BOC Cryogenic Vessels-1

download BOC Cryogenic Vessels-1

of 48

Transcript of BOC Cryogenic Vessels-1

  • 7/30/2019 BOC Cryogenic Vessels-1

    1/48

    WELCOME ALL

    By

    Production Team

  • 7/30/2019 BOC Cryogenic Vessels-1

    2/48

    Cryogenic

    Gas to liquid at sub (minus) temperature

    LIN/LOX/LAR

    Best e.g.. Jet fuel

    Heat transfer

    (conduction/convection/radiation)

    Methodology - vaccum insulation/thermalinsulation

  • 7/30/2019 BOC Cryogenic Vessels-1

    3/48

    Cryogenic Vessels

    VIST- Vaccum insulated storage tank

    VITT- Vaccum insulated transported tank

    VIET- Vaccum insulated evaporated tank

  • 7/30/2019 BOC Cryogenic Vessels-1

    4/48

    VIST- Vaccum insulated storage

    tank

  • 7/30/2019 BOC Cryogenic Vessels-1

    5/48

    VITT- Vaccum insulated

    transported tank

  • 7/30/2019 BOC Cryogenic Vessels-1

    6/48

    VIET- Vaccum insulated

    evaporated tank

  • 7/30/2019 BOC Cryogenic Vessels-1

    7/48

    Importance of the vessels

    service

    Process (gas formation/temp maint)

    Life timeCost

    Rework

  • 7/30/2019 BOC Cryogenic Vessels-1

    8/48

    Vessel orientation

    View from top

    Deg in clock wise direction view from top

    Deg in anti clock wise direction view frombottom

    If looking from Top view top dish is shape

    as a convex and bottom dish as aconcave.

  • 7/30/2019 BOC Cryogenic Vessels-1

    9/48

    Vessel orientation

  • 7/30/2019 BOC Cryogenic Vessels-1

    10/48

    View from bottom anti clock wise

    Pipe lines out

    Vaccum filter

    180 deg

    90

    deg

  • 7/30/2019 BOC Cryogenic Vessels-1

    11/48

    SS cleaning

    Initially apply Bondite Liquid and remove the

    yellow marks/stains by using SS wire brush

    After that Okite Liquid to be apply for protection

    Next Bondite Liquid to be apply once again, froth& Foam develops followed by scrubbing the

    stains using wire brush and wait for 15-

    20minutes.

    Finally wash the Stainless steel plate by Okite

    Liquid

  • 7/30/2019 BOC Cryogenic Vessels-1

    12/48

    SS cleaning

  • 7/30/2019 BOC Cryogenic Vessels-1

    13/48

    Patch plate fitup with vessel

    Bottom dish end with outer skirt fitupand welding can be done before patch

    plate assemble with inner vessel.

    Jacket dish end Assy fitup with innervessel.

  • 7/30/2019 BOC Cryogenic Vessels-1

    14/48

    Jacket Dish with Inner vessel

    assembly

    Tan line

  • 7/30/2019 BOC Cryogenic Vessels-1

    15/48

    Patch plate

    Patch plate fitup with jacket bottom dish

    end and the center line of the patch plate

    should be match with the bottom dish endcenter line i.e. 180 deg.

    Temporary attachment can be done

    between patch plate with jacket bottomdish end (in the form of cantilever ).

  • 7/30/2019 BOC Cryogenic Vessels-1

    16/48

    Patch plate with jacket dish

    assembly

    Both are should

    be in same axis

    Temporary

    support

  • 7/30/2019 BOC Cryogenic Vessels-1

    17/48

    Pipe support with inner vessel

  • 7/30/2019 BOC Cryogenic Vessels-1

    18/48

    Pipe support with inner vessel

  • 7/30/2019 BOC Cryogenic Vessels-1

    19/48

    Individual Pipe connection

    Pipe connection to be made with help of adaptor asshown in fig (socket type joint)

    If we want butt joint, we have to take 100% RT

    We should maintain 1.5mm 3mm gab between pipe

    and adaptor for thermal expansion Pipe with adaptor and ferrules Mock up to done before fit

    up& welding

    Assemble the pipe from both side of top dish end as well

    as patch plate. adjust the length of pipe andmarking/cutting to required size in shell length wise andalso marking/cutting the excess length of pipe from topdish end side.

  • 7/30/2019 BOC Cryogenic Vessels-1

    20/48

    Individual Pipe connection

  • 7/30/2019 BOC Cryogenic Vessels-1

    21/48

    Individual Pipe connection

  • 7/30/2019 BOC Cryogenic Vessels-1

    22/48

    Individual Pipe connection

    After complete the mock up clean the

    inside of both ferrules and pipe by DCE-

    dry chloride ethylene.

    Welding sequence of the pipe in fig

    Gap between Pipelines and Inner vessel

    should be 1 to 1.1/2

  • 7/30/2019 BOC Cryogenic Vessels-1

    23/48

    Individual Pipe connection

  • 7/30/2019 BOC Cryogenic Vessels-1

    24/48

    CLAMP FOR PIPE

  • 7/30/2019 BOC Cryogenic Vessels-1

    25/48

    Hydro test

    Vessel should be in Horizontal Position

    Inlet on flange connection pipe

    Slightly inclined the vessels during hydrotest

    For water Drain, all ferrrules should be in open condition Pressure gauge on N' at 180 degree and Drain on N at 0

    Mild steel ferrule for Dummy the threaded ferrules

    If Non-ferrous material is available, it is best.

    Proper insulation to be provide between MS and SS

    Air block to be remove from all pipes

  • 7/30/2019 BOC Cryogenic Vessels-1

    26/48

    Hydro test

    During hydrotest, vessel upclined

    During Drain, vessel Declined

  • 7/30/2019 BOC Cryogenic Vessels-1

    27/48

    Hydro test

  • 7/30/2019 BOC Cryogenic Vessels-1

    28/48

    Hydro test

  • 7/30/2019 BOC Cryogenic Vessels-1

    29/48

    N&N closing

    During hydro test, plug N & N' by tapping

    Taffelon tape

    After hydrotest, remove taffelon tape and

    weld.

  • 7/30/2019 BOC Cryogenic Vessels-1

    30/48

    Pneumatic test

    Pnuematic test to be done before N & N'

    welding

    Two Pressure Gauges

  • 7/30/2019 BOC Cryogenic Vessels-1

    31/48

    Jacket assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    32/48

    Jacket assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    33/48

    Jacket assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    34/48

    Jacket assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    35/48

    Jacket assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    36/48

    Jacket assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    37/48

    Evacuation Filter Assembly

    If we making continuous length pipe, we

    have to cut the Dummy end because of

    getting continuous hollow from end to end.

  • 7/30/2019 BOC Cryogenic Vessels-1

    38/48

    Vaccum Probe connection

    Vacuum probe pipe to be inserted in the

    Jacket Dish nearby half of its length.

  • 7/30/2019 BOC Cryogenic Vessels-1

    39/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    40/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    41/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    42/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    43/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    44/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    45/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    46/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    47/48

    Evacuation Filter Assembly

  • 7/30/2019 BOC Cryogenic Vessels-1

    48/48

    Evacuation Filter Assembly