BID DOCUMENT FOR N.C.B - apwsipnsp.gov.in Docs/Works/Main/NSLBC/6… · BID DOCUMENT FOR N.C.B ......
Transcript of BID DOCUMENT FOR N.C.B - apwsipnsp.gov.in Docs/Works/Main/NSLBC/6… · BID DOCUMENT FOR N.C.B ......
1
GOVERNMENT OF ANDHRA PRADESH IRRIGATION & CAD (PW) DEPARTMENT
ANDHRA PRADESH WATER SECTOR IMPROVEMENT PROJECT
MODERNISATION OF NAGARJUNA SAGAR PROJECT
BID DOCUMENT FOR N.C.B.WORKS
NAME OF WORK : NSP - APWSIP – Rehabilitation and modernization of
21st Main Branch Canal from KM. 0.000 to
KM. 52.300 of Nagarjunasagar Lal Bahadur
Canal, A.P, India.
PACKAGE No. : LC - KMM – 6.
TENDER NOTICE No. : 9 /2007-08, DATED:17.01.2008.
Superintending Engineer
NSLBC O&M Circle, Tekulapally
Khammam – 507 002, Khammam District – (A.P) Telephone No: 08742 248132 Fax No: 08742 228585.
2
GOVERNMENT OF ANDHRA PRADESH
ANDHRA PRADESH WATER SECTOR IMPROVEMENT PROJECT
AGREEMENT NO.
NATIONAL COMPETITIVE BIDDING
(CIVIL WORKS)
Name of work: NSP - APWSIP – Rehabilitation and modernization of 21st Main Branch
Canal from KM 0.000 to KM. 52.300 of Nagarjunasagar Lal Bahadur
Canal, A.P, India.
PERIOD OF SALE OF : FROM: 21.01.2008
BIDDING DOCUMENT TO 10.03.2008.
TIME AND DATE OF PRE BID :DATE : 05.02.2008 TIME 11.00 HOURS
CONFERENCE
LAST DATE AND TIME FOR :DATE: 11.03.2008 TIME 15.00 HOURS
RECEIPT OF BIDS
TIME AND DATE OF OPENING :DATE: 11.03.2008 TIME 15.30 HOURS
OF BIDS
PLACE OF OPENING OF BIDS : OFFICE OF THE SUPERINTENDING ENGINEER
NSLBC (O&M) CIRCLE : TEKULAPALLY :
KHAMMAM – 507 002.
KHAMMAM District, Andhra Pradesh
Tel. Ph. No: 08742 248316.
Fax No. 08742 228585.
OFFICER INVITING BIDS : SUPERINTENDING ENGINEER
NSLBC (O&M) CIRCLE : TEKULAPALLY :
KHAMMAM – 507 002.
KHAMMAM District, Andhra Pradesh
Tel. Ph. No: 08742 248132.
Fax No. 08742 228585.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
4
GOVERNMENT OF ANDHRA PRADESH
ANDHRA PRADESH WATER SECTOR IMPROVEMENT PROJECT
INVITATIONS FOR BIDS (IFB)
NATIONAL COMPETITIVE BIDDING
Date:17.01.2008
Bid No.: 9/2007-08
1. The Government of India has received a loan from the International Bank for Reconstruction & Development
towards the cost of Andhra Pradesh Water Sector Improvement Project and intends to apply a part of the funds to
cover eligible payments under the contracts for construction of works as detailed in the table below. Bidding is open to
all bidders from eligible source countries as defined in the IBRD Guidelines for Procurement. Bidders from India
should, however, be registered with the Government of Andhra Pradesh or other State Governments /Government of
India, or State/Central Government undertakings. Bidders are advised to note the minimum qualification criteria
specified in Clause 4 of the Instructions to Bidders to qualify for the award of the contract.
2. The Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam invites bids for the construction
of works detailed in the table.
3. Bidding documents (and additional copies) may be purchased from the office of Superintending Engineer,
NSLBC O&M Circle, Tekulapally, Khammam from 21.01.2008 to 10.03.2008, for a non-refundable fee (three sets)
as indicated, in the form of cash or Demand Draft on any Scheduled bank payable at Khammam in favour of Pay and
Accounts Officer, Nagarjuna Sagar Project, Tekulapally, Khammam. Interested bidders may obtain further
information at the same address. Bidding documents requested by mail will be dispatched by registered/speed post on
payment of an extra amount of Rs 1000/-. The Superintending Engineer, NSLBC O&M Circle, Tekulapally,
Khammam will not be held responsible for the postal delay if any, in the delivery of the documents or non-receipt of
the same.
4. Bids must be accompanied by security of the amount specified for the work in the table below, drawn in
favour of Pay and Accounts Officer, Nagarjuna Sagar Project, Tekulapally, Khammam in case of Demand Draft or
Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam in case Bank guarantee. Bid security will
have to be in any one of the forms as specified in the bidding document and shall have to be valid for 45 days beyond
the validity of the bid.
5. Bids must be delivered to the Office of the Superintending Engineer, NSLBC O&M Circle, Tekulapally,
Khammam -507 002, Khammam District, A.P. on or before 15.00 hours on 11.03.2008 and will be opened in the
Office of the Superintending Engineer NSLBC O&M Circle, Tekulapally, Khammam, Khammam District, A.P. on
the same day at 15.30 .hours, in the presence of the bidders who wish to attend. If the office happens to be closed on
the date of receipt of the bids as specified, the bids will be received and opened on the next working day at the same
time and venue.
6. A prebid meeting will be held on 05.02.2008 at 11.00 hrs. at the office of Superintending Engineer, NSLBC
O&M Circle, Tekulapally, Khammam Khammam District, A.P. to clarify the issues and to answer questions on any
matter that may be raised at that stage as stated in Clause 9.2 of ‘Instructions to Bidders’ of the bidding document.
7. Other details can be seen in the bidding documents.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
5
TABLE
___________________________________________________________________________________________
Package
No.
Name of work Approximate
value
of work (Rs.
In Lakhs)
Bid security
(Rs.in
Lakhs)
Cost of
document
(Rs.)
Period of
completion
1
2 3 4 5 6
LC
KMM – 6.
NSP - NSLBC – APWSIP –
Rehabilitation and modernization
of 21st Main Branch Canal from
KM.0.000 to KM. 52.300 of
Nagarjunasagar Lal Bahadur
Canal, A.P, India.
4568.73 45.69. 5600/-
including
Sales Tax.
51 Months
( including water
regulation period
and rainy season
etc.)
Note:- The works inside the canal prism are to be executed during the normal annual canal closure period,
approximately April 1st to July 15
th (90 days) every year. This period may vary some what depending upon
meeting of any urgent water demands as per G.O. A.P. instructions.
__________________________________________________________________________________________
Seal of office
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
7
Section 1: Instructions to Bidders
Table of Clauses
A. General Page No. D. Submission of Bids Page No.
1. Scope of Bid 8 19. Sealing and Marking of Bids 15
2. Source of Funds 8 20. Deadline for Submission of Bids 16
3. Eligible Bidders 8 21. Late Bids 16
4. Qualification of the Bidder 8 22. Modification and Withdrawal of Bids 16
5. One Bid per Bidder 12
6. Cost of Bidding 12
7. Site Visit 12
B. Bidding Documents E. Bid Opening and Evaluation
8. Content of Bidding Documents 12 23. Bid Opening 16
9. Clarification of Bidding Documents 12 24. Process to be Confidential 16
10. Amendment of Bidding Documents 13 25. Clarification of Bids 17
26. Examination of Bids and Determination
of Responsiveness 17
27. Correction of Errors 17
C. Preparation of Bids 28. Currency for Bid Evaluation
29. Evaluation and Comparison of Bids 17
11. Language of Bid 13 30. Preference for Domestic Bidders
12. Documents Comprising the Bid 13
13. Bid Prices 13 F. Award of Contract
14. Currencies of Bid and Payment 14
15. Bid Validity 14 31. Award Criteria 18
16. Bid Security 14 32. Employer's Right to Accept any Bid and
to Reject any or all Bids 18
17. Alternative Proposals by Bidders 15 33. Notification of Award 18
18. Format and Signing of Bid 15 34. Performance Security 19
35. Advance Payment and Security 19
36. Adjudicator 19
37. Fraud and Corruption 20
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
8
A. General
1. Scope of Bid
1.1 The Superintending Engineer NSLBC O&M Circle, Tekulapally, Khammam, Khammam District, A.P invites
bids for the construction of works detailed in the table given in IFB. The bidders may submit bids for works
detailed in the table given in IFB.
1.2 The successful bidder will be expected to complete the works by the intended completion date specified in the
Contract data.
2. Source of Funds
2.1 The Government of India has received a loan from the International Bank for Reconstruction and
Development/the (hereinafter interchangeably called “the Bank”) towards the cost of Andhra Pradesh Water
Sector Improvement Project and intends to apply a part of the funds to cover eligible payments under the
contract for the Works. Payments by the Bank will be made only at the request of the borrower and upon
approval of the Bank in accordance with the Loan Agreement, and will be subject in all respects to the terms
and conditions of that Agreement. Except as the Bank may specifically otherwise agree, no party other than the
borrower shall derive any rights from the Loan Agreement or have any rights to the loan proceeds.
2.2 The loan agreement prohibits a withdrawal from the loan account for the purpose of any payment to persons or
entities, or for any import of goods, if such payment or import, to the knowledge of the Bank, is prohibited by a
decision of the United Nations Security Council, taken under Chapter VII of the Charter of the United Nations.
3. Eligible Bidders
3.1 This Invitation for Bids is open to all bidders from the eligible countries as defined under the IBRD Guidelines
for Procurement. Any materials, equipment, and services to be used in the performance of the Contract shall
have their origin in the eligible source countries.
3.2 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a statement that the Bidder
is not associated, nor has been associated in the past, directly or indirectly, with the Consultant or any other
entity that has prepared the design, specifications, and other documents for the Project or being proposed as
Project Manager for the Contract. A firm that has been engaged by the Borrower to provide consulting services
for the preparation or supervision of the works, and any of its affiliates, shall not be eligible to bid.
3.3 Government-owned enterprises in the Employer’s country may only participate if they are legally and
financially autonomous, operate under commercial law and are not a dependent agency of the Borrower or Sub-
borrower.
3.4 Bidders shall not be under a declaration of ineligibility for corrupt and fraudulent practices issued by the Bank
in accordance with sub-clause 37.1.
4. Qualification of the Bidder
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a preliminary description of
the proposed work method and schedule, including drawings and charts, as necessary.
4.2 In the event that Pre-qualification of potential bidders has been undertaken, only bids from prequalified bidders
will be considered for award for Contract. These qualified bidders should submit with their bids any information
updating their original prequalification applications or, alternatively, confirm in their bids that the originally submitted
prequalification information remains essentially correct as of date of bid submission. The update or confirmation
should be provided in Section 2.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
9
4.3 If the Employer has not undertaken prequalification of potential bidders, all bidders shall include the following
information and documents with their bids in Section 2:
(a) copies of original documents defining the constitution or legal status, place of registration, and principal
place of business; written power of attorney of the signatory of the Bid to commit the Bidder;
(b) total monetary value of construction work performed for each of the last five years;
(c) experience in works of a similar nature and size for each of the last five years, and details of works under
way or contractually committed; and clients who may be contacted for further information on those
contracts;
(d) major items of construction equipment proposed to carry out the Contract;
(e) qualifications and experience of key site management and technical personnel proposed for the Contract;
(f) reports on the financial standing of the Bidder, such as profit and loss statements and auditor's reports for
the past five years;
(g) evidence of adequacy of working capital for this contract (access to line (s) of credit and availability of
other financial resources);
(h) authority to seek references from the Bidder's bankers;
(i) information regarding any litigation or arbitration resulting from contracts executed by the Bidder in the
last five years or currently under execution. The information shall include the names of the parties
concerned, the disputed amount, cause of litigation, and matter in dispute;
(j) proposals for subcontracting components of the Works which in aggregate add to more than 20 percent
of the Bid Price (for each, the qualifications and experience of the identified sub-contractor in the
relevant field should be annexed; no vertical splitting of work for sub-contracting is acceptable); and
(k) the proposed methodology and program of construction including Environmental Management Plan,
backed with equipment, materials and manpower planning and deployment, duly supported with broad
calculations and quality control procedures proposed to be adopted, justifying their capability of
execution and completion of the work as per technical specifications within the stipulated period of
completion as per milestones .
4.4 Bid from Joint venture are acceptable. Bids submitted by a joint venture of not more than two as partners
shall comply with the following requirements:
[a] the bid shall include all the information listed in Sub-clause 4.3 above;
[b] the bid and, in case of a successful bid, the Agreement, shall be signed so as to be legally binding on all
partners;
[c] one of the partners shall be nominated as being in charge, and this authorization shall be evidenced by
submitting a power of attorney signed by legally authorized signatories of all the partners;
[d] the partner in charge shall be authorized to incur liabilities and receive instructions for and on behalf of any
and all partners of the joint venture and the entire execution of the contract, including payment, shall be
done exclusively with the partner in charge;
[e] all partners of the joint venture shall be liable jointly and severally for the execution of the contract in
accordance with the contract terms, and a statement to this effect shall be included in the authorization
mentioned under [c] above, as well as in the bid and in the Agreement [in case of a successful bid];
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
10
[f] The joint venture agreement should indicate precisely the role of all members of JV in respect of planning,
design, construction equipment, key personnel, work execution, and financing of the project. All members
of JV should have active participation in execution during the currency of the contract. This should not be
varied/modified subsequently without prior approval of the employer;
[g] The joint venture agreement should be registered in khammam so as to be legally valid and binding on
partners; and
[h] a copy of the joint Venture Agreement entered in to by the partners shall be submitted with the bid.
Alternatively, a Letter of Intent to execute a joint Venture Agreement in the event of a successful bid shall
be signed by all partners and submitted with the bid, together with a copy of the proposed Agreement.
4.5 A. To qualify for award of the contract, each bidder in its name should have in the last five years i.e.,
2002-03; 2003-04; 2004-05; 2005-06; 2006-07:
(a) achieved, in at least two financial years, a minimum annual financial turnover (in all classes of civil
engineering construction works only) of Rs. 2237.00 Lakhs.@
b) satisfactorily completed as a prime contractor, at least one similar work of value not less than
Rs. 3802.00 Lakhs.
(c) executed in any one year, the following minimum quantities of work:
- Earth work in both excavation and embankment 884500 Cum
- Cement Concrete (including RCC , PCC & any lining concrete) 19700 Cum
@ 2007-08 price level. Financial turnover and cost of completed works of previous years shall be
given weightage of 5% per year based on rupee value to bring them to 2007-08 price level.
4.5 B. Each bidder should further demonstrate:
(a) availability (either owned or leased or by procurement against mobilization advances) of the following
key and critical equipment for this work:
- Hydraulic Excavators 10 Nos. (6 of + 1 Cum and
4 of + 0.50 Cum Capacity)
- Tippers / Trucks 40 Nos. 10 Tonnes Capacity
- Power Rollers for compaction 5 Nos. 8 to 10 Tonnes
- Plate Vibrators ( for consolidation of CC Lining
placed manually) (Fuel operated / Electric operated). 8 Nos.
- Slope Compactors (for sub-grade compaction) 3 Nos.
- Mechanical concrete mixtures, ( 14/10 cft or 10/7 cft) 4 Nos.
- Weigh Batcher 2 No.
- Concrete paver (for placement of side lining) (15 – 20 Cum/Hr) 5 Nos
- Shot creeting machines (with accessories) 2 Nos
Concrete production & Transporation
- (i) Batching & mixing plants ( + 20Cum/Hr - 30 Cum/Hr) 3Nos
- (ii) Truck – mounted transit concrete mixers 9 Nos
(3 Cum drum capacity)
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
11
Alternatively
- Mobile self loading, weigh batching and mixing, and 4 Nos
Transporting concrete mixers (+ 2.5 Cum drum capacity)
- Vibrators for compaction of concrete (immersion/needle vibrators) 6 Nos.
- Water Tankers (+ 5000 Liters each) 4 Nos.
- Fine air water spray nozzles 4 Nos.
Based on the studies, carried out by the Engineer the minimum suggested major equipment to attain the
completion of works in accordance with the prescribed construction schedule are shown in the above list.
The bidders should, however, undertake their own studies and furnish with their bid, a detailed
construction planning and methodology supported with layout and necessary drawings and calculations
(detailed) as stated in clause 4.3 (k) above to allow the employer to review their proposals.
The numbers, types and capacities of each plant/equipment shall be shown in the proposals along with
the cycle time for each operation for the given production capacity to match the requirements.
(b) availability for this work of a Project Manager with no less than five years' experience in construction of
similar civil engineering works and other key personnel i.e. one Graduate Engineer (Civil) and one
Diploma holder (Civil) with minimum 5 years experience.
(c) liquid assets and/or availability of credit facilities of no less than Rs. 1520.00 Lakhs in the format given
in Section 2. (Credit lines/letter of credit/certificates from Banks for meeting the funds requirement
etc.) -
4.5 C. To qualify for a package of contracts made up of this and other contracts for which bids are invited in the IFB, the bidder must demonstrate having experience and resources sufficient to meet the
aggregate of the qualifying criteria for the individual contracts.
4.6 The figures for each of the partners of a joint venture shall be added together to determine the Bidder’s
compliance with the minimum qualifying criteria of Sub-clause 4.5. However, for a joint venture to qualify,
each of it’s partners must meet at least 50 percent of the minimum criteria set in Sub-clause 4.5 above and
all the partners collectively must meet the criteria specified in Sub-clause 4.5 above in full. Failure to
comply with this requirement will result in rejection of the joint venture’s bid.
Sub-contractors' experience and resources shall not be taken into account in determining the bidder's
compliance with the qualifying criteria.
4.7 Bidders who meet the minimum qualification criteria will be qualified only if their available bid capacity is
more than the total bid value. The available bid capacity will be calculated as under:
Assessed Available Bid capacity = ( A*N*1.5 - B ) where
A = Maximum value of civil engineering works executed in any one year during the last five years (updated
to 2007-08 price level) taking into account the completed as well as works in progress.
N = Number of years prescribed for completion of the works for which bids are invited.
B = Value, at 2007-08 price level, of existing commitments and on-going works to be completed during 51
months (period of completion of the works for which bids are invited)
Note: The statements showing the value of existing commitments and on-going works as well as the stipulated
period of completion remaining for each of the works listed should be countersigned by the Engineer in
charge, not below the rank of an Executive Engineer or equivalent.
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have:
- made misleading or false representations in the forms, statements and attachments submitted in proof of
the qualification requirements; and/or
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
12
- record of poor performance such as abandoning the works, not properly completing the contract,
inordinate delays in completion, litigation history, or financial failures etc.; and/or
- participated in the previous bidding for the same work and had quoted unreasonably high bid prices and
could not furnish rational justification to the employer.
5. One Bid per Bidder
5.1 Each bidder shall submit only one bid for one contract either individually or as partner in a Joint Venture. A
bidder who submits or participates in more than one Bid (other than as a subcontractor or in cases of
alternatives that have been permitted or requested) will cause all the proposals with the Bidder’s participation to
be disqualified.
6. Cost of Bidding
6.1 The bidder shall bear all costs associated with the preparation and submission of his Bid, and the Employer will
in no case be responsible and liable for those costs.
7. Site visit
7.1 The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine the Site of Works
and its surroundings and obtain all information that may be necessary for preparing the Bid and entering into a
contract for construction of the Works. The costs of visiting the Site shall be at the Bidder's own expense.
B. Bidding Documents
8. Content of Bidding Documents
8.1 The set of bidding documents comprises the documents listed in the table below and addenda issued in
accordance with Clause 10:
Invitation for Bids
Section 1 Instruction to Bidders
2 Forms of Bid and Qualification Information
3 Conditions of Contract
4 Contract Data
5 Specifications
6 Drawings
7 Bills of Quantities
8 Forms of Securities
8.2 Of the three sets of the bidding documents supplied, two sets should be completed and returned with the bid.
9. Clarification of Bidding Documents
9.1 A prospective bidder requiring any clarification of the bidding documents may notify the Employer in writing
or by cable (hereinafter "cable" includes telex and facsimile) at the Employer's address indicated in the
invitation to bid. The Employer will respond to any request for clarification which he received earlier than 15
days prior to the deadline for submission of bids. Copies of the Employer's response will be forwarded to all
purchasers of the bidding documents, including a description of the enquiry but without identifying its source.
9.2 Pre-bid meeting
9.2.1 The bidder or his official representative is invited to attend a pre-bid meeting which will take place at the
office of the Superintending Engineer, N.S.L.B.C. (O&M) Circle, Tekulapally on 05.02.2008 at 11.00 hours
(time and date).
9.2.2 The purpose of the meeting will be to clarify issues and to answer questions on any matter that may be raised
at that stage.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
13
9.2.3 The bidder is requested to submit any questions in writing or by cable to reach the Employer not later than
one week before the meeting.
9.2.4 Minutes of the meeting, including the text of the questions raised (without identifying the source of enquiry)
and the responses given will be transmitted without delay to all purchasers of the bidding documents. Any
modification of the bidding documents listed in Sub-Clause 8.1 which may become necessary as a result of
the pre-bid meeting shall be made by the Employer exclusively through the issue of an Addendum pursuant to
Clause 10 and not through the minutes of the pre-bid meeting.
9.2.5 Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10. Amendment of Bidding Documents
10.1 Before the deadline for submission of bids, the Employer may modify the bidding documents by issuing
addenda.
10.2 Any addendum thus issued shall be part of the bidding documents and shall be communicated in writing to all
the purchasers of the bidding documents. Prospective bidders shall acknowledge receipt of each addendum in
writing to the Employer.
10.3 To give prospective bidders reasonable time in which to take an addendum into account in preparing their
bids, the Employer shall extend as necessary the deadline for submission of bids, in accordance with Sub-
Clause 20.2 below.
C. Preparation of Bids
11. Language of the Bid
11.1 All documents relating to the bid shall be in the English language.
12. Documents comprising the Bid
12.1 The bid submitted by the bidder shall comprise the following:
(a) The Bid (in the format indicated in Section 2).
(b) Bid Security;
(c) Priced Bill of Quantities;
(d) Qualification Information Form and Documents;
and any other materials required to be completed and submitted by bidders in accordance with these
instructions. The documents listed under Sections 2, 4 and 7 of Sub-Clause 8.1 shall be filled in without
exception.
12.2 Bidders bidding for this contract together with other contracts stated in the IFB to form a package will so
indicate in the bid together with any discounts offered for the award of more than one contract.
13. Bid Prices
13.1 The contract shall be for the whole works as described in Sub-Clause 1.1, based on the priced Bill Quantities
submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for all items of the
Works described in the Bill of Quantities alongwith total bid price (both in figures and words). Items for
which no rate or price is entered by the bidder will not be paid for by the Employer when executed and shall
be deemed covered by the other rates and prices in the Bill of Quantities. Corrections, if any, shall be made
by crossing out, initialing, dating and rewriting.
13.3 All duties, taxes, and other levies payable by the contractor under the contract, or for any other cause shall be
included in the rates, prices and total Bid Price submitted by the Bidder.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
14
Note: “Bidders may like to ascertain availability of excise/custom duty exemption benefits available in India to the contracts
financed under World Bank loan/credits. They are solely responsible for obtaining such benefits which they have
considered in their bid and in case of failure to receive such benefits for reasons whatsoever, the employer will not
compensate the bidder (contractor). Where the bidder has quoted taking into account such benefits, he must give all
information required for issue of certificates in terms of such notifications as per form attached to the Qualification
Information in the bid. To the extent the employer determines the quantity indicated therein are reasonable keeping in
view the bill of quantities, construction programme and methodology, the certificates will be issued within 60 [sixty] days
of signing of contract and no subsequent changes will be permitted. No certificate will be issued for items where no
quantity/capacity of equipment is indicated in the statement. The bids which do not conform to the above provisions will
be treated as non responsive and rejected. Any delay in procurement of the construction equipment /machinery/goods as
a result of the above shall not be a cause for granting any extension of time.”
13.4 The rates and prices quoted by the bidder are subject to adjustment during the performance of the Contract in
accordance with the provisions of Clause 47 of the Conditions of Contract.
14. Currencies of Bid and Payment 14.1 The unit rates and the prices shall be quoted by the bidder entirely in Indian Rupees.
15. Bid Validity 15.1 Bids shall remain valid for a period not less than ninety days after the deadline date for bid submission
specified in Clause 20. A bid valid for a shorter period shall be rejected by the Employer as non-responsive.
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may request that the
bidders may extend the period of validity for a specified additional period. The request and the bidders'
responses shall be made in writing or by cable. A bidder may refuse the request without forfeiting his bid
security. A bidder agreeing to the request will not be required or permitted to modify his bid except as
provided in 15.3 hereinafter, but will be required to extend the validity of his bid security for a period of the
extension, and in compliance with Clause 16 in all respects.
15.3 Not applicable.
15.4 Bid evaluation will be based on the bid prices without taking into consideration the above correction.
16. Bid Security
16.1 The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in column 4 of the table of
IFB for this particular work. This bid security shall be in favour of Pay and Accounts Officer, Nagarjuna
Sagar Project, Tekulapally, Khammam in case of Demand Draft or Superintending Engineer, NSLBC O&M
Circle, Tekulapally, Khammam in case Bank guarantee and may be in one of the following forms:
- a bank guarantee issued by a nationalized / scheduled bank located in India or a reputable bank
located abroad in the form given in Section 8; in favour of Superintending Engineer, NSLBC O&M
Circle, Tekulapally, Khammam or
- Certified cheque, Bank draft or Letter of Credit in favour of in favour of Pay and Accounts Officer,
Nagarjuna Sagar Project, Tekulapally, Khammam payable at Khammam.
16.2 Bank guarantees issued as surety for the bid shall be valid for 45 days beyond the validity of the bid.
16.3 Any bid not accompanied by an acceptable Bid Security and not secured as indicated in Sub-Clauses 16.1
and 16.2 above shall be rejected by the Employer as non-responsive. ‘The bid security of a joint venture must
define as ‘bidder’ all joint venture partners and list them in the following manner : a joint venture consisting
of ‘ M/s Raghava, Constructions,’ and ‘ M/s B.V.S.R. Constructions, Hyderabad’ .
16.4 The Bid Security of unsuccessful bidders will be returned within 28 days of the end of the bid validity period
specified in Sub-Clause 15.1.
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed the Agreement and
furnished the required Performance Security.
16.6 The Bid Security may be forfeited
(a) if the Bidder withdraws the Bid after Bid opening during the period of Bid validity;
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
15
(b) if the Bidder does not accept the correction of the Bid Price, pursuant to Clause 27; or
(c) in the case of a successful Bidder, if the Bidder fails within the specified time limit to
(i) sign the Agreement; or
(ii) furnish the required Performance Security.
17. Alternative Proposals by Bidders
17.1 Bidders shall submit offers that comply with the requirements of the bidding documents, including the basic
technical design as indicated in the drawing and specifications. Alternatives will not be considered.
18. Format and Signing of Bid
18.1 The Bidder shall prepare one original and one copy of the documents comprising the bid as described in
Clause 12 of these Instructions to Bidders, bound with the volume containing the Form of Bid, and clearly
marked "ORIGINAL" and "COPY" as appropriate. In the event of discrepancy between them, the original
shall prevail.
18.2 The original and copy of the Bid shall be typed or written in indelible ink and shall be signed by a person or
persons duly authorized to sign on behalf of the Bidder, pursuant to Sub-Clauses 4.3. All pages of the bid
where entries or amendments have been made shall be initialed by the person or persons signing the bid.
18.3 The Bid shall contain no alterations or additions, except those to comply with instructions issued by the
Employer, or as necessary to correct errors made by the bidder, in which case such corrections shall be
initialed by the person or persons signing the bid.
18.4 The Bidder shall furnish information as described in the Form of Bid on commissions or gratuities, if any,
paid or to be paid to agents relating to this Bid, and to contract execution if the Bidder is awarded the
contract.
D. Submission of Bids
19. Sealing and Marking of Bids
19.1 The Bidder shall seal the original and copy of the Bid in separate envelopes, duly marking the envelopes as
"ORIGINAL" and "COPY". These envelopes (called as inner envelopes) shall then be put inside one outer
envelope.
19.2 The inner and outer envelopes shall
(a) be addressed to the Employer at the following address:
The Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam, Khammam District,
Andhra Pradesh and be delivered at the office of the Superintending Engineer, khammam, A.P.
(b) bear the following identification:
- Bid for NSP - NSLBC – APWSIP – i.e. Rehabilitation and
modernization of 21st Main Branch Canal from KM. 0.000 to KM. 52.300 of
Nagarjunasagar Lal Bahadur Canal,
A.P, India
- Bid Reference No Package No: LC – KMM - 6. [Insert number]
- DO NOT OPEN BEFORE 15.30 hours on 11.03.2008.
19.3 In addition to the identification required in Sub-Clause 19.2, the inner envelopes shall indicate the name and
address of the bidder to enable the bid to be returned unopened in case it is declared late, pursuant to Clause
21.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
16
19.4 If the outer envelope is not sealed and marked as above, the Employer will assume no responsibility for the
misplacement or premature opening of the bid.
20. Deadline for Submission of the Bids
20.1 Bids must be received by the Employer at the address specified above no later than 15.00 hours
on 11.03.2008. In the event of the specified date for the submission of bids declared a holiday for the
Employer, the Bids will be received up to the appointed time on the next working day.
20.2 The Employer may extend the deadline for submission of bids by issuing an amendment in accordance with
Clause 10, in which case all rights and obligations of the Employer and the bidders previously subject to the
original deadline will then be subject to the new deadline.
21. Late Bids
21.1 Any Bid received by the Employer after the deadline prescribed in Clause 20 will be returned unopened to the
bidder.
22. Modification and Withdrawal of Bids
22.1 Bidders may modify or withdraw their bids by giving notice in writing before the deadline prescribed in
Clause 20.
22.2 Each Bidder's modification or withdrawal notice shall be prepared, sealed, marked, and delivered in
accordance with Clause 18 & 19, with the outer and inner envelopes additionally marked
"MODIFICATION" or "WITHDRAWAL", as appropriate.
22.3 No bid may be modified after the deadline for submission of Bids.
22.4 Withdrawal or modification of a Bid between the deadline for submission of bids and the expiration of the
original period of bid validity specified in Clause 15.1 above or as extended pursuant to Clause 15.2 may
result in the forfeiture of the Bid security pursuant to Clause 16.
22.5 Bidders may offer discounts to, or modify the prices of their Bids only by submitting Bid modifications in
accordance with this clause, or included in the original Bid submission.
E. Bid Opening and Evaluation
23. Bid Opening
23.1 The Employer will open all the Bids received (except those received late), including modifications made
pursuant to Clause 22, in the presence of the Bidders or their representatives who choose to attend at
15-30.hours on the date and the place specified in Clause 20. In the event of the specified date of Bid opening
being declared a holiday for the Employer, the Bids will be opened at the appointed time and location on the
next working day.
23.2 Envelopes marked "WITHDRAWAL" shall be opened and read out first. Bids for which an acceptable
notice of withdrawal has been submitted pursuant to Clause 22 shall not be opened. Subsequently all
envelopes marked “Modification” shall be opened and the submissions therein read out in appropriate detail.
23.3 The Bidders' names, the Bid prices, the total amount of each Bid and of any alternative Bid (if alternatives
have been requested or permitted), any discounts, Bid modifications and withdrawals, the presence or absence
of Bid security, and such other details as the Employer may consider appropriate, will be announced by the
Employer at the opening. No bid shall be rejected at bid opening except for the late bids pursuant to Clause
21. Bids [and modifications] sent pursuant to Clause 22 that are not opened and read out at bid opening will
not be considered for further evaluation regardless of the circumstances. Late and withdrawn bids will be
returned un-opened to bidders.
23.4 The Employer shall prepare minutes of the Bid opening, including the information disclosed to those present
in accordance with Sub-Clause 23.3.
24. Process to Be Confidential
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
17
24.1 Information relating to the examination, clarification, evaluation, and comparison of Bids and
recommendations for the award of a contract shall not be disclosed to Bidders or any other persons not
officially concerned with such process until the award to the successful Bidder has been announced. Any
effort by a Bidder to influence the Employer's processing of Bids or award decisions may result in the
rejection of his Bid.
25. Clarification of Bids
25.1 To assist in the examination, evaluation, and comparison of Bids, the Employer may, at his discretion, ask
any Bidder for clarification of his Bid, including breakdowns of the unit rates. The request for clarification
and the response shall be in writing or by cable, but no change in the price or substance of the Bid shall be
sought, offered, or permitted except as required to confirm the correction of arithmetic errors discovered by
the Employer in the evaluation of the Bids in accordance with Clause 27.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to its bid from the
time of the bid opening to the time the contract is awarded. If the Bidder wishes to bring additional
information to the notice of the Employer, it should do so in writing.
25.3 Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid comparison or
contract award decisions may result in the rejection of the Bidders’ bid.
26. Examination of Bids and Determination of Responsiveness
26.1 Prior to the detailed evaluation of Bids, the Employer will determine whether each Bid (a) meets the
eligibility criteria defined in Clause 3; (b) has been properly signed; (c) is accompanied by the required
securities and; (d) is substantially responsive to the requirements of the Bidding documents.
26.2 A substantially responsive Bid is one which conforms to all the terms, conditions, and specifications of the
Bidding documents, without material deviation or reservation. A material deviation or reservation is one (a)
which affects in any substantial way the scope, quality, or performance of the Works; (b) which limits in any
substantial way, inconsistent with the Bidding documents, the Employer's rights or the Bidder's obligations
under the Contract; or (c) whose rectification would affect unfairly the competitive position of other Bidders
presenting substantially responsive Bids.
26.3 If a Bid is not substantially responsive, it will be rejected by the Employer, and may not subsequently be
made responsive by correction or withdrawal of the non-conforming deviation or reservation.
27. Correction of Errors
27.1 Bids determined to be substantially responsive will be checked by the Employer for any arithmetic errors.
Errors will be corrected by the Employer as follows:
(a) where there is a discrepancy between the rates in figures and in words, the rate in words will govern;
and
(b) where there is a discrepancy between the unit and the line item total resulting from multiplying the
unit rate by the quantity, the unit rate as quoted will govern.
27.2 The amount stated in the Bid will be adjusted by the Employer in accordance with the above procedure for
the correction of errors and, with the concurrence of the Bidder, shall be considered as binding upon the
Bidder. If the Bidder does not accept the corrected amount the Bid will be rejected, and the Bid security may
be forfeited in accordance with Sub-Clause 16.6 (b).
28. Deleted
29. Evaluation and Comparison of Bids
29.1 The Employer will evaluate and compare only the Bids determined to be substantially responsive in
accordance with Clause 26.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
18
29.2 In evaluating the Bids, the Employer will determine for each Bid the evaluated Bid Price by adjusting the Bid
Price as follows:
(a) making any correction for errors pursuant to Clause 27; or
(b) making an appropriate adjustments for any other acceptable variations, deviations; and
(c) making appropriate adjustments to reflect discounts or other price modifications offered in
accordance with Sub Clause 22.5.
29.3 The Employer reserves the right to accept or reject any variation, deviation, or alternative offer. Variations,
deviations, and alternative offers and other factors which are in excess of the requirements of the Bidding
documents or otherwise result in unsolicited benefits for the Employer shall not be taken into account in Bid
evaluation.
29.4 The estimated effect of the price adjustment conditions under Clause 47 of the Conditions of Contract, during
the period of implementation of the Contract, will not be taken into account in Bid evaluation.
29.5 If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer's estimate of the cost of
work to be performed under the contract, the Employer may require the Bidder to produce detailed price
analyses for any or all items of the Bill of Quantities, to demonstrate the internal consistency of those prices
with the construction methods and schedule proposed. After evaluation of the price analyses, the Employer
may require that the amount of the performance security set forth in Clause 34 be increased at the expense of
the successful Bidder to a level sufficient to protect the Employer against financial loss in the event of default
of the successful Bidder under the Contract.
30. Deleted
F. Award of Contract
31. Award Criteria
31.1 Subject to Clause 32, the Employer will award the Contract to the Bidder whose Bid has been determined to
be substantially responsive to the Bidding documents and who has offered the lowest evaluated Bid Price,
provided that such Bidder has been determined to be (a) eligible in accordance with the provisions of Clause
3, and (b) qualified in accordance with the provisions of Clause 4.
31.2 If, pursuant to Clause 12.2 this contract is being let along with other contracts, the lowest evaluated Bid Price
will be determined when evaluating this contract in conjunction with other contracts to be awarded
concurrently, taking into account any discounts offered by the bidders for the award of more than one
contract.
32. Employer's Right to Accept any Bid and to Reject any or all Bids
32.1 Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid, and to cancel the
Bidding process and reject all Bids, at any time prior to the award of Contract, without thereby incurring any
liability to the affected Bidder or Bidders or any obligation to inform the affected Bidder or Bidders of the
grounds for the Employer's action.
33. Notification of Award and Signing of Agreement
33.1 The Bidder whose Bid has been accepted will be notified of the award by the Employer prior to expiration of the
Bid validity period by cable, telex or facsimile confirmed by registered letter. This letter (hereinafter and in the
Conditions of Contract called the "Letter of Acceptance") will state the sum that the Employer will pay the
Contractor in consideration of the execution, completion, and maintenance of the Works by the Contractor as
prescribed by the Contract (hereinafter and in the Contract called the "Contract Price").
33.2 The notification of award will constitute the formation of the Contract, subject only to the furnishing of a
performance security in accordance with the provisions of Clause 34.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
19
33.3 The Agreement will incorporate all agreements between the Employer and the successful Bidder. It will be kept
ready for signature of the successful bidder in the office of employer within 28 days following the notification of
award along with the Letter of Acceptance. Within 21 days of receipt, the successful Bidder will sign the
Agreement and deliver it to the Employer.
33.4 Upon the furnishing by the successful Bidder of the Performance Security, the Employer will promptly notify the
other Bidders that their Bids have been unsuccessful.
34. Performance Security
34.1 Within 21 days of receipt of the Letter of Acceptance, the successful Bidder shall deliver to the Employer a
Performance Security in any of the forms given below for an amount equivalent to 5% of the Contract price plus
additional security for unbalanced Bids in accordance with Clause 29.5 of ITB and Clause 52 of Conditions of
Contract:
- a bank guarantee in favour of Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam
in the form given in Section 8; or
- Certified cheque/Bank draft, in favour of Pay and Accounts Officer, N.S. Project, Tekulapally,
Khammam payable at Khammam.
34.2 If the performance security is provided by the successful Bidder in the form of a Bank Guarantee, it shall be
issued either (a) at the Bidder's option, by a Nationalized/Scheduled Indian bank or (b) by a foreign bank located
in India and acceptable to the Employer or (c) by a foreign bank through a correspondent Bank in India
[scheduled or nationalized]. The performance security of a Joint Venture shall be in the name of the joint
venture’.
34.3 Failure of the successful bidder to comply with the requirements of sub-clause 34.1 shall constitute a breach of
contract, cause for annulment of the award, forfeiture of the bid security, and any such other remedy the Employer
may take under the contract, and the Employer may resort to awarding the contract to the next ranked bidder.
35 Advance Payment and Security
35.1 The Employer will provide an Advance Payment on the Contract Price as stipulated in the Conditions of Contract,
subject to maximum amount, as stated in the Contract Data.
36. Adjudicator
36.1 The Employer proposes that Sri R.Satyanarayana Rao, Chief Engineer (Retired) be appointed as Adjudicator
under the Contract, at a daily fee of Rs. 1000/- plus reimbursable expenses. If the Bidder disagrees with this
proposal, the Bidder should so state in the Bid. If in the Letter of Acceptance, the Employer has not agreed on the
appointment of the Adjudicator, the Adjudicator shall be appointed by President , Institute of Engineers (I), A.P.,
Hyderabad at the request of either party.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
20
37. Fraud and Corruption.
37.1 The Bank’s policy to require that Borrowers (including beneficiaries of Bank loans), as well as Bidders, Suppliers,
Contractors, and their subcontractors under Bank-financed contracts, observe the highest standard of ethics during the
procurement and execution of such contracts.1 In pursuit of this policy, the Bank:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) “corrupt practice”2 is the offering, giving, receiving, or soliciting, directly or indirectly, of anything of
value to influence improperly the action of another party;
(ii) “fraudulent practice” 3 is any act or omission including misrepresentation , that knowingly or
recklessly misleads, or attempts to mislead, a party to obtain a financial or tother benefit or to avoid
an obligation;
(iii) “collusive practice” 4 is an arrangement between two or more parties designed to achieve an improper
purpose, including to influence improperly the actions of another party;
(iv) “coercive practice” 5 is impairing or harming, or harming , or threatening to impair or harm, directly
or indirectly, any party or the property of the party to influence improperly the actions of a party;
(v) “obstructive practice” is
(aa) deliberately destroying, falsifying, altering or concealing of evidence material to the investigation or
making false statements to investigators in order to materially impede a Bank investigation into
allegations of a corrupt, fraudulent, coercive or collusive practice and/or threatening, harassing or
knowledge of matters relevant to the investigation or from pursuing the investigation or
(bb) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for
under sub-clause 3.1 (e) below.
(b) will reject a proposal for award if it determines that the Bidder recommended for award has, directly or through
an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for the
Contract in question;
(c) will cancel the portion of the loan allocated to a contract if it determines at any time that representatives of the
Borrower or of a beneficiary of the loan engaged in corrupt, fraudulent, collusive or coercive practices during
the procurement or the execution of that contract, without the Borrower having taken timely and appropriate
action satisfactory to the Bank to address such practices when they occur;
(d) will sanction a firm or individual, including declaring them ineligible, either indefinitely or for a stated period
of time, to be awarded a Bank-financed contract if it at any time determines that the firm has directly or through
an agent, engaged, in corrupt, fraudulent, collusive or coercive or obstructive practices in competing for, or in
executing, a Bank-financed contract; and
(e) will have the right to require that a provision be included in Bidding Documents and in contracts financed by a
Bank loan, requiring Bidders, Suppliers, Contractors and their sub contractors to permit the Bank to inspect
their accounts and records and other documents relating to the bid submission and contract performance and to
have them audited by auditors appointed by the Bank.
1 in this context, an action taken by a bidder, supplier, contractor or a subcontractor to influence the procurement process or contract execution
for undue advantage is improper.
2 “another party” refers to a public official” includes World Bank staff and employees of contract execution]. In this context, “public official”
includes World Bank staff and employees of other organizations taking a reviewing procurement decisions.
3 a “party” refers to public official; the terms “benefits” and “obligation” relate to the procurement process or contract execution and the “act or
omission” is intended to influence the procurement process or contract execution.
4 “parties” refers to participants in the procurement process (including public officials) attempting to establish bid prices at artificial, non
competitive levels.
5 a “party” refers to a participant in the procurement process or contract execution.
37.2 Furthermore, Bidders shall be aware of the provision stated in sub-clause 23.2 and 59.2 of the Conditions of
Contract.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
21
SECTION 2
FORMS OF BID, QUALIFICATION INFORMATION AND
LETTER OF ACCEPTANCE
TABLE OF FORMS:
- CONTRACTOR’S BID
- QUALIFICATION INFORMATION
- LETTER OF ACCEPTANCE
- NOTICE TO PROCEED WITH THE WORK
- AGREEMENT FORM
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
22
Contractor's Bid
Description of the Works: NSLBC - APWSIP - Rehabilitation and Modernization of 21st MBC From
KM 0.000 TO 52.300.
BID
To : The Superintending Engineer,
Address : Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam, Khammam District, A.P
GENTLEMEN,
Having examined the bidding documents including addendum, we offer to execute the Works described above in
accordance with the Conditions of Contract, Specifications, Drawings and Bill of Quantities accompanying this Bid
for the Contract Price of Rs.52,00,17,475.59 [in figures]( Rupees Fifty two crores seventeen thousand four hundred
seventy five and paisa fifty nine only.) [in letters].1
The advance Payment required is: Rupees As per Tender conditions.
We accept the appointment of Sri R.Satyanarayana, CE (Retd.) I&CAD Dept., Hyderabad as the Adjudicator.
(OR)
We do not accept the appointment of ___________________ as the Adjudicator and propose instead that
_______________________ be appointed as Adjudicator whose daily fees and biographical data are attached.
This Bid and your written acceptance of it shall constitute a binding contract between us. We understand that you are
not bound to accept the lowest or any Bid you receive.
We hereby certify that we have taken steps to ensure that no person acting for us or on our behalf will engage in
bribery.
We also undertake that, in competing for and, if the award is made to us, in executing) the above contract, we will
strictly observe the laws against fraud and corruption in force in India namely “Prevention of Corruption Act 1988”.
Commissions or gratuities, if any, paid or to be paid by us to agents relating to this Bid, and to contract execution if we
are awarded the contract, are listed below :
Name and address of agent Amount Purpose of Commission or gratuity
________NONE________ _NONE_ ______________NONE________
______________________ ________ ____________________________
______________________ ________ ____________________________
(if none, state “none”)
3 To be filled in by the Bidder, together with his particulars and date of submission at the bottom of the Form of Bid.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
23
We hereby confirm that this Bid complies with the Eligibility, Bid Validity and Bid Security required by the Bidding
documents.
Yours faithfully,
Authorized Signature:
Name & Title of Signatory:
Name of Bidder : M/s Rahava Constructions & M/s B.V.S.R. Constructions (J.V)
Address : Hyderabad.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
24
Qualification Information
The information to be filled in by the Bidder in the following pages will be used for purposes of post qualification as
provided for in Clause 4 of the Instructions to Bidders. This information will not be incorporated in the Contract.
1. For Individual Bidders
1.1 Constitution or legal status of Bidder Attached with Technical Bid.
[Attach copy]
Place of registration: Hyderabad
Principal place of business: Hyderabad
Power of attorney of signatory of Bid Attached with technical bid.
[Attach]
Total value of Civil Engineering construction work
executed and payments received in the last five years
(in Rs. Lakhs)
M/s Raghava BVSR Constructions
Constructions. Rs. in Lakhs.
Rs. in Lakhs.
2002-2003 -- Rs.5023.14
2003-2004 -- Rs.4602.94
2004-2005 -- Rs.8090.59
2005-2006 Rs.2380.37 Rs.7455.99
1.2
2006- 2007 Rs.2640.61 Rs.7473.83
1.3.1 Work performed as prime contractor (in the same name) on works of a similar nature over the last five years. 2002 – 03 , 2003-04, 2004-05,2005-06 & 2006 – 07.
Project
Name
Name
of the
Employer*
Description
of work
Contract No. Value of
contract
(Rs.
Million)
Date of
issue of
work
order
Stipulated
period of
completion
Actual date
of
completion*
Remarks
explaining
reasons for delay
and work
completed
AMRP EE/AMRP
Division No.5,
G.V.Gudem.
Package.
No.78
22 SE /
2004-05
dt.24.03.05.
40.52
Crores.
24.03.05 3 Years. -- Completed in
time (by M/s
Raghava
Constructions.
SRSP EE/FFC
Division No.1,
Metpally.
Constructio
ns of
Aqueduct.
10 FFC/04-05,
dt.02.12.2004.
66.58
Crores
02.12.04 18 M 30.04.07 E.O.T. granted
and completed
(M/s BVSR
Constructions)
1.3.2 Quantities of work executed as prime contractor (in the same name and style) in the last five years: Viz 2002-03 to 2006-07.
Year Name Name Quantity of work performed (cum) @ Remarks *
of the
Work
of the
Employer*
Cement concrete
(including RCC&PCC and any
lining concrete)
Earth work (indicate contract Ref)
2002-03
2003-04
2004 -05
2005-06
--
--
--
--
--
2006-07 -- -- 28195 Cum (P.51 & 53)
M/s Raghava Constructions
101360.84 Cum (P.135)
M/s BVSR Constructions
782545 Cum (P.53)
M/s Raghava Constructions
940956 Cum (P.129)
M/s BVSR Constructions
Certificate attached with
technical bid.
*Attach certificate(s) from the Engineer(s)-in-Charge
β Attach certificate from Chartered Accountant.
@ The item of work for which data is requested should tally with that specified ITB clause 4.5 A ( c ).
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
25
1.4 Information on Bid Capacity (works for which bids have been submitted and works which are yet to be completed) as on the date of this bid.
(A) Existing commitments and on-going works:
Description
of work
Place &
State
Contract
No. &
Date.
Name and
Address
of
Employer
Value
of
Contract
(Rs.
Million)
Stipulated
period of
completion
Value of Work * remaining to
be completed (Rs. million)
Anticipated
date of
completion.
1 2 3 4 5 6 7 8
As per statement attached with technical bid of both (J.V)
firms. M/s Raghava Constructions
Rs. 765.49 Lakhs.
M/s BVSR Constructions
Rs.24980.35 Lakhs.
--
(B) Works for which bids already submitted:
___________________________________________________________________________________________________________________
Description Place Name and Estimated Stipulated Date when Remarks
of & Address of value of works period of decision is if any
Work State Employer (Rs. million) completion expected
(1) (2) (3) (4) (5) (6) (7)
Statement attached with technical bid of both (J.V) firms.
* Attach certificate(s) from the Engineer(s)-in-Charge.
1.5 The following items of Contractor's Equipment are essential for carrying out the Works. The Bidder should list all the information requested
below. Refer also to Sub Clause 4.3 (d) of the Instructions to Bidders.
_______________________________________________________________________________________________________________________
Item of Requirement Availability proposals Remarks
equipment No. Capacity Owned/leased/ Nos. / Age/ (From whom to be
to be procured capacity condition purchased)
_______________________________________________________________________________________________________________________
- Hydraulic Excavators 10 Nos. (6 of + 1 Cum and
4 of + 0.50 Cum Capacity)
- Tippers / Trucks 40 Nos. 10 Tonnes Capacity
- Power Rollers for compaction 5 Nos. 8 to 10 Tonnes
Plate Vibrators ( for consolidation
of CC Lining placed manually)
(Fuel operated / Electric operated). 8 Nos.
- Slope Compactors (for sub-grade
compaction) 3 Nos.
- Mechanical concrete mixtures,
( 14/10 cft or 10/7 cft) 4 Nos.
- Weigh Batcher 2 No.
- Concrete paver (for placement of side lin
ing) (15 – 20 Cum/Hr) 5 Nos
- Shot creeting machines (with accessories) 2Nos
As per the details attached with Technical Bids of both (J.V) firms.
Concrete production & Transporation
- (i) Batching & mixing plants
( + 20 - 30 Cum/Hr) 3 Nos
- (ii) Truck – mounted transit
concrete mixers 9 Nos
(3 Cum drum capacity)
Alternatively
- Mobile self loading, weigh batching 4 Nos
and mixing, and transporting concrete
mixers (+ 2.5 Cum drum capacity)
- Vibrators for compaction of concrete 6 Nos.
(immersion/needle vibrators)
- Water Tankers (+ 5000 Liters each) 4 Nos.
- Fine air water spray nozzles 4 Nos.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
26
1.6 Qualifications and experience of key personnel proposed for administration and execution of the Contract. Attach
biographical data. Refer also to Sub Clause 4.3 (e) and 4.5 (B) (b) of instructions to Bidders and Sub Clause 9.1 of
the Conditions of Contract.
Position Name Qualifications Years of
experience
(general)
Years of
experience in
the proposed
position
Project Manager Sri P.Prasada Reddy
Graduate 20 Years 20Years
Technical Agents
Sri. T.S.Kameswara Rao B.E. (Civil) 43 Years 3 Years
1 Graduate Engineer
Sri. M.Venkateswara Rao L.C.E. 30 Years 2 Years
2 Diploma Holder.
Sri. S.Sambasiva Rao L.C.E. 30 Years 2 Years
1.7 Proposed subcontracts and firms involved. [Refer ITB Clause 4.3 (j)]
_______________________________________________________________________________________
Sections Value of Sub-contractor Experience in
of the works Sub-contract (name and address) similar work
_______________________________________________________________________________________
-- NIL --
______________________________________________________________________________________
1.8 Financial reports for the last five years: balance sheets, profit and loss statements, auditors' reports (in case of
companies/corporation), etc. List them below and attach copies.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash in hand, lines of credit,
etc. List them below and attach copies of support documents [sample format attached].
1.10. Name, address, and telephone, telex, and fax numbers of the Bidders' bankers who may provide references if
contacted by the Employer.
1.11 Information on litigation history in which the Bidder is involved.
__________________________________________________________________________________
Other party(ies) Employer Cause of dispute Amount involved Remarks showing
Present status
_________________________________________________________________________________
-- NIL --
__________________________________________________________________________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
27
1.12 Statement of compliance under the requirements of Sub Clause 3.2 of the instructions to Bidders.
-- NIL --
1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and charts as necessary to
comply with the requirements of the Bidding documents. [Refer ITB Clause 4.1 and 4.3 (k)].
2. Qualification Information.
‘2. Joint Ventures -
2.1 The information listed in 1.1-1.12 above shall be provided for each partner of the joint venture.
2.2 The information in 1.13 above shall be provided for the joint venture.
2.3 Attach the power of attorney of the signatory [ies] of the bid authorizing signature of the bid on behalf of the
joint venture.
2.4 Attach the agreement among all partners of the joint venture [and which is legally binding on all partners], which
shows the requirements as indicated in sub-clause 4.4 of the Instructions to Bidders’. Alternatively, a Letter of
Intent to execute a Joint Venture Agreement in the event of a successful bid shall be signed by all partners and
submitted with the bid, together with a copy of the proposed Agreement.
2.5 Furnish details of participation proposed in the joint venture as below:
DETAILS OF PARTICIPATION IN THE JOINT VENTURE
PARTICIPATION DETAILS FIRM’A’ (Lead Partner)
FIRM ‘B’
Financial
80 %
20 %
Name of the Banker(s) Vijaya Bank, Vijayanagar Colony,
Hyderabad.
Andhra Bank,
Saidabad,
Hyderabad.
Planning
100 %
--
Construction Equipment
50 %
50 %
Key Personnel
50 %
50 %
Execution of Work
(Give details on contribution of
each).
--
--
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
28
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the requirements of Clause 4 of the
Instructions to the Bidders, if applicable.
-- NIL --
_______________________________________________________________________________________________
SAMPLE FORMAT FOR EVIDENCE OF ACCESS TO OR AVAILABILITY OF CREDIT FACILITIES –* CLAUSE 4.5 [B] [c] OF ITB
BANK CERTIFICATE
This is to certify that M/s. …………………………… is a reputed company with a good financial standing.
If the contract for the work, namely …………………………………………………………. [funded by the World
Bank] is awarded to the above firm, we shall be able to provide overdraft/credit facilities to the extent of Rs.
…………… to meet their working capital requirements for executing the above contract.
__ Sd. __
Name of Bank
Senior Bank Manager
Address of the Bank
• Change the text as follows for Joint Venture:
This is to certify that M/s. …………………………………………………………. Who has formed a JV with
M/s. …………………………………….. and M/s. ………………………………….. for participating in this bid, is
a reputed company with a good financial standing.
If the contract for the work, namely …………………………………………………….[ funded by the World
Bank] is awarded to the above Joint Venture, we shall be able to provide over draft / credit facilities to the
extent of Rs. …………………. To M/s. ……………………….. to meet the working capital requirements for
executing the above contract.
[ This should be given by the JV members in proportion to their financial participation.].
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
29
Form ……….
(Name of the Project)
(Declaration regarding customs/excise duty exemption for materials/
construction equipment bought for the work)
(Bidder’s Name and Address)
To:
The Superintending Engineer,
NSLBC O&M Circle, Tekulapally,
Khammam A.P.
(Name of the Employer)
Dear Sir:
Re: [Name of Work] NSLBC - APWSIP - Rehabilitation and Modernization of 21st MBC From
KM 0.000 TO 52.300. - Certificate for Import/Procurement of Goods / Construction
Equipment
1. We confirm that we are solely responsible for obtaining customs/excise duty waivers which we have considered
in our bid and in case of failure to receive such waivers for reasons whatsoever, the Employer will not
compensate us.
2. We are furnishing below the information required by the Employer for issue of the necessary certificates in
terms of the Government of India Central Excise Notification No. 108/95 and Customs Notification No. 85/99.
3. The goods/construction equipment for which certificates are required are as under:
Items Make/
Brand
Name
Capacity
[where
applicable]
Quantity Value State whether it will
be procured locally
or imported [if so
from which country]
Remarks regarding
justification for the
quantity and their
usage in works
Goods
[a] Bitumen
[b] Others
As per statement attached with Technical Bid.
Construction Equipment
[a]
[b]
[c]
[d]
As per statement attached with Technical Bid.
4. We agree that no modification to the above list is permitted after bids are opened.
5. We agree that the certificate will be issued only to the extent considered reasonable by the Employer for the
work, based on the Bill of Quantities and the construction programme and methodology as furnished by us
along with the bid.
6. We confirm that the above goods will be exclusively used for the construction of the above work and
construction equipment will not be sold or otherwise disposed of in any manner for a period of five years from
the date of acquisition.
Date: ___________________ (Signature) ____________________
Place: __________________ (Printed Name) _________________
(Designation) __________________
(Common Seal) ________________
This certificate will be issued within 60 days of signing of contract and no subsequent changes will be permitted.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
30
Letter of Acceptance
(letterhead paper of the Employer)
________________________[date]
To: M/s Raghava – BVSR Constructions (J.V) Hyderabad. [Name and address of the Contractor]
Dear Sirs,
This is to notify you that your Bid dated 11.03.08 for execution of the NSP - NSLBC – APWSIP –
Rehabilitation and modernization of 21st Main Branch Canal from KM.0.000 to KM. 52.300 of Nagarjuna Sagar Lal
Bahadur Canal, A.P, India [name of the contract and identification number, as given in the Instructions to Bidders] for
the Contract Price of Rupees Fifty two crores seventeen thousand four hundred and seventy five and paisa fifty nine
only Rs.52,00,17,475.59 [amount in words and figures], as corrected and modified in accordance with the Instructions
to Bidders1 is hereby accepted by our Agency.
We accept/do not accept that __________________________ be appointed as the Adjudicator2.
We note that as per bid, you do not intend to subcontract any component of work.
[OR]
We note that as per bid, you propose to employ M/s. .......................................... as sub-contractor for executing
….........................................
[Delete whichever is not applicable]
You are hereby requested to furnish Performance Security, plus additional security for unbalanced bids
in terms of ITB clause 29.5, in the form detailed in Para 34.1 of ITB for an amount of Rs. 2,60,00,874/- (Performance
Security only) within 21 days of the receipt of this letter of acceptance valid up to 28 days from the date of expiry of
Defects Liability Period i.e. up to 10.12.2013 and sign the contract, failing which action as stated in Para 34.3 of ITB
will be taken.
We have reviewed the construction methodology submitted by you along with the bid in response to ITB Clause
4.3[k] and our comments are given in the attachment. You are requested to submit a revised Program including
environmental management plan as per Clause 27 of General Conditions of Contract within 14 days of receipt of this
letter.
Yours faithfully,
Authorized Signature
Name and Title of Signatory
Name of Agency
1 Delete "corrected and" or "and modified" if only one of these actions applies. Delete "as corrected and modified
in accordance with the Instructions to Bidders" if corrections or modifications have not been effected.
2 To be used only if the Contractor disagrees in his Bid with the Adjudicator proposed by the Employer in the
"Instructions to Bidders."
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
31
Issue of Notice to proceed with the work (letterhead of the Employer)
————— (date)
To
M/s Raghava Constructions & M/s BVSR Constructions (J.V), (name and address of the Contractor)
H.No.3-6-532 / A, Flat.No.201,
Himayatnagar, Hyderabad – 29 (A.P.)
Dear Sirs:
Pursuant to your furnishing the requisite security as stipulated in ITB clause 34.1 and signing of the contract
agreement for the construction of NSP - NSLBC – APWSIP – Rehabilitation and modernization of 21st Main Branch
Canal from KM.0.000 to KM. 52.300 of Nagarjuna Sagar Lal Bahadur Canal, A.P, India @ a Bid Price of
Rs.52,00,17,475.59, you are hereby instructed to proceed with the execution of the said works in accordance with the
contract documents.
Yours faithfully,
(Signature, name and title of
signatory authorized to sign on
behalf of Employer)
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
32
Agreement Form
Agreement
This agreement, made the 13th
day of June 2008, between Sri B.V.Siddhartha, Superintending Engineer, NSLBC
(O&M) Circle, Tekulapally, Khammam (A.P) [name and address of Employer] (hereinafter called “the Employer)” of
the one part and M/s Raghava – BVSR (J.V), Himayatnagar, Hyderabad (A.P.) [name and address of contractor]
(hereinafter called “the Contractor” ) of the other part.
Whereas the Employer is desirous that the Contractor execute NSP - NSLBC – APWSIP – Rehabilitation and
modernization of 21st Main Branch Canal from KM.0.000 to KM. 52.300 of Nagarjuna Sagar Lal Bahadur Canal, A.P,
India [ name and identification number of Contract] (hereinafter called “the Works”) and the Employer has accepted
the Bid by the Contractor for the execution and completion of such Works and the remedying of any defects therein, at
a contract price of Rs.52,00,17,475.59.
NOW THIS AGREEMENT WITNESSETH as follows:
1. In this Agreement, words and expression shall have the same meanings as are respectively assigned to them in
the Conditions of Contract hereinafter referred to, and they shall be deemed to form and be read and construed as
part of this Agreement.
2. In consideration of the payments to be made by the Employer to the Contractor as hereinafter mentioned, the
Contractor hereby covenants with the Employer to execute and complete the Works and remedy any defects
therein in conformity in all aspects with the provisions of the Contract.
3. The Employer hereby covenants to pay the Contractor in consideration of the execution and completion of the
Works and the remedying the defects wherein the Contract Price or such other sum as may become payable
under the provisions of the Contract at the times and in the manner prescribed by the Contract.
4. The following documents shall be deemed to form and be read and construed as part of this Agreement, viz.:
i) Letter of Acceptance;
ii) Notice to proceed with the works;
iii) Contractor’s Bid;
iv) Contract Data;
v) Conditions of contract (including Special Conditions of Contract);
vi) Specifications;
vii) Drawings;
viii) Bill of Quantities; and
ix) Any other document listed in the Contract Data as forming part of the contract.
x) Joint Venture Agreement.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
33
In witness whereof the parties thereto have caused this Agreement to be executed the day and year first before written.
The Common Seal of ____________________________________________________________
was hereunto affixed in the presence of:
Signed, Sealed and Delivered by the said _________________________________________________
_____________________________________________________________________________________
_____________________________________________________________________________________
in the presence of:
Binding Signature of Employer Sd/-
Binding Signature of Contractor Sd/-
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
35
Conditions of Contract
Table of Contents
A. General Page No. C. Quality Control Page No.
1. Definitions 36 33. Identifying Defects 42
2. Interpretation 37 34. Tests 42
3. Language and Law 37 35. Correction of Defects 43
4. Engineer's Decisions 38 36. Uncorrected Defects 43
5. Delegation 38
6. Communications 38
7. Subcontracting 38 D. Cost Control
8. Other Contractors 38 37. Bill of Quantities 43
9. Personnel 39 38. Changes in the Quantities 43
10. Employer’s & Contractor's Risks 39 39. Variations 43
11. Employer's Risks 39 40. Payments for Variations 43
12. Contractor’s Risks 39 41. Cash Flow Forecasts 44
13. Insurance 39 42. Payment Certificates 44
14. Site Investigation Reports 40 43. Payments 44
15. Queries about the Contract 44. Compensation Events 44
Data 40 45. Tax 45
16. Contractor to Construct the 46. Currencies 45
Works 40 47. Price Adjustments 45
17. The Works to Be Completed by 48. Retention 46
the Intended Completion Date 40 49. Liquidated Damages 46
18. Approval by the Engineer 40 50. Bonus 46
19. Safety 40 51. Advance Payment 46
20. Discoveries 40 52. Securities 47
21. Possession of the Site 40 53. Day works 47
22. Access to the Site 40 54. Cost of Repairs 47
23. Instructions 41
24. Disputes 41
25. Procedure for Disputes 41 E. Finishing the Contract
26. Replacement of Adjudicator 41
55. Completion 47
B. Time Control 56. Taking Over 47
27. Program 41 57. Final Account 47
28. Extension of the Intended 58. Operating and Maintenance Manuals 47
Completion Date 42 59. Termination 47
29. Acceleration 42 60. Payment upon Termination 48
30. Delays Ordered by the 61. Property 48
Engineer 42 62. Release from Performance 48
31. Management Meetings 42 63. Suspension of World Bank Loan 48
32. Early Warning 42 or Credit
F. Special Conditions of Contract 49
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
36
Conditions of Contract
A. General
1. Definitions
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of Contract but keep
their defined meanings. Capital initials are used to identify defined terms.
The Adjudicator is the person appointed jointly by the Employer and the Contractor to resolve disputes
in the first instance, as provided for in Clauses 24 and 25. The name of the Adjudicator is defined in the
Contract Data.
Bill of Quantities means the priced and completed Bill of Quantities forming part of the Bid.
Compensation Events are those defined in Clause 44 hereunder.
The Completion Date is the date of completion of the Works as certified by the Engineer in accordance
with Sub Clause 55.1.
The Contract is the contract between the Employer and the Contractor to execute, complete and
maintain the Works. It consists of the documents listed in Clause 2.3 below.
The Contract Data defines the documents and other information which comprise the Contract.
The Contractor is a person or corporate body whose Bid to carry out the Works has been accepted by
the Employer.
The Contractor's Bid is the completed Bidding document submitted by the Contractor to the Employer.
The Contract Price is the price stated in the Letter of Acceptance and thereafter as adjusted in
accordance with the provisions of the Contract.
Days are calendar days; months are calendar months.
A Defect is any part of the Works not completed in accordance with the Contract.
The Defects Liability Period is the period named in the Contract Data and calculated from the
Completion Date.
The Employer is the party who will employ the Contractor to carry out the Works.
The Engineer is the person named in the Contract Data (or any other competent person appointed and
notified to the contractor to act in replacement of the Engineer) who is responsible for supervising the
execution of the works and administering the Contract.
Equipment is the Contractor's machinery and vehicles brought temporarily to the Site to construct the
Works.
The Initial Contract Price is the Contract Price listed in the Employer's Letter of Acceptance.
The Intended Completion Date is the date on which it is intended that the Contractor shall complete
the Works. The Intended Completion Date is specified in the Contract Data. The Intended Completion
Date may be revised only by the Engineer by issuing an extension of time.
Materials are all supplies, including consumables, used by the contractor for incorporation in the
Works.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
37
Plant is any integral part of the Works which is to have a mechanical, electrical, electronic or chemical
or biological function.
The Site is the area defined as such in the Contract Data.
Site Investigation Reports are those which were included in the Bidding documents and are factual
interpretative reports about the surface and sub-surface conditions at the site.
Specification means the Specification of the Works included in the Contract and any modification or
addition made or approved by the Engineer.
The Start Date is given in the Contract Data. It is the date when the Contractor shall commence
execution of the works. It does not necessarily coincide with any of the Site Possession Dates.
A Subcontractor is a person or corporate body who has a Contract with the Contractor to carry out a
part of the work in the Contract which includes work on the Site.
Temporary Works are works designed, constructed, installed, and removed by the Contractor which
are needed for construction or installation of the Works.
A Variation is an instruction given by the Engineer which varies the Works.
The Works are what the Contract requires the Contractor to construct, install, and turn over to the
Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also means female or
neuter, and the other way around. Headings have no significance. Words have their normal meaning
under the language of the Contract unless specifically defined. The Engineer will provide instructions
clarifying queries about the Conditions of Contract.
2.2 If sectional completion is specified in the Contract Data, references in the Conditions of Contract to the
Works, the Completion Date, and the Intended Completion Date apply to any Section of the Works
(other than references to the Completion Date and Intended Completion date for the whole of the
Works).
2.3 The documents forming the Contract shall be interpreted in the following order of priority:
(1) Agreement
(2) Letter of Acceptance, notice to proceed with the works
(3) Contractor’s Bid
(4) Contract Data
(5) Conditions of Contract including Special Conditions of Contract
(6) Specifications
(7) Drawings
(8) Bill of Quantities and
(9) any other document listed in the Contract Data as forming part of the Contract.
3. Language and Law
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
38
3.1 The language of the Contract and the law governing the Contract are stated in the Contract Data.
4. Engineer's Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual matters between the
Employer and the Contractor in the role representing the Employer.
5. Delegation
5.1 The Engineer may delegate any of his duties and responsibilities to other people except to the
Adjudicator after notifying the Contractor and may cancel any delegation after notifying the Contractor.
6. Communications
6.1 Communications between parties which are referred to in the conditions are effective only when in
writing. A notice shall be effective only when it is delivered (in terms of Indian Contract Act).
7. Subcontracting
7.1 The Contractor may subcontract with the approval of the Engineer but may not assign the Contract
without the approval of the Employer in writing. Subcontracting does not alter the Contractor's
obligations.
7.2 The contractor shall not be required to obtain any consent from the employer for:
a) the sub-contracting of any part of the Works for which the Sub-contractor is named in the contract;
b) the provision of labour; and
c) the purchase of materials which are in accordance with the standards specified in the Contract.
Beyond this if the contractor proposes sub-contracting any part of the work during execution of works, because
of some unforeseen circumstances to enable him to complete the work as per terms of the contract, the
Engineer will consider the following before according approval:
- The contractor shall not sub-contract the whole of the Works.
- The contractor shall not sub-contract any part of the Work without prior consent of the Engineer. Any
such consent shall not relieve the contractor from any liability or obligations under the contract and he
shall be responsible for the acts, defaults and neglects of any sub-contractor, his agents or workmen as
fully as if they were the acts, defaults or neglects of the contractor, his agents or workmen.
- The Engineer should satisfy whether (a) the circumstances warrant such sub-contracting; and (b) the sub-
contractors so proposed for the Work possess the experience, qualifications and equipment necessary for
the job proposed to be entrusted to them in proportion to the quantum of work to be sub-contracted.
- If payments are proposed to be made directly to that sub-contractor, this should be subject to specific
authorization by the prime contractor so that this arrangement does not alter the contractor's liability or
obligations under the contract.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public authorities, utilities, and
the Employer between the dates given in the Schedule of Other Contractors. The Contractor shall as
referred to in the Contract Data, also provide facilities and services for them as described in the
Schedule. The employer may modify the schedule of other contractors and shall notify the contractor of
any such modification.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
39
9. Personnel
9.1 The Contractor shall employ the key personnel named in the Schedule of Key Personnel as referred to in
the Contract Data to carry out the functions stated in the Schedule or other personnel approved by the
Engineer. The Engineer will approve any proposed replacement of key personnel only if their
qualifications, abilities, and relevant experience are substantially equal to or better than those of the
personnel listed in the Schedule.
9.2 If the Engineer asks the Contractor to remove a person who is a member of the Contractor’s staff or his
work force stating the reasons the Contractor shall ensure that the person leaves the Site within seven
days and has no further connection with the work in the Contract.
10. Employer’s and Contractor's Risks
10.1 The Employer carries the risks which this Contract states are Employer’s risks, and the Contractor
carries the risks which this Contract states are Contractor’s risks.
11. Employer's Risks
11.1 The Employer is responsible for the excepted risks which are (a) in so far as they directly affect the
execution of the Works in the Employer’s country, the risks of war, hostilities, invasion, act of foreign
enemies, rebellion, revolution, insurrection or military or usurped power, civil war, riot commotion or
disorder (unless restricted to the Contractor’s employees), and contamination from any nuclear fuel or
nuclear waste or radioactive toxic explosive, or (b) a cause due solely to the design of the Works, other
than the Contractor’s design.
12. Contractor’s Risks
12.1 All risks of loss of or damage to physical property and of personal injury and death which arise during
and in consequence of the performance of the Contract other than the excepted risks are the
responsibility of the Contractor.
13. Insurance
13.1 The Contractor shall provide, in the joint names of the Employer and the Contractor, insurance cover
from the Start Date to the end of the Defects Liability Period, in the amounts and deductibles stated in
the Contract Data for the following events which are due to the Contractor’s risks:
(a) loss of or damage to the Works, Plant and Materials;
(b) loss of or damage to Equipment;
(c) loss of or damage of property (except the Works, Plant, Materials and Equipment) in connection
with the Contract; and
(d) personal injury or death.
13.2 Policies and certificates for insurance shall be delivered by the Contractor to the Engineer for the
Engineer’s approval before the Start Date. All such insurance shall provide for compensation to be
payable in the types and proportions of currencies required to rectify the loss or damage incurred.
13.3 If the Contractor does not provide any of the policies and certificates required, the Employer may effect
the insurance which the Contractor should have provided and recover the premiums the Employer has
paid from payments otherwise due to the Contractor or, if no payment is due, the payment of the
premiums shall be a debt due.
13.4 Alterations to the terms of an insurance shall not be made without the approval of the Engineer.
13.5 Both parties shall comply with any conditions of the insurance policies.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
40
14. Site Investigation Reports
14.1 The Contractor, in preparing the Bid, shall rely on any site Investigation Reports referred to in the
Contract Data, supplemented by any information available to the Bidder.
15. Queries about the Contract Data
15.1 The Engineer will clarify queries on the Contract Data.
16. Contractor to Construct the Works
16.1 The Contractor shall construct and install the Works in accordance with the Specification and Drawings,
and as per instructions of Engineer.
17. The Works to Be Completed by the Intended Completion Date
17.1 The Contractor may commence execution of the Works on the Start Date and shall carry out the Works
in accordance with the program submitted by the Contractor, as updated with the approval of the
Engineer, and complete them by the Intended Completion Date.
18. Approval by the Engineer
18.1 The Contractor shall submit Specifications and Drawings showing the proposed Temporary Works to
the Engineer, who is to approve them if they comply with the Specifications and Drawings.
18.2 The Contractor shall be responsible for design of Temporary Works.
18.3 The Engineer's approval shall not alter the Contractor's responsibility for design of the Temporary
Works.
18.4 The Contractor shall obtain approval of third parties to the design of the Temporary Works where
required.
18.5 All Drawings prepared by the Contractor for the execution of the temporary or permanent Works, are
subject to prior approval by the Engineer before their use.
19. Safety
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
20. Discoveries
20.1 Anything of historical or other interest or of significant value unexpectedly discovered on the Site is the
property of the Employer. The Contractor is to notify the Engineer of such discoveries and carry out the
Engineer's instructions for dealing with them.
21. Possession of the Site
21.1 The Employer shall give possession of all parts of the Site to the Contractor. If possession of a part is
not given by the date stated in the Contract Data the Employer is deemed to have delayed the start of the
relevant activities and this will be Compensation Event.
22. Access to the Site
22.1 The Contractor shall allow the Engineer and any person authorized by the Engineer access to the Site, to
any place where work in connection with the Contract is being carried out or is intended to be carried
out and to any place where materials or plant are being manufactured / fabricated / assembled for the
works.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
41
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer which comply with the applicable laws
where the Site is located.
23.2 The Contractor shall permit the bank to inspect the Contractor’s accounts and records relating to the
performance of the Contractor and to have them audited by auditors appointed by the Bank, if so
required by the Bank.
24. Disputes
24.1 If the Contractor believes that a decision taken by the Engineer was either outside the authority given to
the Engineer by the Contract or that the decision was wrongly taken, the decision shall be referred to the
Adjudicator within 14 days of the notification of the Engineer's decision.
25. Procedure for Disputes
25.1 The Adjudicator shall give a decision in writing within 28 days of receipt of a notification of a dispute.
25.2 The Adjudicator shall be paid daily at the rate specified in the Contract Data together with reimbursable
expenses of the types specified in the Contract Data and the cost shall be divided equally between the
Employer and the Contractor, whatever decision is reached by the Adjudicator. Either party may refer a
decision of the Adjudicator to an Arbitrator within 28 days of the Adjudicator's written decision. If
neither party refers the dispute to arbitration within the above 28 days, the Adjudicator's decision will be
final and binding.
25.3 The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special
Conditions of Contract.
26. Replacement of Adjudicator
26.1 Should the Adjudicator resign or die, or should the Employer and the Contractor agree that the
Adjudicator is not fulfilling his functions in accordance with the provisions of the Contract, a new
Adjudicator will be jointly appointed by the Employer and the Contractor. In case of disagreement
between the Employer and the Contractor, within 30 days, the Adjudicator shall be designated by the
Appointing Authority designated in the Contract Data at the request of either party, within 14 days of
receipt of such request.
B. Time Control
27. Program
27.1 Within the time stated in the Contract Data the Contractor shall submit to the Engineer for approval a
Program including Environmental Management Plan showing the general methods, arrangements, order,
and timing for all the activities in the Works along with monthly cash flow forecast.
27.2 An update of the Program shall be a program showing the actual progress achieved on each activity and
the effect of the progress achieved on the timing of the remaining work including any changes to the
sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval, an updated Program at intervals no longer
than the period stated in the Contract Data. If the Contractor does not submit an updated Program within
this period, the Engineer may withhold the amount stated in the Contract Data from the next payment
certificate and continue to withhold this amount until the next payment after the date on which the
overdue Program has been submitted.
27.4 The Engineer's approval of the Program shall not alter the Contractor's obligations. The Contractor may
revise the Program and submit it to the Engineer again at any time. A revised Program is to show the
effect of Variations and Compensation Events.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
42
28. Extension of the Intended Completion Date
28.1 The Engineer shall extend the Intended Completion Date if a Compensation Event occurs or a Variation
is issued which makes it impossible for Completion to be achieved by the Intended Completion Date
without the Contractor taking steps to accelerate the remaining work and which would cause the
Contractor to incur additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended Completion Date within 21 days
of the Contractor asking the Engineer for a decision upon the effect of a Compensation Event or Variation
and submitting full supporting information. If the Contractor has failed to give early warning of a delay or
has failed to cooperate in dealing with a delay, the delay by this failure shall not be considered in assessing
the new Intended Completion Date.
29. Deleted
30. Delays Ordered by the Engineer
30.1 The Engineer may instruct the Contractor to delay the start or progress of any activity within the Works.
31. Management Meetings
31.1 Either the Engineer or the Contractor may require the other to attend a management meeting. The business of
a management meeting shall be to review the plans for remaining work and to deal with matters raised in
accordance with the early warning procedure.
31.2 The Engineer shall record the business of management meetings and is to provide copies of his record to
those attending the meeting and to the Employer. The responsibility of the parties for actions to be taken is to
be decided by the Engineer either at the management meeting or after the management meeting and stated in
writing to all who attended the meeting.
32. Early Warning
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely future events or
circumstances that may adversely affect the quality of the work, increase the Contract Price or delay the
execution of works. The Engineer may require the Contractor to provide an estimate of the expected effect of
the future event or circumstance on the Contract Price and Completion Date. The estimate is to be provided
by the Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and considering proposals for how the effect of
such an event or circumstance can be avoided or reduced by anyone involved in the work and in carrying out
any resulting instruction of the Engineer.
C. Quality Control
33. Identifying Defects
33.1 The Engineer shall check the Contractor's work and notify the Contractor of any Defects that are found.
Such checking shall not affect the Contractor's responsibilities. The Engineer may instruct the
Contractor to search for a Defect and to uncover and test any work that the Engineer considers may
have a Defect.
33.2 The contractor shall permit the Employer’s Technical auditor to check the contractor’s work and notify
the Engineer and Contractor of any defects that are found. Such a check shall not affect the
Contractor’s or the Engineer’s responsibility as defined in the Contract Agreement.
34. Tests
34.1 If the Engineer instructs the Contractor to carry out a test not specified in the Specification to check
whether any work has a Defect and the test shows that it does, the Contractor shall pay for the test and
any samples. If there is no Defect the test shall be a Compensation Event.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
43
35. Correction of Defects
35.1 The Engineer shall give notice to the Contractor of any Defects before the end of the Defects Liability
Period, which begins at Completion and is defined in the Contract Data. The Defects Liability Period
shall be extended for as long as Defects remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified Defect within the length
of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a Defect within the time specified in the Engineer’s notice, the
Engineer will assess the cost of having the Defect corrected, and the Contractor will pay this amount.
Note: Where in certain cases, the technical specifications provide for acceptance of works within specified
tolerance limits at reduced rates, Engineer will certify payments to Contractor accordingly.
D. Cost Control
37. Bill of Quantities
37.1 The Bill of Quantities shall contain items for the construction, installation, testing, and commissioning
work to be done by the contractor.
37.2 The Bill of Quantities is used to calculate the Contract Price. The Contractor is paid for the quantity of
the work done at the rate in the Bill of Quantities for each item.
38. Changes in the Quantities
38.1 If the final quantity of the work done differs from the quantity in the Bill of Quantities for the particular
item by more than 25 percent, provided the change exceeds 1% of Initial Contract Price, the Engineer
shall adjust the rate to allow for the change.
38.2 The Engineer shall not adjust rates from changes in quantities if thereby the Initial Contract Price is
exceeded by more than 15 percent, except with the Prior approval of the Employer.
38.3 If requested by the Engineer, the Contractor shall provide the Engineer with a detailed cost breakdown
of any rate in the Bill of Quantities.
39. Variations
39.1 All Variations shall be included in updated Programs produced by the Contractor.
40. Payments for Variations
40.1 The Contractor shall provide the Engineer with a quotation (with breakdown of unit rates) for carrying
out the Variation when requested to do so by the Engineer. The Engineer shall assess the quotation,
which shall be given within seven days of the request or within any longer period stated by the Engineer
and before the Variation is ordered.
40.2 If the work in the Variation corresponds with an item description in the Bill of Quantities and if, in the
opinion of the Engineer, the quantity of work above the limit stated in Sub Clause 38.1 or the timing of
its execution do not cause the cost per unit of quantity to change, the rate in the bill of Quantities shall
be used to calculate the value of the Variation. If the cost per unit of quantity changes, or if the nature or
timing of the work in the Variation does not correspond with items in the Bill of Quantities, the
quotation by the Contractor shall be in form of new rates for the relevant items of work.
40.3 If the Contractor's quotation is unreasonable (or if the contractor fails to provide the Engineer with a
quotation within a reasonable time specified by the engineer in accordance with Clause 40.1), the
Engineer may order the Variation and make a change to the Contract Price which shall be based on
Engineer’s own forecast of the effects of the Variation on the Contractor's costs.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
44
40.4 If the Engineer decides that the urgency of varying the work would prevent a quotation being given and
considered without delaying the work, no quotation shall be given and the Variation shall be treated as a
Compensation Event.
40.5 The Contractor shall not be entitled to additional payment for costs that could have been avoided by
giving early warning.
41. Cash flow forecasts
41.1 When the Program is updated, the contractor is to provide the Engineer with an updated cash flow
forecast.
42. Payment Certificates
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated value of the work
completed less the cumulative amount certified previously along with details of measurement of the
quantity of works executed in a tabulated form as approved by the Engineer.
42.2 The Engineer shall check the details given in the Contractor's monthly statement and within 14 days
certify the amounts to be paid to the Contractor after taking into account any credit or debit for the
month in question in respect of materials for the works in the relevant amounts and under conditions set
forth in sub-clause 51(3) of the Contract Data (Secured Advance).
42.3 The value of work executed shall be determined by the Engineer after due check measurement of the
quantities claimed as executed by the contractor.
42.4 The value of work executed shall comprise the value of the quantities of the items in the Bill of
Quantities completed..
42.5 The value of work executed shall include the valuation of Variations and Compensation Events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the proportion of any
item previously certified in any certificate in the light of later information.
43. Payments
43.1 Payments shall be adjusted for deductions for advance payments, retention, other recoveries in terms of
the contract and taxes, at source, as applicable under the law. The Employer shall pay the Contractor the
amounts certified by the Engineer within 28 days of the date of each certificate. If the Employer makes a
late payment, the Contractor shall be paid interest on the late payment in the next payment. Interest shall
be calculated from the date by which the payment should have been made upto the date when the late
payment is made at 8% per annum.
43.2 If an amount certified is increased in a later certificate or as a result of an award by the Adjudicator or an
Arbitrator, the Contractor shall be paid interest upon the delayed payment as set out in this clause.
Interest shall be calculated from the date upon which the increased amount would have been certified in
the absence of dispute.
43.3 Items of the Works for which no rate or price has been entered in will not be paid for by the Employer
and shall be deemed covered by other rates and prices in the Contract.
44. Compensation Events
44.1 The following are Compensation Events unless they are caused by the Contractor:
(a) The Employer does not give access to a part of the Site by the Site Possession Date stated in the
Contract Data.
(b) The Employer modifies the schedule of other contractors in a way which affects the work of the
contractor under the contract.
(c) The Engineer orders a delay or does not issue drawings, specifications or instructions required for
execution of works on time.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
45
(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon work which
is then found to have no Defects.
(e) The Engineer unreasonably does not approve for a subcontract to be let.
(f) Ground conditions are substantially more adverse than could reasonably have been assumed before issuance
of Letter of Acceptance from the information issued to Bidders (including the Site Investigation Reports),
from information available publicly and from a visual inspection of the Site. (g) The Engineer gives an instruction for dealing with an unforeseen condition, caused by the
Employer, or additional work required for safety or other reasons.
(h) Other contractors, public authorities, utilities or the Employer does not work within the dates and
other constraints stated in the Contract, and they cause delay or extra cost to the Contractor.
(i) The advance payment is delayed.
(j) The effect on the Contractor of any of the Employer’s Risks.
(k) The Engineer unreasonably delays issuing a Certificate of Completion.
(l) Other Compensation Events listed in the Contract Data or mentioned in the Contract.
44.2 If a Compensation Event would cause additional cost or would prevent the work being completed before
the Intended Completion Date, the Contract Price shall be increased and/or the Intended Completion
Date is extended. The Engineer shall decide whether and by how much the Contract Price shall be
increased and whether and by how much the Intended Completion Date shall be extended.
44.3 As soon as information demonstrating the effect of each Compensation Event upon the Contractor's
forecast cost has been provided by the Contractor, it is to be assessed by the Engineer and the Contract
Price shall be adjusted accordingly. If the Contractor's forecast is deemed unreasonable, the Engineer
shall adjust the Contract Price based on Engineer’s own forecast. The Engineer will assume that the
Contractor will react competently and promptly to the event.
44.4 The Contractor shall not be entitled to compensation to the extent that the Employer's interests are adversely
affected by the Contractor not having given early warning or not having cooperated with the Engineer.
45. Tax
45.1 The rates quoted by the Contractor shall be deemed to be inclusive of the sales and other taxes that the
Contractor will have to pay for the performance of this Contract. The Employer will perform such
duties in regard to the deduction of such taxes at source as per applicable law.
46. Currencies
46.1 All payments shall be made in Indian Rupees.
47. Price Adjustment
47.1 Contract price shall be adjusted for increase or decrease in rates and price of labour, materials, fuels and
lubricants in accordance with the following principles and procedures and as per formula given in the
contract data:
(a) The price adjustment shall apply for the work done from the start date given in the contract data
upto end of the initial intended completion date or extensions granted by the Engineer and shall
not apply to the work carried out beyond the stipulated time for reasons attributable to the
contractor.
(b) The price adjustment shall be determined during each quarter from the formula given in the
contract data.
(c) Following expressions and meanings are assigned to the work done during each quarter:
R = Total value of work done during the quarter. It would include the amount of secured
advance for materials paid for (if any) during the quarter, less the amount of the secured
advance recovered, during the quarter. It will exclude value for works executed under
variations for which price adjustment will be worked separately based on the terms
mutually agreed.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
46
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is not covered by the
provisions of this or other clauses in the contract, the unit rates and prices included in the contract shall
be deemed to include amounts to cover the contingency of such other rise or fall in costs.
48. Retention
48.1 The Employer shall retain from each payment due to the Contractor the proportion stated in the Contract
Data until Completion of the whole of the Works.
48.2 On Completion of the whole of the Works half the total amount retained is repaid to the Contractor and
half when the Defects Liability Period has passed and the Engineer has certified that all Defects notified
by the Engineer to the Contractor before the end of this period have been corrected.
48.3 On completion of the whole works, the contractor may substitute retention money (balance half) with
an “on demand” Bank guarantee.
49. Liquidated Damages
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day stated in the Contract
Data for each day that the Completion Date is later than the Intended Completion Date (for the whole of
the works or the milestone as stated in the contract data). The total amount of liquidated damages shall
not exceed the amount defined in the Contract Data. The Employer may deduct liquidated damages from
payments due to the Contractor. Payment of liquidated damages does not affect the Contractor's
liabilities.
49.2 If the Intended Completion Date is extended after liquidated damages have been paid, the Engineer shall
correct any overpayment of liquidated damages by the Contractor by adjusting the next payment
certificate. The Contractor shall be paid interest on the over payment calculated from the date of
payment to the date of repayment at the rates specified in Sub Clause 43.1.
50. Deleted
51. Advance Payment
51.1 The Employer shall make advance payment to the Contractor of the amounts stated in the Contract Data
by the date stated in the Contract Data, against provision by the Contractor of an Unconditional Bank
Guarantee in a form and by a bank acceptable to the Employer in amounts and currencies equal to the
advance payment. The guarantee shall remain effective until the advance payment has been repaid, but
the amount of the guarantee shall be progressively reduced by the amounts repaid by the Contractor.
Interest will not be charged on the advance payment. ‘The bank guarantee of a joint venture shall be in
the name of the joint venture’.
51.2 The Contractor is to use the advance payment only to pay for Equipment, Plant and Mobilization
expenses required specifically for execution of the Works. The Contractor shall demonstrate that
advance payment has been used in this way by supplying copies of invoices or other documents to the
Engineer.
51.3 The advance payment shall be repaid by deducting proportionate amounts from payments otherwise due
to the Contractor, following the schedule of completed percentages of the Works on a payment basis.
No account shall be taken of the advance (mobilization and equipment only) payment or its repayment
in assessing valuations of work done, Variations, price adjustments, Compensation Events, or
Liquidated Damages.
51.4 Secured Advance:
The Engineer shall make advance payment in respect of materials intended for but not yet incorporated
in the Works in accordance with conditions stipulated in the Contract Data.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
47
52. Securities
52.1 The Performance Security shall be provided to the Employer no later than the date specified in the Letter
of Acceptance and shall be issued in an amount and form and by a bank or surety acceptable to the
Employer, and denominated in Indian Rupees. The Performance Security shall be valid until a date 28
days from the date of expiry of Defects Liability Period and the additional security for unbalanced bids
shall be valid until a date 28 days from the date of issue of the certificate of completion. ‘The
performance security of joint venture shall be in the name of the joint venture’.
53. Deleted
54. Cost of Repairs
54.1 Loss or damage to the Works or Materials to be incorporated in the Works between the Start Date and
the end of the Defects Correction periods shall be remedied by the Contractor at the Contractor's cost if
the loss or damage arises from the Contractor's acts or omissions.
E. Finishing the Contract
55. Completion
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of the Works and the
Engineer will do so upon deciding that the Work is completed.
56. Taking Over
56.1 The Employer shall take over the Site and the Works within seven days of the Engineer issuing a
certificate of Completion.
57. Final Account
57.1 The Contractor shall supply to the Engineer a detailed account of the total amount that the Contractor
considers payable under the Contract before the end of the Defects Liability Period. The Engineer shall
issue a Defect Liability Certificate and certify any final payment that is due to the Contractor within 56
days of receiving the Contractor's account if it is correct and complete. If it is not, the Engineer shall
issue within 56 days a schedule that states the scope of the corrections or additions that are necessary. If
the Final Account is still unsatisfactory after it has been resubmitted, the Engineer shall decide on the
amount payable to the Contractor and issue a payment certificate, within 56 days of receiving the
Contractor’s revised account.
58. Operating and Maintenance Manuals
58.1 If “as built” Drawings and/or operating and maintenance manuals are required, the Contractor shall
supply them by the dates stated in the Contract Data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated in the Contract Data,
or they do not receive the Engineer’s approval, the Engineer shall withhold the amount stated in the
Contract Data from payments due to the Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party causes a fundamental
breach of the Contract.
59.2 Fundamental breaches of Contract include, but shall not be limited to the following:
(a) the Contractor stops work for 28 days when no stoppage of work is shown on the current
program and the stoppage has not been authorized by the Engineer;
(b) the Engineer instructs the Contractor to delay the progress of the Works and the instruction is not
withdrawn within 28 days;
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
48
(c) the Employer or the Contractor is made bankrupt or goes into liquidation other than for a
reconstruction or amalgamation;
(d) a payment certified by the Engineer is not paid by the Employer to the Contractor within 56 days
of the date of the Engineer's certificate;
(e) the Engineer gives Notice that failure to correct a particular Defect is a fundamental breach of
Contract and the Contractor fails to correct it within a reasonable period of time determined by
the Engineer;
(f) the Contractor does not maintain a security which is required;
(g) the Contractor has delayed the completion of works by the number of days for which the
maximum amount of liquidated damages can be paid as defined in the Contract data; and
(h) if the Contractor, in the judgment of the Purchaser has engaged in fraud and corruption, as
defined in GCC Clause 64, in competing for or in executing the Contract.
( i ) “The contractor (in case of joint venture) has modified the composition of the joint venture and /
or the responsibility of each member of the joint venture from what is stated in joint venture
agreement without prior approval of the Employer”.
59.3 When either party to the Contract gives notice of a breach of contract to the Engineer for a cause other
than those listed under Sub Clause 59.2 above, the Engineer shall decide whether the breach is
fundamental or not.
59.4 Notwithstanding the above, the Employer may terminate the Contract for convenience.
59.5 If the Contract is terminated the Contractor shall stop work immediately, make the Site safe and secure
and leave the Site as soon as reasonably possible.
60. Payment upon Termination
60.1 If the Contract is terminated because of a fundamental breach of Contract by the Contractor, the
Engineer shall issue a certificate for the value of the work done less advance payments received up to
the date of the issue of the certificate, less other recoveries due in terms of the contract, fewer taxes due
to be deducted at source as per applicable law and less the percentage to apply to the work not
completed as indicated in the Contract Data. Additional Liquidated Damages shall not apply. If the total
amount due to the Employer exceeds any payment due to the Contractor the difference shall be a debt
payable to the Employer.
60.2 If the Contract is terminated at the Employer's convenience or because of a fundamental breach of
Contract by the Employer, the Engineer shall issue a certificate for the value of the work done, the
reasonable cost of removal of Equipment, repatriation of the Contractor's personnel employed solely on
the Works, and the Contractor's costs of protecting and securing the Works and less advance payments
received up to the date of the certificate, less other recoveries due in terms of the contract and less taxes
due to be deducted at source as per applicable law.
61. Property
61.1 All materials on the Site, Plant, Equipment, Temporary Works and Works are deemed to be the property
of the Employer, if the Contract is terminated because of a Contractor’s default.
62. Release from Performance
62.1 If the Contract is frustrated by the outbreak of war or by any other event entirely outside the control of
either the Employer or the Contractor the Engineer shall certify that the Contract has been frustrated.
The Contractor shall make the Site safe and stop work as quickly as possible after receiving this
certificate and shall be paid for all work carried out before receiving it and for any work carried out
afterwards to which commitment was made.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
49
63. Suspension of World Bank Loan or Credit
63.1 In the event that the World Bank suspends the Loan or Credit to the Employer, from which part of the
payments to the Contractor are being made:
(a) The Employer is obligated to notify the Contractor of such suspension within 7 days of having
received the World Bank’s suspension notice.
(b) If the Contractor has not received sums due to it upon the expiration of the 28 days for payment
provided for in Sub-Clause 43.1, the Contractor may immediately issue a 14-day termination
notice.
64. Fraud and Corruption
64.1 The Bank’s policy to require that Borrowers (including beneficiaries of Bank loans), as well as Bidders, Suppliers,
Contractors, and their subcontractors under Bank-financed contracts, observe the highest standard of ethics during the
procurement and execution of such contracts.1 In pursuit of this policy, the Bank:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) “corrupt practice”2 is the offering, giving, receiving, or soliciting, directly or indirectly, of anything of
value to influence improperly the action of another party;
(ii) “fraudulent practice” 3 is any act or omission including misrepresentation , that knowingly or
recklessly misleads, or attempts to mislead, a party to obtain a financial or tother benefit or to avoid
an obligation;
(iii) “collusive practice” 4 is an arrangement between two or more parties designed to achieve an improper
purpose, including to influence improperly the actions of another party;
(iv) “coercive practice” 5 is impairing or harming, or harming , or threatening to impair or harm, directly
or indirectly, any party or the property of the party to influence improperly the actions of a party;
(v) “obstructive practice” is
(aa) deliberately destroying, falsifying, altering or concealing of evidence material to the investigation or
making false statements to investigators in order to materially impede a Bank investigation into
allegations of a corrupt, fraudulent, coercive or collusive practice and/or threatening, harassing or
knowledge of matters relevant to the investigation or from pursuing the investigation or
(bb) acts intended to materially impede the exercise of the Bank’s inspection and audit rights provided for
under sub-clause 3.1 (e) below.
(b) will reject a proposal for award if it determines that the Bidder recommended for award has, directly or through
an agent, engaged in corrupt, fraudulent, collusive, coercive or obstructive practices in competing for the
Contract in question;
(c) will cancel the portion of the loan allocated to a contract if it determines at any time that representatives of the
Borrower or of a beneficiary of the loan engaged in corrupt, fraudulent, collusive or coercive practices during
the procurement or the execution of that contract, without the Borrower having taken timely and appropriate
action satisfactory to the Bank to address such practices when they occur;
(d) will sanction a firm or individual, including declaring them ineligible, either indefinitely or for a stated period
of time, to be awarded a Bank-financed contract if it at any time determines that the firm has directly or through
an agent, engaged, in corrupt, fraudulent, collusive or coercive or obstructive practices in competing for, or in
executing, a Bank-financed contract; and
(e) will have the right to require that a provision be included in Bidding Documents and in contracts financed by a
Bank loan, requiring Bidders, Suppliers, Contractors and their sub contractors to permit the Bank to inspect
their accounts and records and other documents relating to the bid submission and contract performance and to
have them audited by auditors appointed by the Bank.
1 in this context, an action taken by a bidder, supplier, contractor or a subcontractor to influence the procurement process or contract execution
for undue advantage is improper.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
50
2 “another party” refers to a public official” includes World Bank staff and employees of contract execution]. In this context, “public official”
includes World Bank staff and employees of other organizations taking a reviewing procurement decisions.
3 a “party” refers to public official; the terms “benefits” and “obligation” relate to the procurement process or contract execution and the “act or
omission” is intended to influence the procurement process or contract execution.
4 “parties” refers to participants in the procurement process (including public officials) attempting to establish bid prices at artificial, non
competitive levels.
5 a “party” refers to a participant in the procurement process or contract execution.
F. Special Conditions of Contract
1. LABOUR :
The Contractor shall, unless otherwise provided in the Contract, make his own arrangements for the engagement
of all staff and labour, local or other, and for their payment, housing, feeding and transport.
The Contractor shall, if required by the Engineer, deliver to the Engineer a return in detail, in such form and at
such intervals as the Engineer may prescribe, showing the staff and the numbers of the several classes of labour
from time to time employed by the Contractor on the Site and such other information as the Engineer may
require.
2. COMPLIANCE WITH LABOUR REGULATIONS :
During continuance of the contract, the Contractor and his sub contractors shall abide at all times by all existing
labour enactments and rules made there under, regulations, notifications and bye laws of the State or Central
Government or local authority and any other labour law (including rules), regulations, bye laws that may be
passed or notification that may be issued under any labour law in future either by the State or the Central
Government or the local authority. Salient features of some of the major labour laws that are applicable to
construction industry are given below. The Contractor shall keep the Employer indemnified in case any action is
taken against the Employer by the competent authority on account of contravention of any of the provisions of
any Act or rules made there under, regulations or notifications including amendments. If the Employer is caused
to pay or reimburse, such amounts as may be necessary to cause or observe, or for non-observance of the
provisions stipulated in the notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the
part of the Contractor, the Engineer/Employer shall have the right to deduct any money due to the Contractor
including his amount of performance security. The Employer/Engineer shall also have right to recover from the
Contractor any sum required or estimated to be required for making good the loss or damage suffered by the
Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be treated as the employees of the
Employer at any point of time.
SALIENT FEATURES OF SOME MAJOR LABOUR LAWS APPLICABLE TO ESTABLISHMENTS
ENGAGED IN BUILDING AND OTHER CONSTRUCTION WORK
(The law as current on the date of bid opening will apply)
a) Workmen Compensation Act 1923: The Act provides for compensation in case of injury by accident arising out
of and during the course of employment.
b) Payment of Gratuity Act 1972: Gratuity is payable to an employee under the Act on satisfaction of certain
conditions on separation if an employee has completed 5 years service or more or on death the rate of 15 days
wages for every completed year of service. The Act is applicable to all establishments employing 10 or more
employees.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
51
c) Employees P.F. and Miscellaneous Provision Act 1952 (since amended): The Act Provides for monthly
contributions by the employer plus workers @ 10% or 8.33%. The benefits payable under the Act are :
(i) Pension or family pension on retirement or death, as the case may be.
(ii) Deposit linked insurance on the death in harness of the worker.
(iii) payment of P.F. accumulation on retirement/death etc.
d) Maternity Benefit Act 1951: The Act provides for leave and some other benefits to women employees in case
of confinement or miscarriage etc.
e) Contract Labour (Regulation & Abolition) Act 1970: The Act provides for certain welfare measures to be
provided by the Contractor to contract labour and in case the Contractor fails to provide, the same are required
to be provided, by the Principal Employer by Law. The Principal Employer is required to take Certificate of
Registration and the Contractor is required to take license from the designated Officer. The Act is applicable to
the establishments or Contractor of Principal Employer if they employ 20 or more contract labour.
f) Minimum Wages Act 1948: The Employer is supposed to pay not less than the Minimum Wages fixed by
appropriate Government as per provisions of the Act if the employment is a scheduled employment.
Construction of Buildings, Roads, Runways are scheduled employments.
g) Payment of Wages Act 1936: It lies down as to by what date the wages are to be paid, when it will be paid and
what deductions can be made from the wages of the workers.
h) Equal Remuneration Act 1979: The Act provides for payment of equal wages for work of equal nature to Male
and Female workers and for not making discrimination against Female employees in the matters of transfers,
training and promotions etc.
i) Payment of Bonus Act 1965: The Act is applicable to all establishments employing 20 or more employees. The
Act provides for payments of annual bonus subject to a minimum of 8.33% of wages and maximum of 20% of
wages to employees drawing Rs.3500/-per month or less. The bonus to be paid to employees getting Rs.2500/-
per month or above up to Rs.3500/- per month shall be worked out by taking wages as Rs.2500/-per month
only. The Act does not apply to certain establishments. The newly set-up establishments are exempted for five
years in certain circumstances. Some of the State Governments have reduced the employment size from 20 to
10 for the purpose of applicability of this Act.
j) Industrial Disputes Act 1947: The Act lays down the machinery and procedure for resolution of Industrial
disputes, in what situations a strike or lock-out becomes illegal and what are the requirements for laying off or
retrenching the employees or closing down the establishment.
k) Industrial Employment (Standing Orders) Act 1946: It is applicable to all establishments employing 100 or
more workmen (employment size reduced by some of the States and Central Government to 50). The Act
provides for laying down rules governing the conditions of employment by the Employer on matters provided in
the Act and get the same certified by the designated Authority.
l) Trade Unions Act 1926: The Act lays down the procedure for registration of trade unions of workmen and
employers. The Trade Unions registered under the Act have been given certain immunities from civil and
criminal liabilities.
m) Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of children below 14 years
of age in certain occupations and processes and provides for regulation of employment of children in all other
occupations and processes. Employment of Child Labour is prohibited in Building and Construction Industry.
n) Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Service) Act 1979: The Act is
applicable to an establishment which employs 5 or more inter-state migrant workmen through an intermediary
(who has recruited workmen in one state for employment in the establishment situated in another state). The
Inter-State migrant workmen, in an establishment to which this Act becomes applicable, are required to be
provided certain facilities such as housing, medical aid, traveling expenses from home up to the establishment
and back, etc.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
52
o) The Building and Other Construction workers (Regulation of Employment and Conditions of Service) Act 1996
and the Cess Act of 1996: All the establishments who carry on any building or other construction work and
employs 10 or more workers are covered under this Act. All such establishments are required to pay cess at the
rate not exceeding 2% of the cost of construction as may be modified by the Government. The Employer of the
establishment is required to provide safety measures at the Building or construction work and other welfare
measures, such as Canteens, First-Aid facilities, Ambulance, Housing accommodations for workers near the
work place etc. The Employer to whom the Act applies has to obtain a registration certificate from the
Registering Officer appointed by the Government.
p) Factories Act 1948: The Act lays down the procedure for approval at plans before setting up a factory, health
and safety provisions, welfare provisions, working hours, annual earned leave and rendering information
regarding accidents or dangerous occurrences to designated authorities. It is applicable to premises employing
10 persons or more with aid of power or 20 or more persons without the aid of power engaged in manufacturing
process.
3. SUB-CONTRACTING (GCC Clause 7) Please add the following as Clause 7.2:
The contractor shall not be required to obtain any consent from the employer for:
a) the sub-contracting of any part of the Works for which the Sub-contractor is named in the contract;
b) the provision of labour; and
c) the purchase of materials which are in accordance with the standards specified in the Contract.
Beyond this if the contractor proposes sub-contracting any part of the work during execution of works, because
of some unforeseen circumstances to enable him to complete the work as per terms of the contract, the
Engineer will consider the following before according approval:
- The contractor shall not sub-contract the whole of the Works.
- The contractor shall not sub-contract any part of the Work without prior consent of the Engineer. Any
such consent shall not relieve the contractor from any liability or obligations under the contract and he
shall be responsible for the acts, defaults and neglects of any sub-contractor, his agents or workmen as
fully as if they were the acts, defaults or neglects of the contractor, his agents or workmen.
- The Engineer should satisfy whether (a) the circumstances warrant such sub-contracting; and (b) the sub-
contractors so proposed for the Work possess the experience, qualifications and equipment necessary for
the job proposed to be entrusted to them in proportion to the quantum of work to be sub-contracted.
- If payments are proposed to be made directly to that sub-contractor, this should be subject to specific
authorization by the prime contractor so that this arrangement does not alter the contractor's liability or
obligations under the contract.
4. ARBITRATION (GCC Clause 25.3)
The procedure for arbitration will be as follows:
25.3 (a) In case of Dispute or difference arising between the Employer and a domestic contractor relating to any
matter arising out of or connected with this agreement, such disputes or difference shall be settled in
accordance with the Arbitration and Conciliation Act, 1996. The arbitral tribunal shall consist of 3
arbitrators one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be
chosen by the two Arbitrators so appointed by the Parties and shall act as presiding arbitrator. In case of
failure of the two arbitrators appointed by the parties to reach upon a consensus within a period of 30
days from the appointment of the arbitrator appointed subsequently, the Presiding Arbitrator shall be
appointed by the President of the Institution of Engineers (India)
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
53
(Note: 1. All bidders are expected to indicate clearly in the bid, if they proposed sub-contracting elements of the works amounting to more than 20 percent
of the Bid Price. For each such proposal the qualification and the experience of the identified sub-contractor in the relevant field should be furnished along
with the bid to enable the employer to satisfy himself about their qualifications before agreeing for such sub-contracting and include it in the contract. In
view of the above, normally no additional sub-contracting should arise during execution of the contract.
2. However, [a] sub contracting for certain specialized elements of the work is not unusual and acceptable for carrying out the works more
effectively; but vertical splitting of the works for subcontracting is not acceptable. [b] In any case, proposal for sub-contracting in addition
to what was specified in bid and stated in contract agreement will not be acceptable if the value of such additional sub-contracting
exceeds 25% of value of work which was to be executed by Contractor without sub-contracting.
3. Assignment of the contract may be acceptable only under exceptional circumstances such as insolvencies/liquidation or
merger of companies etc.
(b) In the case of dispute with a Foreign contractor the dispute shall be settled in accordance with
provisions of UNCITRAL Arbitration Rules. The Arbitral Tribunal shall consist of three Arbitrators
one each to be appointed by the Employer and the Contractor. The third Arbitrator shall be chosen by
the two Arbitrators so appointed by the Parties, and shall act a presiding arbitrator. In case of failure
of the two arbitrators appointed by the parties to reach upon a consensus within a period of 30 days
from the appointment of the arbitrator appointed subsequently, the Presiding arbitrator shall be
appointed by the President of the Institution of Engineers (India).
(c) If one of the parties fails to appoint its arbitrator in pursuance of sub-clause (a) and (b) above within 30
days after receipt of the notice of the appointment of its arbitrator by the other party, then the President
of the Institution of Engineers (India), both in cases of the Foreign Contractor as well as Indian
Contractor, shall appoint the arbitrator. A certified copy of the order of the President of the Institution
of Engineers (India) making such an appointment shall be furnished to each of the parties.
(d) Arbitration proceedings shall be held at Hyderabad, Andhra Pradesh, India, and the language of the
arbitration proceedings and that of all documents and communications between the parties shall be
English.
(e) The decision of the majority of arbitrators shall be final and binding upon both parties. The cost and
expenses of Arbitration proceedings will be paid as determined by the arbitral tribunal. However, the
expenses incurred by each party in connection with the preparation, presentation, etc. of its proceedings
as also the fees and expenses paid to the arbitrator appointed by such party or on its behalf shall be
borne by each party itself.
(f) Where the value of the contract is Rs.50 millions and below, the disputes or differences arising shall be
referred to the Sole Arbitrator. The Sole Arbitrator should be appointed by agreement between the
parties; failing such agreement, by the appointing authority, namely the President of the Institution of
Engineers (India).
(g) Performance under the contract shall continue during the arbitration proceedings and payments due to
the contractor by the owners shall not be withheld, unless they are the subject matter of the arbitration
proceedings.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
54
5. PROTECTION OF ENVIRONMENT:
Add the following as GCC Clause 16.2:
The contractor shall take all reasonable steps to protect the environment on and off the Site and to avoid damage
or nuisance to persons or to property of the public or others resulting from pollution, noise or other causes
arising as a consequence of his methods of operation.
During continuance of the contract, the contractor and his sub-contractors shall abide at all times by all existing
enactments on environmental protection and rules made there under, regulations, notifications and bye-laws of
the State or Central Government, or local authorities and any other law, bye-law, regulations that may be passed
or notification that may be issued in this respect in future by the State or Central Government or the local
authority.
Salient features of some of the major laws that are applicable are given below:
The Water (Prevention and Control of Pollution) Act, 1974, this provides for the prevention and control of
water pollution and the maintaining and restoring of wholesomeness of water. 'Pollution' means such
contamination of water or such alteration of the physical, chemical or biological properties of water or such
discharge of any sewage or trade effluent or of any other liquid, gaseous or solid substance into water (whether
directly or indirectly) as may, or is likely to, create a nuisance or render such water harmful or injurious to
public health or safety, or to domestic, commercial, industrial, agricultural or other legitimate uses, or to the life
and health of animals or plants or of aquatic organisms.
The Air (Prevention and Control of Pollution) Act, 1981, This provides for prevention, control and abatement of
air pollution. 'Air Pollution' means the presence in the atmosphere of any 'air pollutant', which means any solid,
liquid or gaseous substance (including noise) present in the atmosphere in such concentration as may be or tend
to be injurious to human beings or other living creatures or plants or property or environment.
The Environment (Protection) Act, 1986, This provides for the protection and improvement of environment and
for matters connected therewith, and the prevention of hazards to human beings, other living creatures, plants
and property. 'Environment' includes water, air and land and the inter-relationship which exists among and
between water, air and land, and human beings, other living creatures, plants, micro-organism and property.
The Public Liability Insurance Act, 1991, This provides for public liability insurance for the purpose of
providing immediate relief to the persons affected by accident occurring while handling hazardous substances
and for matters connected herewith or incidental thereto. Hazardous substance means any substance or
preparation which is defined as hazardous substance under the Environment (Protection) Act 1986, and
exceeding such quantity as may be specified by notification by the Central Government.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
55
6. LIQUIDATED DAMAGES:
Sub-clause 49.1:
Please substitute the last sentence with the following:
“Time is the essence of the contract and payment or deduction of liquidated damages shall not relieve the
contractor from his obligation to complete the work as per agreed construction program and milestones or from
any other of the contractor’s obligations and liabilities under the contract.”
______________________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
57
Contract Data
Items marked "N/A" do not apply in this Contract.
The following documents are also part of the Contract: Clause Reference
· The Schedule of Operating and Maintenance Manuals [58]
· The Schedule of Other Contractors [8]
· The Schedule of Key Personnel [9]
· The Methodology and Program of Construction & Environmental Management Plan [27]
· The Schedule of Key and Critical equipment to be deployed [27]
on the work as per agreed program of construction
· Site Investigation reports [14
The Borrower is Government of India/ Government Andhra Pradesh [1.1]
The World Bank means International Bank for Reconstruction and Development (IBRD) 1.1]
and loan refers to an IBRD Loan
The above insertions should correspond to the information provided in the Invitation of Bids.
The Employer is
Name: Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam (1.1)
Address: Office of the Superintending Engineer,
NSLBC O&M Circle, Tekulapally, Khammam – 507 002,
Khammam District, A.P.
Name of authorized Representative: Superintending Engineer, NSLBC O&M Circle, Tekulapally, Khammam.
The Engineer is (1.1)
Name: Executive Engineer
Address: O & M Division, Kalluru, Khammam.Dt.
Name of Authorized Representative: Deputy Executive Engineer, O & M Sub – Division, Tallada.Khammam. Dt.
The Adjudicator appointed jointly by the Employer and Contractor is:
Name : Sri R.Satyanarayana (1.1)
Address : Chief Engineer (Retired) I&CAD Department, Hyderabad.
The name and identification number of the Contract is NSP - APWSIP – Rehabilitation and modernization of 21st Main
Branch Canal from KM. 0.000 to KM. 52.300 of Nagarjunasagar Lal Bahadur Canal, A.P, India. Package No. LC - KMM – 6.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
58
Scope of Work:- This package mainly consists of Resectioning i.e., Strengthening and widening of banks, removal of deposited earth from
canal bed, Cement Concrete lining for bed and sides for the reach from km. 0.000 to 2.568 with Paver finisher with the assistance of Batching
plants and transit mixers , repairs to Structures such as cladding concrete along the rear side abutments, Providing 100mm thick Cement concrete
protective lining to upstream and downstream of structures with conventional placement, Repointing and Grouting to masonry piers and abutments
of structures, reconstruction and repairs to SL and DL bridges, repairs and painting to hand rails of bridges and Replacement of worned out
mechanical parts of Off take sluices such as Shutters, Gear boxes with painting to the shutters with enamel paint.
The Start Date shall be the date of issue of notice to proceed with the work. (1.1)
INTENDED COMPLETION DATE FOR THE WHOLE OF THE WORKS IS 51 MONTHS WITH THE FOLLOWING MILE STONES.
Mile stone Physical work to be completed Quantity Cumulative Quantity
Period Period Cumulative
15 Months 15 Months
1. EARTH WORK 1381998Cum 1381998Cum 2. C.C. LINING 23635 Sqm
(2363 Cum) 23635 Sqm (2363 Cum)
3. CEMENT CONCRETE ITEMS 3422 Cum 3422 Cum
4. SHOT CREETING 24087Sqm 24087Sqm
5. STRUCTURES (REPAIRS) 24 Nos 24 Nos
1st Mile stone
6. Mechanical works 3 Nos. 3 Nos.
12 Months 27 Months
1. EARTH WORK 829199Cum 2211197Cum
2. C.C. LINING 94541 Sqm (9454 Cum)
118176 Sqm (11818 Cum)
3. CEMENT CONCRETE ITEMS 13686 Cum 17108 Cum
4. SHOT CREETING 18075 Sqm 42162 Sqm
5. STRUCTURES (REPAIRS) 18 Nos 42 Nos
2nd
Mile stone
6. Mechanical works 3 Nos. 6 Nos.
12 Months 39 Months
1. EARTH WORK 552799 Cum 2763996 Cum
2. C.C. LINING 94541 Sqm (9454 Cum)
212717 Sqm (21272 Cum)
3. CEMENT CONCRETE ITEMS 13686Cum 30794 Cum
4. SHOT CREETING 18075 Sqm 60237 Sqm
5. STRUCTURES (REPAIRS) 18 Nos 60 Nos
3rd Mile stone
6. Mechanical works 2 Nos. 8 Nos.
12 Months 51 Months
1. EARTH WORK -- 2763996 Cum
2. C.C. LINING 23635 Sqm (2363 Cum)
236352 Sqm (23635 Cum)
3. CEMENT CONCRETE ITEMS 3422 Cum 34216 Cum
4. SHOT CREETING 16060 Sqm 76297 Sqm
5. STRUCTURES (REPAIRS) 16 Nos. 76 Nos.
4th Mile stone
6. Mechanical works 2 Nos. 10 Nos.
ALL ITEMS COMPLETE
ALL ITEMS COMPLETE
Note:- The works inside the canal prism are to be executed during the normal annual canal closure period, approximately April 1st to July 15th ( 90 days ) every year. This period may vary some what depending upon meeting of any urgent water demands as per G.O. A.P. instructions
The following documents also form part of the Contract: [2.3]
Andhra Pradesh Standard Specifications,
Relevant Indian Standard Specifications and codes.
The Contractor shall submit a revised Program including Environmental
Management Plan for the Works (in such form and detail as the
engineer shall reasonably prescribe) within 14 days of
delivery of the Letter of Acceptance. [27]
The Site Possession Dates shall be: The date of issue of notice to procced with the work.
Section 1 _______________________________
Section 2 _______________________________
Section 3 _______________________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
59
The Site is located at Khammam Revenue Division of Khammam District and is defined in drawings Nos. 4 [1]
The Defects Liability Period is 365 days ( 1 Year ) from the date of certification of completion of works. (where
sectional completion certificate is issued this will apply from those dates for those sections). [35]
Insurance requirements are as under: [13]
Minimum Cover for
Insurance
Maximum deductible for
Insurance
(i) Works and Plant and Materials
100 % Minimum 5%
(ii) Loss or damage to Equipment
100 % Minimum 5%
(iii) Other Property
100 % Minimum 5%
(iv) Personal injury or death insurance:
a) for other people;
100 %
Nil
b) for Contractor’s Employees In accordance with the statutory requirements applicable to
India
NOTE:- The absolute figures will be mentioned during signing of contract.
The following events shall also be Compensation Events: [44]
1. – NIL –
2. - NIL –
3. – NIL -
The period between Program updates shall be 30 days. [27]
The amount to be withheld for late submission of an updated
Program shall be Rs. 1.00 Lakh. [27]
The language of the Contract documents is English [3]
The law which applies to the Contract is the laws of Union of India [3]
The currency of the Contract is Indian Rupees. [46]
Fees and types of reimbursable expenses to be paid to the Adjudicator [25]
Appointing Authority for the Adjudicator is president, Institute of Engineers India. [26]
The formula(e) for adjustment of prices are: [47]
R = Value of work as defined in Clause 47.1 of Conditions of Contract.
Adjustment for labour component
(i) Price adjustment for increase or decrease in the cost due to labour shall be paid in accordance with the
following formula:
VL = 0.85 x Pl/100 x R x (Li - Lo)/Lo
VL = increase or decrease in the cost of work during the quarter under consideration due to changes in
rates for local labour.
Lo = the average consumer price index for industrial workers for Vijayawada centre for the quarter
preceding the date of opening of Bids as published by Labour Bureau, Ministry of Labour,
Government of India.
Li = The average consumer price index for industrial workers for Vijayawada centre for the quarter
under consideration as published by Labour Bureau, Ministry of Labour, Government of India.
Pl = Percentage of labour component of the work.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
60
Adjustment for cement component
(ii) Price adjustment for increase or decrease in the cost of cement procured by the contractor shall be paid in
accordance with the following formula.
Vc = 0.85 x Pc/100 x R x (Ci - Co)/Co
Vc = Increase or decrease in the cost of work during the quarter under consideration due to changes in
the rates for cement
Co = The all India average wholesale price index for cement for the quarter preceding the date of
opening of Bids as published by the Ministry of Industrial Development, Government of India,
New Delhi
Ci = The all India average wholesale price index for cement for the quarter under consideration as
published by Ministry of Industrial Development, Government of India, New Delhi
Pc = Percentage of cement component of the work
Adjustment for steel component
(iii) Price adjustment for increase or decrease in the cost of steel procured by the Contractor shall be paid in
accordance with the following formula:
Vs = 0.85 x Ps/100 x R x (Si - So)/So
Vs = Increase or decrease in the cost of work during the quarter under consideration due to changes in
the rates for steel
So = The all India average wholesale price index for steel (Bars and Rods) for the quarter preceding the
date of opening of Bids as published by the Ministry of Industrial Development, Government of
India, New Delhi
Si = The all India average wholesale price index for steel (Bars and Rods) for the quarter under
consideration as published by Ministry of Industrial Development, New Delhi
Ps = Percentage of steel component of the work
Note: For the application of this clause, index of Bars and Rods has been chosen to represent steel
group.
Adjustment of Bitumen component
(iv) Price adjustment for increase or decrease in the cost of bitumen shall be paid in accordance with the
following formula:
Vb = 0.85 x Pb/100 x R x (Bi - Bo)/Bo
Vb = Increase or decrease in the cost of work during the quarter under consideration due to changes in
the rate for bitumen.
Bo = The average official retail price of bitumen at the IOC depot at Vijayawada on the day 30 days
prior to date of opening of Bids.
Bi = The average official retail price of bitumen at IOC depot at Vijayawada for the 15th day of the
middle calendar month of the quarter under consideration.
Pb = Percentage of bitumen component of the work.
Adjustment of POL (fuel and lubricant) component
(v) Price adjustment for increase or decrease in cost POL (fuel and lubricant) shall be paid in accordance
with the following formula:
Vf = 0.85 x Pf/100 x R x (Fi - Fo)/Fo
Vf = Increase or decrease in the cost of work during the quarter under consideration due to changes in
rates for fuel and lubricants.
Fo = The average official retail price of High Speed Diesel (HSD) at the existing consumer pumps of
IOC at Hyderabad on the day thirty days prior to the date of opening of Bids.
Fi = The average official retail price of HSD at the existing consumer pumps of IOC at Hyderabad for
the 15th day of the middle calendar month of the quarter under consideration.
Pf = Percentage of fuel and lubricants component of the work.
Note: For the application of this clause, the price of High Speed Diesel oil has been chosen to represent
fuel and lubricants group.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
61
Adjustment for Plant and Machinery Spares component
(vi) Price adjustment for increase or decrease in the cost of plant and machinery spares procured by the
Contractor shall be paid in accordance with the following formula:
Vp = 0.85 x Pp/100 x R x (Pi - Po)/Po
Vp = Increase or decrease in the cost of work during the quarter under consideration due to changes in
the rates for plant and machinery spares
Po = The all India average wholesale price index for heavy machinery and parts for the quarter
preceding the date of opening of Bids as published by the Ministry of Industrial Development,
Government of India, New Delhi
Pi = The all India average wholesale price index for heavy machinery and parts for the quarter under
consideration as published by Ministry of Industrial Development, New Delhi
Pp = Percentage of plant and machinery spares component of the work
Note: For the application of this clause, index of Heavy Machinery and Parts has been chosen to
represent the Plant and Machinery Spares group.
Adjustment of Local materials
(vii) Price adjustment for increase or decrease in cost of local materials other than cement, steel, bitumen and
POL procured by the contractor shall be paid in accordance with the following formula:
Vm = 0.85 x Pm/100 x R x (Mi - Mo)/Mo
Vm = Increase or decrease in the cost of work during the quarter under consideration due to changes in
rates for local materials other than cement, steel, bitumen and POL.
Mo = The all India average wholesale price index (all commodities) for the quarter preceding the date of
opening of Bids, as published by the Ministry of Industrial Development, Government of India,
New Delhi.
Mi = The all India average wholesale price index (all commodities) for the quarter under consideration
as published by Ministry of Industrial Development, Government of India, New Delhi.
Pm = Percentage of local material component (other than cement, steel, bitumen and POL) of the work.
The following percentages will govern the price adjustment for the entire contract:
1. Labour - Pl 20 %
2. Cement - Pc 15 %
3. Steel - Ps 45 %
4. Bitumen - Pb 0 %
5. POL - Pf 5 %
6. Plant & Machinery Spares - PP 0 %
7. Other materials - Pm 15 %
Total 100%
The proportion of payments retained (retention money) shall be 6% from each bill
subject to a maximum of 5% of final contract price (48)
“In addition to the retention money” an amount equivalent to 20% of the cost of structures shall be with held from
the running bills for non completion such as hydraulic structures, measuring devises etc. other items of work in that
specified mile stone. This amount will be released after completion of such item of works in the respective milestone.
The liquidated damages for the whole of the works are Rs. 2.38 Lakhs per day. [49]
For Mile stone 1 Rs. 0.70 Lakhs per day
For Milestone 2 Rs. 0.76 Lakhs per day
For Milestone 3 Rs. 0.68 Lakhs per day
For Milestone 4 Rs. 0.24 Lakhs per day
The maximum amount of liquidated damages for the whole of the works is ten percent of final contract price. [49]
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
62
The amounts of the advance payment are: [51]
Nature of Advance Amount (Rs.) Conditions to be fulfilled
1. Mobilization 5% of the Contract price On submission of un-conditional Bank Guarantee.
(to be drawn before end of 20% of Contract period)
2. Equipment
(This advance is not
applicable for
equipment already
owned or hired/
leased by the
contractor.)
90% for new and 50% of depreciated
value for old equipment. Total
amount will be subject to a maxi-
mum of 5% of the Contract price.
After equipment is brought to site as per agreed
construction program (provided the Engineer is
satisfied that the equipment is required for
performance of the contract) and on submission of
unconditional Bank Guarantee for amount of advance.
3. Secured advance
for non-
perishable
materials brought
to site
75% of Invoice value or Market
value - lower of the two.
a) The materials are in-accordance with the
specification for Works;
b) Such materials have been delivered to site, and are
properly stored and protected against damage or
deterioration to the satisfaction of the Engineer.
The contractor shall store the bulk material in
measurable stacks.;
c) The Contractor’s records of the requirements,
orders, receipt and use of materials are kept in a
form approved by the Engineer and such records
shall be available for inspection by the Engineer;
d) The contractor has submitted with his monthly
statement the estimated value of the materials on
site together with such documents as may be
required by the Engineer for the purpose of
valuation of the materials and providing evidence
of ownership and payment thereof;
e) Ownership of such materials shall be deemed to
vest in the Employer for which the Contractor
has submitted an Indemnity Bond in an
acceptable format; and
f) The quantity of materials are not excessive
and shall be used within a reasonable time as
determined by the Engineer.
(The advance payment will be paid to the Contractor no later than 15 days after fulfillment of the above conditions).
Repayment of advance payment for mobilization and equipment: [51]
The advance shall be repaid with percentage deductions from the interim payments certified
by the Engineer under the Contract. Deductions shall commence in the next Interim Payment
Certificate following that in which the total of all such payments to the Contractor has
reached not less than 15 percent of the Contract Price or ONE months from the date of
payment of first installment of advance, whichever period concludes earlier, and shall be
made at the rate of 7.50% of the amounts of all Interim Payment Certificates until such time
as the advance has been repaid, always provided that the advance shall be completely repaid
prior to the expiry of the original time for completion.
Repayment of secured advance:
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
63
The advance shall be repaid from each succeeding monthly payments to the extent materials
[for which advance was previously paid pursuant to Clause 51.4 of G.C.C. and 51(3) of
Contract Data on pre page] have been incorporated into the Works.
The Securities shall be for the following minimum amounts equivalent as a percentage of [52]
the Contract Price:
Performance Security for 5 per cent of contract price plus Rs.2,22,08,000.00 vide BG.No.2008/02,
dt.10.12.2013 + Rs.37,92,874.00 vide BG.No.4025 IBG ISO 80062 dt.10.12.2013 valid up to 10.12.2013
(Rs.2,22,08,000.00 + Rs.37,92,874.00 = Rs.2,60,00,874/-) (Performance Security only) [in terms of ITB Clause
29.5].
The standard form of Performance Security acceptable to the Employer shall be an unconditional
Bank Guarantee of the type as presented in Section 8 of the Bidding Documents.
Not applicable [58]
The following events shall also be fundamental breach of contract: [59.2]
1. The Contractor has contravened Sub-clause 7 of GCC read with SCC and Clause 9.0 of
GCC
2. The contractor does not adhere to the agreed construction program and agreed
environmental management plan (Clause 27 of GCC) and also fails to take satisfactory
remedial action as per agreements reached in the management meetings (Clause 31) for
a period of 60 days.
3. The contractor fails to carry out of the instructions of Engineer within a reasonable time
determined by the Engineer in accordance with GCC Clause 16.1 and 23.1.
The percentage to apply to the value of the work not completed representing the Employer's [60]
additional cost for completing the Works shall be 20 percent.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
65
DIVISION-1: GENERAL SPECIFICATIONS
The term the Indian standard Specifications as used herein means the recent Indian Standard Specifications with all
amendments published up to the date of submission of tenders. A statement of applicable Indian standard Specification
applicable is tabulated below:
LIST OF INDIAN STANDARDS
S. No.
SHORT TITLE
I.S.NUMBER
I
AGGREGATES
1 Aggregate (Coarse and Fine) from Natural Source for
Concrete
383-1970
2 Natural Manufactured
Aggregates for Use in Mass Concrete
515-1950
3 Specification for Sand for Masonry 2116-1980
4 Method for Tests for Aggregates for Concrete 2386-1963
II
BUILDING STONES
1 Method of Test for Determination of Strength Properties for
natural Building Stones
Part I – Compressive Strength
Part II- Transverse Strength
Part III – Tensile Strength
Part IV – Shear Strength
1121-1974
(Part I to Part IV)
2 Quarrying Stones for Construction purposes Recommended
Practice
8321-1977
3 Measurement of Building and Civil Engineering Works 1200-1975
4 Part IV- Stone Masonry: Specifications for Dressing
Natural Building Stones
1129-1972
III
STEEL
1 Code of Practice for Bending and Fixing of Bars for
Concrete Reinforcement
2502-1963
2 Specifications for High Strength Deformed Steel Bars and
Wires for Concrete Reinforcement
1786-1985
3 Welding of MS bars used for Reinforcement 2751-1966
4 Use of Metal Welding for Construction in Mild Steel 816-1969
5 Deformed Bars for RCC Reinforcement Hot Rolled MS and
Medium Tensile Steel
1130-1966
6 Recommendation for Detailing of Reinforcement in
Reinforced Cement Concrete Works
5525-1969
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
66
S. No.
SHORT TITLE
I.S.NUMBER
7 Mild Steel and Medium Tensile Steel Bars for Concrete
Reinforcement
432-1960
8 Code of Practice for Bending and Fixing of Bars for
Concrete Reinforcement
(Part-I)
9 Code of Practice for Safety and Health Requirement in
Electric and Gas Welding and Cutting Operations
818-1968
10 Code of Practice for Fire Precautions in Welding and
Cutting Operations
3016-1966
11 Measurement of Building and Civil Engineering Works 1200-1967
12 Measurement of Building and Civil Engineering Works
(Steel Work and Iron Work)
1200-1967
(Part – VIII)
13 Filter Rods and Wire for Gas Welding 1278-1972
IV
MASONRY:
1 Code of Practice for Construction of Stone Masonry Part-I
Rubble Stone Masonry
1597
(Part-I) – 1967
2 Code of Practice for Construction of Stone Masonry Part –
II Ashlar Masonry
1597
(Part-II) – 1967
3 Specifications for Fly ash for Use as Pozzolana 3812-1981
(Part I)
4 Measurement of Building and Civil Engineering Works
Part – XII Plastering and Pointing
1200-1976
(Part-XII)
V
CONCRETE:
1 Measurement of Building and Civil Engineering Works
Method of Concrete Works
1200-1974
2 Concrete Works Code of Practice for Plain and Reinforced
Concrete
456-2000
3 Pre-cast Concrete Coping Blocks 5751-1969
4 Method of Test of Strength of Concrete 516-1959
5 Code of Practice for Laying in-situ Cement Concrete on
Drains
3873-1978
6 Specifications for Admixture for Concrete 9103-1979
7 Method of Test for Autoclaved Cellular Concrete Products 6441-1972 c 1973 Part-I to
IX
8 Method of Sampling and analysis of Concrete 1199-1976
9 Concrete Mixer – Batch Type 1971-1968
10 Concrete Vibrators – Immersible Type 2502-1968
11 Method of Test for Permeability of Cement Mortars and
Concrete
3035-1966
12 Specifications for Fly ash for Use as Pozzolana as
Admixture for Concrete
3812-1966
(Part-II)
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
67
S. No.
SHORT TITLE
I.S.NUMBER
13 Portable Swing weigh Batch for Concrete (Single And
double Bucket Type)
2722-1964
14 Code of Practice for Installation of Joints in Concrete
Pavements
6509-1972
VI
EARTH WORK
1 Method of Measurement of Building and Civil Engineering
Works Part – I Earth Work
1209-1974
(Part-I)
2 Safety Code for Piling and other deep foundations 5121-1969
3 Code of Practice for Design, Installation, Observation and
Maintenance of Uplift Pressure pipes for Hydraulic
Structure on Permeable Foundation
6532-1972
4 Safety Code for Excavation Works 3764-1966
5 Protection of Slopes for Reservoir Embankments 8237-1976
6 Code of Practice for Earth Works on Canals 4701-1982
7 Guidelines for Lining of Drains in Expansive Soils 9451-1980
8 Method of Test for Soils Part-I Determination of Water
Content
1973
9 Determination of Water content , Dry Density 2720-1975
(part-VII)
10 Determination of Dry Density of Soils in Place 2720-1975
(part-XXVIII)
11 Determination of Dry Density of Soils in Place 2720-1975
(part-XXIX)
12 Safety Code of Blasting and Related Drilling Operations 4031-1967
13 Guide Lines for Planning and Design of Surface Drains 8835-1978
VII
CEMENT
1 Specification for 33 Grade ordinary Portland cement 269-1989
2 Specification for Rapid hardening Portland cement 8041-1990
3 Specification for Portland Pozzolona cement. 1489 – (part. 1&2) 1991
4 Methods of physical test for hydraulic cement 4032 – 1988
5 Method of chemical analysis of hydraulic cement.
4032 – 1985
6 Method of sampling for hydraulic cement
3535 – 1986
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
68
S. No.
SHORT TITLE
I.S.NUMBER
7 Standard sand for testing of cement
650 – 1991
8 Specification for 43 Grade OPC……
8182 – 1989
9 Specifications for 53 Grade OPC……
12269 – 1987
VIII
OTHER SUBJECT
1 Safety Code for Scaffold 3698-1966
(Part-I)
2 Safety Code for Ladders 3696-1966
(Part-II)
3 Recommendation on stacking and storage of Construction
Materials at site
4082-1977
In addition to the Indian Standard Specifications, wherever necessary the specifications prescribed in Andhra
Pradesh Standard Specification shall also be followed.
______________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
69
DIVISION – 2 : SITE WORK
SECTION-2.1: CLEARING AND GRUBBING
a) Clearing:
The portion of the right-of-way where required for construction the work under these specifications shall be
cleared of all vegetation, plants, bushes, rubbish, and other objectionable matter. Trees designated by the
Engineer-in-Charge shall not be cut and shall be protected from injury. Such cleared material shall be
disposed off as provided in sub-paragraph c, below or removed from the site of work before the date of
completion of the contract as approved by the Engineer-in-Charge. The clearing operation shall be in
accordance with clauses 4.1, 4.1.1, 4.2 and 4.3 of I.S.4701-1982 Indian code of practice for earth work in
canals. Surface boulders either loose or partly embedded in the ground will have to be removed and stacked
as directed.
b) Grubbing:
The ground surface under all embankments of normal dimensions as shown on the drawings and under other
embankments where directed by the Engineer-in-Charge and the surface of all excavation that is to be used
for embankments shall be cleared of all stumps, roots and vegetable matter of every kind. The stumps shall
be pulled or otherwise removed and roots shall be grubbed.
c) Disposal of cleared and grubbed material:
The disposal of cleared and grubbed material shall be in accordance with clause 4.1.1 of I.S.4701 Code of
practice for earth work in canals. All waste material to be burnt shall be piled neatly and when in suitable
condition, shall be burnt completely to ashes. Piling of waste material for burning shall be done at such a
location and in such a manner as would not cause any fire risk. Necessary precaution shall be taken to
prevent spreading of fire to areas beyond the limits of cleared areas. Suitable materials and equipment for
prevention and suppression of fire shall be kept available at all times.
d) Payments:
Separate payment will not be made for clearing and grubbing including disposal of the cleared and grubbed
material required under the above paras. The contractor shall include the cost thereof in the price bid in the
bill of quantities of the contract for the relevant finished item of work for which clearing and grubbing as
mentioned in the above paras are required. No payment towards removal of small stones and boulders of size
less than 0.03 cubic meters will be made and the rate quoted for excavation should be inclusive of this item.
However surface boulders of size greater than 0.03 cum but less than 3 cubic meters, either loose or partly
embedded in the ground when removed, payment will be made for actual quantity at the rate quoted in bill of
quantities for the relevant classification on stack measurement, duly deducting 40% towards voids.
Payment will be made for clearing of juliflora (prosafis) jungle including uprooting and removing of
juliflora etc., complete and thrown out side the banks at the rate quoted in bill of quantities.
_________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
70
DIVISION – 3 : EARTH WORK
SECTION 3.1: EXCAVATION
3.2.1 Excavation for Canals/ Drains :
General:
The canal/ drain sections are shown on the drawings. Drains are also indicated, wherever needed, on the
drawings. The Government reserves the right, during the progress of work to vary the slopes of Excavations
and the slopes of the embankment and the dimensions thereon. Any increase or decrease of quantities
excavated as a result such variations will be included in the estimates. If the Engineer-in-charge determines
that the contractors costs of performing the work will be increased or decreased by reasons of such variations
an equitable adjustment will be made to cover his increased or decreased costs and the payment will be done
as per conditions of contract. Stones and indurate material shall be removed from materials to be used for
compacted embankments. Suitable material excavated from the drains and not required for construction of
the canal / drains, embankments shall be used to construct O & M roads, ramps and bridge approach
embankments. The excavation of drain both in soils and rock shall confirm to Clauses 5.1 to 5.3 of I.S: 4701-
1982.
3.2.2 Earth Work Excavation in Canals/ Drains:
1. a) Pre-levels shall be taken by the department officers for preparation of detailed estimates reflecting the
status of pre-excavation condition of the canals before the tenders are invited. The pre-levels are with
reference to reference points fixed permanently for indicating the chainage and with reference to bench
marks established along the drains/canal on permanent points. Cross sections are generally taken at 25m
intervals along the length of the Main/Major and Medium canals and at 50 m intervals for minor canals.
Levels in the cross sections are at 3 m intervals. Where felt necessary the levels will be taken at closer
intervals. The pre-levels are recorded, checked and super checked according to the rules in force.
b) Bench marks are available along the drains/canals at about 500 metes intervals. Reference line and
center line are also available. The Contractor at his own cost shall establish additional reference lines at
suitable points as considered by him for the convenience of carrying out the works. The Contractor will be
responsible for the accuracy of his B.M s and reference lines. The Contractor shall take precautions to see
that the lines, the points (pegs etc.) and B.M s fixed by the Department are not disturbed.
2. After conclusion of the agreement for the work, the levels taken reflecting the pre-execution status of the
canal /drain are made available to the contractor. The contractor may make his own arrangements to get the
levels checked if he considers it necessary and seek clarification in the event of any variations. The decision
of the Executive Engineer as to the final reconciliation of the levels in the event of any clarification sought or
protest made by the Contractor is final.
3. The Contractor should accept and sign the record of levels after obtaining any clarifications as detailed in
condition (2) above from the Executive Engineer. The site shall be handed over and the contractor is
permitted to commence the work only after such acceptance. In case the contractor does not accept the record
of levels or delay in giving his acceptance, it will in no way alter or diminish his obligations under the
agreement and restrain the Departmental Officers in exercising their power.
4. Each milestone shall be divided into sub-reaches of 25 m. length for main and branch canals and major and
medium drains and at 50 m for minor drain depending upon the labor mustered for the purpose of executing
the work.
5. Earth work shall be done from the lower end of the drains/canal, its confluence with another drains/canal or
with sea or river and extended to the Upper end.
6. The contractor will be permitted to occupy only such length of the reach adequate for a month’s work for the
labour mustered or machinery engaged by the contractor on the commencement of the work.
7. On completion of one sub-reach, work in another sub-reach will be permitted.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
71
8. The contractor shall complete every sub-reach of 25 m for main and branch canals and major and medium
drains and 50 m for minor drains or such other length as permitted to ultimate levels and achieve the final
section of execution.
9. On completion some sub-reaches fully, the contractor shall notify such completed sub-reaches with full
details to the concerned Departmental Officers with a request to record the final measurements of such
completed sub-reaches.
10. If only part work is done in a sub-reach it does not qualify for payment and will not be measured for payment.
Any claim for payment for part work done in sub-reach will not be entertained. Where for valid reasons, only
part could be done in any sub-reach, payment for the work, done in full or the part could be made under the
orders of the Superintending Engineer.
11. The measurements for any completed sub-reach will be valid only when recorded by levels and check leveled
and super checked according to the rules in force. Payment shall then be made only for the completed sub-
reach, the measurements for which have been recorded by levels.
12. The contractor before starting the work shall construct model sections at specified intervals as per rules for
the full design section and levels.
13. a) Excavation must be done in accordance with the cross section to the designed bed levels and side slopes.
The excavated earth has to be deposited on banks for forming continuous banks on either side of the
drains/canal as directed by the department.
b) Measurement and payment: Except as specified herein, measurement, for payment of excavation for
drain/canal will be made to the lines shown on drawing or as prescribed by the Engineer-in-Charge. Payment
for excavation for drain/canal will be made at the applicable unit prices per cubic meter bid for drain/canal
excavation there for in the schedule which shall be inclusive of all head leads and head lifts based on
certification by Q.C. organization. The quantity for payment will be arrived at by taking cross section levels
of pre-drain/canal excavation levels and finished drain/canal profile at 25 M meters intervals for main and
branch canals and major and Medium drains/canal and 50 meters for minor drains and the levels on each
cross section shall be at 3 m. interval. However, in the case of Rock excavation occurring in bed or sides the
actual quantity of rock shall be arrived at by taking block levels at 3 m. interval along the entire rock area in
bed and sides. The soil classification will be based on the open classification and not on the trail Trench
classification. The decision of the Executive Engineer/Superintending Engineer regarding the classification
of soil shall be final and binding and payment will be made on this open bay classification.
3.2.3 Excavation for cut off trenches for embankments:
General: The contractor shall excavate cut off trenches for the embankments as per the details shown on the drawings.
The excavated material shall be used as follows:
a) All material suitable for embankment formation as determined by the Engineer-in-charge shall be
used in formation of embankments. Any materials unsuitable for embankment shall be disposed off as
prescribed in paragraph 3.1.4.
b) Measurements for payment of excavation for cut off trenches for embankments will be made to the
dimensions shown on the drawings and / or prescribed by the Engineer-in-charge and of the total length
excavated.
Payment for excavation of cut off trench for embankments will be made at the unit prices per cubic meter bid
in the scheduled ‘A’ for excavation. This unit price shall include the cost of placing the material, in
embankments at locations directed or otherwise disposing of the excavated materials, of pumping or
dewatering or all work necessary to maintain the excavation in good order during formation of embankment.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
72
OVERHAUL (LEADS AND LIFTS):
Measurements and Payments:
The contractor shall procure the required materials from the quarries of his choice as per specifications
mentioned in the tendered schedules and as per drawings. The quoted rates shall be inclusive of all leads and
lifts of all materials etc., Complete for finished item of work.
Beyond 100 meters head lead and depth of excavation in drain/canal exceeding 9 meters and the payment for
overhaul will be made as follows:
Measurement and payment for overhaul will be as detailed below regardless of the methods and types of
equipment used in excavation and hauling.
Where material is taken from drain/canal excavation and deposited in Drain / Canal embankment the length
of haul will be measured along the center line of the Drain from the center of gravity of the material as found
in excavation, to the center of gravity of material as deposited. Regardless of haul routes actually traveled,
the above lengths of haul will be distance measured along the center line between the center of gravity the
excavation as projected on the center line and the center of gravity of the deposit as projected on the center
line.
Where material is excavated from the Drain/Canal and is deposited in embankment other than the
embankment of drain/canal from which excavated, the length of haul will be measured along a straight line
distance as determined by the Engineer-in-charge, from the center of gravity of the material as found in the
excavation to the center of gravity of the material as deposited.
In measuring quantities of overhaul for payment, the volume of the overhauled material will be measured in
cubic meter units for excavation in rock and in soils up to hard disintegrated rock. The length of haul will be
measured as stated above in kilometers payment for overhead will be made at the unit price bid for kilometer
extra lead therefore in bill of quantities.
3.2.4 Disposal materials:
a) General:
All suitable materials removed in excavation or as much there of as maybe needed as determined by the
Engineer-in-charge shall be used in the construction of Drain/Canal embankments, roadway embankments
and for selected bedding material or for back fill about structures, If there is an excess of material in the
excavation for any reach it shall be used to strengthen the embankment on either side of the drain/canal
deposited in low areas uphill of the drain/canal to eliminate trapped drainage or otherwise wasted as directed
by the Engineer-in-charge. The disposal of excavated material shall be in accordance with clauses 8.1 and 8.2
1S 4701-1982.
When directed by the Engineer-in-charge excess material shall also be placed in low areas that may occur
adjacent to bridge sites between the O&M Road ramps and Drain/canal bank.
Material removed in excavation and not suitable or required for embankments, backfill or other required earth
work, shall be deposited in waste banks on right way owned by or controlled by the Government as directed
by the Engineer-in-charge and any overhaul necessary shall be in accordance with Para 3.2.5.
The soil obtained from drain/canal cutting which is considered useful by the Engineer-in-charge shall be fully
utilized for the formation both the banks of the drain/canal to the required profiles as shown in the drawings
simultaneously with the excavation of the drain/canal and without involving any re-handling of the earth.
The soil not useful for the banks has to be thrown parallel to the bank and away from it as may be directed by
the Engineer-in-charge during execution to form the spoil bank. (In case of deep cutting the spoils shall be so
disposed off as not to result in unsightly heaps and shall be leveled and properly dressed). The top of both the
finished banks shall slope way from the inner edge with a suitable gradient.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
73
The useful rock obtained from the canal-cutting shall not be mixed with other soils and shall be deposited on
the outer slopes of the canal drain spoil bank. If the rock and soil are mixed up while depositing at the spoil
banks suitable deduction from the agreement rate as decided by the Engineer-in-charge will be made which is
binding on the contractor.
b)Cost:
Except as specially provided in these specifications or payment for hauling or placing of individual items of
excavated materials the cost of all works described in this paragraph shall be included in the unit price per
cubic meter bid in the Bill of quantities for excavation for drain/canal.
c) Roads and Ramps:
In conjunction with construction of drain/canal embankments, the contractor shall construct operation and
maintenance roads and earth ramps adjacent to the drain and structures where shown on the drawings and
where directed at his own expense. Suitable material from required excavation shall be placed as
embankment for the Engineer-in-charge may direct excavation from borrow areas.
The Width of road shall be provided as shown in the drawings and where the width of road is not shown on
the drawings it shall have a width not less than 4.25 meters. The Work required for construction, operation
and maintenance of roads and for earth ramps shall include grading to a uniform surface equal to that
obtainable with a motor grader to provide for safe travel with a two wheel-drive automobile in high gear at
moderate speed. Special rolling or compaction will not be normally required.
3.2.5 Dewatering of Drain / Canal
a) The contractor shall not be paid separately for dewatering and the amount needed for dewatering is loaded
to the relevant item of work. The incidental dewatering during execution for the entire drain/canal and bailing
out any seepage water, rain water, drainage water, from field and town will have to be done by the contractor
and no extra will be paid on this account. If for any reasons the period of execution is prolonged or extended
to next working season resulting in forming the cross bunds and dewatering the drain/canal for the 2nd
time in
the next season no extra will be paid on this account. The contractor should make his own arrangements for
dewatering and cross bundling at his own cost during the next working season of the work not completed in
the first working season within agreement period
b) In case of any damages occurred to cross bund to rains, cyclones flash or untimely floods and tidal action
and any other account during the period of work, the contractor will have to make good the same at his cost
without hindrance to the progress of work and until work is handed over to the Department. No payment will
be made on this account. After completion of work, no payment will be made on this account the cross bunds
are to be removed by the contractor to the satisfaction of the Engineer-in-charge. The removed earth is to be
deposited as directed by the Engineer-in-charge.
c) Intermediate cross bund between adjacent reaches will have to be done by the contractor at his own cost
and no extra amount will be paid on this account. The dewatering of the drain will have to be done outside
the drain and not in to the adjacent reaches.
d) Water is proposed to be released into irrigation canals for drinking purposes for a period of about 10 to 26
days during the months of March/April (summer months) to the extent required. The Contractor has to make
all the arrangements required to prevent water entering into the drains covered under the work. No separate
charges will be paid on this account and the rates quoted by the contractor for the Various items of work in
Schedule-A of the tender shall be inclusive of the expenditure required to be incurred by the contractor for all
such arrangements as may be found necessary excavation, deposited in low areas uphill to eliminate trapped
or otherwise wasted as directed by the Engineer-in-charge. The disposal of excavated material shall be in
accordance with clauses 8.1 and 8.2 of I.S. 4701-1982.
When directed by the Engineer-in-charge excess material shall also be placed in low areas that may occur
adjacent to bridge sites between the O&M Road ramps and the bank.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
74
Material removed in excavation and not suitable or required for embankments, backfill or other required earth
work, shall be deposited in waste banks on right of way owned by or controlled by the Government as
directed by the Engineer-in-charge and any overhaul necessary shall be in accordance with Para 3.2.5.
The soil obtained from cutting which is considered useful by the Engineer-in-charge shall be fully utilized for
the formation of banks to the required profile as shown in the drawings simultaneously with the excavation
and without involving any re-handling of the earth. The soil not useful for the banks has to be thrown parallel
to the bank and away from it as may be directed by the Engineer-in-charge during excavation to form the
spoil bank. (In case of deep cutting the spoils shall be so deposited off as not to of result in unsightly heaps
and shall be leveled and properly dressed). The top of both the finished banks shall slope away from the
inner edge with a suitable gradient.
The useful rock obtained from the cutting shall not be mixed with other soils and shall be deposited on the
outer slopes of the spoil bank. If the rock and soil are mixed up while depositing at the spoil banks suitable
deduction from the agreement rate as decided by the Engineer-in-charge will be made which is binding on the
contractor.
COST:
Except as specially provided in these specifications for payment for hauling of placing of individual items of
excavated materials the cost of all work described in this paragraph shall be included in the unit price per
cubic meter bid in the Bill of Quantities for excavation.
SECTION – 3.2: EMBANKMENT
3.3.1 PRESERVATION OF SURFACES UNDER EMBANKMENTS:
The preparation of surfaces under embankments shall be in accordance with clauses 6.1 and 6.5 of I.S. 4701-
1982.
Before commencing the work, the toe of slope on each side of the banks shall be lock spitted (dog belled) and
marked by pegs firmly driven into the ground at intervals of about 20 meter profiles made by bamboo’s or
other convenient materials and strings shall be set up for guidance of the workmen at about 50 meters apart
over straight reaches and about 25 meters apart at curves. In setting of the profile for an embankment a
suitable allowance of 10% shall be made for settlement for embankment in which controlled compaction has
not been carried out.
Except in areas of rock the areas under the drain or canal embankments shall be pre wetted by sprinkler
irrigation before clearing, grubbing or excavation operations of embankments construction begins. The
moisture content shall be optimum to a depth of 1 meter below the original ground surface or to impervious
material whichever is less as directed by the Engineer-in-Charge. Whenever possible all water shall be added
uniformly in one operation. Areas on the sides of canal bank upon which the Engineer-in-Charge may direct
spill banks to be constructed will not require application of moisture.
The contractor is cautioned to control carefully the application of water and to check on the depth and amount
of water penetration during application so as to avoid over watering, accumulation of water in depressions or
excessive run off.
If at any location on embankment foundations, before or during embankment construction, there is excessive
moisture as determined by the Engineer-in-Charge steps shall be taken to reduce the moisture by excavating
drains as directed by the Engineer-in-charge by allowing adequate drain time or by any other approved
means.
The contractor shall not be entitled for any additional allowance above the unit prices bid in the schedule on
account of the requirement for excavating drains for allowing additional time for drying, delays or increased
costs due to poor traffic ability on the embankment inundations, or on the haul roads, reduced efficiency of
the equipment the contractor elects to use or on account of any operational difficulties caused by overly set
embankment foundation or haul roads.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
75
Where the ground surface under any embankment is not suitable as determined by the Engineer-in-charge for
a foundation for the embankment, the contractor shall strip the area under embankment of such unsuitable
material to such depths as may be directed. The material so removed shall be disposed off as provided in
paragraph 3.1.4. Measurement for payment of stripping unsuitable material under embankments will be made
only to the lines and to such depths as may be directed and payment therefore will be made at the unit prices
per cubic meter bid in the schedule for excavation canal or drain.
Before beginning the construction of embankments, the surface area of ground to be occupied shall be cleared
of all roots and vegetable matter of any kind stripped to a suitable depth. The stumps shall be pulled or
otherwise removed and the roots grubbed. The stumps and roots removed shall be suitable disposed off.
The depth which to soil is removed shall be adequate to remove all perishable materials and any soil which
may become unstable on saturation or may interfere with development of proper bond between foundation
and embankment. It is not necessary to remove all the soil containing fine hair like roots but only the rather
heavy mat. The underlined table may be as a guide for fixing the depth of stripping.
S. No. Type of vegetable Cover Depth of Stripping
1.
2.
Soil Containing Light Grass
Agricultural Land
5 to 7.5 centimeters
To Bottom of Ploughed Zone
Usually 15 to 20 centimeters
The ground surface under all canal embankments, excepting rock surfaces where it is below the full supply
level in the canal shall be scarified making open furrows not less than 20 centimeters deep surface at intervals
of not more than 1.0 meter. However, where the ground surface is below the bed level of the drain or canal
the entire surface of the foundations for embankments shall be stripped to a depth of not less than 20
centimeters.
Immediately after preparation of the embankment foundation the contractor shall excavate cut off trenches in
accordance with para 3.1.3. Following this operation as soon as feasible and as approved by the Engineer-in-
charge the contractor shall place and compact embankment in the cut off trenches and place 1 meter of
embankment over the entire embankment foundation compact where required. This procedure will seal the
foundation against loss of moisture and provide some consolidation of the foundation.
The cost of scarifying the foundation surface under the canal embankment and other embankments shall be
included in the unit price per cubic meter bid in the schedule for compacting embankment.
Payment for excavation for cut off trenches will be made at the unit cubic price meter bid in the bill of
quantities for excavation for canal.
Payment for compacting embankment if the cut off trenches will be made in the unit price per cubic meter bid
in the schedule for compaction embankments.
Water applied for pre-wetting areas under the canal embankments and under other embankments will not be
measured for payment and shall be included in unit price per cubic meter bid in the bill of quantities.
3.3.2 CONSTRUCTION OF EMBANKMENTS:
a) General:
Canal Embankment shall be constructed to top width and side slopes as shown on the drawing duly providing
for an allowance of 2 cm per meter height of compacted bank for settlement. The embankment shall be built
to heights as directed above those shown in the drawings. The top of all drain or canal embankments shall be
graded to be suitable for a roadway in accordance with sub paragraph (b) and the top of other embankments
shall be graded or scarified as directed.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
76
The material used for the compacted embankments shall be suitable material as determined by the Engineer-
in-charge and shall be obtained from required excavation or from approved borrow areas. The material shall
conform to clause 6.4 of I.S 4701-1982.
All material shall be deposited in embankments so that cobbles, gravel and boulders are well distributed
through other material and not to be nested in any position within or under the embankment as enunciated in
clause 6.4 of I.S. 4701-1982.
In areas where required excavation does not furnish suitable or adequate material for construction
embankments, materials shall be obtained from areas where material in excess of that required constructing
the adjacent embankment available.
Where the original ground surface is below the grade of the canal or drain and where construction of a fill
below the bottom of the canal or drain is prescribed such fill shall be placed as compacted embankment.
Where the original ground surface is below the base of a structure, the fill required to form a suitable
foundation for the structure shall be placed as compacted embankment.
DOWEL BANKS:
Dowel banks of size 500 mm x 500 mm limiting the bottom width to 2m and continuing the inner slope of the
canal prism up to top of the dowel bank. When the top width of canal bank is less than 5 meters, the size of
dowel bank may be reduced to 250 mm X 250 mm.
Payment will be made for construction of dowel banks as per Bill of Quantities.
b) Roads and Ramps:
In connection with construction of canal embankment, the contractor shall construct operation and
maintenance road and earth ramps adjacent to the drain/canal and structures where shown on the drawings
and where directed at his own expense. Suitable material from required excavation shall be placed as
embankment for the roads and ramps. If sufficient material is not available form required excavation the
Engineer-in-charge may direct excavation from borrow areas.
The width of road shall be provided as shown in the drawings and where the width of the road is not shown
on the drawings it shall have a width of not less than 4.25 meters. The work required for construction,
operation and maintenance of roads and for earth ramps shall include grading to a uniform surface equal to
that obtainable with a motor grader to provide for safe travel with a two wheeler drive, automobile in high
gear at moderate speed. Special rolling or compaction will not normally be required, provided that, if
compaction is directed the embankments shall be compacted in accordance with paragraph 3.2.3.
c) Embankment not to be compacted:
Embankments not to be compacted shall be formed conforming to clause 6.6.1 of I.S. 4701-1982. The
material for these embankments shall have optimum moisture content before earth moving equipment is
routed over the embankments. The embankment shall be built in layers not exceeding 30cm or as directed by
the Engineer-in-charge in thickness. Embankments shall be built in approximately horizontal layers carried
across the entire width of the embankments to the required slopes. Embankments shall not be widened with
loose material or by excavating machinery depositing the materials directly form the excavation
Embankments built by excavating and hauling equipment and shall be made in horizontal layers and shall be
kept as close to level as practicable. The travel over the embankments during construction shall be routed so
as to distribute the compacting effect of the equipment to the best practicable advantage.
Embankments built by excavating machinery depositing the material directly from the excavation shall be
made in horizontal layers having a thickness of 30cm or as specified by the Engineer-in-charge. Finer
portions of the material excavated shall be placed in that part of embankment nearest the water and coarser
materials shall be placed in the outer part of the embankment.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
77
d) Embankment to be compacted:
The requirements for compacted embankments shall be as specified in paragraph 3.2.3. All materials in
compacting embankments shall be placed, moistened and compacted.
e) Cost:
Expect as otherwise provided for compaction of embankments and for over haul, the costs of all work
described in this para including the cost of head leads and head lifts shall be included in the unit prices in the
bill of quantities of excavation.
3.2.3 COMPACTING EMBANKMENTS:
a) General:
Before the material for first layer of the embankment is placed, the foundation of the embankment shall be
prepared as provided in paragraph 3.2.1. and shall be moistened and compacted in the manner herein
specified for each layer to be compacted to the specified density. The embankments shall be compacted to
the specified density to the elevation to the top widths and side slopes shown on the drawings or prescribed
by the Engineer-in-charge.
The layers shall be placed in rows approximately parallel to the axis of the bank. The base of embankment at
every height is to be made to its full width of each zone as shown in the drawing plus off sets of not less than
0.45 meter beyond the finished profile on either side for compaction. No payment will be made for the
offsets or for their subsequent removal and the unit price quoted for the banking is deemed to include this.
No additions will be allowed to the slopes for full design sections of the bank after the bank is raised.
All materials in embankment to be compacted shall be placed duly moistened and compacted.
The contracting operation in the excavation of materials for the compacted embankment shall be such as will
result in an acceptable gradation of materials to provide for impermeability and stability when compacted.
The maximum dimensions of stones and indurate material placed in the compacted embankment shall not
exceed 80 millimeters. Stones or indurate materials larger than 80 millimeters shall be removed by ranking or
other methods approved by concerned Engineer-in-charge prior compacting operation. Due to size and
amount of materials larger than 80 mm, it is expected that scalping or screening operation will be required.
The moisture in soil for embankment and for filling of cut off trenches shall be determined by tests in
accordance with I.S. 2720. If the moisture content is below optimum moisture content for the given
compaction, then necessary water shall be added by sprinkling and the soil shall be compacted. If the
moisture content of the soil is more than optimum moisture content then it shall be allowed to dry down to the
optimum moisture content and then compacted. The moisture content shall be uniform throughout the layer
of material and ploughing, disking, harrowing or other methods of mixing may be required to obtain uniform
distribution.
Compaction shall be achieved by the use of smooth wheeled rollers, pneumatic type rollers, vibratory power
rollers, fuel operated vibratory compactors, sheep’s foot rollers, vibrating plates, frog rammers, power
rammers and such other equipment as shall be specified. The number of passes of different types of rollers to
be used shall be determined by testing the density of the compacted soils at site after taking trail compaction
for specified passes of the rollers. The number of passes shall be those at which the required compaction is
achieved as determined by necessary tests for each type of soil. Rolling shall commence at edges and
progress towards centre longitudinally. Each pass of the roller shall overlap not less than one third of the
track width made in the preceding areas. Density tests shall be made on each compacted layer and unless
otherwise specified dry density attained shall not be less than 98% of the maximum dry density when
compacting the “Cohesive material”. In respect of the compaction of cohesion less soils, the relative density
of compacted material shall not be less than 70%, determined in accordance with clause 6.6.3.1 of IS 4701-
1982.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
78
b) Measurement and Payment:
Payment for compacting embankment will be made by level payment at the unit price cubic meter bid
therefore in the bill of quantities and shall include the cost of placing the materials in layers, removing
materials larger than 80 mm, furnishing water and moistening as provided in this paragraph.
c) Roads and Ramps:
In connection with construction of canal/ drain embankments, the contractor shall construct operation and
maintenance roads and earth ramps adjacent to the drain and structures where shown on the drawings and
where directed at his own expense. Suitable material from required excavation shall be placed as
embankment for the roads and ramps. If sufficient material is not available from required excavation
Engineer-in-charge may direct excavation from borrow areas.
The width of the road shall be provided as shown in the drawing and where the width of road is not shown on
the drawing it shall have a width of not less than 4.25mts. The work required for construction, operation and
maintenance of roads and for earth ramps shall include grading to a uniform surface equal to that obtainable
with a motar grader to provide for safe travel with a two wheel drive automobile in high gear at moderate
speed. Special rolling or compaction will not be normally required.
3.2.4 DEWATERING OF DRAIN/CANAL:
a) The contractor shall not be paid separately for dewatering and the amount needed for dewatering is loaded to
the relevant item of work The incidental dewatering during execution for the entire drain/canal and bailing
out any seepage water, rain water, drainage water from field and town will have to be done by the contractor
and no extra will be paid on this account. If for any reasons the period of execution is prolonged or extended
to next working season resulting the forming the cross bunds and dewatering the drain/canal for the second
time in the next season no extra will be paid on this account. The contractor should make his own
arrangements for dewatering and cross bunding at his own cost during the next working season, if the work
not completed in the first working season within agreement period.
b) In case of any damages occurred to cross bund due to rains, cyclones flash or ultimately floods and tidal
action and any other account during the period of work, the contractor will have to make good the same at his
cost without hindrance to the progress of work and until work is handed over to the department. No payment
will be made on this account. After the completion of work, the cross bunds are to be removed by the
contractor to the satisfaction of the Engineer-in-Charge. The removed earth is to be deposited as directed by
the Engineer-in-Charge.
c) Intermediate cross bund between adjacent reaches will have to be done by the contractor at his own cost and
no extra amount will be paid on this account. The dewatering of the drain will have to be done outside the
drain and not into the adjacent reaches.
d) Water is proposed to be released into irrigation canals for drinking purposes for a period of about 10 days
during the months of March/April to the extent required. The contractor has to make all the arrangements
required to prevent water entering in to the drains covered under the work. No separate charges will be paid
on this account and the rates quoted by the contractor for the various items of work in schedule – A of the
tender shall be inclusive of the expenditure required to be incurred by the contractor for all such arrangements
as may be found necessary.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
79
3.2.5 TESTS AND THEIR FREQUENCIES FOR EMBANKMENT CONSTURCTION
S.No. Test Frequency of test Purpose Test designation
1. Grain size analysis
for classification
One test per day
Or
Periodically
as directed by
Engineer
To know the
classification of soil actually put in
embankment
IS : 2720-IV-1995
2. Atterberg limit test One test per day To know the
classification of soil actually put in
embankment
IS : 2720-V-1970
3. Specific gravity One test per day To know the
classification of soil actually put in
embankment
IS : 2720-III-1964
4. Field density and
moisture content
One test in
300 m3
of
earth work or test in
each layer laid
To determine the placement density
and moisture content
IS : 2720-XXVIII-1974
IS : 2720-XXIX-1996
IS : 2720-XXXIII-1971
5. Standard proctor test One test per day for
individual borrow
area
To determine MDD (maximum dry
density) and OMC
(optimum moisture
content) of the soil
and compare the
results with
laboratory value
IS : 2720-VII-1970
6. Moisture content One test in each
sample
To know the moisture content in the
sample
IS : 2720-II-1975
7. Relative density test One test in 300m3 of
earth work placement
or test in each layer
laid
To know the relative density of
cohesion
less soil
IS : 2720-XIV-1968
Note: The expenditure towards all the above tests will be borne by the contractor. The rates quoted by the contractor
shall be inclusive of this expenditure and no refund on any ground of such expenditure will be admissible.
3.2.6 MEASUREMENT
The work shall be measured on the basis of cross section. The cross section shall be taken at an interval of 25m or
at closer distances as found necessary. The cross sections will indicate separate zones of hearting casing and rock
toe etc.
3.2.7 BENCHING TO EXISTING EARTHWORK
On sloping ground or in case of existing canals where embankment portions are to be modified, benching of slopes
shall be done with a little slope towards the inside of benches so as to give a good grip/bond to the embankment soil
with the sub-grade. Unless otherwise specified, the benches shall be 0.3 X 0.6m (or of any suitable dimensions) on the
front and rear slope of the embankment. Before benching, canal slopes shall be cleared of all roots, vegetation, rubbish
etc. No separate payment shall be made for these and the rates quoted for raising the embankment is inclusive of these
operations. The areas shall be pre wet by sprinkling water before the construction of embankment.
Note: 1. Incase of cohesive soils, controlled by “Proctor Test” acceptable density of compacted earth fill placement
on main canals, branch canals shall be 98% and 95% on majors/distributories/minors etc.
2. Incase of cohesion less soils, controlled by “Relative Density Test” acceptable relative density shall be
70% in case of main canals and branch canals, while it shall be 65% in respect of majors/distributories/minors
etc.
______________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
80
DIVISION -4 : ROUGH STONE DRY PACKING
SECTION-4.1: ROUGH STONE DRY PACKING FOR APRONS AND REVETMENTS
4.1.1 GENERAL:
The section covers the specifications for construction of 600 mm/450 mm/300 mm rough stone dry packing
for pitching aprons and revetments as specified in bill of quantities and its materials.
4.1.2 QUALITY OF MATERIAL FOR PITTCHING:
Stone shall be used of required specifications and quality and shall be subject to through inspection and
approval by the Engineer. The bed pitching material shall consist of the most durable rock fragments of
approved quality selected for the purpose. The stone shall be sound, hard, dense, resistant to abrasion,
durable and free from segregation, scams, cracks, shale partings weathered portions, conglomerate, bands and
other structural defects or imperfections tending to affect their soundness and strength, stone shall generally
be freshly quarried with sharp edges and clean faces. They shall be free from rounded worn or weathered
surfaces or skin or coating. Stone subject to marked deterioration by water or weather shall not be used. The
shape of the individual stones shall be angular. Stones when immersed in water for 24 hrs shall not absorb
water by more than 5% of their weight when tested as per I.S. 1125-1974. or its latest edition.
SIZE OF STONE:
The size of stone to be used for various thickness of revetments shall be as follows:
The size of stone shall be as large as possible. In no case any fragment shall weigh less than 40 kg. The
specific gravity of stones shall be as high as possible and it shall not be less than 2.50 unless otherwise
specified. For revetments up to 450 mm thickness, the length of the stones shall be equal to the revetment
thickness. For revetment over 450 mm thick at least 50% of the stones shall be 450 mm long. No stone shall
have any dimension less than 150 mm or less than 50% of the maximum dimension of the stone. The stone
proposed for pitching under water shall be as per requirement of CE, CDO drawings.
The minimum volume of the individual stones used for various thickness of revetments shall be as follows:
---------------------------------------------------------------------------------------------------
Thickness of Revetment Volume of Stones
---------------------------------------------------------------------------------------------------
225 mm 0.015 cum
300 mm 0.015 cum
450 mm 0.030 cum
600 mm 0.045 cum
---------------------------------------------------------------------------------------------------
4.1.3 STACKING:
Stacking shall be done as detailed below at the locations specified or ordered by the Engineer.
a. Stacks shall be formed to regular shape and uniform cross section.
b. Materials shall be stacked on even ground stacking shall not be done in floods zones or in water logged areas.
c. Rough stone shall be packed so closely a to give minimum quantity of voids possible without actual dressing
of stone to fill interstices. In case of improper stacking done by the contractor, the Engineer shall have the
right to either reject the stacks partly or completely.
d. Unless otherwise, specified templates shall be provided to the sizes and dimensions of the stack as may be
specified at the contractor’s expense.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
81
4.1.4 PREPATION OF BED AND SLOPES:
a. BED:
The surface on which the rough stone is to be laid shall be excavated to the required level and leveled and
prepared for the length and width as shown on the drawings. The base shall be compacted suitably with hand
rammers or other means to have even bedding. No packing shall be uncompacted made up soil.
b. SIDE SLOPES:
The sides of banks to receive rough stone revetment shall be trimmed to the required slope and profiles put up by
means of line and pegs at intervals of 3 meters to ensure, regular, straight and a uniform slope throughout.
Depressions shall be filled and thoroughly compacted.
4.1.5 LAYING APRON (BED PITCHING) AND REVETMENT (PITCHING TO SIDES):
i) LAYING APRON (BED PITCHING):
a. Apron shall be provided to the dimensions and levels shown on drawings.
b. To ensure regular and orderly disposition of the full intended quantity of stone in the apron, template or cross
wall in dry masonry shall be built about a meter thick and to the full height of the specified thickness of apron
at intervals of 10 meters or closer as directed by the Engineer, all along the length and width of the apron. In
between the cross walls, the stone shall be hand packed.
c. The thickness of the apron shall be made with one stone only. Total thickness shall not be made up in two or
more layers.
d. The stones shall be laid closely in position of the prepared bed and firmly set with their broadest ends
downwards so that they may meet all round their bases and with the top of the stone level with the finished
surface of packing. The stones shall be laid breaking joint as far as possible in the direction of the flow of
water. The stones shall be placed normal to the surface to be protected.
e. The interstices between adjacent stones shall be filled in with stones of the proper size, well driven in, with
crow bars to ensure tight packing and complete filling of all interstices. Such filling shall be carried on
simultaneously with the placing in position of the large stones and shall in no case be permitted to lag behind.
The final wedging shall be done only after obtaining the orders of Engineer. The final wedging shall be done
with the largest size chips or spalls practicable, each chip or spall being well driven home with a hammer to
that no chip or spall is possible of being picked up or removed by hand to ensure tight packing. The sizes of
spalls shall be minimum 25 mm and shall be suitable to fill the voids in the pitching.
f. On completion, the surface presented by the apron revetment shall be even throughout, free from
irregularities and the required length, breadth and slope as specified or as shown on the plans.
ii) REVETMENT (PITCHING TO SIDES):
a. Revetment shall be constructed to the required length, level, depth and slopes shown on the drawings.
b. Profiles or strings and pegs shall be put up to ensure that the pitching is done true, straight and to the proper
slope throughout.
c. Revetment shall in all cases be built up from the foot of the bund to be riveted and built up in courses
upwards. Care is necessary that a strong to a wall or other protection is always given to the revetment which
protective measure shall be shown on the plans.
d. Stones shall be placed to the required length by derrick or by hand. Stones shall be set normal to the slope
and placed so that the largest dimension is perpendicular to the face of the slope unless such dimension is
greater than the specified thickness of pitching. The largest stones shall be placed in the bottom courses and
for use as headers for subsequent courses.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
82
4.1.6 MEASUREMENT AND PAYMENT:
i) MEASUREMENT:
The protection works shall be measured as set forth below:
i. Unless otherwise specified for measurement, materials shall have to be stacked before laying and no extra
cost will be paid to the contractor for this stacking.
ii. All linear measurement for apron and revetment shall be in meters connected 0.01 meter volume shall be
in cubic meters connected to 0.01 meters. The unit for payment shall be in one cubic meter. 1 m3
revetment/bed pitching shall not be less than 1.10 m3 stock measurements.
iii. Preparation of bed and trimming of the side slopes for laying apron and revetment to sides shall be
deemed to have been included in the main item and shall not be measured separately unless otherwise
specified.
iv. No extra payment for construction of template, cross walls in apron shall be made.
ii) PAYMENTS:
a. The bid rate for one cubic meter in the bill of quantities for finished work of apron shall include the cost of
preparing base, profiles, cost of all material, conveyance, labour tools and plants for laying, completing the
work according to the drawings and specifications.
b. The rate for one cubic meter of the stone pitching to side slopes in bill of quantities shall include the cost of
preparing the base by trimming, putting the profiles, laying stone pitching of dry rubble to the specified
thickness, lines, curves, slopes and levels and cost of all labour materials including conveyance as well as
tools and plants required for the work in completing the work as per drawings.
c. The payment will be made to the contractor for finished item of work for pitching based on levels. Pre-levels
will be taken before starting to item of the work and final levels will be recorded after the work is completed.
4.1.7 MURRAM OR GRAVEL BACKING TO ROUGH STONE DRY PACKING:
PREPARATION OF BASE:
The surface to receive the gravel backing shall be neatly trimmed to the required slopes, dimensions and free
from all roots and vegetation and profusely wetted before murram is laid on.
GRAVEL QUALITY:
a. The gravel shall be composed of well grades, coarse siliceous grains, sharp and gritty touch and free from
direct and other deleterious matter. It shall not contain lumps larger than 20 mm and the fines (passing
through 75 microns IS sieve) shall not exceed 10%.
b. The liquid limit shall be -20.
c. Plasticity Index – Not more than 6.
d. Murram stacking shall be as per standards.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
83
4.1.8 PREPARATION AND LAYING:
a. Gravel shall be mixed with water on the previous day. Next day morning, it shall be well mixed and worked
with mammoties till it can be formed into stiff plastic walls.
b. Gravel so mixed shall be carried in baskets to where it is to be laid and deposited in a single layer to give 150
mm thick of finished thickness and shall be well rammed in position with flat wooden rammers or any other
method approved by the Engineer.
c. The finished surface of gravel shall be left untouched until it dries up and does not show signs of yielding.
d. If any thickness other than 150 mm is specified the work shall be executed to this specification ramming in
layers not exceeding 150 mm thickness.
4.1.9 MEASUREMENT AND PAYMENT:
i) MEASUREMENT
a. All linear measurements shall be in meters, correct to 0.01 of a meter.
b. All volumes shall be computed correct to 0.01 cubic meters.
The gravel shall be stacked and pre-measurements shall be taken before laying. 1cum of finished item of
work shall not be less than 1.16 cum of stack measurement.
ii) PAYMENTS:
The unit for payment shall be one cubic meter.
The bid rate in bill of quantities shall be for 1 cubic meter of finished work inclusive of cost of material, all
leads, lifts, labour besides conveyance charges and incidental charges for completing the work to the
specifications and drawings.
__________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
84
DIVISION – 5: CONCRETE
SECTION – 5.1: EXCAVATION FOR STRUCTURES
5.1.1 GENERAL:
Excavation for the foundation of structures shall be to the elevation shown in the drawings or as directed by the
Engineer-in-Charge. In so far as practicable the material removed in excavation for structures shall be used for
back fill and embankments. Otherwise, it shall be wasted.
a. FOUNDATION FOR STRUCTURES / CUT OPEN:
The contractor shall prepare the foundations/cut open at structures/site by methods which will provide firm
foundation for the structures. The bottom and side slopes of common excavation upon or against which the
structure is to be placed shall be finished to the prescribed dimensions and the surfaces so prepared shall be
moistened and tamped with suitable tools to form firm foundation upon or against which to place the structure.
The contractor shall prepare the foundation for the structures/cut open as shown on respective drawings. The
natural foundation material beneath the required excavation shall be moistened if required and compacted in
place.
If it is considered necessary by the Engineer-in-Charge to consolidate the foundation strata by grouting cement,
slurry, the drilling and grouting or any other foundation treatment as directed by the Engineer-in-charge shall be
done by the contractor and the payment will be made as per agreement conditions.
Separate payment will not be made to contractor for moistening and compacting the foundation of structures. The
contractor shall include cost there of in the prices bid per cubic meter of the item of the bill of quantities for
preparation of foundations.
When unsuitable material is encountered in the foundation for structure the Engineer-in-Charge will direct
additional excavation to remove the unsuitable material. The additional excavation shall be refilled as follows. In
excavation in soils the over excavation shall be filled in by M15 grade cement concrete. Measurement and
payment for excavation back fill will be made as per clause 5.3.2.
b. OVER EXCAVATION:
If at any point in common excavation the foundation material is excavated beyond the lines required to receive the
structures, or if at any point in common excavation the natural foundation material is disturbed or loosened during
the excavation process, it shall be compact in place or where directed, it shall be removed and replaced as follows.
In excavation in soils the over excavation shall be filled in by selected bedding material and compacted. In
excavation in rock, it shall be filled by M15 grade cement concrete. Any and all excess excavation or over
excavation performed by the contractor for any purpose or reason except for additional excavation as may be
prescribed by the Engineer-in-Charge and whether or not due to the fault of the contractor shall be at the expense
of the contractor. Filling for such excess excavation or over excavation shall be at the expense of the contractor.
c. MEASUREMENT FOR PAYMENT:
Excavation for structures will be measured for payment for box cutting with vertical sides of foundation
dimensions. The contractor will have to make his own arrangements for shoring, strutting, provision of adequate
slopes for the sides to prevent slips etc. and no separate payment and charge will be paid for any incidental
charges arising either during excavation of foundation or construction of the structure.
The quantity for payment of excavation in soils and rock will be arrived at by taking prelevels and finished levels
of respective strata. Block levels will be taken at 3 meters of less interval as directed by Engineer-in-Charge. The
levels will be plotted on a graph sheet and average levels arrived at for the purpose of determining the quantity of
excavation. The contractor’s signature in taken of his acceptance has to be recorded in the cross section sheets.
Final payment will be based on levels only. The contractor shall expose the surface of the strata for the inspection
of Engineer-in-Charge for taking levels whenever the classification in strata gets changed.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
85
d. PAYMENT :
Payment for excavation for structures will be made at the unit price per cubic meter bid there for in the bill of
quantities for structures. The unit price bid in the bill of quantities for excavation for structures shall include the
cost of all labour materials for coffer dam and other temporary construction, of all pumping and dewatering, of all
other work necessary to maintain the excavation in good order during construction, of removing such temporary
to maintain the excavation in good order during construction, of removing such temporary construction where
required and shall include the cost of disposal of the excavated material.
SECTION – 5.2
5.2.1 BEYOND 100 METERS HEAD LEAD AND DEPTH OF EXCAVATION IN RIVERS EXCEEDING 9
METERS AND THE PAYMENT FOR OVERHAUL WILL BE MADE AS FOLOWS:
Measurement and payment for overhaul will be made as detailed below regardless of the methods and types of
equipment used in excavation and hauling.
Where material is taken from river excavation and deposited in river embankment the length of haul will be
measured along the centre line of the river from the centre of gravity of the material as found in excavation to the
centre of gravity of material as deposited. Regardless of haul routes actually traveled, the above lengths of haul
will be distance measured along the center line between the centre of gravity the excavation as projected on the
centre line and the centre of gravity of the deposit as projected on the centre line and the centre of gravity of the
deposit of the deposit as projected on the centre line.
Where material is excavate from the river and is deposited in embankment other than the embankment of river
from which excavated, the length of haul will be measured along a straight line distance as determined by the
Engineer-in-Charge, from the centre of gravity of the material as found in the excavation to the centre of gravity
of the material as deposited.
In measuring quantities of overhaul for payment, the volume of the overhauled material will be measured in cubic
meter units for excavation in rock and in soils up to hard disintegrated rock. The length of haul will be measured
as stated above in kilometers. Payment for over haul will be made at the unit price bid for kilometer extra lead
there for in bill of quantities.
5.2.2 DISPOSAL OF MATERIALS:
a. GENERAL:
All suitable materials removed in excavation or as much there of as may be needed as determined by the
Engineer-in-Charge shall be used in the construction or river embankments, road way embankments and for
selected bedding material or for backfill about structures. If there is an excess of materials in the excavation for
any reach, it shall be used to strengthen the embankment on either side of the river, deposited in low areas up hill
of the river or other wise wasted as directed by the Engineer-in-Charge. The disposal of excavated material shall
be in accordance with clauses 8 and 8.2 of IS 4701 – 1982.
When directed by the Engineer-in-Charge excess material shall also be placed in low areas that may occur
adjacent to bridge sits between the O&M road ramps and the river bank.
Material removed in excavation and not suitable or required for embankments, back fill or other required earth
work, shall be deposited in waste banks on right of way owned by or controlled by the government as directed by
the Engineer-in-Charge and any over haul necessary shall be in accordance with para 5.2.1.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
86
The soil obtained from river cutting which is considered useful by the Engineer-in-Charges shall be full utilized
for the formation of both the banks of the river to the required profiles as shown in drawings simultaneously with
the excavation of the river and without involving any rehandling of the earth. The soil not useful for the banks has
to be thrown parallel to the bank and away from it as may be directed by the Engineer-in-Charge during execution
to form the spoil bank. (In case of deep cutting the spills shall be so disposed of as not result in unsightly heaps
and shall be leveled and properly dressed). The top of both the finished banks shall slope away from the inner
edge with a suitable gradient.
The useful rock obtained from the river cutting shall not be mixed with other soils and shall be deposited on the
outer slopes of the river spoil bank. If the rock and soil are mixed up while depositing at the spoil banks, suitable
deduction from the agreement rate as decided by the Engineer-in-Charge will be made which is binding on the
contractor.
b. COST:
Except as specially provided in these specifications for payment for hauling or placing of individual items of
excavated materials, the cost of all work described in this paragraph shall be included in the unit price per cubic meter
bid in the bill of quantities for excavation for river.
SECTION – 5.3: BACK FILL
5.3.1 BACK FILL ABOUT STRUCTURES:
a. General:
The item for the schedule for back fill about structures including pipe portions of structures includes all back fill
required to be placed under these specification.
b. Material:
The type of material used for back fill the amount there of and the manner of depositing the material shall be
subject to approval of Engineer-in-Charge. In so far as practicable back fill material shall be obtained from
material moved in required excavations for structures. But when sufficient suitable material is not available from
this source or from adjacent river excavation additional material shall be obtained from approved borrow areas.
The borrow pit excavation, shall be in accordance with 9.1 to 9.3 of IS 9451 – 1982.
Except as otherwise provided below, back fill material if to be compacted, shall contain no stones larger than 80
mm in diameter and if not to be compacted, shall contain no stones larger than 130 mm in diameter. If the
excavation for the foundations of the structure is in swelling soils, a layer of cohesive non-swelling soil
conforming to IS 9451 – 1980 and paragraph 6.2.1 should be interposed between the swelling soil of the structure
compacted to at least 98 % standard proctors density.
c. Placing Back Fill:
Back fill shall be placed to the lines and grades shown on the drawings as prescribed in this paragraph or as
directed by the Engineer-in-charge. All back fill shall be placed carefully and spread in uniform layers so that all
spaces about rocks and clods will be filled. Backfill shall be brought up as uniformly as practicable on both sides
of walls and all sides of structure to prevent unequal loading. Back fill shall be placed to about the same elevation
on both sides of the pipe positions of the structures to prevent unequal loading and displacement of the pipe. The
contractor shall at this cost provide at least 60 cm thick earth cover over the top of pipe to prevent damage from
construction equipment loads. If a haul road is built over a pipe all back fill about and over the pipe shall be
placed to a uniform surface and no humps or depressions will be permitted at the pipe crossing. Back fill required
to be compacted shall be compacted in accordance with paragraph 5.3.2.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
87
d. Structures on Fill:
Where the original ground surface is below the base of a structure or below the bottom of pipe, all fill required for
the structure foundation and all fill up to the bottom of the pipe shall be placed as compacted embankment. The
embankment over the natural ground up to pipe bottom and over the pipe shall be laid in accordance with clauses
9..2.4, 9.2.5 and 9.2.6 of IS 783, Indian Code of Practice for laying of concrete pipes, clauses 9.2.4, 9.2.5 and
9.2.6, incorporated specify that the compacted back fill shall be placed in horizontal layers not exceeding 15
centimeters after compaction. Heavy stone shall neither be dropped on top of the pipe nor shall be allowed to roll
down the side of the embankment against the pipe.
e. Measurement and Payment:
Excavation refill required to be placed about structures that is within the pay line limits for excavation for the
structures, will be measure in place for payment as back fill about structure provided that where the contractor
selects not to excavate material which is outside the limits of the actual structure or pipe, but within the pay line
limits of excavation, all such material will be included in the measurement for payment of back fill.
Refill of excavation performed outside the established pay lines for excavation for structures shall be placed in the
same manner as specified for the adjacent back fill and such refill shall be placed at the expense of the contractor.
5.3.2 COMPACTING BACK FILL ABOUT STRUCTURES:
a. General:
Unless otherwise shown on the drawings back fill above structures shall be compacted as prescribed in 5.3.1. The
compacting equipment shall be so selected as to give maximum safety to the structure. The compaction of back
fill under or over the pipes shall be in accordance with clauses 9.2.4, 9.2.5 and 9.2.6 of IS 783. In the case of very
high embankments, the embankments shall be built to an elevation above the tope of the pipe equal to the external
diameter of pipe after which a trench shall be excavated and the pipe laid when the back fill is placed above the
vertical surfaces of the trench above the top of the pipe shall not be more than 20 cm beyond the outside diameter
of the pipe. After the pipe has been laid, suitable back fill material shall be placed around the pipe and carefully
compacted in layers, not more than 15 centimeters after compaction up to the top pipe. Thereafter, a loose fill of a
depth equal to external diameter of the pipe shall be placed before further layers are added and compacted.
Compact back fill shall be placed in horizontal layers not exceeding 15 cm after compaction.
b. Material and Compaction:
The material used for back fill to be compacted shall be selected material containing no stones larger than 80 mm
or as approved by the Engineer-in-Charge and obtained from required excavation or approved borrow pit. To
prevent unequal loading and displacement of a pipe, the back fill shall be placed and compacted in layers having
essentially the same top elevation on each side of the barrel. All materials in back fill to be compacted shall be
placed moistened and compacted as provided in paragraph 5.3.1.
c. Measurement and Payment:
Measurement for payment of compacting back fill above structures will be made in place to the lines shown on
the drawings as prescribed in this paragraph or as directed by the Engineer-in-Charge and will be made only for
the quantities actually compact within the limits of the established pay lines for back fill about structures and the
compaction of refill outside of excavation pay lines shall be performed at the expense of the contractor. Payment
for compaction back fill about structure will be made at the unit price per cubic meter bid therefore, in the bill of
quantities and will be in addition to the payment made for back fill about structures.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
88
The unit price bid in the schedule for compaction back fill about structures shall include the costs of furnishing
water and moistening material.
Cast-in-place concrete for the structures shall confirm to the requirements of section 5.5 pipe and fittings
miscellaneous metal work, mechanical and electrical equipment and other items forming a part of the structure are
provided for else where in these specifications. The structure will be located at various points along the river as
shown on the drawings, or as otherwise designated.
SECTION – 5.4: CONCRETE STRUCTURES:
5.4.1 CONCRETE IN STRUCTURES:
a) Concrete is structures shall conform to the requirement of paragraphs 5.5.1 through 5.5.25.
b) Measurement and payment for concrete in structures will be made as prescribed in paragraph 5.5.24 and
5.5.25.
5.4.2 CONSTRUCTION OF STRUCTURES:
The structures to be constructed include the following.
a) Road bridges including abutment and piers.
b) Cross drainage works like under tunnels, aqueducts, super passages, and inlets and outlets.
c) Regulators
d) Out-take sluices
e) Out fall sluices
f) Spill way Regulator
g) Anicut and Aprons.
The item of schedule for concrete in the structures includes all cast in place concrete in the structures listed at (a)
to (g) above.
The structures will be located at various points along the canal/drain as shown on the drawings, or as otherwise
designated.
The structures shall be built to the lines, grades and dimension as shown on the drawings. The dimensions of each
structure as shown on the drawings will be subject to such modifications as may be found necessary by the
Engineer-in-charge to adopt the structure to the conditions disclosed by the excavation or to meet other
conditions. Where the thickness of any portion of a concrete structure is variable, it shall vary uniformly between
the dimensions shown. Where necessary as determined by the Engineer-in-charge the contractor will be furnished
additional detailed drawings of the structures to be constructed. The contractor will not be entitled to any
additional allowances above the prices bid in schedule by reason of the dimensions fixed by the Engineer-in-
charge or by reasons of some modifications of extensions of a minor character to adopt a structure to a situation,
site as determined by the Engineer-in-charge.
The cost of furnishing all materials and performing all work for installing timber, metal and other accessories for
which specific prices are not provided in the schedule shall be included in the applicable prices bid in the schedule
for the work to which such items are appurtenant.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
89
SECTION – 5.5: GENERAL CONCRETE REQUIREMENTS
5.5.1 GENERAL: Concrete shall be composed of cement, sand coarse aggregate water and admixtures (if any) as specified and
all well mixed in concrete mixers by weight and brought to the proper consistency. It shall conform to IS 456-
2000.
5.5.2 CEMENT
The cement to be used on works shall be of the following types subject to the approval of the Engineer-in-
Charge.
a. 33 Grade OPC conforming to IS 269
b. 43 Grade OPC conforming to IS 8112
c. 53 Grade OPC conforming to IS 12269
d. Portland slag cement conforming to IS 455
e. Portland Pozzolana Cement conforming to IS 1489 (Part I)
Or any other type specified by the Engineer-in-charge
I. CEMENT PROCUREMENT AND STORAGE
i. The contractor shall make his own arrangements to procure cement of specified/required specifications for the
works from reputed cement factories to the satisfaction of the Engineer-in-charge. He shall make his safer
arrangements for adequate storage and transportation of cement.
ii. The contractor shall produce the proof of purchase of cement from the cement factory/authorized agents. The
purchase bill supported by delivery challan and excise gate pass shall constitute adequate proof of purchase.
The cement shall be stored in such a way as to allow the removal and use of cement in chronological order of
receipt i.e. first received being first used.
iii. If godown facilities are available with the Government the same may be utilized by the contractor as per the
terms and conditions laid down by the Government. The contractor will have to produce the test certificate
for the quality of the cement procured by him. If department desires it can independently test the cement
sample. The cement sample will be provided free of cost by the contractor as and when desired for testing.
iv. Contractor shall provide satisfactory storage at site of work for adequate quantity and shall keep the cement
stored in a manner that will satisfy the Engineer-in-charge. The arrangement of storage and utilization shall
be such as to assure the utilization of cement in the order of its arrival at the storage and the contractor shall
maintain satisfactory records which would at all times show the dates of receipts and proposed utilization of
cement lying in the stores at site.
v. The Engineer-in-charge or his representative shall at all times have access to the storage and the sites of the
contractor and shall have authority to check and examine the method of storage records, accounting and
security provided by the contractor. The contractor shall comply with instructions that may be given by the
Engineer-in-charge.
vi. The contractor shall not be allowed to use the damaged cement on the work.
vii. He shall produce the test certificates issued by the manufactures. He shall make his own arrangements for
transportation and adequate storage of cement.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
90
viii. The contractor shall create a suitable and adequate infrastructure for handling, storing and conveying bulk or
bagged cement procured by him with advance planning of work to be done during the next 2 weeks to 4
weeks, duly approved by the Engineer-in-charge. Bagged cement shall be stored above the ground level in
perfectly dry and leak-proof sheds and shall be stacked not more than 8 bags high. Cement more than 3
months old shall invariably be tested to ascertain its suitability for use in terms of acceptability requirements.
II. DELIVERY OF CEMENT
The cement shall be packed in polythene bags bearing manufactures name or his registered trademarks. The words 33
grade or 43 grade or 53 grade, as the case may be (or the trade mark of other type of cement, as approved by the
Engineer) ordinary Portland cement and nominal average net mass of cement shall be legibly marked on each bag.
Bags shall be in good condition at the time of inspection. The cement bag should also be at the name of Government
of Andhra Pradesh.
III. SAMPLING (IS : 3535 – 1986)
The samples shall be taken within three weeks of the delivery and the tests as considered necessary by the Engineer,
shall be commenced within one week of sampling.
When it is not possible to test the sample within one week the samples shall be packed and stored in airtight
containers.
The contractor shall provide all facility for taking and packing the samples for testing.
IV. PHYSICAL REQUIREMENT
1. FINENESS
When tested for fineness by “Blains” air permeability analysis method (IS: 4031, part 2-1988) the specific surface of
cement shall not be less than 2250 cm2
/kg. (225 m2/kg). For determination of fineness the fineness by dry sieving (as
per IS : 4031 – Part-1 1998), the residue should not exceed 10%.
2. SOUNDNESS
When tested by ‘Le-chateleir’ method (IS:4301, part 3-1988) and autoclave method (for cement having a moisture
content more than 3%), the undried cement shall not have an expansion of more than 10mm and 0.8 percent
respectively.
3. CONSISTENCY
Normal consistency is about 30%.
4. SETTING TIME
When tested by Vicat apparatus method (IS: 4031, part 5-1988) the setting time of cement shall confirm to the
following requirements.
Initial setting time - Not less than 30 minutes
Final setting time - Not more than 600 minutes
The ratio of final penetration measured after 5 minutes of completion of mixing period to the initial penetration
measured exactly after 20 seconds of completion of mixing period shall be not less than 50 percent.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
91
5. COMPRESSIVE STRENGTH
The average compressive strength of 43 grade OPC cement tested as per IS : 4031 part 6-1988 shall be as follows:
a) 71± 1 hour - Not less than 230 kg/cm2
(16mpa)
b) 168 ± 2 hours - Not less than 330kg/cm2
c) 672 ± 4 hours (28 days) - Not less than 430kg/cm2
(43mpa)
Corresponding figures for 33 grade OPC shall be: 160 kg/cm2;
220 kg/cm2;
and 330 kg/cm2. The 28 day compressive
strength for 53 grades OPC shall be not less than 530 kg/cm2.
The cement shall show a continuous increase in strength from the strength at 72 hrs.
V. CHEMICAL REQUIREMENT
1 When tested in accordance with the method given in IS : 4032-1985 the ordinary Portland cement shall
comply with the chemical requirement as given below:
i. Total loss on ignition - Not more than 5 percent
ii. Total sulphate content - Note more than 2.5 percent
iii. Magnesia (by mass) - Not more than 6 percent
iv. Insolute residue (by mass) - Not more than 5 percent
v. Ratio of percentage of alumnia
to that from oxide - Not less than 0.66 percent
vi. Ratio of percentage of lime to
Silice, alumnia to iron oxide - Between 0.66 and 1.02.
2. TESTS
The sample of cement to be used in works shall be tested for fineness, soundness consistency, setting time, and
compressive strength in order to exercise proper control on quality in the manner as per following Indian Standards:
Test IS specification 1) Fineness by dry sieving 4031 (Part-I) - 1998
2) Fineness, Blain air permeability method 4031 (Part-1I) - 1998
3) Soundness by: 4031 (Part-II1) - 1998
i) Le-Chatelier method
ii) Autoclave method
4) Consistency 4031 (Part-IV) – 1998
5) Setting time 4031 (Part-V) - 1998
6) Compressive strength 4031 (Part-VI) – 1998
The temperature for testing shall be 27 ± 20C as far as possible.
Note: For concrete works exposed to the coastal environment, Portland slag cement conforming to IS: 455 (with slag
content more – 50 %) shall be used. Such cement exhibits better sulphate resistant and chloride resistant properties.
Sulphate resistant cement (IS 12330) shall be used wherever, so required by the Engineer-in-Charge to resist sulphate
attack.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
92
VI. REJECTION
Cement may be rejected if it does not comply with the Indian Standard requirements.
Cement in bags stored for more than 3 months shall be re-tested before use and may be rejected and shall not be used
on works if it fail to confirm to any of the requirement.
VII. TOLERANCE
Average net mass of cement packed in bags in a sample shall be equal to or more than 50kg. The number of sample to
be checked for net mass of cement per bag in a given number of bags shall be as given below:
100 to 150 bags - 20 sample
151 to 280 bags - 32 sample
281 to 500 bags - 50 sample
501 to 1200 bags - 80 sample
1201 to 3200 bags - 125 sample
3201 and above - 200 sample
The bags in a sample shall be selected at random.
5.5.3 SAND (FINE AGGREGATE)
I The sand shall be tested for grain size, specific gravity, water absorption, fineness modulus, petrographic
analysis, deleterious constituents etc. The presence of impurities if any is to be tested by chemical analysis.
Quick colour test shall also be conducted in the field to determine the presence of any harmful organic
impurities in sand with 3% solution of sodium hydroxide (caustic soda), as under :
• A colour less liquid indicates clean sand free from organic matter.
• A straw coloured liquid indicates some organic matter but not enough to be seriously objectionable.
• A dark colour will mean that the sand contains injurious amount of organic impurities and shall not be used
unless it is washed and a retest then shows that it is satisfactory.
Sand to be used shall be well graded with maximum size limit to 4.75 mm. Well-graded sand is essential to impart
good workability and good finish. The gradation requirement of sand for concrete work is indicated below:
II. MECHANICAL ANALYSIS
For concrete work, sand shall confirm to IS-383-1970, as per the following table:
Percentage Passing For IS Sieve
Designation Grading Zone-1 Grading Zone-
II
Grading Zone-III Grading
Zone-IV
10 mm 100 100 100 100
4.75 mm 90 - 100 90 - 100 90 – 100 95 – 100
2.36 mm 60 - 95 75 - 100 85 – 100 95 – 100
1.18 mm 30 - 70 55 - 90 75 - 100 90 – 100
600 micron 15 - 34 35 - 59 60 - 79 80 - 100
300 micron 5 - 20 8 - 30 12 - 40 15 – 50
150 micron 0 – 10 0 – 10 0 – 10 0 - 15
Note: Sand of zone 4 shall not be used in the reinforced concrete work.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
93
(i) FINENESS MODULUS
Sand shall have FM between 2.2 to 3.2. The sand content shall be proportioned to be around 33 to 35% of
total aggregate. However, the actual proportioning shall be fixed on the basis of lab tests. It shall, preferably
be natural sand and confirming to IS: 2116-1965. It shall be got approved from the Engineer-in-Charge
before use. The Engineer-in-Charge may allow the use of crusher fines/crushed stone sand with natural sand
after his full satisfaction that the mixture meets the specified criteria.
(ii) The amount of deleterious substances shall not exceed the percentage given below:
Deleterious substances Percentage more than Shale 1.00
Coal and ignite 1.00
Clay lumps 1.00
Cinders and clinkers 0.50
Material passing 75-micron sieve 3.00
Alkali, mica and coated grain 2.00
The sum of the percentages of all deleterious substances shall not exceed 5% by weight. The sand shall also
be sound and free from any amounts of organic impurities.
(iii) SPECIFIC GRAVITY
The sand shall have a minimum specific gravity of 2.6.
(iv) The sum of the percentages of all deleterious substances in the sand shall not exceed 5% by weight. The sand
shall also be sound and free from organic impurities.
(v) QUALITY
The sand shall consist of hard, dense, durable, unquoted rock fragments and shall be free from dust, lumps,
soft or flaky particles, shale, alkali, loam, mica and other deleterious substances.
III. ALLOWANCE FOR BULKAGE
If the sand as obtained from quarry or after its washing is found to be moist, bulkage will be measured and
allowed, provided sand is stacked at the site at least for 48 hours before use. Bulkage of such a stack will be
measured regularly as directed by the Engineer-in-Charge and allowed according to these observations.
Allowance for bulkage will be made as per Indian Standard procedure and allowance will be made as under :
Bulkage observed Allowance to be made
Below 5 % Nil
5 to 10 5 %
10 to 15 10 %
15 to 20 15 %
5.5.4. COARSE AGREEGATE
I. GENERAL
The coarse aggregate to be used shall be hard & well graded to produce a dense concrete of the specified
strength and consistency that will work readily into position without segregation. It shall be tested for
specific gravity, water absorption, deleterious materials, crushing impact, and abrasion values.
Representative samples shall also be got tested for any alkali – aggregate reaction potential. Minimum
specific gravity shall be 2.6.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
94
II. SIZE
The nominal maximum size of aggregate shall be as large as possible within the limits specified but in no
case greater than one-fourth of the minimum thickness of the member, provided that the concrete can be
placed without difficulty so as to surround all reinforcement thoroughly and fill the corners of the form work.
For most works, 20 mm aggregate shall be used and where there is no restriction to the flow of concrete into
sections, 40 mm size (MSA) shall be used. For any heavily reinforced concrete members, the nominal
maximum size of aggregate shall usually be restricted to 5mm less than the minimum cover to the
reinforcement or 5mm less than the minimum clear distance between the main bars.
Coarse aggregate shall comprise of all aggregate particles of size greater than 4.75 mm. The rubble from
which coarse aggregate is crushed shall have a crushing strength of not less than 750 kg/cm2. The aggregate
shall conform to IS: 383 -1970 clause 3.1, 3.2 and 3.2.1 (Table-1).
III. TESTS
The different tests and the zone of acceptability limits are given below:
Name of test IS code Acceptance criteria
Sieve analysis IS 2386-Part-1-1963 As per concrete design
Deleterious materials IS 2386 – Part-II - 1963 Less than 5 %
Specific gravity IS 2386 – Part-III - 1963 2.5 to 3.0
Absorption value IS 2386 – Part-III- 1963 Less than 5% by weight
Aggregate crushing value IS 2386 – Part-IV - 1963 For wearing surface, less than
30%, for concrete other than
wearing surface less than
45%
Impact value IS 2386 – Part-IV - 1963 As above
Abrasion value IS 2386 – Part-IV - 1963 For wearing surface, less than
30%, for concrete other than
wearing surface less than
50%
Soundness (Sodium
sulphate method)
IS 2386 – Part-V - 1963 Less than 12 %
Petrographic examination IS 2386 – Part-VIII - 1963 Deleterious constituents plus
silt shall not exceed 5 %
Note: The expenditure towards all the above tests will be borne by the contractor. The rates quoted by the
contractors shall be inclusive of this expenditure and no refund on any ground of such expenditure will be
admissible.
IV. GRADING
The coarse aggregate as delivered to the mixer, shall be well graded as per IS specification. Maximum size of
aggregate used for the work shall be 20mm or 40mm or as specified in items in the bill of quantities and it
shall confirm to IS : 383-1970, clause 4.2 (Table-2). However, the exact gradation required to produce a
dense concrete of specified strength and desired workability shall be decided as per laboratory test by the
Engineer.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
95
Coarse aggregate for use in concrete shall be well graded and shall conform to IS: 383-1970 requirements (as
per Table-II) given below:
% passing by weight for graded aggregate of nominal size IS Sieve
40mm 20mm 16mm 12.5mm
63mm 100 - - -
40mm 95 – 100 100 - -
20mm 30 – 70 95 – 100 100 -
16mm - - 90 – 100 100
12.5mm - - - 90 – 100
10.0mm 10 – 35 25 – 55 30 – 70 40 – 85
4.74mm 0 5 0 - 10 0 - 10 0 – 10
V. IMPURITIES
The broken stone shall be free from dust and dirt and shall be washed in necessary to ensure that all faces of
the stones are perfectly clean. The minimum individual percentages by weight of deleterious substance in
any size of coarse aggregate shall not exceed the following values:
Materials passing through No. 100 screen (ASTM) 1 %
Shale ….. 1 %
Coal ……. 1 %
Soft fragments ………. 1 %
Clay lumps ………………. 1 %
Fourth Other deleterious substances……….. 1 %
The sum of the percentages by weight of all deleterious substances in any size shall not exceed 5 %.
VI. STORAGE
Aggregate shall be stacked in such a way as to prevent the intrusion of any foreign materials such as soil,
rubbish, vegetation etc. Heaps of fine and coarse aggregate shall be kept separate. When different sizes of
fine and coarse aggregates are procured separately, they shall be stored in separate stock-piles, so that they do
not get intermixed.
The aggregate shall be stock piled near to the mixer site/B&M plan so as to require minimum re-handling
when conveyed to the mixer.
The aggregate shall be placed on a dry hard patch of ground if available, otherwise a platform or plain
galvanized iron sheets or alternatively a floor of dry bricks shall be prepared, or a floor of thin layer of lean
concrete.
To minimize moisture variations the stock piles shall be as large in area as possible but left low and fairly
uniform in height preferably 1.25 to 1.5m and the lowest layer of about 30cm height shall be allowed to act as
drainage layer and not be used till the end.
5.5.5. WATER
1.0 The water used in concrete shall be clean and free from objectionable quantities of silt, salts, organic matter,
alkali and other impurities. Normally potable water is considered satisfactory for mixing concrete. As a
guide, the following concentration represents the maximum permissible values.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
96
a) To neutralize 100ml sample of water, using phenolphthalein as an indicator, it should not require more than 5
ml of 0.02 nomral NaOH. The details of test are given in 8.1 of IS: 3025 (Part-22).
b) To neutralize 100 ml sample of water, using mixed indicator, it should not require more than 25ml of 0.02
normal H2SO4. The details of test shall be as given in 8 of IS: 3025 (Part-23).
c) Permissible limits for solids shall be as given in the following table:
Percentage of solids should not exceed the following:
Test as per
Organic - 200 mg/litre IS: 3025 (Part-18)
Inorganic - 3000 mg/litre IS: 3025 (Part-18)
Sulphates - 400 mg/litre IS: 3025 (Part-24)
Chlorides (as CI) - 2000 mg/litre for concrete not containing
embedded steel and 500 mg/litre for
reinforced concrete work. IS: 3025 (Part-32)
Suspended matter - 2000 mg/litre. IS: 3025 (Part-17)
2.0 pH value of water shall not be less than 6.0 and be within the range of 6.0 to 9.0.
3.0 Water found satisfactory for mixing concrete is also suitable for curing the concrete. However, water used
for curing should not produce any objectionable stain or unsightly deposit on the concrete surface.
SECTION 5.6: FORM WORK
5.6.1 GENERAL
Forms shall be used, wherever necessary, to confine the concrete and to shape it to the required lines. Normally
all exposed concrete surfaces having slope steeper than two horizontal to one vertical shall be formed.
The condition of forms influence not only appearance of the structure but also quality. Use of good form material
and proper form construction and maintenance is very important in field control. The use of steel form work
enhances the appearance of placed concrete. It should be recognized that it is not particularly economical to use
poor quality form. Too often any savings from use or injudicious re-use of poor timber form are negated by
manual labour in repairs and final dressing of the structure to an acceptable appearance.
5.6.2 TOLERANCES
The form work shall be designed and constructed to the shapes, lines, and dimensions shown on the drawings
within the following tolerances:
A. Linear Outline.
(a) In any 6m of length ±12 mm
(b) In any 12m of length ± 18 mm
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
97
B. Plumb, specified batter, or from the curved surfaces of all structures including the lines and surfaces of
columns, walls, piers, buttresses etc.
(a) In 3m of height ±12mm
(b) In 6m of height ±18mm
(c) In 12m of height or greater ±30mm
C. Deviations from specified
Dimensions of cross-section +12mm
of columns and beams. -6mm
D. Deviation from dimensions of footings.
(a) Dimensions of plan + 50mm
- 12mm
(b) Eccentricity 0.02 times the width of the footing in the
direction of deviation but not more than
50mm.
(c) Thickness ± 0.05 times the specified
thickness.
Note: These tolerances apply to concrete dimensions only, and specified thickness not to the positioning of vertical
reinforcement steel.
5.6.3 WORKMANSHIP, CLEANLINESS, AND STRENGTH OF FORM WORK.
The form work shall be of steel, timber forms shall not be allowed. Supports shall also be of steel. Suitable wedges in
pairs be provided to facilitate adjustment and subsequent releasing of forms. The contractor shall furnish the details of
his proposed form work to the Engineer-in-charge for his approval before erection there-of.
All rubbish, particularly chippings, saw dust and grout etc. shall be removed from the interior of forms before these
are erected. Cleanliness of forms shall be again checked after the forms are in place and before the concrete is placed.
The face of the form work, which is to be in contact with the concrete shall be cleaned and treated with suitable form
oil or release agent. The form oil shall be applied so as to provide a thin uniform coating to the forms without coating
the reinforcement.
Forms shall have sufficient strength to withstand all pressure resulting from concrete placement and vibration without
deflection from the prescribed lines during and after the placement of concrete and shall be maintained rigidly in
position. Where form vibrators are to be used, it shall be ensured that the form work is adequately rigid to effective
transmit energy from the form vibrators to the concrete without damaging or altering the positions of forms. The
forms shall be made sufficiently rigid by use of ties and bracings to prevent any displacement or sagging. Suitable
struts or stiffeners shall be used wherever considered necessary. The forms shall be made mortar tight.
After the forms for concrete structures have been erected to line and grade, they shall be meticulously inspected as to
their adequacy. If the forms are not tight, there will be a loss of mortar which shall result in honey-combing of
concrete or a loss of water which shall cause sand streaking. If the inspection reveals that the forms are not strong
enough to hold the concrete or are not braced sufficiently to stay in alignment, the Engineer-in-charge shall
immediately notify the contractor to set right the deficiencies and concrete shall not be placed before the forms are re-
inspected and found OK. It shall also be checked during inspection that the form work, as erected, conforms to the
line, grade, alignment to the specified tolerance limits. Fully adequate rigidity of forms is of paramount importance
since the tolerance limits specified are for finished concrete and NOT for the forms. Use of internal vibrators requires
that the forms be tight and strong.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
98
Stability is a very important consideration in the construction of forms. Every one concerned including the contractor
shall be made to understand that the common deficiencies resulting in form failure are:
i. Inadequate cross bracing of shores;
ii. Inadequate horizontal bracing;
iii. Failure to regulate the rate of placement of concrete in the forms;
iv. Poor regulation of the horizontal balance of the form filling;
v. Abnormal form displacements during and after concrete placement;
vi. No provision for lateral pressures; and
vii. Lack of adequate inspection of form work;
In form construction, it is very important that ready access be provided for proper placement,
working, and vibration, and for inspection of these operations.
The surface of form work shall be made such as to produce surface finishes as specified and the joints shall be tight
enough to prevent loss of liquid/slurry/mortar from concrete. Joints between the form work and the previous lift shall
be grant tight.
5.6.4 HORIZONTAL CONSTRUCTION JOINTS
A very common blemish on formed concrete surfaces is the off-set often found at horizontal construction joints where
the forms have given way a fraction of couple of centimeters at the bottom of the new lift. For surfaces where
appearance and alignment are of considerable importance, these off-sets shall be prevented by so setting the forms as
to fit snugly against the top of concrete in the previous lift and then securing them so as to remain in tight contact
during the concrete placing operations. The anchoring shall be done by using an ample number of ties and bolts,
above and within a few centimeters of the construction joint. The ties in the top of previous lift cannot be relied on to
prevent a slight spreading of the forms at the joint. Forms shall overlap the hardened concrete in the lift previously
placed by not more than about 50mm though 25mm lap is considered sufficient. Utmost care shall thus, be taken by
the contractor to ensure that the construction joints are smooth, free from sharp deviations, projections, or edges.
5.6.5 SPALLING FROM THE FACE OF CONCRETE
Occasionally, spalling may occur from the face of the concrete when forms are removed. This is often caused by
rough spots on the forms where mortar adheres strongly enough to over come the tensile strength of the green
concrete. Such areas on the forms shall be cleaned, polished, and then covered with a suitable form oil. Wire brushing
of timber forms shall be done very carefully to remove the set mortar as else it may aggravate the situation.
5.6.6 FILLING OF BOLT HOLES (SHE-BOLTS) OR HOLES OF TIES/RODS
The holes left on the concrete surfaces by she-bolts or rods etc. shall be reamed, cleaned, and filled with “dry pack
mortar” within a reasonable period of the removal of form work. Such filling shall be made flush with the concrete
surface.
5.6.7 RE-USE OF FORMS
The forms required to be used more than once shall be maintained in a good condition and shall be thoroughly cleaned
and repaired (if required) before reuse. Where metal sheets are used for lining the forms, the sheets shall be placed
and maintained in the forms without lumps or other imperfections. All forms shall be checked for proper shape,
cleanliness, and strength before re-use.
5.6.8 INSPECTION OF FORMS
The contractor shall inform the Engineer-in-charge well in time before commencement of placement of concrete in the
forms to enable him or his representative to inspect the formwork as to its adequacy, suitability, alignment, strength,
and overall fitness; and such inspection shall not relieve the contractor of his sole responsibility for the safety of men,
materials, equipment and the results obtained.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
99
5.6.9 QUALITY ASSURANCE
Ok Card System shall be introduced. The form-at of OK card shall be determined by the Engineer-in-charge and the
contractor or his representative shall be required to fill in the first column of ok card against all relevant items (as
prescribed by the Engineer-in-charge) and sign to indicate that these are in conformity with specifications. There after
the engineer, authorized by the Engineer-in-charge shall inspect these items and any defects pointed by him shall be
duly rectified by him. Broadly, the items shall comprise of:
• Preparation of surface of forms, form oil applications;
• Alignment, tolerances;
• Stability, bearing and support adequacy, ties, and spacers;
• Inspection openings, size, spacing, and locations;
• Final clean-up; and
• Final ok for concrete placement.
5.6.10 STRIPPING OF FORM WORK
The Engineer-in-charge shall be informed in advance by the contractor of his intention to strike/remove any form. The
forms shall not be removed until the concrete has achieved adequate strength. As per IS: 456-2000, the concrete
should have achieved a strength of at least twice the stress to which the concrete may be subjected at the time of
removal of form work. While this criteria of strength shall be the guiding factor for removal of form work, in normal
circumstances, where ambient temperature does not fall below 150
C and where ordinary Portland cement is used and
adequate curing is done, following striking period of forms be adopted, which shall satisfy the above criteria of
strength of concrete:
Type of form work
Minimum period before
striking form work
a.
Vertical form work to columns, walls, beams.
16 to 24 hours
b.
Soffit form work to slabs (props to be refixed
immediately after removal of form work)
3 days
c.
Soffit form work to beams (props to be refixed
immediately after removal of form work)
7 days
d. Props to slabs:
1. Spanning upto 4.5m. 7 days
2. Spanning over 4.5m. 14 days
e. Props to beams and arches:
1. Spanning upto 6.0m 14 days
2. Spanning over 6.0m. 21 days
For cements other than OPC and lower temperatures, the stripping time specified above shall be suitably modified by
the Engineer-in-charge. The contractor shall ensure and it is his responsibility that the number of props left under,
their sizes, and disposition shall be such as to be able to safely carry the full dead load of the slab, beam, or arch, as the
case may be, together with any live load likely to occur during curing or further construction.
Forms shall be removed with care so as to avoid any damage to the concrete. Concrete damages, if any due to removal
of forms, shall be promptly repaired by the contractor as per method of such repairs prescribed / directed by the
Engineer-in-charge to his entire satisfaction.
The cost of form is included in the concrete/lining item and will not be paid separately.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
100
SECTION – 5.7: STEEL REINFORCEMENT
5.7.1 SCOPE
This item shall cover, providing all labour, material & equipment transporting the material, storing, bending,
cutting, straightening, placing and / or correcting in position, securing and maintaining in position all
reinforcement bars plain or deformed or ribbed for steel and fabric. It also includes splicing of the bars as
shown on drawings or as required by the Engineer-in-charge and providing the hooks at the ends required.
5.7.2 GENERAL
a) This section covers specifications for providing steel reinforcement in bridges, aqueducts, super passages,
siphons, under tunnels, retaining walls, inlets, outlets, head walls, regulators, off-take sluices, canal side
walls, cut-off walls, spillways, and other similar concrete structures.
b) This work shall consists of furnishing and placing reinforcement of the shape, size/dimensions shown on the
drawings and as specified in the specifications, including cutting, bending, cleaning, placing binding/welding,
and fixing in position. The steel reinforcement shall be arranged by the contractor.
A list of applicable Indian Standards is furnished below:
IS 456 – 2000 Code of practice for plain and Reinforced concrete.
IS 1786 – 1985 Specifications for high strength deformed steel bars and wires for concrete
reinforcement.
IS 432 - 1982 Specifications for mild steel and medium steel bars for
(Part-1) concrete reinforcement and hard drawn steel wire.
IS 2502–1963 Code of practice for bending and fixing of bars for concrete
reinforcement.
IS 9417–1989 Recommendations for welding cold worked bars for
reinforced concrete construction.
IS 2751-1979 Welding of mild steel plain and deformed bars for reinforced construction.
IS 814-1996 Electrodes for manual arc welding of carbon and carbon
manganese steel.
IS 1278-1972 Filler rods and wires and gas welding.
5.7.3 MATERIAL
The contractor shall make his own arrangements to procure high yield strength deformed (HYSD) bars to IS
432 – 1982, as shown on the drawings. Tested quality of steel reinforcement bars shall be used. Requisite
I.S.I. test certificates are to be provided to the Engineer-in-charge before use of reinforcement on the work.
Steel bars shall be stored in such a way as to avoid distortion and to prevent deterioration by corrosion.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
101
The diameters and weight of steel bars be as following:
S.No. Diameter of bar Sectional weight in Kg. Per running meter
both for plain and HYSD steel bars.
1. 6 mm 0.22
2. 8 mm 0.39
3. 10 mm 0.62
4. 12 mm 0.89
5. 14 mm 1.21
6. 16 mm 1.58
7. 18 mm 2.00
8. 20 mm 2.47
9. 22 mm 2.98
10. 25 mm 3.85
11. 28 mm 4.83
12. 32 mm 6.31
Note: If any steel bars other than those specified above are used, the weights shall
be as per standards steel tables.
Cutting, bending, and binding of reinforcement.
(a) Reinforcement steel bars shall conform accurately to the dimensions given in the ‘bar bending schedules’
shown on relevant drawings.
(b) Bars shall be bent cold to the specified shape and dimensions by a bar bender by hand or power to attain
the proper and specified radii of bends as shown in the drawings.
(c) Bars shall not be bent or straightened in a manner that would injure the material.
(d) Bars bent during transport and handling shall be straightened before being used on work. The bars shall
not be heated to facilitate bending.
(e) Reinforcement bars available from any rejected reinforced concrete shall not be used.
(f) The radii of the bends in the main reinforcement bars shall not be less than 4 times bar diameter for plain
mild steel bars or 6 bar diameters in deformed bars. The radii of bends for stirrups shall not be less than
twice the diameter of round bar. In the case of bars which are not round, and in the case of deformed
bars, the diameter shall be taken as the diameter of a circle having an equivalent effective area.
(g) Hooks/stirrups shall be suitably encased to prevent any splitting on concrete.
(h) Where reinforcement bars are bent aside at construction joints and after wards bent back into their
original positions, care shall be taken to ensure that at no time is the radius of the bend less than 4 bar
diameters for plain mild steel or 6 bar diameters for deformed bars. Care must also be taken when
bending back bars to ensure that the concrete around the bars is not damaged.
5.7.4 PLACING OF REINFORCEMENT
a) Before the reinforcement is placed, the surface bars and the surfaces of any metal
bar supports shall be cleaned of rust, loose mill scale, dirt, grease, and any other
objectionable matter.
b) All reinforcement bars shall be accurately placed in exact position shown on the drawing, and shall be securely
held in position during placement of concrete by annealed bending wire and by using stays, blocks, or metal
chairs, spacers, or other approved devices at sufficiently close intervals.
c) Wire for binding reinforcement shall be soft and annealed mild steel of 16 SWG and shall conform to IS: 280 -
1978. Binding wire shall have tensile strength of not less than 5600 Kg./Cm2 and an yield point of not less than
3850Kg/Cm2.
d) Bars shall not be allowed to sag between supports. These shall not be allowed to be displaced during concreting or
any other operation during the work.
e) The contractor must ensure that there is no disturbance caused to the reinforcing bars already placed in concrete.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
102
f) All devices used for positioning of bars shall be of non-corrodible material. Metal supports shall not extend to the
surface of concrete, except where shown in the drawings. Pieces of broken stone, or brick or wooden blocks shall
not be used.
g) Placing on layers of freshly laid concrete as work progress for adjusting of bar spacing shall not be allowed.
h) Layers of bars shall be separated by spacer bars, precast concrete blocks or other approved devices allowed by the
Engineer-in-charge.
i) Reinforcement bars after being placed in position shall be maintained in a clean condition until completely
embedded in concrete. Special care shall be taken to prevent any displacement of reinforcement in concrete
already placed.
j) It MUST BE ENSURED that CONCRETE COVER, as indicated in the drawings, IS METICULOUSLY
PROVIDED.
All bars protruding from concrete and to which other bars are to be spliced, and which are likely to be exposed for
a long period, SHALL BE PROTECTED BY A THICK COAT OF NEAT CEMENT GROUT.
k) Bars crossing each other, where required, shall be secured by binding wire (annealed) of size not less than 1mm
diameter and conforming to IS: 280-1978 in such a manner that they do not slip over each other at the time fixing
and concreting.
l) Minimum distance between individual bars
As per IS: 456-2000, the following shall apply for spacing of bars:
(A) The horizontal distance between two parallel main reinforcing bars shall
usually be not less than the greatest of the following:
i. The diameter of the bar if the diameters are equal:
ii. The diameter of the larger bar if the diameters are unequal:
iii. 5mm more than the nominal maximum size of the coarse aggregate.
Note: The size of aggregate may be reduced around congested reinforcement of comply with this
provision.
(B) Greater horizontal distance than the minimum specified in (A) above should
be provided wherever possible. However when needle vibrators are used, the horizontal distance between
bars of a group may be reduced to two-thirds the nominal maximum size of coarse aggregate, provided
that sufficient space is left between groups of bars to enable the vibrators to be immersed.
(C) wherever, there are 2 or more rows of bars, the bars shall be vertically in line
and the minimum vertical distance between the bars shall be 15mm or two-
thirds the nominal maximum size of aggregate, or the maximum size of bars,
whichever is greater.
5.7.5 SPLICING
a) Where it is necessary to splice reinforcement, the splices shall be made by lapping welding, or by mechanical
couplings.
When permitted or specified on the drawings, joints of reinforcement bars shall be butt welded so as to
transmit their full strength. Welding of bars shall be done as directed by the Engineer-in-charge and
conforming to the requirements of clause 12.4 of IS 456-2000, reproduced below:
“Welded joints or mechanical connections in reinforcement may be used but in all cases of important
connections, tests shall be made to prove that the joints are of full strength of bars connected. Welding of
reinforcement shall be done in accordance with the recommendations of IS: 2751-1966 (code of practice for
welding of mild steel bars used for reinforced concrete construction)”
• If it is proposed to use welded splices in reinforcing bars, the equipment, the material, and all welding and
testing procedures shall be subject to the approval of Engineer-in-charge. The contractor shall also carry out
test welds as required by the Engineer. No extra payment will be made for welding reinforcement test welds.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
103
• For welded splices for reinforcing bars conforming to IS: 1786-1985 (High strength deformed steel bars),
welding shall be done in accordance with IS: 9417-1979. For the reinforcing bars conforming to IS: 432
(Part-1) -1982 (mild steel)/medium steel), the welding shall be done in accordance with IS: 2751 – 1979. The
electrodes for manual arc welding shall conform to IS:814 (Part-1) 1974 and IS:814 (Part-II) 1974. Mild steel
filler rods for oxyacetylene welding shall conform to IS: 1278-1972 provided they are capable of giving a
minimum butt weld tensile strength of 41 Kg/mm2
Electric arc welding shall be used. Ends of bars shall be cleaned of all rust, mill scale, grease, paint, or any
other foreign matter before welding.
b) Reinforcing bars of 28mm in diameter and larger may be connected by butt welding provided that the lapped
devices will be permitted if found to be more practical than butt welding and if lapping does not encroach on
cover limitation or hinder concrete or reinforcement placement.
c) Reinforcing bars of 25mm in diameter and less may be lapped or butt welded whichever is considered more
practical by the Engineer-in-charge.
Note: Welded pieces of reinforcement shall be tested at the rate of 0.5% of the total number of joints
welded or as decided by the Engineer-in-Charge. Specimens shall be taken from the actual site of
work. Strength of weld provided shall be at least 25% higher than the strength of bar.
5.7.6 TOLERANCES ON PLACING OF REINFORCEMENT
Unless otherwise specified by the Engineer-in-Charge, reinforcement shall be placed within the following
tolerances (as per IS: 456-2000, clause 12.3):
a) For effective depth 200mm or less ±10mm
b) For effective depth more than 200mm ±15mm
The cover shall in no case be reduced by more than one third of specified cover or 5mm whichever is less.
5.7.7 NOMINAL COVER TO REINFORCEMENT
A. NOMINAL COVER
Nominal cover is the design depth of cover to all steel reinforcements, including links. It is the dimension
used in design and indicated in the drawings. It shall not be less than the diameter of the bar. For a
longitudinal reinforcing bar in a column, the nominal cover shall in any case be not less than 40mm or less
than the diameter of such bar. In the case of columns of minimum dimension of 200mm or less, whose
reinforcing bars do not exceed 12mm, a nominal cover of 25mm may be used.
For footings, minimum cover shall be 50mm.
The followings table may be referred to for the concrete cover for reinforcement,
unless otherwise specified.
1. Thin slabs and walls Not less than diameter of bar; minimum 15mm
2. (i) Beam sides Not less than diameter of bars; minimum 25mm.
(ii)Beam top and 2 times dia of bars; minimum 25mm.
bottom ends
3. Columns Not less than diameter of bars; minimum 25mm
upto 200mm sides and minimum 40mm above 200mm sides
4. Footings Minimum 50mm.
5. Foundations 40mm.
6. Water retaining 35mm for concrete of grade M35 or more and
hydraulic structures 40mm for concrete for grade less than M35.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
104
B. NOMINAL COVER TO MEET DURABILITY REQUIREMENT
The Engineer-in-Charge, in consultation with Designs Organization, taking into due consideration the conditions
of exposure (as per clause 8.2.2.1, Table 3 of IS: 456-2000), may require the contractor to provide the following
minimum nominal covers of reinforcement to the concrete, as per clause 26.4.2, Table 16 of IS: 456-2000, from
the durability consideration.
Nominal cover to Meet Durability Requirements.
Exposure Nominal Concrete cover
in mm not less than Mild 20mm
Moderate 30mm
Severe 45mm
Very Severe 50mm
Extreme 75mm
Notes:
1. For main reinforcement up to 12mm dia bar, for mild exposure the nominal cover may be reduced by 5mm.
2. Unless otherwise specified, actual concrete cover should not deviate from the required nominal cover by
+ 10mm and – 0 mm.
3. For exposure condition ‘Severe’ and ‘very severe’ reduction of 5mm may be made where concrete grade is
M35 and above.
5.7.8 PAYMENT
The Bid Rate in the bill of quantities for reinforcement includes cost of steel, binding wire or welding
material at site of work, its cutting, bending, cleaning, placing/welding and fixing in position as shown on the
drawings and as directed by the Engineer-in-charge . The unit rate shall also include cost of all devices for
keeping reinforcement in approved position, cost of jointing as per approved methods and all wastage,
overlaps, dowels, binding wire or welding material and spacers of bars and the cost of all incidental
operations necessary to complete the work as per specifications.
5.7.9 MODE OF MEASUREMENT
The reinforcement shall be paid as the weight in Kg/MT of the actual quantity of steel reinforcement placed
in the structure arrived at by measuring the length of bars multiplied by the standard weight per unit length of
particular diameter of bar (as shown in the bar bending schedule).
The standard weight of the bars shall be as follows:
Diameter of bar in mm Weigh in Kg./Rmt.
M.S. Round bar Ribbed tor steel bar 6 0.22 0.22
8 0.39 0.39
10 0.62 0.62
12 0.89 0.89
16 1.58 1.58
18 2.00 2.00
20 2.47 2.47
22 2.98 2.98
25 3.85 3.85
28 4.83 4.83
32 6.31 6.31
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
105
In case of deformed bars, the weight per unit length of a bar for specified diameter (in nominal size) will be as
shown in the manufactures catalog. The payment to the contractor will be done on the basis of weight given by the
manufactures.
This shall include the quantity in laps, hooks and bends. It shall not include weights of metallic chairs, hangers,
spacer of other suitable devices if used. The length of bars shall be measured to the nearest 10cm. A fraction less
than 5cm shall be neglected and fraction of 5cm or more shall be taken as 10cm.
Accurate records shall be kept at all times of numbers, size lengths and weight of bars placed in position of
different parts of work. The reinforcement shall be paid as the weight of the as actual quantity of steel
reinforcement placed in the structures arrived at by measuring the actual length of the bars used and placed as
shown in bar bending schedule including the bends and laps. The unit rate accepted for the reinforcement shall
include the cost of supplying, cutting, bending, cleaning, and attaching binding wire, separators, hangers etc. shall
be deemed to be included in the unit rate of reinforcement and shall not be measured nor paid for. Welding or
splicing whenever permitted shall not be paid for separately. Chairs if any, as per instruction of Engineer-in-
Charge will be paid separately.
SECTION 5.8 PLAIN AND REINFORCED CONCRETE
5.8.1. GENERAL
Plain and reinforced concrete work shall be carried out generally in conformity with the latest Indian Standards IS
456- 2000.
5.8.2. SCOPE OF WORK
The work covered by this shall consist of –
Furnishing all materials, equipment and labour for the manufacture, transport, placing, compaction and curing of
concrete and performing all the functions necessary and ancillary thereto, including finishing the concrete to the
required shape as per drawing.
Providing and removal of all form work, furnishing all materials, equipment and labour for the manufacture, transport,
erection, keeping in place with necessary fixture and supports, oiling complete.
All concrete involved in the R.C.C. work also stands included in this item.
5.8.3. DESIGN MIX CONCRETE
Design mix concrete (controlled concrete) shall be used for concrete of grade M10 and higher. In proportioning the
concrete, the quantity of both cement and aggregate shall be determined by mass. Water shall be weighed or measured
by volume in calibrated tank. Concrete shall be manufactured in mechanical mixers either in batching mixing plants
or mechanical mixers of various capacities (14/10 or 10/7). Alternatively, mobile self-loading weigh batching –
mixing and transporting mixers of suitable drum capacity can be used, both for mixing and transporting concrete. The
mix proportions shall be such as to ensure the workability of the fresh concrete and when concrete is hardened, it shall
have the required strength, durability, and surface finish. The contractor shall not be entitled for any additional
allowance above the price bid in the schedule due to adjustments of the mix proportions.
The mix shall be designed to produce the grade of concrete having the required workability and a characteristic
strength, not less than appropriate values given below:
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
106
Grade Designation of Specified characteristic
Concrete Compressive Strength of 150mm
Cube at 28 days in
N/mm2
M10 10
M15 15
M20 20
M25 25
The concrete mix shall be designed for the ‘target mean strength’. The target mean strength of concrete mix should be
equal to characteristic strength plus 1.65 times the standard deviation.
Target Mean Strength = Characteristic strength (28-day compressive strength) + 1.65 X Standard deviation.
Where sufficient test results for a particular grade of concrete are not available, the value of standard deviation given
below shall be assumed for design mix of concrete in the first instance. As soon as the results of samples are
available, actual standard deviation shall be used and the mix designed accordingly.
Assumed standard deviation (as per IS: 456 – 2000)
Grade of concrete Assumed standard deviation
M10 3.5
M15 3.5
M20 4.0
M25 4.0
5.8.4. INGREDIENTS
All Ingredients namely cement, sand, coarse aggregate and water shall comply with the specifications mentioned in
Section 1.C.
5.8.5. WATER CEMENT RATIO (W/C)
Water cement ratio is one of the key elements for a durable and sound concrete of adequate strength. Accordingly,
Water cement ratio shall be maintained at correct value. The water cement ratio for various grades of concrete shall be
as determined and ordered by the Engineer-in-Charge. The water contents in both fine and coarse aggregate shall be
determined regularly. The amount of added water shall be adjusted to compensate for any observed variation in
moisture content. The amount of surface water may be estimated from the following table in the absence of exact
data:
Surface water carried by aggregate
S.No. Aggregate Approx. quantity of surface water
% by mass Litre / m3
1. Very wet sand 7.5 120
2. Moderately wet sand 5.0 80
3. Moist sand 2.5 40
4. Moist sand/crushed rock 1.25 to 2.5 20 to 40
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
107
5.8.6. DURABILITY OF CONCRETE
It is essential that the concrete be durable viz. it should perform satisfactorily in the working environment during its
anticipated exposure conditions during service. The materials and mix proportions are to be such as to maintain its
integrity, and (where ever applicable), to protect embedded metal/reinforcement from corrosion.
The different environmental exposure conditions are given below:
Environmental exposure conditions (as per Table 3 of IS 456: 2000)
The minimum cement content and maximum water-cement ratio to be adopted for different exposure conditions for
coarse aggregate of 20mm MSA are outlined below, as per Indian Standard IS: 456-2000. Accordingly, the design
mix shall be duly checked from consideration of durability of concrete.
Plain concrete Reinforced concrete
S. No. Exposure condition Min. cement
content
Kg/m3
Max. free
W/C ratio
Min- cement
content
Kg/m3
Max. free
W/C ratio
(i) Mild 220 0.60 300 0.55
(ii) Moderate 240 0.60 300 0.50
(iii) Severe 250 0.50 320 0.45
(iv) Very severe 260 0.45 340 0.45
(v) Extreme 280 0.40 360 0.40
The cement contents given above are irrespective of the grades of cement used. The above cement contents are for the
coarse aggregate of maximum nominal size of 20 mm. Adjustments to these minimum cement contents for aggregates
other than 20mm MSA aggregates shall be as per following table.
S. No. Environment Exposure conditions
(i) Mild • Concrete surfaces protected against weather or aggressive
conditions, except those situated in coastal area.
(ii) Moderate • Concrete surfaces sheltered from severe rain or freezing whilst
wet.
• Concrete exposed to condensation and rain.
• Concrete continuously under water.
• Concrete in contact or buried under non-aggressive soil/ground
water.
• Concrete surfaces sheltered from saturated salt air in coastal
area.
(iii) Severe • Concrete surfaces exposed to severe rain, alternate wetting and
drying, or occasional freezing whilst wet or severe
condensation.
• Concrete completely immersed in sea water.
• Concrete exposed to coastal environment.
(iv) Very Severe • Concrete surfaces exposed to sea water spray, corrosive fumes
or severe freezing conditions whilst wet.
• Concrete in contact with or buried under aggressive
subsoil/ground water.
(v) Extreme • Surface of members in tidal zone.
• Members in direct contact with liquid/solid aggressive
chemicals.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
108
S.No. Nominal maximum size aggregate mm Adjustments to minimum
cement contents Kg/m3
(i) 10 + 40
(ii) 20 0
(iii) 40 -30
The severity level in the APWSIP works may be assumed moderate to severe, except in such environment which is
associated with corrosive fumes or where the concrete work is exposed to coastal environment or buried under
aggressive sub-soil/ground water. Severity levels shall be assessed by the Engineer in consultation with Chief
Engineer concerned.
5.8.7. WORKABILITY OF CONCRETE
The concrete mix proportions chosen shall be such that the concrete is of adequate workability for the placing
conditions of the concrete and can be properly compacted. Following ranges of workability and slump of concrete,
measured in accordance with IS: 1199 shall be broadly adopted:
Placing conditions Degree of
workability
Slump
(mm)
• Mass concrete,
• Lightly reinforced sections in slabs, beams,
walls, columns;
• Floors
• Footings
Low 25-75
• Heavily reinforced sections in slabs, beams,
walls, columns. Medium 50-100
For canal lining, slump range 50-65mm is considered adequate. It can be increased upto 75mm, if considered
necessary in particular situations for practical usage.
The slump of concrete at the placement shall be as follows:
1. Beams, slabs, columns 25 mm to 40 mm
2. Section with corrugation / heavy
Reinforcement 40 mm to 50 mm
I. The needle / immersion vibrator shall be used to achieve power compaction.
II. Plain concrete:
For Plain concrete work, slump required mentioned in item-I above are applicable. If the specified slump is
exceeded at the placement, the needle / immersion vibrator and vibrator shall be used to achieve compaction.
Concrete is unacceptable. The Engineer-in-charge reserve the right to require lesser slump whenever
concrete of such lesser slump can be consolidated readily in to place by means of vibration specified by the
Engineer-in-charge. The use of any equipment which will not readily handle and place concrete of the
specified slump will not be permitted.
To maintain concrete at proper consistency, the amount of water and sand batched for concrete shall adjusted
to compensate for any variation in the moisture content or grading of aggregates as they enter the mixer.
Addition of water to compensate for stiffening of the concrete after mixing but below placing will not be
permitted. Uniformity in concrete consistency from batch will be required.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
109
5.8.8. ADMIXTURE
Admixtures such as air entraining agents, plasticizers etc. of the concrete shall only be added after the approval of the
Engineer-in-charge. Admixtures of Pozzolana if ordered shall conform to the requirements specified in IS: 9103-1979
(Indian standard Specification for admixtures for concrete).The cost of the admixture, mixing with concrete and
placing the admixed finished concrete shall be done by the contractor without any extra cost and shall stand quoted in
the unit rate of concrete.
5.8.9. MIXING
Concrete ingredients shall be mixed thoroughly in the mechanical mixer and the mixing shall be continued until there
is a uniform distribution of the ingredients and the mass is uniform in colour and consistency. Minimum mixing time
shall be 2 minutes or as determined by the Engineer. The accuracy of the measuring equipment shall be within ± 2
percent of the quantity of cement being measured and within ±3 percent of the quantity of aggregate and water being
measured.
5.8.10. TRANSPORTING AND PLACING
1. TRANSPORTING AND HANDLING
After mixing, concrete shall be transported to the formwork as rapidly as possible by methods which will
prevent the segregating or loss of any of the ingredients or ingress of foreign matter or water and maintaining
the required workability.
During hot or cold weather, concrete shall be transported in deep containers. Other suitable methods to
reduce the loss of water by evaporation in hot weather and heat in cold weather may also be adopted as per
instructions of Engineer-in-charge.
2. PLACING
The concrete shall be deposited as nearly as practicable in its final position to avoid rehandling. The concrete
shall be placed and compacted before initial setting of concrete commences and should not be subsequently
disturbed. Methods of placing shall be such as to preclude segregation. Care shall be taken to avoid
displacement of reinforcement or movement of formwork. The maximum permissible free fall of concrete
shall not be more than 1.5 m.
5.8.11. COMPACTION
1 Concrete shall be thoroughly compacted and fully worked around the reinforcement, around
embedded fixtures and into corners of the formwork.
2 Concrete shall be compacted using mechanical vibrators complying with IS 2505, IS 2506, IS 2514
and IS 4656. Over vibration and under vibration of concrete are harmful and shall be avoided. Vibration of
very wet mixes shall also be avoided.
Whenever vibration has to be applied externally, the design of formwork and the disposition of vibrators shall
receive special consideration to ensure efficient compaction and to avoid surface blemishes.
5.8.12. CONSTRUCTION JOINTS AND COLD JOINTS
Joints are a common source of weakness and, therefore, it is desirable to avoid them. If this is not possible,
their number shall be minimized. Concreting shall be carried out continuously up to construction joints, the
position and arrangement of which shall be indicated in the drawings/or as directed by the Engineer-in-
charge.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
110
Construction joints shall be placed at accessible locations to permit cleaning out of laitance, cement slurry
and unsound concrete, in order to create rough/uneven surface. It is essential to clean out laitance and cement
slurry by using wire brush on the surface of joint immediately after initial setting of concrete and to clean out
the same immediately thereafter. The prepared surface shall be in a clean saturate surface dry condition when
fresh concrete is placed against it.
In the case of construction joints at locations where the previous pour has been cast against shuttering, the
correct method of obtaining of rough surface for the previously poured concrete to be adopted is to expose the
aggregate with a high pressure water jet or any other appropriate means, such as sand blasting/chipping.
Fresh concrete shall be thoroughly vibrated near construction joints so that mortar from the new concrete
flows between large aggregates and develop proper bond with old concrete.
5.8.13.CURING
Effective curing shall be needed to prevent the loss of moisture from the concrete whilst maintaining a
satisfactory temperature regime. The curing regime is to prevent the development of high temperature
gradients within the concrete.
1. MOIST CURING
Exposed surfaces of concrete shall be kept continuously in a damp or wet condition by ponding or by
covering with a layer of sacking, canvas, Hessian or similar materials and kept constantly wet for at least 21
days from the date of placing concrete.
2. MEMBRANE CURING
Approved curing compounds can be used in lieu of moist curing for achieving fool proof curing. Such
compounds shall be applied to all exposed surfaces of the concrete as soon as possible after the concrete has
set. Impermeable membranes such as polyethylene sheet covering closed to the concrete surface may also be
used to provide effective barrier against evaporation.
5.8.14. FINISHING
1. GENERAL
Finishing of formed and unformed surface shall be performed only by skilled workmen. All exposed concrete
surfaces shall be cleaned of all incrustations of cement mortar or grout and unsightly stains shall be removed.
2. FORMED SURFACES
Surface of concrete finished against forms shall be smooth, free from projections and filled thoroughly with
mortar. Immediately upon removal of forms, all unsightly ridges of fines shall be removed and any local building
on expose surfaces shall be remedied by tooling and rubbing. All holes left by the removal of fasteners, shall after
being reamed with toothes reamer, be neatly filled with dry patching mortar. All porous and fractured concrete
and surface concrete to which additions are required to bring it to the prescribed lines shall be sharp edged and
dewed and shall be filled to required lines which fresh concrete or dry patching mortar. Where concrete is used
for filling the chipped opening, these shall not be less than 8 cm in depth and the concrete filling shall be
reinforced and dowelled to the surface of the opening. Honey combed surfaces and surfaces which give a hollow
sound, shall be rectified by guiding at the contractor’s cost, within the unit rate accepted for concrete.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
111
3. DRY PACKING
Dry packing mortar shall consist of one part of cement to 2 parts of sand by volume and just enough water, so that
the mortar as used, will stick together on being moulded into a ball by a slight pressure of the hands and will not
exclude water when pressed but will leave the hands damp. The mortar shall be placed in layers of not more than
25 mm thickness. After being compacted each layer shall be roughed by being scratched to provide and effective
bound with the succeeding layers. The last or finishing layer shall be smooth to form a surface continuous with
the surrounding concrete. All patches shall be bonded thoroughly to the surface of the chipped opening and shall
be sound and free from shrinkage cracks.
4. FINISHING PERMANENTLY EXPOSED SURFACE
Except and otherwise specified or directed all permanently exposed concrete surface and other water way surface
requiring durability under water (except the outlet) shall be finished in the following manner. Immediately upon
the removal of the forms, the surface shall be wetted and all surface pit and air bubbles filled by rubbing mortar
composed of cement and fine sand in proportion (1:2) into the pits with burlap so as to secure a uniformly dense
smooth face. The rubbing shall be performed in such a manner as to leave the surface free of extra mortar not
used for filling the pits if the filling operations be unduly delayed & the surface of the pits become coated with
dirt or other delayed & the surface of the pits become coated with dirt or other contaminating material, they shall
be thoroughly cleaned & washed and shall be maintained in a moist condition, until the mortar filling is placed.
Such cleaning shall be done by means of air and water jet and chipping or brushing or other satisfactory means
without damaging concrete. All operations in connection with the filling of surface pits shall be handled as
quickly as practicable to minimize the period during which the concrete and mortar filling are exposed to drying.
When the treatment of a surface has been completed the surface shall be neat and of the same colour and texture
as the adjoining concrete.
5. FINISHING CONCEALED SURFACE
For exterior concealed surfaces below ground or backfill level or like surfaces not otherwise specified no finish is
necessary except that sand streaks metal pockets, honey combing or other imperfections which are of consequence
affecting strength water tightness or protection of reinforcing steel from corrosion, shall be corrected and repaired
as prescribed for formed surface.
6. FINISHING UNFORMED SURFACE
Unformed surface shall be finished by one or more of the operations of screening, floating & traveling. Working
of the surfaces should be done at proper time employing experienced men and should be just sufficient to produce
the desired finish. Screeding which gives the surface it’s approximate shape by striking off surplus concrete
immediately after compaction shall be accomplished by moving a straight edge or template with a sawing motion
across wood or metal strip that have been established as guides. Where the surface is curved a special screed
should be used. Shortly after the concrete is screed the surface should be brought true to form & grade by
working it sparingly with wooden float. If a coarse textured finished is desired or if the surface is to be steel
trowelled a second or final floating should be performed after some stiffening has occurred and the surface
moisture film or shine has disappeared. Where a smooth dense finish is desired floating shall be followed by steel
trowel ling some time after moisture film, or shine has disappeared from the floated surface and when the concrete
has hardened sufficiently to prevent fine material and water from being worked out to the surface. Excessive
trowel ling particularly at an early time shall be avoided.
5.8.15. DAMAGE DUE TO FLOODS GOVT. NOT RESPONSIBLE
In case of damage of any of the concrete works due to floods, Govt. will not be responsible and whatever
corrective measures are required to be adopted shall be done by the contractor at his cost.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
112
5.8.16. SAMPLING AND STRENGTH OF DESIGNED MIX CONCRETE
(i) SAMPLING OF CONCRETE
A random sampling procedure shall be adopted to ensure that each concrete batch shall have a reasonable
chance of being tested, viz. the sampling should be spread over the entire period of concreting and cover all
mixing units (concrete production units).
(ii) FREQUENCY OF SAMPLING
The minimum frequency of sampling of concrete of each grade shall be in accordance with the following.
Quantity of concrete in the Number of samples
Work, m3
1-5 1
6-15 2
16-30 3
31-50 4
51 and above 4 plus
on additional sample for
each additional
50 m3
or part there-of.
At least one sample shall be taken from each shift.
(iii) TEST SPECIMEN Three test specimens shall be made for each sample for testing at 28 days. Additional specimens may be
taken to determine the strength of concrete at 7 days. Test results of the sample shall be the average of the
strength of 3 specimens. The individual variation should not be more than + 15% of the average strength of 3
specimens. If more, the test results of the sample are considered invalid.
(iv) ACCEPTANCE CRITERIA OF COMPRESSIVE STRENGTH
The concrete shall be deemed to comply with the strength requirement when both the following conditions
are met, as per IS: 456-2000:
(a) The mean strength determined from any group of 4 non-overlapping consecutive test results
complies with the appropriate limits in column 2 of the following table.
(b) Any individual test results complies with the appropriate limits in column3 of the following table.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
113
TABLE
Characteristic compressive strength compliance requirement
In the absence of established value of standard deviation, the following value may be assumed in the first
instance and there-after established values based on the requisite number of test results.
Grade of concrete Assumed standard deviation
M10 and M15 3.5 N.mm2
M20 and M25 4.0 N.mm2
Fck = Characteristic compressive strength of 150mm cube at 28 days in N.mm2 For M15 & M20 grades, fck
is 15 N.mm2 and 20 N.mm
2 respectively.
Standard Deviation: It is calculated from the following equation.
Sd = (X-X) 2
---------
N – 1
N = No. of samples (30 samples are generally considered)
X = Sum of the mean value of 3 test specimens of each sample divided by the number of samples, viz.
overall average strength.
X = Difference between overall average strength and the mean strength of 3 test specimens of each
sample.
(v) TESTS AND THEIR FREQUENCY
The various tests and their frequencies for concrete work shall be carried out as per following Table:
Specified
grade
Mean of the group of 4 non-
Overlapping consecutive test results in N/mm2
Individual test
results in
N/mm2
1 2 3
M 15 fck + 0.825 X established
Standard deviation (rounded off to nearest 0.5 N/
mm2 )
Or
fck + 3 N/ mm2
which ever is greater
Fck - 3
N/ mm2
M20 or above fck + 0.825 X established
Standard deviation (rounded off to nearest 0.5 N/
mm2 )
Or
Fck + 4N/ mm2 which ever is greater
Fck - 4
N/ mm2
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
114
S.N. Name of test Frequency Purpose
Indian
standard
1. Coarse Aggregates:
• Sieve analysis One test for every
150m3 or less
To know the
gradation
IS 2386 –
Part -1 1963
• Specific Gravity,
bulkdensity,
moisture content
and absorption
-do- To assess the
suitability of
aggregate and to
utilized data for
mix design
IS 2386 –
Part – III 1963
• Soundness
(Sodium sulphate
method)
-do- To assess the
quality of
materials
IS 2386 – Part –V
1963
• Abrasion, impact
& crushing values
-do- -do- IS 2386 – Part-IV
1963
• Organic impurities -do- -do- IS 2386 – Part-II 1963
• Petrographic
byanination
Twice in one season To know the
extent of
deleterious
materials & silt
content
IS 2386 – Part-VIII
1963
2. Fine Aggregate
• Screen analysis One test for every
150 m3
of sand used
in concrete
To know grain
size and fineness
modulus of sand
IS 2386 – Part-1 1963
• Unit weight and
bulkage
-do- To know
suitability of sand
and to utilize data
for mix design
IS 2386 –
Part – III
1963
• Organic impurities -do- To assess
The quality
IS 2386 –
Part – II 1963
Specific gravity,
Moisture content
-do- To utilize
data for mix
design
IS 2386 –
Part – III
1963
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
115
3. Cement:
• Fineness test One test for each
brand of cement used
during the working
season, preferably at
3 months interval
To know the
quality of cement
used in
construction
IS 4031 – 1988
• Normal
consistency
-do- -do- IS 4031 - 1988
• Setting time -do- -do- IS 4031 – 1988
• Soundness -do- -do- IS 4031 - 1988
• Compressive
strength
-do- -do- IS 4031 - 1988
• Chemical analysis -do- -do- IS 4032 - 1988
4. Finished concrete:
• Slump test One test in
each shift or at
frequent
intervals to
check
workability
To Check
workability of
concrete / water
cement ratio
IS 1199 – 1959
5. Finished Lining work
• Density of
Concrete
One core each from
bed &
both the
slopes for
250m reach.
To know the
density of
concrete used for
Lining.
The density of
concrete shall not be
less than 2400
kg/Cum.
• Permeability Two crores one each
from bed
and slope for
per Km. of
lined canal.
To know the
permeability of
concrete used for
Lining.
IS – 3085-1965
5.8.17 CONCRETE QUALITY CONTROL MEASURE AND CONCRETE QUALITY ASSURANCE TEST
PROGRAMME
a) Concrete quality control measures:
The contractor shall be responsible for providing quality concrete ensure compliance can be required.
b) Concrete quality assurance program:
The concrete samples will be taken by the Department Engineers and its quality will be tested in the
Departmental laboratory as per the relevant Indian standard specification I.S.NO.516 – 1959 and I.S. 1199 –
1959
“ A random sampling procedure shall be adopted to ensure that each concrete batch shall have a reasonable
chance of being tested, that is that the sampling shall be spread over the entire period of concreting and cover all
mixing units. Concrete of each grade shall be assessed separately. Concrete is liable to be rejected if it is porous or
honey-combed; its placing has been interrupted without providing a proper construction joint; the reinforcement has
been displaced beyond the specified tolerances or construction tolerances have not been met. However, the hardened
concrete may be accepted after carrying out suitable remedial measures to the satisfaction of Engineer-inCharge”.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
116
5.8.18 MODE OF MEASUREMENTS AND PAYMNET
Payment shall be on the net quantity of concrete after deducting quantities for openings and other class of work. No
deduction shall be made for anchor bars reinforcement grout holes and bore or weep holes. Measurements of concrete
shall be taken within the specified pay lines for the structure or as indicated on the drawings.
Any concrete placed in the excavation beyond the line of structures to avoid use of forms shall not be paid for. The
quantity of item shall be computed by using prismodial formula only.
If block outs and slots are necessary for embedding the foundation bolt and other embedded parts shall be provided by
the contractor without any extra cost. The payment for work required for it, shall presumed to be included in the
payment of concrete item.
Payment at the rate decided by the Engineer-in-charge shall be withheld in running payments, Engineer-in-charge shall
inspect the work in relation to finished level and line of concrete laid. And withheld payments shall be released only
after receipt of acceptable test results and satisfactory finishing of work in line and level, in the opinion of the
Engineer-in-charge.
Measurement shall be on cubic metre basis and paid accordingly.
SECTION 5.9 SPECIAL CONCRETE REQUIREMENTS:
5.9.1. P.V.C STRIPS:
The finished P.V.C strips shall be manufactured with shapes conforming to dimensions shown on the
drawings and shall be extruded from virgin, Pigmented, Plasticized P.V.C. The finished PVC strips shall meet
the requirement of table I and II of I.S. 9766-1981.
The PVC water stops conforming to the above requirements shall be placed in the joints as shown in
drawings. The contractor should furnish and I.S.I. test Certificate for the PVC to be proposed to use.
5.9.2 ELASTOMERIC BEARING PADS:
The contractor shall furnish and place elastomeric bearing pads at the locations shown on the drawings and in
accordance with this paragraph. Elastomeric bearing pads shall be fastened to one concrete surface with
rubber cement recommended by the manufacture of the elastomeric bearing pads. Elastomeric pads shall be
stored in as cool a place as practicable, preferably at 70 F or less. Elastomeric pads shall not be stored in open
places or where they will be exposed to the direct rays of the sun.
The Elastomeric compound shall be 100% Virgin Polychloroprene (Neoprene). The contractor should furnish
an ISI test Certificate for the Elastomeric bearing pads be proposed to use.
5.9.3. PLACEMENT OF KRAFT PAPER:
The top surface of the masonry piers and abutments should be leveled and pointed with brush, with asphalitic
emulsion of 20/30 grade, such that the bearing surface is rendered smooth and uniform. Over this surface,
Kraft paper bearing should be placed and the top painted with asphaltic emulsion of 20/30 grade. The unit
price bid therefore in bill of quantities for this item shall include the cost of all materials and labour involved
in the operations.
SECTION 5.10 DRAWINGS:
The drawings are appended to the schedule.
______________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
117
DIVISION-6: MASONRY
6.1.1 STONES FOR MASONRY:
The stones used for stone masonry shall conform to the relevant specifications of clause 3.1 of IS 1587 (part-
I)-1967 code of practice for construction of stone masonry Part-I rubble stone masonry.
The stone of the required quality shall be obtained from the quarries specified in the lead chart appended to
the bill of quantities. The common types of natural stones which are generally used are granite, trap and other
igneous rocks and shall be free from defects like decay, cavities, cracks, flaws, sand, holes, soft seams vain,
patches of soft or loose materials or any other deleterious materials like iron oxide, organic impurities etc.
They shall be free from rounded, worm or weathered surfaces or skin or occulting which prevents the
adherence of mortar. All stones used shall be clean of uniform colour and texture, strong, hard and durable.
The crushing strengths of the stone shall be determined in accordance with IS 1121-1974, the strength shall
be as detailed below Table-4(A)
TABLE-4(a)
S.No. Type of Stone Minimum Crushing Strength __________________________________________________________________
1. Granite 100 kg/sq.cm
2. Basalt 400 kg/sq.cm
3. Lime Stone 200 kg/sq.cm
__________________________________________________________________
The percentage of water absorption shall not exceed 5% by weight as determined in accordance with IS 1121-
1974.
Samples of the stones collected from the stone stacks collected by the controller will be tested for the
standards specified above and other relevant Indian Standards and stones stacks not conforming to the
standards will be rejected. Their cost shall be borne by the contractor. The contractor shall obtain these stones
from the approved quarries only.
Seignorage and Cess fee shall be recovered from the bills of the contractor on the work done and measured
with reference to the quantities used in the works as per the theoretical requirements at the rates as in force.
The approval of the quarries by the Engineer-in-Charge shall not be construed as constituting approval of all
or any of the stones collected from the deposits and the contractor will be held responsible for suitability of
the stones used in the work.
b) Cost:
The cost of collecting the stones for masonry will not be paid separately and their cost including the cost of
quarrying, transporting, stacking, royalties’ charges shall be included in the unit price per cubic meter bid
therefore in the relevant item in the bill of quantities.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
118
6.1.2 SAND FOR MASONRY:
a) General:
Sand shall generally conform to specifications given in paragraph 5.5.6 except that the sand for mortar shall
conform to the grading of sand given in clause 4 of IS 2116-1980 as detailed below in Table-6(B)
TABLE-6(B) ______________________________________________________________
Sl.No. IS Sieve Designation Percentage Passing by Mass _________________________________________________________________
1. 4.75mm 100
2. 2.36mm 90-100
3. 1.18mm 70-100
4. 600 microns 40-100
5. 300 microns 5 to 70
6. 150 microns 0-15
__________________________________________________________________
A sand whose grading falls outside the specified limits due to excess or deficiency of coarse or fine particles
may be processed to comply with the standard by screening through a suitably sized sieve and /or blending with
required quantities of suitable size and particles.
The procurement of sand for masonry shall conform to the specifications given in
paragraph 5.5.8
b) Cost:
The cost of sand or masonry will not be measured and paid separately and the cost of sand including the cost
of stripping and transporting and storing and royalty charges shall be included in the unit price per cubic
meter bid there for in the relevant item of work in the bill of quantities for which this sand is required.
6.1.3 CEMENT:
The specifications and conditions specified for supply of cement are given in paragraph 5.3.3. shall be applicable
here also.
Portland pozzolana cement conforming to IS 1489-1976 shall be used for masonry work. Ordinary Portland
cement conforming to IS 269-1976 may also be used for masonry work in the event of non-availability of
Portland pozzolana cement.
6.1.4 WATER:
The specifications and conditions specified for procuring water in paragraph 6.3.5 shall be applicable here also.
SECTION-6.2: MORTAR
6.2.1 PREPARATION OF MORTAR:
Unless otherwise specified the cement mortar used in masonry works shall be cement mortar mix MM5 (CM 1:5)
grade using minimum 288 kgs. of cement per cubic meter of mortar where a particular mix is indicated in the
specifications and drawings, it shall be used.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
119
Mixing shall be done thoroughly preferably in a mechanical mixer. In such a case, the cement and sand in the
specified proportion shall be mixed dry thoroughly in the mixer operated manually or by power.
Water shall be added gradually and wet mixing continued at least for 3 minutes. Water should not be more than
the required for bringing the mortar to the required working consistency of 90 to 130mm as required in the clause
9.1.1 of IS 2250-1981. The mix shall be clean and free from injurious kind of soil, acid, alkali, organic matter or
deleterious substances.
6.2.2 TIME OF USE OF CEMENT MORTAR:
Cement mortar shall be used as soon as possible after mixing and before it has begun to set within 30 minutes
after the water is added to the dry mixture.
Mortar unused for more than 30 minutes should not be used and shall be removed from site of work. The cost of
such wasted mortar shall be borne by the contractor. The use of retampered mortar will not be permitted to be
used for masonry.
6.2.3 TESTS OF MORTAR:
Mortar test cubes shall be cast for the mortar used on the work and shall be tested in accordance with Appendix-A
of I.S. 2250-1965., code of practice for preparation and use of masonry mortars. Such cubes shall develop a
compressive strength of at least 50 kg/square cm for M.M. 5 grade cement mortar mix, 75 kgs/square centimeter
for M.M. 7.5 grades mortar mix and 30 kgs/square centimeter for M.M.3 grade mortar mix.
Mortar not conforming to the specifications will be rejected and the cost of such wasted mortar shall be borne by
the contractor.
6.2.4 MEASUREMENT AND PAYMENT:
Cement mortar will not be measured and paid separately and its cost including cost of material, mining,
transporting and placing shall be included in the unit price per cubic meter bid there for in the bill of quantities of
the contract for the relevant finished item of work for which cement mortar mix mentioned in the above Paragraph
is required.
SECTION-6.3: STONE MASONRY
6.3.1 General:
Stone masonry in general shall conform to the requirements of I.S. 1597 code of practice for construction of stone
masonry (Part-I) 1967 rubble stone masonry Part-II 1967 Ashlar Masonry I.S.1129-1972 – specification for
dressing natural building stones.
6.3.2 SIZE OF STONE :
The length of the stones shall not exceed three times the highest nor shall the stones be less than twice as height
plus on joint. No stones shall be less in breadth than height and the breadth on base shall not be greater than ¾th
thickness of the wall not les than 15 centimeters.
6.3.3. DRESSING OF THE STONE FOR COURSED RUBBLE MASONRY:
The stones to be used for the faces of the masonry shall be hammer dressed. A hammer dressed stone also known
as hammer faced stone shall have no sharp and irregular corners and shall have a comparatively even surface so
as to fit well in the masonry. Unless otherwise specified the bushing on the face shall not be more than 40
millimeters on the exposed face.
Other stone surfaces like Rock faces stone surface, or punched stone surface or closed pitched stone surface are to
be brought out in dressing as per the orders of the Engineer-in-Charge.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
120
6.3.4 LAYING OF STONES FOR COURSED RUBBLE MASONRY:
The masonry shall be laid to lines, levels, curves, shapes shown in the drawings. Stones in the hearting shall be
laid on their broadest face.
Stratified stones must be laid on their natural beds. Bed joints shall be normal to the line of pressure upon them.
In battered wall, the beds of the stones and the plane of course should be at right angles to the batter.
The courses of the masonry shall ordinarily be predetermined. Where there is to be variation in depth of course,
larger stones shall be placed in the lower courses, the thickness of course decreasing gradually towards the top of
the wall.
The stones shall thoroughly be wetted before placing in position in the masonry and before covering with mortar.
The bed which is to receive the stone shall be cleaned, wetted and covered with a layer of fresh mortar. All stones
shall be bedded full in mortar and the vertical joints filled with mortar. The stones so covered with mortar should
be settled carefully with a wooden mallet immediately on placement and solidly bedded in mortar before it has
set. Clean clips and spalls shall be wedged into the mortar joints and beds wherever necessary. No dry or hollow
space shall be left any where in the masonry and each stone shall have all embedded faces completely covered
with mortar.
Face work and hearting shall be brought up evenly but the top of each course shall not be leveled up by use of
flat chips.
In case of any stone already set in mortar is disturbed or the joints broken, the stone shall be taken out without
disturbing the adjoining stones and the joints the mortar thoroughly cleaned from the joints and the stone reset in
fresh mortar. Attempts shall never be made to shade on stone over another already laid.
Shaping and dressing shall be done before the stone is laid in the work no dressing hammering which will loosen
the masonry will be permitted after it is once placed.
The face stone shall be squared on all joints with beds horizontal and otherwise ordered by the Engineer-in-
Charge they shall be set in regular courses of uniform thickness from bottom to top throughout. No face stone
shall be less than 150 millimeters in width for 400 millimeter thick walls, 200 millimeter in width 450 mm thick
walls and 250mm width for 600mm thick walls. More than half the quantity of stones shall each have a
volume of more than 1/70 cubic meter, 1/50 cubic meter and 1/35 cubic meter being used in for walls of 400 mm
, 450 mm and 600mm thickness respectively. The bed and vertical joints of the stone shall be hammer dressed
square with the face for a width of not less than 75 mm and 40 mm on wards from the face respectively. Bushing
shall not project more than 40 mm in faces.
Unless other wise ordered by the Engineer-in-Charge the height of each course shall be the height of the stone
used in the course. Stones of different depths should not be used. Height of each course shall not exceed breadth
at face nor thickness inwards.
The face stone shall be laid alternately in headers and stretches, so as to break joints by at least 75 mm. Headers
shall project at least 100mm beyond the stretches. The joints should not exceed 12 millimeters in thickness.
In walls upon a width of 600mm bond stones running through the walls shall be provided at intervals of 2m clear
in every course. For walls thicker than 600mm a line of headers each header overlapping the other by 150mm or
more shall be provided from front to back at 2m interval in every course. Care should be taken not to take place
the bond stones of successive courses over each other. The positions of bond stones shall be marked on both the
faces for identification and verification.
All connected masonry in a structure shall be carried up neatly at one uniform level throughout but when breaks
are unavoidable, the masonry shall be raked in sufficiently long steps for facilitating jointing of old and new work.
The stepping of the raking shall not be more than 45 degrees with the horizontal.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
121
For masonry hearting, all stories, chips, spalls etc., shall be washed clean with water before use to ensure a good
bond between the stone and the mortar. The interior of the masonry shall be filled in with good flat bedded stones
set as close as possible and well covered with mortar. Chips and spalls of stone should be covered with mortar all
round, should be wedged in the mortar joints wherever necessary, such that there are no hollow spaces, any where
in the masonry joints nor the mortar joints are thicker than specified.
6.3.5. DRESSING OF STONES FOR RANDOM RUBBLE MANSONRY:
The facing stone shall be hammer dressed on the face, sides and the head to enable it to come into close proximity
with the neighboring stone. The bushing in the face to be plastered. Stones with round surfaces shall not be used
in constructions.
6.3.6 LAYING OF STONES FOR RANDOM RUBBLE MANSONRY:
The laying of stones for Random Rubble Masonry is same as described in paragraph 6.3.4 except that the stones to be
used for face shall be stones as described in paragraph 6.3.5.
SECTION-6.4: CURING
All masonry surfaces shall be treated as specified to prevent loss of moisture from mortar until the required curing
period is elapsed or until placement of other masonry or concrete of back fill against surfaces.
All masonry built with cement mortar shall be kept watered continuously for a minimum period of two weeks from the
date of construction. Watering shall be done carefully so as not to washout the mortar joints or disturb the masonry in
any manner.
If the contractor fails to do curing to the satisfaction of the officer-in-charge of the work, the latter will either made
arrangements to cure the masonry at the risk and coat of the contractor or order the masonry to be pulled down. The
masonry so pulled down should rebuilt by the contractor at his own cost.
SECTION-6.5: MEASUREMENT AND PAYMENT
a) Measurement:
The measurement for coursed rubble masonry shall be to the lines shown in the drawings. 400 millimeters
thickness from face will be measured as coursed rubble masonry in cement mortar mix MM 5 grade and the
balance thickness of the wall will be measured as random rubble masonry in cement mortar.
b) Payment:
Payment for course rubble masonry cement mortar mix MM 5 grade shall be made at the unit prices bid there
for in the bill of quantities which unit prices shall include cost and conveyance of all materials. Dressing
charges, cost of mixing mortar, laying the masonry and curing and all incidental charges there for satisfactory
constructions of the coursed Rubble Masonry.
Payment for Random Rubble Masonry increment mortar mix MM5 grade shall be made at the prices bid
therefore in the bill of quantities which unit price shall include cost and conveyance of materials, dressing
charges, cost of mixing mortar, laying the masonry and curing and all incidental charges there for required for
satisfactory construction of the Random Rubble Masonry.
___________________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
122
DIVISION – 7: PLASTERING & POINTING
SECTION 7.1 MATERIALS
7.1.1. SAND FOR MORTAR FOR PLASTERING & POINING:
a) General:
Sand shall generally conform to specification given in paragraph 5.3.6. except that the sand for preparation of
Mortar for plastering and pointing shall conform to the following gradation, shown in Table 7 (A).
TABLE - 7 (A)
REQUIREMENT OF GRANDING FOR SAND FOR EXTERNAL PLASTERING AND
RENDERING
I.S. Sieve designation Percentage by weight passing L. S. Sieve
Class - A Class – B
4.75 mm 100 100
2.36 mm 90 to 100 90 to 100
1.18 mm 70 to 100 70 to 100
600 micron 40 to 85 40 to 95
300 micron 5 to 50 10 to 65
150 micron 0 to 10 0 to 15
For the purpose of indicating the suitability for use, the sand classified as Class A and Class B in accordance
with the limits of grading. Class A sand shall be used generally for plastering and pointing and which they
are not available Class – B sands may be used with the approval of Engineer-in-Charge.
The procurement of sand for motor for plastering and pointing shall conform to the specifications given in
paragraph 5.3.8.
b) COST:
The cost of sand for mortar for plastering and pointing will not be measured and paid separately and the cost
of sand including the cost of striping, transporting, storing and royalty charges shall be included in the unit
price per cubic meter bid therefore in the relevant item of work in the bill of quantities for which this sand is
required.
7.1.2 CEMENT:
The specifications and conditions specified for supply of cement in paragraph 5.3.3. shall be applicable here
also.
Portland Pozzolona cement conforming to I.S. 1489 – 1976 shall be used for preparation of mortar for
plastering and pointing work. Ordinary Portland cement conforming to I.S. 269 – 1976 may also be used for
plastering and pointing work in the event of non-availability of Portland Pozzolona cement.
7.1.3. WATER:
The specifications and conditions specified for procurement of water in paragraph 5.3.5 shall be applicable
here also.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
123
SECTION 7.2 MORTAR
7.2.1 PREPARATION OF MORTAR FOR PLASTERING WORK:
Unless otherwise specified the cement mortar used in plastering work shall be in cement mortar mix of M 7.5
Grade using minimum 360 kgs of cement per cubic meter of mortar. Where a particular mix is indicated in
the specifications and drawings, it shall be used.
The other specifications and conditions enunciated in paragraph 3.2.1 shall apply for this mortar for plastering
work also.
7.2.2 PREPARATION OF MORTAR FOR POINTING:
The cement mortar used in pointing work shall be cement mortar mix of M 7.5 grade, using 360 kgs of
cement per cubic meter of mortar where a particular mix is indicated in the specifications and drawings, it
shall be used.
The other specifications and conditions enunciated in paragraph 3.2.1 shall apply for this mortar for pointing
work also.
SECTION 7.3: PLASTEING WITH CEMENT
MORTAR MIX M 7.5 GRADE 20MM THICK:
7.3.1 PREPARATION OF SURFACE:
The roughening surface of the back-ground improves the bond of plaster. All joints shall be thoroughly
rocked. After roughening the surface, care shall be taken to moisten the surface sufficiently before plastering
as otherwise freshly exposed surface may tend to absorb considerable amount of water form the plaster. The
surfaces shall be wetted evenly before applying the plaster. Care shall be taken to see that the surface is not
too dry as this may cause lack of adhesion or excessive suction of water from the plaster.
A fog spray may be used for this work. As far as possible the plaster work shall be done under shade.
7.3.2. LAYING OF PLASTERING WITH CEMENT MORTAR MIX M. 7.5 GRAGE 20 mm THICK:
The mortar used for plastering shall be stiff enough to cling land when laid. To ensure even thickness and
true surface, plaster shall be applied in patches of 150 mm X 150 mm of the required 20 mm thickness at not
more than 2 meters intervals horizontally and vertically over the entire surface to serve as guides. The
surface of these guides shall be truly in the place of the finished plaster surface and truly plumb. The mortar
shall then be applied to the surface to be plastered between the guides with a trowel. Each trowel full of
mortar shall overlap and sufficient pressure shall be used to force it in to through content with the surface.
On relatively smooth surface, the mortar shall be dashed on with the travel to ensure, adequate bond. The
mortar shall be applied to a thickness slightly more than that specified using a string stretched out between the
guides. This shall then be brought to a true surface by working with along wooden float with small sawing
motion. The surface shall be periodically checked with a string stretched across it. Finally the surface shall
be rendered smooth with a small wooden float over working shall be avoided. All corners arise and junctions
shall be brought truly to a line with any necessary rounding or chamfering.
Job is necessary to suspend the work at the end of the day it shall be left in a clean horizontal or vertical line
not nearer than 150 millimeters from any corner or arises or parapet tops or copings etc. When re-
commencing the work the edges of the old work shall scraped clean and treated with cement slurry before the
new plaster is laid adjacent to it. After the first coat is done it shall be kept undisturbed for the next 24 hours
and thereafter kept moist and not permitted to dry until the final rendering is applied.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
124
After the plaster has sufficiently hardened cement slurry with cream like consistency shall be applied thinly
and evenly and rubbed to a fine condition.
The finished surface shall be cured with water for a period of 10 days.
SECTION 7.4: POINTING TO C.R. MASONRY WITH CEMENT MORTAR MIX. MM 7.5 GRADE:
7.4.1. PREPARATION OF SURFACE:
The joints in the masonry shall be raised out to a depth not less than the width of the joint or as directed when
the mortar is green. Joints are to be brushed clean off dust and loose particles with a stiff brush. The area
shall then be washed and joints thoroughly wetted before pointing is commenced.
_____________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
125
DIVISION 8 – CANAL LINING
8.1 SCOPE OF WORKS
The item shall include furnishing all materials equipment and labour for providing and laying cement concrete
lining.
It also includes providing and placing (a) reinforcement whenever necessary (b) porous plugs (c) expansion /
contraction and construction joints.
It also includes providing and removal of all form work (whenever necessary) furnishing all materials,
equipment and labour for transportation, erection, keeping in place with necessary fixture and supports, oiling
etc. complete.
It also includes curing of bed and slopes of lining.
8.2 CLEARING SITE
The area proposed for lining as a whole shall be cleared of all objectionable material. Any waste material
obtained from such site clearance shall be disposed off in a manner directed by the Engineer-in-charge. The
cost of this operation shall be deemed to have been covered under the rates quoted for canal lining.
8.3 GENERAL
The provisions of this paragraph apply to the preparation of all sub grade/foundation upon which lining is to be
placed. The lining shall be in-situ cement concrete lining or precast concrete slabs, or random rubble masonry
on side slopes, as shown in the drawing or as directed by the Engineer-in-charge.
The items of schedule for preparing the subgrade for lining includes: dewatering of canal section; carrying out
all excavation below the underside of lining required for placing selected bedding material, wetting the surfaces;
furnishing or procuring soils from stock piles, placing, moistening and compacting the selected bedding
material to specified density by power rollers/approapriate compaction equipment/slope compactors, and
trimming the canal section. This item also includes excavation and preparation of foundation for item also
includes excavation and preparation of foundation for providing necessary under drainage facilities/filter
blanket and pressure relief arrangement wherever required including placing test sections to verify that the
procedures result in acceptable results.
If during construction, it is found necessary to alter the canal sections and side slopes without altering the
thickness of lining, the contractor shall be informed in writing of such change. The rates quoted being on one
square metre basis for the lining thickness, the contractor shall have to execute the work at the same Bid Rate as
quoted in bill of quantities without any claim for change in the section of the canal.
Where as the work of trimming the canal section upto underside of lining shall be carried out well in advance,
the trimming of proud section equivalent to the thickness of lining (for base preparation of lining) shall be
carried out immediately prior to laying of lining but in no case the time interval shall exceed 3 days in nominal
weather and 2 days in adverse conditions.
The preparation of subgrade in different soils for laying the cement concrete lining shall conform to clauses 4.1,
4.2, 4.3, 4.4, 4.5 of Indian standard IS: 3873 – 1978 (Indian code of Practice for laying in-situ cement concrete
lining on canal). It shall also hold good for laying masonry lining. It shall be ensured that the subgrade is made
thoroughly moist with fine water spray through nozzle to a depth of about 15 cm.
8.4 PREPARATION OF SUBGRADE CONSISTING OF EARTH
i. The Subgrade shall be prepared, dressed, and rolled true to level and according to the required cross section
of the canal to form a firm compacted bed for lining.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
126
ii. Sample profiles true to cross section of the canal shall be made at suitable intervals, as directed by the
Engineer, to ensure correct formation of subgrade. The contractor shall place selected bedding material in
test profile true to the cross section of canal, at times and places designated by the Engineer, to show the
adequacy of his construction procedures for laying bedding material. The test sections shall conform to
clause 4.3.2 of IS: 3873 – 1993. Modification shall be made, as necessary, until it is demonstrated that
acceptable results are being consistently obtained. The cost of this operation shall be deemed to have been
covered in his quoted rates.
iii. If at any point, material of subgrade has been excavated beyond the neat lines required to receive lining, the
excess excavation shall be refilled in horizontal layers with material compatible with subgrade material,
moistened if required and thoroughly compacted. Graded filter material, compatible with the subgrade
material, may be used and compacted to not less than 95% of the proctor’s density.
iv. When partial filling of existing canal sections is necessary to reduce the cross sectional area to that required
for lined canal, the fill shall be placed and suitably compacted by rolling/compactors/mechanical tempers to
form firm foundation for placing the lining to avoid its settlement. Slope compactors for placing the lining to
avoid its settlement. Slope compactors shall also be used as required for effective compaction of subgrade to
the specified density. (Refer photocopy).
v. The consolidation of bed in sandy reaches shall be done by saturating the bed with water before lining is
placed. The consolidation of side slopes in such reaches shall be done by over cutting the subgrade in slopes
by 15 cm and refilling it with earth and compacting by vibro-compactors/appriate mechanical compactors.
vi. The compaction of subgrade in other than predominantly sandy reaches shall be done at optimum moisture
content in layers not more than 15 cm – 20 cm thick to obtain a dry bulk density of 95% of the density at
optimum moisture content obtained in accordance with IS: 2720 (Part VII) – 1965. Consolidation shall be
done by power rollers / pneumatic or fuel-powered tampers/suitable compactors. In the sandy reaches,
compaction shall be governed by ‘relative density test’ Compaction by of manual labour shall not be
permitted.
vii. Where placing and compacting bedding material is on sloping foundation, the layers shall be placed parallel
to the surface of the foundation. If at any point the foundation material is disturbed or loosened, it shall be
moistened if necessary and thoroughly compacted to form firm foundation for placing the lining.
viii. All along the canal alignment, the rain cuts on the inner slopes of the banks shall be filled up with approved
soil and shall be compacted thoroughly to required lines, dimensions, and levels.
ix. If at any place, placement of bedding material below the proposed lining is required, due care shall be taken
by the contractor to place the bedding material on scientifically approved surface adequately moistened (to be
wet to a depth of 15 cm or to depth up to impermeable layer below, whichever is less) in layers not exceeding
15 cm in depth in a single operation and thoroughly compacted.
x. All loose materials likely to be present at the end panel of existing lining adjacent to which lining is to be
placed shall be removed and all voids beneath the existing lining shall be refilled and compacted thoroughly.
No extra payment shall be made on this account.
8.5 PREPARATION OF SUBGRADE CONSISTING OF ROCK
i. The sub grade shall be prepared and dressed true to level and according to the required cross-section of
the canal.
ii. Final cutting for 300 mm – 450 mm in hard rock shall be carried out by wedding, barring, controlled
blasting or trimming with pavement breakers etc. No extra payment will be made for this.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
127
iii. The bed and side slopes of the canal excavation profile over which the bedding material, under-
drainage and pressure relief arrangements (where ever so required) are to be placed and over laid with
lining shall be furnished accurately to true and even surfaces and to the dimensions shown on the
drawings.
iv. All excavation including over breakage below the lines of underside of lining shall be back-filled
completely up to the lines of the underside of lining with suitable bedding material as under, or as
directed by the Engineer:-
- The bedding material shall be lean concrete (1:5:10) in bed and sides for thickness of filling less than
15 cm; and RR masonry in cement mortar (1:5) if thickness is more than 15 cm.
OR
In Slopes: In slopes, the selected material shall be suitable semi pervious material / gravelly soil and layer of
pea gravel as binding material duly moistened and compacted buy appropriate compactors/tampers to form a
firm backing for the lining.
In Bed: In bed, the selected bedding material shall be rock spalls and chips to form a firm baking.
Selected bedding material to be used over fractured rock or rubble shall be such as would resist piping and
consequent washing of fines into the sub grade voids and thus losing support. The material shall be approved
by the Engineer for its impermeability and car of placement.
8.6 TOLERANCE IN EXCAVATION
Excavated, trimmed/dressed profile provides the final base for lining and tolerances shall be comparable to the
following:
Departure from establishment ± 20mm on straight reason and + 50 mm
Alignment on tangents, and partial curves.
Departure from established grade ± 20mm on small canals.
The above tolerances shall be negotiated gradually through smooth transition in a length of about 50m. No over
run in excavation, filling with the materials as directed by the Engineer, shall be paid to the contractor. The
selected bedding material in the case of bed and sides of canal profile in normal soils shall be compactable with
sub grade material and thoroughly compacted.
8.7 TOLERANCE IN SURFACE IRREGULARITIES IN PREPARATION OF FINAL SUBGRADE
Surface irregularities shall be tested by the use of a long template consisting of a straight edge or the
equivalent there-of for curved surfaces and shall not exceed the following limits:
(i) 6.25 mm for sub grade in bed.
(ii) 12.50 mm for sub grade in the side slopes.
Final sub grade exceeding these limits shall not be accepted.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
128
8.8 PREPARATION OF SUBGRADE CONSISTING OF EXPANSIVE SOILS (IS: 9451 – 1994)
Field and laboratory tests shall be carried out to determine the physical, textural, engineering, and chemical
properties of expansive soils and evaluate the swelling pressures of soils in various reaches to establish the
thickness of CNS (Cohesive non-swelling soils) layer required so that the resulting deformation is within the
permissible limit of 2 cm. The thickness of CNS layer to be provided normal to the sub grade shall be governed
by the India Standard, IS: 9451 – 1994, out lined below. CNS material shall be non-swelling with a maximum
swelling pressure of 10KN/m2
when tested in accordance with IS 2720 (Part-41) : 1977 at optimum moisture
content and minimum cohesion. Some of the soils which may be considered as cohesive non-swelling soils are
all adequately compacted clayey soils, silty clays, sandy soils are all adequately compacted clayey soils, silty
clays, sandy clays, gravelly sandy clays, etc. Exhibiting cohesive properties and containing predominantly non-
expanding type clay minerals with liquid limit not exceeding 50 percent.
Expansive soils are inorganic or plastic clays characterized by shrinkage, high compressibility, and swelling
properties. To counter act the swelling pressure and prevent deformation of lining, a CNS material of required
thickness is sandwiched between the soil and lining. The thickness of CNS material is normal (perpendicular)
to the sub grade. Guidelines for choosing the thickness of CNS materials (Cohesive Non-Swelling) required for
balancing the different swelling pressures is given in the following tables corresponding to various discharge
ranges given in the following tables corresponding to various discharge ranges in canals. Side slopes shall not
be steeper than 1.5:1, though slopes of 2:1 shall be preferable.
TABL -1
Thickness of CNS layer in channels of carrying capacity less than 3 cumecs
Thickness of CNS layer in cm
(minimum)
Discharge in cumecs
(m3 / sec)
Swell pressure 50-
150 KN/m2
Swell pressure
more than 150
KN/m2
1.4 – 2.0 (50 to 70 cusecs) 60 cm 75 cm
0.7 – 1.4 (25 to 50 cusecs) 50 cm 60 cm
0.3 – 0.7 (10 to 25 cusecs) 40 cm 50 cm
0.03 0 0.3 (1 to 10 cusecs) 30 cm 40 cm
TABLE – 2
Thickness of CNS layer in channels of carrying capacity of 2 cumecs and more
Swelling pressure of soil
KN/m2
Thickness of CNS material
(minimum)
50 to 150 75 cm
150 to 300 85 cm
300 to 500 100 cm
Note:- CNS soil is to be laid in layers and compacted, to specified density.
Specification of CNS Soils
(i) General Gradation of CNS soil
Clay (less than 0.002 mm) 15 to 20 %
Silt (0.06 mm – 0.002 mm) 30 to 40 %
Sand (2mm – 0.06 mm) 0 to 40 %
Gravel (greater than 2 mm0 0 to 10 %
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
129
(ii) The CNS material shall be non-swelling, with a maximum swelling pressure of 10 KN/m2 when
tested in accordance with IS: 2720 (part-41) 1977 at optimum moisture content and minimum cohesion.
(iii) Index properties
Liquid limit Greater than 30, but less than 50%
Plasticity index reater than 15, but less than 30%
If given CNS material is not available, designed soils mix to produce artificial CNS may be used. The
artificial CNS shall satisfy the condition of swelling pressure mentioned in the sub para (ii) above. In respect
of the provision of CNS layer in the bed, it shall be as worked out from consideration of selling pressure.
However, the thickness of CNS layer to be provided on slopes shall, in addition, be governed by the
construction consideration viz. from the Power Roller rollable width consideration for achieving effective
compaction. CNS layers shall be compacted to the specified proctor density.
DURING CONSTRUCTION, IT SHALL BE ENSURED THAT
i. Serrations / steps / benches shall be provided in the side slopes of canal in cutting to provide a good bond
between the CNS layers and expansive soil and to also prevent contact slides between CNS materials
and expansive soil.
ii. Proper moisture shall be added to CNS material and expansive soil.
iii. CNS material shall be laid in layers (± 20 cm thickness0 and compacted to at least 95%/98% Proctor
Density as specified in the Bid documents, preferably, by Power Rollers viz. mechanized compaction.
iv. To avoid slipping and rain cuts during the rainy season, it shall be advisable to provide CNS right up to
the ground level.
v. The sub grade on which CNS layer is to be laid shall, generally, be not kept exposed for more than 4 days
prior to the placement of CNS layer.
vi. Effective and mechanized compaction of sub grade for side lining on slopes and bed is very important in
cutting or embankments. In addition to the designed thickness of CNS, 15cm or more (perpendicular to
side slope 0 of extra thickness (called pride) shall be provided and compacted. This pride shall be
removed only just prior to the placement of lining (a time interval of, say, about one day), thus making a
fresh and well-compacted surface available for bedding. In small section channels, it shall be
appropriate to over excavate the section and fill the entire section with CNS, material ( Laid in
successive layers and compacted to 95%/98% proctor density as specified in the Bid document), and
thereafter, scoop this section to the designed section for placement of lining. This PAD method ensures
effective compaction by 8-10 T power rollers or equivalent power vibratory rollers. The CNS material
so scooped out is utilized in the next reach through re-handling. However this is included in the item
rate of providing CNS & will not be paid separately.
vii. Under drainage arrangement, as per drawing, shall be provided.
8.9 FINAL PREPARATION OF SUBGRADE FOR PLACEMENT OF CONCRETE LINING
The work of trimming canal section up to the under side of concrete lining and preparing sub grade for
concrete placement include removal of pride section. Pride equivalent to the lining thickness on sides and bed
on the under side of lining shall be lift unexcavated and the removal of this pride shall be done prior to laying
of lining but in no case shall the time interval exceed 3 days in normal weather and two days in adverse
weather conditions. Sub grade surface shall be trimmed accurately to the underside dimensions of the lining:
embankment and selected back fill placed in over excavated sections shall be moistened and compacted to
95%/ 98% as specified in the Bid Documents proctor density, so as to ensure a firm and unyielding sub grade.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
130
It shall be ensured that the final sub grade is made thoroughly moist with fine spray nozzles (or with
gardener’s cans) to depth of about 15cm, before placement of concrete to prevent it from absorbing water
from the freshly laid concrete. Water, direct from hoses, shall not be used for wetting of the sub grade to
prevent erosion and slushy conditions on the sub grade.
The rate for providing and laying embankment shall include the cost of final preparation of sub-grade for
placement of concrete lining & no separate payment on this account shall be admissible.
8.10 MODEL SECTIONS/TEMPLATES/CONCRETE SLEEPERS
Model sections or templates of size 15cm x7.5cm or any other size specified and shown in the drawing shall
be constructed up to the bottom of lining at specified interval in straight reaches and curves, so as to achieve a
smooth straight/curved sub grade surface free from unsightly kinks and depressions. The model sections in
the bed and sides shall be constructed in M15 cement concrete conforming to IS:383 standard specification.
The top level of template will be the bottom level of lining.
Since the model sections are to be used as reference for excavation and trimming of sub-grade for seating to
the lining initially and for laying and finishing to required profile and grade to a very close tolerance of 3mm
in a length of 3m, any undulations in the model sections beyond the permissible tolerance shall have to
removed and redone by the contractor. No separate Payment shall be made for this view and shall be deemed
to be included in the rate of lining.
8.11 INGREDIENTS
Ingredients i.e. cement, sand, course aggregates and water should satisfy IS specifications.
8.12 LAYING OF CEMENT CONCRETE LINING: BROAD SELECTION OF LAYING METHODS
The concrete shall be generally governed by IS: 456-2000. The concrete shall also be governed by all the
provisions of section Concrete lining of M15 grade shall be laid in the canal prism, as shown in the drawing,
using well graded aggregates and the requisite cement level with a water cement ratio of about 0.60 or as
directed by the engineer. The requisite maximum nominal size of coarse aggregate shall be 20mm for the
lining thickness of 75mm. and 40mm for the lining thickness of 100mm. ordinary Portland cement
conforming to IS: 269 or 43 grade cement conforming to IS:8112 or 53 grade cement (IS 12269) shall be
used.
It shall be result-oriented from consideration of speed and quality construction of optimize mechanized
placement of CC lining to the optimum extent feasible.
Accordingly, mechanized cement concrete lining of bed and side slopes of the canal section through
deployment of concrete paver shall be done where bed width is more than 3.0m and the slant length is more
than 3.5m.
Mechanized lining of side slopes shall, preferably, be done with Acrow type or equivalent type of light steel
gantry fitted with side shutters and vibrators (slip-form gantry) where the bed width is less than 2m and the
slant length less than 2.7m. bed lining shall be laid by conventional manual method. Conv3entional
(Manual) placement of lining on both the bed and sides shall be done where paver mechanized/slip – form
steel gantry mechanized placement of lining is not considered feasible. Baby paver shall be used for side
lining where the slant length is up to 3.5m. If the concrete lining is to be placed with concrete paver both on
bed and sides PVC strips may be used for both the transverse and longitudinal contraction joints in lieu of
cutting of grooves and filling with sealing compound.
8.13 SLUMP
A slump range of about 50mm-65mm shall be considered adequate at the placement site from considerations
of proper discharge of concrete from the transit mixer/agitator, mechanical mixer, ease of placement and
attaining a well consolidated lining with a good finish.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
131
8.14 AIR ENTRIANING AGENT
AEA, as an admixture, shall be added to the concrete batch in solution in such a manner as will ensure
uniform distribution of admixture throughout the batch during the specified mixing period of about 2.5
minutes. The amount of AEA shall be such as to effect of about 5% air in the mix in order to have good
workability and, thus, secure a good finish of concrete lining.
8.15 CONCRETE PRODUCTION AND TRANSPORTATION
Concrete shall be produced in a stationary weigh batching plant/ plants of adequate capacity installed at
suitable places by the contractor and concrete conveyed to the placement of site/sites in mobile transit mixers
for placement of concrete lining with fully mechanized concrete paver/pavers. No manual concrete making
shall be allowed.
Alternatively, mobile self loading: Weigh batching, mixing and transporting mixer with the mixer drum
capacity of 2.8m3 capacity (or other suitable capacity) shall be deployed by the contractor for production of
controlled concrete as well as transportation of this concrete to the placement site/sites concrete transported
by the transit mixer or mobile/mixing and transporting equipment shall be delivered to the hopper of the site
discharge conveyor of the concrete paver. The paver shall screed of the concrete and duly compact it
(cylinder finishing). Contraction joints shall be cut with groove cutters attached to the paver. Each lining
machine and the associate support equipment shall be capable of placing canal lining at an average
advancement rate of not less than about 8m/hr. so that cutting of contraction joints is achieved smoothly and
efficiently when the concrete is still in a good plastic state. Contraction joints shall be as shown in the
drawing or as directed by the Engineer. However, an expansion joint as per design or as directed by the
Engineer-in-Charge shall be provided between lining and canal structure.
i. Broadly, mechanized cement concrete lining of bed and side slopes of the canal section through
deployment of concrete Paver of adequate capacity shall be done where bed width is 3m and slant length
is more than 3.5m and a continuous lining reach for CC lining is available. Concrete shall be transported
by transit mixer from the batching and mixing plant.
ii. For canals having bed width between 2 to 3mt. Bed lining is to be done manually however baby
Paver may be used for side lining where the slant length is between 2.7m to 3.5m.
iii. In such situations, where the bed width is more than 2.0m and the slant length is less than ±2.7m, or
other situations in such reaches, where in the opinion of Engineer-in-charge, mechanized concrete lining
is not possible, like where PCC lining (100mm thick) is provided in selective patches U/s and d/s of
structure lining may be done with conventional manual method.
iv. Where the bed width is less than 2.0m and the slant length is less than 2.7m, concrete lining on side
slopes shall preferably be done by deployment of a crow or equivalent of type slip form screed steel
gantry fitted with surface vibrators on the shutter plates. Bed lining shall, however, be place manually.
v. In situations associated with lining proposed to be done with A crow or equivalent type slip form
screed gantry in small reaches/staggered reaches, and/or where transit concrete mixers are not considered
feasible of deployment, standard concrete mixers (10/7 cft. Or 14/10 cft) shall be allowed by the
Engineer-in- Charge instead of composite batching and mixing plant. Since the concrete lining operation
if practically continuous with the deployment of slip form steel gantry, the shape of contraction joints in
lining shall be the same as the ones on the lining placed by the concrete pavers.
vi. Concrete shall be placed only in the presence of a duly authorized representative of the Engineer.
vii. Concrete shall be mixed in a mechanical mixer. Hand mixing of concrete shall not be permitted.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
132
viii. When concrete placing operations are stayed for the day or are interrupted because of break down or
are delayed by other causes or where the contractor elects to construct a joint, the edge of the fresh
concrete lining shall be bulk headed to a surface normal to the lining along transverse and longitudinal
lines. Before placing operations are resumed, the surface of hardened concrete shall be prepared as a
construction joint.
Whenever a substantial break-down occurs in the concrete production or concrete transportation system, a
joint should be formed as close to the face of the fresh concrete as possible. All concrete on the new side of
the joint shall be removed. The fresh concrete shall than be placed against the existing concrete with the full
groove for required contraction joint formed in between them. This is essential to eliminate cold joints.
8.16 UNDER DRAINAGE
Whenever specified and shown in drawing, porous concrete plugs of sizes indicated in drawings shall be
provided in bed and side slopes underlain by graded filter of other indicated in the drawings. Porous concrete
shall be composed of one part of cement and 4 parts of coarse aggregate by weight with the size of coarse
aggregate, not more than 20mm. no sand is to be used. Only so much water shall be used in concrete as is
required to produce a paste which will coat the particles without filling the voids. In placing porous concrete
in moulds, care shall be taken to ensure that it is not over tampered or compacted so as to reduce its porosity.
The porous concrete after curing shall be pervious and free draining type. As soon as the concrete hardens
(viz. it attains final setting), it should be kept fully moist with water for at least 14 days. The compressive
strength of porous concrete at 7 days age, as determined by tests on 15cm diameter, 30cm high cylinder
should not be less than 70 kg/cm2. The porosity at 7 days age be such that water shall pass through slab of
porous concrete 30cm thick at a minimum rate of 500 litres/min/m2 with a constant 10cm depth of water on
the slab.
8.17 TOLERANCE IN LINING THICKNESS
The permissible tolerances for the canal lining shall be as under
Variation in thickness of lining ±10% provided average thickness is not less than designed thickness.
8.18 TEMPERATURE OF CONCRETE
Temperature of concrete as placed, critical to cracking control and durability, shall preferably not exceed
about 32.2°C (90°F). Accordingly, placement of concrete in hot weather shall be done during the morning
and evening hours, extending to night hours as required. For work in extreme weather conditions, the
procedure set out in Is 7861 (Part–1) or IS 7861 (Part–2) be broadly followed.
8.19 CURING OF CONCRTE LINING
The concrete lining of the canal bed shall be cured in conventional manner with water by making small earth
bunds of say 20cm to 30cm height with ponding water. The side lining shall be cured with membrane-
forming curing compound only.
8.20 SPECIFICATIONS OF MEMBRANE – FORMING CURING COMPOUND
The white pigmented curing compound, conforming to ASTM designation of C-309-81 (or the Indian
manufacture conforming to International Standard of C-309-81) shall be used to form water retaining membrane
on the surface of concrete. The curing compound shall be used only after it is approved by the engineer. The
curing compound shall be applied immediately after bleeding water shine disappears leaving a dual appearance
on concrete surface. The liquid compound shall be kept continuously stirred mechanically in drum and sprayed
uniformly over the concrete surface. One litre of curing compound shall normally cover about 4.00m2 of
concrete surface.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
133
Accurate coverage should be based on laboratory and field trials. Laboratory tests shall be carried out to check
that with the specified coverage, the loss of water does not exceed 0.55 kg/ m2
over a period of 72 hours. Other
tests related to reflectance and drying time. Day light reflectance of white pigmented curing compound shall not
be less than 60% of that of magnesium oxide. The drying time requirement specifies that the curing compound
could be dry to touch in not more than 4 hours. When the curing of concrete lining is not found satisfactory the
Engineer-in-Charge may direct the contractor in a writing to resort to second layer of membrane curing.
8.21 CORE TESTS
As the concrete lining work progresses and has attained a minimum curing and setting of 28 days period, cores
shall be taken random to evaluate the concrete lining laid in respective reaches. Frequency of coring shall be
determined by the engineer. Broadly, it could be one core from bed lining and one core each from side lining
per 250mts length of lining or as directed by the Engineer, in no case fewer than three cores shall be tested. The
cores shall be examined for segregation, honey-combing and thickness of lining. The contractor shall allow all
facilities in cooperation towards collection of core. The testing of cores shall be carried out either in the project
laboratory or at any other laboratory that the engineer may so decide and the results obtained shall be
considered correct and authentic by the contractor. The contractor shall be given access to all operations and
tests that may be carried out as aforesaid so that he may satisfy himself regarding the methods and procedures
adopted. Final payments shall be made only after the satisfactory core tests results acceptable to the Engineer as
per section 17.4.3 of IS: 456-2000. the rates quoted by the contactor shall be inclusive of all the testing. No
separate payment shall be made on this account.
A standard test cylinder has a diameter one-half its height (viz. L/D ratio is 2). However the cores taken from
the in situ concrete lining may not have these relative dimensions and consequently, L/D ratio will not be 2.
Accordingly, a correction factor according to the height/diameter ratio of specimen after capping shall be
obtained from the curve shown on page 13 of IS: 516-1959. the product of this correction factor and the
measured compressive strength shall be known as the corrected compressive strength, this being the equivalent
strength of a cylinder having a height- diameter ratio of 2. The equivalent cube strength of the concrete shall be
determined by multiplying the corrected cylinder strength by 5/4. The cores shall be prepared and tested as per
IS: 576-1959.
Concrete in the member represented by a core test shall be considered acceptable if the average equivalent
strength of the cores is equal to at least 85% of the cube strength of the grade of the concrete specified and that
no individual core has strength less than 75%.
Regarding particular canal reaches/reach, though the lining be fully complete to acceptable quality levels, such
reach/reaches will not qualify for acceptance and final payment till the associated works necessary for safety of
lining during rains, such as dowel banks, drainage etc., as per drawings are complete along with.
8.22 JOINTS
Contraction joints shall be provided, spaced and treated as shown in the drawings. Expansion joints shall be
provided only where structure intersects the canal lining. No expansion joints are to be provided in CC lining at
any other place.
The first longitudinal joint, (wherever longitudinal, contraction joints are to be provided) shall be at about 18
times thickness of lining below the top edge (viz. about 1.8m for 10cm thick lining). The shape, spacing and
dimensioning of contraction joints shall be as shown in the drawing. Broadly, the joints shall extend to at least
1/3 of lining thickness (viz. 3.3cm fro 10cm thick lining) with a top width 12 mm maximum and tapering to
9mm to join a 45o groove at bottom. The contactor must ensure that the grooves are of specified dimensions,
acceptable to the Engineer-in-Charge. Longitudinal contraction joints are to be provided only where the wetted
perimeter excess 6m.
The longitudinal as well as the transverse contraction joints should be spaced at not more than 36 times
thickness of lining.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
134
Filling of joints:
Filling of joints shall be taken up only after a minimum of 28 days setting period of CC lining. The grooves
shall be cleaned thoroughly to their full depth and width by brush, air jet, water jet etc. all loose particles and
foreign matter shall be removed and the grooves shall be thoroughly cleaned and dried to the satisfaction of
Engineer-in-Charge or his representative so as to ensure good adhesion to the sealant. The primer shall then be
applied by means of brush or any other suitable applicator to cover the sides completely before the application
of prepared sealing component.
8.24 COMPOSITION OF SEALING
Unless otherwise specified, the sealant shall be prepared from the following materials:
1. Bitumen 85/25 = 55%
2. Sand (fineness modules 1.00 to 1.50) = 43%
3. Asbestos powder (of white colour) = 2%
PROCEDURE
The sealant shall be prepared by heating the bitumen to 375oF and sand also to the same temperature separately.
The sand shall be mixed either 2/3rd
quantity of bitumen first and then asbestos powder shall be added to it. The
remaining 1/3rd
quantity of bitumen shall then be added to this mix and stirred thoroughly. The grooves shall be
covered with wooden strip along and held on slopes with the help of clay puddle put along the sides. The
wooded strips shall be coated with grease on inner side so that it may not stick to the filler compound. The
wooden strip shall be gently removed after about 30 minutes and the next joint shall than be filled in similar
manner. The joint shall be finished with a hot trowel and any hole shall be refilled with sealant. Filling of joints
shall commence from bottom of slopes.
8.25 ACCEPTANCE CRITERIA OF LINING
(i) In case the concrete does not conform to the acceptance criteria for specified strength, (such as
characteristic 28 day 150mm cube compressive strength of 15.0 N/mm2) of concrete mentioned in para
18 (iv) of section 4C Plain and Reinforced concrete, the engineer reserves the right to reject the work or
accept the same at a reduced rate derived from tendered rate and as approved by him after examining all
aspects and provided the structural integrity is not affected.
(ii) Acceptance criteria of cores shall be as per section 17.4.3 of IS: 456-2000 outlined in para 8.21 of this
section.
(iii) Also the “Acceptance Criteria” outlined in the para (v) of section 4C Plain and Reinforced concrete shall
be applicable for acceptance of lining chapter on concrete.
8.26 MEASUREMENT AND PAYMENT
All linear measurements shall be in meters, correct to 0.01m. areas shall be computed in square meters. The
perimeter shall be the top finished surface of the lining. Payment for lining shall be made for the thickness
shown on the drawings and on per square meter basis of the superficial area including horizontal coping on both
sides at the lining top. The thickness of lining shall be cross checked by (i) volume of concrete placed and area
covered, (ii) use of probe when concrete is green and plastic and (iii) random coring. Any over run in quantity
of concrete in lining shall not be paid. Running payment will be accepted rate will only be made after receipt of
acceptable test results as per para 16.0 above.
The porous blocks provided for under drainage will be paid on per No. basis, separately. Similarly payment of
contraction joints, construction joints and expansion joints shall be on running meter basis and shall be paid
separately.
__________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
135
DIVISION – 9 SHOT CRETING
SPECIFICATION AND PROCEDURES OF APPLICATION
Materials for Shot Creting
Cement, sand, coarse aggregate, water and admixtures are used in the Shot crete mix. Ordinary Portland cement, 43
grade will be used.
1. Sand: well graded as per either of the following grading can be used
Percentage by mass passing for Sieve Designation
Grading I Grading II
10 mm 100 100
4.75 mm 90-100 90-100
2.36 mm 75-100 85-100
1.18 mm 55-90 75-100
600 micron 35-59 60-79
300 micron 8-30 12-40
150 micron 0-10 0-10
Sand should be free from deleterious substances and organic impurities.
2. Coarse Aggregate: The maximum size of coarse aggregate should be restricted to 10mm. it should be free
from impurities, clay/ shale particles and conform to the requirements of impact, abrasion and crushing
criteria ( viz less than 45%) and the soundness acceptance criteria (less than 12% with sodium sulphate
method). It should have a specific gravity of not less than 2.6. The aggregate should be well graded and
should broadly conform to the following grading.
Sieve Designation Percentage by mass passing for
aggregate of 10 mm Max. size
12.5 mm 100
10 mm 85-100
4.75 mm 30-Oct
2.36 mm 0-10
1.18 mm 0-5
3. Water: Ordinary portable water with pH value not less 6 and not more than 8.5 will be used.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
136
4. Chemical Additives: the following additives be used in the concrete mix in the ‘Dry Mix process’ of shot
creting.
• Sodium carbonate - ½ Kg per 50 kg bag of cement
• Sodium Aluminate - ½ Kg per 50 kg bag of cement
• Calcium Carbonate - 1 kg per 50 kg bag of cement
Total - 2 kg per 50 kg bag of cement
Viz 4% by weight of cement
Alternatively, following Additives can be used:
• Super plasticizer @ 1 % by weight of cement viz 4.5kg of super plasticizer.
• Accelerator (say sodium silicate) @ 5 % by weight of cement viz 22.5 kg
Any other approved admixture can also be used.
Air Supply: properly operating air compressor is essential for a satisfactory shot creting operation. The compressor
should be fitted with a moisture extractor to deliver clean and dry air. For hose length of 30m, air pressure at the
nozzle should be 0.3 N/m2 or more.
Water Supply: the water pressure at the discharge nozzle should be sufficiently greater than the operating air pressure
to ensure that the water is intimately mixed with the other material.
Properly applied shot crete is structurally adequate and durable material capable of excellent bond with concrete as
well as masonry.
Shot Concrete Mix: The water – cement ratio should be maintained within the range of 0.40 to 0.50 by mass. The mix
should have a 28 day characteristic compressive strength of not less than 200 kg/cm2 would be preferable. Normally,
the following mix proportions would be adequate.
Cement = 450 kg/m3
Sand aggregate = 1100 kg/m (0.70 m3)
Coarse aggregate = 500 kg/m (0.30 m3)
(5 mm – 10 mm size)
Proportioning of mix = 1:2.44:1.11 (or the proportioning
n be after 2 or 3 trail mixes)
Application of Shot Crete: Following guidelines and sequence may be followed:
i. All unsound and deteriorated concrete be removed and chipping done, wherever necessary, or sand blasting
done.
ii. Exposed reinforcement bars be cleaned free of rust / scales. Additional reinforcement is provided if any as
warranted.
iii. Ensure sufficient clearance around the reinforcement to permit complete encasement with sound short crete.
A clearance of at least 50 mm should be provided.
iv. Air-water jet be applied for final clean-up of the surface. Spray pneumatically the first layer of shotcrete of
about 38 mm thickness (bellow pockets} will consume more shotcrete).
v. Next “Welded wire mesh of size 100 mm X 100 mm 5 mm be nailed, butting with shotcrete. Binding wire of
20 gauge or 24 gauge be used for binding of wire mesh panels.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
137
vi. The second and final layer of shot Crete of thickness = 38 mm be then pneumatically sprayed over the first
layer. The finished shotcrete surface should be kept continuously wet (viz cured for at least 7 days.
Alternately, membrane – forming chemical curing component be used for curing. A re-bound of 25% to 30%
would occur and the rebound material is NOT to be re-used in the shot crete mix.
Quality Control: The shotcrete operation should be continuously inspected by the engineers who should check the
materials, concrete mix, shotcreting equipment, application of shotcrete and curing. The finished surface should be
sounded with a hammer for detection of any hollow pockets due to lack of bond. Such, hollow pockets or other defects
are required to be carefully cut out and replaced with the shotcrete layer. The first layer is also to be sounded with a
hammer and remedial action taken for any hollow pockets before commencing the application of the final layer.
_____________________________
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
138
DIVISION – 10 GROUTING
SPECIFICATION AND PROCEDURES OF APPLICATION
Materials for grouting:
Cement, fine sand and water are used in the grouting mix. Ordinary Portland cement 43 grade is used or as directed by
the Engineer-in-Charge.
Drilling holes for grouting to existing masonry, abutments, wing walls and returns of under tunnels, aqueducts and
piers shall be of 20mm diameter to a depth of 500mm at 1.5m center to center both ways and inserting PVC pipes of
12mm diameter of 500mm length into the drilled holes.
Grouting mixture ratio of 5:1 by volume and progressively improving to 4:1 and 3:1 and when necessary changing
over to the mortar mix 3:1 with fine modulus of sand 2, injecting into PVC pipes of 12mm diameter with a maximum
pressure of 2.0 kg/cm2 in ascending order is to be followed. The choice of grout mixtures be as directed by the
Engineer-in-Charge.
Grouting shall be continued with the specified pressure the hole refuses to take grouting material and as directed by the
Engineer-in-charge. The grouting is to be done in the presence of Engineer-in-charge or his representative. Whenever
pressure grouting is done, the contractor should inform the Engineer-in-charge.
Utmost care and precautions is to be taken to ensure that the masonry structure or any element of structure is not
damaged during grouting. Any damage caused to the masonry or any element in the structure or adjacent to it is to be
rectified by the contractor at his own expenses and to the satisfaction of the Engineer-in-charge.
Measurement:
The drilled holes shall be measure in numbers as specified in the grout data and paid as directed by the Engineer-in-
charge.
Measurement and payment for pressure grouting shall be made on the basis of cement actually injected into the grout
holes. All wastages due to any operations do not be paid.
Payment for grouting shall be made at the unit price per kg of cement tendered in the Bill of Quantities and shall
include all material, machine and labour required for the grouting operation.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
139
DIVISION – 11 STONE PITCHED LINING
SPECIFICATION AND PROCEDURES OF APPLICATION
Scope: The item shall consist of furnishing of tools, equipment, materials and labour required for Quarrying, transporting and
reasonably smooth surface and uniform thickness and also dressing of embankment to designed slopes and stone pitch
lining shall be carried out.
Preparation of sub grade: The sub grade is to be laid with gravel backing of 150mm thick, moistened and adequately consolidated prior to the
placement of stone pitching.
Laying: Sub grade of the canal slopes should be divided into compartments by concrete ribs. The compartments should have
dimensions not more than 15m along length of the canal. The spacing of ribs cross in the section of the canal should be
so chosen as to divide the canal slopes symmetrically about center line and in such a manner that ribs are provided at
the junctions of the slope & bed and at the upper extremity of the slope. The ribs along the slope of the bank should be
continuous. The concrete ribs should be made of grade M15 concrete in accordance with IS 456. The ribs should be
rectangular in cross section with width equal to the dimension of stone along its longer axis and depth equal to the
thickness of lining plus thickness of gravel backing. Stones should be carefully hand packed in the compartments. The
placing method should be such as to ensure a reasonably smooth surface and uniform thickness. Gaps between stones
should be minimized. Such spaces should be wedged with spells of suitable size to avoid packing material being
washed out. Such filling should immediately follow the placing of stones and as directed by the Engineer-in-Charge.
Dimensions of Stones and Thickness of Lining.
S. No Canal Capacity Thickness of Lining Average Dimension Along
the Largest Axis
m3/s mm mm
i) 0 to less than 10 150 150
ii) 10 to less than 100 225 225
iii) 100 and above 300 300
Measurement and Payment:
The measurement shall be separately taken for ribs, stone pitch lining, gravel backing and excavated soils and are
being paid in cum.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
140
DIVISION – 12 GATES / HOISTING EQUIPMENT
SPECIFICATION AND PROCEDURES OF APPLICATION
Supplemental Specification for Gates / Hoisting Equipment.
I. Recommended Materials:
Component parts. Material. I.S. Specification.
Skin plate horizontal girders and vertical
stiffeners as bottomed and
top struts breading channel.
M.S. Structural steel. 2062 – 1969.
Gate rollers and guide rollers. Cast Iron. 210 – Grade 20
Rubber seals. Rubber. U.T.S.148 Kgs / C.M Elongation 450
Duremeter hair charges shore ‘A’ type
60 – 70.
Bushings. Bronze. 305 – 1981.
The materials referred in the design and drawings materials of the standards specified by the department should be used
on the work. In addition to the above, all other materials used for the work shall confirm to relevant I.S. Specification and
fabrication and erection work also shall be carried out confirming to relevant I.S. Specification.
Rubber for seals:
Rubber for seals is synthetic containing not less than 1% (one percent) by weight of copper inhibitors.
II. Workman ship, Defective work and Materials:
All the work shall be performed and completed in a through workman ship like to the best modern practice in the
manufacture and fabrication of material for the types covered by these specifications. The work shall in all cases be of high grade
and carefully performed to the satisfaction of the authorised representative of the department. The contractor shall warrant all
materials and workman ship furnished by him to be free from injuries defects. He shall replace free of cost to the department any
defective material or workman ship discover during erection and shall bear all costs of the correction in the field of any error for
which he is responsible workman ship shall confirm to the latest standards laid down in Indian Standard Specification & I.R
Specifications.
Necessary certificates for having conducted the ultrasonic testing for the gate shall be furnished by the contractor duly
obtained the authorised testing laboratories.
III. Terms of Payment:
1) 75% of the agreement rate will be paid against supply of the gates hoisting equipment, at site of work duly manufactured as per
the specification indicated in the drawing. Out of this 75% value released for payment, an amount equal to 71/2% will be
retained as further security deposit. The balance 25% will be released errection, testing and commissioning of gates / hoisting
equipment.
The EMD performance security deposit, 71/2% of further security deposit retained from the bills together will be released
after maintenance period.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
141
Compaction of Sub grade on Canal Side Slope
With
Fuel – Operated Portable Compactor
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
142
Compaction of Sub grade on Canal Side Slope
With
Portable Compactor
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
143
Fuel – Operated Compactor for Sub grade Compaction
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
145
Fuel Operated Vibratory Compactor
For
Compaction of Sub grade on Side Slope
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
147
INVENTARY
NAME OF WORK : NSP NSLBC_ APWSIP_ Rehabilitation and modernisation from
KM 0.000 to 52.300 of 21st MAIN BRANCH CANAL
List of Structures proposed for repairs
S.No Type of Structure
Location at KM
Remedial measures
1 Aquiduct for Rly. crossing
0.967 Cut open and cladding concrete to the abutments U/S & D/S protective lining, Repointing and Grouting to the Masonry head walls, wing walls and abutments
2 Box type U.T 1.073 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing and Grouting to the Masonry head walls, wing walls and abutments
3 O.T of Khammam Major-I
2.095 Cut open and placing cladding concrete,Protective C.C.lining U/S &D/S of O.T
4 Type II U.T 2.548 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
5 D.L.Bridge 4.270 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
6 B.T U.T 5.130 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
7 OT Khammam Major II
5.600 Protective C.C.lining U/S &D/S of O.T
8 DL Bridge 5.688 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
9 S.L.Bridge 7.784 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
10 S. Passage 8.315 Skin concrete to the piers, Repointing and Grouting to the masonry piers, and shot creating to the exposed reinforcement of the desk slab.
11 OT of Chintakani Major
8.376 Protective C.C.lining U/S &D/S of O.T
12 S.L.Bridge 11.626 Protective lining, Grouting to the piers, Repairs to hand rails
13 Super Passage 13.076 Skin concrete to the piers, Grouting to the masonry piers, and shot creating to the exposed reinforcement of the desk slab.
14 OT of Bonakal Br. Canal
14.030 Bed and side slope lining, Repointing and grouting to the piers and abutments
15 Cross Regulator, Bonakal Branch Canal
14.030 Providing Repointing, Grouting to the piers, protective bed lining
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
148
1 2 3 4
16 U.T 14.636 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
17 S.L.Bridge 15.624 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments
18 OT of Konijerla Major
15.500 Providing protective lining U/S and D/S of O.T
19 OT of Ganeshwaram Major
16.280 Providing protective lining U/S and D/S of O.T
20 U.T 17.520 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
21 U.T ( Under Tunnel)
18.100 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
22 O.T of Thummalapalli Major - I
18.340 E W E for foundations, Laying CC for foundation and head walls and providing CC lining U/S & D/S and laying RCC pipes
23 S.L.Bridge 18.980 EWE for foundations, laying cement concrete for abutments and piers and VRCC for deck slabs, Hand railing.
24 U.T. 19.560 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
25 O.T Sluice at Tummalapali Major -2
20.093 E W E for foundations, Laying CC for foundation and head walls and providing CC lining U/S & D/S and laying RCC pipes
26 U.T 21.100 E W E for removal of deposited earth from Barrels, Approach and tail channels
27 O.T of Seetharama Banjar Major
21.935 E W E for foundations, Laying CC for foundation and head walls and providing CC lining U/S & D/S and laying RCC pipes
28 S.L.Bridge 21.995 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
29 U.Tunnel 22.800 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
30 O.T of Mekala Kunta Major
24.460 Providing protective lining U/S and D/S of O.T
31 U.T 24.720 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
149
1 2 3 4
32 S.L.Bridge 25.560 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
33 O.T of Singarayapalem, Major
25.696 Providing protective lining U/S and D/S of O.T
34 O.T of Lollarigudem Major
26.381 Providing protective lining U/S and D/S of O.T
35 U.T 26.657 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
36 O.T. Sluice of Gubba Kurthi Major-I
27.400 Providing protective lining U/S and D/S of O.T
37 O.T. Sluice of Gubba Kurthi Major-II
28.135 Providing protective lining U/S and D/S of O.T
38 Under Tunnel 28.835 E W E for removal of deposited earth from Barrels, Approach and tail channels
39 O.T of Gaddalagudem Major
29.008 Providing protective lining U/S and D/S of O.T
40 S.L.Bridge 29.192 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
41 O.T of Gaddalagudem Major - II
29.790 Providing protective lining U/S and D/S of O.T
42 U.T 30.313 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
43 O.T Gaddalagudem Major III
30.868 Providing protective lining U/S and D/S of O.T
44 U.T 31.319 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
45 U.T 31.960 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
46 S.L.Bridge (new) 32.353 Dismantling of VRCC slabs,piers and abutments.EWE for foundations, laying cement concrete for abutments and piers and VRCC for deck slabs, Hand railing.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
150
1 2 3 4
47 U.T 32.936 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
48 U.T 34.474 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
49 S.L.Bridge 35.490 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
50 U.T 36.182 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab,protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
51 Aqueduct (Nimmavagu)
36.820 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
52 U.T 37.327 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
53 O.T of Thimmaraopet Major I
38.248 Providing protective lining U/S and D/S of O.T
54 Escape regulator 38.629 Providing protective lining U/S and D/S of O.T, Repointing to the abutments and grouting
55 O.T of Thimmaraopet Major II
39.126 Providing protective lining U/S and D/S of O.T
56 Cross Regulator 2 nos (12.5'x25') shutters Manual operation
39.140 Providing protective lining U/S and D/S of Regulator
57 U.T 39.428 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
58 S.L.Bridge 39.810 Dismantling of VRCC slabs,piers and abutments.EWE for foundations, laying cement concrete for abutments and piers and VRCC for deck slabs, Hand railing.
59 O.T of Thimmaraopet Major-III
40.070 Providing protective lining U/S and D/S of O.T
60 Aqueduct 40.574 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
151
1 2 3 4
61 OT Peddakrishnaiah Banjara nagar
41.178 Providing protective lining U/S and D/S of O.T
62 S.L.Bridge 41.205 Dismantling of VRCC slabs,piers and abutments.EWE for foundations, laying cement concrete for abutments and piers and VRCC for deck slabs, Hand railing.
63 O.T of Arikayalapadu Major
42.637 Providing protective lining U/S and D/S of O.T
64 U.T 43.106 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
65 O.T of Latchegudem Major
43.430 Providing protective lining U/S and D/S of O.T
66 D.L.Bridge 44.234 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
67 O.T.Burada Raghavapuram Major
44.996 Providing protective lining U/S and D/S of O.T
68 U.T 45.306 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
69 U.T 46.250 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
70 U.T 46.756 Cut open and placing cladding concrete, E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, protective lining, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
71 DL Bridge 47.666 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
72 U.T 47.950 E W E for removal of deposited earth from Barrels, Approach and tail channels and shortcreating to the exposed reinforcement of the deck slab, Repointing, Grouting to the Masonry head walls, wing walls and abutments.
73 O.T of Nookalampadu major
48.105 Providing protective lining U/S and D/S of O.T
74 D.L.Bridge 50.835 Skin concrete to the piers, U/S & D/S protective lining, Repointing and Grouting to the masonry piers and abutments and repairs to Hand rails, and shotcreating to the exposed reinforcement of the desk slab.
75 Manual operation 1 Cross Regulator 2 nos( 13'x25')
52.299 Repointing, Grouting, Providing CC bed,side lining U/S & D/S of Regulator
76 O.T of Siripuram Major
52.299 Protective Lining U/S & D/S of O.T
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
152
INVENTARY
MECHANICAL WORKS
S.No Type of Structure Location at KM
Remedial measures
1 2 3 4
1 Khammam Major 1 2.095 Provided painting to shutter and hoist.
2 Khammam Major 2 5.600 Provided painting to shutter and hoist.
3 Chintakani Major 8.376 Provided painting to shutter and hoist.
4 O.T. of Bonakal Branch canal
14.030 Replacement of dameged parts End gear boxes, Radicon, Plumber box & Barings, Guide rollers,Flange couplings,Main rollers,Sprocket wheels, Sprocket chains, E.M.100 dia Starter Assmbly, Main switchs, Wiring,flat& Bulb rubber Seal,Bolts&Nuts,Electrical motors& provided painting to shutter and hoist.
5 Cross regulator 14.030 Replacement of dameged parts End gear boxes, Radicon, Plumber box & Barings, Guide rollers,Flange couplings,Main rollers,Sprocket wheels, Sprocket chains, E.M.150 dia Starter Assmbly, Main switchs, Wiring,flat& Bulb rubber Seal,Bolts&Nuts,Electrical motors 10HP,Line shaft& provided painting to shutter and hoist.
6 Konijarla Major 15.500 Provided painting to shutter and hoist.
7 Ganeswaram Major 16.280 Provided painting to shutter and hoist,replacement of gear box & thrust baring.
8 Tummalapalli Major 1 18.340 Provided painting to shutter and hoist.
9 Tummalapalli Major 2 20.093 Provided painting to shutter and hoist,replacement of gear box with check nut & thrust baring.
10 Seetarambanjar Major 21.935 Provided painting to shutter and hoist.
11 Mekalakunta Major 24.460 Provided painting to shutter and hoist.
12 Singarayapalem Major 25.690 Provided painting to shutter and hoist.
13 Lollorigudem Major 26.380 Provided painting to shutter and hoist.
14 Gubbagurthy Major 1 27.400 Provided painting to shutter and hoist.
15 Gubbagurthy Major 2 28.135 Provided painting to shutter and hoist.
16 Gaddalagudem Major 1
29.050 Provided painting to shutter and hoist.
17 Gaddalagudem Major 2
29.790 Provided painting to shutter and hoist.
18 Gaddalagudem Major 3
30.808 Provided painting to shutter and hoist.
19 Timmaraopet Major 1 38.248 Provided painting to shutter and hoist,and shuter, shutter frame, gear box, thrust baring .
20 Escape regulator 38.629 Provided painting to gates and hoist.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
153
1 2 3 4
21 Timmaraopet Major 2 39.126 Provided painting to gates and hoist.
22 Cross regulator 39.140 Replacement of new shutters, Gear box,Radicons,Electrical motors 10HP,Screw rods 90mm dia,hozontal girders,vertical girdersTop &Bottom Horizontal runners, Struts,rear bracing channel, Roller support plate,Roller,Side seal angle,Guide rollers,Bottom & Side seal stanching pad, Roller support plate spacer,&painting to gates& hoist.
23 Timmaraopet Major 3 40.070 Provided painting to gates and hoist.
24 P.K.Banjar Major 41.178 Provided painting to gates and hoist.
25 Arkayalapadu Major 20.093 Provided painting to shutter and hoist,and shuter, shutter frame, gear box, thrust baring .
26 Lachagudem Major 43.430 Provided painting to gates and hoist.
27 B.R.Puram Major 44.996 Provided painting to gates and hoist.
28 Nukalampadu Major 48.105 Provided painting to gates and hoist.
29 Siripuram Major 52.299 Provided painting to gates and hoist.
30 Cross regulator 52.299 Replacement of new shutters, Gear box,Radicons,Electrical motors 10HP,Screw rods 90mm dia,hozontal girders,vertical girdersTop &Bottom Horizontal runners, Struts,rear bracing channel, Roller support plate,Roller,Side seal angle,Guide rollers,Bottom & Side seal stanching pad, Roller support plate spacer,&painting to gates& hoist.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
154
Drawings
Page No. : 151 / 1 – to 11
Separate Sheets Enclosed.
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
156
SECTION - 7
BILL OF QUANTITIES
NAME OF WORK: NSP - NSLBC – APWSIP – Rehabilitation and modernization of 21st MBC from KM. 0.000 to KM. 52.300 of Nagarjunasagar Lal Bahadur Canal, A.P,
India.(PACKAGE LC-KMM-VI)
PART - I
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit In figures In words
Amount
1 2 3 4 5 6 7
I. RESECTIONING OF BANKS
1 Earth work excavation with machinery in all soils up
to Soft Disintegrated Rock obtained from borrow area
and depositing on banks for formation of canal banks
as per drawings including breaking clods, neat
sectioning, extra watering, benching old embankment
and mechanized consolidation of fill placement layers
with power roller to 98% proctor density etc. complete
as per specifications for finished item of work, as
directed by the Engineer-In-Charge (Section-5
Specifications)
482145.00 One Cum
251.00 Rupees Two hundred and Fifty one
only.
121018395.00
2 Earth work excavation with machinery cut in all soils
upto Soft Disintegrated Rock and depositing out side
the banks / as directed by the Engineer in charge for
finished item of work for removal of deposited earth
from canal bed. (Section-5 Specifications)
512090.00 One Cum
20.00
Rupees Twenty only.
10241800.00
3 Earthwork excavation by machinery in excavated
soils obtained from cutting by machinery and
depositing on banks for formation of banks
including benching old embankments breaking clods,
neat sectioning, extra watering and consolidation with
power roller and compaction to 98% proctors density
etc. complete as directed by the Engineer in charge.
(Section-5 Specifications)
256045.00 One
Cum
93.00 Rupees Ninety three only. 23812185.00
4 Earth work excavation in Loamy and Clayey soils, like
Black cotton soils, Red earth and Ordinary Gravel by
machinery in excavated soils obtained from cutting by
machinery and depositing away the excavated un
useful banking soils omplete as directed by the
Engineer in charge (Section-5 Specifications)
256045.00 One cum
36.00 Rupees Thirty six only. 9217620.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
157
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit In figures In words
Amount
1 2 3 4 5 6 7
5 Earth work excavation with machinery in all soils up
to Soft Disintegrated Rock from borrow area and
depositing on banks for formation of dowel banks
including breaking clods, neat sectioning, extra
watering and consolidation etc. complete as per
specification for finished item of work, as directed by
the Engineer-In-Charge. (Section-5 Specifications)
56745.00 One cum
172.00 Rupees One hundred and seventy two
only.
9760140.00
6 Earth work excavation with machinery cut in all soils
up to Soft Disintegrated Rock and depositing out side
the banks / as directed by the Engineer in charge for
finished item of work for toe drains. (Section-5
Specifications)
71900.00 One Cum
20.00 Rupees Twenty only. 1438000.00
7 Dry stone pitching with 225 MM thick stone including
cost and conveyance of all materials and labour charges
etc. complete, as directed by the Engineer-In-Charge.
(Section-5 Specifications) Toe Drain.
14380.00 One Cum
1299.00 Rupees One thousand two hundred and
ninety nine only.
18679620.00
8 Supplying and fixing of precast R.C.C M.20 grade
K.M stone of size 1100mm x 370mm x 250mm.using
machine crushed 20mm size hard granite well graded
broken coarse aggregate Including earth work
excavation, painting two coats with enamel paint and
carving lettering, haulage etc., as per drawing / as
directed by the Engineer incharge for finished item of
work. (Section-5 Specifications)
53.00 One No
1047.00 Rupees One thousand and forty seven
only.
55491.00
9 Supplying and fixing of precast R.C.C M.20 grade
H.M.stone of size 900mm X 200mm X 200 mm. using
machine crushed 20mm size hard broken granite well
graded coarse aggregate including earth work
excavation, painting two coats with enamel paint and
carving lettering, haulage etc., as per drawing / as
directed by the Engineer incharge for finished item of
work. (Section-5 Specifications
212.00 One No
547.00 Rupees Five hundred and forty seven
only.
115964.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
158
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit In figures In words
Amount
1 2 3 4 5 6 7
10 Laying of 150 MM thick gravel on bank for
Inspection path obtained from approved quarry
including cost and conveyance of all materials, leads,
lifts, delifts and labour charges for spreading, watering,
and mechanized consolidation with power roller etc.,
complete as per drawing or as directed by the
Engineer-In-Charge for finished item of work.
(Section-5 Specifications)
31380.00 One Cum
350.00 Rupees Three hundred and fifty only. 10983000.00
II. LAYING OF LINING
11 Earthwork excavation and depositing on bank with
loamy and clayey soils like black cottonsoils,red earth
and ordinary gravel with an initial lead of 10m and
initial lift of 2m by manually as directed by the
Engineer for Model sections (Section-5
Specifications)
12000.00 One cum
62.00 Rupees Sixty two only. 744000.00
12 Forming longitudinal /transverse filter drains
including excavation of seating to filter media, cost of
procurement and haulage of all materials, labour,
seigniorage and , form work, placing, packing for
finished item of work, as per drawing as directed by
the Engineer in charge
11336.00 One Rmt
564.00 Rupees Five hundred and sixty four
only.
6393504.00
13 Cement Concrete M.15 grade manual placement
confirming to compressive strength of 15.00 N/mm2
using well graded machine crushed Hard broken
Granite metal maximum size of 40 mm down graded
confirming to I.S Code including cost of materials and
procuring haulage of all materials, form work,
vibrating and curing etc., complete for Construction of
Model sections of size indicated in drawing for
finished item of work / as directed by the Engineer-In-
Charge. (Section-5 Specifications)
7895.00 One Cum
4207.00 Rupees Four thousand two hundred
and seven only.
33214265.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
159
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
14 Construction of Steps/sleepers of size indicated in
drawing in CC M 15 grade concrete manual placement
confirming to compressive strength of 15.00 N/mm2
using well graded machine crushed Hard broken
Granite metal maximum size of 40 mm down graded
confirming to IS Code as per drawings including cost
of procuring materials and haulage of all materials,
form work, vibrating and curing etc. complete as per
specifications for finished item of work / as directed by
the Engineer-In-Charge. (Section-5 Specifications)
471.00 One Cum
4425.00 Rupees Four thousand four hundred
and twenty five only.
2084175.00
15 Supplying and fixing in position pre-cast porous
cement concrete plugs of dimensions indicated in
drawing including cost of procurement and haulage of
all materials, labour, machine mixing, placing, packing,
form work, curing etc. complete for finished item of
work as per drawing and specifications / as directed by
the Engineer-In-Charge. (Section-5 Specifications)
1985.00
One no
315.00 Rupees Three hundred and fifteen
only.
625275.00
16 Laying 100 mm thick Plain Cement Concrete M.15
grade lining for canal bed (in reaches associated with
damaged lining) mechanized placement with concrete
paver confirming to compressive stregth of 15.00
N/mm2 concrete using well graded machine crushed
hard broken granite metal of maximum nominal size of
40 mm and down graded confirming to I.S Code
including cost and conveyance of all materials, air
entraining agent labour charges all leads and
lifts, and mixing concrete in a stationary weigh
batching plant installed at suitable place and
conveying concrete in transit mixers to the work spot
or deploying self loading weigh batching and mixing of
concrete ingradients in the mixer drum (+ 2.5 Cum
capacity) and transporting to the placement sites for
placement of concrete with paver finisher, cutting
grooves for contraction joints, including cost of all
components of machinary, consolidation of concrete
with plate vibrators, water curing etc complete as per
specifications / as directed by the Engineer in charge
for finished item of work. (Section-5 Specifications)
62004.00 One Sqm
507.00 Rupees Five hundred and seven only. 31436028.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
160
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
17 Laying 100 mm thick Plain Cement Concrete M.15
grade lining for canal slopes mechanical placement
with concrete paver confirming to compressive
strength of 15.00 N/mm2 concrete using well graded
machine crushed hard broken granite metal of
maximum nominal size of 40 mm down graded
confirming to I.S. Code including cost and conveyance
of all materials, A ir entraining agent, labour charges,
all leads and lifts, air entraining agent and mixing
concrete in a stationary weigh batching plant installed
at suitable place and conveying concrete in transit
mixers to the work spot or deploying self loading
weigh batching and mixing of concrete ingradients in
the mixer drum (+ 2.5 Cum capacity) and transporting
to the placement sites for placement with paver
finisher, providing contraction joints, including cost
of all components of machinary, curing by the
membrane forming curing compound etc complete as
per specifications / as directed by the Engineer in
charge for finished item of work. (Section-5
Specifications)
54127.00 One Sqm
539.00 Rupees Five hundred and thirty nine
only.
29174453.00
18 Providing and installing PVC strip in the contraction
& cotraction joints of cement concrete lining, placed
with paver, as per specifications and drawings and
directed by the Engineer-in-Charge (Section-5
Specifications)
a) Longitudinal
41088.00 One Rmt
75.00 Rupees Seventy five only. 3081600.00
b) Transverse
40391.00 One Rmt
69.00 Rupees Sixty nine only. 2786979.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
161
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
Amount
III. REPAIRS TO STRUCTURES:
19 Clearing of Juliflora (Prosafis) jungle including
uprooting and removing of juliflora stumps and
carefully stacking complete as directed by the Engineer
in charge. (Section-5 Specifications)
314500 One sqm
5.00 Rupees Five only. 1572500.00
20 Dismantling of old disturbed cement concrete lining /
model section and lugs and clearing away the materials
including all leads and lifts etc. complete as directed by
Engineer-in-charge. (Section-5 Specifications).
1707 One cum
276.00 Rupees Two hundred and seventy
six only.
471132.00
21 Dismantling of old disturbed R.R masonary model
section and lugs and clearing away the materials and
carefully stacking the useful stone including all leads
and lifts etc. complete as directed by the Engineer-in-
charge. (Section-5 Specifications)
1224 One cum
321.00 Rupees Three hundred and twenty
one only.
392904.00
22 Dismantling R.C.C. and clearing away the materials
including all leads and lifts etc. complete as directed by
the Engineer-in-charge. (Section-5 Specifications)
580 One cum
1620.00 Rupees One thousand six hundred
and twenty only.
939600.00
23 Earth work excavation with machinery cut in all soils
upto Soft Disintegrated Rock and depositing outside
the banks including removal of deposited earth in
approach and tail channel of UT's as directed by the
Engineer-in-charge. (Section-5 Specifications)
92870 One cum
20.00 Rupees Twenty only. 1857400.00
24 EWE for profile walls and depositing on banks in the
inner slope scoured portions with extra lead over the
initial lead of 10m and lift of 2m in hard gravelly soils.
(Manual) and depositing soils as directed by the
Engineer in Charge. (Section-5 Specifications)
4546 One cum
62.00 Rupees Sixty two only. 281852.00
25 Earth work excavation in Loamy and Clayey soils,
like Black cotton soils, Red earth and Ordinary Gravel
by machinery depositing away the excavated soils
including clearing of approach and tail
channelcomplete as directed by the Engineer in charge
(Section-5 Specifications)
119391 One cum
56.00 Rupees fifty six only. 6685896.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
162
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
26 Earth work excavation for removal of deposited
earth in ordinary soils like red earth and ordinary
gravel with extra leads and extra lift manually from
UT barrel portion and depositing away as directed by
the Engineer in charge.(Section-5 Specifications)
18262 One Cum
142.00 Rupees One thousand and forty two
only.
2593204.00
27 Cement concrete with C.C. M-10 grade concrete manual placement confirming to compressive strength
of 10.0 N/mm2 concrete using well graded machine
crushed Hard broken Granite metal maximum size of
40 mm down graded confirming to IS Code including
cost and conveyance of all materials, labour charges all
leads and lifts, seigniorage, and compacting concrete
with vibrator, curing with water etc complete for
foundations etc. as directed by the Engineer in charge.
(Section-5 Specifications)
220 One Cum
3871.00 Rupees Three thousand eight
hundred and seventy one only.
851620.00
28 Laying CC M15 grade manual placement using
40mm size HBG machine crushed, down graded metal,
machine mixing, vibrating charges, centering /
shuttering arrangements curing with water etc.
complete for laying Cladding concrete on rear of
abutments etc. as per drawing / specifications and as
directed by Engineer-in-charge. (Section-5
Specifications)
3061 One cum
4695.00 Rupees Four thousand six hundred
and ninety five only.
14371395.00
29 Vibrated Cement concrete with M-15 grade concrete
manual placement confirming to compressive strength
of 15.00 N/mm2 concrete using well graded machine
crushed Hard broken Granite metal maximum size of
40 mm down graded confirming to IS Code
including cost and conveyance of all materials, labour
charges all leads and lifts, machine mixing and
compacting concrete with vibrator, curing with water
etc complete for piers, abutments, walls etc.as
directed by the Engineer in charge (Section-5
Specifications)
712 One Cum
5146.00 Rupees Five thousand one hundred
and forty six only.
3663952.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
163
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
Amount
30 Vibrated Reinforced Cement concrete M 20 grade
concrete manual placement confirming to compressive
strength of 20.00 N/mm2 concrete using well graded
machine crushed Hard broken Granite metal
maximum size of 20 mm down graded confirming to
IS Code including cost and conveyance of all
materials, labour charges, all leads & lifts curing with
water etc complete , compaction with vibrator and
machine mixing for piers,Abutments,wing walls etc
complete, for finished item of work. as directed by the
Engineer in charge.(Section-5 Specifications)
1435 One Cum
6283.00 Rupees Six thousand two hundred and
eighty three only.
9016105.00
31 M 25grade cement concrete confirming to
compressive strength of 25.00 N/mm2 concrete using
well graded machine crushed Hard broken Granite
metal maximum size of 20 mm down graded
confirming to IS Code including cost procuring
hauling of all materials, machine mixing, including
compaction concrete with vibrator and centering,
curing with water etc, complete for the finished item
of work for laying wearing coat over Deck slab as
directed by the Engineer in charge.
82 One cum
5040.00 Rupees Five thousand and forty only. 413280.00
32 Earth refilling with earth obtained from excavated
soils (rehandling of excavated soils) for forming banks
at cut open places including sectioning, watering and
consolidation to 98% proctors density with power
roller including hire charges of roller complete as
directed by the Engineer in charge (Section-5
Specifications
42210 One cum
84.00 Rupees Eighty four only. 3545640.00
33 Earth work excavation with machinery in all soils
upto Soft Disintegrated Rock obtained from borrow
area and depositing on banks for formation of canal
banks as per drawings including breaking clods, neat
sectioning, extra watering, benching old embankment
and mechanized consolidation of fill placement layers
with power roller to 98% procter density etc. complete
as per specifications for finished item of work, as
directed by the Engineer-In-Charge (Section-5
Specifications)
28169.00 One cum
249.00 Rupees Two hundred and forty nine
only.
7014081.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
164
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
34 Construction of Steps of size indicated in drawing in
CC M 15 grade concrete manual placement
confirming to compressive strength of 15.00 N/mm2
using well graded machine crushed Hard broken
Granite metal maximum size of 40 mm down graded
confirming to IS Code as per drawings including cost
of procuring materials and haulage of all materials,
form work, vibrating, machine mixing and curing with
water etc. complete as per specifications for finished
item of work / as directed by the Engineer-In-Charge.
(Section-5 Specifications)
684.00 One cum
4425.00 Rupees Four thousand four hundred and
twenty five only.
3026700.00
35 R.C.C. M20. grade concrete manual placement
confirming to compressive strength of 20.00 N/mm2
concrete using well graded machine crushed Hard
broken Granite metal maximum size of 20 mm down
graded confirming to IS Code ,including and
conveyance of all materials, machine mixing curing
with water, copaction with vibrator and Labour charges
erc complete for finished item of work FOR HAND
RAILS of size 0.31x0.31 as indicated in drawing and
as directed by the Engineer in charge. (Section-5
Specifications)
573.00 One Rmt
793.00 Rupees Seven hundred and ninety three
only.
454389.00
36 Supply and fixing of HYSD bars in position including
cost and conveyance of material and straightening,
cutting, bending including cost of binding wire and
placing in position etc. complete as directed by the
Engineer-in-charge. ( Section-5 Specifications
133660 One Kg
56.00 Rupees Fifty six only. 7484960.00
37 Laying 100 mm thick cement concrete protective lining
for canal bed by manual placement with C.C. M-15
grade concrete confirming to compressive strength of
15.00 N/mm2 concrete using well graded machine
crushed Hard broken Granite metal maximum size of
40 mm down graded confirming to IS Code machine
mixing , including cost and conveyance of all
materials, air entraining agent hire charges
of machinery, labour charges all leads and lifts,
machine mixing, and cutting groves for panel joints,
compacting concrete with vibrates, curing with water
etc complete as directed by the Engineer- in-charge
(Section-5 Specifications) (Protective lining for
structures)
29686 One Sqm
444.00 Rupees Four hundred and forty four
only.
13180584.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
165
Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit Rate Amount
In figures In words
38 Laying100 mm thick cement concreteprotective lining
for canal side slopes by manual with C.C. M-15 grade
concrete confirming to compressive strength of 15.00
N/mm2 concrete using well graded machine crushed
Hard broken Granite metal maximum size of 40 mm
down graded confirming to IS Code ,machine mixing
including cost and conveyance of all materials, air
entraining agent hire charges of machinery
labour charges all leads and lifts, and cutting groves
for panel joints, compacting concrete with vibrates,
curing compound etc complete as directed by the
Engineer- in-charge (Section-5 Specifications)
(Protective lining for structures
31535 One Sqm
445.00 Rupees Four hundred and forty five
only.
14033075.00
39 Laying 75 mm thick Wearing coat in C.C M25 grade
concrete manual placementconforming to compressive
strength of 25N/mm 2 concrete using well graded
machine crushed H.B.G metal of maximum size of 20
mm, down graded confirming to I.S code including
cost and conveyance of all materials and machine
mixing, vibrating, hire charges of machinery and
curing with water etc. complete as directed by the
Engineer-in-charge. ( Section-5 Specifications)
44 One cum
4680.00 Rupees Four thousand six hundred and
eighty only.
205920.00
40 Providing re-pointing in CM(1:3) on exposing CR
masonary surface duly racking old pointing at the joints
and water proof compound including cost and
conveyance of all material scaffolding charges labour
charges for racking the joints , cutting grooves treating
the grooves with water ceiling etc., complete as per
drawings as directed by Engineer in charge.(Section-5
Specifications)
13850 One sqm
138.00 Rupees One hundred and thirty eight
only.
1911300.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
166
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
41 Spplying and fixing of mastic pad 25mm thick for
fixing in construction joints including cost and
conveyance charges etc complete as directed by
Engineer in charge.(Section-5 Specifications)
177 One Sqm
915.00 Rupees Nine hundred and fifteen only. 161955.00
42 Supply and fixing of guide stones ( granite
variety)1200mm x 200mm x200mm size including cost
and conveyance of material and labour charges etc.
complete as directed by the Engineer in charge.
(Section-5 Specifications)
632 One No.
292.00 Rupees Two hundred and ninety two
only.
184544.00
43 Drilling holes for Grouting to existing masonry
abutments, wing walls and returns of under tunnels,
aqueducts and piers by drilling holes of dia 20mm to
a depth of 0.50m at 1.50m c/c both ways, inserting
P.V.C. pipes of 12mm dia and of 0.50m length in to
the drilled holes including hire charges of compressor,
cost of P.V.C pipes etc complete as directed by the
department. (Section-5 Specifications)
7762 One No
93.00 Rupees Ninety three only. 721866.00
44 Grouting the existing masonry abutments, wing
walls and returns of under tunnels, aqueducts, piers
with water cement ratio of 5:1by volume and
progressively improving to 4:1 and 3:1 and when
necessary changing over to the mortar mix of 3:1 with
FM of sand 2, injecting into PVC pipes of 12m dia with
a maximum pressure of 2.0 kg/cm2 in ascending order
including cost of grout additive and conveyance of
cement and all other materials labour charges etc.
complete as directed by the department. (Section-5
Specifications)
1531998 One Kg
9.00 Rupees Nine only. 13787982.00
45 Shotcreting in 2 layers ( each layer of + 38 mm
thickness) duly fixing etc to the damaged concrete
associated with exposed reinforcement bars duly fixing
chain link mesh 5mm x 50mm x 50mm in between the
two layers including cost and conveyance of all
materials and labour charges etc. complete as per
specifications / as directed by the Engineer in charge.
(Section-5 Specifications)
611 One Sqm
1423.00 Rupees One thousand four hundred and
twenty three only.
869453.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
167
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
46 Supply of Kraft paper for laying on abutments
including cost etc complete. As directed by the
Engineer in charge. (Section-5 Specifications)
93 One Sqm
450.00 Rupees Four hundred and fifty only. 41850.00
47 Providing weep holes in the abutments 2inch diameter
as indicated in drawing and as directed by the Engineer
in charge. (Section-5 Specifications)
136 One Rmt
190.00 Rupees One hundred ninety only. 25840.00
48 Providing Drainage spouts in the deck slab 4" PVC
pipe including cost etc complete as directed by the
Engineer in charge. (Section-5 Specifications)
72 One Rmt
150.00 Rupees One hundred and fifty only. 10800.00
59 Supply and fixing fabrication 16mm dia anchor rods
including fixing in RR masonry in position duly
drilling 25mm dia holes to a depth of 0.45mts including
cost and conveyance of all materials and labour charges
etc complete as directed by the Engineer in charge.
(Section-5 Specifications)
10017 One No
190.00 Rupees One hundred and ninety only. 1903230.00
50 Providing Expansion joints in bed and sides (at inter
section of structures with lining) with 12mm thick
preformed joint filler after painting the surface with
approved primer and filled with sealing compound
including cost of procurement and haulage of all
materials placing, etc.,as per drawing / as directed by
the Engineer for finished item of work. (Section-5
Specifications)
230 One Rmt
108.00 Rupees One hundred and eight only. 24840.00
51 Earth work excavation by machinery in all soils upto
SDR, and muck deposited in wet and slushy conditions
including of conveyance and depositing with extra
lead etc., complete as directed by Engineer-in-charge
(Section-5 Specifications)
1363 One Cum
124.00 Rupees One hundred and twenty four
only.
169012.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
168
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity
Unit
In figures In words
52 Back filling with useful excavated soils (other than
sand) complying with standard specification for filling
foundation and sides of head walls, wing walls etc.complete for finished item of work. (Section-5
Specifications)
927 One cum
21.00 Rupees Twenty one only. 19467.00
53 Treatment of contraction joints in cast-in situ cement
concrete in canal bed on sides as per drawing filled
with approved quality of primer and sealing compound
of approved quality including cost of procurement and
handling of all materials placing etc complete as per
drawing as directed by the Engineer-in-Charge.
(Section-5 Specifications)
25150 One Cum
56.00 Rupees Fifty six only. 1408400.00
54 Providing Sealent treatment to expansion joints
between the existing C.C Blocks on bed between the
wings of trough and canal portion including cost and
conveyance of all materials, Cost of sealing compound,
labour charges for rake opening the expansion joint,
sealant filling etc., complete as per drawings or as
directed by Engineer-in-Charge-1 Rmt (Section-5
Specifications)
1574 One Rmt
103.00 Rupees One hundred and three only. 162122.00
55 Vibrated Reinforced Cement concrete M 20 grade
concrete manual placement confirming to compressive
strength of 20.00 N/mm2 concrete using well graded
machine crushed Hard broken Granite metal
maximum size of 20 mm down graded confirming to
IS Code including cost and conveyance and all
materials including centering, vibration, machine
mixing, curing etc., complete for bed block, slabs
over O.T/D.P. Sluices, and for hoist Bridge curing
with water etc complete, for finished item of work as
directed by the Engineer in charge. (Section-5
Specifications)
362 One cum
6300.00 Rupees Six thousand and three hundred
only.
2280600.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
169
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
56 Supplying and fixing of RCC Hume pipe 600mm dia NP2
class including cost and conveyance of all materials , labour
charges, etc complete as directed by the Engineer in charge.
25 One Rmt
1938.00 Rupees One thousand nine hundred and
thirty eight only.
48450.00
57 Supplying and fixing of RCC Hume pipe 800mm dia NP2
class including cost and conveyance of all materials , labour
charges, etc complete as directed by the Engineer in charge.
12.5 One Rmt
3127.00 Rupees Three thousand one hundred and
twenty seven only.
39087.50
IV. MECHANICAL WORKS
58 Supplying and fixing of Gear boxes 2 nos , thrust bearings
2 nos and painting to gates and hoist for the OT of
Chinthakani major @ Km 8.376 of 21 st MBC including
cost and conveyance of all materials and labour charges etc.
as per drawings & as directed by theEngineer in charge
(Section-5 Specifications).
1 job One job
15886.00 Rupees Fifteen thousand eight hundred
and eighty six only.
15886.00
59 Supplying and fixing for OT of BBC regiulator @ Km
14.03 of 21st MBC 3 HP electrical motors 2 Nos. and gear
boxes 4 nos. , radican 2 no. plumber blacks 8 nos.and
bearings 4 nos. guide rollers 8 nos. , flange couplings 6
nos. , main rollers 8 nos, sprocket wheels and chains
including painting to gates and hoists and electrical wiring
and fixing rubber seals etc. including cost and conveyance
of all materials, labour charges etc. complete as per
drawings & as directed by the Engineer in charge (Section-
5 Specifications)
1 job One job
550210.00 Rupees Five Lakhs fifty thousand two
hundred and ten only.
550210.00
60 Supplying and fixing for Cross Regulator @ Km 14.03 of
21 st MBC 10 HP electrical motors 2 Nos. and gear boxes
4 nos. , radican 2 no. plumber blacks 8 nos.and bearings 4
nos. , flange couplings 10 nos. ,sprocket wheels and chains
including painting to gates and hoists and electrical wiring
and fixing rubber seals etc. including cost and conveyance
of all materials, labour charges etc. complete as per
drawings or as directed by the Engineer in charge Engineer
in charge. (Section-5 Specifications)
1 job One job
833283.00 Rupees Eight Lakhs thirty three
thousand two hundred and eighty three
only.
833283.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
170
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
61 Supplying and fixing of Gear boxes 1 nos , thrust bearings
1 nos and painting to gates and hoist for the OT of
Ganeswaram major @ Km16.280 of 21 st MBC including
cost and conveyance of all materials and labour charges etc.
as per drawings or as directed by theEngineer in charge
(Section-5 Specifications)
1 job One job
6750.00 Rupees Six thousand seven hundred and
fifty only.
6750.00
62 Supplying and fixing of Gear boxes 1 nos , thrust bearings
1 nos, checknut and painting to gates and hoist for the OT
of Tummalapalli major-2 @ Km20.093 of 21 st MBC
including cost and conveyance of all materials and labour
charges etc. as per drawings & as directed by theEngineer
in charge (Section-5 Specifications)
1 job One Job
6672.00 Rupees Six thousand six hundred and
seventy two only.
6672.00
63 Supplying and fixing of Gear boxes 1 nos , thrust bearings
1 nos, fabrication of shutter of size 0.70 x0.75 m with screw
rod bolts and nuts etc. and painting to gates and hoist for
the OT of Timmaraopeta major-1 @ Km 38.248 of 21 st
MBC including cost and conveyance of all materials and
labour charges etc. as per drawings & as directed by the
Engineer in charge (Section-5 Specifications)
1 job One job
14755.00 Rupees Fourteen thousand seven
hundred and fifty five only.
14755.00
64 Fabrication , supplying and fixing for the Cross Regulator
@ Km. 39.140 of 21 st MBC, regulator gate size 7.9 x3.9
m in place of damaged gates 2 nos. to suit the vent
consisting of skin plate , horizontal girders, top and bottom
angles, vertical angles bottom and top , rubber seals, cast
iron rollers, with heavy duty bushes, bearings including all
accessories, 10 Hp electrical motors 2 nos., radican 2nos,
and gear boxes 4 nos., plumber blocks 8 nos., flange
couplings 10 nos., chain sprockets 2 nos., and electrical
wiring, starters 2 nos. screw rods 4 nos. , line shafts 2nos.
suitable and painting to the gates and hoist etc. including
cist conveyance of all materials, labour charges, trial run
etc. complete for finished item as per drawings & as
directed by the Engineer - in - charge (Section-5
Specifications)
1 job One job
2606266.00 Rupees Twenty six Lakhs six thousand
two hundred and sixty six only.
2606266.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
171
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of specification) Quantity Unit
In figures In words
65 Supplying and fixing of Gear boxes 1 nos , thrust bearings 1
nos, fabrication of shutter of size 1.20 x 1.20 m with screw rod,
bolts and nuts etc. and painting to gates and hoist for the OT of
Arkayalapadu major @ Km42.630 of 21 st MBC including cost
and conveyance of all materials and labour charges etc. as per
drawings & as directed by the Engineer in charge (Section-5
Specifications)
1 job One job
37155.00 Rupees Thirty seven thousand one
hundred and fifty five only.
37155.00
66 Fabrication , supplying and fixing for the Cross Regulator @
Km. 52.299 of 21 st MBC, regulator gate size 7.62 x 3.81 m in
place of damaged gates 2 nos. to suit the vent consisting of skin
plate , horizontal girders, top and bottom angles, vertical angles
bottom and top , rubber seals, cast iron rollers, with heavy duty
bushes, bearings including all accessories, 10 Hp electrical
motors 2 nos., radican 2nos, and gear boxes 4 nos., plumber
blocks 8 nos., flange couplings 10 nos., chain sprockets 2 nos.,
and electrical wiring, starters 2 nos. screw rods 4 nos. , line
shafts 2nos. suitable and painting to the gates and hoist etc.
including cist conveyance of all materials, labour charges, trial
run etc. complete for finished item as per drawings & as
directed by the Engineer - in - charge (Section-5 Specifications)
1 job Each
2524803.00 Rupees Twenty five Lakhs twenty
four thousand eight hundred and
three only.
2524803.00
67 Painting to gates and hoists for the OT sluices of Khammam
major -1 @ Km. 2.095, Khammam Major - 2 @ km. 5.60,
Konijerla Major @ Km. 15.5, Tummala palli Major -1 @ Km.
18.340, Seetaram banjar Major @ Km. 21.935, Mekala kunta
Major @ Km. 24.460, Singarai palem Major @ Km.25.69,
Lollori gudem Major @ km. 26.380, Gubbagurthi major -1 @
Km. 27.400, Gubbagurthi Major -2 @ Km. 28.135,
Gaddalagudem Major -1 @ km.29.008, Gaddalagudem Major -2
@ Km.29.790, Gaddalagudem Major -3 @ Km.30.868,
Timmaraopeta Major -2 @Km. 39.126, Timmaraopeta Major -
3@ Km.40.070, PK Banjor Major @ Km.41.178, Lachagudem
Major @ Km.43.430, B.R. Puram Major @Km.44.996,
Nukalampadu Major @ Km. 48.105 and Siripuram Major @
km.52.299 and Escape Regulator @ Km.38.629 of 21 st MBC
including cost and conveyance of all materials, labour charges
etc. complete as per drawings & as directed by the Engineer - in
- charge( 45319+ 7020 + 13300 = 65639.00 ) (Section-5
Specifications)
1 job Each
98458.00 Rupees Ninety eight thousand four
hundred and fifty eight only.
98458.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
172
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit In figures
In words
V. DEEP CUTS
68 Earth work Excavation in all soil upto H.D.R. by machine
at the junction of soil and rock. Including dewatering, cross
bund laying and removing, placing and removal of B.C
soils (Section-5 Specifications)
6861.00 One Cum
125.00 Rupees One hundred and twenty five
only.
857625.00
69 Earth work excavation in Loamy and Clayey soils, like
Black cotton soils, Red earth and Ordinary Gravel by
machinery depositing away the excavated soils .Including
dewatering, cross bund laying and removing, placing and
removal of B.C soils complete as directed by the Engineer
in charge (Section-5 Specifications)
665195.00 One Cum
23.00 Rupees Twenty three only. 15299485.00
70 Earth work excavation by machinery in all soils upto
SDR, deposited earth and muck deposited in wet and slushy
conditions including of conveyance and depositing with a
lead of 2 Km etc. .Including dewatering, cross bund laying
and removing, placing and removal of B.C soils, complete
as directed by Engineer-in-charge (Section-5
Specifications)
63921.00 One Cum
136.00 Rupees One hundred and thirty six
only.
8693256.00
71 Dismantling of stone masonry in CM over 3 Mts height,
Clearing away and carefully stacking materials useful for
reuse as directed by the Engineer in charge (Section-5
Specifications)
12531.00 One Cum
321.00 Rupees Three hundred and twenty one
only.
4022451.00
72 Supply and fixing of HYSD bars in position including cost
and conveyance of material and straightening, cutting,
bending including cost of binding wire and placing in
position etc. complete as directed by the Engineer-in-
charge. (Section-5 Specification.
86041.00 One Kg
56.00 Rupees Fifty six only. 4818296.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
173
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of specification) Quantity Unit
In figures In words
73 For Deep Cut bed lining Laying 100 mm thick cement
concrete lining for canal bed with C.C. M-15 grade concrete
confirming to compressive strength of 15.00 N/mm2 using well
graded machine crushed Hard broken Granite metal maximum
size of 40 mm down graded confirming to IS Code including
cost and conveyance of all materials, air entraining
agent labour charges all leads and lifts, and mixing concrete
in a stationary weigh batching plant installed at suitable places
and conveying concrete in transit mixers to the work spot and
placing with paver finisher, cutting groves for panel joints,
including cost of all components of machinery, curing etc
complete as indicated in drawing directed by the Engineer in
charge.(Section-5 Specifications)
59000.00 One Sqm
579.00 Rupees Five hundred and seventy
nine only.
34161000.00
74 Removal of defective concrete, cleaning the surface
thoroughly, applying the short crete mixture (2 layers, each of
38mm thickness and chain link mesh in between, complete as
per technical specifications) mechanically with compressed air
under pressure comprising cement, sand, course aggregates,
water and quick setting compound in the portions including
weld (Section-5 Specifications)
75686.00 One Sqm
1424.00 Rupees One thousand four
hundred and twenty four only.
107776864.00
75 Cleaning and painting the groove with approved primer and
filled with sealing compound of approved quality including cost
of procurement and haulage of all materials, placing, etc.,
complete as per drawings & as directed by the Engineer in
charge for Construction Joints .(Section-5 Specifications)
12424.00 One Rmt
55.00 Rupees Fifty five only. 683320.00
76 Treatment of contraction joints in cast-in-situ cement concrete
in canal bed on sides as per drawing filled with approved quality
of primer and sealing compound of approved quality including
cost of procurement and handling of all materials placing etc
complete as per drawing as directed by the Engineer-In charge.
(Section-5 Specifications)
64884.00 One Rmt
56.00 Rupees Fifty six only. 3633504.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
174
Rate Amount Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
77 Earth work excavation in Loamy and Clayey soils, like
Black cotton soils, Red earth and Ordinary Gravel by
machinery depositing away the excavated soils complete
as directed by the Engineer in charge (Section-5
Specifications)
22071.00 One cum
56.00 Rupees Fifty six only. 1235976.00
78 Dry stone Pitching for revetment with 225mm thick
excluding cost of stone and including the labour charges
and all other materials etc complete. as directed by the
Engineer-in-Charge. (Section-5 Specifications)
7112.00 One Cum
1299.00 Rupees One thousand two hundred
and ninety nine only.
9238488.00
79 Pointing with C.M (1:3) to the exposed face of toe drain
including cost and conveyance of all materials labour
charges curing etc., complete as directed by the Engineer-
in-charge (Section-5 Specifications)
3348.00 One Sqmt
115.00 Rupees One hundred and fifteen
only.
385020.00
80 Drilling holes for 16 mm ø for a depth of 0.5 m by
pneumatic compressor and fixing in position including
cost and conveyance of all material, labour charges
except the cost of steel etc complete as directed by the
Engineer in charge. (Section-5 Specifications)
36600.00 One No
145.00 Rupees One hundred and forty five
only.
5307000.00
81 Clearing away the light jungle including up rooting
and removing the stumps at sides as directed by the
Engineer in charge. (Section-5 Specifications)
104017.00 One Sqm
3.00 Rupees Three only. 312051.00
82 supply and fixing of RCC hume pipe of 300mm dia
including suitable collar fixing etc (Section-5
Specifications)
160.00 One Rmt
364.00 Rupees Three hundred and sixty
four only.
58240.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
175
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
Amount
83 supply of RCC collar suitable to 300mm dia pipe
including cost and conveyance etc
64.00 One No.
85.00 Rupees Eighty five only. 5440.00
84 Vibrated Cement concrete with M-15 grade concrete
manual placement confirming to compressive strength
of 15.00 N/mm2 concrete using well graded machine
crushed Hard broken Granite metal maximum size of
40 mm down graded confirming to IS Code
including cost and conveyance of all materials, labour
charges all leads and lifts, machine mixing, and
compacting concrete with vibrates, curing with water
etc complete for piers, abutments, walls etc.as
directed by the Engineer in charge (Section-5
Specifications)
7294.00 One Cum
5146.00 Rupees Five thousand one hundred
and forty six only.
37534924.00
85 Supplying and fixing in position precast porous
cement concrete plugs including cost of procurement
and haulage of all materials, labour, and machine
mixing, placing, packing form work, curing for
finished item of work as per drawings or as directed
by the Engineer in charge (Section-5 Specifications)
3788.00 One No
229.00 Rupees Two hundred and twenty
nine only.
867452.00
86 Laying plum concrete manual placement M.75 mix
with 60% of 75 mm and 40% of 40 mm HGB metal
including cost and conveyance of all materials,
machine mixing charges, centering charges and
vibrating charges, curing with water etc for filling
cavities at side slopes behind C.C. lining as directed
by the Engineer in charge (Section-5 Specifications)
11500.00 One cum
3300.00 Rupees Three thousand and three
hundred only.
37950000.00
87 Earth work excavation by machinery in soils obtained
from berm cutting and formation of road for
inspection path including breaking clods, neat
sectioning, extra watering and consolidation with
power roller and compaction to 98% proctors density
etc. complete as directed by the Engineer in charge.
(Section-5 Specifications)
18153.00 One cum
76.00 Rupees Seventy six only. 1379628.00
Sd/- CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
176
Rate Sl.
No.
Description of item
(with brief specification and reference to Book of
specification)
Quantity Unit
In figures In words
Amount
88 Earth work excavation in loamy and clayey soils, like
black cotton soils, red earth and ordinary gravel by
machinery depositing away the excavated soils
complete as directed by the Engineer in charge
(Section-5 Specifications)
1707.00 One cum
19.00 Rupees Nineteen only. 32433.00
89 Cement concrete with C.C M-7.5 grade concrete
manual placement confirming to compressive strength
of 7.5N/mm2 concrete using well graded machine
crushed hard broken metal maximum size of 40mm
down graded confirming to I S code including cost and
conveyance of all materials, labour charges, all leads
and lifts, machine mixing, and compacting concrete
with vibrator, curing etc complete for foundations etc
as directed by the Engineer in charge
198.00 One cum
3510.00 Rupees Three thousand five hundred
and ten only.
694980.00
90 Cement concrete with C.C M-10 grade concrete
manual placement confirming to compressive strength
of 10.0 N/mm2 concrete using well graded machine
crushed hard broken metal maximum size of 40mm
down graded confirming to I S code including cost and
conveyance of all materials, labour charges, all leads
and lifts, machine mixing and compacting concrete
with vibrator, curing etc complete for foundations etc
as directed by the Engineer in charge
258.00
One cum
3871.00 Rupees Three thousand eight
hundred and seventy one only.
998718.00
713329870.50 Rebate at 27.10% Less. 193312394.91 Total Rs: 520017475.59
(Rupees Fifty two Crores Seventeen thousand four hundred seventy five and paisa fifty nine.)
Note: (1) Item for which no rate or price has been entered in will not be paid for by the Employer when executed and shall be deemed covered by the other
rates and prices in the Bill of Quantities (refer: ITB Clause 13.2 and GCC Clause 43.3).
(2) Unit rates and prices shall be quoted by the bidder in Indian rupee [ITB Clause 14.1].
(3) Where there is a discrepancy between the rate in figures and words, the rates in words will govern. [ITB Clause 27.1(a) ]
4) Where there is a discrepancy between the unit rate and the line item total resulting from multiplying the unit rate by quantity, the unit rate quoted shall
govern [ITB Clause 27.1 (b)].
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
178
FORMS OF SECURITIES
Acceptable forms of securities are annexed. Bidders should not complete the Performance and Advance Payment
Security forms at this time. Only the successful Bidder will be required to provide Performance and Advance Payment
Securities in accordance with one of the forms, or in a similar form acceptable to the Employer.
Annex A: Bid Security (Bank Guarantee)
Annex B: Performance Bank Guarantee
Annex B1: Performance Bank Guarantee for Unbalanced Items
Annex C: Deleted
Annex D: Bank Guarantee for Advance Payment
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
179
Annex A
BID SECURITY (BANK GUARANTEE)
WHEREAS, _______________________ [name of Bidder] (hereinafter called "the Bidder") has submitted his Bid
dated _______________________ [date] for the construction of _____________________________________ [name
of Contract] (hereinafter called "the Bid").
KNOW ALL PEOPLE by these presents that We ______________________________ [name of bank] of
____________________________ [name of country] having our registered office at
___________________________________ (hereinafter called "the Bank") are bound unto
______________________________[name of Employer] (hereinafter called "the Employer") in the sum of
___________________1 for which payment well and truly to be made to the said Employer the Bank binds itself, his
successors and assigns by these presents.
SEALED with the Common Seal of the said Bank this _________ day of __________ 19____.
THE CONDITIONS of this obligation are:
(1) If after Bid opening the Bidder withdraws his bid during the period of Bid validity specified in
the Form of Bid;
or
(2) If the Bidder having been notified of the acceptance of his bid by the Employer during the period
of Bid validity:
(a) fails or refuses to execute the Form of Agreement in accordance with the Instructions
to Bidders, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the Instruction
to Bidders; or
(c) does not accept the correction of the Bid Price pursuant to Clause 27;
we undertake to pay to the Employer up to the above amount upon receipt of his first written demand, without the
Employer having to substantiate his demand, provided that in his demand the Employer will note that the amount
claimed by him is due to him owing to the occurrence of one or any of the three conditions, specifying the occurred
condition or conditions.
This Guarantee will remain in force up to and including the date ____________________2 days after the deadline for
submission of Bids as such deadline is stated in the Instructions to Bidders or as it may be extended by the Employer,
notice of which extension(s) to the Bank is hereby waived. Any demand in respect of this guarantee should reach the
Bank not later than the above date.
DATE _______________ SIGNATURE OF THE BANK _________________________
WITNESS ____________ SEAL _______________________________________
_________________________________________________________________
[signature, name, and address]
____________________________
1 The Bidder should insert the amount of the guarantee in words and figures denominated in Indian Rupees. This
figure should be the same as shown in Clause 16.1 of the Instructions to Bidders.
2 45 days after the end of the validity period of the Bid.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
180
PERFORMANCE BANK GUARANTEE
To: ______________________________________________ [name of Employer]
_________________________________________ [address of Employer]
WHEREAS _________________________ [name and address of Contractor] (hereinafter called "the
Contractor") has undertaken, in pursuance of Contract No. _____ dated ________________ to execute
__________________________ [name of Contract and brief description of Works] (hereinafter called "the Contract");
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you with
a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance with his obligations in
accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
Contractor, up to a total of ____________________ [amount of guarantee] 1___________________________ [in
words], such sum being payable in the types and proportions of currencies in which the Contract Price is payable, and
we undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums within the
limits of ____________________ [amount of guarantee]1 as aforesaid without your needing to prove or to show
grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before presenting us
with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract or of the
Works to be performed thereunder or of any of the Contract documents which may be made between you and the
Contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such
change, addition or modification.
This guarantee shall be valid until ……… (i.e.) 28 days from the date of expiry of the Defects Liability
Period.
Signature and seal of the guarantor _____________________________
Name of Bank ____________________________________________
Address ____________________________________________
Date ____________________________________________
__________________
1 An amount shall be inserted by the Guarantor, representing the percentage of the Contract Price specified in
the Contract and denominated in Indian Rupees.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
181
PERFORMANCE BANK GUARANTEE (for unbalanced items)
To: ______________________________________________ [name of Employer]
_________________________________________ [address of Employer]
WHEREAS _________________________ [name and address of Contractor] (hereinafter called "the
Contractor") has undertaken, in pursuance of Contract No. _____ dated ________________ to execute
__________________________ [name of Contract and brief description of Works] (hereinafter called "the Contract");
AND WHEREAS it has been stipulated by you in the said Contract that the Contractor shall furnish you with
a Bank Guarantee by a recognized bank for the sum specified therein as security for compliance with his obligations in
accordance with the Contract;
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee;
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
Contractor, up to a total of ____________________ [amount of guarantee] 1___________________________ [in
words], such sum being payable in the types and proportions of currencies in which the Contract Price is payable, and
we undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums within the
limits of ____________________ [amount of guarantee]1 as aforesaid without your needing to prove or to show
grounds or reasons for your demand for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the Contractor before presenting us
with the demand.
We further agree that no change or addition to or other modification of the terms of the Contract or of the
Works to be performed thereunder or of any of the Contract documents which may be made between you and the
Contractor shall in any way release us from any liability under this guarantee, and we hereby waive notice of any such
change, addition or modification.
This guarantee shall be valid until …….. (i.e.) 28 days from the date of issue of the certificate of completion
of works.
Signature and seal of the guarantor _____________________________
Name of Bank ____________________________________________
Address ____________________________________________
Date ____________________________________________
__________________
1 An amount shall be inserted by the Guarantor, representing additional security for unbalanced Bids, if any
and denominated in Indian Rupees.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
182
BANK GUARANTEE FOR ADVANCE PAYMENT
To: __________________________________________ [name of Employer]
__________________________________________ [address of Employer]
___________________________________________[name of Contract]
Gentlemen:
In accordance with the provisions of the Conditions of Contract, subclause 51.1 ("Advance Payment") of the
above-mentioned Contract, ________________________________ [name and address of Contractor] (hereinafter
called "the Contractor") shall deposit with ________________________ [name of Employer] a bank guarantee to
guarantee his proper and faithful performance under the said Clause of the Contract in an amount of _____________
[amount of guarantee] 1_________________________________ [in words].
We, the ____________________ [bank or financial institution], as instructed by the Contractor, agree
unconditionally and irrevocably to guarantee as primary obligator and not as Surety merely, the payment to
____________________ [name of Employer] on his first demand without whatsoever right of objection on our part
and without his first claim to the Contractor, in the amount not exceeding ____________________ [amount of
guarantee]1 __________________________________ [in words].
We further agree that no change or addition to or other modification of the terms of the Contract or of Works
to be performed thereunder or of any of the Contract documents which may be made between
_____________________ [name of Employer] and the Contractor, shall in any way release us from any liability under
this guarantee, and we hereby waive notice of any such change, addition or modification.
This guarantee shall remain valid and in full effect from the date of the advance payment under the Contract
until _________________________ [name of Employer] receives full repayment of the same amount from the
Contractor.
Yours truly,
Signature and seal: _______________________________
Name of Bank/Financial Institution: _________________
Address: _______________________________________
Date: ____________________
__________________________
1 An amount shall be inserted by the bank representing the amount of the Advance Payment, and denominated
in Indian Rupees.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
183
Office of the Superintending Engineer, N.S.L.B.C. O&M Circle, Tekulapally, KHAMMAM
CORRIGENDUM
To certain items of this office NCB Tender Notice No. 9/07-08, dated 17-01-2008.
Sl.
No.
Name of the work & Package No. Item For Read
Approximate Value
of Work (Rs. In
Lakhs
5899.53 5900.67
1 NSP - NSLBC – APWSIP –
Rehabilitation and modernization from
KM29.291to KM59.466of
Nagarjunasagar Lal Bahadur Canal, A.P,
India. (Package No.LC NLG -2)
Bid security
(Rs. In Lakhs 59.00 59.00
Approximate Value
of Work (Rs. In
Lakhs
4736.38 4739.60
2 NSP - NSLBC – APWSIP –
Rehabilitation and modernization from
KM.59.466 to KM. 90.540 of
Nagarjunasagar Lal Bahadur Canal, A.P,
India. (Package No.LC NLG-3)
Bid Security
( Rs. In Lakhs) 47.37 47.40
Approximate Value
of Work (Rs. In
Lakhs)
4568.73 4751.84
3 NSP - NSLBC – APWSIP – Rehabilitation
and modernization of 21st Main Branch Canal
from KM.0.000 to KM. 52.300 of
Nagarjunasagar Lal Bahadur Canal, A.P,
India. (Package No.LC KMM -6)
Bid Security
( Rs. In Lakhs) 45.69 47.52
Approximate Value
of Work (Rs. In
Lakhs)
5816.09 6048.17
4 NSP - NSLBC – APWSIP – Rehabilitation
and modernization of 21st MBC from
KM.52.300 to KM. 117.007 of
Nagarjunasagar Lal Bahadur Canal, A.P,
India. (Package No.LC KRI -7)
Bid Security
( Rs. In Lakhs) 58.16 60.48
Sd/-Superintending Engineer,
NSLBC O&M Circle,
Tekulapally, KHAMMAM.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
184
CORRIGENDUM
Following corrigendum to the item Division-9 shot creating in para (V) of application of
shot crete under Section-5 Specifications.
For
Read
Next “welded wire mesh of size 100
MM X 100 MM 5 MM be nailed,
butting with shotcrete. Binding wire
of 20 gauge or 24 gauge be used for
binding of wire mesh panels.
Next “welded wire mesh of size
50 MM X 50 MM 5 MM be nailed,
butting with shotcrete. Binding
wire of 20 gauge or 24 gauge be
used for binding of wire mesh
panels.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
185
MINUTES OF PREBID CONFERENCE (APPROVED)
01) Minutes of prebid conference held on 12.02.2008.
02) NAME OF WORK : NSP - NSLBC – APWSIP – Rehabilitation and
modernization of 21st Main Branch Canal from KM.0.000 to
KM. 52.300 Nagarasagar Lal Bahadur Canal, A.P,
India. Package No. LC-KMM- 6
03) i)Tender Notice No./Bid.No.9/2007-08, dt.17.01.2008.
ii) Notification No. DB/D6/TN/113M, Dt. 05-02-2008.
04) OFFICERS PRESENT:-
1. Sri M.Ramachandraiah : Chief Engineer,
N.S.Project, Hill Colony.
2. Sri B.V.Siddhartha : Superintending Engineer,
NSLBC (O&M) Circle,
Tekulapally.
3. Sri S.M.Subrahmanyeswara Rao : Dy.Superintending Engineer,
NSLBC (O&M) Circle,
Tekulapally.
4. Sri V.Veera Raju : Executive Engineer,
NSLBC (O&M) Division,
Tekulapally & Kallur.
5. Sri T.Jagdish Babu : Executive Engineer,
NSLBC Monitoring Division,
Tekulapally.
05) BIDDERS PRESENT:-
None of Bidder is present.
A prebid conference was convened in the chambers of the Superintending Engineer, NSLBC
(O&M) Circle, Tekulapally on 12.02.2008 at 11.00 AM as per programme conveyed as per the
modified date vide Notification No. DB/D6/TN/113M, Dt.5.2.2008 for the said work. Only Two
companies have purchased Bid documents till to date. But none of bidder has present during prebid
meeting.
Sd/-Project Director,
PPMU-APWSIP, Hyderabad.
Sd/ CONTRACTOR / BIDDER Sd/- SUPERINTENDING ENGINEER
186
OFFICE OF THE SUPERINTENDING ENGINEER:NSLBC:O&M CIRCLE : TEKULAPALLY.
…
Notification No.DB/D.6/T.N./ 113 M date: 05.02.2008.
Sub:- APWSIP – TENDERS – Postponement of Pre-bid meeting
Notification Issued – Reg.
Ref:-T.O. Tender Notice.No.9 SE(T)/07-08, dt.17.01.2008.
…
The Pre-bid meeting proposed to be held with the bidders on 05.02.2008 @ 11.00 Hrs.
in the chambers of the Superintending Engineer, NSLBC (O&M) Circle, Tekulapally,
Khammam is here by postponed and the revised date of the same meeting is proposed to
conduct on 12.02.2008 @ 11.00 Hrs. @ the same place.
Sd/-
for Superintending Engineer,
NSLBC (O&M) Circle:Tekulapally,
Khammam.
To
All bidders.
Notice Board.