BIM for Civil Engineering - JACIC · BIM is an integrated process built on coordinated, reliable...
Transcript of BIM for Civil Engineering - JACIC · BIM is an integrated process built on coordinated, reliable...
© 2008 Autodesk
BIM for Civil Engineering08/07/2009
Yoshihiko Fukuchi, Ph.D. Industry Solutions Manager, AEC‐IM PLG, Autodesk Inc.
BIM is an integrated process built on coordinated, reliable information about a project from design through construction and into operations.
– Create coordinated, digital design information and documentation.
– Predict performance, appearance, and cost.
– Deliver the project faster, more economically, and with reduced environmental impact.
BUILDINGINFORMATIONMODELING ARCHITECTS
STRUCTURALENGINEERS
MEP SYSTEMSENGINEERS
BUILDERS
OWNERS
CIVILENGINEERS
Building Information Modeling (BIM)Building Information Modeling (BIM)
Accuracy•Ability to speed up design to construction process •Quantities/Takeoff – more accurate takeoff of materials and components versus manual counting•Reduction of errors, omissions, collisions – reducing risk and liability as mistakes found in office not field•Rapid reset should design need to change – production of plans, or updated information
This is CAD This is BIM
Visualization•Reduced time converting 2D to 3D for Visualization•Uses of Visualization
•Agency/Owner presentation•Marketing•Public Meetings/Google Earth
Conventional Way: banks and verges
Machine Control•Export of Design data to Machine Control
•Time to construction – from weeks to hours for machines to begin rolling, changes mid stream rationalized in hours not weeks
•Export of Design Data to GPS/Robotics•Inspection•XYZ coordinates for construction layout and control•Construction project progress tracking, material tracking, daily QA/QC of construction to design model
•Risk Mgmt•Performance verification
AccuGrade Way
Grade Checking of Base CourseGrade Checking of Base Course
High: 15%
Low: 30%
On Grade: 45%0 33 66
Conventional
High: 2%
Low: 0%
On Grade: 98%0 33 66
AccuGrade
Three points every 5m were surveyed A tolerance of ± 2cm was applied
Summary Summary of Resultsof Results
D6N - Operating Times
0
2
4
6
8
10
12
Conventional AccuGrade
hour
s
BaseSubgrade
02:24
08:28
05:46
01:28
330D - Operating Times
0
1
2
3
4
5
6
Conventional AccuGrade
Subgrade
05:19
04:36
140H - Machine Operation
0
0.5
1
1.5
2
Conventional AccuGrade
Base
01:49
00:32
Site Setup (Staking / Data Prep)
00:00
01:12
02:24
03:36
04:48
06:00
07:12
08:24
Conventional AccuGrade
Site Setup
07:31
00:54
Conventional24:32 hrs
AccuGrade11:50 hrs
Summary Summary of Results of Results 100% Increase in Productivity
3,0 days vs. 1,5 days
Increased Machine UtilizationLess waiting timeLonger passes
Savings in Operating Cost43% less Fuel consumption
22
210231
0
50
100
150
200
250
330D D6N 140H
7
136123
0
50
100
150
200
250
330D D6N 140H
Conventional
AccuGrade
43% fuel savings
Summary Summary of Results of Results Reduction in Surveying Cost
18 hrs & 14 min. X 2 people (Old way) vs.. 54 min. for 1 person (New way): 95% time saved and 1 person less.
Increased quality / potential for material saving45% in tolerance vs.. 98% in tolerance & much more consistentVerges and side slopes visually looked much better with AccuGrade9 Trucks vs.. 8 Trucks over 80M – 11% savings
Conventional AccuGrade
Laser Scanning (LIDAR)
•Scan existing conditions for Design parameters/As‐builts•Safety paramount (performed from safe location)•Scanning during construction to verify progress to model for % complete •Scanning during construction for verification of as‐built vs. as design
Quantities for Estimating and Production /Cost Control
•Optimization of Cut/Fill•Haul Road analysis•Wetland/Environmental mitigation•Quantity extraction of materials (concrete/rebar/rock/guardrail/walls/etc.)•More sustainable – wiser use and less material waste when ordering
Construction Simulation•Sequencing•Lane closures•4D Planning•Equipment and Material schedule optimization
Collaboration:•Project team sharing of model
•Currency of the model•Clash Avoidance•Utility/Contractor information sharing
Results – Savings from Clash Detection
CLASH # DESCRIPTION POTENTIAL COSTS1 Grid dimensions were wrong $10,000.002 A-Basin - Shortened Corbel along side wall $2,000.003 A-Basin - Beam pockets sizes4 A-Basin + Membrane - being able to see the section at the channel deck and wall joints. Priceless!5 Headworks - Grit Chambers ftgs./eliminated underslab $5,000.006 Headworks - Sluice Gates blockout sizes and location7 Admin. - Battered walls needed to be elongated due to clash with Curtain Walls $10,000.008 Admin. - Columns in the middle of the 2 main center walls were in the wrong place $5,000.009 Admin. - Chase blockouts on plans were not big enough for all HVACs and Electrical to go through. $5,000.0010 Admin. - By putting in steel beams we were able to see what size blockout and plates were needed, caught $5,000.00
mistake from Able Steel in the process.11 Admin - Eliminated steel beam ?12 Admin. - Ftgs and stems were layed out incorrectly on plans and were wrong size. $25,000.0013 By modeling the masonry we were able to lay out all the door and louver openings.14 Modeling piping & ductbanks $150,000.00
TOTAL SAVINGS $217,000.00
Butler Treatment Plant Clash Savings
Errors and Omissions:•Reduced errors on labeling and design•Better design•“What you see is what you get”
•Data derived from the model•Construction Docs derived from model•No “tricking” model to get desired results