BID # /PROJECT SUBJECT SCOPE OF WORK
Transcript of BID # /PROJECT SUBJECT SCOPE OF WORK
March 29, 2019
BID # /PROJECT: SUBJECT:
18-19-34F Newman ES HVAC Retrofit Addendum #1
The following changes, omissions, and or additions to the Project Manual and/or Drawings shall apply to proposals made for and to the execution of the various parts of the work affected thereby, and all other conditions shall remain the same.
Careful note of the addendum shall be taken by all parties of interest so that the proper allowances may be made in strict accordance with the Addendum, and that all contractors shall be fully advised in the performance of the work which will be required of them.
Bidder shall acknowledge receipt of this Addendum in the Space provided on the Bid Form. Failure to do so may subject Bidder to be disqualified.
In case of conflict, this Addendum shall govern.
SCOPE OF WORK
Correction: Remove / Change the following
III. Building J• Section A
Remove: “Flow selector will be installed on the rooftop, within a Flow selector enclosure, where indicatedby designer. The Flow selector shall be equal to Amairco Airflow Solutions.”
Correction: Change the wording on the following
III. Building J• Section A
o 4. Condensing unit will be installed on roof-level at ground-level, where indicated by designer.
CONTRACTOR’S REQUEST FOR INFORMATION (RFI)
See attached responses to RFI’s
END OF ADDENDUM #1
Attachments: (1) RFI Responses – 2 pages (1) Revised Scope of Work – 7 pages (1) Concrete Drawing (1) Chain Link Fences & Gates – 3 pages
Respectfully submitted,
Anna G. Hamilton Purchasing Director
CHINO VALLEY UNIFIED SCHOOL DISTRICT
Newman ES HVAC Retrofit
Contractors Class C-20 License Required Engineer's Estimate: $225,000.00 Contractor Duration: 90 Calendar Days
The successful contractor shall supply all labor, materials, services, insurance, and equipment necessary to complete the work. The contractor shall thoroughly investigate the premises for a complete understanding of the scope of work required for this bid.
Requester: Maintenance Department District Project Manager: Alex Rivera Budget Code: Deferred Maintenance
Addendum # 1 Changes Included
Scope of Work:
I. Demo [Building H & J] A. Properly shutdown existing HVAC and Electrical system as required to implement the new equipment.
Reclaim any residual refrigerant and dispose of properly. Disconnect and remove condensers on rooftop with the associated Piping to be disposed of properly. No abandoned equipment or materials shall be left in place. Remove and install new Roof Curb Caps. Area shall be prepared for new equipment.
B. Disconnect and cap off gas lines above the ceiling. Disconnect the electrical and remove Air Handler Unit with the associated Piping and Ductwork to be disposed of properly. Demo necessary cabinetry for clearance of the new equipment. No abandoned equipment or materials shall be left in place. Area shall be prepared for new equipment.
II. Building H A. Install new Variable Refrigerant Flow (VRF) system serving the bookrooms (Room 3 & 4). The system
will consist of Vertical Fan Coil Unit, Condensing Unit, and Fan Coil Enclosure. The VRF system shall be equal to Toshiba Carrier MMD FCU, and Toshiba Carrier MCY CU. Each FCU shall be installed in an Enclosure. The Enclosure shall be equal to Team Air Model TFIE.
Ill. Building J
1. All units are to be installed per installation instructions. 2. Installer shall complete the Carrier Toshiba VRF Installation Checklist to be submitted to
District Project Manager. a. Full Port Refrigeration Ball Valves with Access Ports will be utilized for isolation of
each component during service. 3. Enclosure shall utilize existing Outside Air openings. 4. Condensing unit will be installed on roof level, where indicated by designer.
A. Install new Variable Refrigerant Flow (VRF) system serving the Classrooms (Room 25, 26, 27, 28, 31, 32 & 33). The system will consist of Vertical Fan Coil Unit, Condensing Unit, Flow Selector, Fan Coil Enclosure, and Flow Selector Enclosure. The VRF system shall be equal to Toshiba Carrier MMD FCU, Toshiba Carrier MMY CU, and Toshiba Carrier RBM Flow Selectors. Each FCU shall be installed in an Enclosure. The Enclosure shall be equal to Team Air Model TFIE. Flow selector will be installed on the rooftop, within a Flow selector enclosure, where indicated by designer. The Flow selector shall be equal to Amairco Airflow Solutions.
1. All units are to be installed per installation instructions. 2. Installer shall complete the Carrier Toshiba VRF Installation Checklist to be submitted to
District Project Manager. a. Full Port Refrigeration Ball Valves with Access Ports will be utilized for isolation of
each component during service. 3. Enclosure shall utilize existing Outside Air openings. 4. Condensing unit will be installed on roof level, where indicated by designer.
ADD: at ground level,
IV. Controls [Building H & J] A. Each individual indoor system shall be controlled by a Programmable Wired Controller. The controller
shall be equal to Toshiba Carrier RBC. All low voltage wire shall be plenum rated and shielded. 1. Classrooms
a. Programmable Wired Control shall be mounted within Fan Coil Enclosure in an accessible area.
b. Remote sensor shall be mounted on the exterior of the Fan Coil Enclosure in an accessible area.
B. Each individual indoor system shall be working in conjunction with a Passive Infrared Sensor (PIR). The PIR shall be equal to Kele LX-24. All low voltage wire shall be plenum rated and shielded.
V. Materials • Outdoor Condensing Units
(2) Toshiba Carrier 1 Phase Heat Pump MCY-MAP0487HS-UL (Bldg H) (1) Toshiba Carrier 3 Phase Heat Recovery MMY-MAP1686FT9P-UL (Bldg J) (1) Toshiba Carrier 3 Phase Heat Recovery MMY-MAP1206FT9P-UL (Bldg J)
• Flow Selector Units (7) 1 Port FS Unit RBM-Y0613FUL (Bldg J)
• Connection Kit (1) Outdoor Heat Recovery Connection RBM-BT24FUL (Bldg J)
• Indoor Units (9) Vertical Fan Coil Unit MMD-AP0420VHG2UL (Bldg H & J)
• Branch Units (2) Y-Joint RBM-BY305FUL (2) Y-Joint RBM-BY205FUL (2) Y-Joint RBM-BY105FUL
• Control Units (9) Programmable Wired Controller RBC-AMS54E-UL (9) Remote Sensor TCB-TC41 LUL (9) PIR Sensor Kele LX-24
• Fan Coil Enclosures (9) Team Mfg Custom Enclosure Model #TFIE
- all enclosures will be customized per room
VI. Miscellaneous: • Contractor Shall Verify All Voltage & Phase Requirements Prior to Purchase of Equipment • Furnish All Electrical Components Required for Installation • Furnish All Parts/Components Required for Installation • Outside Air Plenum • Pleated Filter • Copper Condensate Piping • Disposal of Old Material Off Site • Prevailing Wage Labor • Dedicated Project Manager • All Work is to Meet or Exceed ANSl/SMACNA and ASHRAE Specifications • All Work is to Meet or Exceed California Code of Regulations, Title 24 • All Work is to Meet or Exceed Manufacturer Specifications and Guidelines • Commissioning of project to be done by Toshiba Carrier Certified Technicians • Awarded contractor will be responsible to repair/restore affected areas caused during the installation
process (i.e. paint, carpet patch, affected cabinetry, VCT floors, and ceilings) • Awarded contractor will have to coordinate with designer.
VII. Hours of Operation • All work to be performed after regular school hours and/or weekends.
o Hours of Operation can be adjusted when the school year ends on May 31, 2019. • All crane work must be scheduled with the District Project Manager prior to ensure that we have all staff off
the site.
VIII. Warranty: • 7 Years on Compressor from Toshiba Carrier • 5 Years on Parts from Toshiba Carrier • 2 Years on Installation/Labor from Installer
~
l:B 123 122 121 120 ~ BLDG·G
119 l1e 111 116 l1s E9 BLDG·F
114 113 l12 I ILOUNGf~ BLDG-0 11 10
19 Is 17 16 I~ ~ BLDG-C
11 13 L rn ~~ - I BLDG-H BLDG·B
NEWMAN ELEMENTARY SCHOOL
~
D AD
MPR BLDG-A
BLDG-E
~ ~ ~ ~
~
BLDG·K
25 I j26 121 12s