Major Western Transmission Projects
Bob SmithDirector; Asset Management and Planning
Arizona Public Service Company
TransForum WestSan Diego, CAMay 6, 2014
Agenda
• APS Background
• APS Ten Year Transmission Plan
• Hassayampa – North Gila 500kV project
• Transmission Development within WestConnect
05/06/2014
APS Service Territories
05/06/2014
APS Service Statistics
• 11 counties
• 34,645 square miles CC&N area
• 1.1 million customers
• 424 substations
• 28,937 distribution line miles
• 5,434 transmission line miles
• 54 generation units
• Over 7200MW Peak load
05/06/2014
Youngs Canyon 345/69kV Substation (Dec. 2013)
Hassayampa-North Gila #2 500kV Line (2015)
Palo Verde-Delaney-Sun Valley 500kV Line (2016)
Mazatzal 345/69kV Substation (2017)
Morgan-Sun Valley 500kV Line (2018)
TS12 230/69kV Substation (2021)
05/06/2014
Palm Valley-Trilby Wash 230kV Line (2016)
Sun Valley-Trilby Wash 230kV Line (2016)
Scatter Wash 230/69kV Substation (2021)
05/06/2014
Hassayampa-North Gila 500kV
• By the Numbers– Line Miles
112– Tons of Lattice Steel 8,000– Tons of Tubular Steel 700– Miles of Cable
700– Cubic Yards of Concrete 5,000– Acres of Laydown Yards 100– Original Estimate $250M– Current Estimate $201M
05/06/2014
Progress - Material
05/06/2014
Progress - Substation
05/06/2014
Progress - Line
05/06/2014
WestConnect Planning Participants
Arizona Public Service Public Service New Mexico
Basin Electric Power Cooperative Sacramento Municipal Utility District
Black Hills Corporation Salt River Project
Colorado Springs Utilities Southwest Transmission Cooperative
El Paso Electric Transmission Agency of No. California
Imperial Irrigation District Tri-State G & T Association
Los Angeles Dept. of Water & Power Tucson Electric Power
NV Energy Western Area Power Administration
Platte River Power Authority Xcel Energy – Public Service Colorado
05/06/2014
Approximate WestConnect Planning Region
Current membership shown All entities are required to
sign the Planning Agreement to become a voting member
Footprint may change due to changes in membership
WAPA BHCSU PSCOPRPA BasinTSGT
WAPATSGTPNMBasin
EPE
WAPABHTSGTBasin
WAPASRPTEPAPSSWTC
Entities in blue text are public utility transmission providers that are required to comply with provisions contained within FERC Order 1000
WAPASMUDTANC
WAPANVE
WAPAIID
LADWP
05/06/2014
Western Interconnection
Regional Planning Entities
05/06/2014
2014 WestConnect Plan Summary
05/06/2014
Status of Projects No. Projects Total Miles Estimated Cost (B$)
Planned 199 6,418 $ 14.494
Conceptual 66 6,452 $ 12.085
2014 WestConnect Transmission Plan
05/06/2014
2014 WestConnect Transmission Plan
05/06/2014
2014 WestConnect Transmission Plan
05/06/2014
Major Transmission Projects in WestConnect
Name of Project Line Miles Voltage From To
Centennial West Clean Line 900 500 kV DC New Mexico California
Chinook Project 1000 500 kV DC Montana Nevada
Harcuvar Transmission Project 90 230 kV Arizona Arizona
High Plains Express Initiative 2500 500 kV Wyoming Arizona
Long View Energy Exchange 90 500 kV Arizona Arizona
Lucky Corridor Project 130 345 kV New Mexico New Mexico
North Gila – Imperial Valley #2 Project 85 500 kV Arizona California
Southline Transmission Project 240/120 345 kV/230 kV New Mexico Arizona
Southwest Intertie Project 339 500 kV Idaho Nevada
SunZia Southwest Transmission Project 500 500 kV New Mexico Arizona
TransWest Express 725 600 kV DC Wyoming Nevada
Tres Amigas Project 22 345 kV New Mexico New Mexico
Western Spirit Clean Line 200 345 kV New Mexico New Mexico
Wyoming-Colorado Intertie 180 345 kV Wyoming Colorado
Zephyr Project 950 500 kV DC Wyoming Nevada
05/06/2014
05/06/2014
Questions?