Bituminous Update2019 Metro State Aid Construction Seminar
Greg Johnson (Assistant Bituminous Engineer)
& Deb Evans (Mix Design Specialist)February 13, 2019
mndot.gov
Every Road Tells a Story
Project Goals
• Problem to Solve
• What will be considered a Success
• Realistic
• Budget
Plant Documentation
• Test Summary Spreadsheet
• AC Bill of Lading
• Scale Checks
• Recordation File
• Plant Diary
• Plant Certification
• MDR
• Weigh Ticket
Field Documentation
• Emulsion Bills of Lading
• Core Stationing Worksheet
• Core Incentive/Disincentive Worksheet
• Pavement Smoothness Files (*.ERD files)
• Pavement Smoothness Worksheet
• Street Diary
• Emulsion Lab Results
• Asphalt Binder Lab Results
Spec Change One Percent Reduced Density
• Change in 2018 Spec book.
• Contractor has to request to have One Percent Reduced Density.
• The Contractor still has to do it by the end of the 3rd day of paving and in writing!
• 1% reduced is required when paving the 1st lift over concrete.
2/13/2019 mndot.gov 6
Longitudinal Joint Density Requirement
Table 2360-20Longitudinal Joint Density Requirement
Location Confined Edge of Mat* Unconfined Edge of Mat║
Long joint 4% Design Void 91.0 89.5 89.5 88.1
Long joint 3% Design Void 92.0 90.5 90.5 89.1
2/13/2019 mndot.gov 7
Starting with the March 2019 Letting
AASHTOware
• What is It?
• MnDOT’s software to house Construction & Materials Data
• When?
• 2020 for Materials
• How will it affect you?
• Currently – Nothing
• This Summer - MnDOT use Excel Spreadsheets instead of LIMS
• Future – Electronic sample cards, reports, database
Tack
• Field Staff must sample 1/50,000 gallons
• Submit in ½ gallon plastic container
• (Identify dilution = CSS-1H, CSS-1H D30, or CSS-1 D50)
• Failures (2018)
• 397 samples – 42 tack (18%) and 3 (2%) chip seal/Micro/CIR,etc.
• Of the 42 failures = 23 were Residue, 14 were Penetration, and 5 were Both
• Causes:
2/13/2019 mndot.gov 9
ResiduePenetrationNo field dilution is allowed!! (2357.2.A)
& Bill of Lading
Effect of Diesel on Penetration
• How much diesel does it take to fail?
2/13/2019 mndot.gov 10
• CSS1-h or CSS-1
• Undiluted, or
• Diluted 70/30 (70% emulsion to 30% water)
• Use Proper Size Nozzles
• Apply a uniform tack coat, 100% coverage. (compare to a brown or black sheet of construction paper) (2357.3.D)
• Tack each lift when placing multiple lifts on the same day (2357.3.D)
• Sample from Distributor (2357.3.F)
Tack Details
Construction Paper
Applied Emulsion
Broken Emulsion
Sample Splitting
• The inspector must witness:
• Sampling, and
• Splitting
• The inspector must take possession of each sample after it is split.
9
9
Who’s Who?What’s What?Will We Match With Our Companion?
4 Days of Cores
Same Letters ?Mixed Up
No Confusion
Better system – ID by lot #
When do we Stop Production
• Stop Production if:
• If all the lots in a day’s production fail
• Or if greater than 50% of lots on multiple days fail
Filling the core holes
Core holes must restore the surface by 24 hours of coring.
Failure = $100/working day/lot
Workmanship
Spread all mixtures without segregation to the cross sections shown on the plans.(2360.3.B.2.a)
Paver Hopper
The need for a consistent amount of material in the paver hopper.
Cold Screed/Cold Mix
After compaction, the finished surface of each lift shall be reasonably free of segregated, open and torn sections, and shall be smooth and true to the grade and cross section shown on the plans with the following tolerances:
Must be free of segregated and open and torn section and deleterious material.Cut or saw and then remove and replace material placed outside the described limitations at no additional cost to the Department. If the Engineer determines the material can remain in place outside the limits, the Department will pay for the material at a reduced cost of $10 per sq. yd.
Paving Items
Paving Date: “Do not place asphalt pavement final wearing course lift after November 1south of an east-west line between Browns Valley and Holyoke. The Engineer may waive these restrictions when:(1) The Contractor is not placing asphalt mixture on the traveled portion of the roadway.(2) The roadway involved is closed to traffic during the following winter, or(3) The Engineer provides written direction to place the mixture.” (2360.3.A.4)
Road Conditions: “Do not place asphalt mixtures when weather or roadbed conditions or moisture conditions or the roadway surface are judged unfavorable by the Engineer. (2360.3.A.4)
Ordinary Compaction Projects: The specification does not allow paving when the air temperature is below 32°F. Table 2360-26 specifies the minimum laydown temperature as measured behind the paver for different combinations of air temperature and lift thickness. (2360.3.D.2.c)
Paver Mounted Thermal Profile (PMTP)
2/13/2019 mndot.gov 23
Why the Technology
• Allows contractor to quickly identify poor quality and apply corrective actions where needed.
• Enhance the quality of pavement being placed.
• Colder mix or cold mix pockets in the mat generally equate to lower density.
– With all things considered, density of the pavement has one of the biggest impacts on long term performance and durability.
• Uniformity, Uniformity, Uniformity
2/13/2019 mndot.gov 25
2/13/2019 mndot.gov 26
Thermal Segregation – End Dump Thermal Segregation
Category
Percent of Sublots
Low 0%
Moderate 0%
Severe 100%
Paver Stop (with a Pickup Machine)
7 minutePaver Stop
Cold Mix from Paver
Details
Keep an eye onthe end product
Keep rollersclose to paver
Thank you!Have a Safe and Productive Season