BASIC ASSESSMENT REPORT (AUGUST 2010) Basic...

43
1 BASIC ASSESSMENT REPORT (AUGUST 2010) Basic Assessment Report in terms of the NEMA Environmental Impact Assessment Regulations, 2010 AUGUST 2010 Kindly note that: 1. This Basic Assessment Report is the standard report required by DEA&DP in terms of the EIA Regulations, 2010 and must be completed for all Basic Assessment applications. 2. This report must be used in all instances for Basic Assessment applications for an environmental authorisation in terms of the National Environmental Management Act, 1998 (Act No. 107 of 1998) (NEMA), as amended, and the Environmental Impact Assessment Regulations, 2010, and/or a waste management licence in terms of the National Environmental Management: Waste Act, 2008 (Act 59 of 2008) (NEM: WA), and/or an atmospheric emission licence in terms of the National Environmental Management: Air Quality Act, 2004 (Act No. 39 of 2004) (NEM: AQA). 3. This report is current as of 2 August 2010. It is the responsibility of the Applicant / EAP to ascertain whether subsequent versions of the report have been published or produced by the competent authority. 4. The required information must be typed within the spaces provided in the report. The sizes of the spaces provided are not necessarily indicative of the amount of information to be provided. It is in the form of a table that will expand as each space is filled with typing. 5. Incomplete reports will be rejected. A rejected report may be amended and resubmitted. 6. The use of “not applicable” in the report must be done with circumspection. Where it is used in respect of material information that is required by the Department for assessing the application, this may result in the rejection of the report as provided for in the regulations. 7. While the different sections of the report only provide space for provision of information related to one alternative, if more than one feasible and reasonable alternative is considered, the relevant section must be copied and completed for each alternative . 8. Unless protected by law all information contained in, and attached to this report, will become public information on receipt by the competent authority. If information is not submitted with this report due to such information being protected by law, the applicant and/or EAP must declare such non-disclosure and provide the reasons for the belief that the information is protected. 9. This report must be submitted to the Department at the postal address given below or by delivery thereof to the Registry Office of the Department. No faxed or e-mailed reports will be accepted. Please note that for waste management licence applications, this report must be submitted for the attention of the Department’s Waste Management Directorate (tel: 021-483-2756 and fax: 021-483-4425) at the same postal address as the Cape Town Office Region A. 10. Unless indicated otherwise, two electronic copies (CD/DVD) and three hard copies of this report must be submitted to the Department. DEPARTMENTAL DETAILS CAPE TOWN OFFICE REGION A (Cape Winelands, City of Cape Town: Tygerberg and Oostenberg Administrations) CAPE TOWN OFFICE REGION B (West Coast, Overberg, City of Cape Town: Helderberg, South Peninsula, Cape Town and Blaauwberg Administrations GEORGE OFFICE (Eden and Central Karoo) Department of Environmental Affairs and Development Planning Attention: Directorate: Integrated Environmental Management (Region A2) Private Bag X 9086 Cape Town, 8000 Registry Office 1 st Floor Utilitas Building 1 Dorp Street, Cape Town Queries should be directed to the Directorate: Integrated Environmental Management (Region A2) at: Tel: (021) 483-4793 Fax: (021) 483-3633 Department of Environmental Affairs and Development Planning Attention: Directorate: Integrated Environmental Management (Region B) Private Bag X 9086 Cape Town, 8000 Registry Office 1 st Floor Utilitas Building 1 Dorp Street, Cape Town Queries should be directed to the Directorate: Integrated Environmental Management (Region B) at: Tel: (021) 483-4094 Fax: (021) 483-4372 Department of Environmental Affairs and Development Planning Attention: Directorate: Integrated Environmental Management (Region A1) Private Bag X 6509 George, 6530 Registry Office 4 th Floor, York Park Building 93 York Street George Queries should be directed to the Directorate: Integrated Environmental Management (Region A1) at: Tel: (044) 805 8600 Fax: (044) 874-2423 View the Department’s website at http://www.capegateway.gov.za/eadp for the latest version of this document.

Transcript of BASIC ASSESSMENT REPORT (AUGUST 2010) Basic...

1

BASIC ASSESSMENT REPORT

(AUGUST 2010)

Basic Assessment Report in terms of the NEMA Environmental Impact Assessment

Regulations, 2010

AUGUST 2010

Kindly note that:

1. This Basic Assessment Report is the standard report required by DEA&DP in terms of the EIA Regulations, 2010 and must be

completed for all Basic Assessment applications. 2. This report must be used in all instances for Basic Assessment applications for an environmental authorisation in terms of the

National Environmental Management Act, 1998 (Act No. 107 of 1998) (NEMA), as amended, and the Environmental Impact Assessment Regulations, 2010, and/or a waste management licence in terms of the National Environmental Management: Waste Act, 2008 (Act 59 of 2008) (NEM: WA), and/or an atmospheric emission licence in terms of the National Environmental Management: Air Quality Act, 2004 (Act No. 39 of 2004) (NEM: AQA).

3. This report is current as of 2 August 2010. It is the responsibility of the Applicant / EAP to ascertain whether subsequent

versions of the report have been published or produced by the competent authority.

4. The required information must be typed within the spaces provided in the report. The sizes of the spaces provided are not necessarily indicative of the amount of information to be provided. It is in the form of a table that will expand as each space is filled with typing.

5. Incomplete reports will be rejected. A rejected report may be amended and resubmitted. 6. The use of “not applicable” in the report must be done with circumspection. Where it is used in respect of material

information that is required by the Department for assessing the application, this may result in the rejection of the report as provided for in the regulations.

7. While the different sections of the report only provide space for provision of information related to one alternative, if more

than one feasible and reasonable alternative is considered, the relevant section must be copied and completed for each alternative.

8. Unless protected by law all information contained in, and attached to this report, will become public information on

receipt by the competent authority. If information is not submitted with this report due to such information being protected by law, the applicant and/or EAP must declare such non-disclosure and provide the reasons for the belief that the information is protected.

9. This report must be submitted to the Department at the postal address given below or by delivery thereof to the Registry

Office of the Department. No faxed or e-mailed reports will be accepted. Please note that for waste management licence applications, this report must be submitted for the attention of the Department’s Waste Management Directorate (tel: 021-483-2756 and fax: 021-483-4425) at the same postal address as the Cape Town Office Region A.

10. Unless indicated otherwise, two electronic copies (CD/DVD) and three hard copies of this report must be submitted to the

Department.

DEPARTMENTAL DETAILS

CAPE TOWN OFFICE REGION A

(Cape Winelands, City of Cape Town:

Tygerberg and Oostenberg

Administrations)

CAPE TOWN OFFICE REGION B

(West Coast, Overberg, City of Cape Town:

Helderberg, South Peninsula, Cape Town

and Blaauwberg Administrations

GEORGE OFFICE

(Eden and Central Karoo)

Department of Environmental Affairs

and Development Planning

Attention: Directorate: Integrated

Environmental Management (Region

A2)

Private Bag X 9086

Cape Town,

8000

Registry Office

1st Floor Utilitas Building

1 Dorp Street,

Cape Town

Queries should be directed to the

Directorate: Integrated Environmental

Management (Region A2) at:

Tel: (021) 483-4793 Fax: (021) 483-3633

Department of Environmental Affairs and

Development Planning

Attention: Directorate: Integrated

Environmental Management (Region B)

Private Bag X 9086

Cape Town,

8000

Registry Office

1st Floor Utilitas Building

1 Dorp Street,

Cape Town

Queries should be directed to the

Directorate: Integrated Environmental

Management (Region B) at:

Tel: (021) 483-4094 Fax: (021) 483-4372

Department of Environmental Affairs

and Development Planning

Attention: Directorate: Integrated

Environmental Management (Region

A1)

Private Bag X 6509

George,

6530

Registry Office

4th Floor, York Park Building

93 York Street

George

Queries should be directed to the

Directorate: Integrated Environmental

Management (Region A1) at:

Tel: (044) 805 8600 Fax: (044) 874-2423

View the Department’s website at http://www.capegateway.gov.za/eadp for the latest version of this document.

2

DEPARTMENTAL REFERENCE NUMBER(S) File reference number (EIA): 16/3/3/6/7/1/B2/21/1299/16

File reference number (Waste): File reference number (Other):

PROJECT TITLE Expansion of tourism facilities, Slanghoek Mountain Resort, Farm 58 of 406

DETAILS OF THE ENVIRONMENTAL ASSESSMENT PRACTITIONER (EAP)

Environmental Assessment

Practitioner (EAP): PHS Consulting

Contact person: Amanda Fritz-Whyte

Postal address: Postbox 1752, Hermanus

Postal code: 7200

Telephone: (028) 312 1734 Cell: 082 327 2100

E-mail: [email protected] Fax: (086) 508 3249

EAP Qualifications MSc Water Resource Management

EAP Registrations/Associations Member WISA

Details of the EAP’s expertise to carry out Basic Assessment procedures

PHS Consulting – Amanda Fritz-Whyte MSc Water Resource Management Fynbosland 323 Reg: 2005/081216/23

EXECUTIVE SUMMARY OF THE CONTENT OF THE BASIC ASSESSMENT REPORT: The expansion of the existing Slanghoek Mountain Resort with 36 additional units of 120m

2 each. 13 existing tented units inside the

existing report will also be formalised to cottages. 29 new units are placed on current agricultural land, and the remainder 7 new units are proposed to be placed in a fynbos area with an estimated 936.25 m

2 of indigenous vegetation to be removed.

Existing internal roads will be used as access for all sites. Water will be provided from the existing borehole on site, through an ELU, and sewage from the units will be contained in conservancy tanks for removal to the Worcester WWTP. Electricity supply to the units will be ESKOM with solar geysers. Recycling will be implemented

in the units, with all waste taken offsite to the Worcester Landfill site for recycling or disposal. In terms of the overall project proposal the following alternatives apply:

Alternative 1 (Preferred Alternative) The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No new footprint.

Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m2 per

unit. Placed on agricultural land. Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Node 6: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 7 units is 936.25m2.

Potable water supply will be from Exiting Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used.

Alternative 2 The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B).

The nodes consist of: Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No

new footprint.

Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m2 per

unit. Placed on agricultural land. Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

3

Node 6: 5 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 9 units is 1 176.25m2.

Potable water supply will be from Exiting Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used.

Alternative 3 (no-go) Existing Resort will continue without expansion.

Upgrade of Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tent Potable water supply will be from Exiting Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

No new roads constructed for access and no removal if indigenous vegetation. Potable water supply will be from Exiting Lawful Use registered for the resort.

4

SECTION A: ACTIVITY INFORMATION 1. PROJECT DESCRIPTION

(a) Is the project a new development? YES X NO X

(b) Provide a detailed description of the development project and associated infrastructure.

The expansion of the existing Slanghoek Mountain Resort with 36 additional units of 120m2 each. 13 existing tented units inside the

existing report will also be formalised to cottages. 29 new units are placed on current agricultural land, and the remainder 7 new units are proposed to be placed in a fynbos area with an estimated 936.25 m

2 of indigenous vegetation to be removed.

Existing internal roads will be used as access for all sites. Water will be provided from the existing borehole on site, through an ELU, and sewage from the units will be contained in conservancy tanks for removal to the Worcester WWTP. Electricity supply to the units will be ESKOM with solar geysers. Recycling will be implemented

in the units, with all waste taken offsite to the Worcester Landfill site for recycling or disposal. In terms of the overall project proposal the following alternatives apply:

Alternative 1 (Preferred Alternative) The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No new footprint.

Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m2 per

unit. Placed on agricultural land. Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Node 6: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 7 units is 936.25m2.

Potable water supply will be from Exiting Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used.

Alternative 2 The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B).

The nodes consist of: Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No

new footprint.

Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m2 per

unit. Placed on agricultural land. Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 6: 5 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 9 units is 1 176.25m2.

Potable water supply will be from Exiting Lawful Use registered for the resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to be used for garden irrigation.

No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used. Alternative 3 (no-go)

Existing Resort will continue without expansion. Upgrade of Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tent Potable water supply will be from Exiting Lawful Use registered for the resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. No new roads constructed for access and no removal if indigenous vegetation. Potable water supply will be from Exiting Lawful Use registered for the resort.

(c) List all the activities assessed during the Basic Assessment process:

GN No. R. 544

Activity No(s):

Describe the relevant Basic Assessment

Activity(ies) in writing as per Listing Notice 1

(GN No. R. 544)

Describe the portion of the development as per the

project description that relates to the applicable listed

activity.

n/a n/a n/a

5

GN No. R. 546

Activity No(s):

Describe the relevant Basic Assessment

Activity(ies) in writing as per Listing Notice 3

(GN No. R. 546)

Describe the portion of the development as per the

project description that relates to the applicable listed

activity.

GN No. R985

Activity 12

The clearance of an area of 300 square metres or more

of indigenous vegetation except where such clearance of indigenous vegetation is required for maintenance purposes undertaken in accordance with a

maintenance management plan. In the Western Cape:

i. Within any critically endangered or

endangered ecosystem listed in terms of Section 52 of NEMBA or prior to the publication of such a list, within an area

that has been identified as critically endangered in the National Biodiversity Assessment 2004;

ii. Within critical biodiversity areas identified in bioregional plans;

29 new units are placed on current agricultural land, and the remainder 7 new units are proposed to be placed in a fynbos

area with an estimated 936.25 m2 of indigenous vegetation to

be removed.

Activity 14 The development of –

(x) buildings exceeding 10m2 in size;

(xii) infrastructure or structures with a physical footprint of 10m

2 or more;

Where such development occurs – (c) if no development setback has been adopted, within 32m of a watercourse, measured from the edge of the

watercourse (f) in Western Cape: I Outside Urban area, in:

(ff) Critical Biodiversity areas or ecosystem service areas as identified in systematic biodiversity plans adopted by the competent authority or in bioregional

plans; (gg) Core areas in Biosphere Reserves;

Three proposed units within Node 4 will be placed on existing

agricultural land within 32m of a drainage line.

Activity 17 The expansion of a resort, lodge, hotel and tourism or

hospitality facilities where the development footprint will be expanded. Areas in the Western Cape:

(i) A protected area identified in terms of the NEMPAA;

(ii) Critical biodiversity areas as identified in

systematic biodiversity plans adopted by the competent authority or in bioregional plans; or

(iii) All areas outside urban areas.

The existing Slanghoek Mountain resort will be expanded by

29 new units on current agricultural land, and the remainder 7 new units in a fynbos area with an estimated 936.25 m

2 of

indigenous vegetation to be removed.

If the application is also for activities as per Listing Notice 2 and permission was granted to subject the application to Basic

Assessment, also indicate the applicable Listing Notice 2 activities:

GN No. R. 545

Activity No(s):

If permission was granted in terms of Regulation 20,

describe the relevant Scoping and EIA Activity(ies)

in writing as per Listing Notice 2 (GN No. R. 545)

Describe the portion of the development as per the

project description that relates to the applicable listed

activity.

N/A N/A N/A

Waste management activities in terms of the NEM: WA (Government Gazette No. 32368):

GN No. 718 - Category A

Activity No(s): Describe the relevant Category A waste management activity in writing.

N/A N/A

Please note: If any waste management activities are applicable, the Listed Waste Management Activities Additional

Information Annexure must be completed and attached to this Basic Assessment Report as Appendix I.

If the application is also for waste management activities as per Category B and permission was granted to subject the

application to Basic Assessment, also indicate the applicable Category B activities:

GN No. 718 – Category B

Activity No(s): Describe the relevant Category B waste management activity in writing.

N/A N/A

Atmospheric emission activities in terms of the NEM: AQA (Government Gazette No. 33064):

GN No. 248

Activity No(s): Describe the relevant atmospheric emission activity in writing.

N/A N/A

6

(d) Please provide details of all components of the proposed project and attach diagrams (e.g. architectural drawings or

perspectives, engineering drawings, process flow charts etc.).

Buildings YES X NO

The expansion of the existing Slanghoek Mountain Resort with 36 additional units of 120m2 each. 13 existing tented units inside the

existing report will also be formalised to cottages. 29 new units will be placed on current agricultural land, and the remainder 7 new units are proposed to be placed in a fynbos area with an estimated 936.25 m

2 of indigenous vegetation to be removed.

Each new unit to have a parking bay of 13.75m2. See SDP Appendix B and Townplanning Application Appendix J.

Infrastructure (e.g. roads, power and water supply/ storage) YES X NO

Provide brief description: Potable water supply will be from Exiting Lawful Use registered for the resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. Conservancy tanks at all new units as with existing resort units, and serviced by Breede Valley Local Municipality. Grey water from units to be used for garden irrigation.

No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used.

Processing activities (e.g. manufacturing, storage, distribution) YES NO X

Provide brief description:

Storage facilities for raw materials and products (e.g. volume and substances to be stored)

Provide brief description:

YES NO X

Storage and treatment facilities for solid waste and effluent generated by the project Yes NO X

Provide brief description:

Other activities (e.g. water abstraction activities, crop planting activities) Yes X No

Provide brief description:

Potable water supply will be from Exiting Lawful Use registered for the resort. Confirmation Letter from BGCMA in Appendix J still outstanding.

2. PHYSICAL SIZE OF THE ACTIVITY

Size of the property:

(a) Indicate the size of the property (cadastral unit) on which the activity is to be undertaken. 64.72 ha

Size of the facility:

(b) Indicate the size of the facility (development area) on which the activity is to be

undertaken.

Existing resort ± 22 455m2

New ± 4815m2

Size of the activity:

(c) Indicate the physical size (footprint) of the activity together with its associated infrastructure: Existing ± 31821m

2

New ± 4815m2

(d) Indicate the physical size (footprint) of the activity:

Existing tented units to be

upgraded ± 1560m2

New units ± 4815m2

(e) Indicate the physical size (footprint) of the associated infrastructure: Existing roads ± 9366m2

and, for linear activities:

Length of the activity:

(f) Indicate the length of the activity: ±m

3. SITE ACCESS

(a) Is there an existing access road? YES X NO

(b) If no, what is the distance over which a new access road will be built? m

(c) Describe the type of access road planned:

Please Note: indicate the position of the proposed access road on the site plan.

4. DESCRIPTION OF THE PROPERTY ON WHICH THE ACTIVITY IS TO BE UNDERTAKEN AND THE

LOCATION OF THE ACTIVITY ON THE PROPERTY

(a) Provide a description of the property on which the activity is to be undertaken and the location of the activity on the

property.

7

Farm 58/406 is located approximately 10km North-West of Rawsonville, on Divisional Road 1398 at the foot of the Badsberg Mountains. The farm is 64.72ha in size. Slanghoek Mountain resort is an existing holiday accommodation facility. The proposed activity is spread over

6 Nodes (see SDP Appendix B).

(b) Please provide a location map (see below) as Appendix A to this report which shows the location of the property and the

location of the activity on the property; as well as a site map (see below) as Appendix B to this report; and if applicable all

alternative properties and locations.

Locality map:

The scale of the locality map must be at least 1:50 000. For linear activities of more than 25 kilometres, a

smaller scale e.g. 1:250 000 can be used. The scale must be indicated on the map. The map must indicate

the following:

an accurate indication of the project site position as well as the positions of the alternative sites, if any;

road names or numbers of all the major roads as well as the roads that provide access to the site(s)

a north arrow;

a legend; the prevailing wind direction (during November to April and during May to October); and

GPS co-ordinates (Indicate the position of the activity using the latitude and longitude of the centre

point of the site for each alternative site. The co-ordinates should be in degrees and decimal minutes.

The minutes should have at least three decimals to ensure adequate accuracy. The projection that

must be used in all cases is the WGS84 spheroid in a national or local projection).

Site Plan:

Detailed site plan(s) must be prepared for each alternative site or alternative activity. The site plan must

contain or conform to the following:

The detailed site plan must be at a scale preferably at a scale of 1:500 or at an appropriate scale. The

scale must be indicated on the plan.

The property boundaries and numbers of all the properties within 50m of the site must be indicated on

the site plan.

The current land use (not zoning) as well as the land use zoning of each of the adjoining properties must

be indicated on the site plan.

The position of each element of the application as well as any other structures on the si te must be

indicated on the site plan.

Services, including electricity supply cables (indicate above or underground), water supply pipelines,

boreholes, sewage pipelines, storm water infrastructure and access roads that will form part of the

development must be indicated on the site plan.

Servitudes indicating the purpose of the servitude must be indicated on the site plan.

Sensitive environmental elements within 100m of the site must be included on the site plan, including (but

not limited to):

o Rivers.

o Flood lines (i.e. 1:10, 1:50, year and 32 meter set back line from the banks of a river/stream).

o Ridges.

o Cultural and historical features.

o Areas with indigenous vegetation (even if it is degraded or infested with alien species).

Whenever the slope of the site exceeds 1:10, then a contour map of the site must be submitted.

(c) For a linear activity, please also provide a description of the route.

N/A

Indicate the position of the activity using the latitude and

longitude of the centre point of the site. The co-ordinates

must be in degrees, minutes and seconds. The minutes should

be given to at least three decimals to ensure adequate

accuracy. The projection that must be used in all cases is the

WGS84 spheroid in a national or local projection.

Latitude (S): Longitude (E):

33°

37‘ 50.97“ 19° 13‘ 49.26“

(d) or:

For linear activities: Latitude (S): Longitude (E):

Starting point of the activity

Middle point of the activity

End point of the activity

Please Note: For linear activities that are longer than 500m, please provide and addendum with co-ordinates taken every 100

meters along the route.

5. SITE PHOTOGRAPHS

8

Colour photographs of the site and its surroundings (taken of the site and from the site) with a description of each photograph.

The vantage points from which the photographs were taken must be indicated on the site plan, or locality plan as applicable. If

available, please also provide a recent aerial photograph. Photographs must be attached as Appendix C to this report. It

should be supplemented with additional photographs of relevant features on the site. Date of photographs must be included.

Please note that the above requirements must be duplicated for all alternative sites.

9

SECTION B: DESCRIPTION OF RECEIVING ENVIRONMENT

Site/Area Description

For linear activities (pipelines, etc.) as well as activities that cover very large sites, it may be necessary to complete copies of this

section for each part of the site that has a significantly different environment. In such cases please complete copies of Section

B and indicate the area which is covered by each copy No. on the Site Plan.

1. GRADIENT OF THE SITE

Indicate the general gradient of the sites (highlight the appropriate box).

Flat Flatter than 1:10 X 1:10 – 1:4 X Steeper than 1:4

2. LOCATION IN LANDSCAPE

(a) Indicate the landform(s) that best describes the site (highlight the appropriate box(es).

Ridgeline

Plateau

Side slope of

hill/mountain

X

Closed

valley

Open

valley

Plain

Undulating

plain/low

hills

Dune Sea-front

(b) Please provide a description of the location in the landscape.

The proposed site is located on the western slopes of the Badsberg Mountain (highest peak 977m) in the Slanghoek Valley flanked by the

Slanghoek Mountains on the south, west and north (highest peak 1695 m). It is located within an area characterised by high mountain

ranges with steep slopes and open cultivated valleys with primarily agricultural and tourism activities. Slanghoek Mountain resort is an

existing holiday accommodation venue.

3. GROUNDWATER, SOIL AND GEOLOGICAL STABILITY OF THE SITE

(a) Is the site(s) located on or near any of the following (highlight the appropriate boxes)?

Shallow water table (less than 1.5m deep) YES NO X UNSURE

Seasonally wet soils (often close to water bodies) YES NO X UNSURE Unstable rocky slopes or steep slopes with loose soil YES NO X UNSURE Dispersive soils (soils that dissolve in water) YES NO X UNSURE Soils with high clay content YES NO X UNSURE Any other unstable soil or geological feature YES NO X UNSURE An area sensitive to erosion YES NO X UNSURE An area adjacent to or above an aquifer. YES NO X UNSURE An area within 100m of the source of surface water YES NO X UNSURE

(b) If any of the answers to the above are “YES” or “unsure”, specialist input may be requested by the Department.

(Information in respect of the above will often be available at the planning sections of local authorities. Where it exists, the

1:50 000 scale Regional Geotechnical Maps prepared by Geological Survey may also be used).

(c) Please indicate the type of geological formation underlying the site.

Granite Shale Sandstone X Quartzite Dolomite Dolorite Other

(describe)

10

4. SURFACE WATER

(a) Indicate the surface water present on and or adjacent to the site and alternative sites (highlight the appropriate boxes)

Perennial River YES NO X UNSURE

Non-Perennial Stream YES X NO UNSURE

Permanent Wetland YES NO X UNSURE

Seasonal Wetland YES NO X UNSURE

Artificial Wetland YES NO X UNSURE

Estuarine / Lagoonal wetland YES NO X UNSURE

(b) Please provide a description.

There are two drainage lines from the Badsberg Mountain in the East towards a tributary of the Slanghoekriver in the West.

They have both been historically altered by farming activities and do not follow their original drainage paths. Three of the

proposed units are within 32m of either of these drainage lines.

5. BIODIVERSITY:

Please note: The Department may request specialist input/studies depending on the nature of the biodiversity occurring on the

site and potential impact(s) of the proposed activity/ies. To assist with the identification of the biodiversity occurring on site and

the ecosystem status consult http://bgis.sanbi.org or [email protected]. Information is also available on compact disc (cd)

from the Biodiversity-GIS Unit, Ph (021) 799 8698. This information may be updated from time to time and it is the applicant/ EAP’s

responsibility to ensure that the latest version is used. A map of the relevant biodiversity information (including an indication of

the habitat conditions as per (b) below) and must be provided as an overlay map to the property/site plan as Appendix D to

this report.

(a) Highlight the applicable biodiversity planning categories of all areas on site and indicate the reason(s) provided in the

biodiversity plan for the selection of the specific area as part of the specific category).

Systematic Biodiversity Planning Category If CBA or ESA, indicate the reason(s) for its selection in biodiversity

plan

Critical

Biodiversity

Area

(CBA) X

Ecological

Support

Area (ESA)

X

Other

Natural

Area (ONA)

No Natural

Area

Remaining

(NNR)

The occurrence of endangered vegetation on site. The vegetation types on

site are mapped as Breede Alluvium Fynbos (endangered) and Breede Shale Fynbos (see Appendix J for CapeNature communication explaining on site verification of vegetation and need for botanical study).

None of the proposed units are in the CBA mapped area. The ESA mapped area covers existing agricultural land that will remain intact (see Appendix

D).

(b) Highlight and describe the habitat condition on site.

Habitat Condition

Percentage of

habitat condition

class (adding up

to 100%)

Description and additional Comments and Observations

(including additional insight into condition, e.g. poor land management

practises, presence of quarries, grazing/harvesting regimes etc).

Natural 52.92ha

The vegetation types on site are mapped as Breede Alluvium Fynbos (endangered) and Breede Shale Fynbos (see also Capenature comment Appendix J).

Near Natural

(includes areas with low

to moderate level of alien

invasive plants)

Degraded

(includes areas heavily

invaded by alien plants)

Transformed

(includes cultivation,

dams, urban, plantation,

roads, etc)

11.8ha

Crops vary from grapes for wine to olive trees. Existing Slanghoek Mountain resort.

(c) Complete the table to indicate:

(i) the type of vegetation, including its ecosystem status, present on the site; and

11

(ii) whether an aquatic ecosystem is present on site.

(d) Please provide a description of the vegetation type and/or aquatic ecosystem present on site, including any important

biodiversity features/information identified on site (e.g. threatened species and special habitats)

The vegetation types on site are Breede Alluvium Fynbos (endangered) and Breede Shale Fynbos. It should be noted that although the

South African Vegetation Map has mapped this area as Breede Shale Fynbos, this is incorrect especially for the hilltop site, which can best be described as Hawequas Sandstone Fynbos (considering the geology as well as the vegetation). There are two drainage lines from the Badsberg Mountain in the East towards a tributary of the Slanghoekriver in the West. They have both been historically altered by

farming activities and do not follow their original drainage paths. Three of the proposed units are within 32m of either of these drainage lines, located within an existing agricultural area.

6. LAND USE OF THE SITE

Please note: The Department may request specialist input/studies depending on the nature of the land use character of the

area and potential impact(s) of the proposed activity/ies.

Untransformed area X

Low density

residential

Medium density

residential

High density

residential Informal residential

Retail Commercial &

warehousing Light industrial Medium industrial Heavy industrial

Power station Office/consulting

room

Military or police

base/station/compound

Casino/entertainment

complex

Tourism &

Hospitality facility

X

Open cast mine Underground

mine Spoil heap or slimes dam

Quarry, sand or

borrow pit

Dam or reservoir

Hospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plant Train station or

shunting yard Railway line

Major road (4 lanes or

more) Airport

Harbour Sport facilities Golf course Polo fields Filling station

Landfill or waste treatment site Plantation Agriculture X River, stream or

wetland

Nature

conservation area

X

Mountain, koppie or ridge X Museum Historical building Graveyard Archaeological

site

Other land uses (describe):

(a) Please provide a description.

The current Slanghoek Mountain Resort is located on a working farm, with vines and olive trees on site. The farm forms part of the

Badsberg Conservancy, and also falls within the Cape Winelands Biosphere reserve.

(vii) LAND USE CHARACTER OF SURROUNDING AREA

(a) Highlight the current land uses and/or prominent features that occur within +/- 500m radius of the site and neighbouring

properties if these are located beyond 500m of the site.

Please note: The Department may request specialist input/studies depending on the nature of the land use character of the

area and potential impact(s) of the proposed activity/ies.

Untransformed area X

Low density

residential

Medium density

residential

High density

residential Informal residential

Terrestrial Ecosystems Aquatic Ecosystems

Ecosystem threat status as per the

National Environmental

Management: Biodiversity Act (Act

No. 10 of 2004)

Critical Wetland (including rivers,

depressions, channelled

and unchanneled

wetlands, flats, seeps

pans, and artificial

wetlands)

Estuary Coastline

Endangered

X

Vulnerable

Least

Threatened YES

NO

X UNSURE YES NO X YES NO X

12

Retail Commercial &

warehousing Light industrial Medium industrial Heavy industrial

Power station Office/consulting

room

Military or police

base/station/compound

Casino/entertainment

complex

Tourism &

Hospitality facility

X

Open cast mine Underground

mine Spoil heap or slimes dam

Quarry, sand or

borrow pit

Dam or reservoir

X

Hospital/medical center School Tertiary education facility Church Old age home

Sewage treatment plant Train station or

shunting yard Railway line

Major road (4 lanes or

more) Airport

Harbour Sport facilities Golf course Polo fields Filling station

Landfill or waste treatment site Plantation Agriculture X River, stream or

wetland X

Nature

conservation area

X

Mountain, koppie or ridge

X Museum Historical building Graveyard Archeological site

Other land uses (describe):

(b) Please provide a description, including the distance and direction to the nearest residential area and industrial area.

The property is located in a typical rural setting. Agricultural land use is the dominant land use in the area with viticulture being the most common activity. Various agri-tourism operations have also been identified in the landscape. The Slanghoek Valley is well-known for its destination weddings, wine tasting, and hiking and mountain biking activities. The closest residential town is Rawsonville approximately

10km SE of the site, with Worcester being the closest town with industrial activities.

8. SOCIO-ECONOMIC ASPECTS

Describe the existing social and economic characteristics of the community in order to provide baseline information.

The majority of people living in the landscape are farm labourers and farmers. Job opportunities are limited to mostly unskilled farming

activities with a small number of managerial opportunities present. The area is also active i.t.o. tourism with restaurants, overnight establishments wine farms and destination wedding facilities, which create job opportunities.

13

(VII) HISTORICAL AND CULTURAL ASPECTS

(a) Please be advised that if section 38 of the National Heritage Resources Act, 1999 (Act No. 25 of 1999), is applicable to your

proposed development, then you are requested to furnish this Department with written comment from Heritage Western

Cape as part of your public participation process. Section 38 of the Act states as follows: “38. (1) Subject to the provisions

of subsections (7), (8) and (9), any person who intends to undertake a development categorised as-

(a) the construction of a road, wall, power line, pipeline, canal or other similar form of linear development or barrier

exceeding 300m in length;

(b) the construction of a bridge or similar structure exceeding 50m in length;

I any development or other activity which will change the character of a site-

(vii) exceeding 5 000 m2 in extent; or

(ii) involving three or more existing erven or subdivisions thereof; or

(vii) involving three or more erven or divisions thereof which have been consolidated within the past five

years; or

(vii) the costs of which will exceed a sum set in terms of regulations by SAHRA or a provincial heritage resources

authority;

(d) the re-zoning of a site exceeding 10 000 m2 in extent; or

(e) any other category of development provided for in regulations by SAHRA or a provincial heritage resources

authority,

must at the very earliest stages of initiating such a development, notify the responsible heritage resources authority

and furnish it with details regarding the location, nature and extent of the proposed development.”

(b) The impact on any national estate referred to in section 3(2), excluding the national estate contemplated in section

3(2)(i)(vi) and (vii), of the National Heritage Resources Act, 1999 (Act No. 25 of 1999), must also be investigated, assessed

and evaluated. Section 3(2) states as follows: “3(2) Without limiting the generality of subsection (1), the national estate may

include—

(a) places, buildings, structures and equipment of cultural significance;

(b) places to which oral traditions are attached or which are associated with living heritage;

I historical settlements and townscapes;

(d) landscapes and natural features of cultural significance;

(e) geological sites of scientific or cultural importance;

(f) archaeological and palaeontological sites;

(g) graves and burial grounds, including—

(i) ancestral graves;

(ii) royal graves and graves of traditional leaders;

(vii) graves of victims of conflict;

(iv) graves of individuals designated by the Minister by notice in the Gazette;

(v) historical graves and cemeteries; and

(vi) other human remains which are not covered in terms of the Human Tissue Act, 1983 (Act No. 65 of 1983);

(h) sites of significance relating to the history of slavery in South Africa;

(i) movable objects, including—

(i) objects recovered from the soil or waters of South Africa, including archaeological and palaeontological objects

and material, meteorites and rare geological specimens;

(ii) objects to which oral traditions are attached or which are associated with living heritage;

(vii) ethnographic art and objects;

(iv) military objects;

(v) objects of decorative or fine art;

(vi) objects of scientific or technological interest; and

(vii) books, records, documents, photographic positives and negatives, graphic, film or video material or sound

recordings, excluding those that are public records as defined in section 1(xiv) of the National Archives of South Africa

Act, 1996 (Act No. 43 of 1996).”

Is section 38 of the National Heritage Resources Act, 1999, applicable to the development? YES NO X

UNCERTAIN

If YES, explain:

The footprint of the proposed development will be rezoned from Residential Zone V and Agricultural

Zone I to Resort Zone I with Consent use for Tourism Facilities on proposed Resort Zone I and Agricultural

zone II to accommodate the proposed extension of the existing resort (see Townplanning document

Appendix J).

A NID and screener was submitted to HWC. See also Appendix J.

Will the development impact on any national estate referred to in section 3(2) of the National

Heritage Resources Act, 1999?

YES NO X

UNCERTAIN

If YES, explain:

Will any building or structure older than 60 years be affected in any way? YES NO X UNCERTAIN

If YES, explain: Farm was recently developed by previous owner

14

Please Note: If uncertain, the Department may request that specialist input be provided.

10. APPLICABLE LEGISLATION, POLICIES AND/OR GUIDELINES

(a) Please list all legislation, policies and/or guidelines that have been considered in the preparation of this Basic Assessment

Report.

LEGISLATION ADMINISTERING AUTHORITY

TYPE

Permit/ license/

authorisation/comment / relevant

consideration (e.g. rezoning or

consent use, building plan approval)

DATE

(if already

obtained):

National Environmental Management

Act No 107 of 1998

The Department of Environmental

Affairs and Development Planning Authorization Pending

National Water Act, Act 36 of 1998 BGCMA Letter re ELU and comment Pending

Bylaw on Municipal Landuse Planning Breede Valley Local Municipality Rezoning and Consent use application Pending

NHRA, Act 25 of 1999 HWC NID application and Screener Pending

POLICY/ GUIDELINES ADMINISTERING AUTHORITY

DEA&DP guidelines on Public Participation DEA&DP

Guidelines for EMP’s DEA&DP

NEMA; EIA Regs 2014 DEA&DP

Guidelines on Alternatives DEA&DP

BGIS SANBI

CapeFarmMapper Western Cape Department of Agriculture

(b) Please describe how the legislation, policies and/or guidelines were taken into account in the preparation of this Basic

Assessment Report.

LEGISLATION / POLICY / GUIDELINE DESCRIBE HOW THE LEGISLATION / POLICY / GUIDELINE WERE TAKEN INTO ACCOUNT

(e.g. describe the extent to which it was adhered to, or deviated from, etc).

National Environmental Management Act (Act 107 of 1998)

Listed Activities which trigger a Basic Assessment (BA), currently being undertaken here.

DEA&DP guidelines on Public Participation

Public Participation Process must take place during the BA process in order for the process to

be transparent and allow for I&AP comments and concerns to be raised and subsequently addressed. Proof of PPP will need to be included in final reports.

Guidelines for EMP’s Ensures that construction and operational activities, should a positive ROD be received, are environmentally friendly and comply with all restrictions or guidelines stipulated in the BA/ROD.

Guidelines for Alternatives Ensures alternative chosen are reasonable and feasible as far as possible.

NWA, Act 36 of 1998 Water use authorization requirements on site – GA granted

NHRA, Act 25 of 1999 NID submitted in terms of S38, and screener.

Please note: Copies of any permit(s) or licences received from any other organ of state must be attached this report as

Appendix E.

15

SECTION C: PUBLIC PARTICIPATION

The public participation process must fulfil the requirements outlined in NEMA, the EIA Regulations, and if applicable the NEM:

WA and/or the NEM: AQA. This Department’s Guideline on Public Participation (August 2010) and Guideline on Exemption

Applications (August 2010), both of which are available on the Department’s website (http://www.capegateway.gov.za/eadp),

must also be taken into account.

Please highlight the appropriate box to indicate whether the specific requirement was undertaken or whether there was a

deviation that was agreed to by the Department.

1. Were all potential interested and affected parties notified of the application by –

(a) fixing a notice board at a place conspicuous to the public at the boundary or on the fence of -

(i) the site where the activity to which the application relates is to be undertaken; and YES X DEVIATED

(ii) any alternative site mentioned in the application; N/A YES DEVIATED

(b) giving written notice to –

(i) the owner or person in control of that land if the applicant is not the owner or person in

control of the land; YES N/A X

(ii) the occupiers of the site where the activity is to be undertaken and to any alternative

site where the activity is to be undertaken; N/A YES DEVIATED

(iii) owners and occupiers of land adjacent to the site where the activity is to be

undertaken and to any alternative site where the activity is to be undertaken; YES X DEVIATED

(iv) the municipal councillor of the ward in which the site and alternative site is situated

and any organisation of ratepayers that represent the community in the area; YES X DEVIATED

(v) the municipality which has jurisdiction in the area; YES X DEVIATED

(vi) any organ of state having jurisdiction in respect of any aspect of the activity; and YES X DEVIATED

(vii) any other party as required by the competent authority; YES X DEVIATED

I placing an advertisement in -

(i) one* local newspaper; and YES X DEVIATED

(ii) any official Gazette that is published specifically for the purpose of providing public

notice of applications or other submissions made in terms of these Regulations; YE S DEVIATED

N/A

X

(d) placing an advertisement in at least one* provincial newspaper or national newspaper,

if the activity has or may have an impact that extends beyond the boundaries of the

metropolitan or local municipality in which it is or will be undertaken.

YE S DEVIATED N/A

X

* Please note: In terms of the NEM: WA and NEM: AQA a notice must be placed in at least two newspapers circulating in the

area in which the activity applied for is to be carried out.

3. Please provide an overall summary of the Public Participation Process that was followed. (The detailed outcomes of

this process must be included in a comments and response report to be attached to the final Basic Assessment Report

(see note below) as Appendix F).

The Draft BAR will be circulated to all Interested and Affected Parties (I&AP’s) as per DEA&DP guidelines and applicable Organs of State for 30 days. An English advert will be placed in the local newspaper, the Worcester Standard, informing all possible I&AP’s of the Basic Assessment, with contact details of the EAP in order to register as an I&AP. Notices will be sent to all I&AP’s

within 100m of the proposed development area. All people requesting to become I&AP’s for the project will be included in the register for I&AP’s. A site notice will be placed at the entrance to the site. All comments received from I&AP’s will be captured in a Comments and Response Report and addressed accordingly. A second draft BAR will be circulated to registered I&AP’s for a

30 day comment period, with the Comments and Response Report updated to reflect feedback.

2. Provide a list of all the state departments that were consulted:

DEA&DP (Western-Cape)

Breede Gouritz Catchment Management Agency (BGCMA)

Department of Agriculture, Forestry and Fisheries (Western-Cape)

CapeNature

Cape Winelands District Municipality

Breede Local Municipality

Department of Public Works and Transport

Heritage Western Cape

National DAFF

DEA&DP Directorate : Waste Management

16

Please note:

Should any of the responses be “No” and no deviation or exemption from that requirement was

requested and agreed to /granted by the Department, the Basic Assessment Report will be rejected.

A list of all the potential interested and affected parties, including the organs of State, notified and a list

of all the register of interested and affected parties, must be submitted with the final Basic Assessment

Report. The list of registered interested and affected parties must be opened, maintained and made

available to any person requesting access to the register in writing.

The draft Basic Assessment Report must be submitted to the Department before it is made available to

interested and affected parties, including the relevant organs of State and State departments which

have jurisdiction with regard to any aspect of the activity, for a 40-day commenting period. With regard

to State departments, the 40-day period commences the day after the date on which the Department

as the competent/licensing authority requests such State department in writing to submit comment. The

applicant/EAP is therefore required to inform this Department in writing when the draft Basic Assessment

Report will be made available to the relevant State departments for comment. Upon receipt of the Draft

Basic Assessment Report and this confirmation, this Department will in accordance with Section 24O(2)

and (3) of the NEMA request the relevant State departments to comment on the draft report within 40

days.

All comments of interested and affected parties on the draft Basic Assessment Report must be recorded,

responded to and included in the Comments and Responses Report included as Appendix F to the final

Basic Assessment Report. If necessary, any amendments in response to comments received must be

effected in the Basic Assessment Report itself. The Comments and Responses Report must also include a

description of the public participation process followed.

The final Basic Assessment Report must be made available to registered interested and affected parties

for comment before submitting it to the Department for consideration. Unless otherwise indicated by the

Department, a final Basic Assessment Report must be made available to the registered interested and

affected parties for comment for a minimum of 21-days. Comments on the final Basic Assessment Report

does not have to be responded to, but the comments must be attached to the final Basic Assessment

Report.

The minutes of any meetings held by the EAP with interested and affected parties and other role players

which record the views of the participants must also be submitted as part of the public participation

information to be attached to the final Basic Assessment Report as Appendix F.

Proof of all the notices given as indicated, as well as of notice to the interested and affected parties of

the availability of the draft Basic Assessment Report and final Basic Assessment Report must be submitted

17

as part of the public participation information to be attached to the final Basic Assessment Report as

Appendix F.

SECTION D: NEED AND DESIRABILITY

Please Note: Before completing this section, first consult this Department’s Guideline on Need and Desirability (August 2010)

available on the Department’s website (http://www.capegateway.gov.za/eadp).

1. Is the activity permitted in terms of the property’s existing land use rights? YES NO X Please explain

The footprint of the proposed development will be rezoned from Residential Zone V and Agricultural Zone I to Resort Zone I with

Consent use for Tourism Facilities on proposed Resort Zone I and Agricultural zone II to accommodate the proposed extension

of the existing resort ( see Townplanning document Appendix J).

2. Will the activity be in line with the following?

(a) Provincial Spatial Development Framework (PSDF) YES X NO Please explain

The Cape Winelands District Municipality SDP Recognises the Cape Winelands Biosphere Reserve as a core area for tourism

and thus economic development.( see Townplanning document Appendix J page 24).

(b) Urban edge / Edge of Built environment for the area YES NO Please explain

N/A

(c) Integrated Development Plan and Spatial Development Framework of the

Local Municipality (e.g. would the approval of this application compromise the

integrity of the existing approved and credible municipal IDP and SDF?).

YES X NO Please explain

The IDP recognises the importance of economic development and upliftment for the Breede Valley area along with rural node

development. The IDP recognises the importance of the tourism sector and its importance to stimulate the local economy in

addition to job creation. (see Townplanning document Appendix J page 24).

(d) Approved Structure Plan of the Municipality YES NO X Please explain

There is no structure plan for the area, except for the Provincial Spatial Development Framework.

(e) An Environmental Management Framework (EMF) adopted by the Department

(e.g. Would the approval of this application compromise the integrity of the existing

environmental management priorities for the area and if so, can it be justified in

terms of sustainability considerations?)

YES

X NO Please explain

The EMF aims to develop agri-environmental partnerships that allow for productive use of farmland while supporting

biodiversity conservation. Slanghoek Mountain Resort lies adjacent to the Badsberg Conservancy and forms part of the Cape

Winelands Biosphere reserve, whilst also located on a working farm.

(f) Any other Plans (e.g. Guide Plan) YES NO X Please explain

3. Is the land use (associated with the activity being applied for) considered

within the timeframe intended by the existing approved Spatial Development

Framework (SDF) agreed to by the relevant environmental authority (i.e. is the

proposed development in line with the projects and programmes identified as

priorities within the credible IDP)?

YES

X

NO Please explain

The IDP recognises the importance of economic development and upliftment for the Breede Valley area along with rural node

development. The IDP recognises the importance of the tourism sector and its importance to stimulate the local economy in

addition to job creation. 4. Should development, or if applicable, expansion of the town/area concerned

in terms of this land use (associated with the activity being applied for) occur

here at this point in time?

YES X NO Please explain

The proposal is in keeping with the existing planning frameworks for the area, and allows Slanghoek Mountain Resort to

expand to meet the growing need for overnight facilities in the area.

5. Does the community/area need the activity and the associated land use

concerned (is it a societal priority)? (This refers to the strategic as well as local

level (e.g. development is a national priority, but within a specific local context

it could be inappropriate.)

YES X NO Please explain

A number of temporary and long term job opportunities will be created with the construction of the proposed development. More tourists coming to the area would also benefit the greater community in terms of trade and exposure. The existing accommodation offered by the resort is insufficient and the expansion will allow the resort to meet the growing need in the area.

6. Are the necessary services with adequate capacity currently available (at the

time of application), or must additional capacity be created to cater for the

development? (Confirmation by the relevant Municipality in this regard must

be attached to the final Basic Assessment Report as Appendix E.)

YES X NO Please explain

Electricity from ESKOM and solar panels; Water from existing ELU as authorised by BGCMA; Waste to landfill; Conservancy tanks to be

emptied to the Worcester WWTP. See communications in Appendix E.

7. Is this development provided for in the infrastructure planning of the

municipality, and if not what will the implication be on the infrastructure

planning of the municipality (priority and placement of services and

opportunity costs)? (Comment by the relevant Municipality in this regard must

YES NO Please explain

18

(17) Please describe how the general objectives of Integrated Environmental Management as set out in section 23 of NEMA

have been taken into account:

This Basic Assessment Report aims to investigate, assess and communicate all potential impacts of the proposed development. All

potential impacts will be identified and any suitable alternatives to mitigate or eliminate these impacts will be explored. Impacts to the environment as well as socio-economic impacts and cultural / heritage impacts will be explored. The No Go option will also be put forward as an alternative along with any other reasonable and feasible alternatives. The Slanghoek Mountain Resort is an existing tourism facility

with existing impacts. The potential impacts from the proposed expansion were considered and mitigation measures were proposed. Principles such as solar energy, water conservation, waste management, biodiversity conservation were considered and integrated with the proposed plan of works. The BAR process allows for public participation to incorporate additional needs of the immediate community.

(18) Please describe how the principles of environmental management as set out in section 2 of NEMA have been taken into

account:

be attached to the final Basic Assessment Report as Appendix E.)

N/A.

8. Is this project part of a national programme to address an issue of national

concern or importance? YES NO X Please explain

9. Do location factors favour this land use (associated with the activity applied

for) at this place? (This relates to the contextualisation of the proposed land

use on this site within its broader context.)

YES X NO Please explain

It is well placed for the use of hiking trails and birding, and other eco-tourism and agri-tourism activities in the area. The scenic view,

tranquillity of the surroundings and proximity to conference and wedding facilities makes the location very favourable.

10. How will the activity or the land use associated with the activity applied for,

impact on sensitive natural and cultural areas (built and rural/natural

environment)?

YES NO X Please explain

The Slanghoek Mountain Resort already exists and this application is for an expansion of the facilities. The site falls within the Badsberg Conservancy and the Cape Winelands Biosphere Reserve. The operational impacts associated with the activity will be addressed in the OEMP. The SEA Botanical study conducted in the area in 2014 (see Appendix J) highlighted Farm 58/406 with development potential

based on a low biodiversity score, but with specialist input needed. That input was supplied by CapeNature during a site verification visit and formal feedback (see also Appendix J) negating the need for a specialist botanical report for the proposed Nodes (3,5,and 6) placed in natural veld areas.

A NID and Screener were submitted to HWC (see Appendix J).

11. How will the development impact on people’s health and wellbeing (e.g. in

terms of noise, odours, visual character and sense of place, etc)? YES NO X Please explain

There will be no negative health impacts due to the proposed activity. The positive health benefits for hikers and birders and tourists

enjoying the area will be significant. The Visual Statement (Appendix G page 21) found the Resort development is compatible with scenic

areas and viniculture, and due to the good screening and VAC the visual impacts are expected to be low if mitigation is applied.

12. Will the proposed activity or the land use associated with the activity applied

for, result in unacceptable opportunity costs? YES NO X Please explain

13. What will the cumulative impacts (positive and negative) of the proposed

land use associated with the activity applied for, be? YES NO Please explain

Positive: Creation of job opportunities and increased tourism to the area with a knock-on effect on other tourism activities in the area.

Negative: The proposed removal of approximately 936.25m2 indigenous vegetation for establishment of the facilities associated with the

project. Decrease in natural water resources due to increased use on site. Increased waste (solid and sewage) from the site and resultant use of storage and treatment facilities in the Worcester area.

14. Is the development the best practicable environmental option for this

land/site? YES X NO Please explain

The Slanghoek Mountain Resort already exists, and will remain part of the Badsberg Conservancy after implementation of the project.

15. What will the benefits be to society in general and to the local communities? Please explain

Temporary construction and permanent operational job opportunities will be created for the local community. Society will benefit from the

availability of the facility in the area from which to enjoy the agri-tourism and eco-tourism opportunities. The Social Status Quo report as part of the SEA conducted for the area in 2014 highlighted the need to address seasonal unemployment with year long employment opportunities and in light of the economic challenges with regards to conventional crops, alternative economic / agricultural ventures

should be considered. Job creation, especially for female employees, should be one of the priorities taken into consideration when alternatives are investigated.

16. Any other need and desirability considerations related to the proposed activity? Please explain

No.

19

The aim of these principles is to guide stakeholders in order to ensure a holistic evaluation is achieved, with the precautionary principle used as a focus in order to encourage development which is sustainable and which retains the sense of place as far as possible whilst

exploring feasible and reasonable alternatives to achieve such objectives. It is anticipated that no cultural / heritage aspects will be disturbed as a result of the proposed development. Furthermore a cautious approach will be used during all stages of the development with the best possible environmental option being explored. The Environmental Management Plan (EMP) for Operation will guide an eco

oriented approach. The Slanghoek Mountain Resort is an existing tourism facility with existing impacts. The potential impacts from the proposed expansion were considered and mitigation measures were proposed. The aim of the project is to create an expansion to an already existing and successful tourism facility, working with the natural resources of the area (mountainous view, available water

resource, sun energy) and minimising the potential impacts associated with the expansion project.

SECTION E: ALTERNATIVES

Please Note: Before completing this section, first consult this Department’s Guideline on Alternatives (August 2010) available on

the Department’s website (http://www.capegateway.gov.za/eadp).

“Alternatives”, in relation to a proposed activity, means different means of meeting the general purposes and requirements of

the activity, which may include alternatives to –

(a) the property on which, or location where, it is proposed to undertake the activity;

(b) the type of activity to be undertaken;

I the design or layout of the activity;

(d) the technology to be used in the activity;

(e) the operational aspects of the activity; and

(f) the option of not implementing the activity.

The NEMA prescribes that the procedures for the investigation, assessment and communication of the potential consequences

or impacts of activities on the environment must, inter alia, with respect to every application for environmental authorisation –

ensure that the general objectives of integrated environmental management laid down in NEMA and the National

Environmental Management Principles set out in NEMA are taken into account; and

include an investigation of the potential consequences or impacts of the alternatives to the activity on the environment

and assessment of the significance of those potential consequences or impacts, including the option of not implementing

the activity.

The general objective of integrated environmental management is, inter alia, to “identify, predict and evaluate the actual and

potential impact on the environment, socio-economic conditions and cultural heritage, the risks and consequences and

alternatives and options for mitigation of activities, with a view to minimising negative impacts, maximising benefits, and

promoting compliance with the principles of environmental management” set out in NEMA.

1. In the sections below, please provide a description of any indentified and considered alternatives and alternatives that

were found to be feasible and reasonable.

Please note: Detailed written proof the investigation of alternatives must be provided and motivation if no reasonable

or feasible alternatives exist.

(a) Property and location/site alternatives to avoid negative impacts, mitigate unavoidable negative impacts and maximise

positive impacts, or detailed motivation if no reasonable or feasible alternatives exist:

No property alternative has been put forward as this is an expansion of an existing resort. The site also has topographical, geological and agricultural constraints within which the optimal layout for the nodes was developed.

(b) Activity alternatives to avoid negative impacts, mitigate unavoidable negative impacts and maximise positive impacts, or

detailed motivation if no reasonable or feasible alternatives exist:

20

In terms of the overall project proposal the following alternatives apply: Alternative 1 (Preferred Alternative)

The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No

new footprint. Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m

2 per

unit. Placed on agricultural land.

Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 6: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 7 units is 936.25m2.

Potable water supply will be from Existing Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to

be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used. Alternative 2

The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No

new footprint. Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m

2 per

unit. Placed on agricultural land.

Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each,

single storey. One parking bay of 13.75m2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 6: 5 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 9 units is 1 176.25m2.

Potable water supply will be from Existing Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to

be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used. Alternative 3 (no-go)

Existing Resort will continue without expansion. Upgrade of Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tents in the existing resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

No new roads constructed for access and no removal if indigenous vegetation. Potable water supply will be from Existing Lawful Use registered for the resort.

(c) Design or layout alternatives to avoid negative impacts, mitigate unavoidable negative impacts and maximise positive

impacts, or detailed motivation if no reasonable or feasible alternatives exist:

Alternative 2 was the first design considered, with 5 units in Node 6. After the site verification by CapeNature (see Appendix J) the units were decreased to decrease the impact on the vegetation of the site, giving rise to the Preferred Alternative (Appendix B). Due to

topographical, geological and agricultural constraints, the other nodes were placed in their optimal position. Alternative 2 requires the removal of 1 176.25m

2 of indigenous vegetation and Alternative 1 requires the removal of 936.25m

2.

(d) Technology alternatives (e.g. to reduce resource demand and resource use efficiency) to avoid negative impacts, mitigate

unavoidable negative impacts and maximise positive impacts, or detailed motivation if no reasonable or feasible alternatives

exist:

Currently the facility is only on ESKOM power, but there will be continuous effort to move towards more sustainable alternative energy sources:

All hot water will be supplied via solar-heated geysers with electrical back-up for these during the winter months to ensure there is still hot water. The electrical back-ups will be on geyser timers;

the use of low energy bulbs throughout the resort.

(e) Operational alternatives to avoid negative impacts, mitigate unavoidable negative impacts and maximise positive impacts,

or detailed motivation if no reasonable or feasible alternatives exist:

Grey water from the units will be routed to the gardens for irrigation. An Environmental Management Plan for Operation has been created for the proposed development (Appendix H). This plan will guide

operational activities in order to use resources efficiently, as well as guide eco sensitive activities during operation.

(f) the option of not implementing the activity (the No-Go Option):

21

Should the expansion of the Slanghoek Mountain Resort not be granted:

Upgrade of Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tents in the existing resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

No new roads constructed for access and no removal if indigenous vegetation.

Potable water supply will be from Existing Lawful Use registered for the resort.

(g) Other alternatives to avoid negative impacts, mitigate unavoidable negative impacts and maximise positive impacts, or

detailed motivation if no reasonable or feasible alternatives exist:

No new roads will be developed to gain access to the nodes for development, thus decreasing the need for additional natural vegetation removal. An Environmental Management Plan (EMP) for Construction and Operational phases (Appendix H) have been developed specifically for

the proposed activity. These EMP’s will ensure that all sensitive areas are well demarcated and that construction and operational activities are guided in order to achieve a low impact approach.

(h) Please provide a summary of the alternatives investigated and the outcomes of such investigation: In terms of the overall project proposal the following alternatives apply: Alternative 1 (Preferred Alternative)

The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No

new footprint. Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m

2 per

unit. Placed on agricultural land.

Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single

storey. One parking bay of 13.75m2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 6: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 7 units is 936.25m2.

Potable water supply will be from Existing Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to

be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used. Alternative 2

The proposal relates to the upgrade of the existing resort Node 1 and the development of 5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tented units to cottages within the existing resort. No

new footprint. Node 2: 26 footprints of 120 m², single storey each for farm holiday accommodation purposes. One parking bay of 13.75m

2 per

unit. Placed on agricultural land.

Node 3: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 4: 3 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single

storey. One parking bay of 13.75m2 per unit. Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Node 6: 5 footprints for cottages to be used for farm holiday accommodation purposes, maximum footprint of 120 m² each, single storey. One parking bay of 13.75m

2 per unit. Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 9 units is 1 176.25m2.

Potable water supply will be from Existing Lawful Use registered for the resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed. Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water from units to

be used for garden irrigation. No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used. Alternative 3 (no-go)

Existing Resort will continue without expansion. Upgrade of Node 1: Existing tourist facilities will remain with possible upgrade of the 13 tents in the existing resort. Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

No new roads constructed for access and no removal if indigenous vegetation. Potable water supply will be from Existing Lawful Use registered for the resort.

Please note: If no feasible and reasonable alternatives exist, the description and proof of the investigation of alternatives,

together with motivation of why no feasible or reasonable alternatives exist, must be provided.

22

SECTION F: IMPACT ASSESSMENT, MANAGEMENT,

MITIGATION AND MONITORING MEASURES

Please note: The information in this section must be duplicated for all the feasible and reasonable alternatives (where relevant).

1. PLEASE DESCRIBE THE MANNER IN WHICH THE DEVELOPMENT WILL IMPACT ON THE FOLLOWING

ASPECTS:

(a) Geographical and physical aspects:

Alternative 1 (Preferred) Alternative 2 Alternative 3 (no go)

The proposal relates to the upgrade of the existing resort Node 1 and the development of

5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible

upgrade of the 13 tented units to cottages within the

existing resort. No new footprint.

Node 2: 26 footprints

of 120 m², single storey each for farm holiday

accommodation purposes. One parking bay of 13.75m

2 per

unit. Placed on agricultural land.

Node 3: 2 footprints

for cottages to be used for farm holiday accommodation

purposes, maximum footprint of 120 m² each, single storey.

One parking bay of 13.75m

2 per unit.

Placed on natural

veldt. Node 4: 3 footprints

for cottages to be

used for farm holiday accommodation purposes, maximum

footprint of 120 m² each, single storey. One parking bay of

13.75m2 per unit.

Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday

accommodation purposes, maximum footprint of 120 m²

each, single storey. One parking bay of 13.75m

2 per unit.

Placed on natural veldt.

Node 6: 3 footprints for

cottages to be used for farm holiday accommodation purposes, maximum

footprint of 120 m² each, single storey. One parking bay of

13.75m2 per unit.

The proposal relates to the upgrade of the existing resort Node 1 and the development of

5 new resort nodes (refer SDP Appendix B). The nodes consist of:

Node 1: Existing tourist facilities will remain with possible

upgrade of the 13 tented units to cottages within the

existing resort. No new footprint.

Node 2: 26 footprints

of 120 m², single storey each for farm holiday

accommodation purposes. One parking bay of 13.75m

2 per

unit. Placed on agricultural land.

Node 3: 2 footprints

for cottages to be used for farm holiday accommodation

purposes, maximum footprint of 120 m² each, single storey.

One parking bay of 13.75m

2 per unit.

Placed on natural

veldt. Node 4: 3 footprints

for cottages to be

used for farm holiday accommodation purposes, maximum

footprint of 120 m² each, single storey. One parking bay of

13.75m2 per unit.

Placed on agricultural land.

Node 5: 2 footprints for cottages to be used for farm holiday

accommodation purposes, maximum footprint of 120 m²

each, single storey. One parking bay of 13.75m

2 per unit.

Placed on natural veldt.

Node 6: 5 footprints for

cottages to be used for farm holiday accommodation purposes, maximum

footprint of 120 m² each, single storey. One parking bay of

13.75m2 per unit.

Existing Resort will continue without expansion. Upgrade of Node 1: Existing

tourist facilities will remain with possible upgrade of the 13 tents in the existing resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be

installed. No new roads constructed for access and no removal if

indigenous vegetation. Potable water supply will be from Existing Lawful Use registered

for the resort.

23

Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 7 units is

936.25m2.

Potable water supply will be from Existing Lawful Use registered

for the resort. Electricity for all units to be from ESKOM direct supply with

additional solar geysers to be installed. Conservancy tanks at all new

units as with existing resort units, and service by Breede Valley Local Municipality.

Grey water from units to be used for garden irrigation. No new roads will be

constructed as existing farm roads and jeep tracks will be upgraded and used.

Placed on natural veldt.

Total estimated natural vegetation to be removed for placement of 9 units is 1

176.25m2.

Potable water supply will be from Existing Lawful Use registered

for the resort. Electricity for all units to be from ESKOM direct supply with

additional solar geysers to be installed. Conservancy tanks at all new

units as with existing resort units, and service by Breede Valley Local Municipality.

Grey water from units to be used for garden irrigation. No new roads will be

constructed as existing farm roads and jeep tracks will be upgraded and used.

(b) Biological aspects:

Will the development have an impact on critical biodiversity areas (CBAs) or ecological support areas

(CSAs)? YES NO

If yes, please describe: There are no CBA’s mapped for any of the development nodes. The ESA mapped (Appendix D) is in an existing

agricultural area.

Will the development have impact on terrestrial vegetation, or aquatic ecosystems (wetlands, estuaries or

the coastline)? YES NO

If yes, please describe:

Will the development have an impact on any populations of threatened plant or animal species, and/or on

any habitat that may contain a unique signature of plant or animal species? YES NO

If yes, please describe: The site was verified by CapeNature (see communication in Appendix J).

Please describe the manner in which any other biological aspects will be impacted:

No other impacts foreseen. Node 4 units within 32m of the drainage line, but placed on land already used for agriculture.

(c) Socio-Economic aspects:

What is the expected capital value of the activity on completion? ±R45M

What is the expected yearly income or contribution to the economy that will be generated by or as a result

of the activity?

± R15M

Will the activity contribute to service infrastructure? YES NO

How many new employment opportunities will be created in the construction phase of the activity? ±30

What is the expected value of the employment opportunities during the construction phase? R120 000 per month

What percentage of this will accrue to previously disadvantaged individuals? 90%

How will this be ensured and monitored (please explain):

The developer will adopt a preferred tender system and will also work with locally known builders who qualify as previously

disadvantaged. The developer will preferably use contractors from the local community.

How many permanent new employment opportunities will be created during the operational phase of the

activity?

± 20

What is the expected current value of the employment opportunities during the first 10 years? ± R8.5M

What percentage of this will accrue to previously disadvantaged individuals? 90%

How will this be ensured and monitored (please explain):

The Owner will empower the previously disadvantaged individuals in the local farming community as the core workforce, through preferential employment.

Any other information related to the manner in which the socio-economic aspects will be impacted:

N/A

(d) Cultural and historic aspects:

No cultural or historical aspects will be impacted upon during the construction phase as per NID and screener submitted to HWC

(Appendix J)

2. WASTE AND EMISSIONS

(a) Waste (including effluent) management

Will the activity produce waste (including rubble) during the construction phase? YES X NO

24

If yes, indicate the types of waste (actual type of waste, e.g. oil, and whether hazardous or not) and

estimated quantity per type?

At this stage the actual quantity that

will be produced during the construction

phase, cannot be estimated. However, due to

building methods and limited cement works, building

waste can be reduced.

Will the activity produce waste during its operational phase? YES X NO

If yes, indicate the types of waste (actual type of waste, e.g. oil, and whether hazardous or not) and

estimated quantity per type?

1) The units will produce domestic

waste – estimated 1 bag per unit per week. 2) Recycled

waste – estimated 1 bag per unit per week. 3)

Composting in place on site. 4) Sewage to be

taken to Worcester WWTP – estimated additional 40 500l

to WWTP per annum from the three additional

conservancy tanks (one 10 000l tank, one 2000l tank and

one 1500l tank).

Where and how will the waste be treated / disposed of (describe)? Disposed of to municipal landfill site in Worcester (see also letter

in Appendix E).

If yes, indicate the types of waste (actual type of waste, e.g. oil, and whether hazardous or not) and estimated quantity per

type per phase of the development? The proposed additional 36 units will generate 2 bags of solid waste per month and 2 bags of recyclables per month each (thus 72 bags

solid waste and 72 bags recyclables). Composting implemented on site.

Has the municipality or relevant authority confirmed that sufficient capacity exist for treating / disposing of

the waste to be generated by this activity(ies)? If yes, provide written confirmation from Municipality or

relevant authority.

YES NO

Will the activity produce waste that will be treated and/or disposed of at another facility other than into a

municipal waste stream? YES NO

If yes, has this facility confirmed that sufficient capacity exist for treating / disposing of the waste to be

generated by this activity(ies)? Provide written confirmation from the facility and provide the following

particulars of the facility: N/A

YES NO

Does the facility have an operating license? (If yes, please attach a copy of the license.) YES NO

Facility name: N/A

Contact person: N/A

Postal address: N/A

Postal code: N/A

Telephone: N/A Cell: N/A

E-mail: N/A Fax: N/A

Describe the measures that will be taken to reduce, reuse or recycle waste:

Recycling on site will be encouraged and implemented in all units. Recyclables will be taken to landfill site Worcester for processing. An Environmental Management Plan (EMP) has been drafted for both the Construction and Operational Phases.

These plans will guide activities in order to encourage reduction, reuse or recycling. Dual flush toilets and low flow shower heads will be put in place for new units.

(b) Emissions into the atmosphere

Will the activity produce emissions that will be disposed of into the atmosphere? YES NO

If yes, does it require approval in terms of relevant legislation? YES NO

Describe the emissions in terms of type and concentration and how it will be treated/mitigated: N/A

3. WATER USE

25

Please indicate the source(s) of water for the activity by ticking the appropriate box(es)

Municipal Water board Groundwater River, Stream,

Dam or Lake Other The activity will not use water

If water is to be extracted from a groundwater source, river, stream, dam, lake or any other natural feature, please indicate

the volume that will be extracted per month: 600m3

Please provide proof of assurance of water supply (eg. Letter of confirmation from municipality / water user associations, yield

of borehole) See Appendix E for ELU confirmation

Does the activity require a water use permit / license from DWAF? YES NO

If yes, please submit the necessary application to Department of Water Affairs and attach proof thereof to this application. Permissible Existing Lawful Use use is applicable to the site. See BGCMA communication Appendix E.

Describe the measures that will be taken to reduce water demand, and measures to reuse or recycle water:

Water tanks for the grey water from the units will reroute this grey water to the gardens for irrigation;

Washbasin and shower taps to be fitted with flow reduction devices;

Toilets should be fitted with reduce flow or preferably a duel flush system;

All hoses on site to be fitted with trigger gun spray nozzles to limit wastage;

Preference should be given to planting only endemic/indigenous gardens and using such for landscaping to minimise water

demand;

Timed irrigation systems with the focus on the hours when the least evaporation occurs;

Irrigation systems to be fitted with a rain sensor to prevent excessive use of water;

Water meter to be installed on retention tanks prior to distribution to units;

Only plants adapted to the local climate used in landscaping to reduce the need for excessive watering;

Irrigation during the evenings and not during daylight hours;

Taps around the property fitted with locks to prevent unauthorised use and included on a maintenance schedule to detect and

repair leaks;

High pressure hoses used wherever possible to reduce water consumption;

Physical brushing or sweeping used in preference to water cleansing wherever possible (e.g. cleaning pathways).

4. POWER SUPPLY

Please indicate the source of power supply eg. Municipality / Eskom / Renewable energy source

Eskom

If power supply is not available, where will power be sourced from?

Solar geysers and panels. Gas geysers also in use already.

5. ENERGY EFFICIENCY

Describe the design measures, if any, that have been taken to ensure that the activity is energy efficient:

Currently the facility is only on ESKOM power, but there will be continuous effort to move towards more sustainable alternati ve energy

sources:

All hot water will be supplied via solar-heated geysers with electrical back-up for these during the winter months to ensure there

is still hot water. The electrical back-ups will be on geyser timers;

Energy saving bulbs in all structures, alternatively use low voltage or compact fluorescent lights;

Natural light used wherever possible during the day in preference to artificial light

Describe how alternative energy sources have been taken into account or been built into the design of the activity, if any:

Alternative energy sources (gas, solar, etc) will be used where possible. Eskom electricity will still be the main supply.

6. DESCRIPTION AND ASSESSMENT OF THE SIGNIFICANCE OF IMPACTS PRIOR TO AND AFTER

MITIGATION

Please note: While sections are provided for impacts on certain aspects of the environment and certain impacts,

the sections should also be copied and completed for all other impacts.

(a) Impacts that may result from the planning, design and construction phase (briefly describe and compare the potential

impacts (as appropriate), significance rating of impacts, proposed mitigation and significance rating of impacts after

mitigation that are likely to occur as a result of the planning, design and construction phase.

Potential impacts on

geographical and

physical aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact: The construction of 36 new units and upgrade of

The construction of 38 new units and upgrade of

Upgrade of Node 1 only - Existing tourist facilities

26

13 existing tented units in the existing resort.

Each unit to be 120m2

with a 13.75m2 parking

area.

Total estimated natural vegetation to be removed for placement of 7 units

is 936.25m2.

No new roads will be constructed as existing

farm roads and jeep tracks will be upgraded and used.

Construction waste.

13 existing tented units in the existing resort.

Each unit to be 120m2

with a 13.75m2 parking

area.

Total estimated natural vegetation to be removed for placement of 9 units

is 1176.25m2.

No new roads will be constructed as existing

farm roads and jeep tracks will be upgraded and used.

Construction waste.

will remain with possible upgrade of the 13 tents

in the existing resort. No new roads constructed for access

and no removal of indigenous vegetation. Construction waste.

Extent and duration of

impact: Local: short term. Local: short term. Local: short term.

Probability of

occurrence: Definite. Definite. Definite

Degree to which the

impact can be

reversed:

Possible. Possible. Possible

Degree to which the

impact may cause

irreplaceable loss of

resources:

Likely Likely Likely

Cumulative impact

prior to mitigation:

Waste will be produced by activity.

Increased risk of erosion from removal of vegetation.

Seven units to be built in natural veldt area, thus loss of natural resource.

Waste will be produced by activity.

Increased risk of erosion from removal of vegetation.

Nine units to be built in natural veldt area, thus loss of natural resource.

Existing 13 tented units

upgraded and use of resources associated with it. Waste will be

produced by activity.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium. Medium Low

Degree to which the

impact can be

mitigated:

Low Low Low

Proposed mitigation:

Minimise area required for establishment. Minimise usage of

natural resources and production of waste.

Minimise area required for establishment. Minimise usage of

natural resources and production of waste.

Minimise usage of natural resources and

production of waste.

Cumulative impact

post mitigation:

Decrease of indigenous

vegetation on site. Decrease in available water resources

downstream. Impact on municipal landfill site and WWTP

due to increased waste stream.

Decrease of indigenous

vegetation on site. Decrease in available water resources

downstream. Impact on municipal landfill site and WWTP

due to increased waste stream

Decrease in available water resources

downstream. Impact on municipal landfill site due to

increased waste stream

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium - Low. Medium - Low. Low

Potential impact on

biological aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3 (no go)

Nature of impact:

Waste, normally associated with

construction (cement bags, etc.) may end up in the landscape.

Vegetation outside of the identified construction areas may be impacted

Waste may end up in the landscape. Vegetation

outside of the identified activity areas may be impacted on.

It will be required to remove 300m

2

indigenous vegetation for

Waste, normally

associated with construction (cement bags, etc.) may end up in

the landscape.

27

on by construction activities. Total estimated

natural vegetation to be removed for placement of 7 units is 936.25m

2.

the vegetable garden. Total estimated natural

vegetation to be removed for placement of 9 units is 1176.25m

2.

Extent and duration of

impact: Local: short term. Local: short term. Local: short term.

Probability of

occurrence:

With the strict implementation of the

EMP’s it is unlikely that construction waste will end up in the

surrounding environment. If the construction sites are

properly fenced off as recommended within the construction EMP, no

vegetation near the construction sites will be impacted on. The

removal of indigenous vegetation for establishment of the activity is unavoidable.

With the strict implementation of the

EMP’s it is unlikely that construction waste will end up in the

surrounding environment. If the construction sites are

properly fenced off as recommended within the construction EMP, no

vegetation near the construction sites will be impacted on. The

removal of indigenous vegetation for establishment of the activity is unavoidable.

Strict implementation of waste handling procedures on site

should prevent waste from reaching the surrounding

environment.

Degree to which the

impact can be

reversed:

Low Low. Low

Degree to which the

impact may cause

irreplaceable loss of

resources:

Probable. Probable. Improbable.

Cumulative impact

prior to mitigation:

Loss of indigenous vegetation localised to

unit footprint areas. If proper construction and erosion controls are not

adopted, erosion can become a problem, resulting in further

vegetation loss.

Loss of indigenous vegetation localised to

unit footprint areas.

Windblown waste and degradation of

surrounding environment

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium Low Low

Degree to which the

impact can be

mitigated:

Possible Possible. Possible

Proposed mitigation:

Only clear vegetation as

required and leave no open areas until construction required, in

order to minimise chance of erosion. Institute no-go areas.

Ongoing alien vegetation management.

Only clear vegetation as

required and leave no open areas until construction required, in

order to minimise chance of erosion. Institute no-go areas.

Ongoing alien vegetation management.

Strict implementation of waste handling procedures on site

should prevent waste from reaching the surrounding

environment.

Cumulative impact

post mitigation:

Minimum erosion and

further vegetation loss as areas are cleared of vegetation.

Minimum erosion and

further vegetation loss as areas are cleared of vegetation.

No impact foreseen

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium to Low Medium to Low Low

Potential impacts on

socio-economic

aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

Positive:The construction of the project facility will result in approximately

30 temporary

Positive:The construction of the project facility will result in approximately

30 temporary

Positive:The construction of the project facility will result in approximately 8

temporary employment

28

employment opportunities.

employment opportunities.

opportunities

Extent and duration of

impact: Local: short term. Local: short term. Local: short term.

Probability of

occurrence: High. High. High.

Degree to which the

impact can be

reversed:

Possible. Possible. Possible.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Likely. Likely. Likely.

Cumulative impact

prior to mitigation:

Job creation during the construction phase as well as the possibility of

skills transfer.

Job creation during the construction phase as well as the possibility of

skills transfer.

Job creation during the construction phase as well as the possibility of

skills transfer.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium (positive) Low (positive) Low (positive)

Degree to which the

impact can be

mitigated:

Mitigation not required. Mitigation not required. Mitigation not required.

Proposed mitigation: Not required. Not required. Not required.

Cumulative impact

post mitigation:

Small scale job creation and transfer of skills.

Knock-on effect on local small scale economy.

Small scale job creation and transfer of skills.

Knock-on effect on local small scale economy.

Small scale job creation and transfer of skills.

Knock-on effect on local small scale economy.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium (positive) Medium (positive) Medium (positive)

Potential noise

impacts: Alternative 1

Alternative 2

Alternative 3

(no go)

Nature of impact:

Noise may occur during the construction of the project.

Noise may occur during the construction of the project.

Noise may occur during the construction of the project.

Extent and duration of

impact: Local: short term. Local: short term. Local: short term.

Probability of

occurrence: Definite. Definite. Definite.

Degree to which the

impact can be

reversed:

Low

Low Low

Degree to which the

impact may cause

irreplaceable loss of

resources:

Not likely. Not likely. Not likely.

Cumulative impact

prior to mitigation:

Noise typical of a small

construction site.

Noise typical of a small

construction site.

Noise typical of a small

construction site.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

Degree to which the

impact can be

mitigated:

Possible. Possible. Possible.

Proposed mitigation:

Ensure normal working hours are adhered to. Ensure that all noisy machinery is fitted with

silencers. Ensure all noise levels adhere to predetermined

standards.

Ensure normal working hours are adhered to. Ensure that all noisy machinery is fitted with

silencers. Ensure all noise levels adhere to predetermined

standards.

Ensure normal working hours are adhered to. Ensure that all noisy machinery is fitted with

silencers. Ensure all noise levels adhere to predetermined

standards.

29

Cumulative impact

post mitigation:

Typical noise impact associated with a

construction phase, with possible methods to limit and reduce these

impacts taken.

Typical noise impact associated with a

construction phase, with possible methods to limit and reduce these

impacts taken.

Typical noise impact associated with a

construction phase, with possible methods to limit and reduce these

impacts taken.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

Potential visual

impacts:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

The expansion in Node 2 will be visible. The units in Node 5 & 6 will not be

visible if not located on the ridgeline.

The expansion in Node 2 will be visible. The units in Node 5 & 6 will not be

visible if not located on the ridgeline.

Existing 13 tented units

construction visible

Extent and duration of

impact: Local: short term. Local: long term. Local: long term.

Probability of

occurrence: Probable. Probable. Probable.

Degree to which the

impact can be

reversed:

Not Possible. Not Possible.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Likely. Likely. -

Cumulative impact

prior to mitigation:

Construction site nodes 2, 5 and 6 will be visible.

Construction site nodes 2, 5 and 6 will be visible.

Existing 13 tented units not visible

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium Medium. Low

Degree to which the

impact can be

mitigated:

Low Low Low

Proposed mitigation:

Make use of natural

materials and colours to ensure that cottages blend in with their

surroundings. Nodes 5 and 6 not to be on ridgeline.

Make use of natural

materials and colours to ensure that cottages blend in with their

surroundings. Nodes 5 and 6 not to be on ridgeline.

Mitigation not needed

Cumulative impact

post mitigation:

Units in nodes 2, 5, and

6 less visible.

Units in nodes 2, 5, and

6 less visible. No impact anticipated.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low

(b) Impacts that may result from the operational phase (briefly describe and compare the potential impacts (as appropriate),

significance rating of impacts, proposed mitigation and significance rating of impacts after mitigation that are likely to

occur as a result of the operational phase.

Potential impacts on

the geographical and

physical aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

Erosion of internal roads may take place should it not be regularly

maintained and proper erosion control measures are not in place.

Erosion of internal roads may take place should it not be regularly

maintained and proper erosion control measures are not in place.

No internal roads with

possible erosion

Extent and duration of

impact: Local: long term. Local: long term. No impact anticipated

Probability of

occurrence: Possible. Possible. -

30

Degree to which the

impact can be

reversed:

Low. Low. -

Degree to which the

impact may cause

irreplaceable loss of

resources:

Low. Low. -

Cumulative impact

prior to mitigation:

Erosion of internal roads

may take place should it not be regularly maintained and proper

erosion control measures are not in place.

Erosion of internal roads

may take place should it not be regularly maintained and proper

erosion control measures are not in place.

No internal roads with possible erosion

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low Low No impact anticipated

Degree to which the

impact can be

mitigated:

Possible. Possible. -

Proposed mitigation: Ongoing maintenance of

existing roads.

Ongoing maintenance of

existing roads. No mitigation required

Cumulative impact

post mitigation:

Possible erosion of existing roads

Possible erosion of existing roads

-

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low

Potential impact

biological aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

Tourists may have an impact on the following:

Vegetation (fires,

unauthorised removal of vegetation, introduction of alien

vegetation);

Animals.

Tourists may have an impact on the following:

Vegetation (fires,

unauthorised removal of vegetation, introduction of alien

vegetation);

Animals.

Tourists may have an impact on the following:

Vegetation (fires,

unauthorised removal of vegetation, introduction of alien

vegetation);

Animals.

Extent and duration of

impact: Local: long term. Local: long term. Local: long term.

Probability of

occurrence: Possible. Possible. Possible

Degree to which the

impact can be

reversed:

Low to medium.

Low to medium.

Low to medium.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Medium. Medium. Medium.

Cumulative impact

prior to mitigation:

Users of the units may have a negative impact on fauna and flora.

Users of the units may have a negative impact on fauna and flora.

Users of the units may have a negative impact on fauna and flora.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium. Medium. Medium.

Degree to which the

impact can be

mitigated:

Possible. Possible. Possible.

Proposed mitigation: Strict implementation of operational EMP’s.

Strict implementation of operational EMP’s.

Strict implementation of operational EMP’s.

Cumulative impact

post mitigation:

Possible negative impact of users on fauna and flora.

Possible negative impact of users on fauna and flora.

Possible negative impact of users on fauna and flora.

Significance rating of

impact after mitigation

(Low, Medium,

Low-medium. Low-medium. Low-medium.

31

Medium-High, High, or

Very-High)

Potential impacts on

the socio-economic

aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

Positive: job creation. Positive: skills development. Twenty

permanent employment positions created.

Positive: job creation. Positive: skills

development. Twenty

permanent employment positions created.

Positive: job creation.

Positive: skills development. Only 2

permanent employment

opportunities will be generated from this.

Extent and duration of

impact: Local: long term. Local: long term. Local: long term.

Probability of

occurrence: Possible. Possible. Probable.

Degree to which the

impact can be

reversed:

Possible. Possible. Possible.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Unlikely. Unlikely. Unlikely.

Cumulative impact

prior to mitigation:

Job creation and skills

development.

Job creation and skills development.

Job creation and skills development.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low to medium. Low to medium. Low to medium.

Degree to which the

impact can be

mitigated:

Possible. Possible. Possible.

Proposed mitigation: Not required. Not required. Not required.

Cumulative impact

post mitigation:

Small scale job creation and skills development.

Small scale job creation and skills development.

Small scale job creation and skills development.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low positive Low positive Low positive

Potential impacts on

the cultural-historical

aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact: No impact anticipated

(see NID in Appendix J)

No impact anticipated

(see NID in Appendix J)

No impact anticipated

(see NID in Appendix J)

Extent and duration of

impact: -

- -

Probability of

occurrence: -

- -

Degree to which the

impact can be

reversed:

-

- -

Degree to which the

impact may cause

irreplaceable loss of

resources:

-

- -

Cumulative impact

prior to mitigation: -

- -

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

-

- -

Degree to which the

impact can be

mitigated:

-

- -

Proposed mitigation: - - -

Cumulative impact - - -

32

post mitigation:

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

-

- -

Potential noise

impacts:

Alternative 1

(Preferred) Alternative 2

Alternative 3

(no go)

Nature of impact: Noise created due to occupancy of units.

Noise created due to occupancy of units.

Noise created due to occupancy of units.

Extent and duration of

impact: Local: long term. Local: long term. Local: long term.

Probability of

occurrence: Possible. Possible. Possible.

Degree to which the

impact can be

reversed:

Medium. Medium. Medium.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Unlikely. Unlikely. Unlikely.

Cumulative impact

prior to mitigation:

Potential noise impact due to occupancy of cottages.

Potential noise impact due to occupancy of cottages.

Potential noise impact due to occupancy of cottages.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium. Medium. Medium.

Degree to which the

impact can be

mitigated:

Medium. Medium. Medium

Proposed mitigation:

Strict regulation with regard to noise created

(no loud music, etc.).

Strict regulation with regard to noise created

(no loud music, etc.).

Strict regulation with regard to noise created

(no loud music, etc.).

Cumulative impact

post mitigation:

Potential noise impact due to occupancy of

cottages.

Potential noise impact due to occupancy of

cottages.

Potential noise impact due to occupancy of

cottages.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

Potential visual

impacts:

Alternative 1

(Preferred) Alternative 2

Alternative 3

(no go)

Nature of impact:

The units in Node 2 will be visible. The units in

Node 5 & 6 will not be visible if not located on the ridgeline, and with

use of natural colours the visibility is greatly reduced.

The units in Node 2 will be visible. The units in

Node 5 & 6 will not be visible if not located on the ridgeline, and with

use of natural colours the visibility is greatly reduced

Existing 13 tented units not visible outside of resort due to trees

screening.

Extent and duration of

impact: Local: long term. Local: long term. Local: long term.

Probability of

occurrence: Probable. Probable. Probable.

Degree to which the

impact can be

reversed:

Medium. Medium. Low

Degree to which the

impact may cause

irreplaceable loss of

resources:

Low Low Low

Cumulative impact

prior to mitigation:

Units visible in nodes 2, 5 and 6.

Units visible in nodes 2, 5 and 6.

Existing 13 tented units not visible outside of resort due to trees

screening

Significance rating of

impact prior to Medium. Medium. Low

33

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Degree to which the

impact can be

mitigated:

Medium. Medium. Low

Proposed mitigation:

Make sure that units

blend in with natural landscape by using natural materials as well

as colours that are not distinguishable from the natural landscape.

Nodes 5 and 6 should not protrude outside ridgeline.

Low level lighting outside at cottages.

Make sure that units

blend in with natural landscape by using natural materials as well

as colours that are not distinguishable from the natural landscape.

Nodes 5 and 6 should not protrude outside ridgeline.

Low level lighting outside at cottages.

Mitigation not required.

Cumulative impact

post mitigation:

Units might still be visible.

Units might still be visible.

Existing 13 tented units

not visible outside of resort due to trees screening.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low

(c) Impacts that may result from the decommissioning and closure phase (briefly describe and compare the potential impacts

(as appropriate), significance rating of impacts, proposed mitigation and significance rating of impacts after mitigation that

are likely to occur as a result of the decommissioning and closure phase.

Potential impacts on

the geographical and

physical aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

Units are left derelict after use.

Possible erosion of roads.

Units are left derelict after use.

Possible erosion of roads.

Units are left derelict after use.

Possible erosion of roads.

Extent and duration of

impact: Local: long term. Local: long term. Local: long term.

Probability of

occurrence: Unlikely. Unlikely. Unlikely.

Degree to which the

impact can be

reversed:

Possible. Possible. Possible.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Unlikely. Unlikely. Unlikely.

Cumulative impact

prior to mitigation:

Units are left derelict after use. Possible erosion of

roads.

Units are left derelict after use. Possible erosion of

roads.

Units are left derelict after use. Possible erosion of

roads.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium. Medium. Medium

Degree to which the

impact can be

mitigated:

Possible. Possible. Possible

Proposed mitigation:

Deconstruct buildings

should operations close down.

Ongoing maintenance of road surface.

Deconstruct buildings

should operations close down.

Ongoing maintenance of road surface.

Deconstruct buildings

should operations close down.

Ongoing maintenance of road surface.

Cumulative impact

post mitigation:

Ongoing maintenance

and monitoring to ensure that no erosion takes place.

Ongoing maintenance

and monitoring to ensure that no erosion takes place.

Ongoing maintenance

and monitoring to ensure that no erosion takes place.

34

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low

Potential impact

biological aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact: No impact anticipated. No impact anticipated. No impact anticipated.

Extent and duration of

impact:

- - -

Probability of

occurrence:

- - -

Degree to which the

impact can be

reversed:

- - -

Degree to which the

impact may cause

irreplaceable loss of

resources:

- - -

Cumulative impact

prior to mitigation:

- - -

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

- - -

Degree to which the

impact can be

mitigated:

- - -

Proposed mitigation: - - -

Cumulative impact

post mitigation:

- - -

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

- - -

Potential impacts on

the socio-economic

aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

The loss of jobs will occur- 20 permanent positions.

The loss of jobs will occur- 20 permanent positions.

The loss of jobs will occur- 2 permanent positions.

Extent and duration of

impact:

Local: medium to long

term.

Local: medium to long term.

Local: medium to long term.

Probability of

occurrence: Possible.

Possible. Possible.

Degree to which the

impact can be

reversed:

Possible. Possible. Possible.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Unlikely. Unlikely. Unlikely.

Cumulative impact

prior to mitigation: Job loss. Job loss. Job loss.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Medium to low. Medium to low. Medium to low.

Degree to which the

impact can be

mitigated:

Possible. Possible. Possible.

Proposed mitigation: Ensure job security of former employees.

Ensure job security of former employees.

Ensure job security of former employees.

Cumulative impact

post mitigation: Temporary job loss. Temporary job loss. Temporary job loss.

35

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

Potential impacts on

the cultural-historical

aspects:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact: No impact anticipated. No impact anticipated. No impact anticipated.

Extent and duration of

impact: -

- -

Probability of

occurrence: -

- -

Degree to which the

impact can be

reversed:

-

- -

Degree to which the

impact may cause

irreplaceable loss of

resources:

-

- -

Cumulative impact

prior to mitigation: -

- -

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

-

- -

Degree to which the

impact can be

mitigated:

-

- -

Proposed mitigation: - - -

Cumulative impact

post mitigation: -

- -

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

-

- -

Potential noise

impacts:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact:

Typical noise impacts

associated with the closure and

decommissioning of the

activity.

Typical noise impacts associated with the

closure and

decommissioning of the activity.

Typical noise impacts associated with the

closure and

decommissioning of the activity.

Extent and duration of

impact: Local: short term. Local: short term. Local: short term.

Probability of

occurrence: Not likely. Not likely. Not likely.

Degree to which the

impact can be

reversed:

Impact can be mitigated

should decommissioning take place.

Impact can be mitigated

should decommissioning take place.

Impact can be mitigated

should decommissioning take place.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Zero. Zero. Zero.

Cumulative impact

prior to mitigation:

Typical noise impacts associated with the closure and

decommissioning of the activity.

Typical noise impacts associated with the

closure and decommissioning of the activity.

Typical noise impacts associated with the

closure and decommissioning of the activity.

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

36

Degree to which the

impact can be

mitigated:

Possible, if necessary. Possible, if necessary. Possible, if necessary.

Proposed mitigation:

Implement hours for closure and possible decommissioning.

Implement hours for closure and possible decommissioning.

Implement hours for closure and possible decommissioning.

Cumulative impact

post mitigation:

Possible noise impacts associated with the closure and

decommissioning of the proposed activity.

Possible noise impacts associated with the closure and

decommissioning of the proposed activity.

Possible noise impacts associated with the closure and

decommissioning of the proposed activity.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

Potential visual

impacts:

Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact: Derelict infrastructure visible

Derelict infrastructure visible

Derelict infrastructure visible

Extent and duration of

impact:

Local: long term. Local: long term. Local: long term.

Probability of

occurrence:

Unlikely. Unlikely. Unlikely.

Degree to which the

impact can be

reversed:

Possible. Possible. Possible.

Degree to which the

impact may cause

irreplaceable loss of

resources:

Zero. Zero. Zero.

Cumulative impact

prior to mitigation:

Derelict infrastructure

visible Derelict infrastructure

visible Derelict infrastructure

visible Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

Degree to which the

impact can be

mitigated:

Possible, if necessary. Possible, if necessary. Possible, if necessary.

Proposed mitigation:

Decommissioning of dwelling units to be

completed and all infrastructure removed with rehabilitation of

footprint.

Decommissioning of dwelling units to be

completed and all infrastructure removed with rehabilitation of

footprint.

Decommissioning of dwelling units to be

completed and all infrastructure removed with rehabilitation of

footprint. Cumulative impact

post mitigation:

No impact anticipated. No impact anticipated. No impact anticipated.

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

Low. Low. Low.

(d) Any other impacts:

Potential impact: Alternative 1

(Preferred)

Alternative 2

Alternative 3

(no go)

Nature of impact: No impact anticipated. No impact anticipated. No impact anticipated.

Extent and duration of

impact: -

- -

Probability of

occurrence: -

- -

Degree to which the

impact can be

reversed:

-

- -

Degree to which the

impact may cause

irreplaceable loss of

resources:

-

- -

37

Cumulative impact

prior to mitigation: -

- -

Significance rating of

impact prior to

mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

-

- -

Degree to which the

impact can be

mitigated:

-

- -

Proposed mitigation: - - -

Cumulative impact

post mitigation: -

- -

Significance rating of

impact after mitigation

(Low, Medium,

Medium-High, High, or

Very-High)

-

- -

7. SPECIALIST INPUTS/STUDIES AND RECOMMENDATIONS

Please note: Specialist inputs/studies must be attached to this report as Appendix G. Also take into account the

Department’s Guidelines on the Involvement of Specialists in EIA Processes available on the Department’s website

(http://www.capegateway.gov.za/eadp).

Specialist inputs/studies and recommendations:

Visual Impact Statement by P Slabbert – PHS Consulting:

1) The development Nodes 2, 5 & 6 only become visible from immediately adjacent to it, by potential scenic drive road users with in

a 60m view window. These users will see the expansion in Node 2, but if charcoal roofs and earthy exterior colours are used

coupled with tree planting amongst the units the impact will be very localised for a few seconds, therefore low.

2) The 5 units in Node 5 & 6 will not be visible if not located on the ridgeline. By making use of charcoal roofs and natural exterior

colours and materials like stone these units will blend into their surroundings.

8. IMPACT SUMMARY

Please provide a summary of all the above impacts.

Alternative 1: (Preferred alternative) Should the expansion of the existing Slanghoek Mountain Resort by 36 units be granted the following will be implemented:

The construction of 36 new units and upgrade of 13 existing tented units in the existing resort.

Each unit to be 120m2 with a 13.75m

2 parking area.

Total estimated natural vegetation to be removed for placement of 7 units is 936.25m2.

Potable water supply will be from Existing Lawful Use registered for the resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water

from units to be used for garden irrigation.

No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used.

Construction phase: On Geographical impacts this alternative has a medium to low rating and on Biological aspects a medium to low rating due to

the required removal of indigenous vegetation for establishment. The socio-economic impact rating is medium positive, while Noise and Visual impact both rate low after mitigation. Operational phase: On Geographical impacts this alternative has a low rating and on Biological aspects a low to medium rating.

The socio-economic impact rating is low positive, while Noise and Visual impact both rate low after mitigation. Closure phase: On Geographical impacts this alternative has a low rating. The socio-economic impact rating is low, while Noise and Visual impact both rate low after mitigation.

Alternative 2: Should the expansion of the existing Slanghoek Mountain Resort by 38 units be granted the following will be implemented:

The construction of 38 new units and upgrade of 13 existing tented units in the existing resort.

Each unit to be 120m2 with a 13.75m

2 parking area.

Total estimated natural vegetation to be removed for placement of 9 units is 1 176.25m2.

Potable water supply will be from Existing Lawful Use registered for the resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed.

Conservancy tanks at all new units as with existing resort units, and service by Breede Valley Local Municipality. Grey water

from units to be used for garden irrigation.

No new roads will be constructed as existing farm roads and jeep tracks will be upgraded and used.

38

. Construction phase:

On Geographical impacts this alternative has a medium to low rating and on Biological aspects a medium to low rating. The socio-economic impact rating is medium positive, while Noise and Visual impact both rate low after mitigation. Operational phase: On Geographical impacts this alternative has a low rating and on Biological aspects a low to medium rating .

The socio-economic impact rating is low positive, while Noise and Visual impact both rate low after mitigation. Closure phase: On Geographical impacts this alternative has a low rating. The socio-economic impact rating is low, while Noise and Visual impact both rate low after mitigation.

Alternative 3: (No-go)

Existing Resort will continue without expansion.

Upgrade of Node 1 only - Existing tourist facilities will remain with possible upgrade of the 13 tents in the existing resort.

Electricity for all units to be from ESKOM direct supply with additional solar geysers to be installed where possible.

No new roads constructed for access and no removal of indigenous vegetation.

Potable water supply will be from Existing Lawful Use registered for the resort. Construction phase:

On Geographical impacts this alternative has a low rating and on Biological aspects a low rating. The socio-economic impact rating is medium positive, while Noise and Visual impact both rate low after mitigation. Operational phase: On Geographical impacts this alternative has a low rating and on Biological aspects a low to medium rating.

The socio-economic impact rating is low positive, while Noise and Visual impact both rate low after mitigation. Closure phase: On Geographical impacts this alternative has a low rating. The socio-economic impact rating is low, while Noise and Visual impact both rate low after mitigation.

9. OTHER MANAGEMENT, MITIGATION AND MONITORING MEASURES

(a) Over and above the mitigation measures described in Section 6 above, please indicate any additional management,

mitigation and monitoring measures.

Construction and Operational Environmental Management Plans (EMP’s) have been drafted to include additional measures for the respective phases.

(b) Describe the ability of the applicant to implement the management, mitigation and monitoring measures.

Construction and Operational Environmental Management Plans (EMP’s) have been drafted. Mitigation and monitoring measures are straight forward with easily obtainable objectives therefore the applicant is capable of achieving these management and mitigation measures.

Please note: A draft ENVIRONMENTAL MANAGEMENT PROGRAMME must be attached this report as Appendix H.

SECTION G: ASSESSMENT METHODOLOGIES AND

CRITERIA, GAPS IN KNOWLEDGE, UNDERLAYING

ASSUMPTIONS AND UNCERTAINTIES

(a) Please describe adequacy of the assessment methods used.

The Basic Assessment process is informed and conducted in an open and transparent manner. If any specialist studies are required, they

will be added to the report. From the current baseline further specialist studies are not required. The initial request for a botanical assessment was negated by CapeNature after an on-site verification visit.

(b) Please describe the assessment criteria used.

A site visit was conducted to determine the ecological significance of the site; this knowledge was then weighed up against the identified and possible impacts.

(c) Please describe the gaps in knowledge.

No gaps in knowledge currently exist at this stage; however should any be identified they will be communicated in an open and transparent manner and documented in the Basic Assessment Report (BAR) or where appropriate.

(d) Please describe the underlying assumptions.

No assumptions have been considered necessary at this stage in the process. Should any assumptions be required they will be identified appropriately.

(e) Please describe the uncertainties.

39

No uncertainties exist at this stage in the process.

SECTION H: RECOMMENDATION OF THE EAP

In my view (EAP), the information contained in this application form and the documentation attached

hereto is sufficient to make a decision in respect of the activity applied for. YES NO

If “NO”, list the aspects that should be further assessed through additional specialist input/assessment or whether this

application must be subjected to a Scoping & EIR process before a decision can be made:

If “YES”, please indicate below whether in your opinion the activity should or should not be authorised:

Activity should be authorised: YES NO

Please provide reasons for your opinion

The need for additional holiday accommodation in the area has given rise to the proposed project. Not only will the proposed Preferred Alternative 1create 36 additional units with scenic views in a rural landscape, but the project will also bring tourists into the area to spend

on other small scale industries. The permanent and temporary jobs created during the operational and construction phases of the project are in line with the need for year long employment outside of seasonal agricultural opportunities . The The Preferred Alternative provided, with the guidance of the EMP’s for construction and operation, will allow for a development that has an

overall low negative ecological impact associated with it.

If you are of the opinion that the activity should be authorised, then please provide any conditions, including mitigation

measures that should in your view be considered for inclusion in an authorisation.

Waste: - All waste generated during the construction phase to be removed. - No dumping of building rubble on the farm allowed.

- Removal of building rubble & waste to occur at least once a week - Contractor to be responsible for waste generated during the construction phase. - Domestic waste must be transferred by the owners to the nearest municipal transfer station.

- The water provided for domestic use must comply with the SANS 241: 2011 guidelines for drinking water (edition 1). Regular monitoring must be done to ensure compliance. lf the quality of the water is of such a nature that it is a threat to human health, then this Office and the Provincial Department of Health must be informed of the procedures to rectify the problem.

- No pollution of surface water or ground water resources may occur.

- Storm water management must be addressed both in terms of flooding and pollution potential. - A water meter should be installed on the distribution system.

Earthmoving/erosion:

- Avoid existing drainage channels. - Ensure that stormwater is regularly and properly channelled away from roads to avoid erosion. - Regular inspections of roads should take place to detect any signs of erosion. Should such signs be located, proper erosion

control measures should be implemented. Visual:

- Use natural materials where possible for construction.

- Use colours that complement the surrounding landscape and that blends in with the natural surroundings. - Nodes 5 and 6 should not be constructed in such a way as to be visible above the ridgeline.

Light: - All lights must be down lights limited with low voltage energy saving bulbs. - Time and motion switches are essential.

Water:

- Monitor water to ensure that no pollution is taking place.

- Install water meter - Grey water systems to be installed at units to use for irrigation of landscaping and lessen the need for potable water use.

General: - The development footprints must be clearly demarcated; all areas outside of this must be considered no go areas. - All areas outside of the development footprints that are disturbed during construction must be rehabilitated.

- A search and rescue of plant species of conservation concern must be conducted under the guidance of a specialist prior to any land clearance. Rescued material should be used on site for the rehabilitation of disturbed areas

- Any re-vegetation should use locally indigenous species.

Duration and Validity:

Environmental authorisations are usually granted for a period of three years from the date of issue. Should a longer period be

required, the applicant/EAP is requested to provide a detailed motivation on what the period of validity should be.

N/A

40

SECTION I: APPENDICES

The following appendices must be attached to this report:

Appendix

Tick the box

if Appendix

is attached

Appendix A: Locality map

Topocadastral map

Appendix B:

Site Development plan Preferred Alternative (Alternative 1)

Site Development plan Alternative 2

20m Contour map

Appendix C:

Site Photographs

Points where photographs taken

Appendix D:

CBA

Vegetation types

Catchment information

Conservation status

Appendix E:

Permit(s) / license(s) from any other organ of state including service letters

from the municipality

Confirmation re ELU from BGCMA (still outstanding)

Service letter BVM re sewage (e-mail)

Service letter BVM re solid waste (e-mail)

Eskom letter of supply (still outstanding)

Appendix F: Public participation information including copy of site advertisement and site

notice, and I&AP register

Appendix G:

Specialist Report(s):

Visual Impact Statement

Appendix H : Draft CEMP

Draft OEMP

Appendix I: Additional information related to listed waste management activities (if

applicable)

Appendix J:

Any Other (if applicable) (describe)

Copy of NID and screener submitted to HWC

Communication CapeNature re vegetation on site

SEA extract (Botanical survey) and enlarged Figure 10

Copy of water quality tests

Townplanning application

41

DECLARATIONS

THE APPLICANT

I .............................................................................., in my personal capacity thereto hereby that I:

regard the information contained in this report to be true and correct, and

am fully aware of my responsibilities in terms of the National Environmental Management Act of

1998 (“NEMA”) (Act No. 107 of 1998), the Environmental Impact Assessment Regulations (“EIA

Regulations”) in terms of NEMA (Government Notice No. R. 543 refers), and the relevant specific

environmental management Act, and that failure to comply with these requirements may

constitute an offence in terms of the environmental legislation;

appointed the environmental assessment practitioner as indicated above, which meet all the

requirements in terms of regulation 17 of GN No. R. 543, to act as the independent environmental

assessment practitioner for this application;

have provided the environmental assessment practitioner and the competent authority with

access to all information at my disposal that is relevant to the application;

will be responsible for the costs incurred in complying with the environmental legislation including

but not limited to –

o costs incurred in connection with the appointment of the environmental assessment

practitioner or any person contracted by the environmental assessment practitioner;

o costs incurred in respect of the undertaking of any process required in terms of the regulations;

o costs in respect of any fee prescribed by the Minister or MEC in respect of the regulations;

o costs in respect of specialist reviews, if the competent authority decides to recover costs; and

o the provision of security to ensure compliance with the applicable management and

mitigation measures;

am responsible for complying with the conditions that might be attached to any decision(s) issued

by the competent authority;

have the ability to implement the applicable management, mitigation and monitoring measures;

hereby indemnify, the government of the Republic, the competent authority and all its officers,

agents and employees, from any liability arising out of, inter alia, the content of any report, any

procedure or any action for which the applicant or environmental assessment practitioner is

responsible; and

am aware that a false declaration is an offence in terms of regulation 71 of GN No. R. 543.

Please Note: If acting in a representative capacity, a certified copy of the resolution or power

of attorney must be attached.

Signature of the applicant:

Name of company:

Date:

42

THE INDEPENDENT ENVIRONMENTAL ASSESSMENT PRACTITIONER (EAP)

I Amanda Fritz-Whyte, as the appointed independent environmental practitioner (“EAP”) hereby

declare that I:

act/ed as the independent EAP in this application;

regard the information contained in this report to be true and correct, and

do not have and will not have any financial interest in the undertaking of the activity, other than

remuneration for work performed in terms of the NEMA, the Environmental Impact Assessment

Regulations, 2010 and any specific environmental management Act;

have and will not have no vested interest in the proposed activity proceeding;

have disclosed, to the applicant and competent authority, any material information that have or

may have the potential to influence the decision of the competent authority or the objectivity of

any report, plan or document required in terms of the NEMA, the Environmental Impact

Assessment Regulations, 2010 and any specific environmental management Act;

am fully aware of and meet the responsibilities in terms of NEMA, the Environmental Impact

Assessment Regulations, 2010 (specifically in terms of regulation 17 of GN No. R. 543) and any

specific environmental management Act, and that failure to comply with these requirements may

constitute and result in disqualification;

have ensured that information containing all relevant facts in respect of the application was

distributed or made available to interested and affected parties and the public and that

participation by interested and affected parties was facilitated in such a manner that all

interested and affected parties were provided with a reasonable opportunity to participate and

to provide comments;

have ensured that the comments of all interested and affected parties were considered,

recorded and submitted to the competent authority in respect of the application;

have kept a register of all interested and affected parties that participated in the public

participation process;

have provided the competent authority with access to all information at my disposal regarding

the application, whether such information is favourable to the applicant or not; and

am aware that a false declaration is an offence in terms of regulation 71 of GN No. R. 543.

Note: The terms of reference must be attached.

Signature of the environmental assessment practitioner:

PHS Consulting

Name of company:

Date:

43

THE PERSON WHO COMPILED A SPECIALIST REPORT OR UNDERTOOK A SPECIALIST PROCESS

I ………………………, as the appointed specialist hereby declare that I:

act/ed as the specialist in this application due to my unequalled knowledge of the flora of the

property. I have studied the flora of the farm and surrounding area for a period of 16 months. This

has enabled me to observe the flora at all seasons on the property, not just at a limited point in

time. I have over 20 years experience as a plant taxonomist, including a PhD in the taxonomy of

the Cape Flora.

regard the information contained in this report as it relates to my specialist input/study to be true

and correct, and

have disclosed, to the applicant, EAP and competent authority, any material information that

have or may have the potential to influence the decision of the competent authority or the

objectivity of any report, plan or document required in terms of the NEMA, the Environmental

Impact Assessment Regulations, 2010 and any specific environmental management Act;

am fully aware of and meet the responsibilities in terms of NEMA, the Environmental Impact

Assessment Regulations, 2010 (specifically in terms of regulation 17 of GN No. R. 543) and any

specific environmental management Act, and that failure to comply with these requirements may

constitute and result in disqualification;

have ensured that information containing all relevant facts in respect of the specialist input/study

was distributed or made available to interested and affected parties and the public and that

participation by interested and affected parties was facilitated in such a manner that all

interested and affected parties were provided with a reasonable opportunity to participate and

to provide comments on the specialist input/study;

have ensured that the comments of all interested and affected parties on the specialist

input/study were considered, recorded and submitted to the competent authority in respect of

the application;

have ensured that the names of all interested and affected parties that participated in terms of

the specialist input/study were recorded in the register of interested and affected parties who

participated in the public participation process;

have provided the competent authority with access to all information at my disposal regarding

the application, whether such information is favourable to the applicant or not; and

am aware that a false declaration is an offence in terms of regulation 71 of GN No. R. 543.

Note: The terms of reference must be attached.

Signature of the specialist:

Name of company:

Date: