Best Management Practices Used for Recent Decommissioning Projects

32
Best Management Practices Used For Recent Decommissioning Projects Best Management Practices Used For Recent Decommissioning Projects Presented by: Simon A. Poulter Padre Associates, Inc.

description

decommissioning oil field

Transcript of Best Management Practices Used for Recent Decommissioning Projects

Page 1: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Presented by: Simon A. PoulterPadre Associates, Inc.

Page 2: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Presentation Outline• Explosives Use• Onshore Pipeline

Decommissioning• Offshore Pipeline

Decommissioning• Heavy Equipment in

Sensitive Areas• Conclusions and

Acknowledgements

Page 3: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Recent Explosives Use • Chevron 4H Platform Decommissioning Project

− Conventional Offshore Production Platform − Pile Severing

• Seacliff Pier Complex Decommissioning Project− Pier Based Oil and Gas Production − Concrete Caisson Removal

• Arco Bird Island− Pier Based Oil and Gas Production − Concrete Caisson Removal

Page 4: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Chevron 4H Platform Explosives Use

Page 5: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Chevron 4H Platform Explosives Use

Page 6: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Chevron 4H Platform Explosives Use

Page 7: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Chevron 4H Platform Explosives Use

Page 8: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Seacliff Pier Explosives Use

Page 9: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Seacliff Pier Explosives Use

Page 10: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Seacliff Pier Explosives Use

Page 11: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Bird Island Explosives Use

Page 12: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Bird Island Explosives Use

Page 13: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Bird Island Explosives Use

Page 14: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Explosive Use BMP’s• Focused Demolition Planning Based Upon Structure

− Explosives use is as much art as it is science− Bigger is not necessarily better

• Effort Implementation of Marine Wildlife Contingency Plan− Marine Mammals− Marine Birds− Marine Fish

Page 15: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Onshore Pipeline Decommissioning• Abandonment Considerations

− Depth of Burial− Future Land Use− Erosion Potential− Stream Crossings− Extent of Onsite

Contamination− Accessibility− Sensitive Habitat

Page 16: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Effective Pipeline Preparation• Pipeline Pigging

and Flushing

• Stability Grouting

Page 17: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Access and Removal Procedures

Page 18: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Slope Restoration

Page 19: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Offshore Pipeline Decommissioning• Abandonment Considerations

− Depth of Burial• Offshore• Surf Zone

− Pipeline Integrity− Pipeline Pigging and Flushing

Procedures− Erosion Potential− Accessibility− Sensitive Habitat

Page 20: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Pipeline Abandonment Considerations

Page 21: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Pipeline Removal In Surf Zone

Page 22: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Offshore Pipeline Handling Considerations

Page 23: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Page 24: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

• Abandonment in Place − Depth of burial exceeds 5 feet. − Seasonal or periodic exposure not

observed.− Depositional area with no dredging

activities likely.− Environmental impacts associated with

removal considered excessive in comparison to the benefit of removal.

Page 25: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Environmental Considerations

Page 26: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Environmental Considerations

Page 27: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Heavy Equipment in Sensitive Areas•• Access Limitation DrivenAccess Limitation Driven•• Effective Mitigation Effective Mitigation

Monitoring and Monitoring and Compliance ProgramCompliance Program

•• Extensive Agency Extensive Agency CoordinationCoordination

•• Clearly Defined Operating Clearly Defined Operating PerimetersPerimeters

•• Well Maintained Well Maintained Equipment Operated by Equipment Operated by Knowledgeable OperatorsKnowledgeable Operators

Page 28: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Effective Site Exposure

Page 29: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Goleta Beach Hazards Removal

Page 30: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Goleta Beach Hazards Removal

Page 31: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Effective Dewatering Procedures

Page 32: Best Management Practices Used for Recent Decommissioning Projects

Best Management Practices Used For Recent Decommissioning Projects

Acknowledgements• Fairweather Pacific

− Tom Kennedy• Chevron• Texaco• ExxonMobil• Unocal• BP Arco• Southern California Edison• County of Santa Barbara• California State Lands

Commission

• Padre Associates, Inc.− Brian Dugas− Mike Weber− Jenn Carnine− Mike Ruiz

• Longitude 123− Mark Steffy

• Divecon− Ted Roche

• Adobe Systems• Associated Pacific

− Paul Gillen