Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10,...

28
Breaking Ground With Alternative Delivery October 10, 2017 BREAKING GROUND WITH ALTERNATIVE DELIVERY Matt McCarter and Mike Midkiff October 10, 2017

Transcript of Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10,...

Page 1: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

BREAKING GROUND WITH ALTERNATIVE DELIVERY Matt McCarter and Mike Midkiff

October 10, 2017

Page 2: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

Agenda

2

10

11-20

25

3-9What is Design-Build

What we can do…our design-build legislative authority

What makes a project a good candidate for design-build?

Questions

1

2

3

5

21-24How PFD can help4

Page 3: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What is Design-Build

An alternative project delivery method to traditional design-bid-build

Primarily a construction contract that includes:

– Design

– Utility coordination and relocation

May also include:

– Right-of-way acquisition

– Obtaining environmental permits

A single contract

– fixed price

– fixed schedule

3

Page 4: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017 4

Page 5: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What is Design-Build

Question: What is the range in price for past TxDOT design-build projects?

– Answer is B:

• Smallest: US 77 at $84M • Largest: IH-35 E at $1.4B

5

US

77

–C

orp

us C

hri

sti

IH-3

5 E

-D

alla

s

Page 6: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017 6

Page 7: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What is Design-Build

Question: Can advancing a project as a design-build project allow TxDOT to expend

construction funds sooner than a design-bid-build project?

– Answer is A: Yes

7

$

Page 8: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

NEPA/Schematic 9 months

Procurement 15 months

Contract Execution

Design 12 months

Environmental Permits 15 months

Utility Coordination 9 months

Utility Relocation 12 months

ROW Acquisition 21 months

Construction 24 months

Design-Build Timeline

What is Design-Build

Construction funds are committed at the execution of the DB contract before

completion of Utility Coordination/Relocation, ROW acquisition and/or Environmental

Permitting

8

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6Design-Bid-Build Timeline

NEPA/Schematic 9 months

Design 12 months

Environmental Permits 15 months

Utility Coordination 9 months

Utility Relocation 12 months

ROW Acquisition 24 months

Letting 3 months

Contract Execution

Construction 30 months

Page 9: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What is Design-Build

Construction funds are committed at the execution of the DB contract before

completion of Utility Coordination/Relocation, ROW acquisition and/or Environmental

Permitting

9

Design-Build Timeline Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

NEPA/Schematic 9 months

Procurement 15 months

Contract Execution

Design 12 months

Environmental Permits 15 months

Utility Coordination 9 months

Utility Relocation 12 months

ROW Acquisition 21 months

Construction 24 months

Page 10: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What we can do…our design-build legislative authority

Texas Administrative code (TAC) Rule 9.150 refers to

Texas Transportation Code (TTC) Chapter 223.242(d-1)

Subchapter F:

– Limits 3 Design-Build projects executed per Fiscal

Year

10

CONSTRUCTION DESIGN

Total

Cost

Page 11: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

Design-Build Cost

– >$150M

Project Development

– Project has not advanced beyond final schematic

Status and complexity of:

– Utility coordination and relocation

– Right of way acquisition

– Obtaining environmental permits

11

Page 12: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

Complexity

– Would the project benefit from innovative design-

construction methodologies early in the

conceptual/schematic design phase?

– Would the project benefit from designer-contractor

integration to reduce coordination challenges?

Site Conditions

– How well are Site Conditions known? (geotechnical/

soil conditions, hazardous materials, utilities)

Alternative Delivery Support Tool

– Completed

– Documents that the project is eligible for Design-Build

12

Page 13: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

Interview the three candidate projects

Discuss some of their characteristics

Choose the project that’s the ideal match for Design-Build

13

1 2 3

Page 14: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

Project 1

14

1

Pro

ject

1

$850M

Complex

Approved EA/FONSI for ultimate improvement

Preliminary schematic for interim improvements

Significant utility relocation with interim/ultimate improvements and main lane and frontage reconstruction

ROW acquisition some acquired by TxDOT, some acquired by DB Contractor

Political completion commitment

before end of 2019

Page 15: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

Pro

ject

2Project 2

15

2

$300M

Approved EA/FONSI for ultimate improvement

Preliminary schematic for interim improvements

Significant utility relocation with interim/ultimate improvements and electric/water

coordination/relocation

No additional ROW acquisition

Political completion commitment

Not complex

Page 16: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

Project 3

16

3

Pro

ejc

t3

$84M

Low complexity typical construction of portions of

freeway/highway and adjacent frontage roads

EIS/ROD

Approved schematic design

No significant utility relocation typical utility coordination/relocation for portions of

freeway/highway and adjacent frontage roads

ROW acquisition for portions of freeway/highway and adjacent

frontage roads

No completion commitment

No significant permits typical permits are needed

Page 17: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

Question: Which of the three candidate projects are good for design-build?

17

Project 1:

$850M

Complex

Approved EA/FONSI for ultimate improvement

Preliminary schematic for interim improvements

Significant utility relocation with interim/ultimate improvements and main lane and frontage reconstruction

ROW acquisition some acquired by TxDOT, some acquired by DB Contractor

Political completion commitment before end of 2019

Page 18: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017 18

Page 19: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

Question: Which of the three candidate projects are good for design-build?

19

$300M

Not complex

Approved EA/FONSI for ultimate improvement

Preliminary schematic for interim improvements

Significant utility relocation with interim/ultimate improvements and electric/ water coordination/relocation

No additional ROW acquisition

Political completion commitment

Project 2:

Page 20: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017 20

Page 21: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

Question: Which of the three candidate projects are good for design-build?

21

$84M

Low complexity typical construction of portions of freeway/ highway and adjacent frontage roads

EIS/ROD

Approved schematic design

No significant utility relocation typical utility coordination/relocation for portions of freeway/highway and adjacent frontage roads

ROW acquisition for portions of freeway/highway and adjacent frontage roads

No completion commitment

No significant permits typical permits are needed

Project 3:

Page 22: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017 22

Page 23: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

What makes a project a good candidate for design-build?

23

Would not meet current >$150M

minimum design-build cost

Project 1: Project 2: Project 3:

Answer: Projects 1 and 2 are good candidates for design-build.

Page 24: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017 24

Page 25: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

How PFD can help

25

Question: How many design-build projects has TxDOT developed/advanced?

– Answer is: C

• TxDOT has advanced 16 design-build projects

Page 26: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

DFW Connector $1.36B

SH 99 Grand Parkway (GP) Segments (F1, F2, & G)

$1.57B

Loop 1604 $126M

CTTS - (SH 130 Seg 1-4) $1.4B

Horseshoe $805M

US 77 $84M

SH 71 Express Lanes $139M

SH 360 $340M

SH 99 GP Segments (H-I) $1.28B

Southern Gateway $606M

SH 249 $674M

IH-35E $1.36B

Loop 375 BWE (CDA-DB) $640M

SH 183 Midtown Express $1.04B

US 181 Harbor Bridge $963M

In Design & Construction CDA Statute: Chapter 223 Subchapter E IH-35E $1.36B

(CDA-DB)Loop 375 BWE (CDA-DB) $640M

SH 183 Midtown Express $1.04B

US 181 Harbor Bridge $963M

In Design & Construction Design-Build (DB) Statute: Chapter 223 Subchapter F (limited to 3 per FY )

Horseshoe $805M

(DESIGN-BUILD)

US 77 $84M

SH 71 Express Lanes $139M

SH 360 $340M

SH 99 GP Segments (H-I) $1.28B

Southern Gateway $606M

SH 249 $674M

In Operations and Maintenance (All Projects) DFW Connector $1.36B (CDA-DB)

SH 99 Grand Parkway (GP) Segments (F1, F2, & G)

$1.57B (CDA-DB)

Loop 1604 $126M (DESIGN-BUILD)

CTTS - (SH 130 Seg 1-4) $1.4B (DESIGN-BUILD)

How PFD can help

26

Page 27: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

2018 2019 2020 2021 2022

116 9

How PFD can help

27

We’re looking for bench depth as we’re building TxDOT’s five-year plan and

ten-year forecast.

810713 1815 54 16 121714

Page 28: Breaking Ground with Alternative Delivery · Breaking Ground With Alternative Delivery October 10, 2017 DFW Connector $1.36B SH 99 Grand Parkway (GP) Segments (F1, F2, & G) $1.57B

Breaking Ground With Alternative Delivery October 10, 2017

???

Questions

28

We are ready for your questions.

?