Bloomsburg University Council of Trustees Meeting
March 5, 2014
Campus Plan 2014
![Page 2: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/2.jpg)
Agenda
1 Campus Plan Final Recommendations
2 Implementation Alternatives
3 Implementation Timeline
![Page 3: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/3.jpg)
Final Recommendations
This plan is rooted in enrollment growth rather than time.
1
![Page 4: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/4.jpg)
1,000+ Number of additional students the facilities can accommodate if this plan is implemented.
![Page 5: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/5.jpg)
Facilities Impacts
![Page 6: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/6.jpg)
ACADEMICS
![Page 7: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/7.jpg)
New Waller Hall
New Academic on Quad
![Page 8: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/8.jpg)
ADMINISTRATION
![Page 9: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/9.jpg)
New President’s Residence
New Alumni / Gateway Center
New Waller Hall
Maintain Carver for Administration
![Page 10: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/10.jpg)
STUDENT LIFE
![Page 11: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/11.jpg)
New Student Union
New Dining at Swisher Village
![Page 12: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/12.jpg)
STUDENT HOUSING
![Page 13: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/13.jpg)
248 Minimum quantity of new beds needed to accommodate existing housing shortages.
![Page 14: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/14.jpg)
Projected Bed Shortages (assumes no new construction / renovation)
248 284
320 357
394 431
469 507
546 585
0
100
200
300
400
500
600
700
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Bed
Sho
rta
ge
Qua
ntity
Year
Projections based on existing bed quantities, no new construction, and 1% enrollment growth per year.
![Page 15: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/15.jpg)
New Swisher Village Housing
New Bookstore Housing
New Penn Village Housing
Renovate Montour
New West Village Apts.
New MPA Apts.
![Page 16: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/16.jpg)
ATHLETICS
![Page 17: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/17.jpg)
Recreation Field Upgrades
New Multipurpose Athletic Fields
Relocate Baseball Field
Relocate Track Throws
New Turf Field
Addition to Nelson Fieldhouse
New Air Structure & Fields
![Page 18: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/18.jpg)
OPEN SPACE
![Page 19: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/19.jpg)
West Village Quad
Swisher Village Quad
Penn Village Quad
Campus Gateway
![Page 20: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/20.jpg)
INFRASTRUCTURE
![Page 21: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/21.jpg)
New East Campus Parking Garage
Campus Loop Road
Ped. Bridge
Other Infrastructure Projects: • Lightstreet Road Intersection • Chiller Plants Lower Campus (east + west ends) • Modified Electrical Distribution to Upper Campus • Electrical Substation Replacement • Lower Campus Electrical Distribution Expansion • District Heating and Cooling on Upper Campus
New Facilities Maintenance Complex
Steam Plant Biomass CHP
Intersection Upgrade
![Page 22: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/22.jpg)
Implementation Alternatives
Most projects can be completed within 15-20 years. Average capital costs are $54M per year.
2
![Page 23: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/23.jpg)
3 Timeline Lower Campus Housing First
![Page 24: Bloomsburg University Campus Plan 2014](https://reader034.fdocuments.net/reader034/viewer/2022051817/5484e5f7b4af9f730d8b4cdf/html5/thumbnails/24.jpg)
Questions?