Transcript of Bond Construction Update Citizens Oversight Committee Long Beach Community College District April...
![Page 1: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/1.jpg)
Bond Construction Bond Construction UpdateUpdateCitizens’ Oversight Citizens’ Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdateCitizens’ Oversight Citizens’ Oversight CommitteeCommittee
Long Beach Community College DistrictApril 21, 2008
BUILDING TOMORROW TODAY
Cordoba Corporation
![Page 2: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/2.jpg)
Agenda Completed Construction Projects Current & Upcoming Construction Projects
South Quad Complex Structure LAC Central Plant Structure LAC Learning Resources Center – Structure LAC Building A, Student Services Retrofit PCC Central Plant PCC Learning Resources Center PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Administration Building)
Q & A
![Page 3: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/3.jpg)
Construction Progress
![Page 4: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/4.jpg)
Completed Construction Projects
PCC Industrial Technology Center Phase 2 – 7/07
PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07
LAC/LRC Interim – 5/07 East Campus Demo – 12/06 LAC Men’s Gym Façade
Replacement (FEMA & Insurance Funded) – 8/06
LAC/LRC Utilities – 6/06 PCC CDC – 4/06 Men’s Gym Boiler
Replacement – 4/06 LAC Athletic Field – 3/06 District Facilities &
Warehouse Complex – 1/06
Various Projects – Completed in 2006 & 2007Various Projects – Completed in 2006 & 2007
![Page 5: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/5.jpg)
LAC Facility Site Plan
l i b
e r
a l
a r
t s
![Page 6: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/6.jpg)
Current and UpcomingConstruction Projects
Part of Infrastructure Master Plan Improvements
Awarded to Siemens on DBOM Contract
Construction 82% Complete Completion Anticipated
Summer 2008
LAC Central Plant – StructureLAC Central Plant – Structure
![Page 7: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/7.jpg)
Current and UpcomingConstruction Projects
Construction 55% Complete
Combined into Single Construction Phase
Completion Anticipated December 2008
LAC/Learning Resources Center – StructureLAC/Learning Resources Center – Structure
![Page 8: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/8.jpg)
Current and UpcomingConstruction Projects
Construction Approx. 52% Complete
Additional Modern Classrooms, Multi-purpose Rm., Offices, etc.
Shifts Campus Center South of Carson off Lew Davis
Completion Anticipated December 2008
South Quad Complex Structure (Bid Pkg. #3)South Quad Complex Structure (Bid Pkg. #3)
![Page 9: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/9.jpg)
Current and UpcomingConstruction Projects
Martinez Architects received Board Approval as the Architect of Record
Contract was negotiated/signed and Notice to Proceed was issued
Programming work began on April 10, 2008
LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
![Page 10: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/10.jpg)
PCC Facility Site Plan
p a
c i f
i c
c
o a
s t
![Page 11: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/11.jpg)
Current and UpcomingConstruction Projects
Part of Infrastructure Master Plan Improvements
Early Utility Package Construction Complete
DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations
Construction Approximately 36% Complete
Completion Anticipated Summer 2008
PCC Central PlantPCC Central Plant
![Page 12: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/12.jpg)
Current and UpcomingConstruction Projects
Construction 78% Complete Modern Facility with
Computer Lab and Multimedia
New Facility Bridge to Bldg. EE Completion Anticipated
July/August 2008
PCC Learning Resources CenterPCC Learning Resources Center
![Page 13: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/13.jpg)
Current and UpcomingConstruction Projects
Replaces Existing Antiquated Structures
Construction is 12% Complete
Modern Facility Houses Machine Tool and Welding Departments
New Northern Face of the Campus
Completion Anticipated Spring 2009
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
![Page 14: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/14.jpg)
Current and UpcomingConstruction Projects
Programming is completed and submitted to the State for Approval
Schematic Design was completed in February 2008
PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) (Multi-Disciplinary Academic Building)
![Page 15: Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.](https://reader036.fdocuments.net/reader036/viewer/2022070306/551659ed550346c6758b5d20/html5/thumbnails/15.jpg)
QUESTIONS & ANSWERS
Prepared byBond Management Team
April 21, 2008