BIG DIG(1)

download BIG DIG(1)

of 14

Transcript of BIG DIG(1)

  • 8/3/2019 BIG DIG(1)

    1/14

    Fahad Nawaz Khan (BBA, MSc )

    EXECUTIVE SUMMARY:-

    Different projects come with various baggage. Some of them go over

    cost and other over time. Every project has its hurdle and must be

    overcome within time or else it becomes an obstacle to completion. It

    does not mean if government is funding a project it will be all perfect.

    Projects tend to go off the track and over run their estimated cost due to

    improper planning and not keeping a consistent check and balance.

    Likewise, Central Artery unofficially known as the BIG DIG went in to

    chaos after all the years of research

    and hard work. What started to be a

    project to ease off traffic and

    congestion went on to become a

    nightmare for the government of

    Boston exceeding the total cost to a

    mammoth $22 Billion from 2 billion of its

    estimated cost. Tragedies also

    struck along the construction of Big

    Dig but worst part is that the 9 years delayed project will not only recover

    its cost till 2038 but according to experts the traffic jams and congestions

    will be starting to happen in the very near future, that is by 2012-2013.

    Only if more attention and continuous planning would have been given in

    the project the government would have been enjoying the sweetness ofthe fruit on time rather than its bitterness.

    Time Line for the Central Artery unofficially known as the

    1 | P a g e

  • 8/3/2019 BIG DIG(1)

    2/14

    Fahad Nawaz Khan (BBA, MSc )

    BIG DIG

    2 | P a g e

    Date

    Description

    1970s

    The project was conceived

    1982

    Planning officially began

    1983

    Project was estimated at $2.8 billion-Environmental studies began

    1987

    Public funding bill was passed by the US congress

    1991

    Ground was first broken to began the project

    1994

    Environmental clearance was delivered

    1998

    Project should have been completed

    199

    950% of the project was complete

    2001

    Contractors got aware of 400-600 leaks in the ceiling andwall fissures-70% of the project was complete

    2004

    95% of the project was complete-Major leak in the Interstate 39 (one of the routes) whichled to 700 further leaks-Problems started to pop

    200

    5

    3 employees of the concrete supplier were arrested on

    fraud charges2006

    False ceiling collapsed on a car killing one passenger andinjuring other

    2007

    The project was completed at last-Completed after 9 years of delay-Interest was up till $7 billion- Cost overrun to staggering 22 billion to be exact $21.83billion in total- Cost of the project will not be paid till 2038

  • 8/3/2019 BIG DIG(1)

    3/14

    Fahad Nawaz Khan (BBA, MSc )

    TRAFFIC BEFORE

    TRAFFIC AFTER

    INTRODUCTION:-

    Hundred of cities all over the world face traffic havoc every single day irrespective of

    them being highly developed or their status of being a developing nation.

    Traffic has always been an issue in commercial cities. So how are they tackled?

    Well, depending on the situation, different strategies have been applied. Even by

    building bridges, trains and subways, creating diversions to subjecting vehicles to

    certain limitations, putting the traffic congestion to rest has always been the tougher

    curb.

    So what happens when one of the largest cities in one of the richest nations of the

    world faces a traffic qualm? What happens when thousands of automobiles congest

    at one of the most important highways of the city and there is no other way to get to

    your destination except to wish for a miracle to make your car fly?

    The fate of Bostons highway construction shall be discussed and analysed in fine

    details with regards to its inception in the mid 20th century till its completion in the21st century. As a major highway project, it had planned to re-route the central artery

    through the heart of the city in to a long tunnel of about 4 miles.

    So what was the central artery and if it was already built, then why did things take yet

    another decade to be planned out?

    The original plan was conceived in the 1970s to replace the central artery which was

    becoming quite rusty. Other than that, there was the bumper to bumper traffic which

    was quite a headache for the business community due to the fact that the highway

    was one of the access to the main terminal, the Logan Airport. The people therefore

    often took the alternative route through the Third Harbor Tunnel. The mayors

    planned to knot the two projects together, the Central Artery and the Third Harbor

    Tunnel 6 (Massdot, 2011).

    The government had good support from the city people, especially the business

    community as it would ease the travelling for all.

    3 | P a g e

  • 8/3/2019 BIG DIG(1)

    4/14

    Fahad Nawaz Khan (BBA, MSc )

    The planning of it therefore officially started in 1982, but by the time all the

    concerning issues had been taken up and reviewed, 4 years had passed. It was the

    year 1987, the bill to start the project was passed, but again turned down by the

    president due to its expensive costs. It then took another 4 years, for the decision to

    be reversed and the project finally got a go-ahead signal (Lewis, R. 2002).

    COST, DELAYS AND INTER RELATED OBSTACLES ANALYSIS:-

    During its review in 1985, the project was initially estimated at around 2.8 billion

    dollars. By 1986, it rose to $3.2b and another year later $4.4b. But by 1990 it had

    gone up to approximately $5b. By then the officials had fleeting doubts for the cost

    estimation to remain constant. They interpreted the cost to inflate further and go up

    to significantly at least more than that of $10b.

    The project planning started in the early 80s, but the actual execution began in

    1991. The expected time of completion given was 1998. Even after four years after

    the expected time of completion, there was no sign of operation except amagnanimous change in the cost estimation. It rose to a staggering $14.6b. The

    project had an almost 200% increase in the budget over-run (Massdot, 2011).

    Besides the two major factors of finances and timing, the project had yet other

    concerns to be accountable for. One of them happened to be the environmental

    factor and the other being the engineering of the project. Bigger problems resided

    with the digging up of the tunnels. Even though they comprised largely of landfills,

    they also included subways and lots of utility piping that would have either had to be

    4 | P a g e

  • 8/3/2019 BIG DIG(1)

    5/14

    Fahad Nawaz Khan (BBA, MSc )

    moved to another place or simply replaced. Digging meant the workers would

    explore not just earthy substance, but also encounters with archaeological,

    histological and geological artefacts and obstacles such as parts of ruined residential

    compounds, glaciar debri and innumerable sunken ships within. However, the project

    had taken care of two objections; one being the release of harmful toxic materials

    and the other of displacing the millions of rats which would incur as a consequence

    to deep excavation and would then go wandering the streets of Boston (Massdot,

    2011).

    Another challenge they had to face was to

    allow the daily commutes to continue operating.

    Thousands of passengers travelled, using thetunnel as well as the trains. The engineers had

    to devise a plan in such a way that the daily

    commuting would not slow down due to the

    ongoing construction and for that they used a

    technology savvy engineering of GROUND

    FREEZING. The soil under the tunnel tracks

    was really soft and loose and therefore it wasmandatory to ground freeze in order to ensure

    firm n solid settled tracks that wouldnt danger

    the railway track operations. Ground freezing

    was a smart decision taken side by side with the construction to assure smooth

    operation of the normal daily traffic. Bring water was pumped into thousands of pipes

    present under and around the tracks and over a subtle amount of time the brine

    worked in a way to withdraw the seat released from the soil and in turn cause the soil

    to freeze from outside the pipes (Lewis, R. 2002).

    The construction of the big dig was completed in stages. In early January, the I-90

    connector tunnel extension inauguration took place. The elevated i-93 tunnel, which

    had to go underground, was completed over a span of a further 10 months, the

    southbound lanes opening several months after the northbound lines.

    5 | P a g e

  • 8/3/2019 BIG DIG(1)

    6/14

    Fahad Nawaz Khan (BBA, MSc )

    By 2004, two other small tunnels and connectors had started operation and almost a

    year later, big dig was 95% completed. 5% remaining construction was contributed

    to major resurfacing and ramp forming, plus reconstructing the streets as well as

    minor configurations of the over lanes and tunnels (Massdot, 2011).

    By early 2006, the final exit ramp was completed and the petty configurations hadbeen taken care of.

    But even then it still wasnt the end of the obstacles for the big dig. Soon after the

    final inauguration, problems started surfacing. And it wasnt that the contractors were

    not aware of it, or that the problems arrived spontaneously, but they knew that

    substandard material was used for the

    construction. The officials knew that there

    were thousands of leaks in the walls and ceilings

    of the project. The drainage systems were

    overloaded and water had extensively

    damaged the steel structures. Another

    $10m was required to repair all the leakages

    and existing defects. It is believed that the

    tunnel was never cleared off debri and

    related wastage before pouring in the concreteand that is why it faced so much destruction

    (Lewis, R. 2002). Considering these defects minor, they were repaired without

    bringing them out in the public eye, but unfortunately a major leak in the year 2004,

    brought back all the discrepancies of the tunnel in front of the people of the city of

    Boston (World Interesting Facts, 2011).

    6 | P a g e

    http://www.worldinterestingfacts.com/http://www.worldinterestingfacts.com/
  • 8/3/2019 BIG DIG(1)

    7/14

    Fahad Nawaz Khan (BBA, MSc )

    All the leakages ever taken place since its inauguration were exposed. Because of

    the severity of the leakages, the investigations were extensive and it was discovered

    that approximately around a 1000 leaks were present overall.

    In 2006, while a passenger was travelling to the

    airport, one of the concrete ceilings of the tunnel

    came crashing down killing the passenger and

    injuring her husband. Because of this incident,

    the road got blocked with traffic and so indirectlykilled another patient who was being taken to the

    hospital, but the ambulance was caught in the

    unmovable car chaos. After a long interrogation it

    came to be known that very substandard epoxy

    glue, which is used for short term bonding, was

    used to hold the roof in place (Wikipedia, 2011).

    Cost over-run, extensive delay of the project operation, major leakages, substandard

    usage of materials and fatal accidents. With so many economical, political and

    environmental destructions, what exactly had happened? Was the authority to be

    blamed for? Or was it simply a game of destiny and eventually meant to happen?

    Lets analyse the different causative factors affecting the construction process and

    the after effects and the ultimate consequences.

    Cost and time over-run:

    It took almost 5 years for the bill to be passed. The bill undoubtedly consists of the

    overview of the entire project. From its cost to time till the possible difficulties that

    could be encountered. True that nobody can determine the exact budget, so even

    when the project goes a little flexible, how much over budgeting is allowed? A few

    hundred thousands, millions or even a billion? But how does one explain the cost

    overrun to go beyond 11 billion dollars?

    7 | P a g e

  • 8/3/2019 BIG DIG(1)

    8/14

    Fahad Nawaz Khan (BBA, MSc )

    Should the officials be blamed for being incapable of devising the wrong approximate

    costs or should the unforeseen changes taking place during the construction, be held

    responsible?

    In this case, it is observed to be both. According to some media and news, it was

    reported that the officials were aware that the cost would never be what it was

    initially projected to be at $2.8m. But they reported it in the bill that way in order to

    have the project approved. Whether they were prepared of it going beyond $11m is a

    question that will probably remain unanswered for good (Wikipedia, 2011).

    The project was described as the biggest most complex highway project in the

    history of US. Bearing that in mind, its tender had to be given to several contractors.

    It was nothing that one company could handle alone. The project had big money

    and money changes the best of interests. The two main companies handling the

    major part of the project broke their agreement. This disagreement caused a lot of

    finances being misused or rather displaced (Ahmed, T. 2008).

    Other than the dirty political games played between various government officials and

    private companies, environmental factors also did play a significant part in the cost

    overrun. Repairs cost hundreds of millions, but why was there room for repairs in thefirst place? Definitely because of sub standard material implementation. Investigating

    responsibilities for the leakage and other weak construction material, lawyers and

    government officials tried determining the exact actual reason for the mishaps. Over

    2 thousand hours were spent by an expert engineer using marine geotechnical

    experience. No definite cause was found, hence it was ultimately attributed to

    unforeseen site changes and conditions plus the contractors incapabalities of

    working under pressure which eventually took its toll on the project (Ahmed, T.

    2008)

    Due to the constant obstacles such as low quality

    material, disagreement between companies,

    leakages and their repairs, new projects in

    collaboration with this project being suggested and

    then being cancelled due to budgets; all lead to the

    delay in project. But no doubt, the major reasonstood to be the costs which slowly increased over

    8 | P a g e

  • 8/3/2019 BIG DIG(1)

    9/14

    Fahad Nawaz Khan (BBA, MSc )

    the years and in order to avoid their increase, the projects memo was constantly

    changed or rather reduced to keep the costs low, in turn costing several years on the

    timeline.

    PROBLEMS AND ROLE OF PROJECT MANAGEMENT:-

    One thing should be clearly understood, that planning stage is as important as the

    developmental stage. Often things are not included in the original design plan, and

    when they surface during development phase they raise huge issues, schedulingand costing, just like the Big Dig did. The golden rule is: take your estimate and

    double it (Boston, 2011).

    Project managers should also keep knowledge of the latest on goings. Ignorance of

    the matter as being insignificant can most certainly become the main cause of

    tragedy after the construction is completed. Had the leaks been seriously taken from

    the first time they had come into notice, the problem would probably not have been

    so magnanimous (Boston, 2011).

    Bechtel never did a test on the ventilation system of the tunnel till after a year after

    the project had already been opened to the city. Once opened, it was eventually

    found out that a contractor had left spaces in the ventilating system which meant

    that in case of fire or smoke, there would be no way for its escape.

    An investigation company called Globe investigations went in to a yearlong

    interrogation on the Big Digs management company from San Francisco, called the

    Bechtel Groups and the other one being

    Parsons Brinckerhoff from Newyork. The

    investigation started after the officials felt

    that the root of all the problems were due

    to the mismanagement of this group. It

    was not one error that could be

    overlooked but actually a string of similar

    9 | P a g e

  • 8/3/2019 BIG DIG(1)

    10/14

    Fahad Nawaz Khan (BBA, MSc )

    problems were credited to Bechtels account. Investigating authorities calculated that

    during cost over runs, $1.6B or better put as the two thirds of cost over run, were

    solely due to the Bechtels incapabilities as a project management firm and hence

    their foolish mistakes (Wikipedia, 2011).

    Repairing and reviving the construction errors ultimately summed up to a $1.6B

    which can be clearly called to the discrepancies in the design and architect, a further

    $400M due to contractors finding construction conditions different from the actual

    design and what they really had to put up with, and approx another $800M went to

    labor and material costs that were no doubtedly the fault of a low grade design.

    Further investigation into the 17 year record of Bechtels association with the Big Dig,

    it was revealed that the company

    never performed the most

    fundamental duties of a project firm.

    Examples include carrying out field

    surveys which would have given them

    an insight in to the occupied and free

    spaces. Had that being carried out

    earlier, the utility lines would not have

    been placed under the building of the

    present Fleet center, but

    unfortunately for them, they didnt

    even mention of such a landmark

    present in that region and eventually gave a 350M$ over run (Wikipedia, 2011).

    Further exposed, Bechtel was caught to create incomplete and fully flaw designswhich cost the project approximately $800M. The Bechtels claimed to have given the

    full and final designs at the time of bid. It was true that they did create all the basic

    and advanced designs for the Big Dig along with scheduling it, but it was a complete

    lie to have said that the designs were complete and competent. Even after they

    made their mistakes as the incompetent architects, they didnt bother heeding

    erwarnings from their own engineers. It was only after the damage was huge and

    noticeable that the Bechtels would run after fixing it causing millions of cost over

    runs. And even the money that was required for the repair and fixtures was

    10 | P a g e

  • 8/3/2019 BIG DIG(1)

    11/14

    Fahad Nawaz Khan (BBA, MSc )

    requested towards the government to account for. This way they got the state to

    approve hundreds of millions of more dollars to cover up their flaws and mistakes

    that were entirely their responsibility (Ahmed, T. 2008).

    PROJECT MANAGEMENT STRATEGIES:-

    So how would project management have helped in sorting out the issues analysed

    above. What actions should have been taken by the owners, employers and the

    contractors to ensure a smoother operation for the big dig?

    To begin with there should have been:

    1. Transparent and honest bidding processes for selecting contractors and

    suppliers (no favours should have be done and decisions should have been

    totally unbiased).

    2. More involvement from the government side which would have caused an

    impact of consistent check and balance on the suppliers and the contractors

    (Greiman, V., 2010).

    3. Strict standards and reviewing them from time to time in order to keep the

    projects standard on the watch for a better as well as a timely finish.

    4. Integration of all the contractors should have made so the planning and

    execution would be more responsible (Boston, 2011).

    5. Deep communication between the parties would have the conditions clearly

    and more understandable to gauge the performance of the project.

    6. Better Incentives, aim and objectives should have been made in to the

    contracts during the projects life cycle to make sure that the safety quality,

    standard, commitments and financial data is on the straight line to meet the

    schedule and budget (Kanu, F. n.d.).

    KEY LESSONS:-

    11 | P a g e

  • 8/3/2019 BIG DIG(1)

    12/14

    Fahad Nawaz Khan (BBA, MSc )

    Now after this extensive reporting, what lessons should the Big Dig have to teach

    us? What are things that are to be kept in mind while making a project outline and

    projecting an outcome? Some are discussed here.

    Firstly, keeping aside political and economical interests, the project officials must

    always be honest towards their investigations and reviews. Eliminating small details

    for other illicit benefits can eventually cost money, schedule and most importantly,

    lives. Once that bill is passed, the project managers should have complete

    comprehension of the fact that the larger is the project, the more important it is to

    break it down into smaller ventures. This not only reduces complexity but also gives

    a clearer insight in to the under-going processes. This way various individual

    companies can be accountable for their part without much hassle being created forthe other departments of the project (Kanu, F., n.d.).

    Project integration is the KEY to a successful project.

    In order to ensure quality within a comfortable budge and safety, goals should be

    built into contracts throughout the project instead of it being judged at the start and

    finish only. Field surveys should be conducted rigorously at all times (Greiman, V.,

    2010).

    And most importantly, all firms should always keep in mind that doing things like it

    has always been done cannot be applicable to every project. Complex projects

    require a good competent design that can go under constant innovation and a

    cultural collaboration without going over the cost and finishing on the scheduled time.

    12 | P a g e

  • 8/3/2019 BIG DIG(1)

    13/14

    Fahad Nawaz Khan (BBA, MSc )

    References:-

    1. Ahmed, T. (2008) Why do most projects go over budge, [Online] Viewed on 04

    March 2011, http://sithsigma.wordpress.com/2008/05/31/why-do-most-

    projects-go-over-budget/

    2. Boston, (2011) Road to Tradegy,A history of Big Dig problems, [Online] Viewed

    on 13 March 2011, http://www.boston.com/news/specials/big_dig_problems/

    3. Greiman, V., ( 2010)The Big Dig: Learning from a Mega Project, [Online] Viewed

    on 03 March 2011, http://www.nasa.gov/offices/oce/appel/ask/issues/39/

    39s_big_dig.html

    4. Kanu, F. (n.d.) What To Do When Your IT Project Is Late, Over Budget, and

    Looks Like Its Never Going To Work, [Online] Viewed on 04 March 2011,

    http://www.geniusone.com/pdf/WhatToDoWhenYourITProjectIsLate.pdf

    5. Lewis, R. (2002) Big Dig overrun is just plain big, [Online] Viewed on 03 March

    2011,http://flyvbjerg.plan.aau.dk/News%20in%20English/BostonGlobe

    %20Costlies%20140702.pdf

    6. Massdot, (2011) The Central Artery/Tunnel Project - The Big Dig, [Online]

    Viewed on 24 February 2011, http://www.massdot.state.ma.us/

    Highway/bigdig/bigdigmain.aspx

    13 | P a g e

    http://sithsigma.wordpress.com/2008/05/31/why-do-most-projects-go-over-budget/http://sithsigma.wordpress.com/2008/05/31/why-do-most-%20%20projects-go-over-budget/http://sithsigma.wordpress.com/2008/05/31/why-do-most-%20%20projects-go-over-budget/http://www.boston.com/news/specials/big_dig_problems/http://opt/scribd/conversion/tmp/scratch16178/%20http://www.nasa.gov/offices/oce/appel/ask/issues/39/%20%2039s_big_dig.htmlhttp://opt/scribd/conversion/tmp/scratch16178/%20http://www.nasa.gov/offices/oce/appel/ask/issues/39/%20%2039s_big_dig.htmlhttp://www.geniusone.com/pdf/WhatToDoWhenYourITProjectIsLate.pdfhttp://flyvbjerg.plan.aau.dk/News%20in%20English/BostonGlobe%20Costlies%20140702.pdfhttp://flyvbjerg.plan.aau.dk/News%20in%20English/BostonGlobe%20Costlies%20140702.pdfhttp://www.massdot.state.ma.us/http://www.massdot.state.ma.us/Highway/bigdig/bigdigmain.aspxhttp://sithsigma.wordpress.com/2008/05/31/why-do-most-projects-go-over-budget/http://sithsigma.wordpress.com/2008/05/31/why-do-most-%20%20projects-go-over-budget/http://sithsigma.wordpress.com/2008/05/31/why-do-most-%20%20projects-go-over-budget/http://www.boston.com/news/specials/big_dig_problems/http://opt/scribd/conversion/tmp/scratch16178/%20http://www.nasa.gov/offices/oce/appel/ask/issues/39/%20%2039s_big_dig.htmlhttp://opt/scribd/conversion/tmp/scratch16178/%20http://www.nasa.gov/offices/oce/appel/ask/issues/39/%20%2039s_big_dig.htmlhttp://www.geniusone.com/pdf/WhatToDoWhenYourITProjectIsLate.pdfhttp://flyvbjerg.plan.aau.dk/News%20in%20English/BostonGlobe%20Costlies%20140702.pdfhttp://flyvbjerg.plan.aau.dk/News%20in%20English/BostonGlobe%20Costlies%20140702.pdfhttp://www.massdot.state.ma.us/http://www.massdot.state.ma.us/Highway/bigdig/bigdigmain.aspx
  • 8/3/2019 BIG DIG(1)

    14/14

    Fahad Nawaz Khan (BBA, MSc )

    7. Wikipedia, (2011) Big Dig, [Online] Viewed on 28 February, 2011,

    http://en.wikipedia.org/wiki/Big_Dig

    8. World Interesting Facts, (2011) Top 10 Most Expensive Projects In The World,

    [Online] Viewed on 01 March 2011, http://www.worldinterestingfacts.com

    /human/top-10-most-expensive-projects-in-the-world.html

    http://en.wikipedia.org/wiki/Big_Dighttp://www.worldinterestingfacts.com/http://www.worldinterestingfacts.com/human/top-10-most-expensive-projects-in-the-world.htmlhttp://www.worldinterestingfacts.com/http://www.worldinterestingfacts.com/human/top-10-most-expensive-projects-in-the-world.htmlhttp://en.wikipedia.org/wiki/Big_Dighttp://www.worldinterestingfacts.com/http://www.worldinterestingfacts.com/human/top-10-most-expensive-projects-in-the-world.htmlhttp://www.worldinterestingfacts.com/http://www.worldinterestingfacts.com/human/top-10-most-expensive-projects-in-the-world.html