Bi-annual Environmental Monitoring Report Project Number: 39176 July 2017 Republic of Azerbaijan: Road Network Development Program: Project I Masalli to Astara Motorway (Financed by the Asian Development Bank) Report 12: 1 st January 2017 to 30 th June 2017 Part II - Loan 2831 AZE, Covering Sections B & C Prepared by Azeravtoyol OJSC for the Asian Development Bank (ADB). The bi-annual environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Transcript of Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for...

Page 1: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Bi-annual Environmental Monitoring Report

Project Number: 39176

July 2017

Republic of Azerbaijan: Road Network Development Program: Project I Masalli to Astara Motorway

(Financed by the Asian Development Bank)

Report 12: 1st January 2017 to 30th June 2017 Part II - Loan 2831 AZE, Covering Sections B & C

Prepared by Azeravtoyol OJSC for the Asian Development Bank (ADB).

The bi-annual environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

Page 2: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii

CURRENCY EQUIVALENTS (As of 1 June 2017)

Currency Unit – Azerbaijan New Manat (AZN)

AZN 1.00 = USD 0.5926 USD 1.00 = AZN 1.6876

ABBREVIATIONS

ADB – Asian Development Bank AAY – AzerAvtoYol AZN – Azerbaijan New Manat BOD – Biological Oxygen Demand EIA – Environmental Impact Assessment EMP – Environmental Management Plan EPM – Environmental Protection Manager EPP – Environmental Protection Plan GRM – Grievance Redress Mechanism IPC – Interim Payment Certificate MENR – Ministry of Ecology and Natural Resources PIU – Project Implementation Unit PMC – Project Management Consultant PPE – Personal Protective Equipment SSEMP – Site-Specific Environmental Management Plan STD – Sexually Transmitted Disease

WEIGHTS AND MEASURES m – Metre km – Kilometre

Page 3: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) iii

TABLE OF CONTENTS

I. INTRODUCTION ...................................................................................................... 6

A. Introduction to Project .................................................................................... 6

B. Objectives of Biannual Environmental Reporting ............................................ 7

C. Methodology .................................................................................................. 7

D. Construction Activities and Project Progress during previous six months ....... 7

E. Project organization and environmental management team ........................... 9

F. Relationships with Contractors, owner, lender, etc. ...................................... 10

II. ENVIRONMENTAL MONITORING ..........................................................................11

A. Status ......................................................................................................... 11

B. Results ......................................................................................................... 11

C. Action ......................................................................................................... 13

III. ENVIRONMENTAL MANAGEMENT........................................................................14

A. Status ......................................................................................................... 14

B. Documents ................................................................................................... 17

C. Inspections and Audits ................................................................................. 18

D. Non-Compliance and Corrective Actions ...................................................... 18

E. Consultations and Complaints ...................................................................... 22

F. Emerging Issues .......................................................................................... 29

G. Conclusions ................................................................................................. 30

IV. APPENDICES .........................................................................................................31

Appendix 1: Environmental Monitoring Results ..................................................... 31

Appendix 2: List of participants at public consultations and Minutes of Meeting .... 70

Page 4: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) iv

LIST OF FIGURES

FIGURE 1: SECTION B CONTRACTOR’S MANAGEMENT STRUCTURE ............................... 9

FIGURE 2: SECTION C CONTRACTOR’S MANAGEMENT STRUCTURE ............................... 9

FIGURE 3: LOCAL ROAD NOW PASSES OVER THE PROJECT ROAD IN HAFTONI, BUT IS NOT YET SURFACED (L), AND PATCHED LOCAL ROAD IN HAFTONI (R) .........14

FIGURE 4: “HIRKAN FOREST” ECOLOGICAL RECOVERY (L) AND UNFORTUNATE DAMMING OF THE STREAM (R) ............................................................................15

FIGURE 5: GOOD CONDITIONS AT THE “OFFICE CAMP” IN BURJALI VILLAGE .................16

FIGURE 6: INSPECTION OF PAPERWORK ON SECTION B ..................................................17

FIGURE 7: NEGLECTED OIL STORAGE AREA REQUIRING CLEANING AT THE SECTION B CAMP DURING PREVIOUS REPORTING PERIOD (L) AND IMPROVED SITUATION DURING PRESENT REPORTING PERIOD (R) ..................................19

FIGURE 8: BUND PROBLEMS AT MAIN ASPHALT PLANT DURING PREVIOUS REPORTING PERIOD (L) AND IMPROVED SITUATION DURING PRESENT REPORTING PERIOD (R) .............................................................................................................19

FIGURE 9: UNPRESSURISED FIRE EXTINGUISHER (L) AND NON-COMPLIANT ASPHALT STORAGE (R) .........................................................................................................19

FIGURE 10: GOOD CONDITIONS ON THE SECTION C ALIGNMENT ...................................20

FIGURE 11: BUND PROBLEMS AT MAIN ASPHALT PLANT DURING PREVIOUS REPORTING PERIOD (L) AND SOMEWHAT IMPROVED SITUATION DURING PRESENT REPORTING PERIOD (R) .....................................................................21

FIGURE 12: NEW BUND PROBLEMS AT THE SECTION C ASPHALT PLANT (L) THOUGH FUEL STORAGE AREA WAS GENERALLY IN EXCELLENT ORDER (R)..............21

FIGURE 13: PUBLIC CONSULTATIONS (L: 2ND MARCH; R: 11TH JUNE) ................................22

FIGURE 14: PUBLIC CONSULTATION (12TH JUNE) ...............................................................23

Page 5: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) v

LIST OF TABLES

TABLE 1: MONTHLY PROGRESS OF THE SECTION B CONTRACTOR DURING THE LAST SIX MONTHS ........................................................................................................... 8

TABLE 2: MONTHLY PROGRESS OF THE SECTION C CONTRACTOR DURING THE LAST SIX MONTHS ........................................................................................................... 9

TABLE 3: INSTRUCTIONS TO SECTION B CONTRACTOR DURING THE LAST SIX MONTHS ...............................................................................................................................20

TABLE 4: INSTRUCTIONS TO SECTION C CONTRACTOR DURING THE LAST SIX MONTHS .................................................................................................................21

TABLE 5: GRIEVANCE REGISTER – SECTION B ...................................................................24

TABLE 6: GRIEVANCE REGISTER – SECTION C...................................................................27

TABLE 7: SECTION B ACTION PLAN ......................................................................................29

TABLE 8: SECTION C ACTION PLAN ......................................................................................29

Page 6: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 6

I. INTRODUCTION

A. Introduction to Project

1. The Masalli to Astara Motorway is a new 62 km motorway section of the M-3 highway corridor that links the capital city, Baku, to the south of the country and the town of Astara, which straddles the Azeri/Iranian border. The project is split into three sections; A (0 - 22.15 km), B (22.15 - 45.00 km), and C (45.00 – 62.14 km).

2. The Executing Agency for the project is the Azeravtoyol Open Joint Stock Company1 (abbreviated to AAY in the present report).

3. Following screening2, an Environmental Impact Assessment (EIA) was carried out for the project in 2007. The EIA report was approved by AAY and ADB, and has served as a basis for the development of the specification and contract documents, and for the preparation and pricing of the Contractor Environmental Management Plan (EMP).

4. The Engineer appointed by AAY is Nippon Koei UK Ltd. The construction contract for Section B was awarded to Özgün Construction Industry and Trading Co. Inc. Section C was awarded to Polat LLC in November 2013.

5. The first bi-annual environmental monitoring report covered the period 1st March to 31st August 2011 (Section A only). Subsequent bi-annual environmental monitoring reports covered the following periods:

• Second: 1st September 2011 to 31st May 20123.

• Third: 1st June 2011 to 31st December 2012.

• Fourth: 1st January 2013 to 30th June 2013.

• Fifth: 1st July 2013 to 31st December 2013.

• Sixth: 1st January 2014 to 30th June 2014.

• Seventh: 1st July 2014 to 31st December 2014.

• Eighth: 1st January to 30th June 2015.

• Ninth: 1st July 2015 to 31st December 2015.

• Tenth: 1st January 2016 to June 2016.

• Eleventh: 1st July 2016 to 31st December 2016.

• Twelfth: 1st January 2017 to 30th June 2017.

6. From the Fifth issue onwards, the report has been split according to loan source into two; Part I, covering Section A and Lenkaran Bridge (Loan 2354 AZE), and Part II, covering Sections B & C (Loan 2831 AZE).

1 Formerly called “The Road Transport Service Department” (The change of name took effect on 22nd February 2007), and then called Azeri Road Service from 2007 to 2015.

2 Screening was carried out according to ADB’s Environment Policy and Operations Manual (OM) 20. The project was classified as Category A, principally due to the anticipated resettlement issues triggering the ADB Policy on Involuntary Resettlement (1995).

3 Due to the extended period of inactivity during the winter season, and so that the present report includes the results of the ADB mid-term review

Page 7: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 7

7. Key milestones relating to mobilisation are summarised below:

• Overall Contract agreement: 15th Dec 2010.

• The Engineer mobilised on 21st February 2011.

• Section B Contract Agreement: 29th March 2013.

• Notice to Commence for Section B was issued on 18th June 2013.

• Earthworks began on Section B in August 2013.

• Section C Contract Agreement: 31st October 2013.

• Notice to Commence for Section C was issued on 27th January 2014.

B. Objectives of Biannual Environmental Reporting

8. The purpose of the Biannual Environmental Monitoring Reports is to provide a summary of the key issues relating to environmental management over the past six months. The summary includes an update on overall project progress, the status of SSEMP implementation, any progress made with environmental management, environmental monitoring results, and other relevant issues such as non-compliance and corrective actions, and monitoring of the Grievance Redress Mechanism (GRM).

9. The Reports are prepared by AAY and are intended to inform ADB and any other interested parties of the status of environmental management of the project. The Reports are summaries; more detailed information is included in the monthly and quarterly reports prepared by the Contractors and the Engineer.

C. Methodology

10. The Biannual Environmental Monitoring Reports are prepared by reviewing and extracting key information from a number of sources, as follows:

• Contractors’ Quarterly Environmental Management Reports;

• Contractors’ Grievance Registers;

• Engineer’s Quarterly and Monthly Progress Reports;

• Engineer’s Environmental Specialist’s Field Reports;

• Monthly instrumented monitoring results;

• Ad Hoc reports from the Contractors on training and public consultation; and

• Correspondence between AAY, Engineer and Contractors relating to environmental and social issues.

11. In addition, some information and opinion in the reports results from site visits, technical meetings and public meetings and interviews over the preceding six months.

D. Construction Activities and Project Progress dur ing previous six months

12. Key milestones and construction activities relating to the past six months’ work are summarised below:

Section B

• Table 1 below shows the Contractor's monthly progress throughout the current reporting period.

Page 8: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 8

• The Contractor made substantial progress during the reporting period and major works accomplished are: (i) embankment and pavement works of main road (100% complete), (ii) access roads of 4 flyover bridges including asphalt pavement (100% complete), (iii) embankment works of access roads and ramps of two interchanges (80% complete), (iv) Remaining culvert construction, (iv) embankment slope protection works (80% complete), (v) bridge construction works (98% complete).

• New Jersey Barrier along central median (90% complete), other road furniture materials procurement in progress.

• Utility relocations (100% complete).

• A total of 23 Interim Payment Certificates (IPC) have been issued.

Table 1: Monthly Progress of the Section B Contract or during the last Six Months

Month Progress (%)

January 2017 0.43

February 2017 0.24

March 2017 1..01

April 2017 4.93

May 2017 2.29

June 2017 1.52

Section C

• Table 2 below shows the Contractor's monthly progress throughout the current reporting period.

• During the first 3 months of the reporting period there were limited activities due to the wet condition of materials and standing water within the working areas.

• Since April all activities resumed and major works accomplished during the reporting period are: (i) Rockfilling (100% complete), (ii) Embankment construction (75% complete), (iii) Granular and asphalt pavement works (70% complete), (iv) Embankment slope protection works (75% complete), and (v) Median drainage works (85% complete).

• Construction works for minor elements of bridges and approach slabs are ongoing (overall 95% complete)

• Utility relocation works are complete except two steel truss tower additionally required at access of the bridge no.3.

• New Jersey Barrier along central median (70% complete).

• A total of 21 Interim Payment Certificates (IPC) has been issued.

Page 9: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 9

Table 2: Monthly Progress of the Section C Contract or during the last Six Months

Month Progress (%)

January 2017 0.75

February 2017 0.67

March 2017 0.64

April 2017 0.97

May 2017 2.76

June 2017 1.99

E. Project organization and environmental managemen t team

13. There has been no change to the organization of the environmental management team within the Contractors, Engineer or the Owner (AAY) over the past six months. For completeness, the Contractors’ organisational structures are shown below.

Figure 1: Section B Contractor’s Management Structu re

Figure 2: Section C Contractor’s Management Structu re

Page 10: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 10

F. Relationships with Contractors, owner, lender, e tc.

14. The relationships between contractors, Engineer, Owner, and Lender are considered normal working relationships.

15. At the working level, communication with regards to environmental issues remains good.

Page 11: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 11

II. ENVIRONMENTAL MONITORING

A. Status

Section B

16. Regular monthly monitoring has been carried out in accordance with the SSEMP throughout the current reporting period, with the exception of at the Hirkan Forest, where only sampling set was taken (June 2017) during the reporting period.

17. The sampling has been carried out by Platan Group, who then send the samples for analysis at the Central Laboratory of the Ministry of Ecology and National Resources of Azerbaijan.

Section C

18. Regular monthly monitoring has been carried out in accordance with the SSEMP throughout the current reporting period.

19. The sampling has been carried out by Platan Group, who then send the samples for analysis at the Central Laboratory of the Ministry of Ecology and National Resources of Azerbaijan.

B. Results

Section B

20. Most water quality monitoring results met the Azeri national standards during the present reporting period, however several results contravened the standards. The contraventions as well as some further observations on the results are discussed below: The full results are provided in Appendix 1.

• pH readings were within the limits at all locations for most of the reporting period, with the following exceptions:

o The Lakar and Ogru Rivers were rather acidic during January; and

o The Gamishli River was rather acidic during May.

o As has been the case in the past, the downstream readings generally show a slightly higher pH than upstream readings, indicating that the acidic conditions are not as a result of the project works.

• DO was below the permitted lower threshold of the Azeri standards for the majority of the reporting period. This has occurred often on all sections and is not considered a significant issue due to the high variability of DO within aquatic environments, and the multiple factors that influence levels, even on a daily basis.

• Turbidity was lower at most locations and at most times in comparison to both the pre-construction monitoring and to previous reporting periods, and were well below the applicable limits. Strangely, TSS levels, whilst often low, have sometimes been fairly high at the same time that turbidity has been low (e.g. May 2017). Whilst a strong linear correlation between turbidity and TSS usually exists, and could point to sampling/analysis errors, certain conditions can lead to a reduction in the strength of the correlation.

Page 12: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 12

• Nitrates / Nitrites and other major ions are well below the standards at all locations, and oil and grease levels are constant throughout the reporting period at a very low level, well below the limits.

• As is usual for the project area due to the prevailing lack of sewage treatment, the faecal coliform levels at all stations are generally high (but below the standards). The project is not thought to be responsible for the continued elevated levels.

21. The water monitoring results for the stream bordering the Hirkan Forest Area continue to be of concern, with very high faecal coliform levels. It remains clear that these results are due to the use of the boundary stream by the adjacent village as both a sewer and a waste dumping area.

22. All air quality monitoring results for all determinants and all monitoring stations were well below Azeri national standards during the present reporting period. As would be expected, dust levels rose slightly throughout the monitoring period, in sync with the changing seasons, however they remained below the limits even in June. Air quality at Hirkan Forest remained very good during the single monitoring event.

23. Noise and vibration monitoring results were all below the permitted limits during the reporting period. Noise levels were approaching the limits at Yuxari Nuvadi at times, but, as has been discussed in previous reports, the principal noise sources in this area are not project-related.

Section C

24. Most water quality monitoring results met the Azeri national standards during the present reporting period, however several results contravened the standards. The contraventions as well as some further observations on the results are discussed below: The full results are provided in Appendix 1.

• pH fluctuated considerably between the sampling months, but not much between stations. This suggests that factors such as temperature and rainfall may have been the major influence in variation of pH.

• As with the previous reporting period, BOD, turbidity and TSS were generally low though one reading at one location (Penser 1, downstream in April) was ever so slightly over the limit for TSS.

• Sulphates, Nitrates / Nitrites and oil and grease results are all well below the standards at all locations.

• Faecal coliform levels remain generally rather high at all stations, as they have been on all sections of the project throughout.

25. All air quality monitoring results for all determinants and all monitoring stations were below Azeri national standards during the present reporting period, and as with Section B, dust levels rose slightly during the latter months.

26. Noise and vibration monitoring results were all below the permitted limits during the reporting period. In common with Section B, noise levels were approaching the limits at Yuxari Nuvadi on occasion, but, as has been discussed in previous reports, the principal noise sources in this area are not project-related.

Page 13: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 13

C. Action

27. No action on site is required on either Section B or Section C in response to the monitoring results from the present reporting period.

Page 14: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 14

III. ENVIRONMENTAL MANAGEMENT

A. Status

28. Environmental management of the project for the Section B is described in two parts; one covers general project activities and the second is dedicated to works around Hirkan forest area. This is due to the sensitivity and importance of the area requiring special attention.

Section B

29. With occasional exceptions, environmental management on Section B has continued to be of an acceptable standard during the present reporting period, and has improved somewhat since the previous reporting period. Any non-compliances noted during site audits are usually resolved quickly (see Part D below) however, repetitions of similar non-compliances have continued during the present reporting period.

30. The physical mitigation measures set out in the SSEMP are generally all constructed and functioning as designed (with the exception of the asphalt plant – see Part D below). General cleanliness and waste management has improved since the previous reporting period.

31. On the alignment environmental management was compliant with the SSEMP, and the site was clean, tidy, and well maintained. The situation was improved over previous reporting periods, and there were no isolated problems of waste management as have been frequently observed in the past. Unusually, no Health and Safety problems were observed, despite significant works being carried out.

32. The local road crossings along Section B have still not been completed and asphalted, however the situation is improved compared to the previous reporting period, during which several of the local roads and crossing points were observed to be non-compliant. During the present reporting period, all local roads crossing the alignment, whilst not tarred, were well graded and compacted, and were therefore passable.

33. The road through Haftoni village has been improved via filling of the potholes, but still requires a more permanent fix; this will presumably be included within the overall surfacing work for the local road crossing, which now passes over the new bridge (Figure 3). The fact that the Section B camp can now be accessed directly from the project road should now mean that traffic through Haftoni will be minimal from hereon in.

Figure 3: Local road now passes over the project ro ad in Haftoni, but is not yet surfaced (L), and patched local road in Haftoni (R)

Page 15: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 15

34. There have been no accidents during the reporting period involving the public, and none involving project workers. HIV and other on the job training has continued regularly throughout the reporting period.

35. The sole borrow pit operated by the Section B Contractor is Qrunba, situated just to the west of the project alignment to the south of Haftoni village. The borrow pit is no longer being exploited by the Contractor, however the current status with respect to ownership/licencing is unclear; it is understood that the local executive powers wish to continue to operate the site as a borrow pit for other projects/requirements, and have therefore prevented the Contractor from carrying out reinstatement activities.

36. No topsoil has been stripped during the present reporting period. Most of the material previously stockpiled at locations along the RoW is now being used for final reshaping and reinstatement alongside the road shoulder.

37. The issue of stockpiles and reinstatement will be closely examined during the next, final report.

Hirkan Forest area

38. During the previous audit, it was observed that the embankment and asphalting was complete at the “Hirkan Forest” area, with only installation of road furniture and the installation of permanent noise barriers remaining to be carried out. During the present reporting period, there has been little further progress. Likewise, previous audits reported that the forest was recovering well from the clearance and drainage works, and that ecological recovery continues, and again, the situation remains unchanged (Figure 4). Regretfully, the local population continues to use the SE corner of the forest as a rubbish dump, and has dammed the stream.

Figure 4: “Hirkan Forest” Ecological Recovery (L) a nd unfortunate damming of the stream (R)

39. Other than the issues described above, which are outside the control and responsibilities of the Contractor, environmental management in the Hirkan Forest area is good.

Page 16: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 16

Section C

40. The Section C Contractor’s site performance remains good, and is largely compliant with the provisions of the SSEMP. As usual, the Contractor has made some efforts over the past months to address the non-compliances that were observed during the previous site audits, and in general, environmental management was of a comparatively good standard.

41. As with Section B, the works on the alignment have advanced well over the past six months, and all works observed on site during audits were being carried out in adherence to the SSEMP.

42. In common with Section B, the diversion/local road crossings remain generally unpaved, but were found to be in passable condition.

43. There have been no accidents during the reporting period involving the public, and none involving project workers. HIV and other on the job training has continued regularly throughout the reporting period.

44. The Contractor’s “office camp” (in Burjali village) is generally very well managed. The camp area is clean and tidy, senior staff accommodation is of a good standard, and the welding area is well equipped. Health and safety standards are also good.

Figure 5: Good Conditions at the “office camp” in B urjali village

45. At the Contractor’s “plant camp” (at km 33+000 / Yuxari Nuvadi village), the facilities are of a good standard in general, and most non-compliances previously observed have been satisfactorily solved, though one new non-compliance arose, and this is discussed further in Part D below. As with the “office camp”, the Contractor generally resolved any problems raised by the Engineer within an acceptable timeframe.

46. The sole borrow pit operated by the Section C Contractor is Rvo, situated around 10 km west of Lenkaran, alongside the Lenkaran River and close to the Lerik highway. The borrow pit is no longer being exploited by the Contractor, however as is common in the area, the local executive powers have granted use of the site to more than one contractor/company. Reinstatement of the site is therefore challenging, due to its ongoing use by third parties.

47. It should be noted that all required local and national level permits were obtained prior to the opening/operation of each borrow pit in Sections B and C, and furthermore, stand-alone borrow pit management plans were developed to ensure adequate environmental management during opening, operation and closure of the sites.

Page 17: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 17

48. The reinstatement status described above and for Section B, whilst not satisfactory from a best practice standpoint, are entirely within the bounds of the national environmental management and legal systems, which devolve most management and decision-making to the local executive powers.

49. No topsoil has been stripped during the present reporting period. Most of the material previously stockpiled at locations along the RoW is now being used for final reshaping and reinstatement alongside the road shoulder.

50. The issue of stockpiles and reinstatement will be closely examined during the next, final report.

B. Documents

Section B

51. Reporting for Section B is compliant, with the Quarterly Environmental Reports and weekly audits being carried out/submitted correctly and on time. An inspection of site documentation in May 2017 showed that all relevant paperwork, including the Grievance Register, was present at the site office, and maintained up to date.

Figure 6: Inspection of Paperwork on Section B

Section C

52. Inspection showed that Section C reporting and paperwork is similarly compliant as with Section B.

Page 18: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 18

C. Inspections and Audits

53. There were no inspections or audits from the ADB’s international staff during the present reporting period, however ADB national specialists visited the site on several occasions.

54. The Section B & C contractor’s EPMs conduct ad hoc site visits on a daily basis, with a full audit of all sites once a week.

55. The Engineer’s National Environmental Specialist is based at the Section C camp area and he visits all sites on a twice-weekly basis, with additional ad hoc visits as required. The Engineer’s National Environmental Specialist also accompanies the Section B & C contractor’s EPMs on their site audits.

56. During the present reporting period The Engineer’s International Environmental Specialist visited construction sites between the 12th-14th May 2017.

57. The Executing Agency has made a number of ad hoc visits to site as required.

D. Non-Compliance and Corrective Actions

Section B

58. The Contractor has again significantly advanced the construction works on site over the past six months, and has mainly done so within the bounds of the SSEMP; works on the alignment were generally compliant, and the site was for the most part kept clean, tidy, and well maintained. As has been discussed in the preceding sections, the overall level of management has been improved over the past six months when compared to the previous reporting period.

59. The general situation at the construction camp was improved since the previous audit, with equipment stored in a good fashion and most of the previous non-compliances addressed satisfactorily. These efforts include:

• Closing up and reinstating the area in the eastern corner of the camp where the septic tanks were previously leaking;

• The cleaning of the oil storage area, which was observed to be in a better condition than previously (Figure 7);

• Bunding repairs (Figure 8); and

• Removal of large quantities of equipment and waste previously reported at the site.

60. Nevertheless, some non-compliances did arise during the reporting period:

• The prime coat asphalt plant located adjacent to the vehicle wash station was observed to have breaches in the bund where pipes pass through it, and a bitumen tank was located both outside the bund, and below ground level, where the opportunity for ground and water contamination is present (Figure 9);

• The bund wall at the main asphalt plant that was previously observed to have significant breaches was repaired, however a new breach appeared; and

• Fire extinguisher checks again revealed failures (Figure 9).

61. The above issues were addressed with varying levels of satisfaction, and follow up in some areas is ongoing.

Page 19: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 19

Figure 7: Neglected oil storage area requiring clea ning at the Section B Camp during previous reporting period (L) and improved situatio n during present reporting period (R)

Figure 8: Bund problems at main asphalt plant durin g previous reporting period (L) and improved situation during present reporting period (R)

Figure 9: Unpressurised fire extinguisher (L) and n on-compliant asphalt storage (R)

Page 20: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 20

Hirkan Forest Area

62. There were no non-compliances observed at the Hirkan Forest area during the present reporting period. As described in preceding sections, the embankment and road works are now completed in the area, and the temporary noise barriers have been removed. Ecological recovery appears to be progressing well.

Table 3: Instructions to Section B Contractor durin g the last Six Months

No Date Description of Instruction 1 19/05/2017 Letter No BNK1093

Environmental Management Issues

Section C

63. The Section C Contractor’s site performance remains good, and is largely compliant with the provisions of the SSEMP. As always, the Contractor has made an effort over the past months to address the non-compliances that were observed during the previous reporting period, and only a few new minor non-compliances were noted.

64. No significant problems were noted on the alignment during the present reporting period.

Figure 10: Good Conditions on the Section C Alignme nt

65. The outstanding non-compliances at the two construction camps from the previous visit were inspected; some were found to have been resolved (for example the labourer accommodation had been somewhat improved) and only one notable non-compliance was observed during the present reporting period; whilst the previously observed breaches in the asphalt plant bund wall had been repaired (Figure 11), elsewhere in the bund, pipes had been passed through the bund wall at low-level (Figure 12). This clearly negates the purpose of the bund and required immediate attention.

Page 21: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 21

Figure 11: Bund problems at main asphalt plant duri ng previous reporting period (L) and somewhat improved situation during present reportin g period (R)

Figure 12: New bund problems at the Section C Aspha lt Plant (L) though fuel storage area was generally in excellent order (R)

66. The concrete plant, workshop, crushing area and oil change area were all in good condition and operating very well. Overall, both the “office camp” and the “plant camp” were in good condition and substantially compliant with the provisions of the SSEMP.

Table 4: Instructions to Section C Contractor Durin g the last Six Months

No Date Description of Instruction 1 16/05/2017 Letter No CNK749

Environmental management issues

Page 22: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 22

E. Consultations and Complaints

Section B

67. Previous reports discussed changes to the public consultation meeting format and frequency, which were aimed at making them more meaningful. Despite sustained pressure from the Engineer on the Contractor, the quality of the public consultations has not been significantly improved. This is entirely attributable to a lax attitude from the EPM, and the situation is a disappointment.

68. Despite the above disappointment, consultation meetings were held on the 2nd March (Dasdaligjar village) and 11th June 2017 (Haftoni and Laj villages), and they offered a chance to update local community leaders on the progress of the works and the expected finishing dates, and to remind them of the grievance redress mechanism.

Figure 13: Public Consultations (L: 2 nd March; R: 11 th June)

69. Lists of the participants were provided to the Engineer within monthly and quarterly reports, and these are provided in Appendix 2, along with the Minutes of Meeting.

70. One new grievance was lodged during the present reporting period. The complaint related to deterioration of local roads, and the grievance was addressed by the Contractor. A summary of all grievances to date and how they were resolved is provided in Table 5 below.

Page 23: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 23

Section C

71. The current situation regarding public consultations is the same for Section C as it is for Section B.

72. Two consultation meetings were held during the present reporting period – on the 7th March and 12th June 2017, both with Yuxari Nuvadi village.

Figure 14: Public Consultation (12 th June)

73. Lists of the participants were provided to the Engineer within monthly and quarterly reports, and these are provided in Appendix 2, along with the Minutes of Meeting.

74. Two new grievances were reported on Section C during the past six months. These grievances were recorded outside of the consultation meetings, and related to the blocking of access by the works. A summary of all grievances to date and their status is provided in Table 6 below.

Page 24: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 24

Table 5: Grievance Register – Section B

No Tranche Location Date Received

How grievance was received Complainant Description of the

issues/complaints Contact details

Notes, undertaken actions Status

1 Section B Haftoni Village 15.08.2013

From local Municipality

Rovshen Zeynalov

During the delivery of materials construction vehicles caused dust on local roads

050-546-86-20

Contractor appointed the water truck on that roads and the local roads had been watered by sprinkler truck on July, August and during dry weather periods every hour

Solved

2 Section B Haftoni Village 26.08.2013

From local Municipality

Rovshen Zeynalov

Contractor had been requested for recruited workers from close communities

050-546-86-20

Request was accepted and a 15 workers recruited from close communities

Solved

3 Section B Laj Village 04.07.2014 From local Executive Representative

Cefer Bayramov Contractor was requested to excavate the village channel for rain water

070-203-94-69 Request was accepted and the Laj village channel excavated for rain water

Solved

4 Section B Laj Village 09.10.2014 From local Executive Representative

Cefer Bayramov Village access road near the Bridge No 3 is destroyed

070-203-94-69 Village access road near the Bridge No 3 is repaired

Solved

5 Section B Laj Village 24.11.2014 In person Name unknown Kargalan village access road near the Bridge No 4 is destroyed

TBC Road has been repaired Solved

6 Section B Kargalan Village

30.11.2014 In meeting Vaqif Aliyev Village access road near the Bridge No 4 is destroyed

TBC Road has been repaired Solved

7 Section B Kargalan Village

10.04.2015 GRM Samed Dadashov Sapnakaran village access road near the B ridge No 1 Interchange is destroyed

TBC Road has been repaired Solved

Page 25: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 25

No Tranche Location Date Received

How grievance was received Complainant Description of the

issues/complaints Contact details

Notes, undertaken actions Status

8 Section B Kargalan Village

12.06.2015 GRM Aslan Xelilov Kargelan village access road is destroyed

TBC Road has been repaired Solved

9 Section B Haftoni Village

16.10.2015 In meeting Kenan Bagirzade

Haftoni settlement access road near the Bridge No 4 is destroyed

TBC Road has been repaired Solved

10 Section B Qrunba Village

01.12.2015 GRM Elekberov Firdovsi Existing culverts near the Bridge No 5 are not enough for rain water flow

TBC

It was promised that another big size of culverts will be placed near the Bridge No 5

Ongoing

11 Section B Haftoni Village

20.05.2016 In meeting Zeynal Haydarov

The Haftoni settlement road is destroyed

TBC

Haftoni settlement road is repaired

Solved

12 Section B

Yuxari

Nuvedi Village 20.05.2016 In meeting Cesaret Suvarov

During the material transportation the contractor heavy trucks making dust near the houses at Yuxari Nuvedi village

TBC

Contractor increased watering by sprinkler trucks during dry weather periods to every 2 hours

Solved

13 Section B

Yuxari

Nuvedi Village

20.05.2016 In meeting Cesaret Suvarov

Domestic waste was littered near the Bridge No 5 temporary camp at Yuxari Nuvedi village.

TBC

Domestic waste was cleaned up and the area was reinstated Solved

14 Section B Haftoni Village

20.09.2016 In meeting Orxan Azimov

The Haftoni road near Bridge No 4 is destroyed. When will the Contractor repair the village access road?

TBC

Haftoni settlement road near the Bridge No 4 is repaired

Solved

15 Section B Haftoni Village

20.09.2016 c

Xudaverdiev Farid During the material transportation the contractor heavy trucks making dust near the houses at camp entrance. When will the contractor

TBC

Short section at camp entrance was asphalted and water trucks was increased at this area

Solved

Page 26: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 26

No Tranche Location Date Received

How grievance was received Complainant Description of the

issues/complaints Contact details

Notes, undertaken actions Status

repair this short section with asphalt and increase the number of water trucks at this area?

16 Section B Haftoni Village

20.11.2016 GRM NA

The Haftoni Laj road is destroyed. When will the Contractor repair the village access road?

TBC

The Laj village road near the Bridge No 3 was repaired.

Solved

17 Section B Dasdaligjar village

02.03.2017 In meeting Nazim

Emenullayev

When the will contractor repair the Dasdaligjar village road near the Bridge No 8?

050-343-00-45

The Dasdaligjar village road near the Bridge No was repaired.

Solved

Page 27: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 27

Table 6: Grievance Register – Section C

No Tranche Location Date Received

How grievance was received Complainant Description of the

issues/complaints Contact details

Notes, undertaken actions Status

1 Section C

Between km

60+950 & 61+400

21.07.2014 Directly from landowners

Names unknown

During the site clearance the contractor was interrupted by a land owner between Ch. 60+950 ~ 61+400. They claimed that they had not been reimbursed for all of his land

Unknown

Contractor has informed Engineer by its official letter MASAC-107/14 dated 22 July 2014

Contractor waiting for answer from Engineer

2 Section C

Yuxari Nuvadi village

10.09.2014 From local Municipality

Names unknown

During the installation of Crushing plant there was a noise at night time at Plant Yard

Unknown

Contractor has been reminded about night time working restrictions

Solved

3 Section C Shiyakaran

village 18.04.2015 in a meeting Ayaz Rzayev Village access road is destroyed at bridge No 2

Unknown Road has been repaired Solved

4 Section C

Yuxari Nuvadi village

14.05.2015 unknown Izam Efendiyev During the regular material transportation Yuxari Nuvedi village access road is destroyed

Unknown Road has been asphalted Solved

5 Section C 20.05.2016 in a meeting Cesaret Suvarov

During the material transportation the contractor trucks are making dust near the contractor Plant Yard. Please water this area intensively during the summer periods.

Unknown

Contractor increased watering by sprinkler trucks during dry weather periods to every 2 hours

Solved

6 Section C 20.05.2016 in a meeting Rustem Gurbanov

During the material transportation the contractor trucks are making dust near Shiyakaran village.

Unknown

Contractor increased watering by sprinkler trucks during dry weather periods to every 2 hours

Solved

Page 28: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 28

No Tranche Location Date Received

How grievance was received Complainant Description of the

issues/complaints Contact details

Notes, undertaken actions Status

7 Section C

Kolatan, Sahagaci and Kakalos villages

10 June 2017

By local Municipality on behalf of local villages` people

Local people People needs access road to reach their ploughed field parallel with road alignment

Local Municipality

The arisen issue in the grievance was reviewed and that access road is under construction process and is in the final stage of completion.

In the solution stage

8 Section C Siyekeran village

10 June 2017

By local Municipality on behalf of local village people

Local people People needs access road to reach their ploughed field parallel with road alignment

Local Municipality

The arisen issue in the grievance was reviewed and that access road is under construction process and is in the final stage of completion.

In the solution stage

9 Section C Ercivan village

10 June 2017

By local people letter No 758

A group of village people

People needs access road to reach their ploughed field parallel with road alignment

Local Municipality

The arisen issue in the grievance was reviewed and that access road is under construction process and is in the final stage of completion.

In the solution stage

Page 29: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 29

F. Emerging Issues

75. There are currently no emerging site issues, however it should be mentioned that, in accordance with the current status of the construction contracts, both Sections B and C should be completed during the next reporting period. Assuming that completion occurs as expected, the next report will take the format of a “closeout report”.

76. Action plans for the coming reporting period are provided below in Tables 6 and 7.

Table 6: Section B Action Plan

Action Timeframe Responsibility

Resolve breaches in bund at

prime coat asphalt plant

Immediately Contractor

Remove subterranean bitumen

tank at prime coat asphalt plant

Immediately Contractor

Repair broken bund at main

asphalt plant

Immediately Contractor

Repair Haftoni road Immediately Contractor

Ensure all crossing points and

diversions remain passable to

traffic

Throughout reporting period Contractor & Engineer’s National

Environmental Specialist

Ensure all firefighting equipment

is functional and inspected

Throughout reporting period Contractor & Engineer’s National

Environmental Specialist

Ensure finishing works are

carried out in accordance with

SSEMP

Throughout reporting period Contractor & Engineer’s National

Environmental Specialist

Monitor reinstatement progress Throughout reporting period Engineer’s National

Environmental Specialist

Verify completion of

reinstatement in accordance

with SSEMP / post construction

audit

After construction is complete Engineer’s International

Environmental Specialist

Table 7: Section C Action Plan

Action Timeframe Responsibility

Resolve breaches in bund at

asphalt plant

Immediately Contractor

Ensure all crossing points and

diversions remain passable to

traffic

Throughout reporting period Contractor & Engineer’s National

Environmental Specialist

Ensure finishing works are

carried out in accordance with

SSEMP

Throughout reporting period Contractor & Engineer’s National

Environmental Specialist

Monitor reinstatement progress Throughout reporting period Engineer’s National

Environmental Specialist

Verify completion of

reinstatement in accordance

with SSEMP / post construction

audit

After construction is complete Engineer’s International

Environmental Specialist

Page 30: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 30

G. Conclusions

77. The past six months have been a period of intense construction activity for both Section B and C contractors. During this period, both contractors maintained a generally good level of environmental management, have maintained their documentation in good order, and have avoided accidents and incidents.

78. Only a handful of non-compliances observed, and these were all restricted to the camp areas. The gradual completion of the road sections, and in particular the diversion/crossing roads, will reduce negative impacts such as airborne dust and traffic noise affecting local populations.

79. The Hirkan Forest area has been in a good condition during the present monitoring period, during which there has been little change from the previous six months.

80. The requested improvements to public consultations for both Sections have not been made, despite repeated attempts.

81. The focus in the coming months will be on ensuring that the required permanent environmental mitigation measures are correctly installed by the contractors, and that site reinstatement is correctly carried out.

Page 31: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 31

IV. APPENDICES

Appendix 1: Environmental Monitoring Results

Section B

Water Quality

1) Pre-Construction Monitoring

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.7 7.7 7.6 7.5 7.5 7.5 7.6 7.7 6.0-9.0

Electrical conductivity X103

cm/cm

0.204 0.205 0.203 0.204 0.204 0.204 0.206 0.207 -

Limpidity Cm 24.0 25.0 24.0 24.0 24.0 25.0 25.0 25.4 <30

Turbidity mg/l 26.3 26.4 26.7 25.5 25.5 25.7 24.9 24.9 <30

Dissolved O2 mg/l 4.2 4.2 4.4 4.6 4.9 4.7 4.5 4.7 4.6-6.0

BOD mg/l 1,6 1,6 1,9 1,9 2,8 2,7 2,7 2,9 3

Total roughness mqekv/l 4.13 4.15 4.18 4.22 4.56 4.59 4.60 5.15 7.0

Calcium ion Ca2+ mg/l 114.0 115.0 128.0 128.0 108.0 109.0 106.0 105.9 180.0

Magnesium ion Mg2+ mg/l 10.2 10.3 11.9 11.9 9.9 9.9 9.9 9.9 200.0

Chloride ion Cl- mg/l 145.2 146.1 148.7 148.8 138.5 139.3 137.8 138.2 350.0

Sulphate SO42- mg/l 266.3 261.6 269.9 269.9 178.4 178.5 177.9 177.9 500.0

Bicarbonate ion, HCO3- mg/l 229.4 229.7 231.9 231.9 182.6 183.4 182.5 182.8 -

Na++K+ ions mg/l 157.9 158.6 159.7 159.8 144.9 144.9 144.7 144.9 -

Sum of ions,∑ 1 mg/l 932.7 933.4 934.3 935.5 743.4 743.2 745.3 745.8 1000.0

Ammonium ion, NH4+ mg/l 0.336 0.337 0.337 0.338 0.231 0.231 0.240 0.242 0.39

Nitrite ion, NO2- mg/l 0.007 0.008 0.007 0.007 0.007 0.008 0.005 0.006 0.02

Nitrate ion, NO3- mg/l 3.22 3.24 3.20 3.23 2.52 2.53 2.34 2.40 9.0

Oil & grease mg/l 0.002 0.003 0.003 0.003 0.002 0.002 0.001 0.002 0.05

Faecal coliform per 100

ml

<2.0x105 <2.0x105 <2.0x105 <2.0x105 <2.0x105 <2.0x105 <2.0x105 <2.0x105 <2.0

TSS mg/l 0.226 0.226 0.228 0.229 0.110 0.113 0.114 0.117

SSAM mg/l 0.028 0.029 0.033 0.033 0.020 0.025 0.025 0.026 0.1

Phenol mg/l 0.001 0.001 0.001 0.001 0.001 0.0002 0.0003 0.0004 0.001

Page 32: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 32

2) January 2017

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 6.0 6.1 5.4 5.6 5.7 6.0 6.5 6.7 6.0-9.0

Electrical conductivity X103

cm/cm

0.260 0.260 0.211 0.213 0.192 0.192 0.153 0.157 -

Limpidity Cm 19.4 19.3 18.3 18.4 19.2 19.2 22.8 23.1 <30

Turbidity mg/l 19.0 19.2 17.1 18.2 18.0 17.7 18.0 18.2 <30

Dissolved O2 mg/l 3.0 3.2 3.1 3.3 3.0 3.0 3.3 3.3 4.6-6.0

BOD mg/l 2.2 2.3 2.4 2.4 2.1 2.2 2.2 2.4 3

Total roughness mqekv/l 5.71 5.72 5.81 5.81 4.44 4.44 3.17 3.19 7.0

Calcium ion Ca2+ mg/l 122.0 122.2 120.1 122.2 115.0 116.2 102.1 102.1 180.0

Magnesium ion Mg2+ mg/l 10.0 10.2 11.1 11.2 10.5 10.6 9.8 9.9 200.0

Chloride ion Cl- mg/l 157.0 158.2 148.2 149.2 139.2 139.4 123.2 123.4 350.0

Sulphate SO42- mg/l 254.1 255.4 196.0 197.0 194.2 194.3 187.4 187.5 500.0

Bicarbonate ion, HCO3- mg/l 216.1 216.2 204.0 204.3 198.2 198.4 196.5 196.6 -

Na++K+ ions mg/l 174.8 174.7 169.3 169.5 156.0 156.2 143.3 143.4 -

Sum of ions,∑ 1 mg/l 935.4 935.5 854.4 855.6 815.1 816.3 762.3 763.7 1000.0

Ammonium ion, NH4+ mg/l 0.330 0.331 0.283 0.286 0.280 0.283 0.233 0.233 0.39

Nitrite ion, NO2- mg/l 0.002 0.003 0.004 0.004 0.004 0.005 0.004 0.005 0.02

Nitrate ion, NO3- mg/l 3.60 3.61 2.41 2.42 2.28 2.29 2.22 2.20 9.0

Oil & grease mg/l 0.001 0.001 0.001 0.001 0.002 0.001 0.001 0.002 0.05

Faecal coliform per 100 ml 790 795 834 841 685 689 662 670 1000

TSS mg/l 0.082 0.087 0.049 0.050 0.071 0.072 0.050 0.053

SSAM mg/l 0.01 0.02 0.02 0.02 0.03 0.03 0.01 0.02 0.1

Phenol mg/l 0.0001 0.0001 0.0001 0.0001 0.0001 0.0002 0.0001 0.0002 0.001

Page 33: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 33

3) February 2017

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.1 7.2 7.3 7.3 7.3 7.1 7.3 7.2 6.0-9.0

Electrical conductivity X103

cm/cm

0.180 0.182 0.211 0.212 0.214 0.216 0.213 0.213 -

Limpidity Cm 20.1 20.5 20.6 20.7 17.6 17.4 21.3 21.1 <30

Turbidity mg/l 24.3 23.7 22.5 22.2 26.6 26.6 25.4 25.2 <30

Dissolved O2 mg/l 4.1 4.2 4.0 4.3 4.0 4.2 4.4 4.3 4.6-6.0

BOD mg/l 2.1 2.2 2.4 2.3 2.3 2.4 2.3 2.3 3

Total roughness mqekv/l 5.22 5.21 4.38 4.41 4.45 4.50 5.02 5.02 7.0

Calcium ion Ca2+ mg/l 132.1 133.0 117.6 107.4 126.2 126.4 106.6 109.5 180.0

Magnesium ion Mg2+ mg/l 11.2 11.3 10.7 7.8 12.4 12.6 9.4 9.6 200.0

Chloride ion Cl- mg/l 156.1 156.2 133.5 133.6 143.1 144.0 136.1 136.3 350.0

Sulphate SO42- mg/l 204.4 207.2 173.5 174.6 198.5 197.3 189.1 187.3 500.0

Bicarbonate ion, HCO3- mg/l 205.3 209.3 172.5 173.2 217.3 215.3 198.4 197.1 -

Na++K+ ions mg/l 168.4 167.9 146.6 147.6 159.8 156.7 143.5 145.8 -

Sum of ions,∑ 1 mg/l 877.5 884.9 754.4 744.2 857.3 852.3 783.1 785.6 1000.0

Ammonium ion, NH4+ mg/l 0.434 0.435 0.345 0.346 0.232 0.234 0.254 0.252 0.39

Nitrite ion, NO2- mg/l 0.009 0.008 0.008 0.006 0.006 0.007 0.006 0.008 0.02

Nitrate ion, NO3- mg/l 3.37 3.36 2.32 2.33 2.39 2.37 2.37 2.34 9.0

Oil & grease mg/l 0.002 0.002 0.002 0.001 0.002 0.002 0.003 0.002 0.05

Faecal coliform per 100 ml 817 822 761 763 821 832 883 885 1000

TSS mg/l 0.210 0.212 0.224 0.221 0.130 0.125 0.124 0.122

SSAM mg/l 0.023 0.014 0.030 0.033 0.025 0.027 0.020 0.021 0.1

Phenol mg/l 0.0001 0.0001 0.0002 0.0001 0.0001 0.0002 0.0001 0.0001 0.001

Page 34: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 34

4) March 2017

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.0 7.0 7.1 7.2 7.0 7.1 7.2 7.2 6.0-9.0

Electrical conductivity X103

cm/cm

0.185 0.186 0.210 0.212 0.214 0.215 0.210 0.213 -

Limpidity Cm 20.5 20.6 20.2 20.3 17.1 17.2 21.3 21.4 <30

Turbidity mg/l 24.0 24.0 22.2 22.3 26.6 26.7 25.4 25.1 <30

Dissolved O2 mg/l 3.5 3.8 4.0 4.1 4.0 4.2 4.0 4.0 4.6-6.0

BOD mg/l 2.0 2.1 2.2 2.3 2.3 2.3 2.0 2.2 3

Total roughness mqekv/l 5.20 5.21 4.28 4.31 4.40 4.43 5.02 5.05 7.0

Calcium ion Ca2+ mg/l 132.0 133.0 117.6 107.4 126.3 126.4 106.6 109.5 180.0

Magnesium ion Mg2+ mg/l 11.0 11.1 10.5 10.7 12.0 12.1 9.4 9.9 200.0

Chloride ion Cl- mg/l 156.4 156.5 133.5 133.6 143.2 144.2 136.4 136.5 350.0

Sulphate SO42- mg/l 204.0 207.0 173.1 174.3 198.5 197.6 189.0 189.3 500.0

Bicarbonate ion, HCO3- mg/l 205.1 209.2 172.0 173.2 217.3 217.9 198.1 197.9 -

Na++K+ ions mg/l 168.3 168.9 146.5 147.3 159.8 159.8 143.5 145.9 -

Sum of ions,∑ 1 mg/l 877.1 884.4 754.2 754.2 857.3 858.7 783.1 785.5 1000.0

Ammonium ion, NH4+ mg/l 0.435 0.436 0.345 0.346 0.230 0.231 0.254 0.255 0.39

Nitrite ion, NO2- mg/l 0.008 0.009 0.006 0.006 0.007 0.007 0.006 0.008 0.02

Nitrate ion, NO3- mg/l 3.35 3.36 2.32 2.33 2.33 2.37 2.37 2.38 9.0

Oil & grease mg/l 0.001 0.002 0.002 0.001 0.002 0.002 0.003 0.002 0.05

Faecal coliform per 100 ml 831 839 760 766 828 835 880 888 1000

TSS mg/l 0.208 0.211 0.220 0.221 0.130 0.134 0.124 0.126 0.25

SSAM mg/l 0.023 0.030 0.030 0.033 0.020 0.023 0.020 0.021 0.1

Phenol mg/l 0.0001 0.0002 0.0001 0.0001 0.0002 0.0002 0.0001 0.0002 0.001

Page 35: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 35

5) April 2017

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.0 7.1 7.2 7.3 7.2 7.4 7.0 7.2 6.0-9.0

Electrical conductivity X103

cm/cm

0.175 0.182 0.202 0.205 0.207 0.209 0.212 0.215 -

Limpidity Cm 21.1 21.4 20.3 20.5 21.5 21.7 22.4 22.5 <30

Turbidity mg/l 14.3 13.2 14.6 14.9 15.2 15.3 14.7 14.8 <30

Dissolved O2 mg/l 3.6 3.6 3.2 3.7 3.3 3.4 3.2 3.9 4.6-6.0

BOD mg/l 2.1 2.2 2.0 2.2 2.1 2.3 2.4 2.5 3

Total roughness mqekv/l 5.18 5.19 4.78 4.80 3.50 3.52 3.69 4.05 7.0

Calcium ion Ca2+ mg/l 122.5 122.8 103.2 103.6 108.4 108.5 96.4 96.5 180.0

Magnesium ion Mg2+ mg/l 12.3 12.5 9.4 9.7 10.2 10.3 9.4 9.6 200.0

Chloride ion Cl- mg/l 152.5 153.0 135.2 136.0 134.2 134.5 121.4 122.6 350.0

Sulphate SO42- mg/l 263.1 263.4 170.1 170.5 191.3 191.6 185.6 186.7 500.0

Bicarbonate ion, HCO3- mg/l 221.2 224.1 179.4 181.2 205.7 205.9 193.2 193.4 -

Na++K+ ions mg/l 162.4 163.1 145.3 146.4 151.3 151.6 137.3 138.1 -

Sum of ions,∑ 1 mg/l 934.0 938.9 742.6 747.4 801.1 802.4 743.3 746.9 1000.0

Ammonium ion, NH4+ mg/l 0.322 0.323 0.248 0.252 0.182 0.185 0.254 0.259 0.39

Nitrite ion, NO2- mg/l 0.008 0.009 0.006 0.008 0.003 0.004 0.005 0.006 0.02

Nitrate ion, NO3- mg/l 3.54 3.56 2.41 2.44 2.48 2.47 2.31 2.29 9.0

Oil & grease mg/l 0.002 0.003 0.001 0.002 0.002 0.003 0.002 0.003 0.05

Faecal coliform per 100 ml 752 760 870 874 843 848 860 866 1000

TSS mg/l 0.242 0.245 0.301 0.305 0.145 0.150 0.132 0.137 0.25

SSAM mg/l 0.037 0.038 0.028 0.034 0.024 0.026 0.027 0.031 0.1

Phenol mg/l 0.0001 0.0001 0.0001 0.0001 0.0002 0.0002 0.0001 0.0001 0.001

Page 36: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 36

6) May 2017

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.5 7.7 7.0 7.1 6.2 6.2 5.0 5.1 6.0-9.0

Electrical conductivity X103

cm/cm

0.177 0.181 0.212 0.215 0.204 0.205 0.210 0.212 -

Limpidity Cm 20.1 20.4 19.3 19.5 19.5 19.7 20.4 21.5 <30

Turbidity mg/l 16.3 16.2 16.6 16.4 17.2 17.3 15.4 15.8 <30

Dissolved O2 mg/l 3.6 3.5 3.9 3.5 3.9 3.7 3.2 3.9 4.6-6.0

BOD mg/l 2.2 2.2 2.3 2.4 2.2 2.3 2.5 2.5 3

Total roughness mqekv/l 5.32 5.34 4.84 4.89 3.62 3.70 3.86 4.05 7.0

Calcium ion Ca2+ mg/l 124.4 124.5 105.2 105.6 110.2 110.8 98.7 98.9 180.0

Magnesium ion Mg2+ mg/l 12.5 12.5 10.3 10.5 10.8 10.9 9.6 9.7 200.0

Chloride ion Cl- mg/l 154.3 155.0 137.0 137.4 134.2 134.5 122.3 122.6 350.0

Sulphate SO42- mg/l 265.0 265.8 172.3 172.5 192.4 192.7 186.4 186.7 500.0

Bicarbonate ion, HCO3- mg/l 220.0 221.3 181.5 181.8 207.1 207.4 194.6 195.4 -

Na++K+ ions mg/l 165.7 166.0 147.4 147.6 152.0 152.3 139.2 139.7 -

Sum of ions,∑ 1 mg/l 941.9 945.1 753.7 755.4 806.7 808.6 750.8 753.0 1000.0

Ammonium ion, NH4+ mg/l 0.412 0.413 0.284 0.286 0.262 0.267 0.285 0.290 0.39

Nitrite ion, NO2- mg/l 0.006 0.007 0.006 0.008 0.005 0.006 0.008 0.009 0.02

Nitrate ion, NO3- mg/l 3.54 3.56 2.41 2.44 2.48 2.47 2.31 2.29 9.0

Oil & grease mg/l 0.002 0.003 0.002 0.002 0.002 0.003 0.003 0.003 0.05

Faecal coliform per 100 ml 765 769 857 860 858 865 864 872 1000

TSS mg/l 0.240 0.243 0.291 0.297 0.164 0.172 0.179 0.185 0.25

SSAM mg/l 0.03 0.04 0.05 0.06 0.04 0.05 0.02 0.03 0.1

Phenol mg/l 0.0002 0.0002 0.0001 0.0001 0.0001 0.0002 0.0001 0.0001 0.001

Page 37: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 37

7) June 2017

Determinand Unit

Lakar 1 River Lakar 2 River Ogru River Gamishli River

Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 6.7 6.8 6.5 6.7 7.4 7.5 7.3 7.5 6.0-9.0

Electrical conductivity X103

cm/cm

0.274 0.280 0.204 0.205 0.192 0.195 0.154 0.156 -

Limpidity Cm 19.2 19.2 18.6 18.7 19.4 19.6 23.7 23.9 <30

Turbidity mg/l 16.1 16.2 16.2 16.3 17.5 17.6 12.2 12.5 <30

Dissolved O2 mg/l 3.3 3.4 3.1 3.5 3.0 3.1 3.3 3.4 4.6-6.0

BOD mg/l 2.6 2.7 2.6 2.7 1.8 1.9 1.2 1.3 3

Total roughness mqekv/l 5.79 5.84 5.84 5.86 4.42 4.43 3.10 3.12 7.0

Calcium ion Ca2+ mg/l 124.3 124.5 125.1 125.2 115.2 115.4 101.2 101.4 180.0

Magnesium ion Mg2+ mg/l 11.9 12.1 12.2 12.3 11.3 11.4 9.7 9.8 200.0

Chloride ion Cl- mg/l 156.2 156.4 148.9 149.2 138.4 138.6 122.3 122.6 350.0

Sulphate SO42- mg/l 265.4 265.5 198.2 198.5 195.8 196.0 186.4 186.5 500.0

Bicarbonate ion, HCO3- mg/l 219.3 219.8 202.1 202.6 198.4 198.7 196.4 196.7 -

Na++K+ ions mg/l 170.7 170.9 168.4 168.7 155.2 155.5 142.5 142.8 -

Sum of ions,∑ 1 mg/l 947.8 949.2 854.9 856.5 814.3 815.6 758.5 759.8 1000.0

Ammonium ion, NH4+ mg/l 0.384 0.385 0.280 0.282 0.260 0.263 0.242 0.245 0.39

Nitrite ion, NO2- mg/l 0.007 0.008 0.006 0.007 0.005 0.006 0.004 0.005 0.02

Nitrate ion, NO3- mg/l 3.66 3.69 2.38 2.40 224 2.25 2.20 2.24 9.0

Oil & grease mg/l 0.002 0.003 0.002 0.003 0.001 0.002 0.001 0.002 0.05

Faecal coliform per 100 ml 780 785 812 815 680 682 670 672 1000

TSS mg/l 0.083 0.084 0.015 0.017 0.065 0.070 0.054 0.055 0.25

SSAM mg/l 0.04 0.05 0.05 0.05 0.02 0.03 0.01 0.02 0.1

Phenol mg/l 0.0001 0.0002 0.0003 0.0003 0.0001 0.0001 0.0001 0.0002 0.001

Page 38: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 38

8) Hirkan Forest Preconstruction

Determinand Unit Monitoring Value Limit

pH 7.6 6.0-9.0

Electrical conductivity X103

cm/cm

0.392 -

Limpidity Cm 12.0 <30

Turbidity mg/l 90 <30

Dissolved O2 mg/l 7.5 4.6-6.0

BOD mg/l 0.6 3

Total roughness mqekv/l 3.3 7.0

Calcium ion Ca2+ mg/l 59.6 180.0

Magnesium ion Mg2+ mg/l 4.9 200.0

Chloride ion Cl- mg/l 25.2 350.0

Sulphate SO42- mg/l 38.4 500.0

Bicarbonate ion, HCO3- mg/l 213.5 -

Na++K+ ions mg/l 39.7 -

Sum of ions,∑ 1 mg/l 381.3 1000.0

Ammonium ion, NH4+ mg/l 0.1 0.39

Nitrite ion, NO2- mg/l 0.4 0.02

Nitrate ion, NO3- mg/l 1.7 9.0

Oil & grease mg/l 0.03 0.05

Faecal coliform per 100 ml 45000 1000

TSS mg/l 0.46 0.25

SSAM mg/l 0.000 0.1

Phenol mg/l 0.001 0.001

Page 39: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 39

9) Hirkan Forest June 2017

Determinand Unit Monitoring Value Limit

pH 7.5 6.0-9.0

Electrical conductivity X103

cm/cm

0.187 -

Limpidity Cm 19.2 <30

Turbidity mg/l 10.8 <30

Dissolved O2 mg/l 4.0 4.6-6.0

BOD mg/l 2.9 3

Total roughness mqekv/l 3.34 7.0

Calcium ion Ca2+ mg/l 111.9 180.0

Magnesium ion Mg2+ mg/l 10.3 200.0

Chloride ion Cl- mg/l 142.1 350.0

Sulphate SO42- mg/l 177.7 500.0

Bicarbonate ion, HCO3- mg/l 209.5 -

Na++K+ ions mg/l 146.3 -

Sum of ions,∑ 1 mg/l 781.9 1000.0

Ammonium ion, NH4+ mg/l 0.8 0.39

Nitrite ion, NO2- mg/l 0.007 0.02

Nitrate ion, NO3- mg/l 2.48 9.0

Oil & grease mg/l 0.02 0.05

Faecal coliform per 100 ml 1553 1000

TSS mg/l 0.022 0.25

SSAM mg/l 0.01 0.1

Phenol mg/l 0.0002 0.001

Page 40: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 40

Air Quality

1) Pre-Construction Monitoring

Monitoring locations

Determinand Concentration Allowed concentration

Contractor Camp Dust 0.3 0.5 NO2 0.063 0.085 Carbon monoxide 3 5

Sensitive Receptor 1 Dust 0.3 0.5 NO2 0.060 0.085 Carbon monoxide 3 5

Sensitive Receptor 2 Dust 0.3 0.5 NO2 0.062 0.085 Carbon monoxide 3 5

Sensitive Receptor 3 Dust 0.3 0.5 NO2 0.063 0.085 Carbon monoxide 3 5

Sensitive Receptor 4 Dust 0.3 0.5 NO2 0.055 0.085 Carbon monoxide 3 5

Sapnakaran village Dust 0.3 0.5 NO2 0.063 0.085 Carbon monoxide 4 5

Yuxari Nuvadi village Dust 0.3 0.5 NO2 0.062 0.085 Carbon monoxide 4 5

Mamusta village Dust 0.3 0.5 NO2 0.060 0.085 Carbon monoxide 4 5

Lenkaran Borrow Pit Dust 0.4 0.5 NO2 0.073 0.085 Carbon monoxide 4 5

Sovu Borrow Pit Dust 0.4 0.5 NO2 0.075 0.085 Carbon monoxide 4 5

Page 41: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 41

2) January 2017

Monitoring locations

Determinand Concentration Allowed concentration

Haftoni Village Dust 0.1 0.5 NO2 0.032 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.029 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.033 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.1 0.5 NO2 0.032 0.085 Carbon monoxide 2 5

Sapnakaran village Dust 0.1 0.5 NO2 0.038 0.085 Carbon monoxide 2 5

Yuxari Nuvadi village Dust 0.1 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Dasdaligjar village Dust 0.1 0.5 NO2 0.029 0.085 Carbon monoxide 2 5

Mamusta village Dust 0.1 0.5 NO2 0.026 0.085 Carbon monoxide 2 5

Page 42: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 42

3) February 2017

Monitoring locations

Determinand Concentration Allowed concentration

Haftoni Village Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 1 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.031 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.034 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.031 0.085 Carbon monoxide 1 5

Sensitive Receptor 4 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 1 5

Sapnakaran village Dust 0.1 0.5 NO2 0.037 0.085 Carbon monoxide 2 5

Yuxari Nuvadi village Dust 0.1 0.5 NO2 0.039 0.085 Carbon monoxide 2 5

Dasdaligjar village Dust 0.1 0.5 NO2 0.028 0.085 Carbon monoxide 1 5

Mamusta village Dust 0.1 0.5 NO2 0.025 0.085 Carbon monoxide 1 5

Page 43: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 43

4) March 2017

Monitoring locations

Determinand Concentration Allowed concentration

Haftoni Village Dust 0.1 0.5 NO2 0.037 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.034 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.030 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.039 0.085 Carbon monoxide 1 5

Sensitive Receptor 4 Dust 0.1 0.5 NO2 0.041 0.085 Carbon monoxide 2 5

Sapnakaran village Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Yuxari Nuvadi village Dust 0.2 0.5 NO2 0.046 0.085 Carbon monoxide 2 5

Dasdaligjar village Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 1 5

Mamusta village Dust 0.1 0.5 NO2 0.032 0.085 Carbon monoxide 1 5

Page 44: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 44

5) April 2017

Monitoring locations

Determinand Concentration Allowed concentration

Haftoni Village Dust 0.2 0.5 NO2 0.041 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.2 0.5 NO2 0.039 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.036 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 1 5

Sensitive Receptor 4 Dust 0.2 0.5 NO2 0.043 0.085 Carbon monoxide 2 5

Sapnakaran village Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Yuxari Nuvadi village Dust 0.2 0.5 NO2 0.047 0.085 Carbon monoxide 2 5

Dasdaligjar village Dust 0.1 0.5 NO2 0.037 0.085 Carbon monoxide 1 5

Mamusta village Dust 0.1 0.5 NO2 0.038 0.085 Carbon monoxide 1 5

Page 45: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 45

6) May 2017

Monitoring locations

Determinand Concentration Allowed concentration

Haftoni Village Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.039 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Sapnakaran village Dust 0.3 0.5 NO2 0.047 0.085 Carbon monoxide 2 5

Yuxari Nuvadi village Dust 0.3 0.5 NO2 0.050 0.085 Carbon monoxide 2 5

Dasdaligjar village Dust 0.1 0.5 NO2 0.039 0.085 Carbon monoxide 1 5

Mamusta village Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Page 46: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 46

7) June 2017

Monitoring locations

Determinand Concentration Allowed concentration

Haftoni Village Dust 0.3 0.5 NO2 0.050 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.3 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.2 0.5 NO2 0.047 0.085 Carbon monoxide 2 5

Sapnakaran village Dust 0.3 0.5 NO2 0.051 0.085 Carbon monoxide 2 5

Yuxari Nuvadi village Dust 0.3 0.5 NO2 0.055 0.085 Carbon monoxide 2 5

Dasdaligjar village Dust 0.2 0.5 NO2 0.041 0.085 Carbon monoxide 2 5

Mamusta village Dust 0.2 0.5 NO2 0.043 0.085 Carbon monoxide 2 5

Page 47: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 47

8) Hirkan forest - Pre-Construction Monitoring

Monitoring locations

Determinand Concentration Allowed concentration

Contractor Camp Dust 0.1 0.5 NO2 0.03 0.085 Carbon monoxide 2 5

9) Hirkan forest – March 2017

Monitoring locations

Determinand Concentration Allo wed concentration

Station 1 Dust 0.2 0.5 NO2 0.041 0.085 Carbon monoxide 2 5

Page 48: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 48

Noise & Vibration

1) Pre-Construction Monitoring

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 33 50 Sensitive Receptor 1 32 50 Sensitive Receptor 2 34 50 Sensitive Receptor 3 30 50 Sensitive Receptor 4 29 50 Luveser village 40 50 Sovu village 44 50 Sapnakaran village 40 50 Yuxari Nuvadi village 41 50 Mamusta village 27 50

Vibration level (dB)

Monitoring locations Results Allowed Haftoni Settlement 54 77 Sensitive Receptor 1 51 77 Sensitive Receptor 2 53 77 Sensitive Receptor 3 52 77 Sensitive Receptor 4 41 77 Luveser village 69 77 Sovu village 70 77 Sapnakaran village 63 77 Yuxari Nuvadi village 64 77 Mamusta village 39 77

Page 49: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 49

2) January 2017

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 32.4 50 Sensitive Receptor 1 34.1 50 Sensitive Receptor 2 30.8 50 Sensitive Receptor 3 33.2 50 Sensitive Receptor 4 35.5 50 Sapnakaran village 31.2 50 Yuxari Nuvadi village 40.0 50 Dasdaligjar village 33.8 50 Mamusta village 31.2 50

Vibration level (dB)

Monitoring locations Results Allowed Haftoni Settlement 31 77 Sensitive Receptor 1 30 77 Sensitive Receptor 2 34 77 Sensitive Receptor 3 33 77 Sensitive Receptor 4 35 77 Sapnakaran village 31 77 Yuxari Nuvadi village 40 77 Dasdaligjar village 32 77 Mamusta village 34 77

3) February 2017

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 35.2 50 Sensitive Receptor 1 30.5 50 Sensitive Receptor 2 30.3 50 Sensitive Receptor 3 35.6 50 Sensitive Receptor 4 32.1 50 Sapnakaran village 31.3 50 Yuxari Nuvadi village 40.7 50 Dasdaligjar village 30.3 50 Mamusta village

30.5 50

Page 50: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 50

Vibration level (dB)

Monitoring locations Results Allowed Haftoni Settlement 30 77 Sensitive Receptor 1 31 77 Sensitive Receptor 2 32 77 Sensitive Receptor 3 35 77 Sensitive Receptor 4 32 77 Sapnakaran village 30 77 Yuxari Nuvadi village 41 77 Dasdaligjar village 34 77 Mamusta village 32 77

4) March 2017

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 36.5 50 Sensitive Receptor 1 32.8 50 Sensitive Receptor 2 30.0 50 Sensitive Receptor 3 37.4 50 Sensitive Receptor 4 34.2 50 Sapnakaran village 38.7 50 Yuxari Nuvadi village 41.9 50 Dasdaligjar village 30.8 50 Mamusta village 32.7 50

Vibration level (dB)

Monitoring locations Results Allowed Haftoni Settlement 36.5 77 Sensitive Receptor 1 32.8 77 Sensitive Receptor 2 30.0 77 Sensitive Receptor 3 37.4 77 Sensitive Receptor 4 34.2 77 Sapnakaran village 38.7 77 Yuxari Nuvadi village 41.9 77 Dasdaligjar village 30.8 77 Mamusta village 32.7 77

Page 51: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 51

5) April 2017

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 38.2 50 Sensitive Receptor 1 36.5 50 Sensitive Receptor 2 37.1 50 Sensitive Receptor 3 37.7 50 Sensitive Receptor 4 36.3 50 Sapnakaran village 40.2 50 Yuxari Nuvadi village 42.5 50 Dasdaligjar village 35.1 50 Mamusta village 34.4 50

Vibration level (dB)

Monitor ing locations Results Allowed Haftoni Settlement 36 77 Sensitive Receptor 1 33 77 Sensitive Receptor 2 35 77 Sensitive Receptor 3 37 77 Sensitive Receptor 4 35 77 Sapnakaran village 38 77 Yuxari Nuvadi village 42 77 Dasdaligjar village 33 77 Mamusta village 32 77

6) May 2017

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 39.1 50 Sensitive Receptor 1 37.8 50 Sensitive Receptor 2 36.5 50 Sensitive Receptor 3 39.7 50 Sensitive Receptor 4 38.2 50 Sapnakaran village 40.0 50 Yuxari Nuvadi village 45.2 50 Dasdaligjar village 37.3 50 Mamusta village 35.1 50

Page 52: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 52

Vibration level (dB)

Monitoring locations Results Allowed Haftoni Settlement 39 77 Sensitive Receptor 1 35 77 Sensitive Receptor 2 37 77 Sensitive Receptor 3 38 77 Sensitive Receptor 4 36 77 Sapnakaran village 38 77 Yuxari Nuvadi village 43 77 Dasdaligjar village 35 77 Mamusta village 34 77

7) June 2017

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 41.5 50 Sensitive Receptor 1 38.2 50 Sensitive Receptor 2 35.6 50 Sensitive Receptor 3 40.1 50 Sensitive Receptor 4 38.6 50 Sapnakaran village 40.2 50 Yuxari Nuvadi village 46.5 50 Dasdaligjar village 38.0 50 Mamusta village 35.5 50

Vibration level (dB)

Monitoring loca tions Results Allowed Haftoni Settlement 42 77 Sensitive Receptor 1 37 77 Sensitive Receptor 2 43 77 Sensitive Receptor 3 39 77 Sensitive Receptor 4 37 77 Sapnakaran village 39 77 Yuxari Nuvadi village 48 77 Dasdaligjar village 39 77 Mamusta village 35 77

Page 53: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 53

8) Hirkan Forest - Pre-Construction Monitoring

Noise level (dB)

Monitoring locations Results Allowed Station 1 45.7 50 Station 2 43.2 50

Vibration level (dB)

Monitoring locations Results Allowed Station 1 47 77 Station 2 44 77

9) Hirkan Forest – January 2017

Noise level (dB)

Monitoring locations Results Allowed Station 1 38.6 50 Station 2 35.3 50

Vibration level (dB)

Monitoring locations Results Allowed Station 1 30 77 Station 2 30 77

10) Hirkan Forest – February 2017

Noise level (dB)

Monitoring locations Results Allowed Station 1 32.2 50 Station 2 33.5 50

Vibration level (dB)

Monitoring locations Results Allowed Station 1 32 77 Station 2 30 77

Page 54: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 54

Section C

Water Quality

1) Pre-Construction Monitoring

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.3 7.3 7.2 7.3 7.4 7.5 7.5 7.6 7.4 6.0-

9.0

Electrical

conductivity

X103

cm/c

m

0.184 0.183 0.204 0.206 0.221 0.223 0.226 0.227 0.220 -

Limpidity cm 23.0 23.1 23.0 23.3 22.6 23.7 21.5 22.3 19.4 <30

Turbidity mg/l 26.1 26.3 27.9 28.7 28.6 28.8 29.5 28.9 20.9 <30

Dissolved O2 mg/l 4.0 4.1 4.8 5.1 4.7 4.8 5.4 5.4 3.4 4.6-

6.0

BOD mg/l 2,2 2,4 2,3 2,4 2,1 2,4 2,3 2,3 2,3 3

Total

roughness

mqek

v/l

5.20 5.22 4.68 4.68 4.59 4.59 5.08 5.08 4.01 7.0

Calcium ion

Ca2+

mg/l 123.3 123.3 103.0 103.1 106.2 106.1 96.6 99.1 94.4 180.0

Magnesium

ion Mg2+

mg/l 11.3 11.3 8.3 8.6 8.3 8.4 9.3 9.3 9.3 200.0

Chloride ion

Cl-

mg/l 156.7 156.7 131.5 131.9 135.1 136.6 126.5 126.8 123.1 350.0

Sulphate

SO42-

mg/l 263.0 264.1 173.1 174.2 196.5 197.6 188.1 187.5 180.3 500.0

Bicarbonate

ion, HCO3-

mg/l 229.2 229.3 182.6 183.6 213.0 215.4 196.1 197.0 190.0 -

Na++K+ ions mg/l 167.3 167.4 146.0 146.2 151.6 151.7 139.3 140.7 139.3 -

Sum of

ions,∑ 1

mg/l 933.4 933.6 743.1 744.0 818.0 817.3 749.4 749.8 730.1 1000

Ammonium

ion, NH4+

mg/l 0.338 0.338 0.331 0.330 0.177 0.178 0.254 0.256 0.243 0.39

Nitrite ion,

NO2-

mg/l 0.005 0.005 0.004 0.004 0.004 0.003 0.003 0.003 0.002 0.02

Nitrate ion,

NO3-

mg/l 3.27 3.27 2.38 2.39 2.35 2.38 2.36 2.37 2.34 9.0

Oil & grease mg/l 0.002 0.002 0.001 0.001 0.001 0.002 0.001 0.001 0.001 0.05

Faecal

coliform

per

100

ml

<1.5x107 <1.5x107 <1.3.x104 <1.3x104 <1.4x106 <1.4x106 <1.9x103 <1.9x103 <1.5x107 1000

TSS mg/l 0.223 0.224 0.235 0.236 0.129 0.131 0.125 0.126 0.119 0.25

SSAM mg/l 0.027 0.027 0.035 0.035 0.029 0.032 0.026 0.027 0.023 0.1

Phenol mg/l 0.0001 0.0001 0.0002 0.0001 0.001 0.001 0.0002 0.0002 0.0001 0.001

Page 55: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 55

2) January 2017

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 6.2 6.4 7.3 7.2 7.1 7.2 6.3 6.3 5.5 6.0-

9.0

Electrical

conductivity

X103

cm/c

m

0.193 0.193 0.201 0.202 0.203 0.204 0.202 0.202 0.209 -

Limpidity cm 24.0 24.2 24.1 24.3 22.2 22.0 25.3 25.2 20.4 >30

Turbidity mg/l 25.9 25.6 26.4 26.8 24.3 24.4 26.1 26.7 21.9 >30

Dissolved O2 mg/l 3.0 3.2 3.4 3.5 3.3 3.3 3.2 3.3 3.5 4.6-6.0

BOD mg/l 1.3 1.4 1.3 1.3 3.3 3.0 2.9 2.9 2.2 3

Total

roughness

mqek

v/l

4.19 4.22 4.13 4.15 4.47 4.48 4.50 5.19 4.3 7.0

Calcium ion

Ca2+

mg/l 116.2 117.0 128.3 128.3 108.0 108.3 107.3 107.8 95.0 180.0

Magnesium

ion Mg2+

mg/l 10.4 10.3 11.2 11.3 9.5 9.5 9.3 9.3 9.6 200.0

Chloride ion

Cl-

mg/l 145.2 146.3 149.3 148.3 139.0 139.1 138.3 138.5 124.1 350.0

Sulphate

SO42-

mg/l 265.2 265.3 270.1 271.2 178.3 178.5 176.2 177.3 180.6 500.0

Bicarbonate

ion, HCO3-

mg/l 228.2 228.2 233.5 233.6 184.7 184.8 183.3 182.3 189.4 -

Na++K+ ions mg/l 158.2 158.4 159.6 159.5 145.6 144.7 145.2 144.3 138.1 -

Sum of

ions,∑ 1

mg/l 933.0 933.1 935.3 935.4 743.5 743.6 745.4 745.5 728.4 1000

Ammonium

ion, NH4+

mg/l 0.333 0.333 0.334 0.335 0.230 0.232 0.230 0.237 0.241 0.39

Nitrite ion,

NO2-

mg/l 0.004 0.005 0.004 0.004 0.004 0.005 0.005 0.004 0.004 0.02

Nitrate ion,

NO3-

mg/l 3.23 3.24 3.25 3.26 2.52 2.51 2.38 2.40 2.37 9.0

Oil & grease mg/l 0.001 0.002 0.003 0.003 0.002 0.003 0.002 0.002 0.002 0.05

Faecal

coliform

per

100

ml

885 888 889 894 906 908 877 879 810 1000

TSS mg/l 0.221 0.222 0.223 0.226 0.119 0.120 0.121 0.122 0.127 0.25

SSAM mg/l 0.023 0.022 0.032 0.032 0.026 0.025 0.027 0.028 0.025 0.1

Phenol mg/l 0.0001 0.0001 0.0002 0.0002 0.0002 0.0003 0.0001 0.0001 0.0001 0.001

Page 56: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 56

3) February 2017

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.1 7.4 7.2 7.2 7.1 7.4 7.3 7.3 7.4 6.0-

9.0

Electrical

conductivity

X103

cm/c

m

0.197 0.191 0.211 0.223 0.227 0.204 0.223 0.201 0.219 -

Limpidity cm 24.0 24.3 24.2 24.3 23.2 22.8 23.3 24.2 21.2 <30

Turbidity mg/l 22.5 21.3 20.4 22.6 24.3 24.1 24.3 25.7 20.2 <30

Dissolved O2 mg/l 4.4 4.2 3.2 3.3 4.8 4.7 4.2 4.3 4.5 4.6-

6.0

BOD mg/l 1.3 1.4 1.3 1.5 2.3 2.7 2.5 2.8 2.2 3

Total

roughness

mqek

v/l

4.12 4.29 4.18 4.15 4.37 4.42 4.50 5.19 4.3 7.0

Calcium ion

Ca2+

mg/l 126.2 112.0 117.3 117.5 118.0 115.4 110.8 112.3 99.0 180.0

Magnesium

ion Mg2+

mg/l 11.4 10.7 12.3 11.9 10.2 11 10.3 9.5 9.6 200.0

Chloride ion

Cl-

mg/l 132.5 134.0 145.3 146.3 136.3 138.1 137.4 138.1 124.1 350.0

Sulphate

SO42-

mg/l 245.2 265.3 271.1 272.4 173.3 174.7 171.2 172.3 182.3 500.0

Bicarbonate

ion, HCO3-

mg/l 220.1 221.2 213.4 213.6 174.7 175.8 183.1 182.6 184.4 -

Na++K+ ions mg/l 138 137.4 149.6 149.5 148.6 142.7 143.1 141.3 130.1 -

Sum of

ions,∑ 1

mg/l 873.4 880.6 909.0 911.2 761.1 757.5 755.9 756.1 729.5 1000

Ammonium

ion, NH4+

mg/l 0.313 0.320 0.321 0.315 0.215 0.218 0.220 0.217 0.221 0.39

Nitrite ion,

NO2-

mg/l 0.003 0.004 0.002 0.001 0.003 0.004 0.003 0.003 0.002 0.02

Nitrate ion,

NO3-

mg/l 3.21 3.20 3.15 3.16 2.44 2.50 2.33 2.40 2.35 9.0

Oil & grease mg/l 0.001 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.002 0.05

Faecal

coliform

per

100

ml

785 778 759 744 856 868 871 873 842 1000

TSS mg/l 0.211 0.212 0.213 0.216 0.112 0.114 0.111 0.112 0.120 0.25

SSAM mg/l 0.013 0.012 0.027 0.023 0.016 0.015 0.017 0.02 0.01 0.1

Phenol mg/l 0.0001 0.0003 0.0002 0.0005 0.0001 0.0001 0.0006 0.0007 0.0008 0.001

Page 57: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 57

4) March 2017

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 7.0 7.2 7.1 7.2 7.1 7.2 7.3 7.3 7.0 6.0-

9.0

Electrical

conductivity

X103

cm/c

m

0.185 0.186 0.205 0.207 0.198 0.198 0.203 0.203 0.208 -

Limpidity cm 24.1 24.2 21.1 21.6 22.2 22.0 25.3 25.2 20.4 <30

Turbidity mg/l 15.5 15.6 15.4 15.5 16.3 16.4 14.1 14.7 18.5 <30

Dissolved O2 mg/l 3.0 3.1 3.5 3.8 3.2 3.5 3.0 3.3 3.7 4.6-

6.0

BOD mg/l 1.2 1.3 1.4 1.5 1,3 1.5 1.6 1.8 2.2 3

Total

roughness

mqek

v/l

4.15 4.22 4.13 4.17 4.37 4.38 4.40 4.49 4.5 7.0

Calcium ion

Ca2+

mg/l 115.3 115.6 130.1 130.5 104.3 104.6 108.5 108.9 92.1 180.0

Magnesium

ion Mg2+

mg/l 9.8 9.9 10.3 10.4 9.5 9.6 9.7 9.8 9.3 200.0

Chloride ion

Cl-

mg/l 138.4 139.0 147.9 148.0 137.5 138.0 138.3 138.5 125.2 350.0

Sulphate

SO42-

mg/l 254.3 255.1 256.4 256.7 175.6 175.8 174.2 174.3 178.6 500.0

Bicarbonate

ion, HCO3-

mg/l 218.5 218.6 219.5 219.6 178.9 179.1 178.6 178.7 179.8 -

Na++K+ ions mg/l 147.4 147.6 155.3 155.4 142.5 143.1 145.2 145.4 141.3 -

Sum of

ions,∑ 1

mg/l 883.7 885.8 919.5 920.6 748.3 750.2 754.5 755.6 726.3 1000

Ammonium

ion, NH4+

mg/l 0.313 0.313 0.316 0.318 0.235 0.236 0.232 0.237 0.261 0.39

Nitrite ion,

NO2-

mg/l 0.003 0.004 0.004 0.004 0.005 0.005 0.006 0.006 0.007 0.02

Nitrate ion,

NO3-

mg/l 3.13 3.14 3.22 3.23 2.54 2.55 2.35 2.40 2.47 9.0

Oil & grease mg/l 0.001 0.002 0.002 0.003 0.002 0.003 0.002 0.002 0.003 0.05

Faecal

coliform

per

100

ml

820 827 830 834 810 819 840 846 852 1000

TSS mg/l 0.218 0.222 0.220 0.222 0.114 0.119 0.124 0.127 0.137 0.25

SSAM mg/l 0.020 0.021 0.030 0.033 0.024 0.025 0.027 0.028 0.032 0.1

Phenol mg/l 0.0001 0.0002 0.0001 0.0001 0.0002 0.0002 0.0001 0.0001 0.0003 0.001

Page 58: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 58

5) April 2017

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 6.0 6.0 5.5 5.6 6.5 6.6 6.0 6.2 5.5 6.0-

9.0

Electrical

conductivity

X103

cm/c

m

0.185 0.186 0.205 0.207 0.198 0.198 0.203 0.203 0.208 -

Limpidity cm 22.1 22.2 24.1 24.3 22.2 22.0 25.3 25.2 20.4 >30

Turbidity mg/l 16.4 16.3 15.4 15.5 16.3 16.4 14.1 14.7 18.5 >30

Dissolved O2 mg/l 3.5 3.7 3.3 3.3 3.8 3.9 3.2 3.3 3.5 4.6-

6.0

BOD mg/l 1.7 1.4 1.8 1.9 1.6 1.7 1.6 1.8 2.1 3

Total

roughness

mqek

v/l

4.84 4.87 4.63 4.64 4.72 4.78 4.46 4.49 4.6 7.0

Calcium ion

Ca2+

mg/l 120.1 120.3 132.6 132.7 116.4 116.8 110.2 110.2 102.3 180.0

Magnesium

ion Mg2+

mg/l 9.8 9.9 10.7 10.7 9.6 9.6 9.7 9.8 9.7 200.0

Chloride ion

Cl-

mg/l 142.3 142.4 152.3 152.4 142.3 142.4 141.3 141.5 130.1 350.0

Sulphate

SO42-

mg/l 252.1 252.3 251.4 251.6 178.1 178.9 177.4 178.9 184.5 500.0

Bicarbonate

ion, HCO3-

mg/l 219.8 221.3 218.6 219.2 184.2 184.3 182.5 182.9 192.3 -

Na++K+ ions mg/l 154.3 154.8 156.8 157.2 142.3 143.4 148.1 148.8 147.5 -

Sum of

ions,∑ 1

mg/l 898.4 901.0 922.4 923.8 772.9 775.4 769.2 771.8 766.4 1000.0

Ammonium

ion, NH4+

mg/l 0.332 0.341 0.303 0.312 0.212 0.216 0.212 0.217 0.241 0.39

Nitrite ion,

NO2-

mg/l 0.004 0.005 0.003 0.004 0.004 0.005 0.005 0.006 0.007 0.02

Nitrate ion,

NO3-

mg/l 3.19 3.24 3.22 3.24 2.54 2.55 2.35 2.40 2.45 9.0

Oil & grease mg/l 0.002 0.003 0.002 0.003 0.002 0.003 0.002 0.002 0.002 0.05

Faecal

coliform

per

100

ml

846 852 835 842 890 895 850 855 867 1000

TSS mg/l 0.248 0.252 0.241 0.242 0.174 0.179 0.164 0.167 0.175 0.25

SSAM mg/l 0.02 0.02 0.03 0.03 0.02 0.02 0.01 0.03 0.03 0.1

Phenol mg/l 0.0001 0.0002 0.0001 0.0001 0.0001 0.0001 0.0001 0.0002 0.0002 0.001

Page 59: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 59

6) May 2017

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 6.8 6.9 7.1 7.2 7.2 7.3 7.3 7.4 7.5 6.0-9.0

Electrical

conductivity

X103

cm/c

m

0.215 0.216 0.215 0.217 0.174 0.178 0.183 0.185 0.248 -

Limpidity cm 22.1 22.2 24.1 24.3 25.2 25.0 23.3 23.1 15.4 >30

Turbidity mg/l 16.4 16.3 15.4 15.5 13.3 13.4 14.1 14.4 19.2 >30

Dissolved O2 mg/l 4.0 4.2 4.3 4.4 4.8 4.9 4.5 4.6 4.3 4.6-

6.0

BOD mg/l 1.9 2.0 1.8 2.0 1.3 1.4 1.6 1.8 2.6 3

Total

roughness

mqek

v/l

5.20 5.22 5.32 5.34 3.6 3.62 4.46 4.49 5.8 7.0

Calcium ion

Ca2+

mg/l 119.2 120.3 128.6 129.4 115.6 115.8 118.3 118.5 121.3 180.0

Magnesium

ion Mg2+

mg/l 8.5 8.7 9.3 9.7 8.5 8.6 9.7 9.8 10.5 200.0

Chloride ion

Cl-

mg/l 144.5 145.4 155.3 156.1 140.3 140.4 141.6 141.9 138.4 350.0

Sulphate

SO42-

mg/l 257.6 258.3 258.9 259.6 179.2 179.9 177.4 178.1 203.1 500.0

Bicarbonate

ion, HCO3-

mg/l 222.5 222.8 225.1 226.0 180.1 180.3 185.3 185.9 195.9 -

Na++K+ ions mg/l 157.3 157.8 158.7 159.2 140.7 140.9 151.2 151.6 153.2 -

Sum of

ions,∑ 1

mg/l 910.6 914.3 936.9 941.0 765.4 766.9 783.5 785.8 822.4 1000.0

Ammonium

ion, NH4+

mg/l 0.341 0.343 0.343 0.347 0.180 0.186 0.212 0.217 0.282 0.39

Nitrite ion,

NO2-

mg/l 0.006 0.007 0.003 0.004 0.003 0.004 0.005 0.006 0.009 0.02

Nitrate ion,

NO3-

mg/l 3.32 3.38 3.22 3.24 2.21 2.25 2.35 2.40 3.40 9.0

Oil & grease mg/l 0.002 0.003 0.002 0.003 0.002 0.003 0.002 0.002 0.002 0.05

Faecal

coliform

per

100

ml

869 871 862 870 769 778 852 855 882 1000

TSS mg/l 0.083 0.087 0.081 0.086 0.068 0.072 0.064 0.067 0.097 0.25

SSAM mg/l 0.04 0.05 0.05 0.06 0.01 0.02 0.01 0.03 0.06 0.1

Phenol mg/l 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.001

Page 60: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 60

7) June 2017

Determinant Unit

Penser 1 River Penser 2 River Suhari River Gulyari River

Lake Limit

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

Up

strea

m

Do

wn

strea

m

pH 6.0 6.3 4.5 5.2 4.0 4.7 6.0 6.3 5.2 6.0-9.0

Electrical

conductivity

X103

cm/c

m

0.222 0.222 0.223 0.224 0.182 0.185 0.180 0.182 0.247 -

Limpidity cm 20.1 20.4 20.3 20.5 24.0 24.1 23.5 23.6 17.5 >30

Turbidity mg/l 21.4 21.3 17.6 17.7 14.3 14.4 15.2 15.6 20.4 >30

Dissolved O2 mg/l 3.2 3.2 3.4 3.4 3.6 3.7 3.7 3.6 3.5 4.6-

6.0

BOD mg/l 2.2 2.3 1.9 1.9 1.9 1.9 1.8 1.7 2.1 3

Total

roughness

mqek

v/l

5.19 5.20 5.32 5.32 3.58 3.60 4.40 4.42 6.0 7.0

Calcium ion

Ca2+

mg/l 120.2 120.1 129.0 129.2 115.4 115.3 117.5 117.6 128.0 180.0

Magnesium

ion Mg2+

mg/l 10.1 10.2 10.2 10.4 9.8 9.9 10.5 10.6 10.1 200.0

Chloride ion

Cl-

mg/l 148.3 148.4 152.1 152.0 142.2 142.2 142.6 143.8 144.4 350.0

Sulphate

SO42-

mg/l 257.3 258.5 258.4 258.5 175.0 176.6 178.1 179.0 200.4 500.0

Bicarbonate

ion, HCO3-

mg/l 221.1 221.2 223.1 223.2 179.3 180.0 180.1 180.3 194.2 -

Na++K+ ions mg/l 158.3 159.2 160.0 160.2 144.6 144.6 144.2 145.0 153.2 -

Sum of

ions,∑ 1

mg/l 915.1 916.1 935.2 936.3 768.4 770.2 774.0 775.2 830.0 1000.

0

Ammonium

ion, NH4+

mg/l 0.367 0.368 0.355 0.356 0.186 0.187 0.217 0.217 0.320 0.39

Nitrite ion,

NO2-

mg/l 0.008 0.008 0.006 0.007 0.005 0.005 0.005 0.006 0.006 0.02

Nitrate ion,

NO3-

mg/l 3.50 3.55 3.64 3.66 2.26 2.28 2.33 2.39 3.51 9.0

Oil & grease mg/l 0.003 0.003 0.001 0.001 0.002 0.003 0.001 0.002 0.002 0.05

Faecal

coliform

per

100

ml

882 889 883 893 760 768 854 860 873 1000

TSS mg/l 0.050 0.052 0.060 0.062 0.060 0.061 0.064 0.066 0.078 0.25

SSAM mg/l 0.02 0.02 0.04 0.05 0.04 0.04 0.02 0.03 0.06 0.1

Phenol mg/l 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.0001 0.001

Page 61: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 61

Air Quality

1) Pre-Construction Monitoring

Monitoring locations Determinand Concentration Allowed concentration Contractor Camp Dust 0.2 0.5

NO2 0.040 0.085 Carbon monoxide 1 5

Sensitive Receptor 1 Dust 0.2 0.5 NO2 0.039 0.085 Carbon monoxide 1 5

Sensitive Receptor 2 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.1 0.5 NO2 0.041 0.085 Carbon monoxide 1 5

Sensitive Receptor 5 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.050 0.085 Carbon monoxide 3 5

Sensitive Receptor 7 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 1 5

Burjali village Dust 0.2 0.5 NO2 0.052 0.085 Carbon monoxide 3 5

Yuxari Nuvedi village

Dust 0.3 NO2 0.055 Carbon monoxide 3

Bellebur village

Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 1 5

Page 62: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 62

2) January 2017

Monitoring locations Determinand Concentrati on Allowed concentration

Burjali village Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 2 5

Yuxari Nuvedi village

Dust 0.2 0.5 NO2 0.037 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.029 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.1 0.5 NO2 0.030 0.085 Carbon monoxide 2 5

Sensitive Receptor 5 Dust 0.2 0.5 NO2 0.034 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.036 0.085 Carbon monoxide 3 5

Sensitive Receptor 7 Dust 0.1 0.5 NO2 0.030 0.085 Carbon monoxide 2 5

3) February 2017

Monitoring locations Determinand Concentration Allowe d concentration

Burjali village Dust 0.1 0.5 NO2 0.030 0.085 Carbon monoxide 2 5

Yuxari Nuvedi village

Dust 0.2 0.5 NO2 0.033 0.085 Carbon monoxide 1 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.025 0.085 Carbon monoxide 1 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.034 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.032 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.1 0.5 NO2 0.031 0.085 Carbon monoxide 1 5

Sensitive Receptor 5 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.030 0.085 Carbon monoxide 1 5

Sensitive Receptor 7 Dust 0.1 0.5 NO2 0.027 0.085 Carbon monoxide 2 5

Page 63: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 63

4) March 2017

Monitoring locations Determinand Concentration Allowed concentra tion

Burjali village Dust 0.1 0.5 NO2 0.034 0.085 Carbon monoxide 2 5

Yuxari Nuvedi village

Dust 0.2 0.5 NO2 0.039 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.033 0.085 Carbon monoxide 1 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.030 0.085 Carbon monoxide 1 5

Sensitive Receptor 3 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.2 0.5 NO2 0.037 0.085 Carbon monoxide 2 5

Sensitive Receptor 5 Dust 0.1 0.5 NO2 0.038 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.036 0.085 Carbon monoxide 1 5

Sensitive Receptor 7 Dust 0.1 0.5 NO2 0.031 0.085 Carbon monoxide 2 5

5) April 2017

Monitoring locations Determinand Concentration Allowed concentration

Burjali village Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Yuxari Nuvedi village

Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.1 0.5 NO2 0.039 0.085 Carbon monoxide 1 5

Sensitive Receptor 2 Dust 0.1 0.5 NO2 0.035 0.085 Carbon monoxide 1 5

Sensitive Receptor 3 Dust 0.2 0.5 NO2 0.037 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 5 Dust 0.2 0.5 NO2 0.039 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 1 5

Sensitive Receptor 7 Dust 0.1 0.5 NO2 0.036 0.085 Carbon monoxide 2 5

Page 64: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 64

6) May 2017

Monitoring locations Determinand Concentration Allowed concentration

Burjali village Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Yuxari Nuvedi village

Dust 0.3 0.5 NO2 0.049 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.2 0.5 NO2 0.038 0.085 Carbon monoxide 1 5

Sensitive Receptor 3 Dust 0.2 0.5 NO2 0.039 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Sensitive Receptor 5 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Sensitive Receptor 7 Dust 0.2 0.5 NO2 0.041 0.085 Carbon monoxide 2 5

7) June 2017

Monitoring locations Determinand Concentration Allowed concentration

Burjali village Dust 0.2 0.5 NO2 0.050 0.085 Carbon monoxide 2 5

Yuxari Nuvedi village

Dust 0.3 0.5 NO2 0.052 0.085 Carbon monoxide 2 5

Sensitive Receptor 1 Dust 0.2 0.5 NO2 0.046 0.085 Carbon monoxide 2 5

Sensitive Receptor 2 Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Sensitive Receptor 3 Dust 0.2 0.5 NO2 0.042 0.085 Carbon monoxide 2 5

Sensitive Receptor 4 Dust 0.3 0.5 NO2 0.047 0.085 Carbon monoxide 2 5

Sensitive Receptor 5 Dust 0.2 0.5 NO2 0.040 0.085 Carbon monoxide 2 5

Sensitive Receptor 6 Dust 0.2 0.5 NO2 0.045 0.085 Carbon monoxide 2 5

Sensitive Receptor 7 Dust 0.2 0.5 NO2 0.046 0.085 Carbon monoxide 3 5

Page 65: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 65

Noise & Vibration

1) Pre-Construction Monitoring

Noise level (dB)

Monitoring locations Results Allowed Haftoni Settlement 31 50 Sensitive Receptor 1 29 50 Sensitive Receptor 2 30 50 Sensitive Receptor 3 32 50 Sensitive Receptor 4 31 50 Sensitive Receptor 5 32 50 Sensitive Receptor 6 35 50 Sensitive Receptor 7 30 50 Burjali village 47 50 Yuxari Nuvadi village 47 50 Bellebur village 31 50

Vibration level (dB)

Monitoring locations Results Allowed Haftoni Settlement 36 77 Sensitive Receptor 1 30 77 Sensitive Receptor 2 28 77 Sensitive Receptor 3 26 77 Sensitive Receptor 4 28 77 Sensitive Receptor 5 29 77 Sensitive Receptor 6 26 77 Sensitive Receptor 7 27 77 Burjali village 30 77 Yuxari Nuvadi village 54 77 Bellebur village 36 77

Page 66: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 66

2) January 2017

Noise level (dB)

Monitoring locations Results Allowed Burjali village 38.1 50 Yuxari Nuvadi village 41.5 50 Sensitive Receptor 1 34.4 50 Sensitive Receptor 2 32.7 50 Sensitive Receptor 3 35.5 50 Sensitive Receptor 4 30.3 50 Sensitive Receptor 5 33.6 50 Sensitive Receptor 6 35.4 50 Sensitive Receptor 7 31.7 50

Vibration level (dB)

Monitor ing locations Results Allowed Burjali village 34 77 Yuxari Nuvadi village 45 77 Sensitive Receptor 1 30 77 Sensitive Receptor 2 33 77 Sensitive Receptor 3 35 77 Sensitive Receptor 4 31 77 Sensitive Receptor 5 32 77 Sensitive Receptor 6 34 77 Sensitive Receptor 7 32 77

3) February 2017

Noise level (dB)

Monitoring locations Results Allowed Burjali village 35.5 50 Yuxari Nuvadi village 40.2 50 Sensitive Receptor 1 32.1 50 Sensitive Receptor 2 32.4 50 Sensitive Receptor 3 33.7 50 Sensitive Receptor 4 30.4 50 Sensitive Receptor 5 33.1 50 Sensitive Receptor 6 36.2 50 Sensitive Receptor 7 30.4 50

Page 67: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 67

Vibration level (dB)

Monitoring locations Results Allowed Burjali village 31 77 Yuxari Nuvadi village 42 77 Sensitive Receptor 1 32 77 Sensitive Receptor 2 30 77 Sensitive Receptor 3 33 77 Sensitive Receptor 4 30 77 Sensitive Receptor 5 36 77 Sensitive Receptor 6 37 77 Sensitive Receptor 7 35 77

4) March 2017

Noise level (dB)

Monitoring locations Results Allowed Burjali village 37.1 50 Yuxari Nuvadi village 40.0 50 Sensitive Receptor 1 32.5 50 Sensitive Receptor 2 33.2 50 Sensitive Receptor 3 35.5 50 Sensitive Receptor 4 32.1 50 Sensitive Receptor 5 35.2 50 Sensitive Receptor 6 35.6 50 Sensitive Receptor 7 32.4 50

Vibration level (dB)

Monitoring locations Results Allowed Burjali village 34 77 Yuxari Nuvadi village 45 77 Sensitive Receptor 1 36 77 Sensitive Receptor 2 33 77 Sensitive Receptor 3 35 77 Sensitive Receptor 4 32 77 Sensitive Receptor 5 35 77 Sensitive Receptor 6 38 77 Sensitive Receptor 7 36 77

Page 68: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 68

5) April 2017

Noise level (dB)

Monitoring locations Results Allowed Burjali village 38.5 50 Yuxari Nuvadi village 42.3 50 Sensitive Receptor 1 36.2 50 Sensitive Receptor 2 35.6 50 Sensitive Receptor 3 35.1 50 Sensitive Receptor 4 37.3 50 Sensitive Receptor 5 35.5 50 Sensitive Receptor 6 37.2 50 Sensitive Receptor 7 34.7 50

Vibration level (dB)

Monitoring locations Results Allowed Burjali village 36 77 Yuxari Nuvadi village 48 77 Sensitive Receptor 1 38 77 Sensitive Receptor 2 35 77 Sensitive Receptor 3 37

77

Sensitive Receptor 4 36 77 Sensitive Receptor 5 35 77 Sensitive Receptor 6 39 77 Sensitive Receptor 7 37 77

6) May 2017

Noise level (dB)

Monitoring loc ations Results Allowed Burjali village 39.1 50 Yuxari Nuvadi village 44.5 50 Sensitive Receptor 1 37.3 50 Sensitive Receptor 2 35.2 50 Sensitive Receptor 3 38.6 50 Sensitive Receptor 4 36.2 50 Sensitive Receptor 5 35.4 50 Sensitive Receptor 6 38.1 50 Sensitive Receptor 7 37.3 50

Page 69: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 69

Vibration level (dB)

Monitoring locations Results Allowed Burjali village 40 77 Yuxari Nuvadi village 52 77 Sensitive Receptor 1 39 77 Sensitive Receptor 2 37 77 Sensitive Receptor 3 38

77

Sensitive Receptor 4 35 77 Sensitive Receptor 5 38 77 Sensitive Receptor 6 40 77 Sensitive Receptor 7 39 77

7) June 2017

Noise level (dB)

Monitoring locations Results Allowed Burjali village 40.5 50 Yuxari Nuvadi village 45.0 50 Sensitive Receptor 1 39.2 50 Sensitive Receptor 2 35.5 50 Sensitive Receptor 3 39.3 50 Sensitive Receptor 4 37.7 50 Sensitive Receptor 5 38.1 50 Sensitive Receptor 6 35.4 50 Sensitive Receptor 7 36.0 50

Vibration level (dB)

Monitoring locations Results Allowed Burjali village 45

77

Yuxari Nuvadi village 55 77 Sensitive Receptor 1 42 77 Sensitive Receptor 2 39 77 Sensitive Receptor 3 40

77

Sensitive Receptor 4 35 77 Sensitive Receptor 5 42 77 Sensitive Receptor 6 45 77 Sensitive Receptor 7 43 77

Page 70: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 70

Appendix 2: List of participants at public consulta tions and Minutes of Meeting

Section B: 2nd March 2017

Minutes of Meeting

Rashad Karimov – Environmental Protection Manager of Section B firstly welcomed all participants and informed that “Ozgun” is committed to integration with the society and the environment. He said that, we would like to bring into your attention that, under the offer of Azer Road Service OJC, the construction of Masalli – Astara project (Section B) is being carried out by “Ozgün Construction Industry and Trade Co” Inc, and work are currently scheduled to be completed by 2017. According to ecological and environmental policy of the company, we are constantly monitoring ecology and safety requirements at international level. However it is impossible to avoid of some negative impacts during construction (e.g. dust-mist, noise, vibration etc.) We do apologize to the owners of land, houses and etc. on behalf of our company administration for the temporary inconvenience that will be generated during the process of construction.

He said that Public Information Leaflets outlines the Masalli – Astara Motorway (Section B) project and describes the construction process. The leaflets also provide information on how to register complaints during the construction so that your concerns are dealt with swiftly and to your satisfaction. As a responsible contractor, “Ozgün Construction Industry and Trade Co” Inc is working with the Engineer

Page 71: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 71

and Owner. Therefore Ozgün was already established a Grievance Redress Mechanism to ensure swift and satisfactory resolution of local public issues arising from the construction activities.

The GRM system consists of following steps below:

• People should contact with Grievances Focal Point (GFP). For Haftoni – Laj area the GFP is Rovshen Zeynalov (050-546-86-20), for Luveser – Lenkaran area the GFP is Aflatun Askerov (050-365-89-65), for Sovu – Lenkaran area the GFP is Kamal Huseynov (050-346-31-21) and for Dasdaligjar – Lenkaran area the GFP is Nazim Emenullayev (050-343-00-45);

• Your local GFP will meet with ÖZGÜN (the Contractor), register the complaint and will try to find a satisfactory solution;

• If your local GFP is not able to reach agreement with the Contractor, or if the Contractor does not solve the problem within one week, your GFP should contact the Project Supervision Consultant (assistant team leader) Farrux Mutallimov (055-450-69-79) and report the problem;

• If the complaint has not been dealt within a further 2 weeks the GFP will present the complaint to the Grievances Redress Committee (composed of representatives from the Contractor, Supervision Consultants, AAY and local government);

• The Grievance Redress Committee will decide a final resolution on the complaint within 2 weeks.

Even though he mentioned about waste problem near the Moscow Forest area. He said that it is very pity that the local village people still continuing to litter different kind of domestic waste close to Moscow Forest area. Please help us for solution this problem and protect the local environment.

Questions asked during the meetings were as follows:

Safiq Abbasov – from Dasdaligjar village (male)

Q: When the construction process will be finished for Section B?

A: The construction works are currently scheduled to be completed by 2017.

Nazim Emenullayev – from Dasdaligjar village Municipality (male)

Q: Please help for recruited workers from Dasdaligjar village communities.

A: HR Manager Heydar Heydarov has already been informed about this issue and it will be

solved during construction process. The contact mobile number of Heydar is (055-450-69-94)

Nazim Emenullayev – from Dasdaligjar village Municipality (male)

Q: When the contractor will repair the Dasdaligjar village road near the Bridge No 8?

A: Project Manager Perviz Ahmedzadeh has already been informed about this problem and it

will be solved next week. The contact mobile number of Perviz is (055-450-69-59)

Page 72: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 72

Section B: 11th June 2017

Page 73: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 73

Minutes of Meeting

Rashad Karimov – Environmental Protection Manager of Section B firstly welcomed all participants and informed that “Ozgun” is committed to integration with the society and the environment. He said that, we would like to bring into your attention that, under the offer of Azer Road Service OJC, the construction of Masalli – Astara project (Section B) is being carried out by “Ozgün Construction Industry and Trade Co” Inc, and work are currently scheduled to be completed by 2017. According to ecological and environmental policy of the company, we are constantly monitoring ecology and safety requirements at international level. However it is impossible to avoid of some negative impacts during construction (e.g. dust-mist, noise, vibration etc.) We do apologize to the owners of land, houses and etc. on behalf of our company administration for the temporary inconvenience that will be generated during the process of construction.

He said that Public Information Leaflets outlines the Masalli – Astara Motorway (Section B) project and describes the construction process. The leaflets also provide information on how to register complaints during the construction so that your concerns are dealt with swiftly and to your satisfaction. As a responsible contractor, “Ozgün Construction Industry and Trade Co” Inc is working with the Engineer and Owner. Therefore Ozgün was already established a Grievance Redress Mechanism to ensure swift and satisfactory resolution of local public issues arising from the construction activities.

The GRM system consists of following steps below:

• People should contact with Grievances Focal Point (GFP). For Haftoni – Laj area the GFP is Rovshen Zeynalov (050-546-86-20), for Luveser – Lenkaran area the GFP is Aflatun Askerov (050-365-89-65), for Sovu – Lenkaran area the GFP is Kamal Huseynov (050-346-31-21) and for Dasdaligjar – Lenkaran area the GFP is Nazim Emenullayev (050-343-00-45);

• Your local GFP will meet with ÖZGÜN (the Contractor), register the complaint and will try to find a satisfactory solution;

• If your local GFP is not able to reach agreement with the Contractor, or if the Contractor does not solve the problem within one week, your GFP should contact the Project Supervision Consultant (assistant team leader) Farrux Mutallimov (055-450-69-79) and report the problem;

• If the complaint has not been dealt within a further 2 weeks the GFP will present the complaint to the Grievances Redress Committee (composed of representatives from the Contractor, Supervision Consultants, AAY and local government);

• The Grievance Redress Committee will decide a final resolution on the complaint within 2 weeks.

Note: During the meeting there was no question from the local community.

Page 74: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 74

Section C: 7th March 2017

Minutes of Meeting

Ayaz Abdurrehmanov – Health and Safety Manager of Section C firstly welcomed all participants and informed that “Polat” is committed to integration with the society and the environment. It has made it a priority to provide the best working environment for its employees, taking into account the human and safety factors, in a spirit of responsibility towards the environment, and has undertaken to minimize occupational diseases and accidents at work.

He said that Public Information Leaflets outlines the Masalli – Astara Motorway (Section C) project and describes the construction process. The leaflets also provide information on how to register complaints during the construction so that your concerns are dealt with swiftly and to your satisfaction. As a responsible contractor, Polat is working with the Engineer and Owner. Therefore Polat was already established a Grievance Redress Mechanism to ensure swift and satisfactory resolution of local public issues arising from the construction activities.

The GRM system consists of following steps below:

Page 75: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 75

• People should contact with Grievances Focal Point (GFP). For Burjali – Rvo (Lenkeran) area the GFP is Kamal Huseynov (050-346-31-21), for Kakalos – Shiyakaran (Astara) area the GFP is Cefer Ahmedov (050-371-73-96) and Tofiq Aliyev (050-313-08-37);

• Your local GFP will meet with POLAT (the Contractor Project Manager 051-297-95-96), register the complaint and will try to find a satisfactory solution;

• If your local GFP is not able to reach agreement with the Contractor, or if the Contractor does not solve the problem within one week, your GFP should contact the Project Supervision Consultant (assistant team leader) Ferrux Mutellimov (055-450-69-79) and report the problem;

• If the complaint has not been dealt within a further 2 weeks the GFP will present the complaint to the Grievances Redress Committee (composed of representatives from the Contractor, Supervision Consultants, AAY and local government);

• The Grievance Redress Committee will decide a final resolution on the complaint within 2 weeks.

Alieva Sevda – Burjali village representative said that during the road construction process contractor was solved all problems raised by local villages people we are very happy that the construction process for Masalli – Astara Motorway (Section C) is finishing. It is a big project and will have a positive impact on regional development. Even though he said that it is good that the contractor company as Polat wants to share all information with the local community helps to the local people by providing them with different jobs according to their ability.

Note: During the meeting there was no question from the local community.

Page 76: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 76

Section C: 12th June 2016

Minutes of Meeting

Ayaz Abdurrehmanov – Health and Safety Manager of Section C firstly welcomed all participants and informed that “Polat” is committed to integration with the society and the environment. It has made it a priority to provide the best working environment for its employees, taking into account the human and safety factors, in a spirit of responsibility towards the environment, and has undertaken to minimize occupational diseases and accidents at work.

He said that Public Information Leaflets outlines the Masalli – Astara Motorway (Section C) project and describes the construction process. The leaflets also provide information on how to register complaints during the construction so that your concerns are dealt with swiftly and to your satisfaction. As a responsible contractor, Polat is working with the Engineer and Owner. Therefore Polat was already established a Grievance Redress Mechanism to ensure swift and satisfactory resolution of local public issues arising from the construction activities.

The GRM system consists of following steps below:

• People should contact with Grievances Focal Point (GFP). For Burjali – Rvo (Lenkeran) area the GFP is Kamal Huseynov (050-346-31-21), for Kakalos – Shiyakaran (Astara) area the GFP is Cefer Ahmedov (050-371-73-96) and Tofiq Aliyev (050-313-08-37);

Page 77: Bi-annual Environmental Monitoring Report...Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) ii CURRENCY EQUIVALENTS (As of 1 June 2017)

Twelfth Bi-annual environmental monitoring report for the Masalli to Astara Motorway (Part II) 77

• Your local GFP will meet with POLAT (the Contractor Project Manager 051-297-95-96), register the complaint and will try to find a satisfactory solution;

• If your local GFP is not able to reach agreement with the Contractor, or if the Contractor does not solve the problem within one week, your GFP should contact the Project Supervision Consultant (assistant team leader) Ferrux Mutellimov (055-450-69-79) and report the problem;

• If the complaint has not been dealt within a further 2 weeks the GFP will present the complaint to the Grievances Redress Committee (composed of representatives from the Contractor, Supervision Consultants, AAY and local government);

• The Grievance Redress Committee will decide a final resolution on the complaint within 2 weeks.

Note: During the meeting there was no question from the local community.