BIM at Stanford - Building Success

77
BIM at Stanford Hospital and Clinics April 2014

Transcript of BIM at Stanford - Building Success

Page 1: BIM at Stanford - Building Success

BIM at Stanford Hospital and Clinics

April 2014

Page 2: BIM at Stanford - Building Success

Stanford Hospital and Clinics

Stanford Main Campus

Page 3: BIM at Stanford - Building Success

Stanford Hospital and Clinics

Existing Hospital New HospitalAdvanced Medicine CenterLPCHLPCH Expansion

1.1M sqft824K sqft221K sqft303K sqft476k sqft

Page 4: BIM at Stanford - Building Success

Stanford Hospital and Clinics

Existing Hospital New HospitalAdvanced Medicine CenterLPCHLPCH Expansion

1.1M sqft824K sqft221K sqft303K sqft476k sqft

Page 5: BIM at Stanford - Building Success

Stanford Hospital and Clinics

Existing Hospital New HospitalAdvanced Medicine CenterLPCHLPCH Expansion

1.1M sqft824K sqft221K sqft303K sqft476k sqft

Page 6: BIM at Stanford - Building Success

Stanford Hospital and Clinics

Existing Hospital New HospitalAdvanced Medicine CenterLPCHLPCH Expansion

1.1M sqft824K sqft221K sqft303K sqft476k sqft

Page 7: BIM at Stanford - Building Success

Stanford Hospital and Clinics

Existing Hospital New HospitalAdvanced Medicine CenterLPCHLPCH Expansion

1.1M sqft824K sqft221K sqft303K sqft476k sqft

Page 8: BIM at Stanford - Building Success

Stanford Hospital and Clinics

3M+ sqft on campus

4.5M sqft on and off site and growing

Page 9: BIM at Stanford - Building Success

9

Organization

Design and Construction

Engineering & Maintenance

New Stanford Hospital

Capital Improvement

Projects

LPCH Expansion

Project

Engineering & Maintenance

Page 10: BIM at Stanford - Building Success

Stanford Cath Labs 7, 9, & 10 Numeric results of CAD vs. BIM to 2” vs. full BIM

Jason Holbrook David Denysenko Eric Peabody

Page 11: BIM at Stanford - Building Success
Page 12: BIM at Stanford - Building Success

7

9

10

Page 13: BIM at Stanford - Building Success

BIM Use Area* Start**

Cath Lab 7 CAD 720 SF 2006

Cath Lab 9 2” Standard 1,173 SF 2009

Cath Lab 10 Everything 1,060 SF 2010

Experimental Variables

*Results expressed per SF to normalize this variable**Cost values escalated to 2010 relative value to normalize this variable

Experimental Controls

Page 14: BIM at Stanford - Building Success

Potential Savings

Save up to 35% on project costsComplete project 35% fasterDrop change order rate to <0.1%44% fewer RFIs

Page 15: BIM at Stanford - Building Success

Potential Savings

35% less $Complete project 35% fasterDrop change order rate to <0.1%44% fewer RFIs

Page 16: BIM at Stanford - Building Success

Potential Savings

Save up to 35% on project costs

35% fasterDrop change order rate to <0.1%44% fewer RFIs

Page 17: BIM at Stanford - Building Success

Potential Savings

Save up to 35% on project costsComplete project 35% faster

Changes to <0.1%44% fewer RFIs

Page 18: BIM at Stanford - Building Success

Potential Savings

Save up to 35% on project costsComplete project 35% fasterDrop change order rate to <0.1%

44% fewer RFIs

Page 19: BIM at Stanford - Building Success

19

Cath Lab 7

Cath Lab 7CAD Only

Page 20: BIM at Stanford - Building Success

7

Page 21: BIM at Stanford - Building Success

Cath Lab 7: Siemens Biplane Cath LabProject Area: 720 Gross Square Feet Construction Start: 2006

Procedure Room: 600 Net Square Feet BIM Use: None

Page 22: BIM at Stanford - Building Success

(E) CAD V.I.F. (N) CAD Construction

Page 23: BIM at Stanford - Building Success

(E) CAD V.I.F. (N) CAD Construction

Page 24: BIM at Stanford - Building Success

(E) CAD V.I.F. (N) CAD Construction

Page 25: BIM at Stanford - Building Success

(E) CAD V.I.F. (N) CAD Construction

Page 26: BIM at Stanford - Building Success

“ ”The delay was caused…by the over-head structural and M/E/P/FP not being coordinated. The majority of the overhead had to be re-designed.

DPR Construction

Cath Lab 7

Page 27: BIM at Stanford - Building Success

27

Cath Lab 9

Cath Lab 9Model to 2”

Page 28: BIM at Stanford - Building Success

9

Page 29: BIM at Stanford - Building Success

Cath Lab 9: Siemens Biplane Hybrid ORProject Area: 1,173 Gross Square Feet Construction Start: 2009

Procedure Room: 821 Net Square Feet BIM Use: Model to 2”

Page 30: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 31: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 32: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 33: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 34: BIM at Stanford - Building Success

34

Cath Lab 10

Cath Lab 10Model Everything

Page 35: BIM at Stanford - Building Success

10

Page 36: BIM at Stanford - Building Success

Cath Lab 10: Siemens Biplane Pediatric Cath LabProject Area: 1060 Gross Square Feet Construction Start: 2010

Procedure Room: 717 Net Square Feet BIM Use: Model Everything

Page 37: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 38: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 39: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 40: BIM at Stanford - Building Success

3D Scan (E) Model (N) Model Construction

Page 41: BIM at Stanford - Building Success

41

Cath Labs 7, 9, 10

Results

Page 42: BIM at Stanford - Building Success

42

Results

BIM Use % from CAD

Cath Lab 7 CADCath Lab 9 2” Standard -15.0%Cath Lab 10 Everything -4.1%

Construction Cost

Change Order Cost

*All figures in 2010 Relative Value

BIM Use % of Total

Cath Lab 7 CAD 12.4%

Cath Lab 9 2” Standard 8.1%

Cath Lab 10 Everything <0.1%

*All figures in 2010 Relative Value

Page 43: BIM at Stanford - Building Success

43

Results

BIM Use Construction Days/SF % from CAD

Cath Lab 7 CAD 8.40 mo 0.23 D/SFCath Lab 9 2” Standard 8.50 mo 0.15 D/SF -34.8%Cath Lab 10 Everything 8.45 mo 0.16 D/SF -30.4%

Construction Schedule

All Costs*

* All costs normalized to 2010 dollars** All design professional fees, including non-BIM fees*** Cath lab contribution margin of ~$8,000 per day

Survey All Services** Construction $ Margin*** Total

Cath Lab 7 18.5% 18.5%

Cath Lab 9 1.6% 27.3% (15.0%) (48.5%) (35.4%)

Cath Lab 10 1.6% 18.5% (4.1%) (54.7%) (34.6%)

Page 44: BIM at Stanford - Building Success

Conclusion

Save up to 23% on project costsComplete project 35% fasterDrop change order rate to <0.1%44% fewer RFIs

Page 45: BIM at Stanford - Building Success

45

That Went Well

Next Project 6% CO RateNot everything was resolved in the modelSome of the same team membersStandard Work is Needed

Page 46: BIM at Stanford - Building Success

46

BIM Procedures Manual

Page 47: BIM at Stanford - Building Success

Ensuring proper equipment access through BIM

Page 48: BIM at Stanford - Building Success

48

• Fire / Smoke Dampers• Domestic Water valves• Heating / Cooling Water Valves• Medical gas valves and pressure sensors• Supply, Exhaust and Return Air Valves• Fan Coil Units• Small Supply and Exhaust Fans• Duct Humidifiers• Re-Heat Coils• Cable Tray• Low Voltage controls such as BMS, lighting, etc.

Typical above ceiling MEP access

Page 49: BIM at Stanford - Building Success

49

The goal is to minimize or eliminate disruptions to patient care caused by maintenance activities.

• Whenever possible place serviceable items in “off-stage” areas like staff working areas, utility rooms and corridors that are not normally used for patients and visitors.

• Avoid placing items above ceilings in areas used for public circulation.

Page 50: BIM at Stanford - Building Success

50

Ceiling Access through an Infection Control Cube

Containment cubes are typically just slightly larger than the 2’ X 4’ ceiling tile opening.

An opened 8’ ladder barely fits within the cube.

Page 51: BIM at Stanford - Building Success

51

Plastic “Zip Wall” Containment:

If you can’t use a portable containment cube the next option is to build a temporary plastic wall. A valve at or above 16 feet high will

require a 14 foot ladder for safe access

14 Foot ladder base is over 100” wide

Page 52: BIM at Stanford - Building Success

52

1st Floor @ 18’

2nd Floor @ 20’

Patient Floors @ 16’

Ground Floor @ 18’

The New Stanford Hospital’s deck to deck heights range from 16’ to 20’.

This makes it easy to place MEP equipment out of reach even if there is nothing blocking it’s access.

Page 53: BIM at Stanford - Building Success

53

MEP Access Zone Guidelines

These guidelines are intended to be used during finite coordination to reduce possible remodeling and re-coordination efforts needed to maintain maintenance access to above ceiling MEP equipment.

Fire / Smoke Damper access:• Accessible from the corridor side. • Place over break rooms, conference rooms, mechanical and electrical rooms.

Valves:• Do not install more than 12 feet above the floor.• Locate valves in corridors, storerooms, utility rooms, etc.• Never place over nurse’s stations or within patient rooms.• Do Not locate valves above any patient care room door.

Do not place MEP serviceable items above fixed equipment, shelving or casework.

How Stanford is addressing access issues during modeling:

Page 54: BIM at Stanford - Building Success

54

MEP Access Zone Guidelines continued . . . . .

Supply, Exhaust and Return Air valves:• Provide access directly below actuators.• When actuator is on top of unit, place access adjacent to the air valves.

Fan Coil Units, Supply and Exhaust Fans:• Align ceiling grid, light fixtures, sprinkler heads, etc. with bottom access units to insure

access doors open fully.• In hard lid ceilings insure access hatches are located on the service side of the

equipment.

Other above ceiling MEP considerations:• BMS and Lighting Control boxes require front access.• Medical gas valves and pressure sensors placed below 12’ above the floor.• Re-Heat coil access to control valves and duct access hatch.• Consider sharing Cable Tray access zones with other MEP access zones.

Page 55: BIM at Stanford - Building Success

55

“Sufficient access is determined not only by above ceiling clearances but by the ability to use a containment cube and an appropriate sized ladder placed below the ceiling.”

Reviewing the model for access issues:

Page 56: BIM at Stanford - Building Success

56

Access Zones should be modeled to the floor and clashed with (known) fixed equipment, shelving and casework.

Modeling Access Zones:

Page 57: BIM at Stanford - Building Success

57

• Route the cable tray over the duct or use J-hooks to get over the duct.

• Whenever possible place cable tray 18” – 24” from the wall to share access zones.

Resolve all access clashes: (or they’ll need to be resolved in the field)

Page 58: BIM at Stanford - Building Success

58

• Model review completed after 1st pass Finite Coordination• Discrepancies logged and shared with the Design Team• Changes made and closed out during 2nd pass Finite Coordination

Model Reviews and Issues Log:

Page 59: BIM at Stanford - Building Success

59

Taking the model to the field to support construction:

BIManywhere Pro iPad App shown here

Using the model in the field is critical to insuring that the fully coordinated model becomes a fully coordinated building.

Stanford will be using the model to it’s fullest potential.

Page 60: BIM at Stanford - Building Success

60

For future projects:

1. Make it a requirement to model access zones from the equipment to the floor below and clash with fixed equipment and furniture.

2. Add the “MEP Access Zones Guidelines” to the BIM Management Plan.

3. Insist on getting experienced Facilities Maintenance staff involved. They are your best resource for identifying true access issues.

4. Keep it reasonable. Access to MEP equipment above ceilings has to be provided but it doesn’t always have to be easy access.

Page 61: BIM at Stanford - Building Success

BiM for Facilities Management

i=information without information its only a building model

April 2014

Page 62: BIM at Stanford - Building Success

Model is complete and building is close to activation? What Now ?

Facilities Services & Planning currently maintains 1.2 million square feet onsite 1 million square feet offsite Staff of 60 building engineers and facility managers with avg of 150

work orders/day New Hospital adds 820,000 SF of high demand clinical space consisting

patient rooms, level 1 trauma,ED, surgical, diagnostic and treatment rooms. Maintenance of the facility must be 24/7 with no equipment

failures or down time

Page 63: BIM at Stanford - Building Success

63

Current FM Practices

• Cost and time needed to develop input for CMMS (normally around $1-$3per gross SF, takes significant time after startup

• Cost and time needed to refer to paper files when FM problems occur• Poorer building and equipment performance (lack of adequate data for

preventive maintenance)

Page 64: BIM at Stanford - Building Success

64

Integration

Page 65: BIM at Stanford - Building Success

65

BIM is a better tool in reducing time to complete a work order

Service Scenario AssignmentFacilities Engineer is assigned to service HVAC Building with 70 VAV, 8 pumps, 14 fan motors & 2 centrifugal pumpsEqualing = 18 tickets per day per trade

Page 66: BIM at Stanford - Building Success

66

Real Case

Page 67: BIM at Stanford - Building Success

67

Nightmare Case

Page 68: BIM at Stanford - Building Success

68

Use Case with BIM

Page 69: BIM at Stanford - Building Success

69

Potential Cost Savings just for service on VAVs,pumps and motors

Note:Cost Savings per year in service to VAVs, pumps and motors related to HVAC system

Page 70: BIM at Stanford - Building Success

70

Simple and Intuitive

Mobile Capability

Page 71: BIM at Stanford - Building Success

Integrated Project Delivery ensure’s delivery of BIM for FM upfront

Page 72: BIM at Stanford - Building Success

72

Construction Operations Building Information Exchange

What is COBie?• A standard method of exchanging

information that drives down cost

Page 73: BIM at Stanford - Building Success

73

COBie

Page 74: BIM at Stanford - Building Success

74

COBie

Page 75: BIM at Stanford - Building Success

75

The Plan and current Deliverables

Stanford Hospital & Clinics is in the research and discovery Phase

1. Toured several hospital on the east coast and locally and observed: Technology is NEW and not fully developed in facilities management Lack of data in the model Lack of training in facilities maintenance staff

Goals for FY15

Define Use Cases and Specifications• In 3D model: Simple access to O&M manuals, Warranties, product data and replacement value• In 3D model: Metadata for all objects ie fire rating, floor type,• In 2D drawings: MEP and med gas system flow diagrams with shut off valves and Single lines• Integrated with employee name, dept. & machine• an ‘energy’ model and ability to compare actual energy use to baseline design energy use

Actions• Form BIM for FM execution team • Conduct pilot project and implement use cases in production with staff • Define BIM gaps in current BIM model and establish BIM deliverables from construction team

Estimate costs to maintain BIM system • For TI/remodels: update models, drawings, equip. metadata• Internal staffing and related vendor costs ( BIM Department)

Page 76: BIM at Stanford - Building Success

76

Operating Costs

Page 77: BIM at Stanford - Building Success

77

Vision: BIM for FM with complete integration with CMMS/BAS/Asset Management/Space Management