BHUTAN POWER CORPORATION...

18

Transcript of BHUTAN POWER CORPORATION...

Page 1: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV
Page 2: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER CORPORATION LIMITED

BHUTAN POWER SYSTEM OPERATOR (BPSO)

THIMPHU: BHUTAN

BHUTAN POWER SYSTEM CONTINGENCY PLAN

&

OPERATING PROCEDURES

Reviewed and updated in November 2019

BPSO

Page 3: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

Table of Contents

1 INTRODUCTION ....................................................................................................... 1

2 SYSTEM IMPROVEMENT FEATURES ................................................................. 1

2.1 Basochu (BHP) Pondage ......................................................................................... 1

2.2 Reactor in Tala Hydro Power Plant (THP) .............................................................. 1

2.3 Reactor in Kurichu Hydro Power Plant ................................................................... 1

2.4 Reactor at Jigmeling................................................................................................ 1

2.5 Reactor at MHEP .................................................................................................... 1

3 BUS CONFIGURATION ............................................................................................ 2

3.1 220kV Semtokha substation .................................................................................... 2

3.2 220kV Chukha Switchyard...................................................................................... 2

3.3 400kV Malbase substation ...................................................................................... 3

3.4 220kV Rurichu Switchyard ..................................................................................... 4

3.5 220kV Tsirang Substation ....................................................................................... 4

3.6 400/220kV Jigmeling Substation ............................................................................. 5

4 SYSTEM UNDER NORMAL CONDITION ............................................................. 6

5 CONTINGENCY AND OPERATING PROCEDURE .............................................. 6

5.1 Failure of 220kV Rurichu-Semtokha line ................................................................ 6

5.2 Failure of 220kV Rurichu-Semtokha and 220kV Rurichu-Tsirang Lines ................. 7

5.3 Failure of 220kV Rurichhu-Semtokha and 220kV Tsirang-Jigmeling Lines ............ 8

5.4 Failure of 220kV Chukha-Semtokha and 220kV Rurichhu-Tsirang lines ................. 9

5.4.1 Operation procedure for above line failure ....................................................... 9

5.5 Western black out (Semtokha)............................................................................... 10

5.6 Failure of any one of 220kV Chukha-Birpara lines during the peak generation ...... 12

5.7 Failure of 220kV D/C Chukha-Birpara lines.......................................................... 13

5.7.1 Operation procedure for above line failure ..................................................... 14

5.8 Total shutdown of KHP during peak season under normal system condition. ........ 14

5.9 Utilization of 400/220kV ICT at Jigmeling ........................................................... 14

Page 4: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 1 of 14

1 INTRODUCTION

The Bhutan Power System Contingency Plan & Operating Procedures document shall be

a dynamic document, which will be updated with change in power system network. Any

necessary revision arising out of the changes in the power system network shall be made after

thorough discussion in the Operation Coordination Committee (OCC) meetings. The

endorsement shall also be done by OCC forum.

2 SYSTEM IMPROVEMENT FEATURES

The power system infrastructural features such as the pondage and the reactors play a critical

role in improving the grid security. Brief explanation on the utilization of pondage and the

reactors at various plants and substation is as described below.

2.1 Basochu (BHP) Pondage

Under normal condition, Basochu pondage shall be kept filled to meet the Thimphu load during

emergency. BHP shall inform the System Operator before depletion or maintenance of the

pondage.

2.2 Reactor in Tala Hydro Power Plant (THP)

THP has a shunt reactor of 1x63 MVAR, which shall be connected to the 400kV bus when the

system voltage goes above the permissible limit of 1.05 times the rated voltage while the same

shall be disconnected when the system voltage goes below the permissible limit of 0.95 times

the rated voltage.

2.3 Reactor in Kurichu Hydro Power Plant

Kurichhu Hydropower Plant (KHP) has a shunt reactor of 1x5 MVAR, which shall be

connected to the 132kV bus when the system voltage goes above the permissible limit of 1.05

times the rated voltage while the same shall be disconnected when the system voltage goes

below the permissible limit of 0.95 times the rated voltage.

2.4 Reactor at Jigmeling

Jigmeling has a shunt reactor of 2 x 80 MVAR, which shall be connected to the 400kV bus

when the system voltage goes above the permissible limit of 1.05 times the rated voltage while

the same shall be disconnected when the system voltage goes below the permissible limit of

0.95 times the rated voltage. As per the requirement of the grid, the System Operator shall

instruct operators at Jigmeling to put ON both the reactors.

2.5 Reactor at MHEP

Mangdechu Hydro Electric Plant (MHEP) has a shunt reactor of 1x80 MVAR, which shall be

connected to the 400kV bus when the system voltage goes above the permissible limit of 1.05

times the rated voltage while the same shall be disconnected when the system voltage goes

below the permissible limit of 0.95 times the rated voltage.

Page 5: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 2 of 14

3 BUS CONFIGURATION

With the bus coupler remaining healthy, the bus configuration shall be kept as described below.

3.1 220kV Semtokha substation

a. The 220kV Chukha-Semtokha line and one of the 50MVA, 220/66kV transformers shall

be connected to Bus A.

b. The 220kV Rurichu-Semtokha line and other 50 MVA, 220/66kV transformers shall be

connected to Bus B.

c. The bus coupler shall be kept closed.

CHP Incomer

Rurichu Incomer

50MVA220/66kV

50MVA220/66kV

Bus A

Bus B

Figure 3-1 Bus Configuration of Semtokha Substation

3.2 220kV Chukha Switchyard

a. Two generating units and two 20 MVA, 220/66kV transformers along with the 220kV

CHP-Malbase and 220kV CHP-Semtokha feeders shall be connected to Bus A. The

configuration shall be changed depending on the season.

b. Two other generating units and two 220kV CHP-Birpara lines shall be connected to Bus

B.

c. The bus coupler shall be kept closed.

Unit-III & IV

2x20MVA220/66kV

Bus B

Bus A

GUnit-I & II

G

Semtokha

Birpara-IIBirpara-I

Malbase

Figure 3-2 Bus Configuration of Chukha Switchyard

Page 6: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 3 of 14

3.3 400kV Malbase substation

a. The 400kV Tala-Malbase line and 400kV Malbase-Siliguri line shall be connected to

400kV Bus A, while 400/220kV 200MVA ICT shall be connected to 400kV Bus B.

b. The tie-breaker shall be kept closed.

c. The 220kV Chukha-Malbase line and 220kV Malbase-Birpara line shall be connected to

220kV Bus A, while the 400/220kV 200MVA Inter connecting transformer (ICT) along

with the Bhutan load (220kV Malbase-Singhegaon line, 220kV Malbase-Damdum and

all 220/66kV transformers) shall be connected to 220kV Bus B.

d. The bus coupler shall be kept closed.

Bus A

Bus B

Siliguri

Birpara CHP

Tala

Singyegaon Damdum

Bus A

Bus B

3x220/66kV

400/220kV 200 MVA

Figure 3-3 Bus Configuration of Malbase Substation

Page 7: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 4 of 14

3.4 220kV Rurichu Switchyard

a. One generating unit along with the 220kV Rurichu-Semtokha line shall be connected to

Bus A, while the other generating unit along with the 220kV Rurichu-Tsirang line and

30MVA, 220/66kV ICT shall be connected to Bus B.

b. The bus coupler shall be kept closed.

Unit-I30MVA

220/66kV ICT

Bus A

Bus B

GUnit-II

G

Semtokha

Tsirang

Figure 3-4 Bus Configuration of Rurichu Switchyard

3.5 220kV Tsirang Substation

a. The 220kV Dagachu-Tsirang line, 220kV Tsirang–Jigmeling line and one of the 10MVA,

220/66kV transformers shall be connected to Bus A, while 220kV Rurichu-Tsirang line

and other 10MVA, 220/66kV transformer shall be connected to Bus B.

b. The bus coupler shall be kept closed.

10MVA220/66kV ICT

Bus A

Bus B

Rurichhu

JigmelingDagachhu 10MVA 220/66kV ICT

Figure 3-5 Bus Configuration of Tsirang Substation

Page 8: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 5 of 14

3.6 400/220kV Jigmeling Substation

a. 400kV MHPA-Jigmeling Feeder 1 & 2 and 400kV Jigmeling-Alipurduar feeder 1&2

shall be connected to Bus A.

b. 400kV MHPA-Jigmeling feeder 3 & 4 along with 500MVA, 400/220kV ICT shall be

connected to Bus B.

c. All tie breaker shall kept closed

d. The 220kV Tsirang–Jigmeling line along with 2X63/80MVA, 220/132kV ICT shall be

connected to Bus A.

e. The bus coupler shall be kept Closed.

Bus B

MHPA-2

MHPA-1MHPA-3

MHPA-4

Alipurduar-2Alipurduar-1

2 X 63/80MVA220/132kV ICT

Bus A

Bus B

Tsirang

Bus A

ICT

Figure 3-6 Bus Configuration of 400kV Jigmeling Substation

Page 9: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 6 of 14

4 SYSTEM UNDER NORMAL CONDITION

Under normal condition, the system for the western grid will be kept as follows irrespective of

the seasons:

a. Both the 66kV Chukha-Semtokha line and 220kV Chukha-Semtokha line shall be in

service to form a ring. However, in the Peak Season, the 66kV Olakha-Bjemina shall be

kept opened to avoid the overloading.

b. Both the 66kV Rurichu-Semtokha line and 220kV Rurichu-Semtokha line shall be service

to form a ring.

c. The 66kV Chukha-Phuentsholing line, 66kV Pling-Gomtu and with 66kV Phuentsholing-

Malbase line shall be kept in ring with 220kV Chukha-Malbase and 220kV Malbase-

Damdum.

d. The eastern and western grid shall be kept connected via 220kV Tsirang-Jigmeling line.

e. During the peak seasons, all the international lines shall be kept in service. However,

during the lean seasons some international lines shall be kept OPEN/CLOSE as per system

requirement.

5 CONTINGENCY AND OPERATING PROCEDURE

5.1 Failure of 220kV Rurichu-Semtokha line

Tintibi

Jigmeling

Gelephu

15.4km

Chukha

(4X84MW)

45.74km

Semtokha

54

.01

km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

50km

70.21km

Basochu(L)

(2X20MW)

Basochu(U)

(2X12MW)

ChukhaWatsa Tap

21.88km

Chumdo

15.1km11.78km

Jemina17.66km

Olakha

1.7km

Semtokha

Dechencholing

11.45km

3.08km

Lobeysa

21.8km

24.33kmGewathang

Basochu(L)

1.5

km

2x15MVA 66/11kV

2x30MVA 220/11kV

30MVA 220/66kV

2x10MVA 220/66kV

2X72MVA 220/11kV

2x50/63MVA 220/66kV

4X105MVA 220/11kV

2x20MVA 220/66kV

2X80MVA 220/132kV

Salakati

Birpara

40.77km

Dog

Dog

70.21km

Panther

Do

g

Dog

Dog

Dog

Dog

Zebra

Zeb

ra

Dog Dog Dog Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Panther

Panther

Malbase

Figure 5-1 Failure of 220kV Rurichhu-Semtokha Line

During the peak seasons, there is a high probability of getting 66kV Rurichu-Gewathang-

Lobeysa line overloaded when there is a failure of 220kV Rurichhu-Semtokha line. So,

Page 10: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 7 of 14

30MVA ICT at BHP shall be kept opened, thereby segregating the lower and upper stage of

BHP.

System Operator shall instruct BHP to back down their generation, if required, so that the

power flowing towards east should be such that 132 kV Jigmeling-Gelephu-Salakati section is

not overloaded.

5.2 Failure of 220kV Rurichu-Semtokha and 220kV Rurichu-Tsirang Lines

If the 220kV Rurichu-Semtokha line fails along with the failure of 220kV Rurichu-Tsirang

line, the System Operator shall instruct BHP to back down its generation till its total generation

is equal to carrying capacity of the 66kV Rurichu-Lobeysa line during peak seasons.

System Operator shall instruct DHPC to back down its generation, if required, power flowing

towards east should be such that 132 kV Jigmeling-Gelephu-Salakati section is not overloaded.

In such cases, if it leads to overloading of 132kV Nangkor-Deothang line, 132kV Nangkor-

Nganglam or 132kV Nganglam-Tintibi shall be kept opened. Coincidentally, in such a case, if

the Nganglam load (DCCL) is under shutdown, DHPC shall back down its generation.

After the clearance of faults on the above lines, the synchronization shall be carried out at BHP

end.

JigmelingChukha

(4X84MW)

Semtokha

54.0

1km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)

Basochu(U)

(2X12MW)

Olakha

1.7km

Semtokha

Dechencholing

11.45km

3.08km

Lobeysa

21.8km

24.33km

Gewathang

Olakha

Basochu(L)

1.5

km

2x15MVA 66/11kV

2x30MVA 220/11kV

30MVA 220/66kV

2x10MVA 220/66kV

2x5MVA 66/33kV

2X72MVA 220/11kV

3x10/12.5MVA 66/33kV

2x50/63MVA 220/66kV

2x20MVA 66/33kV

4X105MVA 220/11kV

2X80MVA 220/132kV

Birpara

40.77km

Dog

Dog

70.21km

Dog

Dog

Dog

Dog

Zebra

Zeb

ra

Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Zebra

Chukha2x20MVA 220/66kV

Figure 5-2 Failure of 220kV Semtokha-Rurichu-Tsirang Lines

Page 11: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 8 of 14

5.3 Failure of 220kV Rurichhu-Semtokha and 220kV Tsirang-Jigmeling

Lines

If the 220kV Rurichhu – Semtokha line fails along with the failure of 220kV Tsirang –

Jigmeling line, the System Operator shall instruct Dagachhu Hydropower Corporation Ltd.

(DHPC) and BHP to back down its generation until its total generation is equal to power

carrying capacity of the 66kV Rurichhu – Lobeysa line depending upon priority.

After the clearance of faults on the above lines, the line shall be closed at Jigmeling end.

Similarly, for 220kV Rurichhu-Semtokha, it shall be closed at Rurichu end.

If 220kV Tsirang-Jigmeling could not be closed, 220kV BHP-Tsirang shall be kept opened at

both ends after which 220kV Tsirang-Jigmeling shall be closed. DHPC shall then be synced at

Tsirang end.

JigmelingChukha

(4X84MW)

Semtokha

54.0

1km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)

Basochu(U)

(2X12MW)

Olakha

1.7km

Semtokha

Dechencholing

11.45km

3.08km

Lobeysa

21.8km

24.33km

Gewathang

Olakha

Basochu(L)

1.5

km

2x15MVA 66/11kV

2x30MVA 220/11kV

30MVA 220/66kV

2x10MVA 220/66kV

2x5MVA 66/33kV

2X72MVA 220/11kV

3x10/12.5MVA 66/33kV

2x50/63MVA 220/66kV

2x20MVA 66/33kV

4X105MVA 220/11kV

2X80MVA 220/132kV

Birpara

40.77km

Dog

Dog

70.21km

Dog

Dog

Dog

Dog

Zebra

Zebra

Zebra

Zebra

Zebra

Zebra

ZebraZebra

Zebra

Zebra

Chukha2x20MVA 220/66kV

Jigmeling

Figure 5-3 Failure of 220kV Rurichu-Semtokha & 220kV Tsirang-Jigmeling

Page 12: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 9 of 14

5.4 Failure of 220kV Chukha-Semtokha and 220kV Rurichhu-Tsirang

lines

If 220kV Chukha-Semtokha line and 220kV Rurichhu-Tsirang line fails during the lean

generation, Basochu pondage shall be utilized to meet the Thimphu load including the Lobeysa

load.

JigmelingChukha

(4X84MW)

Semtokha

54

.01

km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)

Basochu(U)

(2X12MW)

Malbase Phuntsholing

8.98km

Gedu

16.7km

Chukha

20

.4k

m

Watsa Tap

21.88km

Chumdo

15.1km11.78km

Jemina17.66km

Olakha

1.7km

Semtokha

Dechencholing

11.45km

3.08km

Lobeysa21.8km

24.33km

Gewathang

Olakha

Basochu(L)

1.5

km

2x15MVA 66/11kV

2x30MVA 220/11kV

30MVA 220/66kV

2X72MVA 220/11kV

3x10/12.5MVA 66/33kV

2x50/63MVA 220/66kV

2x20MVA 66/33kV

4X105MVA 220/11kV

2x20MVA 220/66kV

3x50/63MVA 220/66kV

2X80MVA 220/132kV

Birpara

40.77km

Dog

Dog

D

og

70.21km

Do

g

Dog

Dog

Dog

Dog

Zebra

Zeb

ra

Dog Dog

Dog Dog

Dog Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Zebra

Figure 5-4 Failure of 220kV Chukha-Semtokha & 220kV Rurichhu-Tsirang

5.4.1 Operation procedure for above line failure

The following procedure shall be followed:

a. The System Operator shall coordinate with BHP to utilize the pondage for generation to

meet the load of Thimphu. The prioritization of distribution feeder in Thimphu shall be

carried out by Substation Maintenance Division (SMD), Semtokha in coordination with

Electricity Services Division (ESD), Thimphu.

b. The System Operator shall coordinate with the shift in-charge of Semtokha, BHP and

CHP to extend the BHP power supply to Chukha and synchronize at Chukha end once

the 220kV Chukha-Semtokha line is restored.

c. Similarly, in case of 220kV Rurichu-Tsirang line, the line shall be closed at Rurichu end.

Page 13: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 10 of 14

d. After synchronization, BHP shall refill the pondage immediately following the

utilization, backing down the generation of the BHP lower stage.

e. BHP generation needs to back down its generation by 16-17MW to make the power flow

in 66kV SEM-OLA to 30MW (CTR: 300/1A) depending on requirement.

5.5 Western black out (Semtokha)

The western black out especially in Semtokha substation can be seen in different scenarios as

explained below:

Scenario 1: Failure of 220kV and 66 kV lines to Semtokha with CHP intact

CHP shall immediately extend the grid supply to Semtokha considering the stability of the

Indian grid and CHP. Then the supply shall be extended to BHP and synchronize with the grid

at their end.

Tintibi

Jigmeling

Gelephu

15.4km

Chukha

(4X84MW)

45.74km

Semtokha

54

.01

km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

50km

Malbase

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)Basochu(U)

(2X12MW)

Malbase Phuntsholing

8.98km16.7km

Chukha

20

.4k

m

68.12km

Semtokha

Dechencholing

11.45km

3.08km

47.3km

Basochu(L)

2x15MVA 66/11kV

2x30MVA 220/11kV30MVA

220/66kV

2x10MVA 220/66kV

2X72MVA 220/11kV

2x50/63MVA 220/66kV

4X105MVA 220/11kV

2x20MVA 220/66kV

200MVA 400/220/33kV

3x50/63MVA 220/66kV

2X80MVA 220/132kV

Salakati

Birpara

40.77km

Dog

D

og

70.21km

Panther

Dog

Dog

Dog

Zebra

Zeb

ra

Dog Dog

Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Panther

Panther

Zebra

Gedu

Figure 5-5 Failure of 220kV & 66kV lines to Semtokha

Page 14: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 11 of 14

Scenario 2: Failure of Birpara and Binaguri grid with THP, CHP, BHP and DHPC being

pulled out

Tintibi

Jigmeling

Gelephu

15.4km

Chukha

(4X84MW)

45.74km

Semtokha

54

.01

km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

50km

Malbase

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)Basochu(U)

(2X12MW)

Malbase Phuntsholing

8.98km16.7km

Chukha

20

.4k

m

68.12km

Semtokha

Dechencholing

11.45km

3.08km

47.3km

Basochu(L)

2x15MVA 66/11kV

2x30MVA 220/11kV30MVA

220/66kV

2x10MVA 220/66kV

2X72MVA 220/11kV

2x50/63MVA 220/66kV

4X105MVA 220/11kV

2x20MVA 220/66kV

200MVA 400/220/33kV

3x50/63MVA 220/66kV

2X80MVA 220/132kV

Salakati

Birpara

40.77km

Dog

D

og

70.21km

Panther

Dog

Dog

Dog

Zebra

Zeb

ra

Dog Dog

Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Panther

Panther

Zebra

Gedu

Figure 5-6 Failure of Binaguri & Birpara

Option 1: The shift in-charge of BHP control room shall first try to get feedback supply from

Eastern Grid/MHEP in coordination with System Operator. If power supply is available at

Tsirang end, the power shall be extended directly to Semtokha substation, before initiating to

normalize BHP machines. Simultaneously, the power from India shall be also extended to CHP

and synchronized. BHP machines shall be connected to the grid once the supply is extended to

Semtokha substation. The supply shall be further extended to CHP for synchronization with

Western Grid.

Option 2: BHP shall immediately extend the supply to Semtokha substation. The shift in-

charge of Semtokha substation shall ensure that the loads are gradually applied in consultation

with the shift in-charge of BHP. After the complete restoration of power supply to Thimphu,

the power shall be extended to CHP depending on the availability of the lines for

synchronization at their end. Simultaneously, the power from India shall be also extended to

CHP and synchronized.

Page 15: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 12 of 14

Option 3: In case of Indian Grid failure with CHP or BHP being pulled out, the shift in-charge

of CHP control room shall first try to get feedback supply from Indian Grid. If power supply

is available at Birpara end, the power shall be extended directly to Semtokha substation, before

initiating to normalize CHP’s machines. CHP machines shall be connected to the grid once the

supply is extended to Semtokha substation. The supply shall be further extended to BHP for

synchronization with Eastern Grid.

Scenario 3: CHP, BHP and DHPC with Tala intact

Basochu shall extend the power supply to Semtokha and simultaneously power from Malbase

shall be extended to Chukha and sychronized. After the restoration of power supply to

Thimphu, the power shall be further extended to Chukha and synchronized. Here, BHP is

presumed to be running in isolation mode. After extending the power to Semtokha, the same

shall be extended to Tsirang and then further to Dagachu.

5.6 Failure of any one of 220kV Chukha-Birpara lines during the peak

generation

During the peak generation, when one of the 220kV Chukha-Birpara feeder trips, the 220kV

bus coupler at Malbase substation shall automatically open by inter-tripping protection scheme

for equal sharing of load between the 220kV Chukha-Birpara line and 220kV Chukha-

Malbase-Birpara line. However, this scheme shall be disabled during lean season as per the

instruction of the System Operator. In general, the following procedures shall be followed:

Tintibi

Jigmeling

Gelephu

15.4km

Chukha

(4X84MW)

45.74km

Semtokha

54.0

1km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

50km

Malbase

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)

Basochu(U)

(2X12MW)

Malbase Phuntsholing

8.98km16.7km

Chukha

20.4

km

Watsa Tap

21.88km

Chumdo

15.1km11.78km

Jemina17.66km

Olakha

1.7km

Semtokha

Dechencholing

11.45km

3.08km

Lobeysa

21.8km

24.33kmGewathang

Basochu(L)

Damdum

1.5

km

2x15MVA 66/11kV

2x30MVA 220/11kV

30MVA 220/66kV

2x10MVA 220/66kV

2X72MVA 220/11kV

2x50/63MVA 220/66kV

4X105MVA 220/11kV

2x20MVA 220/66kV

200MVA 400/220/33kV

3x50/63MVA 220/66kV

2X80MVA 220/132kV

Salakati

Birpara

40.77km

Dog

Dog

D

og

70.21km

Panther

Dog

Dog

Dog

Dog

Dog

Zebra

Zeb

ra

Dog Dog

Dog Dog

Dog Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Panther

Panther

Zebra

Gedu

Malbase

Figure 5-7 Failure of 220kV Birpara Line

Page 16: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 13 of 14

In general, the following procedures shall be followed:

a. Immediately after the tripping of one of the 220kV Chukha-Birpara lines, the System

Operator shall inform the shift in-charge of Malbase substation regarding the failure of

the line.

b. If the de-coupling of 220kV bus coupler at Malbase leads to overloading of 66kV

Chukha-Gedu line, the shift in-charge of Phuentsholing substation shall open the 66kV

Phuentsholing-Malbase line.

c. After the normalization of the 220kV Chukha-Birpara line, System Operator shall instruct

the shift in-charge of Malbase substation to close the 220kV bus coupler.

d. System Operator shall instruct the shift in-charge of Phuentsholing substation to close the

66kV Phuentsholing-Malbase line after closing the 220kV bus coupler at Malbase.

5.7 Failure of 220kV D/C Chukha-Birpara lines

The maximum power which can be loaded from the 220 kV Chukha-Malbase line, Zebra

Conductor is nearly 200MW considering the current carrying capacity of 600 Amperes as per

the CT setting and power factor of 0.9.

Tintibi

Jigmeling

Gelephu

15.4km

Chukha

(4X84MW)

45.74km

Semtokha

54.0

1km

Basochu(L)

44.9km

Tsirang

46.6km

Dagachu

(2X63MW)20.2km

55.16km

30.56km

50km

Malbase

70.21km

29.84km

Malbase

Basochu(L)

(2X20MW)

Basochu(U)

(2X12MW)

Malbase Phuntsholing

8.98km16.7km

Chukha

20

.4km

Watsa Tap

21.88km

Chumdo

15.1km11.78km

Jemina17.66km

Olakha

1.7km

Semtokha

Dechencholing

11.45km

3.08km

Lobeysa

21.8km

24.33kmGewathang

Basochu(L)

1.21km

41.15km

Singhigaon Damdum

1.5

km

2x15MVA 66/11kV

2x30MVA 220/11kV

30MVA 220/66kV

2x10MVA 220/66kV

2X72MVA 220/11kV

2x50/63MVA 220/66kV

4X105MVA 220/11kV

2x20MVA 220/66kV

200MVA 400/220/33kV

3x50/63MVA 220/66kV

2X80MVA 220/132kV

Salakati

Birpara

40.77km

Dog

Dog

D

og

70.21km

40.15kmZebra Zebra

Panther

Dog

Dog

Dog

Dog

Dog

Zebra

Zeb

ra

Dog Dog

Dog Dog

Dog

Zebra

Zebra

Zebra

Zebra

Zebra

Zebra Zebra

Zebra

Panther

Panther

Zebra

Gedu

Figure 5-8 Failure of 220kV Birpara Lines

Page 17: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV

BHUTAN POWER SYSTEM CONTINGENCY PLAN-2019

Page 14 of 14

The following will be applied, depending on the functioning of generation load reduction

scheme.

5.7.1 Operation procedure for above line failure

During peak generation, if 220kV D/C Chukha-Birpara line trips, the units of CHP shall trip

on over frequency. Until the restoration of 220kV D/C Chukha-Birpara lines, the following

procedure shall be followed:

a. The System Operator shall inform the Shift In-charge of CHP, BHP and DHPC

regarding the failure of the above lines and instruct CHP and BHP and DHPC to

reduce their generation based on priority and ensure that 132kV lines in the East is

not overloaded.

b. Shift In-charge at CHP and System Operator shall maintain the total generation such

that total power flow through 220kV CHP – Malbase line does not exceed 200MW

and 30MW through 66kV Chukha – Phuentsholing line respectively.

c. After normalization of 220kV D/C Chukha – Birpara lines, the Shift In-charge of

CHP shall inform System Operator regarding the normalization of lines. System

Operator shall inform the BHP and DHPC.

Shift In-charge of CHP, BHP and DHPC may increase their respective generation

gradually.

5.8 Total shutdown of KHP during peak season under normal system

condition.

During the total shutdown of KHP, western power tends to flow towards the east and hence

gets overloaded. In such scenario, 132kV Mat-Rangia line or any line, as per the instruction of

the SO, shall be kept opened.

5.9 Utilization of 400/220kV ICT at Jigmeling

In the event of failure of either 132kV Gelephu-Salakati or 132kV Motanga-Rangia during the

peak generation of KHP and DHP, there will be overloading of lines, which will lead to

generation loss. Hence, utilization of 400/220kV ICT shall may avoid the generation loss.

Additionally, the voltage will be improved (utilization subject to further deliberations and

discussions with the concerned as recommended by 59th OCC).

----------------------------------------

Page 18: BHUTAN POWER CORPORATION LIMITEDbpso.bpc.bt/wp-content/uploads/2019/11/Bhutan-Power-System-Contingency... · 5.4.1 Operation procedure for above line failure ... while the 400/220kV