• Metals and alloys
• Paints, varnishes, distempers
• Asphalt, bitumen and tar
• Plastics and fibers
• Glass
• Asbestos, adhesives and abrasives
10/29/2015 1:51 PM 4 Civil Engineering Materials 4
Clay Products
• Clay Products
– Bricks
– Tiles
– Fire clays and fire bricks
– Terracotta
– Earthenware
– Clay pipes
• Bricks
– Block of tampered clay or ceramic material molded to desired shape and size, sun dried and if required burnt to make it more strong, hard and durable
10/29/2015 1:51 PM 5 Civil Engineering Materials 5
Bricks
• Commonly it is rectangular in shape
– Length = twice width of brick + thickness of mortar
– Height = multiple of width of brick
– Usual size available in Pakistan is 8¾ x 4¼ x 2 ¾ inches to make it 9 x 4.5 x 3 inches with mortar
– Indian Standard size 19 x 9 x 9 cm and 19 x 9 x 4 cm to make it 20 x 10 x 10 cm and 20 x 10 x 5 cm with mortar
• Bricks are most common form of structural clay products; others being tiles, pipes, terracotta, earthenware, stoneware, and porcelain
10/29/2015 1:51 PM 6 CE-107 Civil Engineering Materials 6
Historical Development
Began as low walls of stones or caked mud
Sun-dried bricks - With the availability of fire became burnt
bricks
Invention of kilns made mass production of bricks easy
Limestone turned into lime mortar replaced mud as mortar
In Mesopotamia, palaces and temples were built of stone and
sun-dried bricks in 4000 B.C.
The Egyptians erected their temples and pyramids of stones by
3000 B.C.
By 300 B.C., Greeks perfected their temples of limestone and
marble
Romans made the first large-scale use of masonry arches and
roof vaults in their basilica, baths and aqueducts
10/29/2015 1:51 PM 7 CE-107 Civil Engineering Materials 7
Historical Development
Medieval and Islamic civilizations perfected masonry vaulting to a high degree of development - Islamic craftsmen built palaces, markets, and mosques of bricks and often faced them with brightly glazed tiles
Europeans built fortresses and cathedrals using pointed vaults and flying buttresses
In America and Asia other cultures were building with stones
During industrial revolution, machines were developed to quarry and cut stones, mould bricks, and speed the transportation of these materials to site of building
Portland cement came into wide use and this enabled the construction of masonry building of greater strength and durability
10/29/2015 1:51 PM 8 CE-107 Civil Engineering Materials 8
Historical Development
Late in 19th century tall buildings were built, of steel and
reinforced concrete (pored into simple forms), economically
Development of hollow concrete forms in 19th century averted
the extinction of masonry as a building material - Cavity wall,
developed by the British during the earlier part of the 19th
century also contributed to the survival of masonry as a building
material
This facilitated the introduction of thermal insulation
High strength mortars, high-strength masonry units, and
complex shapes of masonry units extended the use of masonry
for buildings
10/29/2015 1:51 PM 9 CE-107 Civil Engineering Materials 9
Historical Development
• Through the mid-1800s – Primary Building Materials
• Late 1800s – New Products Developed
– Ended Masonry’s Dominance
• 20th Century Developments
– Steel Reinforced Masonry
– High Strength Mortars
– High Strength Masonry Units
– Variety of Sizes, Colors, Textures & Coatings
10/29/2015 1:51 PM 10 10/29/2015 1:51 PM CE-107 Civil Engineering Materials 10
Adobe
• Spanish-American name applied to sun-dried brick and to the clay soil from which the brick is made
• Adobe soil is composed of very fine mixture of clay, quartz, and other minerals
• Adobe soil has great plasticity when moist, but when dry is so coherent that tillage is almost impossible
• Soil is used combined with straw, molded and baked in sun for 7 to 14 days
• Used in regions of low rainfall and dampness
10/29/2015 1:51 PM 11 CE-107 Civil Engineering Materials 11
Civil Engineering Uses
• Construction of exterior and interior walls,
partitions and boundary walls
• Construction of piers, abutments
• Construction of footings
• Construction of miscellaneous load
bearing structures
10/29/2015 1:51 PM 12 CE-107 Civil Engineering Materials 12
Classification of Bricks
Bricks
Sun Dried
Katcha
Un Burnt
Burnt
Pucca
Practice Usage Finish Manufacture Burning Strength
10/29/2015 1:51 PM 13 CE-107 Civil Engineering Materials 13
Classification of Bricks
• Sun Dried, Un-burnt or Kacha Bricks
– After molding dried in sun, and are used in
the construction of temporary structures
which are not exposed to rains.
• Burnt or Pucca Bricks
– Burnt in an oven called kiln to provide
strength and durability
10/29/2015 1:51 PM 14 CE-107 Civil Engineering Materials 14
Classification of Burnt Bricks
Burnt
Bricks
Practice Usage Finish Manufacture
1st Class
2nd Class
3rd Class
4th Class
Common
Brick
Facing
Brick
Engg
Brick
Sand
Faced
Rustic
Hand
Made
Machine
Made
Burning
Pale Bricks
Under Burnt
Body Bricks
Well Burnt
Arch Bricks
Over Burnt
Strength
Class A
Class B
Classes
350 to 35
10/29/2015 1:51 PM 15 CE-107 Civil Engineering Materials 15
Classification of Burnt Bricks
Field Practice • First Class Bricks
– Thoroughly burnt, deep red, cherry or copper color
– Straight edges, square corners, smooth surface
– Free from flaws, cracks, stones and nodules
– Uniform texture & ringing sound
– No scratch marks with fingernails
– Water absorption 12-15% of dry weight in 24 hours
– May have only slight efflorescence
– Crushing strength not less than 10.5 N/mm2
– Recommended for pointing, exposed face work, flooring and reinforced brick work
10/29/2015 1:51 PM 16 CE-107 Civil Engineering Materials 16
Classification of Burnt Bricks
Field Practice • Second Class Bricks
– Small cracks and distortions permitted
– Water absorption 16-20% of dry weight allowed
– Crushing strength not less than 7.0 N/mm2
– Recommended for all hidden work and centering of RBC
• Third Class Bricks, Pilla Bricks – Under burnt, Soft and light colored producing dull sound
– Water absorption 25% of dry weight
– Recommended for temporary structures
• Fourth Class Bricks, Jhama, Khingar – Over burnt and badly distorted in shape and size
– Brittle in nature
– Ballast of these bricks used for foundation and floors and as road metal
10/29/2015 1:51 PM 17 CE-107 Civil Engineering Materials 17
Classification of Burnt Bricks
Strength Based • Classes
– 350 (35 N/mm2) 125 (12.5 N/mm2)
– 300 (30 N/mm2) 100 (10 N/mm2)
– 250 (25 N/mm2) 75 (7.5 N/mm2)
– 200 (20 N/mm2) 50 (5 N/mm2)
– 175 (17.5 N/mm2) 25 (2.5 N/mm2)
– 150 (15 N/mm2)
• Sub Classes – Subclass A. Tolerance 0.3% in dimensions
– Subclass B. Tolerance 0.8% in dimensions
• Heavy Duty. Compressive strength > 40 N/mm2
10/29/2015 1:51 PM 18 CE-107 Civil Engineering Materials 18
Classification of Burnt Bricks
• Basis of Usage
– Common Brick. General multi-purpose
– Facing Brick. Good appearance, color, textured,
durable under severe exposure
– Engineering Bricks. Strong, impermeable, smooth
and hard
• Basis of Finish
– Sand Faced Brick. Textured surface by sprinkling
sand inside mold
– Rustic. Mechanically textured finish
10/29/2015 1:51 PM 19 CE-107 Civil Engineering Materials 19
Classification of Burnt Bricks
• Basis of manufacturing method
– Hand Made. Hand molded
– Machine Made. Wire cut, pressed and molded bricks
• Basis of Burning
– Pale Bricks are under burnt
– Body Bricks are well burnt in central portion of kiln
– Arch Bricks are over burnt. Also called clinker
10/29/2015 1:51 PM 20 CE-107 Civil Engineering Materials 20
Comparison of Stones and Bricks
• Stone – Natural material
– Heavier
– High dressing cost
– Costly except in hilly areas
– Less porous, good for hydraulic structures
– Greater strength
– Better heat conductor
– Weather resistant
– Superior quality stone is monumental and decorative
• Bricks – Manufactured from clay
– Lighter
– Moldable to any shape
– Cheaper except in hilly areas
– More porous, needs water proof treatment
– Reasonable for normal loads
– Poor heat conductor
– Needs pointing and plastering
– Architectural effect is achievable
10/29/2015 1:51 PM 21 CE-107 Civil Engineering Materials 21
Ingredients of Good Brick Earth
• Brick earth is formed by the disintegration of igneous rocks. Potash feldspars, orthoclase or microcline yield clay minerals which decompose to yield kaolinite, a silicate of alumina. On hydration it gives a clay deposit Al2O3. 2H2O called kaolin.
• Alumina or clay 20-30% by weight
• Silica or sand 35-50% by weight
• Silt 20-35% by weight
• Remaining ingredients 1-2% by weight – Lime (CaO)
– Magnesia (MgO)
– Iron oxides
– Alkalis (Sodium potash, etc)
• Water
10/29/2015 1:51 PM 22 CE-107 Civil Engineering Materials 22
Ingredients of Good Brick Earth
• Silica, Sand – Present as free sand or silicate. Its presence in clay produces hardness, resistance to heat, durability and prevents shrinkage and warping.
• Alumina – Fine grained mineral compound. Moldable plastic when wet, becomes hard, shrinks, warps and cracks when dry.
• Lime – Acts as binder for brick particles. Reduces shrinkage when present in small amount, excess causes the brick to melt and lose shape.
10/29/2015 1:51 PM 23 CE-107 Civil Engineering Materials 23
Ingredients of Good Brick Earth
• Magnesia – Provides darker yellow color
with iron. Usually less than 1%.
• Iron Oxide – Helps fusion of brick and
provides light yellow to red color to brick.
Should not be present as iron pyrites
10/29/2015 1:51 PM 24 CE-107 Civil Engineering Materials 24
Ingredients of Good Brick Earth
• Harmful Substances – Lime in excess or in lumps and pebbles, gravel, etc
– Iron Pyrites
– Alkalis in excess
– Organic Matter
– Carbonaceous Materials
• Additives – Fly Ash – silicates help in strength development
– Sandy Loam – controls drying of plastic soil
– Rice Husk Ash – controls excessive shrinkage
– Basalt Stone Dust – modifies shaping, drying & firing
10/29/2015 1:51 PM 25 CE-107 Civil Engineering Materials 25
Operations in Manufacturing of Bricks
• Preparation of Brick Earth
– Un-soiling
– Digging
– Weathering
– Blending
– Tempering
• Molding of Bricks
• Drying of Bricks
• Burning of Bricks
10/29/2015 1:51 PM 26 10/29/2015 1:51 PM CE-107 Civil Engineering Materials 26
Preparation of Brick Earth
• Un-soiling – Removal of top 20 cm organic matter and freeing from gravel, coarse sand, lime etc
• Digging – additives spread, soil excavated, puddled, watered and left over for weathering
• Weathering – heaps left for one month for oxidation and washing away of excessive salts in rain
• Blending – sandy earth and calcareous earth mixed in right proportions with right amount of water
• Tempering – kneading of blended soil with feet or with a pug mill to improve plasticity and homogeneity
10/29/2015 1:51 PM 28 10/29/2015 1:51 PM CE-107 Civil Engineering Materials 28
Manufacturing of Burnt Bricks
• Molding – giving right shape
– Hand molding • Ground molding. Molded on sand. No frog in bricks
• Table molding. Molded on stock boards with frog
– Machine molding • Plastic method or Stiff-Mud process. Molded stiff clay bar
cut by wire into brick size pieces. Structural clay products
• Dry Press method. Moist powdered clay fed into machine to be molded into bricks. Roof, floor and wall tiles
• Drying – Removing 7-30% moisture present during molding stage. This controls shrinkage, fuel and burning time. Natural open air driers in shades
10/29/2015 1:51 PM 33 10/29/2015 1:51 PM CE-107 Civil Engineering Materials 33
Extruded – Wire Cut Extruded – Smooth
Wood Mold Extruded – Raked
10/29/2015 1:51 PM 35 CE-107 Civil Engineering Materials 35
Manufacturing of Burnt Bricks
• Burning Stages – Dehydration (400-650 °C). Water smoking stage in
which water from pores driven off
– Oxidation (650-900 °C). Carbon eliminated and ferrous iron oxidized to ferric form. Sulphur is removed
– Vitrification (900-1250 °C). Mass converted into glass like substance
• Incipient vitrification. Clay just softens to adherence
• Complete vitrification. Maximum shrinkage
• Viscous vitrification. Soft molten mass, loss in shape, glossy structure on cooling
10/29/2015 1:51 PM 36 CE-107 Civil Engineering Materials 36
Manufacturing of Burnt Bricks
• Clamp or Pazawah Burning – Alternate layers of bricks and fuel encased in mud plaster.
– Fuel consists of grass, cow dung, litter, wood, coal dust
– Brick layer consists of four to five courses of brick
– 25,000 to 100,000 bricks in three months cycle
• Kiln Burning – Intermittent kiln. Loaded, fired, cooled and unloaded before
next loading
– Continuous kiln. Bricks are loaded, fired, dried and cooled simultaneously in different chambers. Example: Bull’s trench kiln and Hoffman’s kiln
10/29/2015 1:51 PM 42 CE-107 Civil Engineering Materials 42
Characteristics of Good Bricks
• Size and shape – uniform size, rectangular surfaces, parallel sides, sharp straight edges
• Color – uniform deep red or cherry
• Texture and compactness – uniform texture, fractured surface should not show fissures, holes, grits or lumps of lime
• Hardness and soundness – not scratchable by finger nail. Produce metallic ringing sound
• Water absorption – should not exceed 20% wt
• Crushing strength – not less than 10.5 N/mm2
• Brick earth – free from stones, organic matter
10/29/2015 1:51 PM 43 CE-107 Civil Engineering Materials 43
Special
Forms
of
Bricks
a. Round ended
brick
b. Cant brick
c. Splay brick
d. Cornice brick
e. Compass brick
f. Bull nosed brick
g. Perforated brick
h. Hollow brick
i. Coping brick
j. Plinth level brick
k. Split brick (Queen
closer)
l. Split brick (King
closer)
10/29/2015 1:51 PM 46 CE-107 Civil Engineering Materials 46
Testing of Bricks
• Dimension Test. Sample size 50. 20 pieces selected to determine length, width and height tolerances.
• Compressive strength Test. Sample prepared from smooth, parallel face, brick is soaked 24 hours and stored under damp jute bags for 24 hours followed by further immersion in water for three days. Load applied @ 14 N/mm per minute till failure. Maximum load at failure divided by average area of bed face gives compressive strength.
10/29/2015 1:51 PM 47 CE-107 Civil Engineering Materials 47
Testing of Bricks
• Absorption Test. – 24 hours immersion cold water test.
• Dry bricks oven dried at 105° ± 5° C
• Room temperature cooled bricks weighed W1
• Bricks immersed in water at 27° ± 2° C for 24 hrs
• Soaked bricks weighed W2
• Water absorption in % = (W2 – W1)/W1 x 100
– Five hours boiling water test • Oven dried bricks weight W1
• Bricks immersed in water and boiled for 5 hours and then cooled down at room temperature in 16-19 hours
• Cooled down weight as W3
• Water absorption in % = (W3 – W1)/W1 x 100
10/29/2015 1:51 PM 48 CE-107 Civil Engineering Materials 48
Testing of Bricks
• Efflorescence Test. Ends of brick kept in 150 mm dia porcelain/glass dish containing 25 mm deep water at 20°–30°C till all water is absorbed – Nil imperceptible efflorescence
– Slight deposit covers area < 10% of exposed area
– Moderate deposit covers exposed area 10% to 50%
– Heavy deposit covers exposed area > 50%
– Serious deposits are heavy and powder or flake away the surface
10/29/2015 1:51 PM 49 CE-107 Civil Engineering Materials 49
Defects of Bricks
• Over-burning. Burnt beyond complete vitrification
• Under-burning. Burnt less not to cause complete vitrification
• Bloating. Spongy swollen mass over the surface due to excess carbonaceous matter and sulphur
• Black Core. Due to bituminous matter or carbon
• Efflorescence. Grey white crystallization of alkalis on the surface, due to water absorption
• Chuffs. Deformation due to rainwater falling or hot bricks
• Checks or Cracks. Due to lumps of lime getting in contact with water
• Spots. Dark sulphur spots due to iron sulphides
• Blisters. Broken blisters due to air entrapped during molding
• Laminations. Thin lamina produced due to air entrapped in voids of clay
10/29/2015 1:51 PM 50 CE-107 Civil Engineering Materials 50
Brick Masonry
• Brick sides
– Header
– Stretcher
• Brick Bonds
– English
• Brick Masonry Patterns
– Herringbone
– Basket weave
– Flemish
10/29/2015 1:51 PM 52 CE-107 Civil Engineering Materials 52
Basic Brickwork Terminology
Bed
Joint
Head
Joint
Course - horizontal layer of brick
10/29/2015 1:51 PM 53 CE-107 Civil Engineering Materials 53
Basic Brickwork Terminology
Header - Bonds two wythes together
Wythe: vertical layer 1 unit thick
Soldier - Laid on its end, face parallel
Rowlock -
laid on face,
end visible
Stretcher - long dimension horizontal
& face parallel to the wall
10/29/2015 1:51 PM 54 10/29/2015 1:51 PM CE-107 Civil Engineering Materials 54
Joint Color that “Blends” w/ Brick Color
10/29/2015 1:51 PM 59 10/29/2015 1:51 PM CE-107 Civil Engineering Materials 59
Simulated Precast Concrete Lintel
(actually a steel lintel supports the assembly)