BOMA BC – Market Insights
Accelerating success.
Whole Building Retrofits
Presented By: Jim MacKenzie
Colliers Global Coverage
United States125 offices3,800 employees260M SF managed24,000 sale/lease transactions
Canada36 offices1,400 employees47M SF managed4,200 sale/lease transactions
Asia32 offices2,000 employees374M SF managed4,500 sale/lease transactions
Europe/The Middle East/Africa 117 offices2,600 employees156M SF managed9,300 sale/lease transactions
What’s Driving Whole Building Retrofits
> Building inventory in Lower Mainland approaching 25 – 40 years
> Older buildings relied on central plant design• More robust, less efficient equipment exceeding anticipated life• Resulted in deferred capital upgrades• Upgrades may be co-dependent and impact other systems
> Results: Many original systems still in operation with minimal upgrades
> Opportunity for full building review as equipment begins to fail
What Are Clients Most Interested In?
> Reducing vacancy
> Reducing operating costs
> Positioning property as sustainable
> Don’t want to spend exorbitant consulting fees
> Want their Property Manager to be advocates for sustainability
> Don’t want to be subservient to technology
> Want to manage and reduce capital
Understanding Clients Objectives
> Need to understand owners investment objectives and horizon
> Building retrofit and paybacks need to be planned with investment horizon in mind - Future redevelopment
- 1 to 5 years – short term (integrate sustainability into operations)- 5 to 10 years – medium (individual upgrades)- 11+ years - long term (whole building retrofits)
> Don’t propose lengthy payback or high capital if investment horizon is short term
> Balance upgrades within existing capital budget and amortization schedules
Colliers Sustainability Services
> Green Building Assessment - a pre-feasibility screening tool
> Comprehensive survey of all aspects of sustainability - Energy- Water- Indoor air quality- Tenant satisfaction- Operating policies and practices
Provides a high level assessment of how a property aligns with industry standards
- BOMA BESt- LEED
> Generates a summary of initiatives that can be implemented in accordance with owners objectives
> Content used to develop asset management plan and strategy
OpportunitiesBlend projects with high and low payback.
HVAC – Enthalpy control
Measurement and Verification> Monitor and share utility consumption with building operators
Tenant Improvement Criteria> Design electrical distribution to accommodate sub metering> Segregate domestic hot water loads for tenants> Data centre cooling loop> Recapitalize systems during tenant improvements
Lighting> Do test areas to establish similar levels prior to retrofit> Adjust levels using ballast factors> Anticipate power factor correction> Reduction in heat load> PCB’s
Tenant Engagement> Blinds, lights, office equipment, etc.
ChallengesCommissioning> Operating deficiencies identified but not resolved during construction
Cradle to Grave > technology becoming obsolete before reaching end of amortization period
Tenant Training> Tenants tampering with improvements (lighting, air balancing, HVAC settings)
Variable Frequency Drives> Induced magnetic bearing failure
Low flush toilet & waterless urinals > Source of tenant frustration > Horizontal distance from risers> Increased maintenance & odors
Green Landscaping> No pesticide and herbicide alternatives resulting in higher maintenance costs
Tenant Leases> Leases which exempt the recovery of capital, where tenants benefit from cost savings
Case Study 1 - Building Recomissioning
Property Overview> 105,000 SF> Downtown Vancouver office space> Managed by Colliers for 12 years
Challenge> Major tenant had expanded their premises – new space significantly increased the
density of occupants > Comfort and energy costs immediately increased
Solution> Initiated a review of energy use in the property > Recognized that the programming of the Direct Digital Controls system no longer
matched the change in occupancy and use of building> Recomissioned the Direct Digital Controls system and verified operation and split range
of valves
Results> Improved comfort throughout the building> Energy consumption for heating reduced by 26% resulting in 2 month payback
Case Study 2 – Energy Analysis
Property Overview> Client portfolio of 10 properties> Located in Toronto downtown core
Challenge> Higher than market energy intensity
Services> Utilized energy management database to measure, report and target
Results> Identified opportunities to reduce energy spend by approximately $1,000,000
across portfolio, which included, optimal start and stop in relation to occupancy, temperature reset, and energy retrofits.
Case Study 3 – Whole Building Retrofit
Property Overview – The Good Earth Building> 112,127 SF> Downtown Vancouver tier B office space> Whole building retrofit - 2006
Challenges> Existing building systems reaching end of useful life> Higher than average energy costs> Limited HVAC control
Solution> Energy study> Whole building retrofit
Case Study 3 – Whole Building Retrofit
ORIGINAL SYSTEMSBoilers> Natural Draft> Low efficiency> Heat exchanger failure> Primary loop with no hot water reset
Chiller> R-11 – not cost effective to convert> Approximately 30% oversized > Insufficient part load capacity> No redundancy> False loaded through makeup air heating coil
Cooling Tower> End of life> Low/high speed fan operation> Piping design issue
Case Study 3 – Whole Building Retrofit
ORIGINAL SYSTEMSLighting> T-12 – magnetic ballasts> Some ballasts with PCB’s> No lighting control system
Controls> Pneumatic> DDC restricted to time clock function> No chilled water control valves on floor fans> Only means of temperature control to reset chiller set point
Ventilation> No free cooling capability> VAV boxes had no minimum ventilation levels set> Duct static damper control
Case Study 3 – Whole Building Retrofit
NEW SYSTEMSBoilers> High efficiency – condensing boilers> Primary secondary loop with hot water reset> Redundancy
Chillers> Modular chillers with redundancy > Capacity matched to part and full load > Chilled water reset
Cooling Tower> New cooling tower with variable frequency drive> Plate exchanger installed for free cooling
Case Study 3 – Whole Building Retrofit
NEW SYSTEMSControls> Lighting controls – floor by floor> DDC Systems for primary systems> Chilled water control to air handling units> Variable speed drives and high efficiency motor for air handling units> Variable speed pumping> Reset and calibrated VAV boxes
Lighting> T-8 lamps & electronic ballasts
Results> Simple payback in 12.9 years> 32% reduction in energy costs> 618 tons of CO2 equivalent per year reduction