Calhoun County Road Department Culvert Replacement Project Baseline Road East of Collier Avenue, Bedford Township 1 Bidders List Balkema Excavating Inc. 1500 River St Kalamazoo, MI 49048 Concord Excavating P.O. Box 250 Concord, MI 49237 Grand River Construction Inc. 5025 40 th Ave Hudsonville, MI 49426 Hoffman Brothers 8574 Verona Road Battle Creek, MI 49014 HunterPrell 149 Richmond Ave. Battle Creek, MI 49014 J. E. Kloote Contracting Inc. 11116 Fitzgerald Suite F Nunica, MI 49448 Milbocker & Sons, Inc. 1256 29 th Street Allegan, MI 49010 Peters Construction Co. 3325 E Kilgore Rd Kalamazoo, MI 49001

Transcript of Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near...

Page 1: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

  

1  

Bidders List  

 

Balkema Excavating Inc. 1500 River St Kalamazoo, MI 49048  

Concord Excavating P.O. Box 250 Concord, MI 49237 

 

Grand River Construction Inc. 5025 40th Ave Hudsonville, MI 49426  

Hoffman Brothers 8574 Verona Road Battle Creek, MI 49014  

Hunter‐Prell   149 Richmond Ave.   Battle Creek, MI 49014 

 

J. E. Kloote Contracting Inc. 11116 Fitzgerald Suite F Nunica, MI 49448  

Milbocker & Sons, Inc. 1256 29th Street Allegan, MI 49010  

Peters Construction Co. 3325 E Kilgore Rd Kalamazoo, MI 49001   

 

  

Page 2: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

  

2  

Table of Contents 

Invitation for Bids .......................................................................................................................................... 3 

Location Map ................................................................................................................................................ 4 

General Provisions & Instructions ................................................................................................................. 5 

Scope of Work ............................................................................................................................................... 5 

Special Requirements ................................................................................................................................... 5 

Questions/Additional Information ................................................................................................................ 6 

Progress Clause ............................................................................................................................................. 7 

Project Log .................................................................................................................................................... 8 

Proposed Baseline Road Culvert Information ............................................................................................. 11 

Special Provisions ........................................................................................................................................ 12 

  Aluminum Box Culvert .......................................................................................................................... 12 

  Crushed Concrete Near Water ............................................................................................................. 14 

  Detour Route ........................................................................................................................................ 15 

  Maintaining Traffic ............................................................................................................................... 18 

  Slope Restoration, Modified ................................................................................................................. 19 

  Stream Diversion .................................................................................................................................. 20 

Notice to Bidders ........................................................................................................................................ 24 

Utility Coordination ..................................................................................................................................... 25 

Public Utilities ............................................................................................................................................. 25 

Attachment A: Bid Security Requirements & Bid Forms ............................................................................. 26 

Bid Security ........................................................................................................................................... 27 

Bid Sheet ............................................................................................................................................... 28 

Attachment B: MDEQ Permit ...................................................................................................................... 32 

 

Page 3: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

  

3 Calhoun County is an affirmative-action, equal-opportunity employer.

 

 

Calhoun County Road Department "Building A Better County Through Responsive Leadership"

  13300 15 Mile Road Marshall, MI 49068 (269) 781-9841 Voice (800) 781-5512 Toll Free (269) 781-6101 Fax 

Christopher J. Bolt, MPA, PE Managing Director

[email protected] www.calhouncountyroads.com 

 

Invitation for Bids 

Culvert Replacement for Baseline Road East of Collier Avenue, Section 16, Bedford Township 

 Sealed  bids  will  be  received  by  the  Calhoun  County  Road  Department  at  their  offices  on 13300 15 Mile Road, Marshall, MI 49068 until 12:00 PM EST on Monday, May 22nd, 2017  for the removal and replacement of a culvert on Baseline Road east of Collier Avenue, T1S, R8W, Section 04, Bedford Charter Township.  This culvert is located in Calhoun County, Michigan.  All bids must be in sealed envelopes marked:  

Baseline Road East of Collier Avenue Culvert Replacement 

 No  pre‐bid meeting will  be  held.   Questions  about  this  bid  package must  be  submitted  by Monday, May 15th, at 12:00 PM via email to [email protected]   The Calhoun County Road Department reserves the right to reject any and all bids and to make the award in the best interest of the Calhoun County Road Department and Calhoun County  

 

____________________________________  Brian Kernstock, EIT, Civil Engineer

Page 4: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

4  

Location Map 

 

 

PROJECT LOCATION 

Page 5: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

5  

General Provisions & Instructions 

Scope of Work 

The work covered by  this proposal consists of  installing soil erosion and sedimentation control  items, 

total stream diversion, removal items (including the existing culvert), grading and subgrade undercut (if 

necessary),  culvert bedding;  replacement of  the existing 36  inch  culvert with a 45  foot  long, 9.2  foot 

span,  3.3  foot  rise  aluminum  box  culvert  according  to  the  drawings  attached  to  the MDEQ  permit, 

placement  of  culvert  bedding,  structure  backfill,  aggregate  base,  and  restoration  items  on  Baseline 

Road. 

All work shall be performed in accordance with the Michigan Department of Transportation’s (MDOT) 

2012 Standard Specifications for Construction or as modified by these General Provisions and 

Instructions. 

 

Special Requirements 

1. Persons wanting to submit a bid on this project shall submit the forms from Appendix A & Bid 

Security  Requirements.    Bid  forms  should  be  submitted  to  the  Calhoun  County  Road 

Department.  After the bid opening, a decision will be made to purse what is in the best interest 

of the Calhoun County Road Department and Calhoun County 

 

2. A  preconstruction  meeting  will  be  held  to  finalize  a  progress  schedule  and  to  determine 

execution‐administration  of  the  contract.    Work  on  the  project  shall  begin  on  or  about 

May 30, 2017 or on  a date  agreed upon with  the Calhoun County Road Department  and  the 

Calhoun County.  The completion date for all work shall be June 13, 2017.   

 

3. Payment:  The  contractor  shall  submit  invoices  for  completed  contract  items  to  the  Calhoun 

County Road Department  (Brian  Kernstock).    The  invoice will  be  processed  and  payment  for 

approved contract  items  (less  retainage,  if necessary) will be made within  thirty  (30) calendar 

days or less of receiving the invoice. 

 

4. The contractor shall furnish a statement to the Calhoun County Road Department certifying that 

all subcontractors and suppliers that furnished  labor, equipment, and materials for the project 

have been paid before the final payment on the contract is made. 

 

 

Page 6: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

6  

Questions/Additional Information 

Questions regarding this project should be directed to: 

Brian Kernstock, EIT Civil Engineer Calhoun County Road Department 13300 15 Mile Road Marshall, MI 49068 P: 269.781.0025 [email protected]   

 

Page 7: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

7  

Progress Clause 

Start work on the date shown below or on a date agreed upon with the Engineer. 

START DATE: On or around May 30, 2017 

COMPLETION DATE: On or before June 13, 2017 

The approved  low bidder(s) for the work shall be required to participate  in a pre‐construction meeting 

with the Calhoun County Road Department to work out a detailed progress schedule. The schedule for 

this meeting will be set within three (3) days after the approved low bidder is determined.  The Calhoun 

County Road Department will arrange the time and place for this meeting. 

The progress schedule shall include, at a minimum, the controlling work items for the completion of the 

project  and  the  planned  dates  or work  days  that  these  items will  be  controlling  operations.   When 

specified  in  the bidding proposal,  the date  the project  is  to be opened  to  traffic, as well as  the  final 

project completion date, shall also be included in the project schedule. 

Page 8: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

8  

Project Log 

Project Location 

The Baseline Road culvert is located on Baseline Road between Collier Avenue and Banfield Road, T01S, 

R08W, Section 04.  This culvert carries Seven Mile Creek underneath Baseline Road, a local road within 

Bedford Charter Township.   

Description of Work 

Remove the existing 36 inch Corrugated Metal Pipe (CMP) culvert and construct a 45‐foot long, 9.2‐foot 

span, 3.3‐foot rise aluminum box culvert at the Baseline Road crossing of Seven Mile Creek as outlined in 

the attached MDEQ permit and plans.  0.03 acres of wetlands will be impacted and all activities will be 

completed  in accordance with  the approved plans and permit  conditions. There  shall be no  in water 

work between October 1st and April 30th due to fish spawning restrictions.  

Project Log  

The Contractor  shall  follow all provisions and  limitations of  the MDEQ permit and  is advised  that  the 

proposed  culvert  elevations  are  critical;  adherence  to  these  elevations  is mandatory.    Construction 

methods, including density requirements, shall be met according to MDOT 2012 Standard Specifications 

for Construction. 

Contractor shall install all necessary traffic control items for road closure in accordance with the Special 

Provision for Maintaining Traffic.  The contractor must submit a Traffic Control & Detour Signage Plan to 

CCRD for approval at the preconstruction meeting.  A detour route is included with this bid document. 

Contractor  shall  give  48  hours’  notice  to  Calhoun  County  Road  Department  (CCRD)  prior  to  closing 

Baseline Road  

Silt  fencing shall be placed on  the upstream and downstream sides of  the culvert such  that sediment 

does not enter the stream during construction. The silt fence must be trenched in to a depth of 6‐inches 

and shall not be placed  in any areas of concentrated or channelized flow.   This  item will be paid for as 

Erosion Control, Silt Fence. 

CCRD will  furnish  the  new  culvert  and will  deliver  it  to  the  site when  requested  by  the  contractor, 

although 48 hours’ notice prior to the expected delivery date should be given. 

The contractor  shall completely divert  the  stream around  the culvert  location  in accordance with  the 

Special  Provision  “Stream  Diversion,  Temp,  Modified”  which  describes  three  methods  that  the 

contractor may choose from to divert the flow. The contractor shall present their plan for  isolating all 

construction activities from the water to CCRD for review and acceptance.  This item shall be paid for as 

Stream Diversion, Temp, Modified. 

Page 9: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

9  

The existing HMA pavement will be saw cut and removed for the width of the road above the proposed new culvert, paid for as HMA Surface, Rem.  The contractor will excavate a trench according to the Limits of Excavation (Page 5 of 6 of the approved 

MDEQ  permit  drawings).    The  contractor  is  responsible  for  the  disposal  of  all  spoils  and materials 

according to the conditions of the MDEQ permit. The contractor will then place and compact a minimum 

of 12‐inches of 6A culvert bedding according to the upstream and downstream elevations of the culvert.  

A geotextile separator will be placed on top of the bedding material.   

Assemble and  install the culvert and appurtenances along the  lines and grades shown on the plans,  in 

strict  accordance  with  the  manufacturer’s  recommendations.  The  Contractor  is  responsible  for  all 

construction  traffic on  the culvert. Do not exceed  the specified design  loads with construction  traffic. 

Geotextile blanket will be wrapped around any culvert joints.   

6A  aggregate will  then  be placed  to  a depth of  1.3‐feet  to  adequately bury  the base of  the  culvert.  

Granular material Class  III will then be placed around the culvert up  to a depth of 8‐inches below the 

road surface.  All backfill material is to be compacted in no more than 8‐inch lifts to a density of at least 

95% in accordance with subsection 206.03.B.  This work shall be completed according to Section 401 of 

the  MDOT  2012  Standard  Specifications  for  Construction  &  the  Special  Provision  “Aluminum  Box 

Culvert” and shall be paid for as Culv, Alum Box, ___ inch by ___ inch. 

Any additional excavation to remove unsuitable  foundation soils beyond the  limits shown on the plan 

will  be  paid  for  separately  as  Excavation,  Earth.    In  accordance  with  the  MDOT  2012  Standard 

Specifications  for  Construction  406.03.G.2,  unstable/disturbed  subsoils  or  obstructions  other  than 

bedrock  should  be  undercut  (removed)  and  replaced  with  or  stabilized  using  a  layer  of  6A  coarse 

aggregate.  This layer should be a minimum of 12‐inches thick, but may need to be thicker depending on 

the  field  conditions.   The  6A  coarse  aggregate  should  be  placed  over  the  entire  unstable  area.   For 

undercuts  that  extend  beyond  the  outer  edges  of  the  culvert,  the  base  of  the  undercut  should  be 

located beyond a 1:1 slope extended down from the outside bottom edge of the culvert to the base of 

the undercut.  The MDOT 6A  coarse aggregate  should be placed  in  lifts not exceeding 12‐inches and 

should be  compacted  in deeper excavations or  tamped/charged  into  the unstable  subgrade with  the 

backhoe bucket until the subgrade is sufficiently stable.  The additional 6A coarse aggregate fill material 

will be included in the Culv, Alum Box, ___ inch by ___ inch pay item. 

8‐inches of 22A aggregate shall be placed and compacted up to the existing height of the roadway paid 

for as Aggregate Base, 8 inch. 

Riprap shall be placed at the upstream and downstream ends of the culvert in accordance to Section 916 

of the MDOT 2012 Standard Specifications for Construction and paid for as Riprap, Plain. 

The  embankment  around  the  culvert  shall  be  restored  to  a  3:1  slope  paid  for  as  Embankment,  CIP. 

Excavated material may be used as embankment material with approval from the Engineer. 

Page 10: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

10  

The  slope  of  the  embankment  shall  be  restored  and  paid  for  as  Slope  Restoration, Modified. Mulch 

blanket must be used on the 3:1 slopes. 

Page 11: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

11  

Proposed Baseline Road Culvert Information 

Benchmark #1: Elevation  ....................................................................................................... 876.87 

o RR Spike (See MDEQ Permit) 

Upstream (north) invert elevation .......................................................................................... 871.53 

Downstream (south) invert elevation ..................................................................................... 871.40 

Upstream streambed elevation* ............................................................................................ 872.83 

Downstream streambed elevation* ....................................................................................... 872.70 

*Proposed culvert will be buried approximately 1.3 feet

Page 12: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

12  

Special Provisions 

Aluminum Box Culvert 

Crushed Concrete Near Water 

Detour Route 

Maintaining Traffic 

Slope Restoration, Modified 

Stream Diversion, Temp, Modified 

Page 13: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

13  

CALHOUN COUNTY ROAD DEPARTMENT

SPECIAL PROVISION FOR

ALUMINUM BOX CULVERT

CCRD: BJK 1 of 2 04/19/2017

a. Description. Assemble, install, and backfill an aluminum structural plate arch culvert of the size and shape specified on the plans. Perform this work according to the Michigan Department of Transportation 2012 Standard Specifications for Construction and as described herein.

b. Materials. All materials shall meet the requirements of Sections 902, 908, and 910 of

the Michigan Department of Transportation’s (MDOT) 2012 Standard Specifications for Construction.

Item Section 6A Aggregate ................................................................................................................ 902 Granular Material Class III ............................................................................................ 902 Steel Bolts ..................................................................................................................... 908 Geotextile Blanket ......................................................................................................... 910 Geotextile Separator ..................................................................................................... 910

c. Construction Methods. Perform this work according to Section 401. Furnish, install,

and maintain necessary equipment and materials necessary to dewater the site sufficiently to install culvert bedding or engineered foundation improvements as specified on the plans. The contractor will excavate a trench according to the Excavation Cross Section shown in the MDEQ permit. The contractor is responsible for the disposal of all spoils and materials according to the conditions of the MDEQ permit. The contractor will then place and compact a minimum of twelve inches (12") of 6A culvert bedding according to the upstream and downstream elevations of the culvert. A geotextile separator will be placed on top of the bedding material. Assemble and install the culvert and appurtenances along the lines and grades shown on the plans, in strict accordance with the manufacturer’s recommendations. The Contractor is responsible for all construction traffic on the culvert. Do not exceed the specified design loads with construction traffic. Geotextile blanket will be wrapped around any culvert joints. Place the culvert on top of the geotextile separator. 6A aggregate will then be placed to a depth as directed by the engineer in the project log to adequately bury a portion of the culvert. Granular material Class III will then be placed around the culvert up to a depth of eight (8) inches below the road surface. All backfill material is to be compacted in no more than eight (8) inch lifts to a density of at least 95% in accordance with subsection 206.03.B.

Page 14: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

14  

CCRD: BJK 2 of 2 03/13/2017

d. Measurement and Payment. The completed work for Culv, Alum Box, ___inch by

___ inch, will be measured by length, in feet, along the culvert centerline, per the plans, including end sections. Payment for Culv, Alum Box, ___ inch by ___inch includes all equipment, materials, and labor to furnish, assemble, install and backfill the aluminum box culvert and all appurtenances including, but not limited to, end sections, headwalls, wing walls, and toe footings or cutoff sheets, as shown on the plans and as specified herein.

Payment includes bedding, geotextile blanket, geotextile separator and excavation to the limits shown on the plans, including areas of undercutting required to place culvert bedding or engineered culvert foundation as shown on the plans. Over-excavation to remove unsuitable foundation soils, beyond the limits shown on the plans, will be paid for separately as Excavation, Earth.

Payment also includes all materials, equipment, and labor required to dewater the site sufficient to install the specified foundation improvements and culvert, as shown on the plans and specified herein.

Pay Item Pay Unit Culv, Alum Box, ___ inch by ___ inch .......................................................................... Foot

Page 15: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

15  

12SP902(C)

MICHIGAN DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISION

FOR CRUSHED CONCRETE NEAR WATER

C&T:JFS 1 of 1 C&T:APPR:KAS:DBP:02-24 12 FHWA:APPR:02-24-12

Add the following paragraph after the first paragraph of Subsection 902.05 on page 743 of the Standard Specifications for Construction:

The use of crushed concrete is prohibited on the project within 100 feet of any water course (stream, river, county drain, etc.) and lake, regardless of the application or location of the water course or lake relative to the project limits.

Add the following paragraph after the first paragraph of Subsection 902.06 on page 743 of the Standard Specifications for Construction:

The use of crushed concrete is prohibited on the project within 100 feet of any water course (stream, river, county drain, etc.) and lake, regardless of the application or location of the water course or lake relative to the project limits.

Add the following paragraph after the fourth paragraph of Subsection 902.07 on page 744 of the Standard Specifications for Construction:

The use of crushed concrete is prohibited on the project within 100 feet of any water course (stream, river, county drain, etc.) and lake, regardless of the application or location of the water course or lake relative to the project limits.

Page 16: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

16  

CALHOUN COUNTY ROAD DEPARTMENT

BASELINE ROAD EAST OF COLLIER AVENUE CULVERT REPLACEMENT

DETOUR ROUTE

CCRD: BJK 1 of 1 03/14/2017

a. Detour Route

Culvert Location

Page 17: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

17  

CALHOUN COUNTY ROAD DEPARTMENT

SPECIAL PROVISION FOR

MAINTAINING TRAFFIC CCRD: ANK, BJK 1 of 1 03/15/17

a. Description. Traffic detour and maintenance during construction shall be in accordance with Section 104.11 of the Michigan Department of Transportation 2012 Standard Specifications for Construction. All signs, barricades, and other traffic control devices shall be in accordance with the 2011 Michigan Manual of Uniform Traffic Control Devices (MMUTCD).

No work will be allowed on Sundays or holidays and all work must be performed during the daylight hours.

b. Construction Influence Area. The Construction Influence Area (CIA) shall consist of

the project right of way five-hundred (500) feet in all directions. c. Traffic Control Devices and Restrictions. All traffic control devices and their usage

must conform to Part 6 of the MMUTCD. The Contractor must review, adjust, and maintain all traffic control devices on a daily bases or as directed by the Engineer. The Contractor must notify the Engineer at least twenty-four (24) hours in advance of erecting construction zone signing. Access to all businesses and residences must be maintained at all times and work must be coordinated with the Engineer.

The Contractor must maintain all traffic control devices and is responsible for reviewing the adequacy and condition of all traffic control devices at least once per day for the duration of the project. Replacement and repair of the traffic control devices will be restricted to daylight hours. All signs damaged as a result of the Contractor’s operations must be replaced by the Contractor at his expense.

d. Measurement and Payment. Items necessary for maintaining traffic being measured

and paid for separately include: Pay Item Pay Unit Minor Traf Devices ............................................................................................. Lump Sum Barricade, Type III, High Intensity, Double Sided, Lighted, Furn ................................ Each Barricade, Type III, High Intensity, Double Sided, Lighted, Oper ................................ Each Plastic Drum, High Intensity, Furn ............................................................................... Each Plastic Drum, High Intensity, Oper .............................................................................. Each Sign, Type B, Temp, Prismatic, Furn .............................................................. Square Foot Sign, Type B, Temp, Prismatic, Oper .............................................................. Square Foot

Page 18: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

18  

Signing for lane or road closures, if applicable, shall be in accordance with the Michigan Department of Transportation maintaining traffic typical drawings WZD-125E, WZD-100A, M0020a, M0040, and M0150a.    

Page 19: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

19  

CALHOUN COUNTY ROAD DEPARTMENT

SPECIAL PROVISIONS FOR

SLOPE RESTORATION, MODIFIED

CCRD: ANK 1 of 1 03/15/17

a. Description. The work of “Slope Restoration, Modified” shall consists of preparing areas to be seeded, placing topsoil, seeding, fertilizing, mulching, anchoring mulch, and watering as shown on the plans and in accordance with Section 816 of the 2012 Standard Specifications for Construction.

b. Materials. All materials shall meet the requirements of Sections 911 and 917 of the Michigan Department of Transportation’s (MDOT) 2012 Standard Specifications for Construction.

c. Construction Methods. The Contactor shall restore disturbed areas as described in Subsection 816.03 of the MDOT’s 2012 Standard Specifications for Construction. Materials shall be placed at rates specified in Section 816 of MDOT’s 2012 Standard Specifications for Construction.

Topsoil thickness shall be placed at a minimum thickness of 3 inches. In the event that sufficient suitable topsoil is not salvaged from the grading operation, the Contractor shall furnish the additional topsoil required as part of “Slope Restoration, Modified”. The application rates for other items covered under “Slope Restoration, Modified” shall meet or exceed the rates called for in Section 816 of the MDOT’s 2012 Standard Specifications for Construction.

d. Measurement and Payment. “Slope Restoration, Modified” will be measured and paid for based on the area restored. “Topsoil Surface, 3 inches”, “Seeding, Mix TUF”, “Fertilizer, Chemical Nutrient Cl. A”, “Mulch”, “Mulch Anchoring”, and “Water, Sodding/Seeding” shall be used and will be considered as included in the pay item ”Slope Restoration, Modified”. “Water Sodding/Seeding” shall be used at the Contractor’s discretion to insure a well-established turf. No separate payment will be made for these various items of work. For steep slopes and ditch bottoms, mulch blankets shall be used in place of “Mulch and “Mulch Anchoring”. Areas that are restored with mulch blankets will be paid for as Slope Restoration, Modified”.

Pay Item Pay Unit

Slope Restoration, Modified ............................................................................ Square Yard

Payment for “Slope Restoration, Modified” will be made based on the following schedule: Upon completion of the work, payment will be based on 50% of the contract unit price. After the grass germinates and the Engineer is satisfied that the amount and area of the grass germination should reasonably provide a well-established turf, the remaining balance of the contract unit price will be paid.    

Page 20: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

20  

CALHOUN COUNTY ROAD DEPARTMENT

SPECIAL PROVISION FOR

STREAM DIVERSION, TEMP, MODIFIED

CCRD: BJK 1 of 4 03/13/2017

a. Description. The pay item “Stream Diversion, Temp, Modified” includes all labor, equipment, and materials required to temporarily divert the stream flow around the culvert construction area, isolating culvert removal and construction activities from the stream flow.

b. Construction Methods. The Contractor may choose from the methods shown below:

Page 21: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

21  

CCRD: BJK 2 of 4 03/13/2017

c. Pump Method (Figure 1). The pump and hoses used to divert water around the construction area shall have sufficient flow capacity to minimize ponding of water against the upstream barrier and potential water damage to upstream properties. Water shall be discharged from the hoses onto an area stabilized with riprap. All labor, equipment, and materials required to temporarily divert the stream flow with pumps and hoses, including a discharge area stabilized with riprap is included with the pay item “ Stream Diversion, Temp, Modified”.

d. Diversion Method (Figure 2). Construction Sequence: 1. Excavate a diversion ditch from Point A to Point B. 2. Line the diversion ditch with plastic sheeting. The top edge of the plastic sheeting shall be

anchored to the top of the ditch above the water surface. Sections of plastic sheeting shall be overlapped for a minimum distance of 2 feet in the downstream direction and have a sufficient quantity of washed 6A or 6AA stone placed on the overlap area to prevent undermining of the sheeting.

3. Excavate the diversion ditch from Point A to the stream then excavate from Point B to the stream. Stabilize the ditch in these areas with washed 6A or 6AA stone.

4. Place a barrier to direct flow through the diversion ditch at the upstream end. 5. Place a barrier at the downstream end. 6. Dewater the construction area. 7. Remove the existing culvert, place and backfill the new culvert. Place riprap at the culvert

inlet and outlet as shown on the plans. 8. Remove the downstream barrier. 9. Remove the upstream barrier. 10. Backfill the diversion ditch. The diversion ditch in the area beneath the influence of the

pavement and shoulder shall be backfilled in accordance with Section 401.03.F.1 of the Michigan Department of Transportation’s (MDOT’s) 2012 Standard Specifications for Construction.

All labor, equipment, and materials required to perform items 1-5 and 8-10 shown above are included with pay item “Stream Diversion, Temp, Modified”.

Page 22: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

22  

CCRD: BJK 3 of 4 03/13/2017

e. Diversion Culvert Method (Figure 2). Construction Sequence 1. Install and backfill the temporary diversion culvert. 2. Stabilize the inlet and outlet ends of the culvert with 6A or 6AA aggregate and riprap. 3. Place a barrier upstream from the construction area to redirect flow into the inlet end of the

diversion culvert. 4. Place a barrier downstream from the construction area. 5. Dewater the construction area. 6. Remove the existing culvert, install and backfill the culvert. Place riprap at the inlet and

outlet ends of the new culvert. 7. Remove the downstream barrier. 8. Remove the upstream barrier. 9. Remove the temporary diversion culvert and backfill it’s trench. The culvert trench under

the influence of the pavement and shoulder shall be backfilled in accordance with Section 401.03.F.1 of the Michigan Department of Transportation’s (MDOT’s) 2012 Standard Specifications for Construction.

All labor, equipment, and materials required to perform items 1-4 and 7-9 shown above are included with the pay item “Stream Diversion, Temp, Modified”.

f. Offset Method (Figure 3). Construction Sequence: Stage 1 1. Place upstream and downstream barriers as shown in Figure 3. 2. Install and backfill the new culvert, relocate the channel to align with the new culvert and

place riprap as detailed on the plans. Stage 2 1. Reorient the upstream and downstream barriers to direct the stream flow through the new

culvert and isolate the existing culvert from the stream flow. 2. Remove and backfill the existing culvert.

All labor, equipment, and materials required to perform items in Stage 1 and 2 (other than removal of the existing culvert and installing the new culvert) shown above are included with the pay item “Stream Diversion, Temp, Modified”.

Page 23: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

23  

CCRD: BJK 4 of 4 03/13/2017

g. Materials. The upstream and downstream barriers shown in figures 1, 2, and 3 shall be constructed with steel interlocking sheet piling. Other materials may be used to construct these barriers if approved by the engineer. Backfill materials for areas beneath the influence of the payment and shoulder shall be Granular material Class II meeting the requirements of Section 902.08 of MDOT’s 2012 Standard Specifications for Construction. The stone used for stabilization shall be 6A or 6AA aggregate meeting the requirements of Section 902.03 of MDOT’s 2012 Standard Specifications for Construction. The culvert used for the “Diversion Culvert Method” shall have a cross-sectional area large enough to keep discharge velocities at the culvert end low enough to limit erosion. Any type of culvert that the contractor elects to use will be acceptable as long as water velocities exiting the downstream end of the culvert do not cause erosion.

h. Measurement and Payment. “Stream Diversion, Temp, Modified” will be paid for at the contract unit price for the following Contract Item (Pay Item), which shall be payment in full for all labor, equipment, and materials required: Pay item Pay Unit “Stream Diversion, Temp, Modified” .................................................................. Lump Sum    

Page 24: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

24  

Notice to Bidders 

 

Use of Crushed Concrete for Dense‐ & Open‐Graded Aggregates & Granular Material 

Pursuant to the Special Provision for Crushed Concrete Near Water, included elsewhere in the contract 

documents,  the  used  of  crushed  concrete  for  dense‐graded  aggregate,  open‐graded  aggregate,  and 

granular material is prohibited within one‐hundred (100) feet of a water course or lake.  The estimated 

amount of material and the location (by pay item) affected by this prohibition is: 

Aggregate Base, 8 inch, 54 Syd 

Riprap, Plain, 50 Syd 

Page 25: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

25  

Utility Coordination 

The  contractor  shall  cooperate  and  coordinate  construction  activities with  the  owners  of  utilities  as 

stated in Section 104.08 of the 2012 MDOT Standard Specifications for Construction.  In addition, for the 

protection of underground utilities, the contractor shall follow the requirements in Section 107.12 of the 

2012 MDOT Standard Specifications  for Construction.   Contractor delay claims  resulting  from a utility 

will be determined based upon Section 109.05 of the MDOT Standard Specifications for Construction. 

For protection of underground utilities and in conformance with Public Act 53, the contractor shall dial 

1‐800‐482‐7171 a minimum of  three  (3)  full working days, excluding Saturdays, Sundays and holidays 

prior  to  beginning  each  excavation  in  areas where  public  utilities  have  not  been  previously  located.  

Members will  thus be  routinely notified.   This does not  relieve  the contractor of  the  responsibility of 

notifying utility owners who may not be a part of the “MISS DIG” alert system. 

 

Public Utilities 

The following public utilities have facilities located within the right‐of‐way: 

Gas and Electric 

Consumers Energy 311 E Michigan Ave #100 Battle Creek, MI 49014 Matthew Koepke ‐ (269) 969‐8595  

Telephone 

Barry County Telephone 123 W. Ochard, Box 128 Delton, MI 49046 Jeff Beaver ‐ (269) 623‐9964   

Natural Gas 

Semco 15851 Helmer Road S. Battle Creek, MI 49015 Julie Conant – (269) 968‐8111   Cable TV  Comcast Cable 16718 US Highway 12 Cement City, MI 49233 Jim Newby – (517) 206‐8100  

The owners of existing  service  facilities  that are within grading or  structure  limits will move  them  to locations  designated  by  the  Engineer  or will  remove  them  entirely  from  the  roadway  right  of way.  Owners of public utilities will not be  required by  the CCRD  to move additional poles or  structures  in order to facilitate the operation of construction equipment unless it is determined by the Engineer that such  poles  or  structures  constitute  a  hazard  to  the  public  or  are  extraordinarily  dangerous  to  the Contractor’s operations.    

Page 26: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

26  

Attachment A: Bid Security Requirements & Bid Forms 

 

Page 27: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

27  

Bid Security 

Bid security shall be made payable to the Calhoun County Road Department in an amount equal to 5% 

of the total bid. The bid security can be cash, certified check, or a bid bond issued by a surety.  

The bid security of the successful low bidder will be retained by the Calhoun County Road Department 

until  a  contract  is  executed.  The  bid  security  shall  be  returned  to  the  successful  low  bidder within 

ten (10) business days of the date the contract is executed.  

The successful low bidder’s bid security will be forfeited if the Calhoun County Road Department and the 

successful low bidder fail to reach agreement on a progress schedule or if the low bidder fails to return 

an  executed  contract  to  the  Calhoun  County  Road  Department    within  ten  (10)  business  days  of 

receiving notice of award. 

The bid  security of other bidders  shall be  returned within  ten  (10) business days of  the bid opening.

Page 28: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 29: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Schedule of Items (Itemized Bid Sheet)

Letting Date: Monday, May 22, 2017 12:00 PM

Contract ID: Baseline Culv.

Location: Baseline Road east of Collier AvenueDescription: Culvert Replacement

Project Number: 000001 Project Engineer: Brian Kernstock

Estimate Number: 4 Date Created: 3/20/2017Project Type: Miscellaneous Fed/State #:

Location: Baseline Road east of Collier Avenue Fed Item:

Control Section:

Description:

Instructions toBidders:

IMPORTANT NOTICE:If the proposal establishes a maximum price for any of the following work items, and if you bid a price higherthan that maximum price, your bid will be considered to have quoted the maximum price and your bid total willbe adjusted to reflect that maximum price.

If the proposal provides a specified price for any of the following work items, and if you bid a price higher orlower than that specified price, your bid will be adjusted to reflect that specified price.

If your bid is the lowest accepted bid, and if you refuse to accept the award of the contract due to the changein what you quoted as a maximum or specified price, you will forfeit your proposal guaranty.

Contract # Baseline Culv. (Baseline Road east of Collier Avenue)MERL: 5.3.2

5/8/2017 9:30:53 AM

Page 1 of 3

Page 30: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Pay Item Description Quantity Units Unit Price Bid Amount

Dollars Cts Dollars Cts

1 LSUM1500001 Mobilization, Max

1 Ea2030002 Culv, Rem, 24 inch to 48 inch

20 Cyd2050010 Embankment, CIP

5 Cyd2050016 Excavation, Earth

200 Ft2080036 Erosion Control, Silt Fence

1 LSUM2090001 Project Cleanup

54 Syd3020020 Aggregate Base, 8 inch

45 Ft4017001 _ Culv, Alum Box, 110 inch by 39 inch

1 LSUM7047051 _ Stream Diversion, Temp, Modified

6 Ea8120012 Barricade, Type III, High Intensity, DoubleSided, Lighted, Furn

6 Ea8120013 Barricade, Type III, High Intensity, DoubleSided, Lighted, Oper

1 LSUM8120170 Minor Traf Devices

15 Ea8120260 Plastic Drum, High Intensity, Lighted, Furn

15 Ea8120261 Plastic Drum, High Intensity, Lighted, Oper

250 Sft8120350 Sign, Type B, Temp, Prismatic, Furn

250 Sft8120351 Sign, Type B, Temp, Prismatic, Oper

50 Syd8130010 Riprap, Plain

85 Syd8167011 _ Slope Restoration, Modified

Contract # Baseline Culv. (Baseline Road east of Collier Avenue)MERL: 5.3.2

5/8/2017 9:30:53 AM

Page 2 of 3

Page 31: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Pay Item Description Quantity Units Unit Price Bid Amount

Dollars Cts Dollars Cts

Total Bid:

Contractor:

(Signature) (Date)

Contract # Baseline Culv. (Baseline Road east of Collier Avenue)MERL: 5.3.2

5/8/2017 9:30:53 AM

Page 3 of 3

Page 32: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 33: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...

Calhoun County Road Department Culvert Replacement Project 

Baseline Road East of Collier Avenue, Bedford Township 

32  

Attachment B: MDEQ Permit 

 

 

 

 

 

Page 34: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 35: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 36: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 37: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 38: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 39: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 40: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 41: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 42: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 43: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 44: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...
Page 45: Baseline Culvert Bid Package - Calhoun County Road … Box Culvert..... 12 Crushed Concrete Near Water ... 14 Detour Route ...