Beautifuel Waste to Energy Plant

15
WASTE-TO-ENERGY WITH PLASMA GASIFICATION Date By: Dr. I.J. van der Walt Senior Scientist

description

Plasma gasification

Transcript of Beautifuel Waste to Energy Plant

Page 1: Beautifuel Waste to Energy Plant

WASTE-TO-ENERGY WITH PLASMA GASIFICATION

Date

By:

Dr. I.J. van der Walt

Senior Scientist

Page 2: Beautifuel Waste to Energy Plant

Main Objective

The main objective for the waste-to-energy system is

twofold:

To convert waste or a renewable feed into syngas by plasma

gasification.

To convert syngas into electricity or synfuel via a Fischer

Tropsch process.

2

Page 3: Beautifuel Waste to Energy Plant

History

3

• 2007 ICOPS conference in USA

• 2008 visit to Zwilag, Switzerland

Page 4: Beautifuel Waste to Energy Plant

History

4

• Demonstration system at Necsa to:

o Promote Plasma Technology as a solution to nuclear waste

treatment in SA

o Demonstrate the technology on a small scale

Page 5: Beautifuel Waste to Energy Plant

History COMPS

Centre of Materials and Process Synthesis (COMPS);

15 years experience in sustainable technology for electricity

and fuel production;

2 full scale FT pilot plants have been built in China and

Australia;

2 Lab scale FT plants in SA and China;

5

Page 6: Beautifuel Waste to Energy Plant

Benefit

Benefits

– Solution to serious municipal waste problems;

– Solution to medical waste problems;

– Solution to various other waste problems;

– Takes pressure off fuel supply to remote areas;

– Takes pressure off electricity supply to remote areas;

– Promotes the decrease of the carbon footprint;

– Opportunity for renewable energy supply;

– Job creation;

– Trade waste for electricity.

6

Page 7: Beautifuel Waste to Energy Plant

BeauTi-fueLTM

7

Necsa Wits COMPS

• Non-nuclear waste in plasma gasification as spin off from nuclear

waste treatment research

• Wits Fischer Tropsch technology

Fischer Tropsch

Plasma Gasification

BeauTi-fueLTM

Page 8: Beautifuel Waste to Energy Plant

BeauTi-fueLTM

8

Page 9: Beautifuel Waste to Energy Plant

BeauTi-fueLTM

9

Page 10: Beautifuel Waste to Energy Plant

BeauTi-fueLTM

10

Page 11: Beautifuel Waste to Energy Plant

Future

System layout electricity production

11

Page 12: Beautifuel Waste to Energy Plant

Future

System layout fuel production

12

Page 13: Beautifuel Waste to Energy Plant

Future

Product capabilities

13

Electricity only Electricity and fuel Unit size (tpd)

Municipal land fill sites X 100 – 200

De-localised municipal waste sites X 1 – 10

Farming plant waste X 1 – 3

Farming animal manure waste X 1 – 3

Renewable feedstock X 100 – 200

Tyre waste X 10 – 50

Medical waste X 1

Toxic waste X 1

Nuclear waste X 10

Page 14: Beautifuel Waste to Energy Plant

Future

Up-scaling modular systems (50 % accuracy)

14

Plant 1 10 50 100

Feed quantity ~2 - 3 tpd ~10 - 15 tpd ~50 - 70 tpd ~100 – 150 tpd

Plasma size 30 kW 150 kW 500 kW 1000 kW

Availability 2012 2013 2015 2017

Estimated

Development Cost R10 mil R25 mil R60 mil R125 mil

Electricity only

or 150 kW 750 kW 3.75 MW 7.5 MW

Diesel and

Electricity 2 bbl

50 kW

10 bbl

250 kW

50 bbl

1.25 MW

100 bbl

2.5 MW

Page 15: Beautifuel Waste to Energy Plant

Thank You!!!

15