Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery...

29
Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25, 2019 1 Flood Resilience Selection

Transcript of Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery...

Page 1: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Battery Park CityBallfields &

Community Center Resilience Project

BPCA MeetingJuly 25, 2019

1

Flood Resilience Selection

Page 2: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Agenda

• Site Review

• Permanent Solution: Reinforced Concrete Wall (DFE 14.5’)

• Interim Solution: Steel Plate Wall (DFE 11’)

• Guiding Objectives Review

• Next Steps

2

Page 3: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Topography

3

+13.7’

+8.5’

+8.3’

+7.0’

+6.8’

+8.0’

+7.5’

+11.0’

+14.3’

+15.8’

+16.4’

+15.9’

+17.1’

+16.6’

+11.0’

Page 4: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

4

Page 5: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Permanent Solution: Reinforced Concrete Wall (DFE 14.5’)

5

• Reinforced Concrete Wall to DFE 14.5’ (NAVD88)

• Hybrid Alignment of Wall (Interior and Exterior)

• 6 Deployable Flood Barriers, 8 ConEd Grates

• Level of Protection DFE 14.5’ = BFE 11’ + 2.5’ SLR + 1’ Freeboard

Wall at lowest grade = 7.7’

Full seepage cutoff

Page 6: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Permanent Solution: Reinforced Concrete Wall Warren Street

6

Save and Protect Existing Fence

Align Top of Fence with Bottom of Horizontal Rail

Walkway

Existing Fence Footing Beyond

Flood Wall with Interior Alignment

Existing Granite Wall

New Piles and Flood Wall Foundation

3” Safety PadsDFE 14.5

KEY PLAN

Page 7: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Permanent Solution: Reinforced Concrete Wall Alignment

7

Moveable Flood

Protection Device

Permanent Wall with

Architectural Treatment

Architectural Treatment

without Flood Barrier

Fence

Permanent Store In-Place

Vehicular Flood Gate

Permanent Wall

Existing Fence

MAINTAINING EGRESS

AND EMERGENCY

ACCESS TO BUILDINGS

DURING STORM

EVENTS AT LOADING

BAY ON MURRAY ST.

PROTECT AND SEAL MEP.

ELECTRICAL AND

CONDUITS INTO BUILDING

OR UTILITY VAULTS TO

MAINTAIN FLOOD WALL

ALIGNMENT

Page 8: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Permanent Solution: Reinforced Concrete Wall Warren Street

8Looking Northeast along Warren St.

PROPOSED WALL

THICKNESS (18”-

24”)

EXISTING WALL

THICKNESS (+/- 18”)

El. +/-9.5’

DFE

El.

Page 9: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Potential Materials for Reinforced Concrete Wall

9

Page 10: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Interim Solution: Steel Plate Wall (DFE 11’)

10

• Reuse Existing Fence Foundations

• ¾-inch Thick Steel Plate

• Alignment Exterior to Fence

• 3 Moveable Flood Protection Device, 6 Community Center Flood-Rated Doors + Flood-Rated Glass

• Level of Protection DFE 11’ = BFE 11’ (no SLR, no Freeboard) Max wall height 4’ due to structural capacity Limited seepage protection

Page 11: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Interim Solution: Steel Plate Wall

11

Steel Plate Wall

Store In-Place Vehicular Flood Gate

Existing Fence

Moveable Flood Protection DeviceWall with Architectural TreatmentArchitectural Treatment without Flood BarrierFence

Page 12: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Interim Solution: Steel Plate WallWarren Street

12

Save and Protect Existing Fence

Align Top of Fence with Bottom of Horizontal Rail

Walkway

Existing Fence Footing

Proposed Grade Beam

Existing Granite Wall

11.0

KEY PLAN

Page 13: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Community Center Hardening

13

Protect the Community Center with Flood-Rated Glass and Flood Doors

Page 14: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Potential Materials for Interim Solution

14

Page 15: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Interim Solution: Steel Plate WallMurray Street

15

4’ tall steel plate wall is “stepped-down” to match slope in grade surface

Page 16: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Interim Solution: Steel Plate WallWarren Street

16

Page 17: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Interim Solution: Steel Plate WallCorner of West St. and Murray St.

17

Page 18: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives

18

Permanent Solution(DFE 14.5’)

Interim Solution(DFE 11’)

4% chance of exceedance in 10 years

10% chance of exceedance in 10 years

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

Page 19: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Foundation Comparison

19Steel Plate Wall Reinforced Concrete Wall

Page 20: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives

20

Permanent Solution(DFE 14.5’)

Interim Solution(DFE 11’)

• 8-foot max wall height

• More finish options• Permanent wall

• 4-foot max wall height

• Fewer finish options• Removable wall

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

Page 21: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Integration with Landscape

21

8-foot max wall height

4-foot max wall height

Page 22: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives

22

Permanent Solution(DFE 14.5’)

Interim Solution(DFE 11’)

30’ field width for pile operation total duration

approx. 15 months

6’ field width for grade beam operation total

duration approx. 6 months

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

Page 23: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Minimize Construction

23

Reinforced Concrete Wall

Steel Plate Wall

Page 24: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives

24

Permanent Solution(DFE 14.5’)

Interim Solution(DFE 11’)

Est. $9.5-10.5M Est. $4-5M

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

Page 25: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives

25

Permanent Solution(DFE 14.5’)

Interim Solution(DFE 11’)

End Date: Q2 2021

End Date: Q2 2020

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

Page 26: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Schedule

26

Steel Plate WallReinforced

Concrete Wall

Construction

Bidding and Permitting

04

Page 27: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Guiding Objectives - Summary

27

Permanent Solution(DFE 14.5’)

Interim Solution(DFE 11’)

Est. $9.5-10.5M Est. $4-5M

• Flood risk

• Integration with landscape and built environment

• Minimize loss of field use and duration of construction

• Cost

• Schedule

30’ field width for pile operation total duration

approx. 15 months

6’ field width for grade beam operation total

duration approx. 6 months

4% chance of exceedance in 10 years

10% chance of exceedance in 10 years

End Date: Q2 2021

End Date: Q2 2020

• 8-foot max wall height

• More finish options• Permanent Wall

• 4-foot max wall height

• Fewer Finish Options• Removable wall

Page 28: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Next Steps

• Decision between Interim Solution and Permanent Solution

• Alignment Decision (only permanent solution)

• Pre-Application Agency Meetings

• 30% Design Development

• Continued Community Input

• Next Public Meeting (Approximately September 2019)

28

Page 29: Battery Park City Ballfields & Community Center Resilience Project ... · 25-07-2019  · Battery Park City Ballfields & Community Center Resilience Project BPCA Meeting July 25,

Discussion

Deliver a world-class public realm design for Wagner Park – beloved by the community –

that protects from future storms

Questions and Comments

29