International Association for Management of Technology IAMOT 2010 Proceedings Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 1 Bottleneck-based synchronization of engineering and manufacturing BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING JOHANNES HINCKELDEYN Hamburg University of Applied Science Department Mechanical Engineering and Production Berliner Tor 21, 20099 Hamburg, Germany Email: [email protected] Rob Dekkers University of the West of Scotland Business School Paisley PA1 2BE, United Kingdom Email: [email protected] Nils Altfeld Hamburg University of Applied Science Department Mechanical Engineering and Production Berliner Tor 21, 20099 Hamburg, Germany Email: [email protected] Jochen Kreutzfeldt* Hamburg University of Applied Science Department Mechanical Engineering and Production Berliner Tor 21, 20099 Hamburg, Germany Email: [email protected] *corresponding author Abstract: The synchronization of manufacturing and engineering is crucial for companies in the engineer to order or the make to order environment. The competitive advantage of these companies is based on the flexible fulfillment of customer requirements. A shortage of engineers, like for example in Germany, is especially threatening to these companies. To face this challenge, the productivity of engineering has to be increased. Many experiences in the field of productivity improvement measures have been gained in production management until today. The objective of this paper is therefore to investigate, if production man- agement principles could be applied to engineering management. Engineering and manufacturing processes are compared and the similarities are identified. Based on this evaluation two possible bottleneck management approaches from manufac- turing are assessed regarding their applicability in engineering. Keywords: Engineering Management, Bottlenecks, Drum Buffer Rope, Slot Planning, Production Management Impact of Engineering to Manufacturing A good and quick engineering of products and processes is especially important for companies, who work in a make to order (MTO) or engineer to order (ETO) environment. The competitive advantage of these companies is based on the fulfillment of individual customer requirements (Westkämper 2006, p.16), which can be satisfied by engineering the product according to the customer’s preference. The approach demands a high flexibility and capability in manufacturing and engineering processes. The success factor is the capability to deliver the specific order in time (Handfield 1994, p.384). Therefore a short lead time and effective synchronization of the individual process management could be viewed as

Transcript of BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF...

Page 1: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 1

Bottleneck-based synchronization of engineering and manufacturing

BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING

JOHANNES HINCKELDEYN

Hamburg University of Applied Science

Department Mechanical Engineering and Production

Berliner Tor 21, 20099 Hamburg, Germany

Email: [email protected]

Rob Dekkers

University of the West of Scotland

Business School

Paisley PA1 2BE, United Kingdom

Email: [email protected]

Nils Altfeld

Hamburg University of Applied Science

Department Mechanical Engineering and Production

Berliner Tor 21, 20099 Hamburg, Germany

Email: [email protected]

Jochen Kreutzfeldt*

Hamburg University of Applied Science

Department Mechanical Engineering and Production

Berliner Tor 21, 20099 Hamburg, Germany

Email: [email protected]

*corresponding author

Abstract: The synchronization of manufacturing and engineering is crucial for companies in the engineer to order or the make to order

environment. The competitive advantage of these companies is based on the flexible fulfillment of customer requirements. A

shortage of engineers, like for example in Germany, is especially threatening to these companies. To face this challenge, the

productivity of engineering has to be increased. Many experiences in the field of productivity improvement measures have

been gained in production management until today. The objective of this paper is therefore to investigate, if production man-

agement principles could be applied to engineering management. Engineering and manufacturing processes are compared

and the similarities are identified. Based on this evaluation two possible bottleneck management approaches from manufac-

turing are assessed regarding their applicability in engineering.

Keywords: Engineering Management, Bottlenecks, Drum Buffer Rope, Slot Planning, Production Management

Impact of Engineering to Manufacturing

A good and quick engineering of products and processes is especially important for companies, who

work in a make to order (MTO) or engineer to order (ETO) environment. The competitive advantage of

these companies is based on the fulfillment of individual customer requirements (Westkämper 2006,

p.16), which can be satisfied by engineering the product according to the customer’s preference. The

approach demands a high flexibility and capability in manufacturing and engineering processes. The

success factor is the capability to deliver the specific order in time (Handfield 1994, p.384). Therefore a

short lead time and effective synchronization of the individual process management could be viewed as

Page 2: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 2

Bottleneck-based synchronization of engineering and manufacturing

crucial. The manufacturing of a product is directly related to engineering process, as this process sup-

plies the manufacturing process with the necessary information. The organization of the manufacturing

process in MTO and ETO environments are usually job shops (Dyckhoff 2007, p. 28; Lödding 2008, p.

97), which cooperate closely with the engineering process. This type of manufacturing organization

provides the necessary degree of flexibility to handle the individual engineered orders in this kind of

companies to assure the competitive advantage of engineering companies.

Germany as an example of engineering bottlenecks

The economy in Germany is quite powerful and the country holds the fourth position in the ranking of

economies in the world (UNCTAD 2008, p.399). The competitive advantage of German mechanical en-

gineering companies lies in the high quality and the flexible consideration of customer requirements

(Berkermann et.al. 2009, p.5), but it is threatened by a shortage of skilled engineers. These companies

invested in 2008 approximately 50 billion Euros in research and development for new and existing

products (Krebs 2008). The respective engineering processes therein must have an accordingly high

standard of capability and coordination. The activities of these engineering processes are mostly carried

out by professionals, who hold usually a University degree in an engineering subject (Krebs 2007). A

shortage of these skilled workers is especially threatening to engineering companies, because their staff

has a disproportionately high amount of engineers. The rate of engineers within the whole workforce of

the branch has doubled over the last 25 years to 16.5 percent (Krebs 2007). Despite the financial crisis,

Germany is still suffering from a shortage of 44.000 skilled engineers, which creates an economic dam-

age of at least 6.6 billion € in 2009 (Koppel 2009). It is quite unlikely, that this constraint can be solved

within the next years by enhancing engineering capacities, because there will not be enough engineering

students available (OECD 2008). In addition other German speaking countries, like Switzerland, are al-

so suffering from similar shortages (Gehrig & Fritschi 2008). A possible solution for the problem is to

increase the productivity of engineering processes. Production management has gained much experience

in this field over the years of research and application in industry. Bottleneck management could serve

as an example for a productivity enhancement method. However, most approaches for bottleneck man-

agement are restricted to manufacturing processes. It is therefore important to assess, if an adoption of

bottleneck mechanisms from production management is possible.

Objectives and approach of the paper

The objective of the paper is to compare manufacturing and engineering processes and to discuss the

applicability of production management principles in engineering. The question is raised, if the produc-

tivity in engineering could be increased through application of experiences from production manage-

ment. The paper is structured as follows: The next section gives an overview about the background of

engineering management approaches from literature. Thereafter engineering and manufacturing

processes are outlined and compared to underpin the applicability of production management principles.

Two possible bottleneck solutions from production management are chosen and their characteristics are

described. These possible bottleneck management approaches are evaluated regarding their applicability

in engineering. The outcomes are discussed and steps for further research in this field are identified. A

recent study shows, that the resource management in research and development processes is only poorly

implemented and incorporates a high potential for optimization (Franke et.al. 2009). The bottlenecks in

engineering are usually known in the organization, but no systematic concepts have been developed so

far. This is in contrast to production management, where a huge amount of bottleneck solutions are

available. This contribution investigates the applicability and restrictions of such bottleneck approaches

to engineering processes.

Page 3: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 3

Bottleneck-based synchronization of engineering and manufacturing

Background of engineering management

Productivity is related to the resource planning and control of engineering projects. Several approaches

for managing engineering projects have been developed so far. According to Coates et.al.(2004), the

project outcomes are determined by five success factors. These are the coordination within the project,

the communication between project partners, a reasonable task allocation, an all-embracing time man-

agement and a resource planning for the effective utilization of all project partners. Wheelwright and

Clark (1992a) introduce a procedure for capacity balancing in engineering processes. Based on a project

categorization system, a processing sequence of engineering projects is detected for planning of engi-

neering processes.

According to Chang (2004), planning and control is an essential task of engineering management. The

problem in planning engineering workload is the creative character of engineering activities, which

creates uncertainty in planning parameters. The engineering as a capacity bottleneck is identified by

Färber et.al.(2002). A possible solution for planning engineering parameters is to compute average dura-

tions and workloads of previous engineering projects (Tracht 2001). The relationships between product

function and resource allocation is modeled in an interdependence matrix by Meier and Hanenkamp

(2003). An additional way of planning is process modeling. Wheelwright and Clark (1992b) develop an

ideal process to reduce the throughput time of development projects. This procedure is intensified in

concurrent engineering (Yassine & Braha 2003) by integrating relevant parties as soon as possible in the

engineering process. A similar solution can be found in simultaneous engineering (Bullinger & War-

schat 1997; Chang et.al. 1994), which tries to parallelize tasks in engineering processes. Engineering

productivity can be controlled through performance measurement. A comprehensive set of solutions for

performance measurement in engineering is developed by Leyndekker (2000a). In a first step, he de-

scribes general dimensions of performance in engineering. In his further articles, he emphasizes on solu-

tions for measuring adherence to schedules (Leyndekker 2000b), capability for innovation (Leyndekker

2000c) and personal performance (Leyndekker 2000d). All these approaches are integrated a balanced

scorecard model (Leyndekker 2000e). All these approaches are not derived from production manage-

ment.

Planning and control is an original activity of production management. The applicability of production

management principles in engineering processes are hypothesized by Dekkers (2006). Examples for

successful applications are lean thinking in development processes (Adler et. al. 1996) and a Just in

Time scheduling system for engineering (Wildemann 1994). The literature review in engineering man-

agement showed that a scheduling method has to be able to work with project management. Goldratt

expanded his Theory of Constraints (TOC) (Goldratt 1990) on project management with his book “Crit-

ical Chain” (Goldratt 1997). The adherence to schedules is assured by placing projects buffer along the

critical path of a single project and thus the rate of delayed projects decreased (Rand 2000). The placing

of project buffers has been facilitated in the meanwhile by considering more parameters (Wei et.al.

2002). However engineering projects are usually carried out in a multi project management environ-

ment. Fricke and Shenbar (2000) propose a multi-project-management for the planning of engineering

projects. They emphasize on the prioritization of projects and the allocation of resources. Steyn (2002)

provides an application of TOC in the multi project management environment. Based upon the Drum

Buffer Rope method, he creates a bottleneck based scheduling of projects. Engineering projects however

are creative information transformation processes (Eversheim et.al. 1994) and therefore services, which

cannot be stored (Meffert 2000). Drum Buffer Rope works with a sophisticated buffer management and

it is questionable, if this is the right scheduling system for engineering projects. To evaluate the applica-

bility, the engineering and manufacturing process are compared. Based on this evaluation the Drum

Buffer Rope method is evaluated against another scheduling method from production management.

Page 4: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 4

Bottleneck-based synchronization of engineering and manufacturing

Parallels of manufacturing and engineering processes

The following section is concerned with the hypothesis, that engineering can be managed with produc-

tion management principles in the focus of productivity improvement. Productivity improvement meas-

ures optimize the relation of input and output (Slack et.al. 2007; p.51) and can be manifold. Examples

are decreasing input with a sophisticated resource allocation or raising output through automated

processes or intelligent bottleneck utilization. The hypothesis to treat engineering management with

production management principles was assessed in a focus group investigation. Focus group research is

a method, which is commonly used for the development of hypothesis (Rook 2007, p. 125). This re-

search method facilitates the data collection through interaction within a group to elicit rich experiences

and expertise in the addressed research area (Asbury 1995, p.414). Here, the focus group contained eight

participants. All of the participants have gained at least three years of working experience as an engi-

neering and production manager. The group consisted of three engineering managers, three production

managers and two managers, who have gained experience in both fields. This group composition was

chosen to foster the exchange and the discussion, whether production management principles are appli-

cable to engineering. To support and guide the group discussion a questioning route of nine questions

was developed. The group discussion took two hours and the outcomes were documented with field

notes supported by audio recording. The protocol of the focus group was analyzed thematically (Rook

2007, p.122). The analysis process was structured according to the classical analysis strategy from

Krueger (2009, p.118), which offers a systematic approach to assign answers to the investigated ques-

tions. The answers are integrated in the subsequent sections.

Scope of engineering processes

Engineering is usually concerned with the transformation of specific customer requirements into infor-

mation to satisfy the customer needs (Eversheim et.al. 1994). Therefore, the overall objective is to fulfill

efficiently the customer requirements regarding quality and timeliness (Stewart & Calloway 1982). At

first, the activities of the operative engineering process must be defined. The research and development

process can be divided into five phases (Abele et.al. 2006):

1. Research for basic innovation, like the investigation of new active principles or materials.

2. New platform development means usually to develop new products and it is therefore often dif-

ficult to reuse older parts or components.

3. The development of application for the adjustment of products to market demands are change

request or product variations. These orders are easier to plan and control, because of the consi-

derable amount of reuse of previous parts and projects.

4. The development of production processes and techniques can be carried out parallel or after the

development of new products or applications.

5. Manufacturing support is responsible for ramp-up of new and improvement of existing produc-

tion processes.

The research process (1.) is not considered as part of an engineering process. Such projects show usually

a unique character and therefore mostly processed in own project organizations without any contact to

the manufacturing department (Abele et.al. 2006). However product and process development in me-

chanical engineering companies are usually carried out close to the manufacturing and in incremental

innovative steps (Keegan & Turner 2002). Figure 1 shows the framework of the operative engineering

process:

Page 5: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 5

Bottleneck-based synchronization of engineering and manufacturing

Figure 1: Framework of engineering process.

A process according to DIN ISO 9000 (2005) is defined as a set of tasks, which are related via interac-

tions or interdependencies. The purpose of these tasks is to transform input into output. Engineering is

carried out with interfaces to purchasing, customers, manufacturing, work preparation, research, sales

and service process. The input of the engineering process can come from both internal and external cus-

tomers. External customers buy products of a company and generate new orders, which must be

processed through the engineering process. In addition internal customers can also generate engineering

orders, e.g. orders for the development of production equipment or new production procedures. Both in-

ternal and external customer orders can be described through specific requirements and delivery date of

the expected outcome. The outputs of the engineering process are mostly attributes or specifications of

products, processes or systems. These outcomes are information for the related processes, which be-

come manifest in form of documents, e.g. construction drawings, bills of materials, working plans or

process descriptions. The number of documents is sometimes used for workload planning in engineering

(Eversheim 1994). It is important to notice, that engineering is a service and its output is therefore most-

ly intangible. The resources in development task are allocated through projects (O’Connor, 1994),

which can be characterized by a well defined start and delivery date. Solutions for engineering project

planning are provided in literature (Tracht 2001; Wildemann 2003). To achieve the project objectives

the boundaries of time, costs and resources have to be considered. Further, engineering processes work

usually iteratively.

This iterative character is caused by the information transformation process of engineering. The degree

of uncertainty is related to the novelty of the engineering task. Application development in form of

change requests is in most of the cases easy to predict and to handle, because the engineering can go

back to previous projects and experiences for planning purposes. For that reason, a good knowledge

management and a well documented database are the foundation of a good engineering planning, be-

cause 69% of all engineering processes can reuse at least 25% of the parts for several times (Hörnig &

Gittmann 2006). The platform development however is more difficult to plan and control, because of the

rising degree of novelty and 87% of all engineering processes change often (Hörnig & Gittmann 2006).

It depends on the experience of the company and the individual engineer if there are sufficient expe-

riences and expertise is available to plan and control such a project. This transformation process can be

supported be various software tools, which can automate some process steps (Hörnig & Gittmann 2006,

p.15), but this attribute is usually poorly developed (Franke et.al. 2008, p.19). Examples for software

tools are Computer Aided Development (CAD), Computer Aided Manufacturing (CAM) or Product Da-

ta Management (PDM). Some companies introduce additionally a phase model, sometimes known as

Sale

sResearch

Engineering

Manu-facturing

CustomerPurchasing

Work preparation

Service

Application development

Platformdevelopment

Process development

Manufac-turing support

Legend:

Flow of material

Flow of information

Page 6: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 6

Bottleneck-based synchronization of engineering and manufacturing

Stage-Gate model (Cooper 1990, p.44), to streamline their development process comparable to a manu-

facturing process.

A process is defined by performed task and input and output. To differentiate input from and output into

the related processes figure 2 shows an input / output diagram of the engineering process in the organi-

zational context. The engineering process itself is displayed as blue box. The grey boxes provide re-

sources for processing engineering orders. For complex products, like in mechanical engineering com-

panies, a project team of technical specialists is usually responsible (Crabtree et.al. 1997). These spe-

cialists can be divided into functions, which are mainly concerned with a certain area of engineering

work, e.g. mechanical engineering, electrical engineering, software engineering or industrial engineering

(Chang 2004). The functional departments are the optimal organization for expert resources (Kunz

2007). These functions provide expertise and resources for processing engineering projects. Engineering

departments are mostly multi-project management environments and have often a matrix structure

(Dammer 2008). In case of capacity shortage or know how bottlenecks, engineering departments are us-

ing outsourcing contractors to solve these problems (Bromberg 2007). These service contractors work

usually in close coordination to the functional engineering department. In addition project management

resources have to be provided; these tasks can be fulfilled by engineers from the functional engineering

department or, for larger projects, from full-time project managers.

Figure 2: Engineering process in organizational context.

The related processes are displayed on white background. The research process is providing basic inno-

vations, which can be used as expertise in the engineering process (Abele et.al. 2006). Customer re-

quirements may occur due to different processes. If it is an external customer the input is coming from

the sales process, mostly in form of customer orders or change requests. Internal customers, like the

manufacturing or service process, can also request orders. Examples are change requests of existing

products or the development of process equipment. These requirements contain technical parameters,

which have to be fulfilled for a proper solution as well as time constraints. The set of requirements in

MTO and ETO environments is for every order individual. The processed information contains usually a

considerable degree of uncertainty and is documented in the specification sheet of a project. As process

activity, the input is translated into information to manufacture and service the product. In case of out-

Engineeringprocess

Sales Process

Research Processes

Outsourcing Contractor

Engineering Project

Management

FunctionalEngineering

DepartmentsSupplier

Manufacturing Process

Service Process

Technical Ressources,Expertise

Technical Ressources,Expertise

Project ManagementRessources

Basic Innovation

Attributes, Specifications

Control Information

Attributes, Specifications

SpecificRequirements, Time Schedule

SpecificRequirements, Time Schedule

TechnicalInformation

Information

Resources

Legend:

Material

SpecificRequirements, Time Schedule

Parts, Components

Page 7: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 7

Bottleneck-based synchronization of engineering and manufacturing

sourcing, the development has to be carried out in cooperation with suppliers, which are responsible for

producing parts and components for the manufacturing and service process according to the given speci-

fication of the engineering. Usually, these suppliers provide technical information and feedback for the

development process. Table 1 summarizes the process parameter of an engineering process to compare

it with the manufacturing process:

Table 1: Process Parameters of Engineering.

Parameter Value

Input Information (from all process participants), engineering expertise, personal capacity

Output Information (attributes, specification) to manufacture products

Recurrence

of activities

Recurrence range from low to medium depending on the novelty of the engineering

task

Recurrence

of parts

Recurrence range from low to medium depending on the novelty of the engineering

task

Buffer man-

agement

Engineering processes are services and can therefore not be stored

Scheduling The accuracy of scheduling is depending on the novelty of the engineering task

Reasons for

bottlenecks

Shortage of capacity, expertise unavailable or insufficient, information not available

Sequence of

operations

Highly iterative, due to adjustment of interrelationship between the parts of the de-

veloped system.

Degree of

automation

Supported by software tools, but poorly developed at the moment

Using these processing parameters, Drum Buffer Rope and slot planning shall be tested and compared

for their applicability for engineering planning.

Manufacturing from a process point of view

In manufacturing processes personal capacity, material and infrastructure are transformed into products

(Gutenberg 1976) under consideration of costs, time and resources. Products can be tangible, intangible

or hybrid. In ETO and MTO companies, the production orders are going hand in hand with specific in-

formation for the processing of the order. This information can come directly from the engineering de-

partment in form of drawings or process descriptions. Additionally, some companies have special func-

tion for the translation of engineering parameters into manufacturing parameters and the planning of the

manufacturing orders. This function is called work preparation. This flow of information is synchro-

nized with the material, which is purchased for processing.

For the consideration of the detailed organizational context, an input / output diagram of a manufactur-

ing process is drawn in figure 3. The specific information for order processing is provided from the en-

gineering process (in some cases translated through the work preparation) An undersupply of these in-

formation lead to decreasing performance of the manufacturing process, even if material and capacity

are available. Usually orders in the mechanical engineering industry are carried out as projects, which

are planned and controlled from project managers. To carry out his activities, the manufacturing process

needs technical resources, which can come from the manufacturing department itself, independent from

its organization. These resources contain personal and machine capacity as well as expertise in the man-

ufacturing process, what is crucial in the processing of customer individual orders. For automation pur-

poses, some of the companies invest in manufacturing equipment, like Computerized Numerical Control

(CNC) machines or robotics. The degree of automation is highly related with the manufactured product

and in ETO and MTO environments lower than in mass production. If the company works with service

contractors, these resources are provided from other companies. The manufacturing process needs fur-

ther parts and components from his supplier. In ETO and MTO environments, the supplier receives the

Page 8: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 8

Bottleneck-based synchronization of engineering and manufacturing

necessary information for manufacturing from the engineering process. The output of the manufacturing

process is manufactured goods, which are transported and installed for the customer. Further, the manu-

facturing process is responsible to supply the service process with spare parts for carrying out his main-

tenance and service activities.

Figure 3: Manufacturing process in the organizational context.

In summary, the process parameters of manufacturing processes are depending on the variety of the

goods and the process tasks (Slack et.al. 2007). A high variety manufacturing process has diverse and

complex process tasks, which can be as unique as the product, which is manufactured. These tasks are

usually carried out in a job shop organization, which is quite common in MTO or ETO environments.

However, a low variety manufacturing process contains repeated and divided tasks, which are carried

out in a continuous process flow. This allows the production of a large number of goods and usually a

flow shop organization is used for those processes. These processes must be understood as the extreme

points of a spectrum, which is spread over all manufacturing processes. The process parameters of this

spectrum are listed down below in the table:

Manufacturingprocess

Engineering Process

Outsourcing Contractor

Project Management

Manufacturing Department Supplier

Logistic andInstallation

Process

Service Process

Technical Ressources,Expertise,Capacity

Technical Ressources,Expertise,Capacity

Project ManagementRessources

Manufacturedgoods

Control Information

Attributes,Specifications

Parts, Components

Information

Resources

Legend:

Material

spare parts

Page 9: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 9

Bottleneck-based synchronization of engineering and manufacturing

Table 2: Process Parameters of Manufacturing.

Parameter Value

Input Information (from engineering and project management), personal and ma-

chine capacity, material

Output Products (for customers) and spare parts (for service)

Recurrence

of activities

Recurrence ranges from high (mass or continuous process) to low (project

processes or job shops)

Recurrence

of parts

Rate of recurrence ranges from high (mass or continuous process) to low

(project processes or job shops)

Buffer

management

Buffers are possible in all stages of the manufacturing process.

Scheduling Precision in scheduling ranges from medium (job shops) to accurate (flow

shops)

Reasons

for bottlenecks

Shortage of capacity, availability of material

Sequence

of operations

Manufacturing processes can be sequential (flow shops) or non-directional

and iterative (job shops)

Degree of

automation

The degree of automation ranges, depending on the manufactured product,

from medium (job shops) to high (mass production)

Comparison of manufacturing and engineering processes

As mentioned above, the manufacturing process can be distinguished into job shops and flow shops to

cover the whole spectrum of manufacturing processes. A comparison of manufacturing processes and

engineering process is shown in the table 3.

Table 3: Comparison of process parameters of engineering and manufacturing

Parameter Engineering process Job Shop Flow shop

Input Information, engineering

expertise, personal capaci-

ty

Information, personal

and machine capacity,

material

Information, personal and

machine capacity, material

Output Information Products (for customers)

and spare parts (for ser-

vice)

Products (for customers)

and spare parts (for ser-

vice)

Recurrence

of activities

Low to medium Low to medium Medium to high

Recurrence

of parts

Low to Medium Low to medium Medium to high

Buffer man-

agement

Engineering outcomes are

services and not storable

Buffers are possible in all

stages of the process

Buffers are possible in all

stages of the process

Scheduling Low to medium precision

in scheduling

Medium precision in

scheduling

High precision in schedul-

ing

Reasons for

bottlenecks

Shortage of capacity,

availability of expertise

and information

Shortage of capacity,

availability of material

Shortage of capacity,

availability of material

Sequence of

operations

Highly iterative and non-

directional

iterative and non-

directional

sequential

Degree of

automation

Low, depending on soft-

ware environment

Usually medium Usually high

It is evident, that engineering process can be more compared to job shops, than to flow shops. This con-

firms also the hypothesis from previous authors (Adler et.al. 1996; Steyn 2002). Jobs shops primarily

Page 10: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 10

Bottleneck-based synchronization of engineering and manufacturing

used in ETO and MTO companies, which are producing customer individual goods. These companies

are based upon the requirement to produce a customer individual good. Engineering and manufacturing

have to provide high flexibility and excellent capabilities for the fulfillment of individual customer or-

ders. Furthermore engineering departments are organizations with functional expertise and are according

to this often functionally organized, which is a characteristic of job shops. Based on this comparison and

the conclusion to treat engineering processes like job shops, bottleneck management approaches from

production management are reviewed to find a contrast to Drum Buffer Rope.

Bottleneck Management in manufacturing

Bottlenecks in manufacturing processes are a widely known and investigated phenomenon. The amount

of literature in this field is overwhelming. The first description of bottlenecks in a business context was

done by Gutenberg (1976). He identified bottlenecks as the resource of a company that only can be uti-

lized until a certain threshold. The resource with the lowest threshold limits the performance of the

overall system. Moreover, the American Production and Inventory Control Society (APICS) defines a

bottleneck as an asset, a function, a department or a resource, whose capacity is smaller or equal to the

faced demand (Blackstone 2008). These definitions can be applied to all company processes.

Bottlenecks can appear in several dimensions, e.g. capacity, material or information, led to various ap-

proaches, which are able to identify and evaluate different types of bottlenecks. Developed approaches

measure various key indicators (Wiendahl & Nyhuis 1998) for a workstation and propose activities to

improve the logistical targets of a manufacturing organization (Nyhuis & Wiendahl 2003). Key indica-

tors are also used to prioritize bottlenecks with resource portfolios (Nyhuis 2008). The breakdown and

repair rates of machines on bottlenecks and throughput are analyzed by Ching et al. (2008). The dynam-

ic effects of shifting bottlenecks are modeled by Juran et.al. (2008). To articulate the effect of bottle-

necks on the shop floor for improvement measures, a visual approach for identification and evaluation

of bottlenecks is developed and shows the relationship between the workload and the throughput of an

order flow as a characteristic curve (Schultheiss & Kreutzfeldt 2009). Based on the identification and

assessment of bottlenecks, several bottleneck based scheduling approaches for production are devel-

oped. Betterton & Cox III (2009) do a comparative study on simulation models to investigate bottle-

neck-based scheduling in serial production lines. The problems of bottlenecks are also discussed by

Chen and Chen (2009) and Rajendran and Alicke (2007). Both develop scheduling rules for bottleneck

resources. A solution for complex job shops is proposed by Mönch & Zimmermann (2007). They tackle

the scheduling problem by applying an agent-based scheduling system. This allows re-scheduling in

shifting bottlenecks situations. A similar agent-based solution for dynamic and uncertain production en-

vironments is developed from Miyashita & Rajesh (2010). All of these approaches are only dealing with

logistical problems in the manufacturing environment.

As mentioned before, Drum Buffer Rope method is bottleneck-based scheduling approach for multi

project management (Steyn 2002), like the engineering process. The disadvantage of this solution is the

demand on a proper buffer management and the need for detailed scheduling. Both characteristics are

not given from engineering processes. Therefore the Drum Buffer Rope Approach is evaluated against a

slot planning solution, which is able to work without buffer management and detailed schedules on the

bottleneck.

Drum Buffer Rope Method

The Drum-Buffer-Rope Method (DBR) is the scheduling system employed by the TOC (Goldratt &

Fox, 1986) and aims on increasing the performance of a system. DBR works on the basis of a finite ca-

pacity scheduling method and is similar to a scheduling function with a simple input / output control.

Page 11: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 11

Bottleneck-based synchronization of engineering and manufacturing

The primary focus is the inventory control of a production system (Gupta & Boyd 2008). Therefore, two

well balanced inventories (Buffers) are introduced in a DBR system, which is shown in Figure 5.

Figure 5: Drum Buffer Rope Approach (Moore & Scheinkopf, 1998)

The first buffer is introduced in front of the primary bottleneck of the production system. This buffer

protects the bottleneck from variances in the upstream functions. The first assumption here is that the

performance of the production system is maximized with the utilization of the bottleneck. The second

buffer is placed as a shipping buffer to the customer and protects the system from delivery difficulties.

The second assumption is that non-bottleneck resources have excess capacity, so that they are able to

process an order immediately. In the scheduling algorithm, the orders are selected by due date and

roughly loaded to every work station. An iterative capacity evaluation is carried out until the primary

bottleneck (Drum) is identified. This drum sets the pace for the release of new orders. An information

system (Rope) is introduced, which ties up all necessary dates for new order release. After identification

of the bottleneck, a detailed scheduling of the order is performed. First, the orders are scheduled on the

bottleneck, therefore the shipping buffer and bottleneck processing time is subtracted from the customer

due date. The next step is to subtract the bottleneck buffer from the order start time of the buffer. From

the order arrival at the bottleneck, the orders are scheduled backwards. The orientation on the overall

bottleneck of the whole system makes it possible to achieve a global optimum. In the case of engineer-

ing bottlenecks, the engineering process can serve as the drum in the scheduling system and therefore

hold responsible for the pace of the process. Nevertheless, DBR systems have never been applied to en-

gineering processes. The method characteristics (MC) of DBR systems are summarized below:

1. The objective (MC1a) of DBR is to increase the throughput of a system, according to the basic as-

sumption of all TOC methods (Goldratt, 1990).

2. The approach is based upon buffer management (MC2a). Two kinds of buffer are used, a bottle-

neck buffer, which ensures a high utilization of the bottlenecks resource and a shipping buffer,

which ensures the fulfillment of customer requests.

3. The scheduling (MC3a) is carried out roughly until the identification of a bottleneck. After the ap-

pearance of a bottleneck, a detailed scheduling is carried out.

4. The bottleneck resource (MC4a) sets the pace for new order release. The order release is supported

by an information system, the rope.

5. Non-bottleneck resources (MC5a) have excess capacity to process orders. Therefore, the queue be-

fore these resources is relatively small. This protects the system performance from process varia-

tions.

Slot Planning

Slot planning is a sequence-based scheduling method for single and multi-stage processes. These mod-

els show an integrated planning and scheduling algorithm and are called full-space methods (Maravelias

& Sung 2008). Slot planning is focusing on resource constraints and production costs. Many approaches

of slot planning and scheduling have been applied and implemented to various industries. For example:

Supplier CustomerWork

stationWork

stationDrum

Work station

ShippingBuffer

Bottleneck Buffer Inventory Inventory

Rope

Page 12: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 12

Bottleneck-based synchronization of engineering and manufacturing

- Madas and Zografos (2006) tackle the problem of capacity shortfalls and delay management at air-

ports. They offer five different models for the management of slot-allocation at airports that also in-

clude methods for implementation. The models encompass a variety of instruments and rules to dis-

tribute the slots to airlines.

- Lei et al. (2008) provide a mathematical model for the investigation of the operational performance

of container shipping scheduling under three different management policies.

- Solutions for the chemical batch production are introduced by Pinto and Grossmann (1995) and

Sundaramoorthy and Karimi (2005). The author’s present mathematical models for the solving of

scheduling problems in multistage batch-plants using time slots for batch order release.

- Leeuwaarden et al. (2006) propose a scheduling model for the data transfer in cable networks,

which distinguishes between arrival and departure slots.

- A slot planning model for manufacturing processes is proposed by Barták (2000a). The approach

can cope with resource, transition and dependency constraints. The orders are released and sche-

duled by a dynamic algorithm. The goal of constraint satisfaction is to find a set of variables that

will satisfy a set of limiting factors.

In general, slots are like empty shells and organized around the resource (Barták 2000b). During sche-

duling, these shells are filled with one or more activities. These orders can be described with start time,

end time and duration. A scheduling model for mechanical engineering products is described by Becker

and Beckmann (2008) and shown in figure 6. Based on a simulation model, which is able to estimate the

workload of future orders at the bottleneck by their functional description, a slot plan for next period is

designed. It is important to notice, that bottlenecks in slot planning can be identified in several dimen-

sions, e.g. workload, space or machine functionality. This slot plan contains several slots, grouped by

product type, which can be filled with customer orders. The slots are filled by the sales department. To

meet the customer due date, the sales department has to schedule backwards and to fill the certain slot,

so that the bottleneck can synchronize his delivery date with the customer due date. Further, the order

start time is computed with a backward scheduling from the bottleneck resource. The main focus of the

slot model is to meet the customer due date for a certain order under consideration of special customer

characteristics.

Figure 6: Slot Planning Model for Manufacturing (Becker & Beckmann, 2008).

It is obvious, that the slot planning model has some similarities with the DBR approach. Unlike DBR

the slot model is not operating with buffers, especially without a shipping buffer. This is not possible, if

the orders are customer individual. Moreover, the slot model operates without a detailed schedule at the

bottleneck. The slots can be compared to shells with a standardized size of capacity. The order is usually

smaller or equal to the slot size, but in most of the cases not at the exact size. The reason is here also the

customer individuality of every order, which creates variances in every workload. The slot model tries

to cope with these variances by standardizing workload slots. Nevertheless, it has never been attempted

Customer

Slot

Sales

Simulation

Bottleneck

Legend:

DeliveryDate

Slot Plan

Customer Due Date

Page 13: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 13

Bottleneck-based synchronization of engineering and manufacturing

to apply these slot models to engineering processes. Slot planning can be described with following me-

thod characteristics (MC):

1. The objective (MC1b) of slot planning is to fulfill the delivery dates of the customers.

2. The approach shows no explicit buffer management (MC2b), but the attempt to meet all delivery

dates implies keeping buffers as low as possible to achieve a short throughput time.

3. The scheduling (MC3b) is roughly based on the estimation of process times, because slots are only

reserved and standardized shells for orders and not a detailed plan.

4. The objective of an order is to pass the bottleneck resource (MC4b) until a well defined moment,

so idle capacity on the bottleneck is accepted. Bottlenecks are determined in several dimensions, not

only as a capacity bottleneck.

5. Non-bottleneck resources (MC5b) in the slot planning are scheduling based on the slot of the bot-

tleneck. This should ensure a good conformity to the slot at the bottleneck and the delivery date of

the customer.

Applicability of Bottleneck Management in Engineering

The next section evaluates, if the bottleneck approaches from above are applicable to synchronize engi-

neering and manufacturing in the case of an engineering bottleneck. To achieve this, the process charac-

teristics are mapped against the methods characteristics.

Drum Buffer Rope system for engineering processes

The drum buffer rope approach provides a bottleneck-oriented order release solution. It has to be eva-

luated, if this solution could be applicable to engineering processes. Therefore, the described process

and method characteristics are compared:

1. The objective of the drum buffer rope approach is to achieve as much throughput as possible, whe-

reas throughput is defined as goods, which are sold to the customer. Engineering processes are aim-

ing at the same objective, due to fulfilling customer demand under consideration of time and specific

requirements. Both process and method try to satisfy as much customer orders as possible. In the

case of engineering processes, throughput can be understood as properly finished and from the cus-

tomer accepted engineering projects. Therefore drum buffer rope systems are aiming at the same ob-

jective as engineering processes.

2. For projection of process variations, drum buffer rope is relying on a sophisticated buffer manage-

ment. However, engineering processes are service processes, mostly creative transformation of cus-

tomer requirements into specifications. Service processes are usually carried out in direct coopera-

tion with process stakeholders, like customers or suppliers, and intangible. It is a characteristic of

services, that they are not storable and mostly customer individual. It is therefore not possible to

have a shipping buffer to protect the meeting of delivery dates. As the duration and workload of en-

gineering projects have considerable variations, a proper control of the buffer is difficult. The buffer

management of drum buffer rope can probably not be implemented to engineering processes.

3. Drum buffer rope requires a detailed scheduling on the bottleneck resource. The planning of engi-

neering processes is usually not able to provide that data, because of the uncertainty in the input in-

formation. Up to now, several scheduling methods for engineering projects have been developed,

but they consider only estimated workload and capacity. It would be therefore difficult for engineer-

ing processes to provide the necessary information for drum buffer rope.

4. The bottleneck resource in drum buffer rope sets the pace for order release and bottlenecks are

identified by comparison of workload and capacity. Bottlenecks in engineering can appear due to in-

sufficient capacity, expertise or information. The lack of expertise is up to now not considered with-

Page 14: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 14

Bottleneck-based synchronization of engineering and manufacturing

in the drum buffer rope approach. Nevertheless, if the bottleneck is identified, it will be possible for

the bottleneck resource to set the pace for new order release.

5. Non-bottleneck resources in drum buffer rope processes must have enough idle capacity to ensure

a quick processing in this process steps. To meet these criteria in engineering processes, capacity, in-

formation and expertise must be available at a sufficient level.

Only the objective of DBR Systems seems to be suitable for engineering processes. However, the con-

trol of buffers, the detailed schedule requirement and the identification of capacity bottlenecks are not

adequate for bottleneck management in engineering. For application of DBR to engineering, the method

must be adopted for these specific processes. In that case, the idea to orientate the new order release on

the pace of bottleneck, here engineering, can provide a good orientation to engineering companies.

Slot planning for engineering processes

The slot planning solution combines a multi-dimensional bottleneck approach with a control loop for

new order release. In a second step, the slot planning is evaluated regarding his applicability on engi-

neering processes:

1. The slot planning approach has the objective to fulfill customer orders in time. Finishing the order

in time would mean that all other specific requirements are also met. This corresponds to the objec-

tive of engineering process, which aims to meet all the customer requirements punctually. Therefore

slot planning is a solution to achieve the objective of engineering processes.

2. Buffer management is not an explicit part of slot planning, but the throughput time should be mi-

nimal to ensure a low average tardiness of all orders. This implies minimal buffers before the work

stations. As engineering projects are services and therefore not storable, a process without an expli-

cit buffer management is suitable for processing. However, the documentation of engineering

projects can be stored for knowledge management to reuse previous parts in further projects.

3. Slot planning provides a rough scheduling approach. Every order or activity is placed in a shell with

an estimated size. The size of the shell can be compared to an amount of free capacity. The size of

the workload should not be bigger than this amount. The workload of engineering order is difficult

to plan, due to its creative element in the engineering process. This leads to the rough estimation of

workloads. If this estimation is compared to the shells in slot planning, a certain slot for every engi-

neering order could be reserved.

4. Bottleneck resources in engineering can appear due to different reasons; insufficient capacity, ex-

pertise or information. All this causes impede the processing of engineering orders and bottlenecks

must therefore be identified in more than the capacity dimension. Slot planning offers the possibility

of identifying bottlenecks in more than the capacity dimension. However, slot planning has never

been applied to engineering processes and therefore expertise or information bottlenecks are not

considered. For a proper application, the slot planning approach has to be expanded and slots should

contain expertise and information dimension, as well.

5. Non-bottleneck resources in engineering must have the necessary capacity, expertise and informa-

tion to process the engineering orders. According to slot planning, all these must be timely available.

The point in time is oriented on the slot at the bottleneck resource. The procedure for capacity plan-

ning is well known from production planning. To apply this approach to engineering the flow of in-

formation and the capacity in the form of expertise must be incorporated in the scheduling model.

The objective, buffer management and scheduling approach of slot planning is suitable with the charac-

teristics of engineering processes. However, the identification of bottlenecks, even it is already multi-

dimensional, has never been applied to engineering processes. The bottleneck identification has to be

expanded to consider expertise, personal skill and the availability of information. Therefore, the engi-

neering planning and control system must be enhanced with these parameters.

Page 15: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 15

Bottleneck-based synchronization of engineering and manufacturing

Discussion

The application of bottleneck management approaches from production in engineering is difficult to

realize. Basic ideas, like the orientation on the bottleneck resource, should be adopted. It is possible to

detect capacity bottlenecks. If capacities and workload are properly planned and controlled in a multi-

project environment, the slot planning method is a possible solution to synchronize engineering and

manufacturing in a common bottleneck approach. However, only a comparison of workload and capaci-

ty is not sufficient. Engineering, as an information transformation process, needs more parameters. In

this sense, the raw materials of engineering are information. To transform this information into proper

specification, which describes a product, system or process, the necessary capabilities for engineering

tasks are also required. Hence, an exclusive capacity consideration is not enough. The planning and con-

trol of engineering, as well as the bottleneck approach has to incorporate a particular solution for the

treatment of personal skills and expertise of the engineers. However the idea of managing bottlenecks in

engineering like bottlenecks in production is worth to think about.

In general, it can be assumed to treat engineering processes with principles from production. Thus engi-

neering can be considered as a job shop. This is particularly important for companies who have a have

different organization in manufacturing, compared to engineering. As production has mostly less staff

with highly sophisticated expertise, the different characteristics have to be taken into account for a suc-

cessful application of production management principles. This applies especially for the resource man-

agement in engineering, which is very important to achieve higher productivity and efficiency to handle

the bottleneck of engineers. As production has gained great experience in the field of bottleneck-

oriented planning, scheduling and control, optimization and bottleneck management in general, the ap-

plicability of these approaches in engineering must be investigated. First attempts with lean principles

(Adler et.al. 1996) and Just in Time (Wildemann 1994) were very promising. Engineering Managers

should pay attention to the principles of production management to benefit from existing experience, es-

pecially in the field of productivity improvement.

Concluding remarks

In summary, this paper outlines the idea of ongoing research to manage bottlenecks in engineering like

bottlenecks in manufacturing. Therefore, two methods (Drum Buffer Rope and slot planning) are dis-

cussed. Both of them have never been applied to engineering and it is questionable, if it is possible

without adjustments. Nevertheless, engineering processes have to be more productive, because a capaci-

ty expansion is not possible. The reason lies in the shortage of skilled engineers in Germany and a relax-

ation of situation cannot be expected for the future. For not deteriorating the competitive advantage of

engineering companies, the engineering process has to be managed more systemically according to the

system constraints. This would be first step to align the German mechanical engineering companies on

the real bottleneck of the system – the scarce engineering resources. Therefore the research project “en-

gineerproduktiv” is applied to the German Ministry of Education and Research. The objective of the

project is the development of a systematic and software based bottleneck management in engineering

and production. The first step is to prove the three hypotheses, mentioned above. The project draws a lot

of attention in industry and the consortium consists of three universities, three mechanical engineering

companies and two software houses. The project start is expected for summer 2010.

The discipline of production management has gained a tremendous amount of experience in productivity

enhancement in general, beyond bottleneck management. This knowledge should be investigated for

application in engineering processes. The chances and boundaries of these concepts in engineering must

be evaluated. The objective of further research would be to investigate the relationship of product archi-

tecture, engineering and manufacturing. This would help to find an appropriate organization structure

Page 16: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 16

Bottleneck-based synchronization of engineering and manufacturing

for the engineering department. A further thinkable analogy is the cost management of production,

where activity based costing could be applied to engineering processes. The idea of developing a work

preparation function for engineering could also be very promising. The work preparation today supports

the manufacturing process by creating more transparency. This enables a better planning and control of

manufacturing process, even if they have unique character. A similar function for engineering could

provide better planning data and would enable a more accurate control. A further aspect to examine is

the load-oriented resource allocation, which means to release only as much orders as can be processed in

a certain period and achieve therefore a minimum lead time. However, this presumes an accurate trans-

parency in the capacities of the engineering process. Sometimes it is difficult to differentiate the engi-

neering workload, because the documentation of workload is not very disciplined. This shows the poten-

tial for drawing analogies from production management to engineering processes and will be the starting

point of new research initiatives.

Acknowledgements

We would like to thank Mitchell Smith for his assistance in literature research and proof reading of the

conference paper.

References

Abele, E., Kluge, J. & Näher, U., 2006. Handbuch Globale Produktion 1. Aufl., Hanser Fachbuchver-

lag.

Adler, P. u. a., 1996. Getting the most out of your product development process. Harvard Business Re-

view, (March), 134 - 152.

Asbury, J., 1995. Overview of Focus Group Research. Qual Health Res, 5(4), 414-420.

Bartak, R., 2000a. A Slot Representation of the Resource-Centric Models for Scheduling Problems. In

Proceedings of ERCIM Working Group on Constraints/CompulogNet Area on "Constraint Program-

ming" Workshop. Padova.

Bartak, R., 2000b. Slot Models for Schedulers Enhanced by Planning Capabilities. In Proceedings of the

Nineteenth Workshop of the UK Planning and Scheduling Special Interest Group (PlanSIG). Milton

Keynes, S. 1 - 13.

Becker, K. & Beckmann, A., 2008. Slot-Planung in der variantenreichen Einzelfertigung. Zeitschrift für

wirtschaftlichen Fabrikbetrieb, 103(11), 809 - 813.

Berkermann, U., Eckert-Kömen, J. & Nemarnik, N., 2009. Maschinenbau 2020: Globaler Markt - mit-

telständische Strukturen, IKB.

Betterton, C.E. & Cox III, J.F., 2009. Espoused drum-buffer-rope flow control in serial lines: A compar-

ative study of simulation models. International Journal of Production Economics, 117(1), 66-79.

Blackstone, J., 2008. APICS Dictionary - 12th Edition 12. Aufl., APICS - The Association for Opera-

tions Management.

Bromberg, T., 2007. Engineering-Dienstleistungen in der Automobilindustrie: Verbreitung, Kooperati-

onsformen und arbeitspolitische Konsequenzen, Dortmund: Universität Dortmund.

Bullinger, H. & Warschat, J., 1997. Forschungs- und Entwicklungsmanagement 1. Aufl., Teubner Ver-

lag.

Page 17: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 17

Bottleneck-based synchronization of engineering and manufacturing

Chang, C.M., 2004. Engineering Management: Challenges in the New Millennium illustrated edition.,

Prentice Hall.

Chang, T. u. a., 1994. Conceptual robustness in simultaneous engineering: An extension of Taguchi's

parameter design. Research in Engineering Design, 6(4), 211-222.

Chen, C. & Chen, C., 2009. A bottleneck-based heuristic for minimizing makespan in a flexible flow

line with unrelated parallel machines. Computers & Operations Research, 36(11), 3073-3081.

Ching, S., Meerkov, S.M. & Zhang, L., 2008. Assembly systems with non-exponential machines:

Throughput and bottlenecks. Nonlinear Analysis: Theory, Methods & Applications, 69(3), 911-917.

Coates, G. u. a., 2004. Engineering management: operational design coordination. Journal of Engineer-

ing Design, 15(5), 433-446.

Cooper, R.G., 1990. Stage-gate systems: A new tool for managing new products. Business Horizons,

33(3), 44-54.

Crabtree, R.A., Fox, M.S. & Baid, N.K., 1997. Case studies of coordination activities and problems in

collaborative design. Research in Engineering Design, 9(2), 70-84.

Dammer, H., 2008. Multiprojektmanagement, Wiesbaden: Betriebswirtschaftlicher Verlag Dr.Th. Gab-

ler / GWV Fachverlage GmbH, Wiesbaden.

Dekkers, R., 2006. Engineering management and the Order Entry Point. International Journal of Pro-

duction Research, 44, 4011-4025.

DIN ISO 9000, 2005. DIN EN ISO 9000 - Grundlagen und Begriffe (ISO 9000:2005). In Qualitätsma-

nagementsysteme. Berlin: Beuth Verlag GmbH, S. 22 - 25.

Dyckhoff, H., 2007. Produktionswirtschaft 2. Aufl., Berlin, Heidelberg: Springer-Verlag Berlin Heidel-

berg.

Eversheim, W., Pollack, A. & Walz, M., 1994. Auch Entwicklungsprozesse sind planbar. VDI-Z,

136(6), 78 - 83.

Färber, U., Kuppinger, R. & Löllmann, P., 2002. Das 3Liter-PPS Konzept: Die richtige Dosis PPS für

Kundenauftragsfertiger. wt Werkstatttechnik online, Jahrgang 92(5), 242 - 247.

Franke, R. u. a., 2009. Governance und Strategische Steuerung der Produktentwicklung, Berlin: Bearing

Point.

Fricke, S. & Shenbar, A., 2000. Managing multiple engineering projects in a manufacturing support en-

vironment. Engineering Management, IEEE Transactions on, 47(2), 258-268.

Gehrig, M. & Fritschi, T., 2008. Ingenieurmangel in der Schweiz und im Kanton Graubünden.

Goldratt, E., 1994. Theory of Constraints 1. Aufl., Gower Publishing.

Goldratt, E.M., 1997. Critical Chain, Gower Publishing Ltd.

Page 18: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 18

Bottleneck-based synchronization of engineering and manufacturing

Goldratt, E. & Cox, J., 2004. The goal: A process of ongoing improvement 3. Aufl., Great Barringtion:

The North River Press.

Grein, G., 1997. Wissensbasierte Kapazitäts-/ Terminplanung von Konstruktionsprozessen. Karlsruhe.

Gutenberg, E., 1976. Grundlagen der Betriebswirtschaftslehre 22. Aufl., Berlin Heidelberg New York:

Springer Verlag.

Haberlandt, K., 1999. PPS-Anforderungen bei Werkstattfertigung. PPS Management, 4(3), 47 - 52.

Handfield, R.B., 1994. Effects of concurrent engineering on make-to-order products. IEEE Transactions

on Engineering Management, 41(4), 384-393.

Hörnig, B. & Gittmann, M., 2006. Wirtschaftsfaktor Konstruktion. Ungenutzes Potential im Enginee-

ring, München: Autodesk Deutschland GmbH.

Juran, I. u. a., 2009. A dynamic traffic assignment model for the assessment of moving bottlenecks.

Transportation Research Part C: Emerging Technologies, 17(3), 240-258.

Keegan, A. & Turner, J.R., 2002. The Management of Innovation in Project-Based Firms. Long Range

Planning, 35(4), 367-388.

Koppel, O., 2009. Ingenieurmangel in Deutschland - Ausmaß und gesamtwirtschaftliche Konsequenzen,

Köln: Verein deutscher Ingenieure.

Krebs, S., 2007. Ingenieure im Maschinen- und Anlagenbau, VDMA.

Krebs, S., 2008. Kennzahlen zu Forschung und Innovation im Maschinenbau, VDMA.

Krueger, R.A., 2008. Focus Groups: A Practical Guide for Applied Research 4. Aufl., Sage Publicati-

ons.

Kunz, C., 2007. Strategisches Multiprojektmanagement 2. Aufl., Wiesbaden: Deutscher Universitäts-

Verlag | GWV Fachverlage GmbH, Wiesbaden.

van Leeuwaarden, J., Denteneer, D. & Resing, J., 2006. A discrete-time queueing model with periodi-

cally scheduled arrival and departure slots. Performance Evaluation, 63(4-5), 278-294.

Lei, L. u. a., 2008. Collaborative vs. non-collaborative container-vessel scheduling. Transportation Re-

search Part E: Logistics and Transportation Review, 44(3), 504-520.

Leyndekker, H., 2000a. Die Konstruktion ist nur Teil der Prozesskette. VDMA Maschinenbau Nachrich-

ten, 01.

Leyndekker, H., 2000b. Leistungsmessung in der Konstruktion - ein Dilemma? VDMA Maschinenbau

Nachrichten, 38.

Leyndekker, H., 2000c. Probieren geht über Studieren. VDMA Maschinenbau Nachrichten, 48.

Page 19: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 19

Bottleneck-based synchronization of engineering and manufacturing

Leyndekker, H., 2000d. Termintreue in der Konstruktion messen - aber wie? VDMA Maschinenbau

Nachrichten, 35.

Leyndekker, H., 2000e. Was leistet die Konstruktion. VDMA Maschinenbau Nachrichten, 42.

Leyndekker, H., 2000f. Was macht die Konstruktion. VDMA Maschinenbau Nachrichten, 46.

Leyndekker, H., 2000g. Wie kann die Innovation und Kreativität in der Konstruktion bewertet werden?

VDMA Maschinenbau Nachrichten, 38.

Lödding, H., 2008. Verfahren der Fertigungssteuerung: Grundlagen, Beschreibung, Konfiguration 2.

Aufl., Springer, Berlin.

Madas, M.A. & Zografos, K.G., 2006. Airport slot allocation: From instruments to strategies. Journal of

Air Transport Management, 12(2), 53-62.

Maravelias, C.T. & Sung, C., 2009. Integration of production planning and scheduling: Overview, chal-

lenges and opportunities. Computers & Chemical Engineering, 33(12), 1919-1930.

Meffert, H., 2000. Marketing 9. Aufl., Dr. Th. Gabler Verlag.

Meier, H. & Hanenkamp, N., 2003. Modellierung und Planung komplexer Produktionsysteme. Indu-

striemanagement, (5), 50 - 53.

Miyashita, K. & Rajesh, G., 2010. Multiagent coordination for controlling complex and unstable manu-

facturing processes. Expert Systems with Applications, 37(3), 1836-1845.

Mönch, L. & Zimmermann, J., 2007. Simulation-based assessment of machine criticality measures for a

shifting bottleneck scheduling approach in complex manufacturing systems. Computers in Industry,

58(7), 644-655.

Moore, R. & Scheinkopf, L., 1998. Theory of Constraints and Lean Manufacturing: Friends of Foes?.

Nyhuis, P., 2008. Beiträge zu einer Theorie der Logistik 1. Aufl., Springer, Berlin.

Nyhuis, P. & Wiendahl, H., 2003. Logistische Kennlinien: Grundlagen, Werkzeuge und Anwendungen,

O'Connor, P.D.T., 1994. The Practice of Engineering Management: A New Approach, John Wiley &

Sons Ltd.

OECD, 2008. Deutschland verliert bei Ausbildung von Hochqualifizierten international weiter an Bo-

den. OECD Pressemitteilung.

Rajendran, C. & Alicke, K., 2007. Dispatching in flowshops with bottleneck machines. Computers &

Industrial Engineering, 52(1), 89-106.

Rand, G.K., 2000. Critical chain: the theory of constraints applied to project management. International

Journal of Project Management, 18(3), 173-177.

Rook, D.W., Stewart, D.W. & Shamdasani, P.N., 2006. Focus Groups: Theory and Practice 2. Aufl.,

Sage Publications.

Page 20: BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING … · BOTTLENECK-BASED SYNCHRONISATION OF ENGINEERING AND MANUFACTURING ... Bottlenecks, Drum Buffer Rope, ... is assured by placing

International Association for Management of Technology

IAMOT 2010 Proceedings

Johannes Hinckeldeyn; Rob Dekkers; Nils Altfeld; Jochen Kreutzfeldt 20

Bottleneck-based synchronization of engineering and manufacturing

Schultheiss, J. & Kreutzfeldt, J., 2009. Performance improvement in production systems through prac-

tice-oriented bottleneck management. In Proceedings of the 4th European Conference on Technology

Management. Glasgow, S. 1 - 20.

Slack, N., Chambers, S. & Johnston, R., 2006. Operations Management 5. Aufl., FT Prentice Hall.

Stewart, W.T. & Calloway, R.J., 1982. Engineering productivity: The management of improvement.

Engineering Management International, 1(2), 109-116.

Steyn, H., 2002. Project management applications of the theory of constraints beyond critical chain

scheduling. International Journal of Project Management, 20(1), 75-80.

Sundaramoorthy, A. & Karimi, I., 2005. A simpler better slot-based continuous-time formulation for

short-term scheduling in multipurpose batch plants. Chemical Engineering Science, 60(10), 2679-2702.

Tracht, K., 2001. Planung und Steuerung des Werkzeug- und Formenbaus auf Basis eines integrierten

Produktmodells. Hannover.

UNCTAD, 2008. UNCTAD Handbook of Statistics, United Nations Pubn.

Wheelwright, S.C. & Clark, K.B., 1992a. Competing through development capability in a manufactur-

ing-based organization. Business Horizons, 35(4), 29-43.

Wheelwright, S.C. & Clark, K.B., 1992b. Creating project plans to focus product development. Harvard

Business Review, 1 - 14.

Wei, C., Liu, P. & Tsai, Y., 2002. Resource-constrained project management using enhanced theory of

constraint. International Journal of Project Management, 20(7), 561-567.

Westkämper, E., 2005. Einführung in die Organisation der Produktion 1. Aufl., Springer, Berlin.

Wiendahl, H. & Nyhuis, P., 1998. Engpaßorientierte Logistikanalyse : Methoden zur kurzfristigen Leis-

tungssteigerung in Produktionsprozessen, München: TCW Transfer-Centrum.

Wildemann, H., 1994. Just-in-time in F & E : Leitfaden zu JIT in Forschung & Entwicklung und Kon-

struktion 2. Aufl., München: TCW Transfer-Centrum.

Wildemann, H., 2003. Vorhersage von Entwicklungszeiten. Industriemanagement, 19(1), 68 - 71.

Yassine, A. & Braha, D., 2003. Complex Concurrent Engineering and the Design Structure Matrix Me-

thod. Concurrent Engineering, 11(3), 165-176.