![Page 1: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/1.jpg)
Best Practices of Project Management
Capacity Building Workshop
Farhad Abdollahyan
Acílio Marinello
Practical Thinking Consultants
![Page 2: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/2.jpg)
Who are we?
![Page 3: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/3.jpg)
3 WHO ARE WE?
UNOPS is a central resource for the United Nations system in
sustainable Project Management, Infrastructure and Procurement
management, including the related capacity development
activities
![Page 4: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/4.jpg)
4 UNOPS TEAM
Over 6,500 employees
Headquarters Copenhagen
Denmark
5 Regional Offices
24 Hubs, Operations and Project
Centers
Over a thousand projects annually
Activities in more than 80
countries
![Page 5: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/5.jpg)
Workshop Objectives and Outcomes
![Page 6: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/6.jpg)
6 TODAY’S WORKSHOP
Part of a Capacity Building Program led by UNOPS
Infrastructure and Project Management Group to foster better understanding about
Project Management aspects and benefits
Over 35 editions
More than 1500 participants
Africa
Asia
Europe
North America
Latin America
Middle East
![Page 7: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/7.jpg)
7 WORKSHOP OUTCOMES
Understand the difference between projects and other
works
The value you can get from managing your projects better
Basic steps of the planning process
Bring the results of the simulation
exercise to the real projects
![Page 8: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/8.jpg)
8 OBJECTIVES
What is Project
Management
The Value of Project
Management
Project Lifecycle
Planning and Executing a
Project
Results and discussion
Final messages
![Page 9: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/9.jpg)
9
Start time: 10:00
Finish time: 18:00
Lunch: 13:00 to 14:30
Certificate All attendees will receive a UNOPS Certificate of attendance electronically through email after the
course
Feedback Help UNOPS to improve this workshop
AGENDA
![Page 10: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/10.jpg)
What is Project Management
![Page 11: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/11.jpg)
11 WHAT IS PROJECT MANAGEMENT
Why are we here to
talk about project
management?
![Page 12: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/12.jpg)
12 UNDERSTANDING THE PROJECT CONTEXT
Source: VARGAS, R. Planning in 140 Tweets
GEF 2020 Vision
To be the champion of the global
environment building on its role as
financial mechanism of several
multilateral environmental conventions,
supporting transformational change, and
achieving global environmental benefits
on a larger scale.
GEF Key Strategic Priorities
Addressing drivers of environmental
degradation
Delivering integrated solutions
Enhancing resilience and adaptation
Ensuring complementarity and synergies
in the global financing architecture
Choosing the right influencing models
![Page 13: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/13.jpg)
13
GEF Sustainable Development Goals
Portfolio
14-Life Below Water
Areas Beyond Jurisdiction
Program
Coastal Fisheries Initiative
2-Zero Hunger6-Clean Water and
Sanitation15-Life on Land
Food Security Program
13-Climate Action
Renewable Energy
Climate Change
15-Life on Land
Amazon Region Protected Areas
Program
Taking Deforestation out of Commodity Supply
Chains
Illegal Wildlife Trade
11-Sustainable Cities and
Communities
Sustainable Cities Program
WORK BREAKDOWN STRUCTURE (A PORTFOLIO VISION FOR GEF)
![Page 14: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/14.jpg)
14
Trinidad and Tobago Sustainable Development
Goals Portfolio
14-Life Below Water
Areas Beyond Jurisdiction
Program
Project A
Project B
Coastal Fisheries Initiative
Project C
Project D
2-Zero Hunger6-Clean Water and
Sanitation15-Life on Land
Food Security Program
Project E
Project F
13-Climate Action
Renewable Energy
Project G
Climate Change
Project H
Project I
15-Life on Land
Deforestation/Supply Chains
Project J
Illegal Wildlife Trade
Project K
11-Sustainable Cities and Communities
Sustainable Cities Program
Project L
Project M
A POSSIBLE TRINIDAD AND TOBAGO PERSPECTIVE
![Page 15: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/15.jpg)
15 WHAT IS A PROJECT?
Temporary
Has a specific end date!
Can take 1 day, 1 year or 10
years
Has a life cycle (start and finish
date)
Unique
It is something you do not do
everyday!
It requires a different approach to
execute
![Page 16: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/16.jpg)
16 WHAT IS PROJECT MANAGEMENT
Project Management is the
application of knowledge, specific
skills, tools, and techniques to
project activities to meet the project
requirements, in order to increase
success rates.
Manage/not manage a project is a
personal and/or
organizational decision
![Page 17: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/17.jpg)
The Value of Project Management
![Page 18: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/18.jpg)
18 THE VALUE OF PROJECT MANAGEMENT
Source: 2012 PMI Economic Pulse Survey
![Page 19: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/19.jpg)
19 THE VALUE OF PROJECT MANAGEMENT
![Page 20: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/20.jpg)
20 THE VALUE OF PROJECT MANAGEMENT
Source: Standish Group – The CHAOS Report
![Page 21: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/21.jpg)
Project Life Cycle
![Page 22: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/22.jpg)
22 GEF PROJECT LIFECYCLE
![Page 23: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/23.jpg)
23 UNDERSTANDING THE “SPEED FACTOR”
![Page 24: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/24.jpg)
24 EFFORT DURING THE PROJECT
![Page 25: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/25.jpg)
25 ADDING VALUE OVER THE TIME
![Page 26: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/26.jpg)
26 CORRECTION COSTS OVER THE TIME
![Page 27: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/27.jpg)
27 WHEN IS THE RIGHT TIME TO PLAN?
![Page 28: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/28.jpg)
Planning & Executing a ProjectSustainable Bridge Simulation Exercise
![Page 29: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/29.jpg)
29 WHY DO WE NEED TO PLAN BEFORE EXECUTING?
Increase success rate
Reduce the chances of problems
Improve time and cost
estimates
Increase control
Optimize resource allocation
Reduce waste (time, money,
resources)
![Page 30: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/30.jpg)
30 SIMULATION BENEFITS
Includes “execution” of the plan
Links simulation results to real life
It is practical
Fun!
![Page 31: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/31.jpg)
31 BEFORE WE START… WHAT DO I EXPECT FROM YOU?
Strategic thinking
Teamwork
Haste makes waste
Attention to the rules
Team ethics
![Page 32: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/32.jpg)
Sustainable Bridge Workshop
![Page 33: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/33.jpg)
33 BACKGROUND – UNDERSTANDING THE CONTEXT
Over the last decades, the Government of
Globalia has been implementing a
development strategy, not strongly focusing
on the environmental, social and economic
dimensions of development.
A new Government has just decided to
strengthen strategic linkage of environment
with socio and economic developmental
goals.
Recently, the Government initiated a
project for building a bridge in the town of
Kan, northern part of Globalia. The main
outcome of the project is to contribute to
the environmental protection of Globalia’ s
river (UNESCO biosphere reserve),
improving fostering trade of the local
community, by removing the need for
polluting crossing ferries.
![Page 34: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/34.jpg)
34 EXPECTED OUTCOME
The bridge would provide improved access to market for
agricultural products and remove isolation of communities as well
as facilitating for the implementation of aid and
development programs
The bridge will improve environmental conditions in Globalia’s
river basin by:
• Eliminating polluting crossing ferries system that has been proven to
contribute to habitat and biodiversity degradation
• Eliminating the use of old quays and jetties that are harmful to local
fauna
• Provide safer means of river crossing to local communities
• Fostering economic development and facilitating trade, thereby
improving access to market for agricultural products and removing
isolation of communities
![Page 35: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/35.jpg)
35 WHAT IS “OUR” PROJECT?
You are submitting a proposal for the bridge and have been requested to provide accurate estimates in terms of time/cost/quality. To assist with creating such estimate,
you have decided to build a prototype of the bridge.
![Page 36: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/36.jpg)
36 PROJECT OBJECTIVE
Build a 2 dimensional prototype
of the Sustainable Bridge using
the materials provided, within a
duration under 50 minutes and
a cost below $5,000.00 as
agreed with the Globalia
procurement agency.
SSpecific
MMeasurable
AAgreed
RRealistic
TTime Constrained
http://en.wikipedia.org/wiki/SMART_criteria
![Page 37: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/37.jpg)
37 PROJECT PRODUCT
Bridge prototype with provided materials
Based on the concept drawing of Vista Learning Company - Canada
![Page 38: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/38.jpg)
38 EXPECTED PERFORMANCE AND QUALITY CRITERIA
Solid construction Exact design Parts can not be bended or twisted
Resources can not be shared between work packages and
teams
Work area must be kept organized
Duration must be below 50 minutes
and the cost should be below $5,000
![Page 39: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/39.jpg)
Project Planning
![Page 40: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/40.jpg)
40 THE ROLE OF THE PROJECT MANAGER
Manage the development of the product/services to be created by the
project
Lead the project team
Manage project risks Negotiate all project
aspects
![Page 41: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/41.jpg)
41 THE DESIRED PROJECT MANAGER
Lead and inspire the
team
Communicate clearly project
objectives
It is not risk averse and not a risk seeker
Plan properlyIt is a very
scarce resource
![Page 42: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/42.jpg)
42 PROJECT MANAGER SELECTION – TEAM FORMATION
![Page 43: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/43.jpg)
43 WORK BREAKDOWN STRUCTURE (WBS)
Scope management tool
Addresses all work that must
be completed
Can be detailed to the level you
and the team feel is needed to
track performance and
are comfortable with
![Page 44: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/44.jpg)
44
Improving Forest and Protected Area Management
Project
Improvements to the legal and institutional
arrangements for protected area management
National Legislation
National Protected Areas System Plan
Ecological Research
Public Education and Awareness
Biodiversity Information
Improvements to Infrastructure for Biodiversity conservation
and Forest restoration
Upgrade of Visitor Facilities
Upgrade of Equipment
Identification of Degraded Areas
Development and testing of sustainable financing system
NFPA Fund
Operating procedures and Manuals
Training
Monitoring and Evaluation and Information Dissemination
Project Monitoring System
Midterm Evaluation
Final Evaluation
Knowledge Management
Project Website
A WBS FOR A BIODIVERSITY PROJECT (INCOMPLETE)
![Page 45: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/45.jpg)
45 MILESTONES AND DELIVERABLES
Related to the deliverables
Zero duration
Checkpoints
Simplify the reporting process
![Page 46: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/46.jpg)
46 UNDERSTANDING THE WBS
Arrange the work in a logical
way
Group elements by affinity
Easy to assign
resources/responsibilities
The Good!
Does not relate the duration
with the size of the boxes
Does not show relationships
among packages
The Bad!
![Page 47: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/47.jpg)
47 SOME TIPS…
Product Oriented (PBS)
Foundation of the planning
process
Usually detailed to 4/6 levels
Does not contain verbs (actions)
No “single child” for package
![Page 48: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/48.jpg)
48 DECOMPOSITION TECHNIQUE
Break the project into big pieces of work
Check each piece of work
separately and break down to one level more
Repeat the process to the other pieces of
work
Stop when the level of detail is sufficient
![Page 49: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/49.jpg)
Group Exercise
Using Post-It® Notes, suggest a WBS
for the Sustainable Bridge Project
Up to 3 levels (including the project
level)
No “single child”
![Page 50: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/50.jpg)
50 PROJECT PRODUCTS
Left
Tower
Left
CableCable
Saddle
DeckLeft
Foundation
![Page 51: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/51.jpg)
51 PROPOSED WBS
![Page 52: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/52.jpg)
52 DETERMINING THE SEQUENCE OF ACTIVITIES
Now that we have identified what needs to be produced,
in what order should things be done and produced?
![Page 53: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/53.jpg)
53
Improving Forest and Protected Area Management
Improvements to the legal and institutional
arrangements for protected area management
National Legislation
National Protected Areas System Plan
Formal Protected Areas
NFPAMA Training
Ecological Research
Public Education and Awareness
Biodiversity Information
Improvements to Infrastructure for
Biodiversity conservation and Forest
restoration
Upgrade of Visitor Facilities
Upgrade of Equipment
Identification of Degraded Areas
Development and testing of sustainable
financing system
NFPA Fund
Operating procedures and Manuals
Training
Monitoring and Evaluation and
Information Dissemination
Project Monitoring System
Midterm Evaluation
Final Evaluation
Knowledge Management
Project Website
USING THE WBS TO CREATE THE NETWORK DIAGRAM
Work package
level
![Page 54: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/54.jpg)
54 CREATING A NETWORK DIAGRAM WITH DURATIONS
Project Start1 day
Task A7 days
Task C6 days
Task G3 days
Task H2 days
Project End1 day
Task B3 days
Task D3 days
Task E3 days
Task F2 days
Task nameduration
es ef
ls lf
14
0 1
1 8 14 17
17 19 19 20
8
1 4 4 7 7 10
4 6
12 14
8 11 11 14 14 17
17 19 19 200 1
1 8 8 14 14 17
![Page 55: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/55.jpg)
55
Predecessor
•A task (or activity)that must be startedor finished beforeanother task ormilestone can beperformed.
Successor
•A task or milestonethat is logicallylinked to one or morepredecessor tasks.
NETWORK DIAGRAM
Organize tasks / packages in a specific order of execution
![Page 56: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/56.jpg)
56 DIFFERENT TYPES OF RELATIONSHIPS
![Page 57: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/57.jpg)
Group Exercise
Using Post-It® Notes, suggest a
Network Diagram for the
Sustainable Bridge Project
Use the Proposed WBS you received
as a starting point
Use only Finish to Start relationships
10 Minutes
![Page 58: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/58.jpg)
58 PROJECT PRODUCT
Bridge prototype build with provided materials
Left
Tower
Left
Foundation
Deck
Left
CableCable
Saddle
![Page 59: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/59.jpg)
59 PROPOSED NETWORK DIAGRAM
![Page 60: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/60.jpg)
60 DURATION AND RESOURCE ALLOCATION
Duration: Time you need to execute
the task/package
Directly related to the resources you
have to execute the task/package
![Page 61: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/61.jpg)
61 DURATION AND RESOURCE ALLOCATION
![Page 62: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/62.jpg)
62
Distribute WBS Dictionary Distribute Planning Pieces
WBS DICTIONARY AND PLANNING PIECES
team members: pieces used:
type quant ity
Opt imist ic
mOst LiKeLy
pessimist ic
© UNOPS 2012 - All rights reserved
![Page 63: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/63.jpg)
Exercise –Part 1
Based on the team experience,
WBS Dictionary and the use of
the planning materials, estimate
the duration of each work
package in minutes.
There is no right answer
The team can choose any
duration they think is reasonable
Add the duration on the
Network Diagram Provided
5 Minutes
![Page 64: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/64.jpg)
Exercise –Part 2
Based on the team experience,
WBS Dictionary and the use of
planning materials, estimate the
required resources of each work
package in minutes.
There is no right answer
The team can choose any team
members
Put the name of the team
members on the WBS Chart
Provided
![Page 65: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/65.jpg)
65 CRITICAL PATH
The critical path is the path
with the tasks that directly
affect the duration of the
project.
Any delays on the critical
path activities will impact
the project finish date.
![Page 66: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/66.jpg)
66
It’s a path where any delay in any task will impact the project duration.
It’s the longest path of all possible paths on a project.
There can be more than one critical path.
It’s the path with no floats or with the smallest float.
It determines the shortest possible duration for the project.
CRITICAL PATH
![Page 67: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/67.jpg)
67
Task A
Task B
Task C
Task D
Task E
Task F
CRITICAL PATH ON A GANTT CHART – AN EXAMPLE
![Page 68: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/68.jpg)
68 EXERCISE
Based on the provided Network
Diagram, calculate
•Project Duration
•Critical Path Tasks
![Page 69: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/69.jpg)
69 CALCULATING THE PROJECT DIRECT COST
Directed related to the project work
Calculate based on the project scope
and allocated resources
Poor scope leads to poor cost budgeting
![Page 70: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/70.jpg)
70 BOTTOM-UP ESTIMATING
![Page 71: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/71.jpg)
Group Exercise
Prepare your Project
Cost
Assembly Kits
K$2.000,00
Team member
K$15,00 per minute per
member
Can not be over
K$5.000,00
![Page 72: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/72.jpg)
72 GROUP BID
Based on your planning
documents, propose a
bid for your team using
the form provided
![Page 73: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/73.jpg)
Execution
![Page 74: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/74.jpg)
74
Clean all the tables
Wait for the Clock
Good luck!
EXECUTION
![Page 75: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/75.jpg)
Results and discussions
![Page 76: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/76.jpg)
76
What can we learn with the
simulation?
What went well and
why?
What went wrong and
why?
What will you do
different next time
EXECUTION
![Page 77: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/77.jpg)
Final messages
![Page 78: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/78.jpg)
78 WHAT WE LEARNED TODAY
Understand the difference from
project and other works
The value you can get of managing your
projects better
Basic steps of the planning process
Bring the results of the simulation
exercise to the real projects
![Page 79: Best Practices of Project Management - Presentation EN.pdf · Best Practices of Project Management Capacity Building Workshop Farhad Abdollahyan ... WORK BREAKDOWN STRUCTURE (A PORTFOLIO](https://reader030.fdocuments.net/reader030/viewer/2022040515/5e71b9f5b0cba926e604ce86/html5/thumbnails/79.jpg)
79 FINAL MESSAGES
Project Management is one of the most
reliable tools that a government has to
deliver value
Despite of great machines, people
are always managing the projects
Understand the project context is a
critical knowledge for long term
sustainability