Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the...

37
I- Consulmis Eeg A CMS Energy Company Big Rock Point Nuclear Plant Kurt M. Haag 10269 US-31 North General Manager Charlevoix, Ml 49720 March 31, 2005 10 CFR 50.82(a)(7) U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 DOCKETS 50-155 AND 72-043 - LICENSE DPR-6 - BIG ROCK POINT PLANT - POST SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT (PSDAR); REVISION 4 Pursuant to 10 CFR 50.82(a)(7), Consumers Energy hereby submits Revision 4 to the Post Shutdown Decommissioning Activities Report (PSDAR) for Big Rock Point Plant. This revision incorporates a revised, detailed schedule and table of decommissioning activities. The schedule revision also updates the previous revision by indication of completed activities. Minor revision to the "General Decommissioning Activities Relating to Removal of Radiological Components and Structures" was made to eliminate specific discussion on methods of monitoring airborne contamination. This revision was made to ensure consistency with the requirements of the Offsite Dose Calculation Manual (ODCM). The discussion on cost estimate has also been revised, consistent with the information presented to the Michigan Public Service Commission in March 2004. The revision includes a reference to the annual Big Rock Point Plant (BRP) submittal of Financial Certification pursuant to 10 CFR 50.75(f)(1). Revisions included update of the discussion on the total volume of radioactive waste disposed and editorial revisions on the temporary on-site storage of low-level radioactive waste and the disposal of hazardous wastes. This revision on volume has been previously reviewed and approved by the U.S. Nuclear Regulatory Commission in their Safety Evaluation Report (SER) of February 19, 2005, "Approval of Proposed Revision to Disposal Procedures in Accordance with 10 CFR 20.2002." Therefore, the environmental impacts associated with site-specific decommissioning activities continue to remain in compliance with 10 CFR 50.82(a)(6)(ii). I 001

Transcript of Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the...

Page 1: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

I-

Consulmis Eeg

A CMS Energy Company Big Rock Point Nuclear Plant Kurt M. Haag10269 US-31 North General ManagerCharlevoix, Ml 49720

March 31, 2005 10 CFR 50.82(a)(7)

U.S. Nuclear Regulatory CommissionDocument Control DeskWashington, DC 20555-0001

DOCKETS 50-155 AND 72-043 - LICENSE DPR-6 - BIG ROCK POINT PLANT - POSTSHUTDOWN DECOMMISSIONING ACTIVITIES REPORT (PSDAR); REVISION 4

Pursuant to 10 CFR 50.82(a)(7), Consumers Energy hereby submits Revision 4 to the PostShutdown Decommissioning Activities Report (PSDAR) for Big Rock Point Plant. This revisionincorporates a revised, detailed schedule and table of decommissioning activities. The schedulerevision also updates the previous revision by indication of completed activities.

Minor revision to the "General Decommissioning Activities Relating to Removal of RadiologicalComponents and Structures" was made to eliminate specific discussion on methods ofmonitoring airborne contamination. This revision was made to ensure consistency with therequirements of the Offsite Dose Calculation Manual (ODCM).

The discussion on cost estimate has also been revised, consistent with the information presentedto the Michigan Public Service Commission in March 2004. The revision includes a reference tothe annual Big Rock Point Plant (BRP) submittal of Financial Certification pursuant to 10 CFR50.75(f)(1).

Revisions included update of the discussion on the total volume of radioactive waste disposedand editorial revisions on the temporary on-site storage of low-level radioactive waste and thedisposal of hazardous wastes. This revision on volume has been previously reviewed andapproved by the U.S. Nuclear Regulatory Commission in their Safety Evaluation Report (SER)of February 19, 2005, "Approval of Proposed Revision to Disposal Procedures in Accordancewith 10 CFR 20.2002." Therefore, the environmental impacts associated with site-specificdecommissioning activities continue to remain in compliance with 10 CFR 50.82(a)(6)(ii).

I 001

Page 2: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

This PSDAR revision (Attachment I) entirely replaces PSDAR revision 3, which was submittedon May 28, 2003. Therefore, no replacement pages are included.

Kurt M. HaasSite General Manager

cc: Administrator, Region III, USNRCNRC Decommissioning Inspector, Big Rock PointNRC NMSS Project Manager

ATTACHMENTS

2

Page 3: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

ATTACHMENT I

Big Rock Point PlantMarch 31, 2005

POST SHUTDOWN DECOMMISSIONING ACTIVITY REPORTRevision 4

16 pages

Page 4: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

PSDAR TABLE OF CONTENTS

INTRODUCTION ..................................................... I

BACKGROUND ..................................................... I

DESCRIPTION OFPLANNED DECOMMISSIONING ACTIVITIES .................................... 2Decommissioning Activities and Planning ..................................................... 2Planning Activities ...................................................... 2Plant Dismantlement ..................................................... 3

SIGNIFI CANT DECOMMISSIONING ACTIVITIES ..................................................... 4Reactor Vessel ..................................................... 4Steam Drum ..................................................... 5Primary Coolant System ..................................................... 5Containment Vessel ..................................................... 5Spent Fuel Pool ..................................................... 5

OTHER DECOMMISSIONING CONSIDERATIONS ..................................................... 5Chemical Decontamination of the Primary Coolant System ................................................... 6General Decommissioning Activities Relating to Removal ofRadiological Components and Structures .............. 6......................................6Special or Unusual Programs ..................................................... 8Bulk Material Removal Program ....................................... :.8Low' Level Radioactive Waste Removal and Handling ...................................... 8Soil Remediation ...................................... 8Processing and Disposal Site Locations ....................................... 8Resource Conservation and Recovery Act and Removal of Mixed Wastes ............................. 8Spent Fuel and Greater Than Class C Waste..........................................................................9

SITE RESTORATION ........................................................ 9

ENVIRONMENTAL IMPACTS.................................................................................................. I 0

TABLE I - SCHED ULE FOR DECOMMISSIONING A CTI VI TIES ...................................... 12

ESTIMATE OF EXPECTED DECOMMISSIONING COSTS ................................................. 14

REFERENCES............................................................................................................................. 15

Rev. 4March 31, 2005

i

Page 5: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

BIG ROCK POINT PLANTPOST SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT

REVISION 4

INTRODUCTION

Under the provisions of 10 CFR 50.82(a)(7), Consumers Energy Company hereby submitsRevision 4 to the Post Shutdown Decommissioning Activities Report (PSDAR) to describeplanned decommissioning activities, a schedule for their accomplishment, estimate expectedcosts, and provide the reasons for concluding that the environmental impacts associated withsite-specific decommissioning activities will be in compliance with 10 CFR 50.82(a)(6)(ii).

BACKGROUND

When Consumers Energy Company's Big Rock Point Plant began operation in September 1962,it was the first commercial nuclear power plant constructed in Michigan and the fifth in theUnited States. The General Electric Boiling Water Reactor (BWR) was rated for 240 Megawatt(MW) Thermal, and was built by Bechtel Corporation. By letters dated June 18, 1997, and June26, 1997, Consumers Energy Company notified the Nuclear Regulatory Commission (NRC)pursuant to 10 CFR 50.82(a)(1)(i), that Big Rock Point Plant would permanently cease operationby August 30, 1997. On August 29, 1997, the reactor was permanently shutdown, ending 35years of electric power generation as the nation's oldest and longest running nuclear plant. It wasclosed because its relatively small size (67MW Electric) was likely to make it too expensive tooperate in an increasingly competitive environment. On September 22, 1997, another letter wasforwarded to the Commission certifying that the fuel has been removed from the reactor vesseland placed in the spent fuel pool for storage.

Consumers Energy Company's goal is to immediately dismantle Big Rock Point Plant in a safe,environmentally conscious, and cost effective manner. This action will result in the timelyremoval of the existing nuclear plant in accordance with the DECON option found acceptable tothe NRC in its Final Generic Environmental Impact Statement (FGEIS) [Reference 1].Completion of this option is contingent upon continued access to one or more low level wastedisposal sites. Currently, Consumers Energy Company has access to Chem Nuclear - Barnwell,South Carolina and Envirocare of Utah - Clive, Utah.

1

Page 6: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

DESCRIPTION OF PLANNED DECOMMISSIONING ACTIVITIES

Decommissioning Activities and PlanningThe activities planned for decommissioning of the Big Rock Point Plant reflect theDECON option for the site. Work plans will be completed for decommissioning activitiesprior to commencing the activity. Table 1 shows the major decommissioning periods andmilestones for the Big Rock Point Restoration Project. This summary table begins withsignificant pre-shutdown milestones and highlights the major periods, phases, andmilestones throughout the decommissioning process.

License Termination Plan (LTP) Chapter 3, submitted April 1, 2003, contains a ProjectSchedule that shows the significant decommissioning activities. The information in thissubmittal supplements and serves as a revision to the LTP Chapter 3 Project Schedule.

Planning ActivitiesSubsequent to the Consumers Energy Company June 18, 1997 notification to the NRC ofplans to permanently shutdown the Big Rock Point Plant, a site organization was developedto decommission the plant. This organization became effective September 15, 1997.Revisions to the site Emergency Plan, Security Plan, Fire Protection Plan, TechnicalSpecifications, Offsite Dose Calculation Manual, Updated Final Hazards Summary Report(UFHSR), and Quality Program Description were revised to support decommissioning andwill continue to be revised and submitted to the NRC, as necessary.

Continuing planning and execution of decommissioning includes the following generalizedtypes of tasks.

Review all existing plant programs to assess their applicability to decommissioningand dry fuel storage on an Independent Spent Fuel Storage Installation (ISFSI),

Review and reclassify systems important to decommissioning activities (This task hasbeen completed),

Revise procedures and license basis documents to reflect the plant's permanentlydefueled and dry fuel storage configuration,

Complete the radiological and hazardous material characterization of the site,

Design and procure equipment and facilities to support decommissioning and dry fuelstorage activities,

Identify all specific decommissioning and dry fuel storage activities,

Prepare work plans for all decommissioning and dry fuel storage activities,

Prepare dose estimates for all decommissioning activities,

2

Page 7: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

Evaluate disposition options for site components and structures,

Develop a cost measurement and control mechanism, (This task has been completed)and

Develop an activity schedule consistent with the overall schedule. A key step in thedecommissioning planning was the completion of the selection of a project staff andestablishment of an organizational structure. This step mobilized site managementand staff personnel augmented with on-site specialty contractors.

Plant DismantlementFormer industrial area decommissioning planning was based on selecting the DECONoption and will result in the complete dismantlement and restoration of the area. Thefacilities remaining to support dry storage of the fuel will be decontaminated and/ordismantled after the U.S. Department of Energy (DOE) has received the spent fuel.

The following significant activities are anticipated to occur or have occurred during thedismantlement period:

Perform primary system decontamination (completed),

Establish a site construction power system (completed),

Remove asbestos insulation and plant piping systems (activity in progress,approximately 98% complete),

Remove turbine control oil (completed),

Establish a new spent fuel pool cooling system (completed),

Construct an Independent Spent Fuel Storage Installation (ISFSI) for dry cask storage(completed),

Remove all fuel from wet storage in the spent fuel pool and store fuel on the ISFSI inthe dry fuel storage casks, including greater than class C waste (completed),

Drain the spent fuel pool (completed),

Dismantle systems, structures and components not required for the safe storage ofspent fuel on the ISFSI, including major component removal (completed),

Conduct decontamination of facility surfaces, components and piping surfaces asrequired,

Conduct soil remediation as necessary,

3

Page 8: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

Ship and properly disposition all radioactive materials,

Perform a comprehensive final status survey to demonstrate compliance withapproved site release criteria (10 CFR 20, subpart E).

The only structures and facilities remaining after plant dismantlement and former industrialsite restoration will be those needed to support the dry storage of the spent fuel, andportions of the former intake line and supporting structures in Lake Michigan. Allsubsurface structures will be removed with the exception of the septic drainfield.

SIGNIFICANT DECOMMISSIONING ACTIVITIES

10 CFR 50.2 defines major decommissioning activities as those that result in permanentremoval of major radioactive components (e.g. reactor vessel and internals, large borereactor coolant system piping, and other large components that are radioactive to acomparable degree), permanently modify the structure of the containment, or result indismantling components for shipment containing greater than class C waste.

The following discusses several planned (and completed) significant decommissioningactivities at Big Rock Point Plant:

Reactor VesselThe reactor vessel was fabricated from carbon steel with an internal stainless steelcladding. The entire outside of the reactor vessel was insulated with 3-inch thick metallicinsulation. It was attached to the reactor vessel by banding and was supported by bracketswelded to the outside surface of the reactor vessel. The reactor vessel was supported by 12brackets attached to the exterior vessel shell. Twenty-four 2-1/2-inch diameter hanger rodsattached to these brackets transfered the reactor vessel weight to supports anchored in thesurrounding concrete.

During power operations, neutron irradiation from the fission process generated activationproducts in the stainless steel vessel liner, the carbon steel vessel shell, and metallicinsulation. The radionuclide inventory for the reactor vessel as a unitized package was aType B quantity, meeting the Low Specific Activity (LSA) material criteria. As a result,the reactor vessel as a unitized package was exempt from the requirements of 10 CFR71.73, "Hypothetical Accident Conditions." The radionuclide content estimates wereverified with a radiation survey of the reactor vessel after the internal components wereremoved. Detailed classification evaluations were completed as a part of detailed planningfor the reactor vessel removal activity.

The reactor vessel and head were shipped to licensed low-level radioactive waste disposalfacility. The reactor vessel was shipped as class B waste and the reactor head was shippedas class A waste.

4

Page 9: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

Steam DrumThe steam drum was part of the Nuclear Steam Supply System and was located in thereactor building. It was a 40-foot 9-inch long by 7-foot 2-inch diameter, horizontal steelcylinder with ellipsoidal heads. The steam drum contained 60 steam separators arranged intwo equal rows. The steam drum's vessel wall was 4-3/8 inches thick A-212B carbon steelwith 5/32" Type 304 stainless steel cladding. The nozzles were primarily ASTM A-105Grade II carbon steel with a 5/32-inch Type-304 stainless steel clad. Nozzles, smaller than4 inches, were made from SB-166 Inconel material. Internal components were made fromType 304 stainless steel.

The steam drum was chemically decontaminated as part of the Nuclear Steam SupplySystem, and was drained and isolated until ready for dismantlement in accordancewith general decommissioning activities. The steam drum was shipped to a low-levelradioactive waste disposal facility.

Primary Coolant SystemPrimary coolant system piping connected all major components of the Nuclear SteamSupply System. The primary coolant system was chemically decontaminated, drained, andisolated for dismantlement. Large bore piping was removed from this system and wasshipped to a low-level radioactive waste disposal facility.

Containment VesselThe containment vessel is a 130-foot diameter, Hortonsphere steel vessel. The sphereextends 27 feet below grade and 103 feet above grade. The containment vessel isconstructed of 3/4-inch (nominal) steel plates. The exterior columns were used duringconstruction and were unloaded after construction and testing of the containment vessel.During the decommissioning process they will be reloaded or removed, as necessary. Thefoundation of the containment vessel is a reinforced concrete cradle in the shape of aninverted spherical dome segment approximately 7 feet thick.

The containment surfaces and structures will be decontaminated and dismantled inaccordance with general decommissioning activities.

Spent Fuel PoolThe spent fuel pool was emptied; it was decontaminated and was dismantled in accordancewith general decommissioning activities.

OTHER DECOMMISSIONING CONSIDERATIONS

The decontamination and/or dismantlement of contaminated systems, structures, andcomponents may be accomplished by decontamination in place, dismantlement anddecontamination, or dismantlement and disposal. A combination of these methods may beutilized to reduce contamination levels, worker radiation exposure, and project costs.General considerations applicable to these activities are described below.

5

Page 10: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

Chemical Decontamination of the Primary Coolant SystemA chemical decontamination of the primary coolant system was performed prior toconducting any major decommissioning activity. Approximately 425 Curies wereremoved. The chemical decontamination was a significant ALARA initiative performed toreduce personnel exposure during decommissioning work activities. This decontaminationeffort included the reactor vessel and steam drum, steam risers and recirculation piping, andthe shutdown cooling system. The cleanup system was decontaminated in a similar manner.The reactor recirculating water pumps were used to circulate the cleaning solutionthroughout the primary and selected interconnected systems. Modifications were requiredto establish specific flow paths and isolation points. A qualified contractor, followingapproved site-specific controls, performed this decontamination effort.

General Decommissioning Activities Relating to Removal of Radiological Components &StructuresComponents will be safely and efficiently removed using the most appropriate methods forthe particular circumstance. Work packages will be prepared for activities related to thedismantlement of plant systems, structures, and components. Openings in components willtypically be covered to prevent the spread of contamination. Components may be moved toa processing area for volume reduction and packaging into containers for shipment to awaste disposal site or a processing facility for decontamination.

Following are several general decontamination and dismantlement considerations that willbe incorporated into the decommissioning work packages:

* Release of airborne contamination will be controlled in accordance with theOffsite Dose Calculation Manual (ODCM)

* Radioactive particulate emission will be monitored in accordance with theODCM.

* Decommissioning activities that use liquids will ensure that the contaminatedliquids will be processed, as necessary, and sampled and monitored inaccordance with the ODCM prior to release.

* Non-radioactive hazardous materials and wastes will be dispositioned inaccordance with Consumers Energy Company Waste Management Program.Typical materials handled and disposed of through this program include fuel oil,lubricating oil, 1,1,1-trichloroethane, laboratory chemicals, lead, mercury, paints,battery acid, and asbestos containing materials. Considerations include thefollowing:

- Materials containing asbestos (e.g. insulation) will be removed andprocessed in accordance with this program.

- The decontamination and dismantlement methods to be used on systems,structures, and components that contained or were immersed in chromated

6

Page 11: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

solutions will be evaluated and the methods selected to minimize thepotential for creating a mixed waste.

- Instrumentation and control components will be evaluated, and thedismantlement method will be selected to minimize the potential forcreating a hazardous waste. Switching elements that contain mercury willbe removed from the instrument when practicable.

* Contaminated systems, structures, and components with significant externalcontamination, will be decontaminated to remove the loose externalcontamination, coated to stabilize the contamination, bagged to prohibitcontamination spread, or otherwise controlled to prevent personnel or plantcontamination during removal.

* Contaminated piping and tubing should be removed as follows:

- Piping will be cut using methods that minimize the generation of airbornecontamination. When appropriate, remote cutting systems may be used tomaintain worker exposure ALARA.

- Protective covers or plugs may be installed on ends of contaminated pipingto confine internal contamination.

- Piping penetrations will be cut as close as practicable to the containmentvessel shell. The openings in the containment vessel will be covered orplugged once the piping is removed.

- Underground piping identified for removal will be evaluated prior to cuttingand removal to identify a method appropriate to the physical condition ofthe pipe.

* Contaminated supports will be removed in conjunction with the equipmentremoval activities.

* Systems and components may be removed from areas and buildings prior tothe start of structural decontamination activities. Walls may be removed asrequired to permit removal of components.

* Embedded contaminated piping, conduits, ducts, plate, channels, anchors,sumps and sleeves may be removed or decontaminated during area andbuilding structural decontamination activities.

* Equipment designated for asset recovery or re-use in the Consumers EnergyCompany system may be preserved in accordance with vendorrecommendations or Consumers Energy Company practices.

7

Page 12: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

* Components with paint coatings containing regulated quantities of PCBswill be identified, stored, and disposed of in accordance with federalregulations and guidance. Mixed PCB/radwaste disposal options will beaddressed throughout the decommissioning process.

Special or Unusual ProgramsThere are no special or unusual programs planned. All procedures and processes to beapplied at Big Rock Point Plant are consistent with those discussed in the Final GenericEnvironmental Impact Statement on Decommissioning (NUREG-0586).

Bulk Material Removal ProgramU.S. Nuclear Regulatory Commission approval for disposal of demolition debris containingless than 5 pCi/gram of principle gamma emitters, pursuant to 10 CFR 20.2002, wasobtained on February 5, 2002 and amended on January 19, 2005. Approximately 110million pounds of demolition debris will be shipped to a State of Michigan Type IILicensed landfill and approximately 3 million pounds of demolition debris contaminatedwith polychlorobiphenyl (PCB) will be shipped to a landfill licensed by Michigan and theU. S. Environmental Protection Agency (EPA).

Low Level Radioactive Waste Removal and HandlingLow level radioactive waste will be handled in accordance with plant procedures, thenshipped either to licensed offsite processors for further processing such as decontaminationfor free release, metal melt, incineration, or shipped for disposal at licensed facilities. Noonsite incineration will be performed.

Soil RemediationSoils, residual concrete rubble from demolition of structures, rubblized paving and othersoil-like materials not disposed of in an offsite landfill will be surveyed to determine ifresidual radioactivity of plant origin is present, and if so, the radioactivity concentrationspresent. Such soils and soil-like materials will be remediated (i.e., removed, processed, anddisposed of at a licensed facility) if determined to contain levels of radioactivity whichwould result in doses above the NRC site release guideline values of 10 CFR 20, subpart E.

Processing and Disposal Site LocationsA number of facilities are available for processing of radioactive waste materials. Thesefacilities provide services that include, but are not limited to, decontamination, incineration,metal melt, compaction or other methods of consolidation and disposal of low-levelradioactive wastes. A partial list of such facilities includes: Duratek, Oak Ridge, TN andBarnwell, SC; and Envirocare of Utah, Clive, UT.

Resource Conservation and Recovery Act and Removal ofMixed WastesAll applicable regulations of state and federal authorities will be followed in the handling,storage and transport of hazardous and mixed wastes. Transport will only be by authorizedlicensed transporters and shipment will be only to licensed facilities. If technology,resources, and approved processes are available to render hazardous or mixed waste non-

8

Page 13: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

hazardous, such processes may be considered to minimize the hazards of transport anddisposal of the wastes.

Spent Fuel and Greater Than Class C WasteSpent fuel was stored wet in the spent fuel pool until dry transportable storage canisterswere available, and fuel had decayed sufficiently to meet license conditions of thecanisters. Loading of dry fuel storage canisters was completed on March 26, 2003. Anonsite Independent Spent Fuel Storage Installation (ISFSI) accommodates all spent fuel inseven storage casks. Fuel is expected to be retained until U.S. Department of Energy(DOE) fulfills their obligation to receive the fuel.

Greater than Class C (GTCC) wastes are comprised of reactor internals exposed to manyyears of neutron flux. GTCC waste generated from the operation of the reactor was cutinto dimensions suitable for storage within a dry storage canister. Loading of the GTCCstorage canister was completed on May 2, 2003. This GTCC canister is stored on the onsiteISFSI. It will be transferred to DOE as GTCC waste. This option is allowed by storagecanister design. The Big Rock Point Staff will continue to monitor industry efforts andprogress towards GTCC shipment to DOE.

SITE RESTORATION

During the process of dismantlement and decontamination to greenfield (DECON) status,plant materials will be surveyed to determine whether such materials:

1) Are uncontaminated and may be free released,2) Are controlled by the Bulk Material Removal Program approved by the U.S.

Nuclear Regulatory Commission pursuant to 10 CFR 20.2002.3) Retain traces of detectable radioactivity, but at levels below NRC site release

criteria, in which case the materials either will:a) Remain on site,b) Be decontaminated for free release, orc) Be shipped to licensed vendor facilities for offsite processing such as metal

melt, incineration, or further decontamination, or4) Retain significant levels of radioactivity, in which case these materials will be

shipped to licensed facilities for processing or disposal.

A final survey to confirm that the site (with the exception of approximately a thirty acreISFSI Owner-Controlled Area) meets NRC release criteria will be performed on thegreenfield site prior to application of topsoil and vegetative plantings while original soiland any residual rubblized materials are readily accessible at and near the surface for InSitu gamma spectral analysis. Successful completion of the final survey will allow licensetermination with the formal industrial site released for unrestricted use. A similar processwill be performed on the ISFSI site following final shipment of fuel to DOE at a later date.

9

Page 14: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

ENVIRONMENTAL IMPACTS

Big Rock Point Plant has performed a review of the site and evaluated the potential impactsof the proposed decommissioning activities. The review concludes that impacts due todecommissioning of Big Rock Point Plant will be in compliance with 10 CFR50.82(a)(6)(ii). This conclusion is reached on the basis of the following:

The DECON method of decommissioning currently chosen for Big Rock PointPlant, as well as the SAFSTOR option which has also been thoroughly studiedfor this site, are fully addressed by the FGEIS.

There are no unique aspects of the decommissioning techniques to be utilizedthat would invalidate the conclusions reached in the FGEIS.

Big Rock Point Plant is significantly smaller and contains a radioactive sourceterm that is only on the order of 10% that of the standard BWR addressed by theFGEIS. As such, Big Rock Point Plant provides lower impacts for potentialradiological accidents.

Worker doses projected for the decommissioning of Big Rock Point Plant havebeen compared on a task-by-task basis with the FGEIS. Due to smaller size andlower radioactivity source term, doses are projected to be well under the 1845person-rem identified for the reference BWR by the FGEIS.

Doses to the public will not exceed those estimated by the FGEIS for thereference BWR.

No site-specific factors at Big Rock Point Plant would alter the conclusions of theFGEIS.

The total occupational radiation exposure expected for the decommissioning interval hasbeen initially estimated at 700 person-rem. This is a goal based on techniques ofmaintaining plant doses as low as reasonably achievable (ALARA). This number maychange and will be updated as detailed plans for each activity is developed over the courseof decommissioning. However, in no event is dose expected to exceed the value of 1845person-rem estimate of the FGEIS.

No significant environmental impacts are expected from the disposal of demolition debriswith trace concentrations of licensed radioactive materials in a State of Michigan licensedlandfill or alternate licensed PCB landfill. Total volume of landfill waste projected forBRP decommissioning is 1.34 million cubic feet including 142,000 cubic feet ofradioactive waste and 1.2 million cubic feet of demolition debris. In comparison,NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioning ofNuclear Facilities, " (FGEIS) lists a radioactive waste volume for the reference boilingwater reactor (BWR) of 18,975 cubic meters (670,096 cubic feet), including disposablecontainers.

10

Page 15: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

Radiation dose due to transportation of radioactive waste will be well below (on the orderof 10 to 20% based on waste volume and activity ratios) the 110 person-rem for transportworkers and 10 person-rem for the public presented by the FGEIS. Number of shipments(and therefore, doses as well as accident probabilities) also will be less than 20% of that thelarger reference plant, based on waste volume ratios. In addition, plant experience showsthat transport vehicle dose rates seldom approach the levels assumed by the FGEIS analysisin the calculation of transport worker and public doses.

Radiation exposure to offsite individuals due to postulated accidents are bounded by theFGEIS analysis for non-fuel related events, and by EPA Protective Action Guides[Reference 3] for these, as well as fuel related events. Effluents release levels, and publicdose due to effluents have decreased below the low levels observed during plant operation,due to lack of radionuclide production with the reactor defueled, and decay of theradionuclide inventory over time.

Disposal of low-level radioactive wastes at licensed disposal facilities is expected to bepossible in a timely manner. However, should temporary storage be required, adequateonsite storage space is available in a suitability facility. No significant environmentalimpacts are anticipated due to temporary onsite storage. Such storage will be incompliance with all applicable federal and state regulations.

Disposal of hazardous waste is in a timely manner. Hazardous wastes, mixed radioactivehazardous wastes and PCB wastes are stored and disposed of in compliance with allapplicable federal and state regulations.

Non-radiological environmental impacts from decommissioning the Big Rock Point Plantwill be minor short-term increases in noise, dust and truck traffic flow in the immediatevicinity of the plant site during dismantlement. An increased risk of industrial health issuesand accidents is recognized. Additional safety professionals have been added to thedecommissioning staff, and safety programs are receiving added emphasis inacknowledgement of this risk. The only significant socioeconomic impacts identified arethose of local job loss and lowered tax base. No detrimental impacts to local culture,terrestrial or aquatic resources have been identified. Although future uses of the plant sitehas not yet been determined, the property provides potential for a wide variety of beneficialuses. The chosen greenfield (DECON) option, coupled with unrestricted releasecompliance, will ensure that future uses are not limited by final site condition.

11

Page 16: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

TABLE 1SCHEDULE FOR DECOMMISSIONING

Decommissioning Plan and Preparation for Shutdown* Decommissioning Team formed - 10/10/1993* Original Decommissioning Plan - 2/27/1995* Plant Shutdown - 8/29/1997

Hazard Reduction* Core Off-Load - 9/20/1997* Spent Fuel Pool Cleanout - Non-SNM and GTCC materials -

3/10/2000* Chemical Decontamination of the Primary System - 1/21/1998* Phase 1 of Decommissioning Power - 3/11/1998* Phase 2 of Decommissioning Power- 2/12/1999* Removal of hazardous waste - i.e., asbestos (in progress)* Decontamination of structures, systems, and components (in progress)

Mobilization* High Efficiency Particulate Air Filters -1/21/1998* Monitoring Station - 2112/1999* Spent Fuel Pool Cooling Skid - 5/5/1999* General Licensee under 10 CFR Part 72 - 2/15/2001* Construction of the ISFSI - 6/30/2001* Containment Building Crane Installation - 10/30/2001* All fuel in Dry Storage Casks on the ISFSI - 3/26/2003* Greater Than Class C (GTCC) Waste Canister on the ISFSI -5/2/2003* ISFSI Operation (in progress)

Decommissioning Work Packages - System & Component Removal* Complete 3/17/2005

Removal of Major Components* Spent Fuel Pool Fuel Racks - 4/28/2003* Reactor Vessel - 10/22/2003* Steam Drum -11/19/2003* Spent Fuel Pool Liner - 12/18/2003* Irradiated Concrete Removal - 2/16/2005

12

Page 17: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

Demolition of Structures* ASD Building Removal - 4/26/2001* Solid Radwaste Building - 3/5/2003* Administrative Building - 9/8/2004* Screenhouse - 11/19/2004* Stack - 3/31/2005* Turbine Building - 3/31/2005* Liquid Radwaste Vaults (3rd Quarter 2005)* Containment Building (1st Quarter 2006)* Buried Piping and Building Foundations (2nd Quarter 2006)

License Termination* Develop and Submit Plan - 4/1/2003* Public Meetings on the LTP - 8/10/2003* NRC Plan Approval - 3/24/2005* Final Site Survey (FSS) - Non-ISFSI area (4h Quarter 2006)* Regulatory Review FSS - Non-ISFSI (4h Quarter 2006)* Partial Release of 10 CFR 50 Site (2007)* Shipment of Fuel to Department of Energy (2012)* FSS of the ISFSI (2012)* Regulatory Review FSS (2012)* Termination of Part 50 License (2012)

13

Page 18: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

ESTIMATE OF EXPECTED DECOMMISSIONING COSTS

The estimated cost to decommission the Big Rock Point Nuclear Plant (BRP) based on asite-specific decommissioning study prepared by TLG Services, Inc. in 2003 and filed withthe Michigan Public Service Commission (MPSC) in March 2004, is $439.4 million in yearof expenditure dollars. The site-specific study includes all costs necessary to restore theBRP site to a Greenfield condition by 2006, operate the ISFSI until the Department ofEnergy takes possession of the spent nuclear fuel, and ultimately decommission the ISFSIassumed to be completed by November 2012. Included in the study are $333.9 million ofNRC radiological decommissioning costs, $30.3 million of site restoration or Greenfieldcosts, $73.6 million of spent nuclear fuel storage costs, and $1.6 million of post 9-11incremental security costs.

Consumers Energy provides financial assurance in the amount of $333.9 million for NRCradiological decommissioning costs through the use of an external sinking fund that wasfunded by rates that were established by cost of service ratemaking regulation under thejurisdiction of the MPSC. Based on an order issued by the MPSC in Case No. U-1 1662 onMarch 22, 1999, Consumers Energy discontinued funding collection effective December31, 2000 and is relying on the funds in the MPSC-jurisdictional external sinking fund andfund earnings to cover the remaining amount of decommissioning expenditures. A smallportion of the remaining radiological decommissioning expenditures (approximately $2.0million at year-end 2004) will be funded through a Federal Energy Regulatory Commission(FERC)-jurisdictional reserve balance.

Of the $333.9 million of NRC radiological decommissioning costs, $279.1 million has beenwithdrawn from the MPSC-jurisdictional external sinking fund as of December 31, 2004and an additional $7.7 million has been funded from the FERC-jurisdictional reserve,leaving a remaining cost of $47.1 million. Financial assurance for the $47.1 million ofremaining NRC radiological decommissioning costs has been provided for through funds inthe external sinking fund and assumed fund earnings. At the end of 2004, the balance inthe external sinking fund was $51.4 million, based on State Street Bank and Trust,December 31, 2004 Annual Reports. The year-end balance reflects withdrawals of $279.1million to cover NRC radiological decommissioning expenditures incurred throughDecember 31, 2004.

Annually, BRP submits Certification of Financial Assurance pursuant to10CFR50.75(f)(1). Up-to-date information on decommissioning fund status may be foundin those submittals.

14

Page 19: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 4 March 31, 2005

REFERENCES

1. NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioningof Nuclear Facilities", August 1988.

2. Consumers Energy Company, "Updated Final Hazards Summary Report (UFHSR),Big Rock Point Plant", Revision 6, October 7, 1996.

3. EPA 402-R-92-001, "Manual of Protective Action Guides and Protective Actions forNuclear Incidents", May 1992.

4. Letter from Big Rock Point to the Nuclear Regulatory Commission dated March 27,2002, Certification of Financial Assurance for Decommissioning Pursuant to1OCFR50.75(f)(1).

5. Letter from Big Rock Point to the Nuclear Regulatory Commission dated April 1, 2003,Certification of Financial Assurance for Decommissioning pursuant to10CFR50.75(f)(1).

6. Letter from Big Rock Point to the Nuclear Regulatory Commission dated May 28,2003, Post Shutdown Decommissioning Activities Report (PSDAR), Revision 3

7. Letter from Big Rock Point to the Nuclear Regulatory Commission dated September15, 2004, Request for Approval of Proposed Disposal Procedures in Accordance with10 CFR 20.2002.

8. Letter from Big Rock Point to the Nuclear Regulatory Commission dated March 31,2005, Certification of Financial Assurance for Decommissioning pursuant to1OCFR50.75(f)(1).

15

Page 20: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

ATTACHMENT II

Big Rock Point PlantMarch 31, 2005

POST SHUTDOWN DECOMMISSIONING ACTIVITY REPORTMarked Copy of Revision 3 - Showing Changes for Revision 4

17 pages

Page 21: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

PSDAR TABLE OF CONTENTS

INTRODUCTION..........................................................................................................................1

BACKGROUND..............................................................................................................................1

DESCRIPTION OF PLANNED DECOMMISSIONING ACTIVITIES ..................................... 2Decommissioning Activities and Planning ....................................................... 2Planning Activities ...................................................... 2Plant Dismantlement ....................................................... 3

SI GNIFI CANT DECOMMISSIONING ACTIVITIES ....................................................... 4Reactor Vessel ....................................................... 4Steam Drum ....................................................... 5Primary Coolant System ....................................................... 5Containment Vessel ....................................................... 5Spent Fuel Pool ....................................................... 5

OTHER DECOMMISSIONING CONSIDERATIONS ....................................................... 5Chemical Decontamination of the Primary Coolant System................................................. 6General Decommissioning Activities Relating to Removal ofRadiological Components and Structures ....................................................... 6Special or Unusual Programs ....................................................... 8Low Level Radioactive Waste Removal and Handling ....................................................... 8Bulk Material Removal Prozrain ....................................................... 8Soil Remediation ....................................................... 8Processing and Disposal Site Locations ....................................................... 8Resource Conservation and Recoverv Act and Removal of Mixed Wastes ............................. 8Spent Fuel and Greater Than Class C Waste .................... ................................... 9

SITE RESTORA TION ....................................................... ,.9

ENVIRONMENTAL IMPACTS..................................................................................................10

TABLE 1 -SCHEDULE FOR DECOMMISSIONING ACTIVITIES ...................................... 12

ESTIMATE OF EXPECTED DECOMMISSIONING COSTS............................................. 14

REFERENCES..........................................................................................................................415

Rev. -4iy m 31, 2005

i

Page 22: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28, 2003

BIG ROCK POINT PLANTPOST SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT

REVISION 34

INTRODUCTION

Under the provisions of 10 CFR 50.82(a)(7), Consumers Energy Company hereby submitsRevision 3-4 to the Post Shutdown Decommissioning Activities Report (PSDAR) to describeplanned decommissioning activities, a schedule for their accomplishment, estimate expectedcosts, and provide the reasons for concluding that the environmental impacts associated withsite-specific decommissioning activities will be in compliance with 10 CFR 50.82(a)(6)(ii).

BACKGROUND

When Consumers Energy Company's Big Rock Point Plant began operation in September 1962,it was the first commercial nuclear power plant constructed in Michigan and the fifth in theUnited States. The General Electric Boiling Water Reactor (BWR) was rated for 240 Megawatt(MW) Thermal, and was built by Bechtel Corporation. By letters dated June 18, 1997, and June26, 1997, Consumers Energy Company notified the Nuclear Regulatory Commission (NRC)pursuant to 10 CFR 50.82(a)(1)(i), that Big Rock Point Plant would permanently cease operationby August 30, 1997. On August 29, 1997, the reactor was permanently shutdown, ending 35years of electric power generation as the nation's oldest and longest running nuclear plant. It wasclosed because its relatively small size (67MW Electric) was likely to make it too expensive tooperate in an increasingly competitive environment. On September 22, 1997, another letter wasforwarded to the Commission certifying that the fuel has been removed from the reactor vesseland placed in the spent fuel pool for storage.

Consumers Energy Company's goal is to immediately dismantle Big Rock Point Plant in a safe,environmentally conscious, and cost effective manner. This action will result in the timelyremoval of the existing nuclear plant in accordance with the DECON option found acceptable tothe NRC in its Final Generic Environmental Impact Statement (FGEIS) [Reference 1].Completion of this option is contingent upon continued access to one or more low level wastedisposal sites. Currently, Consumers Energy Company has access to Chem Nuclear - Barnwell,South Carolina and Envirocare of Utah - Clive, Utah.

1

Page 23: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28,2003|

DESCRIPTION OF PLANNED DECOMMISSIONING ACTIVITIES

Decommissioning Activities and PlanningThe activities planned for decommissioning of the Big Rock Point Plant reflect the DECONoption for the site. Work plans will be completed for decommissioning activities prior tocommencing the activity. Table 1 shows the major decommissioning periods and milestones forthe Big Rock Point Restoration Project. This summary table begins with significant pre-shutdown milestones and highlights the major periods, phases, and milestones throughout thedecommissioning process.

License Termination Plan (LTP) Chapter 3, submitted April 1, 2003, contains a Project Schedulethat shows the significant decommissioning activities. The information in this submittalsupplements and serves as a revision to the LTP Chapter 3 Proiect Schedule.

Planning ActivitiesSubsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plansto permanently shutdown the Big Rock Point Plant, a site organization was developed todecommission the plant. This organization became effective September 15, 1997. Revisions tothe site Emergency Plan, Security Plan, Fire Protection Plan, Technical Specifications, OffsiteDose Calculation Manual, Updated Final Hazards Summary Report (UFHSR), and QualityProgram Description are in various stages of development and continue to be submitted to theNRC, as necessary.

Continuing planning and preparation for decommissioning includes the following generalizedtypes of tasks.

Review all existing plant programs to assess their applicability to decommissioning and dryfuel storage on an Independent Spent Fuel Storage Installation (ISFSI),

Review and reclassify systems important to decommissioning activities (This task has beencompleted),

Revise procedures and license basis documents to reflect the plant's permanently defueledand dry fuel storage configuration,

Complete the radiological and hazardous material characterization of the site,

Design and procure equipment and facilities to support decommissioning and dry fuelstorage activities,

Identify all specific decommissioning and dry fuel storage activities,

Prepare work plans for all decommissioning and dry fuel storage activities,

Prepare dose estimates for all decommissioning activities,

1

Page 24: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28, 2003

Evaluate disposition options for site components and structures,

Develop a cost measurement and control mechanism, (This task has been completed) and

Develop an activity schedule consistent with the overall schedule. A key step in thedecommissioning planning was the completion of the selection of a project staff andestablishment of an organizational structure. This step mobilized site management and staffpersonnel augmented with on-site specialty contractors.

Plant DismantlementFormer industrial area decommissioning planning was based on selecting the DECON option andwill result in the complete dismantlement and restoration of the area. The facilities remaining tosupport dry storage of the fuel will be decontaminated and/or dismantled after the U.S.Department of Energy (DOE) has received the spent fuel.

The following significant activities are anticipated to occur or have occurred during thedismantlement period:

Perform primary system decontamination (completed),

Establish a site construction power system (completed),

Remove asbestos insulation and plant piping systems (activity in progress, approximately9098% complete),

Remove turbine control oil (completed),

Establish a new spent fuel pool cooling system (completed),

Construct an Independent Spent Fuel Storage Installation (ISFSI) for dry cask storage(completed),

Remove all fuel from wet storage in the spent fuel pool and store fuel on the ISFSI in thedry fuel storage casks, including greater than class C waste (completed),

Drain the spent fuel pool (completed),

Dismantle systems, structures and components not required for the safe storage of spent fuelon the ISFSI, including major component removal (completed),

Conduct decontamination of facility surfaces, components and piping surfaces as required,

Conduct soil remediation as necessary,

Ship and properly disposition all radioactive materials,

2

Page 25: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005My -28-2003

Perform a comprehensive final status survey to demonstrate compliance with approved siterelease criteria (10 CFR 20, subpart E).

The only structures and facilities remaining after plant dismantlement and former industrial siterestoration will be those needed to support the dry storage of the spent fuel, and portions of theformer intake line and supporting structures in Lake Michigan.

SIGNIFICANT DECOMMISSIONING ACTIVITIES

10 CFR 50.2 defines major decommissioning activities as those that result in permanent removalof major radioactive components (e.g. reactor vessel and internals, large bore reactor coolantsystem piping, and other large components that are radioactive to a comparable degree),permanently modify the structure of the containment, or result in dismantling components forshipment containing greater than class C waste.

The following discusses several planned (and completed) significant decommissioning activitiesat Big Rock Point Plant:

Reactor VesselThe reactor vessel was fabricated from carbon steel with an internal stainless steel cladding. Theentire outside of the reactor vessel is-was insulated with 3-inch thick metallic insulation. It iswas attached to the reactor vessel by banding and is-was supported by brackets welded to theoutside surface of the reactor vessel. The reactor vessel is-was supported by 12 brackets attachedto the exterior vessel shell. Twenty-four 2-1/2-inch diameter hanger rods attached to thesebrackets transfered the reactor vessel weight to supports anchored in the surrounding concrete.

During power operations, neutron irradiation from the fission process generated activationproducts in the stainless steel vessel liner, the carbon steel vessel shell, and metallic insulation.The radionuclide inventory for the reactor vessel as a unitized package is expected to-bewas aType B quantity, meeting the Low Specific Activity (LSA) material criteria. As a result, thereactor vessel as a unitized package weud-be-was exempt from the requirements of 10 CFR71.73, "Hypothetical Accident Conditions." The radionuclide content estimates were verifiedwith a radiation survey of the reactor vessel after the internal components were removed.Detailed classification evaluations were completed as a part of detailed planning for the reactorvessel removal activity and continue as paft ef the weEr planning proeess.

An engineering evaluation was performed to investigate potential reactor vessel removalalternatives. The evaluation identified two technically feasible alternatives: intact vessel remoevaland segmented vessel removal. The intact vessel removal alternative proposed that theThereactor vessel and head be-were shipped to a licensed low-level radioactive waste disposalfacilityies. The segmented vessel removal option proposed removal in separate pieces and thenshipment to a low-level radioactive waste disposal facility. The ev~aluation concluded that nosegmentation was the best alternative and will be pursued by the Big Rock Point RestefatienPfEjeet Staff.-The reactor vessel will bewas shipped as class B waste and the reactor head willbewas shipped as class A waste.

3

Page 26: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31. 2005Ma3,2 203

Steam DrumThe steam drum was part of the Nuclear Steam Supply System and is-was located in the reactorbuilding. It is-was a 40-foot 9-inch long by 7-foot 2-inch diameter, horizontal steel cylinder withellipsoidal heads. The steam drum eCntainscontained 60 steam separators arranged in two equalrows. The steam drum's vessel wall is-was 4-3/8 inches thick A-212B carbon steel with 5/32"Type 304 stainless steel cladding. The nozzles are-were primarily ASTM A-105 Grade II carbonsteel with a 5/32-inch Type-304 stainless steel clad. Nozzles, smaller than 4 inches, are-weremade from SB-166 Inconel material. Internal components are-were made from Type 304stainless steel.

The steam drum was chemically decontaminated as part of the Nuclear Steam SupplySystem, and was drained and isolated until ready for dismantlement in accordance withgeneral decommissioning activities. The steam drum wilbe was shipped to a low-levelradioactive waste disposal facility.

Primary Coolant SystemPrimary coolant system piping connected all major components of the Nuclear Steam SupplySystem. The primary coolant system has-beenwas chemically decontaminated, drained, andisolated for dismantlement. Large bore piping has-beenwas removed from this system and wasshipped to a low-level radioactive waste disposal facility.

Containment VesselThe containment vessel is a 130-foot diameter, Hortonsphere steel vessel. The sphere extends 27feet below grade and 103 feet above grade. The containment vessel is constructed of 3/4-inch(nominal) steel plates. The exterior columns were used during construction and were unloadedafter construction and testing of the containment vessel. During the decommissioning processthey will be reloaded or removed, as necessary. The foundation of the containment vessel is areinforced concrete cradle in the shape of an inverted spherical dome segment approximately 7feet thick.

The containment surfaces and structures will be decontaminated and dismantled in accordancewith general decommissioning activities.

Spent Fuel PoolThe spent fuel pool is-epw as emptied; it will bewas decontaminated and was dismantled inaccordance with general decommissioning activities.

OTHER DECOMMISSIONING CONSIDERATIONS

The decontamination and/or dismantlement of contaminated systems, structures, and componentsmay be accomplished by decontamination in place, dismantlement and decontamination, ordismantlement and disposal. A combination of these methods may be utilized to reducecontamination levels, worker radiation exposure, and project costs. General considerationsapplicable to these activities are described below.

4

Page 27: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May-28-j4M I

Chemical Decontamination of the Primary Coolant SystemA chemical decontamination of the primary coolant system was performed prior to conductingany major decommissioning activity. Approximately 425 Curies were removed. The chemicaldecontamination was a significant ALARA initiative performed to reduce personnel exposureduring decommissioning work activities. This decontamination effort included the reactor vesseland steam drum, steam risers and recirculation piping, and the shutdown cooling system. Thecleanup system was decontaminated in a similar manner. The reactor recirculating water pumpswere used to circulate the cleaning solution throughout the primary and selected interconnectedsystems. Modifications were required to establish specific flow paths and isolation points. Aqualified contractor, following approved site-specific controls, performed this decontaminationeffort.

General Decommissioning Activities Relating to Removal of Radiological Components &StructuresComponents will be safely and efficiently removed using the most appropriate methods for theparticular circumstance. Work packages will be prepared for activities related to thedismantlement of plant systems, structures, and components. Openings in components willtypically be covered to prevent the spread of contamination. Components may be moved to aprocessing area for volume reduction and packaging into containers for shipment to a wastedisposal site or a processing facility for decontamination.

Following are several general decontamination and dismantlement considerations that will beincorporated into the decommissioning work packages:

a The capability to control air flow to the environment through monitored pathways willbe provided when activities in these areas have the potential to ereatc airbofneradioactivity release. Pressure retention capability is not required. This considerationshould not preclude remeval of existing penetrations er- making temporarypenetrations providing that the opening can be closed in a timely manner.Release ofairborne contamination will be controlled in accordance with the Offsite DoseCalculation Manual (ODCM).

* Radioactive particulate emission will be monitored in accordance with the OffSiteDese Galeulatien Manual (ODCM).

* Decommissioning activities that use liquids will ensure that the contaminated liquidswill be processed, as necessary, and sampled and monitored in accordance with theOffsite Dose Calculation Manual (ODCM) prior to release.

* Non-radioactive hazardous materials and wastes will be dispositioned in accordancewith Consumers Energy Company Waste Management Program. Typical materialshandled and disposed of through this program include fuel oil, lubricating oil, 1,1,1-trichloroethane, laboratory chemicals, lead, mercury, paints, battery acid, and asbestoscontaining materials. Considerations include the following:

5

Page 28: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28, 2003 |

- Materials containing asbestos (e.g. insulation) will be removed andprocessed in accordance with this program.

- The decontamination and dismantlement methods to be used on systems,structures, and components that contained or were immersed in chromatedsolutions will be evaluated and the methods selected to minimize the potential forcreating a mixed waste.

- Instrumentation and control components will be evaluated, and the dismantlementmethod will be selected to minimize the potential for creating a hazardous waste.Switching elements that contain mercury will be removed from the instrumentwhen practicable.

* Contaminated systems, structures, and components with significant externalcontamination, will be decontaminated to remove the loose externalcontamination, coated to stabilize the contamination, bagged to prohibitcontamination spread, or otherwise controlled to prevent personnel or plantcontamination during removal.

* Contaminated piping and tubing should be removed as follows:

- Piping will be cut using methods that minimize the generation of airbornecontamination. When appropriate, remote cutting systems may be used tomaintain worker exposure ALARA.

- Protective covers or plugs may be installed on ends of contaminated piping toconfine internal contamination.

- Piping penetrations will be cut as close as practicable to the containment vesselshell. The openings in the containment vessel will be covered or plugged oncethe piping is removed.

- Underground piping identified for removal will be evaluated prior to cutting andremoval to identify a method appropriate to the physical condition of the pipe.

* Contaminated supports will be removed in conjunction with the equipmentremoval activities.

* Systems and components may be removed from areas and buildings prior to thestart of structural decontamination activities. Walls may be removed as requiredto permit removal of components.

* Embedded contaminated piping, conduits, ducts; plate, channels, anchors, sumpsand sleeves may be removed or decontaminated during area and buildingstructural decontamination activities.

6

Page 29: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May-84V I

* Equipment designated for asset recovery or re-use in the Consumers EnergyCompany system may be preserved in accordance with vendor recommendationsor Consumers Energy Company practices.

* Components with paint coatings containing regulated quantities of PCBs will beidentified, stored, and disposed of in accordance with federal regulations andguidance. Mixed PCB/radwaste disposal options will be addressed throughout thedecommissioning process.

Special or Unusual ProgramsThere are no special or unusual programs planned. All procedures and processes to be applied atBig Rock Point Plant are consistent with those discussed in the Final Generic EnvironmentalImpact Statement on Decommissioning (NUREG-0586).

BulkA Material Removal ProgramU.S. Nuclear Regulatory Commission approval for disposal of demolition debris containing lessthan 5pCi/gram of principle gamma emitters, pursuant to 10 CFR 20.2002. was obtained onFebruary 5, 2002 and amended on January 19, 2005. Approximately 110 million pounds ofdemolition debris will be shipped to a State of Michigan Type 11 Licensed landfill andapproximately 3 million pounds of demolition debris contaminated with polychlorobiphenyl(PCB) will be shipped to a landfill licensed by the State of Michigan and the U.S. EnvironmentalProtection Agency (EPA).

Low Level Radioactive Waste Removal and HandlingLow level radioactive waste will be handled in accordance with plant procedures, then shippedeither to licensed offsite processors for further processing such as decontamination for freerelease, metal melt, incineration, or shipped for disposal at licensed facilities. No onsiteincineration will be performed.

Soil RemediationSoils, residual concrete rubble from demolition of structures, rubblized paving and other soil-likematerials not disposed of in an offsite landfill will be surveyed to determine if residualradioactivity of plant origin is present, and if so, the radioactivity concentrations present. Suchsoils and soil-like materials will be remediated (i.e., removed, processed, and disposed of at alicensed facility) if determined to contain levels of radioactivity which would result in dosesabove the NRC site release guideline values of 10 CFR 20, subpart E.

Processing and Disposal Site LocationsA number of facilities are available for processing of radioactive waste materials. Thesefacilities provide services that include, but are not limited to, decontamination, incineration,metal melt, compaction or other methods of consolidation and disposal of low-level radioactivewastes. A partial list of such facilities includes: Duratek. Oak Ridge. TN and Chem. Nuclear,Barnwell, SC; and Envirocare of Utah, Clive, UT-.anDurateck, Oak Ridge,TN.

Resource Conservation and Recovery Act and Removal of Mixed Wastes

7

Page 30: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28, 2003

All applicable regulations of state and federal authorities will be followed in the handling,storage and transport of mixed wastes. Transport will only be by authorized licensedtransporters and shipment will be only to licensed facilities. If technology, resources, andapproved processes are available to render mixed waste non-hazardous, such processes may beconsidered to minimize the hazards of transport and disposal of the wastes.

Spent Fuel and Greater Than Class C WasteSpent fuel was stored wet in the spent fuel pool until dry transportable storage canisters wereavailable, and fuel had decayed sufficiently to meet license conditions of the canisters. Loadingof dry fuel storage canisters was completed on March 26,_2003. An onsite Independent SpentFuel Storage Installation (ISFSI) accommodates all empnt pent fuel in seven storage casks.Fuel is expected to be retained until U.S. Department of Energy (DOE) fulfills their obligation toreceive the fuel.

Greater than Class C (GTCC) wastes are comprised of reactor internals exposed to many years ofneutron flux. GTCC waste generated from the operation of the reactor was cut into dimensionssuitable for storage within a dry storage canister. Loading of the GTCC storage canister wascompleted on May 2, 2003. This GTCC canister is stored on the onsite ISFSI. It will betransferred to DOE as GTCC waste. This option is allowed by storage canister design. The BigRock Point Staff will continue to monitor industry efforts and progress towards GTCC shipmentto DOE.

SITE RESTORATION

During the process of dismantlement and decontamination to greenfield (DECON) status, plantmaterials will be surveyed to determine whether such materials:

1) Are uncontaminated and may be free released,2) Potentially have traces of undetectable radioactivity but arc authorized for State of

Miehigan licensed landfill disposal under 2 Are controlled by the Bulk MaterialRemoval Program approved by the U.S. Nuclear Regulatory Commission pursuant to10 CFR 20.2002.

3) Retain traces of detectable radioactivity, but at levels below NRC site release criteria,in which case the materials either will:

a) Remain on site,b) Be decontaminated for free release, orc) Be shipped to licensed vendor facilities for offsite processing such as metal melt,

incineration, or further decontamination, or4) Retain significant levels of radioactivity, in which case these materials will be shipped

to licensed facilities for processing or disposal.

A final survey to confirm that the site (with the exception of approximately a thirty acre dryISFSI Owner-Controlled Area) meets NRC release criteria will be performed on the greenfield

I

8

Page 31: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 200May 8,203 |

site prior to application of topsoil and vegetative plantings while original soil and any residualrubblized materials are readily accessible at and near the surface for In Situ gamma spectralanalysis. Successful completion of the final survey will allow license termination with theformal industrial site released for unrestricted use. A similar process will be performed on theISFSI site following final shipment of fuel to DOE at a later date.

ENVIRONMENTAL IMPACTS

Big Rock Point Plant has performed a review of the site and evaluated the potential impacts ofthe proposed decommissioning activities. The review concludes that impacts due todecommissioning of Big Rock Point Plant will be in compliance with 10 CFR 50.82(a)(6)(ii).This conclusion is reached on the basis of the following:

The DECON method of decommissioning currently chosen for Big Rock Point Plant,as well as the SAFSTOR option which has also been thoroughly studied for this site,are fully addressed by the FGEIS.

There are no unique aspects of the decommissioning techniques to be utilized thatwould invalidate the conclusions reached in the FGEIS.

Big Rock Point Plant is significantly smaller and contains a radioactive source termthat is only on the order of 10% that of the standard BWR addressed by the FGEIS. Assuch, Big Rock Point Plant provides lower impacts for potential radiological accidents.

Worker doses projected for the decommissioning of Big Rock Point Plant have beencompared on a task-by-task basis with the FGEIS. Due to smaller size and lowerradioactivity source term, doses are projected to be well under the 1845 person-remidentified for the reference BWR by the FGEIS.

Doses to the public will not exceed those estimated by the FGEIS for the referenceBWR.

No site-specific factors at Big Rock Point Plant would alter the conclusions of theFGEIS.

The total occupational radiation exposure expected for the decommissioning interval has beeninitially estimated at 700 person-rem. This is a goal based on techniques of maintaining plantdoses as low as reasonably achievable (ALARA). This number may change and will be updatedas detailed plans for each activity is developed over the course of decommissioning. However, inno event is dose expected to exceed the value of 1845 person-rem estimate of the FGEIS.

9

Page 32: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May-2-,263|

No significant environmental impacts are expected from the disposal of demolition debris withtrace concentrations of licensed radioactive materials in a State of Michigan licensed landfill oralternate licensed PCB landfill. Total volume of landfill waste projected for BRPdecommissioning is 1.34 million cubic feet including 142.000 cubic feet of radioactive waste and1.2 million cubic feet of demolition debris. In comparison. NUREG-0586. "Final GenericEnvironmental Impact Statement on Decommissioning of Nuclear Facilities. " (FGEIS) lists aradioactive waste volume for the reference boiling water reactor (BWR) of 18.975 cubic meters(670.096 cubic feet). including disposable containers.N sigpacts are expected fromthe dispesal of radioaetive waste. Total velume of waste projected for Big Rcek Point Plantdecmmissioning is 72,100 cubic feet, in comparison to the FGEIS volume for the referenceBW 6in g disposable continer.

Radiation dose due to transportation of radioactive waste will be well below (on the order of 10to 20% based on waste volume and activity ratios) the 110 person-rem for transport workers and10 person-rem for the public presented by the FGEIS. Number of shipments (and therefore,doses as well as accident probabilities) also will be less than 20% of that the larger referenceplant, based on waste volume ratios. In addition, plant experience shows that transport vehicledose rates seldom approach the levels assumed by the FGEIS analysis in the calculation oftransport worker and public doses.

Radiation exposure to offsite individuals due to postulated accidents are bounded by the FGEISanalysis for non-fuel related events, and by EPA Protective Action Guides [Reference 3] forthese, as well as fuel related events. Effluents release levels, and public dose due to effluentshave decreased below the low levels observed during plant operation, due to lack of radionuclideproduction with the reactor defueled, and decay of the radionuclide inventory over time.

Disposal of low-level radioactive wastes at licensed disposal facilities is expected to be possiblein a timely manner. However, should temporary storage be required, adequate onsite storagespace is available in one or re, or a combination of the Big Reek Point Plant radioactive wastefacility, the turbine and containment buildings, and an onsite contaminated materials warehouseasuitable facility. No significant environmental impacts are anticipated due to temporary onsitestorage. Such storage will be in compliance with all applicable federal and state regulations.

Disposal of hazardous waste is also expected to be possible in a timely manner. Hazardouswastes, mixed radioactive hazardous wastes and PCB wastes will be required to be stored onsiteuntil such time when a disposal/treatment method is approved. All storage of such waste willbeare stored and disposed of in compliance with all applicable federal and state regulations.

Non-radiological environmental impacts from decommissioning the Big Rock Point Plant will beminor short-term increases in noise, dust and truck traffic flow in the immediate vicinity of theplant site during dismantlement. An increased risk of industrial health issues and accidents isrecognized. Additional safety professionals have been added to the decommissioning staff, andsafety programs are receiving added emphasis in acknowledgement of this risk. The onlysignificant socioeconomic impacts identified are those of local job loss and lowered tax base. Nodetrimental impacts to local culture, terrestrial or aquatic resources have been identified.Although future uses of the plant site has not yet been determined, the property provides

10

Page 33: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28, 2003 I

potential for a wide variety of beneficial uses. The chosen greenfield (DECON) option, coupledwith unrestricted release compliance, will ensure that future uses are not limited by final sitecondition.

11

Page 34: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31. 2005Ma 2,2003 |

TABLE 1SCHEDULE FOR DECOMMISSIONING

Decommissioning Plan and Preparation for Shutdown* Decommissioning Team formed - Otober 10, 199310/10/1993* Original Decommissioning Plan - Februay-2 7, 19952/27/1995* Plant Shutdown - August 29, 19978/29/1997

Hazard Reduction* Core Off-Load - 9/20/1997* Spent Fuel Pool Cleanout - Non-SNM and GTCC materials -

3/10/2000* Chemical Decontamination of the Primary System - 1/21/1998* Phase 1 of Decommissioning Power - 3/11/1998* Phase 2 of Decommissioning Power - 2/12/1999* Removal of hazardous waste - i.e., asbestos (in progress)* Decontamination of Struetufesstructures, systems, and Cemponents

components (in progress)

Mobilization* High Efficiency Particulate Air Filters -1/21/1998* Monitoring Station - 2/12/1999* Spent Fuel Pool Cooling Skid - 5/5/1999* General Licensee under 10 CFR Part 72 - 2/15/2001* Construction of the ISFSI - 6/30/2001*GContainment Building Crane Installation - 10/30/2001aAll fuel in Dry Storage Casks on the ISFSI - 3/26/2003* Greater Than Class C (GTCC) Waste Cask on the ISFSI - 5/2/2003

9 Releeatien efFuel tc the ISFSI (April 2003)-9-

* ISFSI Operation (in progress)

Decommissioning Work Packages - System & Component Removal (im r-egiess)Complete 3/17/2005

Removal of Major ComponentsPeah m 4t Quarter 200-3)* Spent Fuel Pool Fuel Racks (2"nd-Quaiei3-2V"-4/28/2003* Reactor Vessel 4tht Q 10/22/2003* Steam Drum - 11/19/2003* Spent Fuel Pool Liner el" -Quatr 2004)-12/18/2004* Irradiated Concrete Removal (30d Quanef-20104):2/16/2005

12

Page 35: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005M4ay 28, 2003 |

Demolition of Structures* ASD Building Removal - 4/26/2001* Solid Radwaste Building (* M Quarter 2003)-3/5/2003* Administrative Building (l' Quartr- 2004)- 9/8/2004* Screenhouse - 11/19/2004* Stack - 3/31/2005* Turbine Building AddQuaer2 - 3/31 /2005* Liquid Radwaste Vaults (3rd Quarter 2042005)gSer~eenheuse (4'h Quartlr- 2004)9&ekal (,Vh quarter 2n04l

* Containment Building (1st Quarter 20052006)* Buried Piping and Building Foundations ('I-2Lnd Quarter 2 006)

License Termination* Develop and Submit Plan (Is -Quanter- 2003)-4/1/2003* Public Meetings on the LTP ("d-Quarti -2003)-8/10/2003* NRC Plan Approval (4thQuarter 2004)- 3/24/2005* Final Site Survey (FSS) - Non-ISFSI area ( 4th Quarter

20 06)* Regulatory Review FSS - Non-ISFSI (4 th Quarter 2002006)* Partial Release of 10 CFR 50 Site (20052007)* Shipment of Fuel to Department of Energy (2012)• FSS of the ISFSI (2012)* Regulatory Review FSS (2012)* Termination of Part 50 License (2012)

I

13

Page 36: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31, 2005May 28, 20O3

ESTIMATE OF EXPECTED DECOMMISSIONING COSTS

The estimated cost to decommission the Big Rock Point Nuclear Plant (BRP), based on ffnupdate-to a site-specific decommissioning study prepared by TLG Services, Inc. in 2003 andfiled with the Michigan Public Service Commission (MPSC) in 2000March 2004, is $395.3439.4million in 2002 year of expenditure dollars after adjusting the original study for contingenciesthat are not expected tc be spent. The site-specific study includes all costs necessary to restorethe BRP site to a greenfield condition by 20052006, operate the ISFSI until the Department ofEnergy takes possession of the spent nuclear fuel, and ultimately decommission the ISFSIassumed to be completed by November 2012. Included in the study are $2994333.9 -million ofNRC radiological decommissioning costs, $27330.3 -million of site restoration or greenfGePdGreenfield costs, and $68673.6 -million of spent fuel storage costs, and $1.6 million of post 9-1lincremental security costs.

Consumers Energy provides financial assurance in the amount of $2994333.9 -million for NRCradiological decommissioning costs through the use of an external sinking fund, funded by ratesthat are established by cost of service ratemaking regulation under the jurisdiction of theMiehigan Publie Serviee Gemmissien-(MPSQC. Based on an Order issued by the MPSC in CaseNo. U-1 1662 on March 22, 1999, Consumers Energy discontinued decomfissioning fundingcollection effective December 31, 2000 and is relying on the funds in the MPSC-jurisdictionalexternal sinking fund and fund earnings to cover the remaining amount of decommissioningexpenditures. A small portion of remaining radiological decommissioning expenditures(approximately $3-92.0 million at year-end 20022004) will be funded through a Federal EnergyRegulatory Commission (FERC)-jurisdictional reserve balance.

Of the $299.4333.9 million of NRC radiological decommissioning costs, $208279.1 millionhas been withdrawn from the MPSC-jurisdictional external sinking fund as of December 31,2002-2004 and an additional $577.7 million has been funded from the FERC-jurisdictionalreserve, leaving a remaining cost in yCar 2002 dollars of $84.947.1 million. Financial assurancefor the $84947.1 million of NRC radiological decommissioning costs has been provided forthrough funds in the MPSC-jurisdictional external sinking fund and assumed fund earnings. Atthe end of 20022004, the balance in the external sinking fund was $1401.351.4 million, based onState Street Bank and Trust, December 31, 2002L2004 Annual Reports. The year-end balancereflects withdrawals of $208.8279.1 million to cover NRC radiological decommissioningexpenditures incurred through December 31, 2002004.

Annually, BRP submits Certification of Financial Assurance pursuant to 10CFR50.75(f)(1). Up-to-date information on decommissioning fund estimates may be found in those submittals.

14

Page 37: Big Rock Point Plant, Post Shutdown Decommissioning ... · Planning Activities Subsequent to the Consumers Energy Company June 18, 1997 notification to the NRC of plans to permanently

Big Rock Point Plant - PSDAR Revision 34 March 31. 2005Ma 2,2003 |

REFERENCES

1. NUREG-0586, "Final Generic Environmental Impact Statement on Decommissioning ofNuclear Facilities", August 1988.

2. Consumers Energy Company, "Updated Final Hazards Summary Report (UF.HSR), BigRock Point Plant", Revision 6, October 7, 1996.

3. EPA 402-R-92-001, "Manual of Protective Action Guides and Protective Actions forNuclear Incidents", May 1992.

4. Letter from Big Rock Point to the Nuclear Regulatory Commission dated March 27, 2002,Certification of Financial Assurance for Decommissioning Pursuant to 10CFR50.75(f)(1).

6.5. Letter from Big Rock Point to the Nuclear Regulatory Commission dated April 1, 2003,Certification of Financial Assurance for Decommissioning pursuant to 1OCFR50.75(f)(1).

6. Letter from Big Rock Point to the Nuclear Regulatorv Commission dated May 28. 2003, PostShutdown Decommissioning Activities Report (PSDAR): Revision 3.

7. Letter from Big Rock Point to the Nuclear Regulatory Commission dated September 15.2004. Request for Approval of Proposed Disposal Procedures in Accordance with 10 CFR20.2002.

8. Letter from Big Rock Point to the Nuclear Regulatory Commission dated March 31. 2005.Certification of Financial Assurance for Decommissioning Pursuant to IOCFR50.75(f)(1).

15